Page 1

PERTH & KINROSS COUNCIL 
21 DECEMBER 2022 
REVENUE & CAPITAL BUDGET UPDATE 
Contact Officer: Scott Walker, Chief Accountant
(Report No. 22/310) 
1. PURPOSE 
1.1 This report provides an update on progress with the preparation of the
provisional Revenue Budgets for 2023/24, 2024/25 and 2025/26.   
1.2 The report also provides elected members with an update on the current
financial gap facing the Council and outlines several measures which may
contribute towards closing the gap. 
1.3 Finally, the report provides an update on the funding of the Council’s Capital
Budgets.
2. RECOMMENDATIONS 
2.1 The Council is requested to: 
(i) Note the revenue budget update presented in Section 4 of the report
and the proposals illustrated which could potentially be adopted in
managing the Council’s budget position.
(ii) Approve the mid-range scenario on the Council’s forecast consolidated
loans fund rate as the basis for decision making on the Capital Budget
at the Council meeting on 1 March 2023 – see paragraph 5.11.
3. BACKGROUND 
3.1 On 22 June 2022, the Council approved the Financial Strategy which set out a
number of principles to assist Medium Term Financial Planning and
development of Revenue and Capital Budgets (Report No. 22/141 refers). 
3.2 On 28 September 2022 the Council approved the updated Medium Term
Financial Plan (Report No. 22/249 refers).  Within this update the Council
approved the setting of a final revenue budget for 2023/24 and provisional
revenue budgets for 2024/25 and 2025/26 on 23 February 2023 (now 1 March
2023).

Page 2

United Kingdom Autumn Statement
3.3 On 17 November 2022 the Chancellor of the Exchequer delivered the Autumn
Statement.  According to the Fraser of Allander Institute the policy measures
for 2023/24 are largely neutral, with some additional spending compared to
previous plans offset by tax rises. In subsequent years, tax rises and spending
cuts are planned in order to meet, over the longer term, the Chancellor’s fiscal
rule that debt should be falling as a percentage of GDP within a five-year
window. 
3.4 The Autumn Statement did announce some additional departmental spending
relative to previous plans, mainly on the NHS and education in England.  This
additional spending generates consequentials for the Scottish Government of
around £800 million in 2023/24 and £600 million in 2024/25.  How this
additional funding is allocated will be a matter for the Scottish Government. 
Scottish Budget 
3.5 It is anticipated that the Scottish Budget will be published on 15 December
2022.  A verbal update will be provided at the Council meeting. 
4. REVENUE BUDGET 2023/24 TO 2025/26 
Council Wide Expenditure Pressures 
4.1 The Council is faced with several Council Wide expenditure pressures that it
must address in preparing revenue budgets for 2023/24, 2024/25 and
2025/26 as follows – 
• A structural deficit of £10.015m which is a consequence of using
Reserves over several financial years to balance budgets. 
• In relation to staff cost expenditure there is the unfunded element of
the 2022/23 pay award of £1.4 million which must be funded on an
ongoing basis.  Furthermore, the Medium-Term Financial Plan
assumes a 3% pay award in 2023/24, 2024/25 and 2025/26 which
equates to approximately £7.25 million each year. 
• As an employer, there is a positive impact of the recent reversal of the
increase in national insurance charges of approximately £1.5 million
from 2023/24. 
4.2 The Council Wide expenditure pressures totalling £31.665 million are
summarised in the following table.

Page 3

23/24
£m
24/25
£m
25/26
£m
Total
£m
Structural Deficit 10.015  - - 10.015
2022/23 Pay Award  1.400 - - 1.400
Future Pay Awards 7.250 7.250 7.250 21.750 
E’ers National Insurance  (1.500) - - (1.500)
Total  17.165 7.250 7.250 31.665 
Service Delivery Expenditure Pressures and Budget Reductions 
4.3 The Executive Leadership Team has prepared revenue budget submissions
that are aligned to the Council’s new draft Strategic Objectives.  Information
on the contents of these submissions were shared in a high-level presentation
to members of all budget review groups (BRGs) on 7 November 2022. 
4.4 These submissions were shared in detail with individual BRGs on 30
November 2022.  Since then, officers have met with individual BRGs to
provide more details on individual proposals and assumptions.  These
proposals will evolve in the coming weeks / months as more information on
key variables becomes more available, e.g. Scottish Government funding,
inflation rates, energy increases. 
4.5 The contents of the submissions are summarised in the following table with
more analysis set out in Appendix A – 
23/24
£m
24/25
£m
25/26
£m
Total
£m
Total Expenditure Pressures  14.111 7.238 3.608 24.957
Total Budget Reductions  (10.374) (8.364) (9.686) (28.424)
Net Movement
• positive = increase in deficit
• minus = reduction in deficit
3.737 (1.126) (6.078) (3.467) 
Summary of Financial Challenge (as at 15 December 2022) 
4.6 When the Council wide pressures set out in paragraph 4.2 are amalgamated
with the net Service Delivery position set out in paragraph 4.5, over the next
three financial years the Council faces a gap of £28.198 million.  This
assumes that the Council accepts all the budget reduction proposals on 1
March 2023.

Page 4

4.7 This position is summarised in the following table and graph. 
23/24
£m
24/25
£m
25/26
£m
Total
£m
Council Wide Pressures  17.165 7.250 7.250 31.665
Service Delivery Pressures  14.111 7.238 3.608 24.957
Gross Pressures  31.276 14.488 10.858 56.622
Total Budget Reductions  (10.374) (8.364) (9.686) (28.424)
Updated Gap  20.902 6.124 1.172 28.198 
Management / Operational Decisions 
4.8 Within the Service Delivery Expenditure Pressures and Budget Reductions
summarised in the section above, there are several proposals that are
operational in nature.  These reductions, totalling £4.742 million, are actions
that can be put in place by Service Management Teams and have no impact
on the delivery of approved Council policy.  Examples of the individual
proposals are set out in Appendix B and the reductions would take effect as
follows.
2023/24
£m
2024/25
£m
2025/26
£m
2.158  2.022 0.562

Page 5

Options for Managing the Gap 
4.9 The table at paragraph 4.7 identifies a total funding gap of £28.198 million in
2023/24, 2024/25 and 2025/26.  This section provides several indicative
proposals for managing this position.  Formal approval for these indicative
options will be brought to Council on 1 March 2023 when elected members
will be asked to approve the final revenue budget for 2023/24 and provisional
revenue budgets for 2024/25 & 2025/26.
Service Concession Agreements 
4.10 Service Concessions agreements are contracts which provide the Council
with a right to use an asset over a defined contract period. Typical
agreements are Public Finance Initiative (PFI) / Public Private Partnerships
(PPP) arrangements.  For Perth & Kinross Council, the Investment in
Learning (IIL) School Community Campus project, and the Design Build
Finance Maintain (DBFM) Bertha Park Secondary School, are treated as
service concession agreements. 
4.11 Local authorities in Scotland have previously been required to account for
these agreements on a different basis than that applied to other assets in that
the Council currently accounts for these agreements over the contract term
rather than the useful life of the assets concerned. The Scottish Government,
in consultation with COSLA, CIPFA and representatives from the Directors of
Finance section have agreed a review of the accounting treatment for service
concession agreements with revised statutory guidance issued on 6
September 2022 in the form of Local Government Finance Circular 10/2022 -
finance leases and service concession arrangements. 
4.12 Recommendations on the proposed future accounting arrangements for
service concession agreements in line with Finance Circular 10/2022 will be
submitted to Council for approval as part of the consideration of the Revenue
& Capital Budget on 1 March 2023. The opportunity will be taken to discuss
any proposed changes with the Council’s recently appointed external auditors,
Audit Scotland, early in the new year. 
4.13 Without prejudice to any future decision of the Council, given the value of
service concession agreements the potential financial consequences of any
change in accounting treatment are significant. It is currently estimated that a
change in accounting treatment would generate non-recurring resources in
the order of £30 million. This must be considered against the implications of
potentially extending the period over which the Council may choose to
account for these assets.

Page 6

4.14 The potential use of the service concession flexibility has previously been
discussed with members of the political Budget Review Groups. It’s inclusion
and possible use, as set out in the paragraphs below, is shown for illustration
only at this time as one of a range of options available to the Council in
managing the budget position and would be contingent on the Council
approving a change in the accounting treatment of service concession
agreements. 
4.15 One of the main reasons the Council is facing this unprecedented level of
financial challenge is the level of inflation that it may be exposed to in the
short term.  Some of the inflation may be transient rather than fixed so instead
of making permanent reductions to levels of service, an earmarked Reserve
of £10 million could be created to manage this.  This would allow expenditure
pressures to that value to be removed.  The actual impact of inflation in
2023/24 would be monitored with any requests to draw down from the
earmarked Reserve being considered by the Finance & Resources
Committee.  There is a risk that inflation does not subside, and additional
budget reductions are required in future years. For the purpose of illustration,
this is shown as potentially being funded from the service concession
flexibility. 
4.16 Again, for the purpose of illustration, the £20 million estimated balance of the
service concession flexibility could be applied equally across the remaining
financial years of this Council term i.e. 2023/24, 2024/25, 2025/26, 2026/27
and 2027/28 at £4 million per annum. In this scenario, the new Council
administration would be required to identify recurring budget reductions of £4
million from 2028/29 because this non-recurring funding source will have
ceased. 
Council Tax – Number of Band D Properties 
4.17 The Council has previously approved that the first £450,000 of growth in the
Council Tax base is applied to the Loan Charges Budget to support the
Capital Budget. 
4.18 The mid-range assumption within the Medium-Term Financial Plan assumes
growth of 600 band d equivalent properties each year.  On that basis, there is
approximately £350,000 of additional Council Tax income each year, that
amount can be applied towards the gap. 
Council Tax Increase 
4.19 Each 1% change in Council Tax level results in a movement in income of
approximately £1 million.  The Council’s Medium Team Financial Plan

Page 7

included an increase of 3% in 2023/24, 2024/25 and 2025/26 which generated
approximately £3 million of additional Council Tax income each year.  This
same assumption has been used in the modelling set out below. 
4.20 If the Council were to agree an increase of more than 3% then this could
provide elected members with scope to reject budget reductions or invest in
the Council’s strategic priorities.  Conversely an increase of less than 3%
would mean potentially, more budget reductions to be identified. 
Updated Position (Indicative) 
4.21 Based on the proposals illustrated above, the updated gap for the Council
over 2023/24, 2024/25 and 2025/26 would potentially be a net £4.148 million. 
23/24 24/25 25/26 Comment
Updated Gap Per above  20.902 6.124 1.172 
Proposals illustrated within this report
Inflation Pot
(see 5.11)
(10.000) - - Assumes
inflation
transient
Non-recurring contribution
(see 5.12) 
(4.000) - - Unwinds in
28/29
Council Tax – Band Ds  (0.350) (0.350) (0.350) 
Council Tax Increase
(indicative) 
(3.000) (3.000) (3.000) In line with
MTFP
Updated Gap  3.552 2.774 (2.178) 
4.22 For the avoidance of doubt, the updated gap set out in the table above does
assume that the Council accepts all of the £28.424 million of budget
reductions set out in paragraph 4.5. 
4.23 In addition, there are also several variables that could have a material impact
on the Council’s financial planning as follows. 
4.24 Firstly, as agreed in the Medium-Term Financial Plan, all modelling is based
on a flat cash financial settlement from the Scottish Government. 
4.25 Secondly, the latest draft non-domestic rates valuation roll has recently been
published.  The provisional valuations indicate a significant increase in the
rateable values of educational establishments, both locally and nationally.

Page 8

4.26 And thirdly, inflation may continue to add further cost pressures.  Most notably
the investment in learning programme charges for 2023/24 will not be known
until February and March which presents a further risk. 
4.27 The Transformation & Change Strategy may also produce other efficiency
savings that may contribute to the overall gap.  However, these may be in
later years and may be used to replace other budget reductions.
5. CAPITAL BUDGET 2023/24 TO 2028/29 
5.1 In setting the 6 Year Composite Capital Budget 2022/23 – 2027/28 in
February 2022, the Council approved a long-term Capital funding strategy to
deliver the current programme.  This is based on an annual and recurring
increase to the Council’s Loan Charges budget – which funds the revenue
cost of Council borrowing – by an additional £450,000 each and every year,
together with the managed use of the Council’s Capital Fund (Report No
22/36 refers). 
5.2 The funding strategy approved in February created approximately £190
million of capacity within the Composite Capital Budget.  Council approved
£119.5 million of additional Capital expenditure in February, leaving
approximately £70.5 million of capacity to either increase the funding for
existing projects and programmes or finance new expenditure.  In September,
the Finance & Resources Committee approved the application of £33.2
million of this capacity to the delivery of existing projects on site to meet
forecast increases in cost. 
5.3 In common with all Scottish local authorities, other public sector bodies and
the Scottish Government, the Council continues to experience significant
inflationary pressures on the delivery of its Capital investment.  These
pressures have been driven by external factors, outwith the control of the
Council. 
5.4 Between October 2021 and the meeting of the Finance & Resources
Committee in September 2022, the Council has added £188 million of
expenditure proposals to the Capital budget, of which £77.4 million (to date)
reflects inflationary uplifts on existing projects. 
5.5 Detailed work is currently being undertaken to review the projects within the
Capital Programme which are not yet contractually committed or on site to
test continued alignment with the Council’s strategic priorities in light of the
new Corporate Plan, value for money and overall affordability.  Based on
experience to date and the best information available at this time of
unprecedented financial challenge, the forecast impact of cost inflation on

Page 9

major projects under development is expected to exceed the remaining
capacity within the Capital Budget which elected members will need to factor
into their budget deliberations and decision-making. 
5.6 The level of capital investment which can be met from the current funding
strategy is also determined by the cost of borrowing.  Over 75% of the
Council’s capital expenditure is financed through borrowing from the Public
Works Loans Board (PWLB). 
5.7 As noted within the Treasury Activity and Compliance Report 2022/23 Quarter
2 (Report No. 22/295 refers), following the then Chancellor’s fiscal statement
to the UK Parliament on 23 September, the cost of UK government borrowing
– which determines PWLB rates – increased markedly.  PWLB borrowing
rates have fallen from their recent high levels over the last few weeks and are
anticipated to reduce further in the longer term.  In terms of risk however,
borrowing rates are unlikely to return in the short to medium term to the low
rates previously experienced and are expected to be more volatile than
previously assumed over the next few years which is, unfortunately the period
during which the Council is anticipating significantly increasing its borrowing to
meet the cost of the approved capital programme. 
5.8 Three scenarios have been modelled (optimistic, mid-range pessimistic) to
demonstrate how small changes in consolidated loans fund interest rates
have a material impact on the sustainability of the Capital Fund in supporting
the Capital Budget.  The consolidated loans fund rate is the average rate
incurred on all of the Council’s long-term debt including historic debt borrowed
at higher than prevailing Public Works Loans Board Rates (PWLB).  The mid-
range scenario is based upon economic and market forecasts, including
current forecasts on future PWLB borrowing rates, which significantly
influence the Council’s consolidated loans fund rate.  The following graph sets
out the three scenarios from 2022/23 through to 2059/60.

Page 10

5.9 The following table sets out, under each scenario, when the Capital Fund is
anticipated to be fully utilised and the size of the gap in the loans charges
budget that emerges assuming the Council were to take no mitigating action.   
5.10 In line with the approved Capital budget, the modelling from 2027/28 onwards
is based on the Council borrowing to support £12 million of new Capital
expenditure each year. This assumption has not been revised for a number of
years and the level of investment supported is clearly being impacted by
construction inflation.  The size of the gap that the Council faces in future
years will reflect both the level of Capital expenditure incurred and the
mitigating action adopted by the Council, most notably a planned approach to
incrementally increasing the loan charges budget over time. 
Deficit Emerges Range of Gap
Optimistic 2039/40 £3.4m rising to £19.9m
Mid-Range 2030/31 £0.5m rising to £20.9m
Pessimistic 2030/31 £1.0m rising to £21.9m

Page 11

5.11 Action: The Council is asked to approve the mid-range scenario on the
Council’s forecast consolidated loans fund rate as the basis for decision
making on the Capital Budget at the Council meeting on 1 March 2023.
6. WORKFORCE MANAGEMENT 
6.1 The shape and size of the Council will have to change to meet the current
financial challenges.  This includes a reduction in the Council’s workforce.
While no decisions have been taken yet, the number will be significant, and
the impact will be felt across the whole Council. 
6.2 The management of any workforce changes will continue to be mitigated by
applying a positive and proactive approach, including:

Page 12

• Transformation & Change Strategy agreed in June 2022 (5-year
programme, currently undertaking 9 consolidation workstreams, other
projects in Services progressing) 
• Vacancy and post management measures introduced in September
2022 to limit increasing headcount and payroll costs and protect
employment of existing workforce 
• Increased management oversight and scrutiny of use of overtime and
agency 
• Continue to focus on building skills and capacity, optimising existing
workforce opportunities as far as reasonably practical 
• Expectation that a flexible and agile approach is adopted 
• The Council will support people affected through workforce change 
• Job families and job family moves 
• Flexible working opportunities 
• Choices for career change, moving or retirement 
• Managing Workforce Changes Framework 
6.3 The Medium-Term Financial Plan agreed in September sets out principles for
how the Council will address this challenge, including removing its reliance on
non-recurring funding so that it can properly plan for the future. 
6.4 The Transformation & Change Strategy sets out a five-year plan for re-
shaping the Council and the way it works with communities, partners and
across the area. 
6.5 The first programmes introduced are for the consolidation of some areas of
work to improve the effectiveness and efficiency of how the Council works. A
review of the Council’s leadership structure is included as a specific
workstream within the programme. 
6.6 This work is ongoing and the Council is committed to working with Trade
Unions and employees to ensure that it optimises their employment as far as
reasonably practical.
7. NEXT STEPS 
7.1 As set out above, at the time of writing this report it was anticipated that the
Scottish Budget would be announced on 15 December 2022 with the Local

Page 13

Government Finance Circular being issued on the same day.  If this is the
case, a verbal update will be provided at the Council meeting with a wider
elected member briefing scheduled for the new year. 
7.2 Budget Review Groups have started their review of budget submissions and
this work will increase between now and the meeting of the Council on 1
March 2023.  Budget Review Groups will also be kept up to date with the
latest developments and how this may impact the Councils.
8. CONCLUSION 
8.1 In common with all Scottish local authorities and the wider public sector, Perth
& Kinross Council’s budget is under unprecedented pressure reflecting the
combined impact of historically high levels of inflation, continued financial
constraint and the growing need for its services. 
8.2 The potential use of the service concession scheme flexibility will require to be
considered by Council and may provide non-recurring capacity to manage the
financial challenge in the short term but does not detract from the level of
change required to put the Council on a financially sustainable footing. 
8.3 The approved Transformation & Change Strategy will contribute towards
supporting the Council’s financial position, but this will take time. 
8.4 Challenging and difficult decisions will be required in relation to budget
reductions and Council Tax strategy 
APPROVED 
Name  Designation Date
Stewart Mackenzie  Head of Finance 13 December 2022
Karen Donaldson  Chief Operating Officer 13 December 2022

Page 14

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2022 – 2027 lays out seven outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
(i) Tackling poverty
(ii) Tackling climate change and supporting sustainable places
(iii) Growing a sustainable and inclusive local economy
(iv) Enabling our children and young people to achieve their full potential
(v) Protecting and caring for our most vulnerable people
(vi) Supporting and promoting physical and mental wellbeing
(vii) Placing communities at the heart of how we work 
1.2 This report relates to all these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report.

Page 15

Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report. 
Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3 Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council must discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.

Page 16

4. Consultation 
Internal 
4.1 The Executive Leadership Team have been consulted in the preparation of
this report. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
• Appendix A – Summary of Service Expenditure Pressures and Budget
Reduction proposals 
• Appendix B – Examples of Management / Operational Actions