1 | F u l l B u s i n e s s C a s e
APPENDIX A 
Full Business Case 
PERTH HIGH SCHOOL - REPLACEMENT 
Title: Perth High School - Replacement
Executive
Sponsor:
Sheena Devlin Version: 3.0
Author: Greg Boland and Stephen
Crawford
Updated: 09/12/2022

Page 2

2 | F u l l B u s i n e s s C a s e
Executive Summary 
1. Strategic Case 
1.1. Project Objectives 
Perth and Kinross Council's Learning Estate Strategy outlines the strategy to consider
the development and management of the Learning Estate in context of meeting
national and local outcomes, planning ahead and providing best value and benefits to
our communities.  The Learning Estate Strategy aligns with and complements the
Council’s recently approved Investment Blueprint and 30-year Investment Plan. 
The Learning Estate Management Plan (2021-2024) which implements the Learning
Estate Strategy was approved by Lifelong Learning Committee in November 2021 and
includes the project to replace Perth High School with a new, modern and carbon
efficient facility for the delivery of the secondary education curriculum. 
1.2. Existing Arrangements 
Perth High School is the largest secondary school in Perth and Kinross with a capacity
of 1546 pupils.  The capacity of the new school has been slightly increased to 1600
based on analysis of future roll projections. 
The school is currently rated ‘C’ ‘Poor’ in terms of both Condition and Suitability.
Condition ‘Poor’ is defined as showing major defects and/or not operating adequately. 
‘Poor’ in terms of suitability is defined as showing major problems and/or not operating
optimally (the school buildings and ground imped the delivery of activities that are
needed for children and communities in the school).
Condition Summary
Building Structure
Structural investigations in 2015 identified necessary structural repairs.  These were
completed to repair and seal the external façade and structure.  The building is
maintained on an annual structural engineer's visual inspection. 
Roofs
Various essential roof upgrade works, and repairs have been carried out at Perth High
School since the replacement was approved by Council.  This included re-roofing to
the kitchen area and small gym halls.  The roofs are being maintained but given the
age and general condition of the building it is anticipated that further repairs and
maintenance will be required in future.

Page 3

3 | F u l l B u s i n e s s C a s e
Building Fabric, Windows, and Doors                
Perth and Kinross Council have worked in conjunction with Police Scotland to review
the security arrangements around the school following a number of recent vandalism
attempts.  As an outcome, several of external doors were replaced to enhance the
security of the building. 
In general, the building fabric, windows and doors at Perth High School are currently
in a satisfactory condition but the building fabric is beyond its design life and in need
of significant investment over each year the building remains in operation in order to
prevent deterioration to the extent where significant investment is required to bring the
building back to an acceptable standard.
Mechanical and Electrical Infrastructure
The majority of the existing mechanical and electrical infrastructure is now over 50
years old and as such is beyond its original design life.  
Remedial investment was spent on Perth High School in 2018 to partially replace
failing boiler plant and to upgrade some heating circuits serving the CDT, Geography
and Library areas of the school which were failing.
Further investment will be required to the mechanical services installation from 2023
onwards to replace life expired plant and equipment and to install new heating
controls linked to the Council’s Building Management System.  This work is essential
to ensure Service continuity and to support reduced energy consumption and greater
control over heating within the school. 
Statutory electrical inspection and testing (now on a shorter 3-year inspection
schedule) has identified specific areas for investment to the electrical installation in
order to ensure the building is maintained in a safe and operational condition.
Electrical upgrade works have been carried out to replace existing lighting systems
within classrooms, the main concourse, games halls and the assembly hall with new
low energy LED lighting and associated controls.
There is a requirement to progress with further electrical upgrade works within the
main 4-storey block in future years to maintain the electrical installation to a
satisfactory standard.
Given the age and condition of the electrical installation at Perth High School, the
frequency of inspection and testing has been increased in order to identify any
electrical related defects at an early stage.  This approach has been put in place to
reduce potential disruption of Service delivery and ultimately to avoid failure of the
electrical infrastructure. 
Fire and Security                    
A new L1 (designed for the protection of life) fire alarm system was installed alongside
improved fire compartmentalisation in accordance with Scottish Fire and Rescue
Service advice.  The fire alarm system is in working order.

Page 4

4 | F u l l B u s i n e s s C a s e
The existing intruder alarm system requires upgrading to protect against increased
vandalism and attempted break-ins to the school.  These works are being costed at
present with the intention of proceeding with the installation upgrade in 2023/24.
Statutory inspections and servicing programmes are in place for both Fire and
Security systems to highlight any further requirements for repairs and maintenance
going forward.
Reactive Maintenance Calls to Property Services Helpdesk
Over the last 5-year period there has been an average of 284 calls logged on the
Property Helpdesk relating to break downs and repair works.  These calls relate to a
mixture of building, electrical and mechanical repairs of varying levels of priority.  Over
the last 5 years, there has been a consistent increase in the number of reactive calls,
especially related to electrical issues.
Reactive repair calls to helpdesk per annum 
2018/19 2019/20 2020/21 2021/22 2022/23
260 282 236 (Covid-19) 303 342 YTD,
projection
400+  
Maintenance and Investment
Council Revenue and Capital spend on maintenance over the last 5 years at Perth
High School is £3.2m.
Based on the spend profile over the last 5-year period and taking into consideration
both the current condition of Perth High School and the known areas of investment
needed, the estimated annual spend required to maintain Perth High School in a
satisfactory condition is estimated to be in the region of £800k - £1m.  This investment
is needed across the fabric of the building and a range of services.  This assumes the
building would be kept in operation for a further 5-year period and allows for the
anticipated inflationary cost increases.  
Suitability Summary
Perth High School is graded ‘Poor’ in terms of suitability.  This is defined as showing
major problems and/or not operating optimally (the school buildings and ground
impeded the delivery of activities that are needed for children and communities in the
school).
In the latest questionnaire of staff and pupils, 715 of the learners and 58 staff
responded about the current school environment.  65% of learners and 96% of staff
said the existing school building “is not fit for purpose” or “needs to be improved
greatly”.  
77% of staff said noise levels were “poor” or “extremely poor”, 60% said ability to work
in groups was “poor” or “extremely poor”.  83% said that student social space was
“terrible” or “poor”.  87% said that student study space was “terrible” or “poor”.

Page 5

5 | F u l l B u s i n e s s C a s e
The building does not provide the flexible learning spaces which facilitate collaborative
learning and inter-disciplinary learning; access to technology; independent learning
and the social environment.  The school has very poor adjacencies and narrow
circulation space.  This severely inhibits any refurbishment which would aim to
improve the suitability with modern, flexible teaching spaces.
A feasibility study was carried out in 2017 through hub East Central Scotland (hubCo)
strategic services which established an outline strategy and confirmed that the
existing site was, in principle, suitable for a tandem build replacement school.  In
2018, Council approved funding for a new school and this has formed the direction of
travel since then. 
1.3. Business Need 
The results of surveys carried out in 2015 determined the lifespan of the current Perth
High School building at between 10 and 20 years, the risk of failure of our largest
secondary school serving nearly 1600 pupils required action by the Council. 
Due to the poor condition of the building, rating of C, the poor suitability rating of C,
the risk of failure of the building and the subsequent complexities of arranging a
decant of this magnitude and costs associated with a decant, a replacement building
was required and approved by Council.
The replacement Perth High School will provide a modern learning environment which
will support and enhance the experience of learners and staff.
In addition, responding to climate change is a major priority for both the Scottish
Government and Perth and Kinross Council and the carbon impact of the Council’s
current and future estate is required as a part of the Council’s Investment Blueprint.
Perth and Kinross Council has confirmed its commitment to meeting climate targets by
giving approval to proceed with Passivhaus construction methods to achieve energy
efficiency and quality with the Perth High School Replacement project. 
1.4. Scope 
Analysis of the overall secondary capacity within Perth City was undertaken which
determined the need for a like for like replacement of the Perth High School with a
1600 capacity secondary school building on the existing site.
A strategic brief for the project was developed in 2019.  This was a result of a
programme of engagement activities with Council officers, Property Services
stakeholders and Perth High School leadership team, students, and staff.  A target
space budget was produced, and this has been used as the Schedule of
Accommodation including bespoke teaching spaces and learning plazas which has
generated a design that will provide a flexible, inclusive, and fit-for-purpose teaching
environment.  This was also subject to robust utilisation analysis ensuring that the
scoping of the accommodation requirements is efficient and effective.

Page 6

6 | F u l l B u s i n e s s C a s e
In September 2020, as a result of direction in the Interim Climate Change Strategy,
options were presented across all major school projects for developing as low
carbon projects, Council approved the Investment Blueprint & Capital Budget 20/21
– 28/29 including approval to proceed on the basis of a Passivhaus design at Perth
High School.  Council committed to the Passivhaus design which will ensure the
energy efficiency of the building and comply with actions set out in the Interim
Climate Emergency Report and Action Plan.  This specification and approach gave
opportunity to bid for Scottish Government Learning Estate Improvement
Programme Phase 2 funding which was awarded in 2021 which is estimated to bring
in £40.6m to the Council. 
The existing standalone Sports Hall with 4-court hall shall be retained.
Demolition of the school building and making good including all external proposals will
be carried out once the new building has been completed and handed over. 
1.5. Strategic Risks 
The strategic risks of undertaking this project are: 
• The cost of the Council’s overall capital programme has risen considerably,
and it is now unaffordable to deliver all the approved capital projects within the
existing funding available.
• There is still a risk of escalating costs given the volatility of the market, high
rate of inflation, increased cost of borrowing.  This risk is minimised on
reaching Financial Close, currently programmed for February 2023.
• Cost escalation and potential contractor/ manufacturer insolvency due to
construction market conditions and possible predicted recession.
• The Design Team do not satisfy the terms of the prestart Planning Conditions
which prevent the project being taken forward within the required timescale.
The strategic risks of not undertaking this project are: 
• Existing school not meeting the requirements of modern secondary curriculum
delivery with increasing building issues currently being experienced.
• Loss of £40.6m Scottish Government Learning Estate Investment Programme
(LEIP) Phase 2 funding.
• Condition deterioration resulting in failure of fabric of existing building
(recommended urgent works have been carried out to stop immediate
deterioration, prolong the life of the building with annual surveys and
remediation works ongoing in the meantime, but the building is uneconomical
to maintain long term).
• Poor existing building fabric resulting in continued reliance on fossil fuels and a
high energy consumption – particularly relevant as Perth and Kinross Council’s
largest property asset.
• Reliance on ageing mechanical and electrical systems.
• Not reducing the Council’s carbon footprint.

Page 7

7 | F u l l B u s i n e s s C a s e
1.6. Constraints 
Financial Constraints
Further financial commitment of £11.5m is required to build the replacement Perth
High School.
Operational Constraints
It is a necessity that the existing facilities are available to the school and community
throughout the life of the project. 
This necessitates a tandem build approach with the replacement school built on part
of the school playing fields while the existing building remains operational.  This
approach imposes constraints on the design and build including the site available for
construction and formation of replacement external PE facilities.
Commercial Constraints
The market must be able to build a modern fit for purpose 1600 capacity secondary
school.
The predicted recession in 2023 may impact the availability of resource and materials
due to contractor/ manufacturer insolvency.  However, hubCo have been appointed as
development partner and with Perth and Kinross Council they have appointed through
their supply chain a Tier 1 contractor (Robertsons) and key subcontractors to deliver
the contract through a design and build contract. hubCo / Robertson continually
monitor the financial health of their supply chain to mitigate /manage the risk of supply
side failure due to contractor insolvency.   
1.7. Dependencies 
Internal  External 
Area Description of
dependency
Area Description of
dependency 
Planning legislation Planning permission
has been granted
and these
conditions are being
managed by project
team.
Scottish and
Southern Electricity
(as Distribution
Network Operator)
Capacity of local
electrical
infrastructure.  This
has been part of the
precontract
activities and SSE
are contracted to
provide connections
per programme.

Page 8

8 | F u l l B u s i n e s s C a s e
Perth High School
Operations 
School operations.
The school and
project team have a
business change
plan for the
transition to the new
school.   
1.8. Impact on the Community and Community Co-production 
It is anticipated that the completed project will have a positive impact on the
community with modern facilities.  The project will afford opportunities to deliver on the
community and asset management strands of the Perth and Kinross Offer.
The building is being designed to be as flexible as possible so that it can be used for a
range of purposes.  This will include development of and support to the current
community use but may also include use by the private sector 3rd sector and the public
sector.  The school already accommodates a team from Skills Development Scotland
and has links with the private sector.  There will also be opportunities for staff from the
Council to use the school for meetings and ‘touch-down’ space, enabling a more
sustainable and efficient use of assets.  The school is already working with Robertson
Construction as a partner in the Developing the Young Workforce programme and it is
anticipated that experience and training opportunities will increase when on site.
Perth High School’s Sports Hall was created in 2014.  The investment provided a
purpose-built venue for members of the community and local sports clubs as well as
pupils, encouraging participation in sports.  This Sports Hall remains as part of the
overall campus design. 
During construction, measurable community benefits may be provided through
construction suppliers – the most likely direct benefit will be in encouraging trade
apprenticeships and providing skills training to Perth High School.  In addition, the
agreed procurement route for project via hubCo provides a genuine opportunity to
obtain community benefits and to recycle capital spend directly back into the local
economy by using local suppliers and labour where possible. 
1.9. Sustainability 
The building will be designed and constructed to meet the Passivhaus standard.  This
sets a high specification for a low operational energy / sustainable building with a low
carbon footprint and a properly ventilated environment conducive to pupil wellbeing
and learning.  The target is 67kwh/m2/per annum which betters the Council average
of 160kwh/m2/per annum, the target being a criterion to enable draw down of LEIP
Phase 2 funding from the Scottish Government.

Page 9

9 | F u l l B u s i n e s s C a s e
By adopting this approach (with an all-electric heating) in the school with the greatest
pupil numbers, Perth and Kinross Council will move towards complying with actions
set out in its own Interim Climate Emergency Report and Action Plan  and to work
towards Scottish Government targets of a 75% reduction in CO2 emissions by 2030
and Net Zero by 2045.  
Scottish Government LEIP2 funding will be subject to the building meeting enhanced
energy efficiency standards in operation - Passivhaus principles meet this standard
and support the construction quality aspirations of the project. 
1.10.   Inclusion and Equality 
The improved facilities will offer access to Perth High School pupils and staff to a
flexible, inclusive state-of-the-art secondary education learning environment.
As per section 1.8, the design of the new school building is flexible and inclusive to
ensure that appropriate opportunities are available for all areas of the community. 
1.11.   Resource efficiency 
The use of an energy efficient design and plant reduction of waste to landfill, reduction
of vehicle miles by sourcing locally, use of local labour where possible, consideration
of habitat protection during construction can all contribute of an environmentally aware
build. 
2. Economic Case 
2.1 Critical Success Factors 
• Ensuring that the provision of a modern, flexible, inclusive, and fit-for-purpose
school building for the largest secondary cohort of pupils in Perth and Kinross
and for the benefit of the local community.
• Increasing the energy efficiency of the school.
• Maintaining the operation of the school whilst the construction works are ongoing. 
• Ensuring the completed building in operation is able to access the full drawdown
of 25-year LEIP Phase 2 revenue support funding from the Scottish Government. 
2.2  Options Appraisal 
The options considered at the time of the Outline Business Case were: 
Option Accepted/
Rejected
Outcome
(a) Do nothing  Rejected Did not meet objectives, did not address
strategic risk.

Page 10

10 | F u l l B u s i n e s s C a s e
2.3 Recommendation 
The preferred option was to take forward option (c) and was approved by Council in
2018.  
Recent years has seen dramatic changes to the financial landscape.  These
changes have been caused by the COVID-19 pandemic, Brexit and more recently
the war in Ukraine and have necessitated a re-assessment of the Council’s
Corporate Priorities.  
While the replacement of Perth High School almost fully meets the following
Corporate Plan Priorities:
• Tackling poverty
• Tackling climate change and supporting sustainable places
• Enabling our children and young people to achieve their full potential
• Supporting and promoting physical and mental wellbeing
It is also appropriate to review the project against the original Critical Success
Factors:
1. Ensuring that the provision of a modern, flexible, inclusive, and fit-for-purpose
school building for the largest secondary cohort of pupils in Perth and Kinross
and for the benefit of the local community.
The design of the new Perth High School will ensure this Critical Success
Factor is achieved.
2. Increasing the energy efficiency of the school.
The Passivhaus construction will ensure the building is significantly more
energy efficient than the current building therefore meeting the terms of this
Critical Success Factor.
(b) Refurbish Rejected There were restrictions with this option
in terms of meeting current building
standards in a cost-effective manner. 
This option was not considered a
reasonable option due to the lack of
decant facilities for a school of 1600
pupils during refurbishment and lifespan
of the critical structural elements of the
building.  This was not considered value
for money.  In addition, this did not
address the suitability which cannot be
sufficiently improved.
(c) New build
secondary school
Accepted This would address condition and
suitability of the current Perth High
School and provide the opportunity to
enhance the learning environment
without the cost of decant facilities.

Page 11

11 | F u l l B u s i n e s s C a s e
3. Maintaining the operation of the school whilst the construction works are
ongoing.
The proposals and programme are for a tandem build which meets the terms
of this Critical Success Factor.
4. Ensuring the completed building in operation is able to access the full
drawdown of 25-year LEIP Phase 2 revenue support funding from the
Scottish Government. 
The building must be completed before compliance against the terms of the
LEIP Phase 2 funding can be determined.  This Critical Success Factor
cannot be assessed until the construction of the building is completed. 
However, the Passivhaus Institute have advised they believe there is a
pathway for the design to achieve Passivhaus accreditation.  Passivhaus
accreditation will meet the terms of this Critical Success Factor.
With all the information available, the preferred option to replace Perth High School
continues to be the recommendation based on the Full Business Case drivers of
Condition and Suitability, and the subsequent successful grant award of £40.6m from
the Scottish Government. 
2.4  Mandate for Investment 
The replacement of Perth High School has remained a priority for Perth and Kinross
Council since the initial approval of full capital funding on 20 June 2018 based on the
drivers of Condition and Suitability. The subsequent successful grant award of £40.6m
(index linked, drawn down over 25 years) supports the Perth and Kinross Council
investment.
Addressing climate change is one of the agreed Council corporate priorities. This
large investment contributes to this by being designed to Passivhaus standards. 
The following table reflects the budget approvals at Council:
Date Link to
Papers
Decision/ Narrative Approved
Budget
22 February/
19 April 2017
Minutes
Council
Mtg 22
Feb 2017
/Report
17/153
Approval of additional capital
expenditure proposals including
significant investment in Perth High
School (£10M)
£10m
20 June
2018
Report
No.
18/212
Approval of Composite Capital Budget
2018- 2028 including funding for 1600
capacity school replacement by re-
allocation of budgeted expenditure
from projects formerly included in the
Capital programme.
£50m

Page 12

12 | F u l l B u s i n e s s C a s e
30 September
2020
Report
No.
20/175
Appendix
3
Approval of Investment Blueprint &
Capital Budget 20/21 – 28/29
including approval to proceed on the
basis of a Passivhaus design with the
budget subsequently uplifted.
£58.3m 
23 February
2022
Report
No. 22/36
Appendix
1
Approval of Capital Budget 2022/23 -
2027/28 including increased project
budget as a consequence of larger
than anticipated inflation within the
construction sector.  
£68.7m  
The following table reflects the budget increase requested:
Date Link to
Papers
Decision/ Narrative Proposed
Increased
Budget
21 December
2022
Tbc Approval to fund increased costs and
increase the Project Budget by
£11.5m  
£80.2m 
3. Commercial Case 
3.1 Procurement Strategy 
The strategy is for replacement as a tandem build through the hubCo Design and Build
delivery model.  The New Project Request was submitted to hubCo, and Tier 1 and Tier
2 contractors were appointed in 2019.
The established contract strategy with use of hubCo is fully compliant with national
procurement strategies and is promoted by the Scottish Government and the Scottish
Futures Trust (SFT).  Perth and Kinross Council and hubCo are parties to the Territory
Partnering Agreement which establishes a long-term strategic partnership. 
3.2 Service Requirements 
The Project Agreement between Perth & Kinross Council and hubCo is administered by
an Authority Representative (AR) from Property Services.  Project Management
resource is committed and technical support (M&E, architectural, Energy Team etc) is
being provided.  Project specific Authority Construction Requirements (ACRs) have been
developed. 
3.3 Charging Mechanism 
The Project Agreement is administered utilising the Scottish Futures Trust’s standard
form Design and Build Development Agreement (DBDA) including standard construction
payment mechanisms such as interim valuations, applications for payment, interim
certificates, deduction of retentions and payment.

Page 13

13 | F u l l B u s i n e s s C a s e
The contract is a fixed price contract based on a firm design and specification.  Once
Financial Close is reached there are limited contractor opportunities to seek additional
monies, especially in a new build project.  Experience to date with this form of contract
has been successful.  
Payment is made direct to hubCo for works properly executed monthly and, as relevant,
the value of any goods and materials delivered to site. 
3.4 Risk Transfer 
The contract sum agreed at Financial Close (FC) shall be a lump sum fixed price to be
paid to hubCo for carrying out the full obligations agreed within the Project Agreement
namely the design and construction of the replacement Perth High School. 
3.5 Key Contractual Arrangements 
Key contractual arrangements as found within standard forms of building contract such
as provisions for quality assurance, change control, transfer of intellectual property
rights, delay events, making good defects, liquidated damages and dispute resolution
are contained within the Project Agreement. 
3.6 Personnel Implications 
The current staff within the existing Perth High School will transfer to the new school. 
3.7 Accountancy Treatment 
The completed Perth High School will be a fixed asset sitting within the Council’s
balance sheet. 
Recognition expenditure on the acquisition, creation or enhancement of Property, Plant
and Equipment is capitalised on an accrual’s basis, provided that it is probable that the
future economic benefits or service potential associated with the item will flow to the
Council and the cost of the item can be measured reliably. 
4. Financial Case 
4.1 Capital and Revenue Requirements 
The current capital spend on Stage 1 and Stage 2 project development so far has
been £4.3m. 
The estimated total project cost is currently projected to be in the region of £80.2m.  It
should be noted that this is the current estimated capital cost prior to Financial Close
and, given current volatility with the construction sector, this value should be treated
as a best estimate.

Page 14

14 | F u l l B u s i n e s s C a s e
It is intended if the additional funding is secured that officers (via The Head of Legal
Services) enter into a Letter of Intent to secure fixed prices with hubCo to elements of
the build that mitigate against additional cost escalation at Financial close (expected
February 2023). 
The revenue costs of operating a similar new building will be assessed in comparison
to the existing building to establish if there are any increased revenue implications. 
Pupil numbers will remain similar so current staffing will be maintained. 
During the construction period there will be a reduction in external PE facilities
available to the school and alternative facilities will require to provided.  It is likely that
this will introduce a revenue pressure until the completion of the Phase 2 construction
(externals).  However, a budget has been set aside for this. The Business Change
Officer is currently assessing the curriculum requirements with the school. 
4.2 Net Effect on Prices 
It is not anticipated that prices Perth and Kinross Council charge for their services will
change as a direct result of this project. 
4.3 Impact on Balance Sheet   
The balance sheet value will be in accordance with the value of the new asset
once completed. 
4.4 Impact on Revenue Budget 
The costs for this building are estimated and likely to be similar (subject to
inflation) but with £40.6m funding to be received from the Scottish Governments
LEIP Phase 2 grant award, would offset any revenue pressure. 
Any future revenue implications beyond this that are identified would be included
as an expenditure pressure through the revenue budget process. 
4.5 Funding Mechanisms and Affordability 
The project will be funded as part of Perth and Kinross Council’s approved Capital
Budget.
A bid made to the Scottish Government for LEIP Phase 2 for funding of 50%
toward the project was successful and will be provided over a 25-year period
based on the Council meeting specified targets.

Page 15

15 | F u l l B u s i n e s s C a s e
5. Management Case 
5.1  Programme and Project Management Methodology 
The project has full governance and is resourced in accordance with the Perth and Kinross
Council’s project management toolkit.
Project Structure/ Roles & Responsibilities:
Senior Responsible
Officer:
Greg Boland – Head of ECS Business & Resources
Executive Sponsor: Sheena Devlin – Executive Director Education & Children’s Services
Project Manager: Mairi Milne – ECS Team Leader Resource Management (Project
Support) 
Authority
Representative:
John Fyfe – Principal Officer (Project Management) – CDS –
Projects & Operational Support
Project Board: Greg Boland – Head of ECS Business & Resources
Brian Reid – ECS Service Manager – Resource Management
Jim Cockburn – ECS Finance & Governance Manager
Stephen Crawford – Head of Property Services – CDS
Alison O’Brien – Manager CDS – Accountancy  
Norman Ballantine – Capital Programme Manager – Communities 
Stewart MacKenzie – Head of Finance – CDS 
Alan Fraser – Education and Business Change Officer (Learning
Estate)
David Macluskey – Service Manager (Secondary) Education ECS 
5.2  Programme and Project Management Plans 
In line with approved processes and managed by the Project Board. 
5.3  Use of Specialist Advisers 
Legal specialists have been outsourced; all other consultants are procured through
hubCo. 
5.4  Change and Contract Management Arrangements 
Robust change control processes are instigated and maintained by the Project Board
and hubCo to ensure that change management is in line with approved processes.

Page 16

16 | F u l l B u s i n e s s C a s e
5.5  Benefits Realisation 
Benefit Measurement Timescale
Improvement of
educational facilities to
provide a flexible,
inclusive, and modern
secondary school building
appropriate for delivery of
the curriculum and for the
use of the local
community.
Design that satisfies all
scope requirements as
specified in Strategic Brief
and associated Space
Budget, moving the school
suitability rating from C to
A
Proposals reviewed
throughout Stage 1 and 2
project development to
ensure delivery of identified
scope.
Building to be high quality,
air-tight, well insulated,
properly ventilated, and
efficiently serviced.
Suitable design and
construction methodology
used to ensure delivery of
required building standards
and performance as
specified in the Authority’s
Construction
Requirements, moving the
school condition rating
from C to A
Passivhaus designers/
assessors used throughout
design and construction
phases and relevant
certification on completion.
Reduction in Perth and
Kinross Council’s carbon
footprint.
Annual CO2 reduced
(estimated from 473 to 249
tonnes) 
Modelling carried out to
demonstrate design delivers
required reduction and Year
1 in use analysis to be
carried out. 
5.6  Risk Management 
The risk profile is managed through reporting which has been developed into a contract
risk register with regular risk meetings and risk mitigation procedures and reported to
the Project Board for good governance.
Early strategic services provided by hubCo during Stage 1 involved extensive site
investigations which aim to reduce risks to the project. 
5.7  Post Implementation Evaluation Arrangements 
Post project evaluation at 6 months, 12 months and internal lesson learned meetings
updating Authority Change Requirements will be undertaken by the Project Board.

Page 17

17 | F u l l B u s i n e s s C a s e
5.8 Contingency Arrangements 
Contingency arrangements are imbedded in the hubCo delivery process and managed
through the Project Manager and Project Board. 
Financial Contingency
As required by all capital projects within Perth and Kinross Council a financial
contingency will be held by the client. Within the current total project cost there is a 5%
contingency held for any unforeseen issues not included in the construction contract, for
example dark ground under the existing school.  Contingency will also be utilised for
any changes requested by the client during construction.
Any claims against this contingency will be assessed by the Project Manager and if out
with set approval limits will be referred to the Project Board and Senior Responsible
Officer for approval. 
Operational Contingency 
Should the new building not be completed on programme the existing school will remain
active with the appropriate ongoing maintenance being undertaken.