PERTH AND KINROSS COUNCIL 
21 DECEMBER 2022 
PERTH HIGH SCHOOL REPLACEMENT - UPDATE REPORT 
Report by Executive Director (Education and Children’s Services)
(Report No. 22/312) 
1. PURPOSE 
1.1 This report provides the Full Business Case and an update on the project to
replace Perth High School in advance of reaching Financial Close and seeks
the Council to consider the decision on whether to:   
• proceed with an increased capital budget of £80.2m or; 
• to pause and review the project due to the current financial position of the
Council. 
2.      RECOMMENDATION
2.1 It is recommended that Council: 
• notes the current situation and consequential financial impact for
the project to replace Perth High School; 
• notes the contents of the Full Business Case for the project
(attached as Appendix A); and 
• makes the decision to approve an increase of £11.5m to the  
project budget giving a total for the project of £80.2m.  This ensures
that the Council will receive £40.6m of funding from the Scottish
Government through its Learning Estate Investment Programme
(LEIP) Phase 2 and authorises the Head of Legal Services to enter
into a Letter of Intent with the main Contractor prior to Financial
Close to secure prices. 
3.  STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background
• Section 5: Current Situation 
• Section 6:  Financial Impact
• Appendices

Page 2

4.  BACKGROUND 
4.1 The Council had surveys of Perth High School undertaken by external
agents in 2015 which determined the lifespan of the current Perth High
School building at between 10 and 20 years.  The risk of failure of the largest
secondary school in Perth and Kinross, which has a roll of approximately
1600 pupils, and which has 139 (128.54 full time equivalent) staff, required
action to be taken. 
Perth High School was rated as “Poor” for Condition of the building and
“Poor” for Suitability.  Due to the risk of failure of the building, the
subsequent complexities of arranging a decant of 1600 pupils and the
magnitude and costs associated with a decant, a replacement building was
approved by Council. 
Perth and Kinross Council approved and budgeted for a replacement Perth
High School as part of the Capital Budget setting process in 2018 with an
indicative budget of £50m for a 1600 pupil capacity school.  The need for a
like for like replacement had been identified during analysis of the overall
secondary capacity within Perth City. 
A strategic brief for the project was developed in 2019.  This was a result of
a programme of engagement activities with Council officers, Property
Services stakeholders and the Perth High School leadership team, pupils,
and staff.  A target space budget (to determine the correct size of
accommodation) was produced, and this has been used as the Schedule of
Accommodation, including bespoke teaching spaces and learning plazas
which has generated a design that will provide a flexible, inclusive, and fit-
for-purpose teaching environment.  This was also subject to robust utilisation
analysis ensuring that the scoping of the accommodation requirements is
efficient and effective. 
4.2 This project was budgeted based on a feasibility study and Scottish Futures
Trust (SFT) space and cost metrics.  These included the anticipated
accommodation size and relevant building standards at the time of the
study.  Designing to these metrics is a key factor in achieving the LEIP
Phase 2 funding. 
4.3 In September 2020, recognising climate change as a priority, Council
confirmed its commitment to meeting climate targets by giving approval to
proceed with Passivhaus construction methods to achieve energy efficiency
and quality in the new Perth High School (Report No. 20/175/Appendix 3
refers). 
Council subsequently increased the Perth High School budget to £58.3m.   
4.4 Perth and Kinross Council made a bid to the Scottish Government for LEIP
Phase 2 funding and was successful, which will provide revenue funding to
the Council over 25 years to the value of £40.6m (50%) of the capital cost of
the project.  LEIP Phase 2 funding is subject to meeting specified conditions

Page 3

including energy performance standards which will be satisfied by the
Passivhaus construction specification. 
4.5 In February 2022, Council approved the 2022/23 – 2027/28 Capital Budget
including increasing the project budget for Perth High School to £68.7m as a
consequence of inflation within the construction sector as well as supply
chain issues and increased demand for commodities (Report No. 22/36
refers). 
5.  CURRENT SITUATION 
5.1 Perth High School remains rated as ‘C’ ‘Poor’ in terms of both Suitability and
Condition.  Condition ‘Poor’ is defined as showing major defects and/or not
operating adequately. 
In general, the building fabric, windows and doors at Perth High School are
currently in a satisfactory condition but the building fabric is beyond its
design life and in need of significant investment over each year that the
building remains in operation in order to prevent deterioration to the extent
where significant investment is required to bring the building back to an
acceptable standard.  The majority of the existing mechanical and electrical
infrastructure is now over 50 years old and as such, is beyond its original
design life.   
Given the age and condition of the electrical installation at Perth High
School, the frequency of inspection and testing has been increased in order
to identify any electrical related defects at an early stage.  This approach has
been put in place to reduce potential disruption of service delivery and
ultimately to avoid failure of the electrical infrastructure.  Over the last 5-year
period there has been an average of 284 calls logged on the Property
Helpdesk relating to breakdowns and repair works. 
Necessary investment has been made to maintain and improve the condition
of the building over the last 5 years at Perth High School totalling £3.2m.   
Based on the spend profile over the last 5-year period and taking into
consideration of both the current condition of Perth High School and the
known areas of investment need, the estimated annual spend required to
maintain Perth High School in a satisfactory condition is estimated to be in
the region of £800k - £1m.  This investment is needed across the fabric of
the building and a range of services.  This assumes that the building would
be kept in operation for a further 5-year period and allows for the anticipated
inflationary cost increases.   
In the latest questionnaire of staff and pupils, 715 of the learners and 58 staff
responded about the current school environment. 
• 65% of learners and 96% of staff said the existing school building “is not
fit for purpose” or “needs to be improved greatly”.  
• 77% of staff said noise levels were “poor” or “extremely poor”.
• 60% said their ability to work in groups was “poor” or “extremely poor”.
• 83% said that student social space was “terrible” or “poor”.

Page 4

• 87% said that student study space was “terrible” or “poor”. 
The building does not provide the flexible learning spaces which facilitate
collaborative learning and inter-disciplinary learning; access to technology;
independent learning and the social environment.  The school has very poor
adjacencies and narrow circulation space.  This severely inhibits any
refurbishment which would aim to improve the suitability with modern,
flexible teaching spaces. 
5.2 The project has continued as approved in September 2020 as a Passivhaus
project.  The complexity of the design process to meet Passivhaus
accreditation, which requires all elements of the design to be fully detailed
and costed prior to reaching Financial Close combined with construction
sector volatility, has led to increased prices and have prolonged the process
of securing tender packages.  The effects of the COVID-19 pandemic, Brexit
and the war in Ukraine, have resulted in continued intensified inflationary
pressures, and the unavailability of materials and labour.  This has caused
increased uncertainty within the construction market. 
As a result of the latest cost estimate, the project budget now required is
£80.2m.  The project requires an additional £11.5m capital funding to meet
the increased costs. 
There is a risk of further costs escalation due to the volatility of the market
and high rate of inflation prior to the programmed date for Financial Close in
February 2023.  The Council could minimise this risk by agreeing to the
increase in the budget and authorising the Head of Legal Services to enter
into a Letter of Intent with the main Contractor prior to Financial Close thus
securing prices and mitigating against further cost escalation. 
6. FINANCIAL IMPACT 
6.1 In advance of Financial Close, the costings received from contractors are
resulting in a total project cost of £80.2m.  This recent increase has arisen
due to the continued inflationary increases within the construction sector.
While this cost includes contingency and is based on the latest information, it
is not the final contract sum and may be subject to change up until Financial
Close is achieved. 
6.2 The shortfall in the current approved project budget is £11.5m.  To facilitate
a timeous Financial Close and enable the project to progress to the
construction phase, approval of the increased capital budget is required. 
Although the cost of the Council’s overall capital programme has risen
considerably and it is now unaffordable to deliver all the approved capital
projects within the existing funding available, the replacement of Perth High
School has remained a priority for the Council.  The approval of its
replacement is based on the drivers of the Condition and Suitability of the
existing building.  The subsequent successful grant award of £40.6m (index
linked, drawn down over 25 years to support the maintenance of the facility)
supports Council investment by meeting 50% of the project cost.  Any

Page 5

decision to not proceed with the project would mean that this funding would
be lost. 
6.3 The table below is an extract from the Full Business Case detailing budget
movements to date:  
Date Link to
Papers
Decision/ Narrative Approved
Budget
22
February/
19 April
2017
Minutes
Council Mtg 22
Feb 2017
/Report 17/153
Approval of additional capital
expenditure proposals
including significant
investment in Perth High
School (£10m).
£10m
20 June
2018
Report No.
18/212
Approval of Composite
Capital Budget 2018- 2028
including funding for 1600
capacity school replacement
by re-allocation of budgeted
expenditure from projects
formerly included in the
Capital programme.
£50m
30
September
2020
Report No.
20/175
Appendix 3
Approval of Investment
Blueprint & Capital Budget
20/21 – 28/29 including
approval to proceed on the
basis of a Passivhaus design
with the budget subsequently
uplifted.
£58.3m
23 February
2022
Report No.
22/36
Appendix 1
Approval of Capital Budget
2022/23 - 2027/28 including
increased project budget as
a consequence of inflation
within the construction
sector as well as supply
chain issues and increased
demand for commodities.
£68.7m 
The following table reflects the budget increase requested: 
Date  Link to Papers  Decision/ Narrative  Proposed
Increased
Budget 
21 December
2022 
TBC  Approval to fund increased
costs and increase the
Project Budget by £11.5m   
£80.2m

Page 6

Authors
Name Designation Contact Details
Greg Boland 
Stephen Crawford
Head of Business
and Resources 
Head of Property
Services
ECSCommittee@pkc.gov.uk 
01738 475000 
Approved
Name Designation Date
Sheena Devlin Executive Director
(Education and Children’s
Services)
13 December 2022

Page 7

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION  
Strategic Implications Yes/None
Community Plan/Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  Yes 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This section sets out how the proposals relate to the delivery of the Perth and
Kinross Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives. 
Corporate Plan 
1.2 This section sets out how the proposals relate to the achievement of the
Council’s Corporate Plan Objectives: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.

Page 8

1.3 The report also links to the Education & Children’s Services Vision, Values
and Priorities in respect of the following key Priority area: 
• Learning and Achievement 
2. Resource Implications 
Financial 
2.1 The Financial implications arising from this report are detailed within the body
of the main report and within the Full Business Case (Appendix A). 
Workforce 
2.2 The current staff within the existing Perth High School will transfer to the new
Perth High School.  The cost of the staff working on the Perth High
Replacement Project, are in the main, funded from within the Perth High
School capital budget. 
Asset Management (land, property, IT) 
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.   
3.1.1 The proposals have been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA.  
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.2.1 However, no action is required as the Act does not apply to the matters
presented in this report.  This is because these matters relate to the Learning
Estate Strategy which has been considered under the Act as part of the
Council’s Asset Management Plan. 
Sustainability

Page 9

3.3 Under the provisions of the Local Government in Scotland Act 2003, the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.   
Under the Climate Change (Scotland) Act 2009 the Council also has a duty
relating to climate change and, in exercising its functions must act: 
• In the way best calculated to delivery of the Act’s emissions reduction
targets.
• In the way best calculated to deliver any statutory adaption programmes.
• In a way that it considers most sustainable. 
3.3.1 The building will be designed and constructed to meet the Passivhaus
standard.  This sets a high specification for a low operational
energy/sustainable building with a low carbon footprint and a properly
ventilated environment conducive to pupil wellbeing and learning.  The target
is 67kwh/m2/per annum which is betters the Council average of
160kwh/m2/per annum, the target being a criterion to enable draw down of
LEIP Phase 2 funding from the Scottish Government. 
Legal and Governance 
3.4 The Head of Legal and Governance Services has been consulted in the
preparation of this report. 
3.5 N/A 
Risk 
3.6 Key risks associated with the recommendations contained within this report
are outlined in the body of the report and appended Full Business Case
document.  A risk profile is in place for the project and is managed by the
Project Board. 
4. Consultation 
Internal 
4.1 The Head of Finance, Head of Legal and Governance Services and the Head
of Property Services have been consulted in the preparation of this report.    
External 
4.2 Participation and involvement of the community is critical to the ongoing and
future success of Learning Estate investment and an emphasis is placed on
ensuring consultation, over and above that which might be required in terms
of planning requirements and statutory consultation requirements. 
4.2.1 A User Reference Group (URG) has been set up for the project.  The purpose
of the URG is to assist with providing relevant local input to allow the Design
Team to develop the outline concept design into an operational design.  The
formation of a URG is an invaluable source of information, and any project is
reliant on this level of local detail.

Page 10

5. Communication 
5.1 A stakeholder communication plan has been developed for the project. 
The plan aims to support effective communication and engagement with
all project stakeholders. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (and not containing confidential or exempt information)
were relied on to a material extent in preparing the above report. 
3. APPENDICES  
3.1  Appendix A – Full Business Case – Perth High School Replacement