PERTH & KINROSS COUNCIL 
1 March 2023 
STRATEGIC INVESTMENT & CAPITAL BUDGET UPDATE 2023/24 – 2027/28 
Report by the Chief Executive & Head of Finance
(Report No 23/73) 
1. PURPOSE 
1.1 The purpose of this report is to provide Council with an overview of the
strategic context for the Council’s Capital investment and, where appropriate,
managed disinvestment. The report also sets out information on development
of the Council’s corporate asset management strategy and the Investment
Blueprint to inform future capital investment over the longer term. 
1.2 The report provides an update on the Composite (General Fund) Capital
Budget and the affordability of the current programme. It updates Council on
the implications of the 2023/24 local government settlement for Capital
expenditure; recommends that Council set a 5 Year Capital Delivery Plan for
the period 2023/24 – 2027/28 pending further work on asset management
planning and sets out officer recommendations on specific projects.
2. RECOMMENDATIONS 
2.1 The Council is requested to: 
(a) note the contents of the report: 
(b) approve the development of the new Corporate Asset Management Plan
for submission to Council in December 2023. 
(c) approve the development of a long-term Investment Plan, based on
plans to manage all our assets, and revised Capital funding strategy
beyond 2027/28 for consideration in setting the Capital Budget in
February / March next year.
(d) approve Appendix 1 to the report as the basis for updating the
Composite (General Fund) Capital Delivery Plan for the 5-year period
2023/24 - 2027/28. 
(e) approve pausing the delivery of the new Blairgowrie Recreation Centre
on the grounds of overall capital programme affordability, pending further
review of the investment needs of the Blairgowrie community. The

Page 2

existing budget provision for the project of £26.7 million will be retained
pending the outcome of the review.
(f) approve pausing the development and delivery of the PH2O project, on
the grounds of overall capital programme affordability. The existing
budget provision for the project of £90 million will be retained pending
the outcome of the review. 
(g) approve funding of £10 million towards the cost of delivering enabling
works for Phase 1 of the Perth Eco Innovation Park to be met from the
balance of investment capacity as set out in paragraph 5.5 of the report
and remit officers with reflecting the remaining cost of the enabling works
as part of the development of an updated Capital funding strategy for
consideration in 2024. 
(h) approve funding of £4.4 million for the repair of the Garry Viaduct for
inclusion as part of the Council’s Structures programme, to be met from
the balance of investment capacity as set out in paragraph 5.5 of the
report. 
(i) approve additional funding of £442,000 in 2023/24 for the MOSAIC
system, to be met from the balance of investment capacity as set out in
paragraph 5.5 of the report.
(j) approve additional funding of £698,000 to meet annual SEEMIS
licensing costs up to 2027/28 to be met from the balance of investment
capacity as set out in paragraph 5.5 of the report 
3. STRUCTURE OF THE REPORT 
The structure of this report is set out as follows: 
4 – Strategic Context: Strategic Investment Planning and Asset
Management 
5 – Budget Update and Affordability
6 – General Fund Capital Resources & Updated Capital Delivery
Plan 2023/24 to 2027/28
7 – Blairgowrie Recreation Centre
8 – PH2O
9 – Perth Eco Innovation Park
10 – Further Recommendations
11 – Summary

Page 3

4. STRATEGIC CONTEXT: STRATEGIC INVESTMENT PLANNING AND
ASSET MANAGEMENT 
4.1 The new Corporate Plan 2022 – 27, (Report 22/311 refers), approved by
Council in December 2022, sets our vision for “a Perth and Kinross where
everyone can live life well, free from poverty and inequality”. It sets out
our priorities, corporate outcomes which are aligned with the Council’s values
and designed to address or mitigate the impact of the many challenges the
Council and the communities across Perth and Kinross are facing now and in
the coming years. 
4.2 The 7 key priorities set out within the plan are aimed to address, or mitigate
the challenges, focus the Council’s work and resources where it is needed
most, and support the delivery of the Council’s vision through: 
▪ Tackling poverty 
▪ Tackling climate change and supporting sustainable places 
▪ Developing a resilient, stronger, and greener local economy
▪ Enabling our children and young people to achieve their full potential 
▪ Protecting and caring for our most vulnerable people 
▪ Supporting and promoting physical and mental wellbeing 
▪ Placing Communities at the heart of how we work  
4.3 The Council’s Capital investment enables service delivery. The investment
decisions the Council makes on its property; roads and infrastructure;
greenspace; fleet and digital assets must be aligned with and support the
delivery of the Council’s key priorities. 
4.4 In October 2021, the Council approved a Strategic Capital Investment
Planning Framework (Report 21/180 refers) aimed at facilitating a cohesive
and flexible approach to investment planning and resourcing based upon: 
• Investment Blueprint
• 30 Year Investment Plan
• Medium Term Financial Plan
• 6 Year Funded Capital Delivery Programme 
The Medium-Term Financial Plan 2023-2029, which outlines the broad
direction of travel for the Council’s financial management, was approved by
Council on 28 September 2022 (Report 22/249 refers) and the current 6

Page 4

Year Funded Capital Delivery Programme 2022/23-2027/28 was approved
by Council on 23 February 2022 (Report 22/36 refers). 
4.5 The Investment Blueprint aims to set out the strategic rationale; key risks;
challenges and fundamental principles underlying the Council’s Capital
investment in the long term. The five principles previously agreed by Council
are that investment decisions must: 
• mitigate against the impact of climate change
• promote inclusive economic growth and a vibrant economy
• promote equality and fairness
• support the delivery of sustainable public services through effective
management of our assets
• promote and enhance digital inclusion
Although these principles were approved prior to the adoption of the new
Corporate Plan, they remain aligned with the Council’s strategic priorities. 
4.6 The Council has also previously approved the adoption of the HM Treasury 5
case business model (Green book) for the development of all business cases
supporting capital investment and the subsequent gateway review of projects
as they progress to completion. 
4.7 The 5 case model places a strong emphasis on evidence based and driven
decision making. This includes assessing the ongoing strategic or business
need for investment; an economic assessment of the options for meeting this
need; the commercial options around procurement; the financial implications
and the proposed governance and management arrangements for the delivery
of the required investment. 
4.8 The Council is progressing its commitment to engage with the communities
and citizens it serves in shaping future service delivery. This engagement will
help inform and support the evidence base for future Capital investment.
Examples include: 
• The current “Big Conversation” with communities around place
• The work of the Perth & Kinross Climate Commission
• The work of the Anti-Poverty Taskforce
• Previous and current engagement on the Perth & Kinross Offer
4.9 Also supporting the evidence base for Capital expenditure is the investment  
required to deliver the outcomes set out within key Council strategies and
plans, notably: 
• Transformation and Change Strategy 2022/23 -2027/28 (Report 22/142
refers)
• Economic Wellbeing Plan (Report 21/37 refers)

Page 5

• Climate Change Strategy & Action Plan (Report 21/245 refers)
• Draft Strategic Priorities for Culture and Physical Activity / Sport 2023-
2028 (Report 22/309 refers)
• Digital Perth and Kinross - Digital Strategy 2023-27 (Report 23/34
refers)
The three key themes of building sustainable places; enabling the transition to
net zero and driving inclusive economic growth underpin the vision for
Scotland’s infrastructure set out in the Scottish Government’s Infrastructure
Investment Plan for Scotland: 
4.10 Key to establishing an evidence base to inform future Capital investment is
the current condition of the Council’s existing assets and infrastructure.  The
Council uses a range of measures to assess asset condition including
national survey work on the roads network commissioned through the Society
of Chief Officers of Transportation (SCOTS); assessment by Scottish
Government agencies such as the Housing condition survey and our own
internal assessment and inspection of assets including our property estate;
greenspace; bridges & structures; fleet and digital infrastructure. 
4.11 The importance of reinvestment in and maximising the useful life of existing
assets is recognised in the Scottish Government Investment Hierarchy set out
below, with the replacement or creation of new assets identified as the last
option to be considered.

Page 6

4.12 The Council’s investment in maintaining and enhancing its existing assets and
infrastructure is reflected in expenditure on the programmes of works;
including the bridges & structural maintenance; property improvement; school
estate; greenspace and IT programmes. 
Based upon the Capital monitoring report to the Finance & Resources
Committee on 1 February, the near £700 million of gross budgeted
expenditure on the Council’s Capital programme over the period 2022/23 –
2027/28 is currently heavily weighted towards investment in new projects
(70%) as set out in the chart below. 
Budgeted expenditure on projects reflects the scale and complexity of the
Council’s major investment in: 
• Cross Tay Link Road (£150.5 million gross, £110.5m net) which is
currently under construction
• Perth Museum (£27.2 million) which is scheduled to open in 2024.
• Perth High School Replacement (£80.2 million) which is now in
progress on site 
• PH2O (£90 million) allocation for the replacement of Perth Leisure Pool
and Dewars Rinks. 
• Blairgowrie Recreation Centre (£26.7 million) – see Section 7 and
Appendix 2 to the report.

Page 7

Expenditure on Prudential Borrowing largely relates to investment in the
Council’s vehicle fleet and street light column replacement. 
4.13 The current assessed condition of the Council’s existing assets is
summarised, at a high level, in the following table. This assessment has
previously been presented to political Budget Review Groups: 
Asset Category Condition Trend
Community Greenspace Steady but tending towards declining
Vehicle Fleet Steady
Information, Communications &
Technology
Steady
Property Declining
Traffic and Road Safety Declining
Roads Steady but tending towards declining
Structures (Bridges, viaducts etc) Declining
Street Lighting Steady
Flood Protection Infrastructure Steady 
4.14 Assessments are also undertaken of the use of individual assets and their
suitability or fit with intended purpose. This can change over time as
standards and expectations alter and is of relevance in relation to the
Council’s property assets.

Page 8

4.15 The assessed condition of the Council’s existing assets indicates a significant
requirement for future investment if these assets are to be retained and the
higher cost of replacement avoided. 
4.16 In line with statutory requirements; the Council’s strategic commitment to
tackle Climate Change and the approved investment principles set out in
paragraph 4.5 above -   the future fitness for purpose of the Council’s assets,
particularly its fleet and property assets - will require to reviewed. 
4.17 As the Council transitions towards reducing its carbon footprint and ultimately
to net zero, in line with government targets, investment in assets such as
electric and hydrogen powered vehicles and energy conservation; conversion
to low carbon heating and other mitigating measures in respect of the
Council’s property estate will all place an increasing emphasis on investment
in the Council’s existing assets. 
4.18 In a period of significant financial pressure on Council expenditure, there
requires to be a focus on retaining only those assets which are both best
placed to serve the needs of our communities, and which are cost effective to
operate.  This is particularly the case in respect of the Council’s property
estate, including its school estate. 
4.19 The Financial Strategy (Report 22/141 refers) approved by Council in June
2022, includes as a key principle, the commitment to “collaborate with our
public partners to reduce the overall public estate and dispose of assets which
no longer best support the delivery of our strategic objectives.”  Given the
substantial costs of both operating and investing in the property estate, the
Council will require to consider a further programme of property rationalisation
and managed disinvestment in the property estate. 
4.20 In November, the Learning & Families Committee remitted the Executive
Director (Education & Children’s Services) to plan a review of the school
estate in line with the principles of the approved Investment Blueprint and
Financial Strategy; and bring an update on that work back to the Committee in
August 2023 (Report 22/263 refers). It is now proposed that this review is
incorporated into the work on developing the Council’s Corporate Asset
Management Plan as set out in paragraph 4.21 below.  
4.21 Council officers will bring forward a Corporate Asset Management Plan for
consideration by Council in December 2023. The Corporate Asset
Management Plan will include the asset management plans and investment
need across all of the Council’s individual asset streams (property; community
greenspace; roads & structures; fleet vehicles and digital).  
4.22 The Corporate Asset Management Plan will provide an evidenced based
approach for informing future investment and managed disinvestment
decisions. This will then be used to help formulate both a delivery plan for
addressing this need and the underpinning strategy for funding the Council’s

Page 9

General Fund Capital investment within the resources available and overall
levels of affordability 
4.23 The resultant 30 Year Investment Plan will be subject to discussion with
elected members in late 2023 / early 2024 in advance of the Council setting
the Capital budget and the funded delivery plan. 
RECOMMENDATION 
4.24 it is recommended that Council 
(b) Approve the development of the new Corporate Asset Management
Plan for submission to Council in December 2023. 
5. BUDGET UPDATE AND AFFORDABILITY 
5.1 On 23 February 2022, Council approved a 6 Year Composite (General Fnd)
Capital Delivery Plan for the period 2022/23 -2027/28 (Report 22/36 refers). 
5.2 In approving the 6 Year Delivery Plan, the Council approved a long-term
Capital funding strategy based upon incremental growth of £450,000 per
annum in the Council’s budget for borrowing costs (loan charges) combined
with the managed use, over time, of the Council’s Capital Fund. Council
approved addressing the £450,000 additional annual Revenue implications of
this strategy through the ring-fencing of growth in the Council Tax base. 
5.3 The long-term Capital funding strategy provided the Council with
approximately £190 million of investment capacity. In setting the 6 Year
Capital Delivery Programme, the Council allocated £118.7 million of this
capacity as follows:

Page 10

Capital Expenditure approved in February 2022 £ million £ million
Inflation on Existing Projects / Programmes
Perth High School 10.4
Blairgowrie Recreation Centre 2.7
New Primary School at Bertha Park 9.6
Schools Audio Visual Programme 0.5
Flood Protection Schemes 0.2 23.4
New Projects approved February 2022
PH2O 90.0
Technology Enabled Care 6.0
Funding from unallocated Capital Grant -0.7
Net Capital Expenditure Approved February 2022 118.7
5.4 Progress with the approved Composite Capital Delivery Plan and the
Housing Investment Programme has been reported to each meeting of the
Finance & Resources Committee during the current financial year and to
Council on 21 December 2022 (Report 22/310 refers). 
5.5 Since setting the Capital budget in February 2022, additional expenditure of
£45.7 million has been approved at the meetings noted below, to be met
from the Capital funding strategy as set out below, leaving a balance of
£25.6 million. 
£ million £ million
Investment capacity per approved Capital Funding Strategy 190.0
LESS:
Approved by Council on 23 February 2022 (Report 22/36) (118.7)
Approved by Finance & Resources  7 September 2022 (Report 22/209)
Cross Tay Link Road - additional funding (32.5)
Perth Museum - additional funding (0.7)
Approved by Finance & Resources 30 November 2022 (Report 22/298)
Harris Academy Extension - additional funding (1.0)
Approved by Council 21 December 2022 (Report 22/312)
Perth High School replacement - additional funding (11.5) (45.7)
Balance of investment capacity under funding stratgey 25.6

Page 11

Impact of Construction Inflation 
5.6 In common with all public and private sector organisations, the Council has
experienced a significant increase in the cost of Capital investment. Over the
period October 2021 to December 2022, the Council has approved circa.
£200 million of additional Capital expenditure. 
Including the £45.7 million of additional expenditure approved since
February 2022, inflation and contingencies on the cost of delivering
approved projects accounts for £89.9 million (45%) of this total. 
Affordability 
5.7 As reported to the Finance & Resources Committee in November and
Council in December 2022, the current 6 Year Composite Capital Budget, as
it is currently specified is no longer affordable in its entirety due to the
forecast impact of construction inflation. 
As summarised below, the forecast impact of inflation on major Capital
projects together with the programmes of works exceeds the capacity
remaining within the approved Capital funding strategy to deliver them. The
estimated funding shortfall of c. £34 million is likely understated as inflation
projections have only been included for major projects subject to
consideration within the report. 
£ million £ million
Balance of investment capacity under funding stratgey 25.6
Forecast inflation on major projects
Blairgowrie Recreation Centre (revised forecast £36m) (9.3)
PH20 (revised forecast £110m+) (20.0)
Forecast inflation on Capital programmes
10% compound inflation on programmes of works (30.0) (59.3)
Potential funding shortfall (minimum) (33.7)
Recurring Capital Budget from 2028/29 onwards (per annum) 24.0
5.8 There is inherent uncertainty around forecasts of future inflation. The revised
estimate for Blairgowrie Recreation Centre of £36 million is, however, current
and is reflected in the Final Business Case attached to this report. The

Page 12

updated forecast for PH2O is more uncertain but reflects current cost trends
and the complexity of the proposed project – section 7 of this report. 
5.9 Given there is likely to be inflationary pressures on other Capital projects and
programmes not reflected in the table, the potential funding shortfall over the
current Capital Delivery programme should reasonably be viewed as a
minimum. 
5.10 The Council’s long term Capital funding is based upon an assumed £12
million of Scottish Government Capital Grant funding each year matched by
£12 million of additional Council borrowing, giving a recurring Capital budget
from 2028/29 onwards of £24 million each year. 
5.11 Given the condition of the Council’s various asset portfolios; the financial
implications of addressing net zero requirements in developing projects; the
expected demands on the Council’s future Capital budget and the impact of
inflation, the Council’s future Capital budget is now significantly underfunded,
even with a focus on investing in existing assets. 
Impact of Increased Borrowing Costs 
5.12 The level of capital investment which can be met from the current funding
strategy is also determined by the cost of borrowing. The Council’s Capital
expenditure is predominantly financed through long-term borrowing from the
Public Works Loans Board (PWLB) as illustrated below: 
Source: Appendix I, Capital Monitoring Report No 3 (Report 23/31 refers) 
Capital
Borrowing
78%
Contributions
4%
Capital Grants
17%
Capital
Receipts
1%
Financing  of £696 million General Fund Capital Budget
2022/23-2027/28

Page 13

5.13 At the time the Capital Budget was last set in February 2022, the interest
rates on PWLB borrowing were forecast to be in the range of 2%-3% over
the medium to longer term. As Council will be aware, the impact of inflation
and uncertainty in the financial markets has led to a marked increase in
borrowing costs and this applies equally to Council borrowing. This is
particularly significant for the delivery of the Capital Budget given that much
of the Council’s borrowing requirement will be over the next few years when
rates are expected to be most volatile. 
5.14 In December 2022, the Council approved adopting an updated scenario for
long-term borrowing costs. This assumes that the average or consolidated
interest rate on Council borrowing (including both historic and future
borrowing) will be in excess of 3% over the longer term (Report 22/310
refers). 
5.15 As the Council’s Capital financing is supported by the managed use of the
Capital Fund, increased borrowing costs will also accelerate the period over
which the Capital Fund is run down. The funding strategy approved in
February 2022 projected that the Capital Fund would be fully applied by
2045/46, at which point the Council would require to address a recurring
deficit in its borrowing costs.   
5.16 Dependent upon assumptions on the Council’s future consolidated interest
rate, the Council’s Capital Fund may potentially be fully applied somewhere
between the early 2030s and early 2040s. Small movements in the modelling
assumptions can have a significant impact on the sustainability of the Capital
Fund. Forecasts on the Capital Fund will be reviewed in developing an
updated Capital funding strategy for consideration by Council. 
5.17 In the separate Revenue Budget & Change Plan 2023/24 -2025/26 report to
this meeting of the Council, it is proposed to increase the Council’s Loans
Charges Budget by £600,000 per annum from 2023/24 onwards. This
adjustment is intended to provide some resilience against the impact of
forecast higher borrowing costs over the medium term, rather than increasing
the Council’s immediate investment capacity.   
5.18 As set out in section 4 above, work on corporate asset management planning
and the development of the initial 30 Year Investment Plan will be undertaken
over the calendar year. This work is intended to provide a strong evidence
base for future Capital investment and dis-investment based on addressing
need.

Page 14

5.19 It would normally be the case that the Council would roll forward the Capital
Delivery Plan by one year to 2028/29. As set out above in Sections 4 and 5 of
the report, it is not proposed to do this at this time as: 
• Further work requires to be undertaken on the Council’s asset
management planning to review and prioritise the Council’s investment
need over the medium and longer term, with an anticipated focus on
investment in existing assets. 
• The existing approved Capital funding strategy is now insufficient to
support the delivery of the entire Capital programme as currently
specified due to the impact of construction inflation. 
• Recent increases in borrowing costs, which are anticipated to remain
higher than previously forecast, at least in the medium term, will further
increase the Revenue cost of Capital investment. 
• Core funding assumptions beyond 2027/28 are insufficient to meet the
cost of the current Capital programmes of works 
• The Council, therefore, requires to review its Capital funding strategy to
support its identified investment need over the next 12 months. 
RECOMMENDATION 
5.20 It is, therefore, proposed that Council approves updating the current Capital
Delivery Plan for the five-year period 2023/24- 2027/28 in advance of a new
long-term Investment Plan; Capital Delivery Plan and Capital funding strategy,
linked to a new Corporate Asset Management Plan, being approved in
February / March 2024. 
5.21 It is recommended that Council: 
(c) Approve the development of a long-term Investment Plan and revised
Capital funding strategy beyond 2027/28 for consideration in setting the
Capital Budget in February / March next year.

Page 15

6. GENERAL FUND CAPITAL RESOURCES AND UPDATED CAPITAL
DELIVERY PLAN FOR 2023/24 -2027/28
Local Government Finance Circular 11/2022 
6.1 Local Government Finance Circular 11/2022 details provisional Scottish
Government Revenue and Capital grant funding allocations for each local
authority. No funding information is provided beyond financial year 2023/24. 
6.2 Scottish Government Capital grant funding in 2023/24 is £826.641 million
comprising £687.537 million of General Capital Grant and £139.104 million of
Specific Capital Grants. Included within the General Capital Grant allocation is
£33.6 million for flood protection schemes. 
6.3 Perth & Kinross Council’s provisional Scottish Government Capital Grant
funding in 2023/24 is £24.041 million. After adjusting for Capital Grant funding
for 2023/24 received in the current year and resources reflected in the
Revenue Budget, the total amount of Scottish Government Capital Grant
funding for 2023/24 shown in Appendix 1 to the report is £22.832 million,
comprising £22.160m of General Grant and £672,000 of Specific Grant. 
2023/24 Scottish Government Capital Grant Funding
General Specific Total
Grant Grant
£'000 £'000 £'000
General Capital Grant (exc Flood Schemes) 19,103 19,103
General Capital Grant allocation for Flood Schemes
Comrie 1,776 1,776
Milnathort 1,272 1,272
South Kinross 1,076 1,076
Scone 142 142
Specific Capital Grant: Cycling, Walking & Safer Streets 672 672
Grant Funding per Circular 11/2022 23,369 672 24,041
Grant Funding for 2023/24 received in 2022/23
Play Parks 291 291
Coastal Change Adaptation 100 100
LESS: Resources reflected in the Revenue Budget -1,600 -1,600
Scottish Capital Grant Funding in 2023/24 (Appendix 1) 22,160 672 22,832
6.4 Finance Circular 11/2022 also includes updates to Capital Grant funding in
the current financial year with the Council receiving £913,000 of the £30
million national allocation for implementing Free School Meals: £176,000 for
the Nature Restoration Fund and £100,00 for Flood Schemes.

Page 16

6.5 Including all adjustments, the Council’s estimated General Fund, Gross
Capital Resources for the 5-year period 2023/24 -2027/28 total
£565.131million.  Individual budget lines in Appendix 1 are shown net of
Specific Capital Grants; ring-fenced receipts; Tay Cities Deal and Transport
Scotland funding and third party contributions. This position will be updated at
the end of the financial year for resources carried forward from 2022/23. 
6.6 Appendix 1 to the report details the 5 Year Composite (General Fund)
Capital Delivery Plan 2023/24 – 2027/28 based upon estimated Gross
resources over the period. The position has been updated since the Finance
& Resources Committee on 1 February 2023 for a net £12.575 million
increase in resources. 
6.7 Appendix 1 does not include any proposed allocation of the £25.6
million remaining investment capacity under the approved Capital
funding strategy detailed in paragraph 5.5. 
RECOMMENDATION 
6.8 It is recommended that Council: 
(d) Approve Appendix 1 to the report as the basis for updating the
Composite (General Fund) Capital Delivery Plan for the 5-year period
2023/24 - 2027/28. 
7. BLAIRGOWRIE RECREATION CENTRE 
7.1 The Final Business Case for the Blairgowrie Recreation Centre is attached at
Appendix 2 to the report for consideration by Council.   
7.2 The current Blairgowrie Recreation Centre is the main indoor sports facility
serving the Blairgowrie and surrounding Eastern Perthshire community and
Blairgowrie High PE department. Although there have been no major
upgrades to Blairgowrie Recreation Centre since it was built in 1982, it
continues to meet the needs of curriculum delivery.  
7.3 Both Blairgowrie High School and the existing Blairgowrie Recreation Centre
are currently rates as B “Satisfactory” for condition and C “Poor” for suitability.
7.4 In June 2016, the Council approved a Capital budget allocation of £17.2
million to provide for the replacement of Blairgowrie Recreation Centre
(Report 16/277 refers). This represented the estimated cost, at that time, of
replacing the centre on a like for like basis in accordance with prevailing
building standards.

Page 17

7.5 Engagement with the Blairgowrie community was undertaken through a user
reference group facilitated by Council officers and the scope for the project
was developed through a consultation process undertaken by PMR sports
and Sports & Leisure Consultants. 
7.6 The Council’s commitment to tackling climate change and the legislative
responsibilities now placed upon Scottish local authorities to achieve net-zero
have led to the Council adopting Passivhaus low carbon building standards as
the optimum model. The Perth Riverside Primary School and the replacement
Perth High School are both designed to Passivhaus standards. The
Blairgowrie Recreation Centre has similarly been designed to Passivhaus
standards which represent the current highest standards in sustainable
construction and low energy design. 
7.7 The proposed scope of the new Blairgowrie Recreation Centre has also
changed significantly since the original proposal of a direct replacement for
the existing facility. The new Blairgowrie Recreation Centre has now been
designed to comprise: 
• a 6 lane 25m pool
• a 4-court hall
• a 2-court hall/ gymnasium
• dance studio and fitness suite
• accessible changing facilities
• all weather pitch
7.8 The Gross Internal Floor Area (GIFA) of the redesigned Blairgowrie
Recreation Centre will be approximately 78% greater than the existing facility.
The revised footprint for the facility has, however, been designed so as not to
impact upon the operation of Blairgowrie High School. 
7.9 Both the significant increase in scope of the project and the adoption of
Passivhaus design and build standards has led to a series of revised cost
estimates for the proposed project. In October 2020 the cost estimate for the
project was increased to £24m (Report 20/175 refers), which was updated in
setting the budget in February 2022 to £26.7 million (Report 22/36 refers). 
7.10 The current cost estimate for Blairgowrie Recreation Centre is £36 million.
The movement in estimated costs reflects completion of detailed design work
and the tendering of works packages in a climate of significant inflation in
construction costs.  Officers are currently evaluating the offer from Hubco and
the appointed contractor BAM in terms of compliance with the Council’s
specification. 
7.11 The opening date of the new facility is still to be confirmed but, subject to a
final decision of Council, is anticipated to be in 2025.  This would be impacted
by the proposal to pause and review this project.

Page 18

7.12 The annual current and indicative net revenue operating costs (energy;
cleaning; lifecycle maintenance and LAL contract fee) for both the existing
and the proposed new facility are set out section 4.4 of the Full Business
Case and summarised in the table below: 
Current and Indicative Net
Revenue Operating Costs for
Blairgowrie Recreation Centre
(per Full Business Case, Appendix
2)
2022/23
Existing 
Blairgowrie
Recreation
Centre
£’000
2024/25
Existing 
Blairgowrie
Recreation
Centre
£’000
2024/25
New 
Blairgowrie
Recreation
Centre
£’000
Current net operating costs 336  
Indicative net operating costs**  496 595
Additional revenue pressure in
comparison to 2022/23** 
160 259 
**Indicative only and potential issues are referenced in paragraph 7.13 below 
The costing above largely reflects the assumed impact of future energy
inflation on the cost of operating the current facility. In comparison, while a
new facility built to Passivhaus standards will have far greater energy
efficiency, this is forecast to be offset by additional operating costs in relation
to the increased size (78%); complexity and broader range of facilities
provided. 
7.13 Operating costs for the proposed new facility must be considered indicative
at this time as assumptions have required to be made on energy;
maintenance; usage and income. In addition, the following issues will require
to be confirmed: 
Blairgowrie Recreation Centre is currently occupied and operated on behalf
of the Council by Live Active Leisure and attracts 100% charitable Non-
Domestic Rates (NDR) relief through this contractual arrangement.  It is
assumed in the Full Business Case that this will continue and that a new
Blairgowrie Recreation Centre will also be exempt from paying rates. The
total amount of NDR relief the Council can award is, however, a “fixed pot”
limited to the total level of NDR relief in November 2017 uprated for annual
changes in rate poundage and periodic revaluations.  Any future change in
non-domestic rates relief due to the limits of this “fixed pot” would create a
significant additional cost pressure, particularly given the increased size and
rateable value of the proposed new Blairgowrie Recreation Centre. 
Further work requires to be undertaken in developing an operating model for
the proposed new facility and the indicative LAL contract fee included within
the Final Business Case makes no provision for increased opening hours
and / or for the provision of an expanded range of activities.

Page 19

The indicative costing assumes a 15% increase in use and income in the first
year of operation with further growth thereafter. In addition, there are also
assumptions on a review of fees from 2024/25 onwards. The extent to which
actual demand and / or pricing varies from these assumptions will impact on
the net cost of operation. 
7.14 The proposed new Blairgowrie Recreation Centre would represent a
significant investment in expanding the sport and recreation offer to the
Blairgowrie and surrounding Eastern Perthshire community based upon a
building designed and constructed to the highest current standards in terms
of sustainability and energy efficiency. 
7.15 The revised cost of delivering the new facility is, however, significant and has
increased by £9.3 million or approximately 34% from the estimated cost
reflected within the Capital Budget in February 2022. 
7.16 Revenue cost pressures from operating the new facility will depend upon the
operating model adopted; opening hours; the leisure offer as well as demand
and pricing. These factors can be modelled but actual experience may vary.
Based upon indicative costing and modelling, the additional revenue cost of
operating the facility as shown within the attached Final Business Case is
approximately £259,000 per annum more (at assumed 2024/25 prices) than
the current operating costs for the existing facility. 
This excludes any costs (operating contract; energy etc) from an extension
to the existing opening hours to promote increased community access or any
risk around future non - domestic rates relief.   No provision is currently
included within the Provisional Revenue Budget for additional costs in
respect of the operation of a new Blairgowrie Recreation Centre so this
would represent a Revenue pressure which would require to be addressed.   
7.17 The Council is currently undertaking an extensive consultation exercise with
local communities around the issue of Place through the “Big Conversation”.
It is anticipated that the need for further investment in other Council owned
assets in Blairgowrie will be identified through this consultation. In this
context, the assessed suitability rating of Poor for the adjacent Blairgowrie
High School is expected to feature in community feedback.  The completion
of this consultation exercise over the coming months will provide a stronger
evidence base for future investment in Blairgowrie and other communities. 
RECOMMENDATION 
7.18 Given the significant financial pressures on the Council’s Revenue and
Capital Budgets, the officer recommendation is to pause the delivery of the
new Blairgowrie Recreation Centre on the grounds of the affordability of the
overall capital programme. The project could then be considered in the
context of the feedback from the Big Conversation on place as part of a
wider consideration of the Capital investment needs of the Blairgowrie
community.

Page 20

7.19 To date, the Council has incurred £1.9 million in developing the project with
total costs up to the time of Financial Close estimated at approximately £3.03
million. Should the project be significantly reviewed or even cancelled at a
later stage, these costs would require to be met from the provision for the
facility within the Capital Budget.   
7.20 It is recommended that Council:
(e) Approve pausing the delivery of the new Blairgowrie Recreation Centre
on the grounds of overall capital programme affordability, pending
further review of the investment needs of the Blairgowrie community. 
The existing budget provision for the project of £26.7 million will be
retained pending the outcome of the review. 
8. PH2O 
8.1 In February 2023, the Council approved funding of £90 million for the creation
of a combined leisure facility on the current site of the Dewars Centre and  
Perth Leisure Pool. In outline, the proposed facility includes: 
• Large leisure water 
• 25m traditional pool with movable floor 
• 12.5 x 8.5m teaching pool with movable floor  
• Gym/group fitness facilities (3 studios)
• Bowling – 6 lanes 
• Ice – 8 lanes
•  Health spa; family play area; flexible conference facilities and a café.
8.2 The “PH2O” project is envisaged as an ambitious and significant investment
in sport and leisure in Perth city based upon a Passivhaus design to ensure
a building meeting the highest standards in sustainable construction and
energy efficiency. A project Board has been established, supported by
Council officers, comprising elected members and board members of Live
Active Leisure (LAL), to oversee the development of the project. 
8.3 Whilst due diligence was undertaken in arriving at an original cost estimate
for the PH2O project, the inflation impacting upon the Council’s overall
Capital programme has resulted in a revised cost estimate for the PH2O
project of £110 million. This reflects both the scale and complexity of the
proposed facility. 
8.4 The operating model for the proposed PH2O facility is also impacted by the
global rise in energy and maintenance costs. Although the vision is to deliver
a highly energy efficient building, the inherent nature of the facility – which
requires both maintaining large volumes of leisure water at an acceptable
temperature and maintaining ice in an appropriate condition, will inevitably
mean that the facility will be a high energy user. A number of both public and

Page 21

private swimming facilities have recently been temporarily closed in light of
substantial increases in operating costs. 
RECOMMENDATION 
8.5 As elected members will be aware, the Council’s ALEOs operate sports; arts
and cultural facilities owned by the Council both in Perth City and across
Perth and Kinross. Many of these facilities require investment, as do the
facilities owned and operated by LAL. Given the significant financial
pressures on the Council’s budget, it is important to reconsider how best to
target the Council’s investment in its overall sports; arts and leisure offer for
the benefit of the wider community. 
8.6 To date, the Council has incurred approximately £273,000 in developing the
PH2O project. Pending the outcome of the wider review, these costs may
require to be met from within the existing Capital budget 
8.7 The current policy requirement to meet net zero levels in development
projects is resulting in significant additional costs being introduced to
projects such as PH20. At a time when there are challenges in balancing the
financial and sustainability requirements placed upon the Council, it will be
necessary to consider how we maintain both of these Council commitments
within the development of this project and the Council’s wider Corporate
Asset Management Plan. 
8.8 It is recommended that Council 
(f) Approve pausing the development and delivery of the PH2O project, on
the grounds of overall capital programme affordability. The existing
budget provision for the project of £90 million will be retained pending
the outcome of the review. 
9. PERTH ECO INNOVATION PARK  
9.1 The project which is the subject of ‘Perth Eco-Innovation Park’ Outline
Business Case (attached at Appendix 3 to the report) concerns phase 1 of a
larger project and will provide the critical enabling infrastructure and site
preparation works to unlock the full 240-hectare site at Perth West. The
unlocking of Perth West will drive the ambition of the Council and
stakeholders for Perth City to become one of Europe’s most sustainable
small cities through its focus on a net zero, high value and innovation driven
economy. The Eco-Innovation Park will contribute to the diversification of
Perth’s economy, which is over-reliant on generally lower skilled hospitality,
retail and tourism jobs; as well as improving the city’s productivity and
competitiveness and supporting a Just Transition to net zero. 
9.2 The Perth Eco Innovation Park forms part of the Economic Wellbeing Plan
approved by Council in March 2021 (Report 21/37 refers) and is included
within the current Capital Delivery Plan. The project objectives are:

Page 22

-  By 2026, to deliver the enabling infrastructure to unlock 11 hectares
development-ready employment land, establishing the first phase of the
planned 25+ hectare Eco-Innovation Park, alongside residential
development, community facilities, mobility hubs and amenity features. 
-  By 2035, to attract new and grow existing businesses, capture sustainable
mobility and smart energy opportunities to create high value jobs in the clean
growth sector (1,000 jobs). 
- To be a catalyst to drive business and place innovation establishing Perth as
a city-scale ‘living lab’ and support the transition to a data and technology
driven, net-zero economy. The Project will integrate with the Perth
Innovation Highway Tay Cities Deal funded project, a 5-mile innovation
corridor, which will connect Perth Eco-Innovation Park to the city centre in a
sustainable way with physical and intelligent digital, energy and transport
infrastructure. 
9.3 Phase 1 of the project relates to the enabling infrastructure (A9 underpass
and local road improvement works) to allow vehicular access to the site. The
estimated cost for Phase 1 is currently £32.8 million, based upon a projected
£25.2 million cost for works and a 30% contingency in line with HM Treasury
Green Book methodology to provide for delivery uncertainties. Details of the
cost estimates are set out in section 4.1 of the Outline Business Case
attached at Appendix 3. It is acknowledged that completing the enabling
works by 2026 represents a challenging timescale for delivery. 
9.4 Over the long-term, it is forecast that the enabling works will be financed
through developer contributions on housing of £20 million; from the sale of
serviced employment land estimated at £5.1 million and from £5 million of
funding from the Tay Cities Deal for the Innovation Highway which forms part
of the overall project. Members will be aware that the Council’s recent
application for £10 million of Levelling Up grant support towards the cost of
enabling works was unsuccessful and the Council is awaiting feedback on its
application. 
9.5 Members will recognise that the Council operates in a competitive market in
presenting economic development opportunities to potential investors. The
Head of Planning & Development has advised that there is no realistic
prospect of investors meeting infrastructure costs nor, indeed, of any
commitment to investment in advance of a confirmed project. Given the
importance of the overall long-term project to the Perth and Kinross
economy and local employability, the delivery of the Phase 1 enabling work
is considered a strategic priority. 
9.6 The Council is, therefore, requested to approve allocating £10 million from
the balance of investment capacity set out in paragraph 5.5 as a statement
of the Council’s commitment to the project and to enable planning, design
and preliminary works to begin. Officers will bring forward proposals to fund

Page 23

the remaining cost of the enabling works as part of the development of an
updated Capital funding strategy for consideration in 2024.   
9.7 It is recommended that Council: 
(g) Approve funding of £10 million towards the cost of delivering enabling
works for Phase 1 of the Perth Eco Innovation Park to be met from the
balance of investment capacity as set out in paragraph 5.5 of the report
and remit officers with reflecting the remaining cost of the enabling
works as part of the development of an updated Capital funding
strategy for consideration in 2024. 
10 FURTHER RECOMMENDATIONS 
10.1 The Executive Leadership Team has undertaken an early assessment of
asset conditions and priorities across the Council’s current asset portfolios
which has highlighted several immediate investment requirements. From this
assessment, the following projects have been identified as priorities and  are
recommended for inclusion within the 5 Year Composite (General Fund)
Capital Delivery Plan 2023/24 – 2027/28. 
GARRY VIADUCT 
10.2 The Garry Viaduct is a three-span structure supporting the B8019 over the
Garry River and Highland Railway line in the Killiecrankie Gorge. The
structure was constructed in 1969 and the original bearings supporting the
deck (road) are still in place and are now suffering from significant corrosion. 
10.3 The B8019 provides road access from Pitlochry to Loch Tummel and serves
both local communities and the tourism economy in the Pitlochry area. As
the viaduct carries the road over a main railway line, any failure of the
structure and subsequent unplanned closure would likely result in both
significant disruption to local road traffic and, potentially, network rail
operations.   
10.4 The Strategic Business Case for investment is attached at Appendix 4 to
the report with the cost for the repair works currently estimated at £4.4
million phased for design and delivery over the next five years 
10.5 It is recommended that Council 
(h) Approve funding of £4.4 million for the repair of the Garry Viaduct for
inclusion as part of the Council’s Structures programme, to be met from
the balance of investment capacity as set out in paragraph 5.5 of the
report.

Page 24

MOSAIC 
10.6 MOSAIC is the Council’s replacement adult care software system which is
integral to supporting client care: client record management and the efficient
charging for residential services. The Council’s investment in MOSAIC
includes the cost of project support staff implementing the system. Due to
delays in procurement, there is a requirement to extend the contracts of the
project team to ensure that this key system can be appropriately supported
during its implementation phase. The cost of the contract extensions is
£442,000. 
10.7 It is recommended that Council:
(i) Approve additional funding of £442,000 in 2023/24 for the MOSAIC
system, to be met from the balance of investment capacity as set out in
paragraph 5.5 of the report. 
SEEMIS 
10.8 SEEMIS is the Council’s school management information system and is
integral to the operation of the Council’s schools.  The Council has previously
agreed that annual licensing costs for SEEMIS will be transferred from the
Revenue to the Capital budget in line with the treatment of costs for other
corporate systems.   Provision is required in the Capital Delivery Plan of
£698,000 to meet SEEMIS licensing costs over the 5-year period 2023/24-
2027/28 (£98,000 for part year costs in 2023/24, £150,000 per annum
thereafter).  
10.9 It is recommended that Council: 
(j) Approve additional funding of £698,000 to meet annual SEEMIS
licensing costs up to 2027/28 to be met from the balance of investment
capacity as set out in paragraph 5.5 of the report 
11. SUMMARY 
11.1 This report seeks to provide Council with an update on work being progressed
to inform and provide a robust evidence base for future Capital investment; on
the affordability of the current Capital programme and on the Capital grant
funding provided within the 2023/24 local government settlement. 
11.2 The report confirms that the Capital Budget approved by Council in February
2022, is now unaffordable in its entirety, due to the impact of construction
inflation combined with the emerging issue of higher than anticipated
borrowing costs. 
11.3 In response, it is recommended that the Council updates the Composite
(General Fund) Capital Delivery Plan for the 5 Year period 2023/24 – 2027/28

Page 25

at this meeting of the Council and looks to set a future budget for 2027/28 and
beyond on a more sustainable basis in February / March next year. 
11.4 In light of pressures on the Council’s budget and issues of affordability, the
report makes recommendations to Council on specific projects. These
recommendations also reflect proposed additional investment where this is
considered strategic or urgent and important. 
11.5 Under the existing Capital funding strategy approved by Council in February
2022, there is a forecast balance of investment capacity of £25.6 million. The
recommendations contained within this report, if approved in their entirety,
would allocate £15.6 million of this balance as follows: 
Para £ million £ million
Balance of Investment Capacity 5.5 25.6
Recommendations in report
Contribution toward enabling works for Perth 9.7 (10.0)
Eco Innovation Park
Garry Viaduct repairs 10.5 (4.4)
Funding for implemntation of MOSAIC system 10.7 (0.4)
Funding for SEEMIS licensing 10.9 (0.7) (15.5)
Investment Capacity (updated) 10.1   
11.6 Subject to approval of the recommendations on the Blairgowrie Recreation
Centre and PH2O projects, there is no proposed reallocation of the budgets
for these projects pending completion of the proposed review work.  
Author(s)
Name  Designation Contact Details
Stewart MacKenzie Head of Finance CHXFinance@pkc.gov.uk   
Business Case Leads  
Blairgowrie Recreation
Centre
Greg Boland  Head of ECS Business
and Resources 
Perth Eco Innovation
Park
David Littlejohn  Head of Planning &
Development 
Garry Viaduct
Barbara Renton  Executive Director
(Communities)

Page 26

Approved 
Name Designation Date
Stewart MacKenzie Head of Finance  22 February 2022
Karen Donaldson Chief Operating Officer 22 February 2022
Thomas Glen Chief Executive 22 February 2022

Page 27

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
The undernoted table should be completed for all reports. Where the answer is ‘yes’,
the relevant section(s) should also be completed    
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment Yes 
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications    
Corporate Plan 
1.1 The Council’s Corporate Plan 2022 – 2027 lays out seven outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
• Tackling poverty
• Tackling climate change and supporting sustainable places
• Growing a sustainable and inclusive local economy
• Enabling our children and young people to achieve their full potential
• Protecting and caring for our most vulnerable people
• Supporting and promoting physical and mental wellbeing
• Placing communities at the heart of how we work 
1.2 This report relates to all objectives.

Page 28

2. Resource Implications 
Financial 
1.1 There are no direct financial implications arising from this report other than 
those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1  Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups. Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the 
Corporate Equalities Impact Assessment process (“EqIA”) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act
2008, the Council has a general duty to demonstrate its commitment to
sustainability and the community, and the environmental and economic
impact of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Executive Leadership Team has been consulted in the preparation of this
report.

Page 29

2. BACKGROUND PAPERS 
5.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973, other than any containing confidential or exempt
information, were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
Appendix 1 – Composite (General Fund) 5 Year Capital Delivery Plan
2023/24-2027/28 
Appendix 2 – Final Business Case: Blairgowrie Recreation Centre 
Appendix 3 – Outline Business Case: Perth Eco Innovation Park 
Appendix 4 – Strategic Business Case: Garry Viaduct