Bell’s Sports Centre
Future Options Report
January 2024

Page 2

1 | P a g e
P As part of our green office policy all Integratis reports are printed double sided
on 100% sustainable paper. 
Direct enquiries regarding this report should be
submitted to:
Neil Ross, Director, Integratis Consulting
Email: Neil@integratisconsulting.com

Page 3

2 | P a g e
Contents      
Executive Summary
1. Introduction 5
2. Current Situation 6
3. Options 21
4. Options Appraisal 43
5. Recommendations 46
6. Appendices 48

Page 4

3 | P a g e
Executive Summary
This report provides a detailed analysis and strategic appraisal for the future of Bell's
Sports Centre, considering its current operational challenges, financial performance,
and the strategic objectives of Perth and Kinross Council. Following significant flood
damage (which is uninsured) and within the scope of the Council's Transformation
Review, this appraisal critically examines the centre's viability and explores potential
pathways forward.
Current Situation and Financial Overview:
Bell's Sports Centre has experienced fluctuating financial performance from 2019 to
2023, with a notable decline in income during the 2020-21 fiscal year due to the
pandemic, followed by a recovery in subsequent years. The year 2022-23 saw
income rise to £793,934, driven by investments in new fitness facilities. However, the
Centre also faces challenges, including high staff costs and operational deficits, with
the current financial year forecasting a net deficit of £674,875. This is worsened due
to the current venue closure.
Options Appraisal:
Six strategic options are evaluated, ranging from full closure and relocation of fitness
services to Dewars Centre (Option 1), to various levels of reinstatement and service
reconfiguration (Options 2-6). Each option has been assessed for its financial
implications, potential impact on community service provision, and alignment with
the Council's strategic objectives.
Option 1 emerges as the most financially viable, promising significant improvements
in net expenditure and a three-year return on investment however it comes at a
significant cost to community use. This option entails the complete cessation of Bell's
operations and the transfer of fitness services to Dewars Centre. 
An alternative worth considering is Option 4, which involves a partial reinstatement
of Bell's, encompassing 8 – 10 badminton courts and 1 – 2 squash courts, alongside
relocating the fitness facilities to Dewars. This approach results in a balanced
improvement in net expenditure and a return on investment within thirteen years.
Crucially, it enables community groups to resume their activities at Bell's, supporting
local events and maintaining usage.

Page 5

4 | P a g e
Options 2 through 6 explore a spectrum of reinstatement possibilities, each with
unique financial, operational, and community service implications. These range from
full reinstatement to partial operations focusing on fitness services, with varying
degrees of capital investment and projected returns on investment.
Recommendations:
Based on the comprehensive analysis, Option 1 is recommended as the primary
strategy. This approach offers substantial financial benefits, aligns with the Council's
sustainability goals, and ensures the continuity of fitness services within the
community. However, Option 1 has the largest negative impact on usage of the six
options, coming at a significant cost to community use. Programming and planning
at a strategic level across Perth and Kinross would be required to identify
appropriate alternative venues for the diverse array of existing Bell’s arena users.
This includes those involved in both competitive and social sports, individuals with
disabilities and a range of community groups spanning from youth to older adults. It
necessitates strategic planning to address the displacement of other services and
programmes, review of facility booking processes, opening discussions on access to
school facilities during the day and a need for clubs to be prioritised. This would
include protecting access to current facilities at Bell’s for Perthshire Rugby Club.
The secondary recommendation is Option 4. Fitness would be relocated to Dewars
and the partial reinstatement of Bell’s arena and squash allows community groups to
recommence activities. It serves as a viable alternative, offering a blend of financial
prudence and community use continuity with a thirteen year ROI but may be
impacted by PH²0 project timescales.
Conclusion:
The future of Bell's Sports Centre is at a critical juncture. The recommended strategy
of full closure and relocation of services presents a financially and strategically
prudent path forward. It requires careful implementation, strategic collaboration,
community consultation, and alignment with broader council objectives to ensure the
continued provision of valuable leisure and fitness services to the Perth and Kinross
community.

Page 6

5 | P a g e
1. Introduction
The strategic future of Bell's Sports Centre is critically assessed within this report,
against a backdrop of the Perth and Kinross Council's Transformation Review and
the catastrophic impact of a recent flood event. This flood not only inflicted
considerable damage on the facility but also acted as a pivotal moment, prompting a
re-evaluation of leisure services provision within the wider strategic context of Perth's
leisure asset optimisation and sustainability challenges.
1.1 Project Description
This appraisal critically examines the strategic options for Bell's Sports Centre, now
at a crossroads following the flood damage. The flood event has underscored the
vulnerability of ageing infrastructure to environmental risks, intertwining with the
broader challenges identified in the Transformation Review. These include financial
sustainability, the imperative for energy efficiency, and the potential reclassification
of the Centre alongside Perth Leisure Pool as Category B listed buildings,
introducing complex layers of regulatory and conservation considerations into future
planning.
It explores a spectrum of options, from the full reinstatement of the Centre to its
potential closure, framed within the necessity for a consolidated, modernised leisure
offering that aligns with community needs, financial viability, and environmental
sustainability.

Page 7

6 | P a g e
2. Current Situation
2.1 Summary of Current Position
Bell’s Sports Centre closed on the 8th of October 2023 due to devastating flood
damage. In planning the next steps LAL had also to consider the potential impact of
PH20 and whether Bell’s will ultimately be closed and the facilities moved to a new
development on the existing Dewars site. These challenges add to the financial
position and the inability to insure the building. Bell’s is currently partially open for
fitness classes in two studios while additional classes are delivered at Dewars. The
gym, arena and squash courts remain closed.
2.2 Financial Summary
Historical
• 2019-20: Bell's reported an income of £511,003 with staff costs at £745,793, the
highest for the period. Total net expenditure was £602,182 as can be seen in Table
2.1 below.
• 2020-21: Income decreased to £113,643, likely due to external factors including the
pandemic. Staff costs were reduced to £567,567 and total net expenditure increased
to £709,302.
• 2021-22: Income increased to £371,396, with staff costs at £601,961 and total net
expenditure at £550,527.
• 2022-23: Income further rose to £793,934, indicating growth from the investment in
new fitness facilities and recovery from the pandemic. Staff costs increased
significantly to £858,967 with total net expenditure at £570,856.
Table 2.1 highlights that over these years, Bell's showed a trend of increasing
income and fluctuating costs, with a notable decrease in income in 2020-21 due to
the pandemic and a substantial rise in income and staff costs in 2022-23 from
investment in fitness facilities and services.

Page 8

7 | P a g e
Table 2.1: Financial Performance 2019 - 2023
Financial Year 2019-20 2020-21 2021-22 2022-23
Income  -£511,003 -£113,643 -£371,396 -£793,934
Cost of Sales £280 £0 -£497 -£308
Staff Costs £745,793 £567,567 £601,961 £858,967
Property Costs £171,981 £113,494 £151,717 £229,365
Supplies and Services £195,131 £141,884 £168,742 £276,766
Net Expenditure £602,182 £709,302 £550,527 £570,856 
August 2022 – July 2023 Baseline
As requested, the baseline was created for a twelve month period prior to the
closure of Bell’s. Table 2.2 below shows that for the financial year August 2022 to
July 2023, Bell's reported increased income of £1,045,333. However, a substantial
portion of the centre's expenses was tied up in staff costs, which totalled £888,922.
Property costs, were also significant, amounting to £238,801. Additionally, supplies
and services were £307,869. Consequently, the total expenditure for Bell's during
this period was £1,436,289. The net expenditure for Bell’s was £390,956. This
financial overview, serving as the baseline for the report, underscores that while
Bell's generated considerable income, the high expenditure, especially in staff and
property costs, led to a significant operating deficit albeit less than previous years.
Table 2.2: Financial Performance August 2022 - July 2023
Account Centre
Bell’s Sports
Centre
Income Total -£1,045,333
Cost of Sales £697
Staff Costs £888,922
Property Costs £238,801
Supplies & Services £307,869
Expenditure Total £1,436,289
Net Expenditure £390,956 
Bell’s Forecast to Year End 2023
Given the closure of Bell's on October 8th, 2023, the financial forecast for the
remainder of the year reflects the impact of this closure shown below in Table 2.3.

Page 9

8 | P a g e
Originally budgeted to generate £1,001,091, the revised forecast for operating
income has been adjusted down to £718,237 a reduction of £282,854. 
On the expenditure front, the forecast shows a decrease in staff costs to £836,396
from the budgeted £897,782, a saving of £61,386,  attributed to staff reductions and
redeployments following the closure. Supplies and services expenses are also
projected to drop to £327,359, down from the budgeted £369,207, saving £41,848.
Property costs and utilities are forecasted to be lower than budgeted, at £39,038 and
£190,319 respectively, due to the decreased operational needs following the closure.
Overall, the total expenditure is forecasted at £1,393,112, which is £127,666 less
than the budgeted figure of £1,520,778. Despite these reductions in costs, the
forecast still predicts a deficit of £674,875 for the period following the closure until
the year's end. This deficit is larger than the budgeted deficit of £519,687 by
£155,188, reflecting the significant financial impact of the centre's closure.
Table 2.3: Bell's Financial Forecast for 2023
Account Group
Full Year
Forecast Budget Movement
Operating Income -£718,237 -£1,001,091 £282,854
Staff Costs £836,396 £897,782 -£61,386
Supplies & Services £327,359 £369,207 -£41,848
Property Costs £39,038 £43,789 -£4,751
Utilities £190,319 £210,000 -£19,681
Expenditure £1,393,112 £1,520,778 -£127,666
Surplus/ - Deficit -£674,875 -£519,687 -£155,188 
2.3 Membership Performance Aug. 2022 - July 2023
Over the twelve month period from August 2022 to July 2023, LAL experienced
fluctuations in Health and Fitness membership sales, cancellations and the resulting
net gain. The analysis, including the launch of the new gym at Bell's on 9th July 2022,
provides valuable insights into the impact of this strategic move. Bell's boasts the
highest membership share among LAL facilities, contributing to 61% of gym
memberships, 49% for fitness classes and 81% of personal training.
Table 2.4: LAL Membership position Aug. 2022 – July 2023

Page 10

9 | P a g e
Month Sales Cancellations Net Gain
Aug-22 346 154 192
Sep-22 333 190 143
Oct-22 292 138 154
Nov-22 241 164 77
Dec-22 157 157 0
Jan-23 508 141 367
Feb-23 329 165 164
Mar-23 305 224 81
Apr-23 209 285 -76
May-23 212 272 -60
Jun-23 187 230 -43
Jul-23 237 193 44
Totals 3356 2313 1043 
Sales Overview: Sales data seen in Table 2.4 reveals varying monthly figures, with
a strong start in August 2022 post Bell's gym opening, generating 346 new members
an impressive increase of 253 from August 2021. Robust sales continued through
September and October, peaking in January 2023 with 508 new memberships. The
twelve month period resulted in a total of 3356 new membership sales, showing a
significant positive shift from the previous average of 147 new memberships per
month.
Comparatively, the period before Bell's gym opening averaged 147 new
memberships monthly, emphasising the substantial impact of the new facility on
LAL's membership and business. October and November 2021, with peak sales at
179 and 176, respectively, are surpassed by the monthly average of 280 post Bell's
gym launch.
Cancellations: The initial seven months of the analysed period exhibited a positive
trend in cancellations, indicating a favourable response to the new gym. Lower
cancellation figures during this period affirm the positive impact of the facility on
member retention. From March 2023 onwards, cancellations increased, with notable
peaks in April and May 2023. Further exploration of contributing factors during these
months would provide valuable insights.

Page 11

10 | P a g e
Net Gain Analysis: The overall net gain for the period stands at 1043, highlighting
LAL's ability to attract and retain members. Positive net gains in most months
demonstrate successful membership growth within the Health and Fitness segment.
Key Insights:
• Successful Launch Impact: The positive net gain following the new gym's
launch indicated a successful integration of Bell's into LAL's membership
strategy.
• Seasonal Variations: Cancellation peaks in April and May could align with
seasonal trends or external factors affecting member commitment.
Analysing member feedback and engagement during this period could offer
valuable insights.
• Retention Focus: While overall net gains are positive, a deeper analysis of
cancellations in specific months can inform targeted retention strategies.
Understanding member needs during low net gain periods is crucial for
sustained growth.
Conclusion:
The impressive net gain of 1043 members over the twelve month period not only
underscores LAL’s successful sales strategies and member retention efforts but also
shows the positive impact of the gym at Bell's Sports Centre. The successful
integration of this facility into the membership strategy not only surpassed historical
performance but became a pivotal driver in achieving sustained growth and
heightened satisfaction within the Health and Fitness membership base. This
positive impact on membership count and net gain position confirms the importance
of fitness provision in future options. 
2.3.1 Membership Performance (Oct. 2023 – Jan. 2024)
The flooding at Bell's on the 8th October last year significantly impacted LAL
membership dynamics and operational capacity. The entire facility was forced to
close. On the 23rd October 2023 Bell’s partially reopened with fitness classes in two
of the three studios, with studio 1 downstairs remaining closed. Unfortunately, the
closure of key amenities like the arena, squash courts, and gym persisted, leading to
the cancellation of sporting coaching sessions and events that were either cancelled
or relocated to other LAL facilities and Perth schools.

Page 12

11 | P a g e
This disruption had a noticeable effect on LAL's overall membership performance, as
reflected in the following Table 2.5:
Table 2.5: LAL Membership position August 2023 – 22nd January 2024
Month Sales Cancellations Net Gain
Aug-23 271 237 34
Sep-23 226 213 13
Oct-23 138 273 -135
Nov-23 94 363 -269
Dec-23 60 275 -215
Jan-24 111 222 -111 
The significant decline in net gain, reaching -730 from October ’23 to 22nd January
‘24, reflects the challenges faced by LAL in member retention and acquisition
following the facility's closure. The reduced access to key amenities, especially the
gym at Bell's, contributed to a decline in sales and an increase in cancellations.
It's essential to highlight that the negative net gain is a direct consequence of the
facility's closure due to the flooding incident. The impact is not solely reflected in
sales and cancellations but also in the overall member and customer experience,
with activities and services no longer available and several that have not been
successfully relocated to other facilities.
2.4 Bell’s Usage (August 2022 – July 2023)
To form a picture of the facilities that could be reinstated, whether at Bell’s, Dewar’s
or elsewhere, it’s important to review the average usage (prior to closure) to
demonstrate patterns of demand. Bell’s had over 250,000 visits in 2022-2023
second only to Perth Leisure Pool with 362,000 visits. These two sites led
participation performance in the two previous years.
For Bell’s, Sport Go Play made up the majority of participation in 2019-2020 with
69,554 visits, this declined to 40,254 in 2022-2023. Whereas gym participation was
only 7235 in 2019-2020 increasing to 70,886 in 2022-2023. During that same time
participation in events, fun coached, steps coached and education have all declined.
Whereas fitness classes, personal training and non-sport venue hire have all
increased demonstrating the change in demands and business focus. Sport Go Play
at Bell’s has declined by 42% from 2019-2020 to 2022-2023. Across other LAL

Page 13

12 | P a g e
venues Sport Go Play has seen growth and decline at different sites with an overall
decline of 29%.  
Table 2.6 below shows the total average usage for Bell’s Sports Centre. The table
shows that peak usage is Monday to Wednesday from 4 – 9pm and Thursdays and
Fridays 4 – 8pm. During the day, the pattern follows usage before work or education,
dipping 8 – 10am then increasing at 10am with high usage, especially on Tuesdays
with 99.94 average users. Weekend usage displayed a distinct pattern with a notable
peak on Saturday mornings and relatively consistent but lower attendance on
Sundays.
Table 2.6: Bell’s Total Average Usage over 12 months 
The arena has historically been booked for over 40 events per year. The majority
with Scottish Gymnastics and also include Scottish Floorball, Scottish Table Tennis,
indoor hockey and badminton. The events generate income but also prevent
community groups, sports clubs, members and the local public from creating a
pattern of regular bookings, usage or community events. 
We will now consider each area within Bell’s in turn to build a picture of facility need
based on historical usage.
2.4.1 Fitness Gym
As detailed in membership performance section of the report the gym at Bell’s
opened 9th July 2023. The gym usage mirrors that as described for Bell’s overall as it
drives the highest use at the centre. Early mornings, 7am, show higher gym usage,
indicating a demand for early workout sessions before the workday begins. Then
from 10am the gym use is fairly steady until it builds from 4pm through to 9pm on
Monday to Wednesdays and 8pm for Thursdays and Fridays. Saturday and Sundays
show lower usage that is steady throughout the weekend, the highest weekend use
is Saturday 10am-12pm.

Page 14

13 | P a g e
2.4.2 Fitness Classes
Monday to Thursday evenings at 6pm have the highest class attendance, with 42.22
and 25.87 average users, indicating these are highly popular times for fitness
classes.
Mid-morning times on weekdays, particularly from 10am to 12pm, show consistent
moderate usage, with the number of average users ranging from 12.23 to 21.26. 
Saturday and Sunday classes are popular from 9-11am, attracting similar class
attendance as mid-week mornings.
2.4.3 The Arena 
The programme of bookings at Bell's arena is broad and varied. It enables
community interaction and accommodates a diverse range of sports, leisure
activities and community groups. 
Prior to the flooding, the arena had regular bookings from 26 sports clubs/groups,
casual court bookings and hosted national events. These bookings were varied, with
the majority of groups attending four times per month, while others scheduled as
many as 3 per week. The range of users spanned all demographics, including youth,
senior citizens, competitive and social sports, individuals with disabilities and various
community groups. The range of activities was equally diverse, featuring sports such
as table tennis, squash, netball, football, cricket, and rugby, alongside sessions for
disability groups like rebound therapy and the Perth Eagles Wheelchair Sports Club,
as well as non-sporting clubs like the Perth Quilters. 
In addition, Bell’s was the home to the gymnastics programme. There were 34
weekly classes, split into 17 Wee Springers classes, tailored for the younger
participants during the daytime and 17 after-school sessions.
The arena was in use throughout the week, with scheduled activities from 10am to
10pm. Notably, weekend bookings were deliberately kept open to accommodate
events.
Table 2.7 below illustrates a distinct pattern in usage, with morning and evening
slots being the most active, pointing to a drop in participation before 9am and in the
afternoons. Arenas 1 and 2 exhibit robust evening engagement, with usage rates

Page 15

14 | P a g e
between 59.38% and 61.01% across all courts, and similarly substantial morning
activity with usage rates from 42.99% to 59.69%. Arena 3 peaks during after-school
hours, a time when Arenas 1 and 2 are quieter. Arena 3 has the lowest overall usage
as permanently set for gymnastics. Fridays from afternoons onwards throughout the
weekend shows limited usage for arena 3 where sessions are not booked to allow
for set up of weekend events. This pattern suggests that the breadth of activities
traditionally offered in the arena could potentially be consolidated onto 8 - 10 courts,
optimising space usage without compromising service delivery.
Table 2.7: Bell’s Arena and Squash Usage 
In conclusion, the comprehensive utilisation of Bell's arena underscores its integral
role in fostering a thriving and inclusive community. The extensive range of clubs
and groups that called Bell's home demonstrates the centre's unique ability to
accommodate a diverse array of activities, catering to a broad spectrum of interests

Page 16

15 | P a g e
and needs. The usage patterns reveal that while certain arenas exhibit high
engagement during morning and evening sessions, there is potential to reduce the
number of courts and still meet usage demands.
2.4.4 Squash
Squash usage across the week shows a pattern of predominately under utilised
courts as can be seen below in Table 2.8. 
Table 2.8: Average Squash Usage across Monday - Sunday
Squash
Before
9am Morning Afternoon
After
School  Evening
Court 1 2.42% 18.99% 16.70% 36.67% 40.91%
Court 2 2.35% 8.33% 5.98% 31.13% 33.69%
Court 3 1.88% 5.13% 4.40% 5.18% 7.55%
Court 1 has an average usage of 25% across the week, Court 2 is 18% and Court 3
is 5% as can be seen below in Table 2.9. Court 1 peaks on Monday evenings with
55%, followed by 51% after school on Fridays. Similarly, Court 2 peaks on Fridays
after school with 71% and 47% on Monday evenings however these peaks are the
exceptions. Court 3 doesn’t reach an average of 10% on any day across an average
week. Wednesday is the busiest for Court 3 at 8%. 
Table 2.9: Squash Court Usage split by day and booking time group
Description
Booking
Time Mon. Tues. Wed. Thurs. Fri. Sat. Sun. Total
Court 1 After School 38% 41% 44% 34% 51% 10% 13% 33% 
Afternoon 11% 20% 19% 13% 18% 18% 19% 17% 
Before 09:00 0%     11% 21% 11% 
Evening 55% 39% 38% 37% 35%   41% 
Morning 22% 12% 20% 10% 11% 29% 29% 19%
Court 1 Total  25% 28% 30% 24% 29% 17% 20% 25%
Court 2 After School 26% 29% 34% 22% 71% 3% 5% 27% 
Afternoon 4% 5% 5% 4% 5% 9% 9% 6% 
Before 09:00      11% 21% 16% 
Evening 47% 31% 30% 29% 30%   34% 
Morning 4% 5% 13% 3% 7% 17% 9% 8%
Court 2 Total  20% 18% 21% 15% 29% 10% 11% 18%
Court 3 After School 4% 1% 13% 2% 9% 4% 2% 5% 
Afternoon 2% 7% 2% 5% 3% 6% 6% 4% 
Before 09:00  4% 6%     5% 
Evening 5% 5% 13% 7% 7%   8%

Page 17

16 | P a g e
Morning 13% 3% 6% 2% 2% 1% 10% 5%
Court 3 Total  6% 4% 8% 4% 5% 4% 6% 5%
Looking at need, one squash court would be sufficient based on historical usage
patterns. Similarly, only one court is required to participate in Squash leagues.
Finally, these squash usage figures have also been enhanced through some usage
including table tennis which could continue on squash courts or be relocated to the
arena.
2.5 Bell’s Usage Since Partial Closure on 7th October
Prior to the flooding, the arena had 26 distinct clubs and groups scheduled,
projecting a monthly attendance of 1,921 individuals, not accounting for casual court
bookings, events, and educational utilisation of the facilities.
The daytime bookings, predominantly utilised by seven groups, have unfortunately
not found alternative locations, which is partly attributed to restricted daytime access
to school facilities. Of the 19 groups that utilised the evening slots, 8 have
transitioned to new venues, these have been met with challenges which are seen as
temporary short term compromises while Bell’s remains closed. The Fair City
Rollers, Roller Derby club, face unique challenges in finding a suitable venue due to
their specific flooring requirements. Similarly, the Rebound Therapy group that use
trampolines while working with users with additional needs, has been impacted by
the lack of an appropriate space for their large equipment, which is particularly
problematic because they traditionally met during the day.
The gymnastics programme, with its 34 weekly classes, has been significantly
disrupted. The Wee Springers classes are still seeking a new home. While the after-
school and evening classes have been accommodated by a school court, the
relocation is not without its challenges. Bell’s was a preferred venue for over 20
annual Scottish Gymnastics events, a choice made due to its capacity, storage for
specialist equipment, and experienced staff. Scottish Table Tennis and Badminton
also valued Bell's for its facilities, numerous courts, and competition-standard
lighting, a testament to the centre's high-quality provisions.
The closure has significantly disrupted the routine of numerous groups, highlighting
the centre's contribution to community wellbeing.
As the gym at Bell’s remains closed the members may have chosen to join other
operators in the meantime. A reduced programme of fitness classes restarted on the

Page 18

17 | P a g e
23rd October from Bell’s, Dewars and North Inch. As can be seen in Table 2.10
below, the usage numbers for fitness classes drop from 4.2K to 3.3K in October
when Bell’s closes and then increase to 3.8K in November 2023. 
Table 2.10: Fitness Class Usage Bell's and Dewars Aug - Nov 2023 
Likewise, Table 2.11 below shows the number of classes drop from 517 in
September to 339 and 326 in October and November respectively. In November 41
classes were offered at Dewars and 5 at North Inch.        
Table 2.11: Number of Fitness Classes at Bell's and Dewars Aug - Nov 2023 
2.6 Customer Usage and Staff Optimisation
Optimising staffing is crucial for achieving operational efficiency and enhancing
customer and staff satisfaction at Bell’s. By aligning staffing levels with customer
needs and operational demands, service quality can be enhanced, efficiency
improvements made, and ultimately drive business success. 
On reviewing the Bell’s baseline staffing structures, against usage figures, there is
some correlation between the number of staff on duty and the number of users at the
centre. However, the data suggests that they are not consistently aligned and offer
opportunities for cost optimisation.

Page 19

18 | P a g e
Table 2.12 was previously shown in section 2.4 to highlight usage, it is repeated
here to compare with staffing levels and costs.
Table 2.12: Bell's Average Usage over 12 months 
Table 2.13 below shows the number of staff on duty, when compared to the usage
patterns opportunities can be seen. The highest staff levels can be seen highlighted
in red showing Tuesday 4pm and Monday 9am have the highest number of staff
across the week. There are areas where staffing mirrors usage and others, such as
Monday at 9am, where there is opportunity to better align staff to usage.
Table 2.13: Bell's Staff on Duty averaged over 12 months 
Layering the staffing onto the usage it’s key to consider the staff costs per hour as
seen in Table 2.14. The staff costs per hour range from £10.26 to £149.49. The
average weekly staff cost from the baseline expenditure model is £9,963. 
Table 2.14: Bell's Staff costs per hour 
Moving on to then consider the staff costs per customer in Table 2.15 below is
where it’s clearer to see the picture and opportunities. The lowest staff costs per

Page 20

19 | P a g e
customer are highlighted in yellow at 6-7pm Monday to Wednesday, through to the
highest costs in red. The cost per customer ranges from £0.59 for Wednesdays 6-
7pm up to £60.31 per customer on Monday at 6am. 
Table 2.15: Bell's Staff costs per customer 
New Staffing Model
The following models aims to adjust the staffing structure to better match the user
demand while maintaining the right staff in the right areas to deliver high levels of
service.  
Table 2.16 shows the staffing structure for where Bell’s is in full operation. The
principles behind the model are consistent across all options. As can be seen
staffing levels range from two when closing the centre in the evening to nine for peak
times 5 – 8pm Monday to Friday.
Table 2.16: Bell's revised number of staff on duty 
The reductions are reflected in the reduced staff costs per hour in Table 2.17. Costs
start with £10.26 and £11.44 for the closing period of the centre where there are two
staff members finishing on the half hour. The highest costs are £92.76 for 5 – 8pm
Monday to Friday.
Table 2.17: Bell's revised staff costs per hour

Page 21

20 | P a g e
This staffing model combined with the customer usage shows the weekly cost is
£7,228. Table 2..18 below reflects the new model and the impact on staff costs per
customer. Opening the centre continues to be the highest cost time, this has
reduced from £60.31 on Mondays to £39.80 Monday to Friday, still allowing key staff
to set up operations for the day. Throughout the day the staffing flexes alongside the
customer usage.
Table 2.18: Bell's revised staff costs per customer 
In conclusion, optimising staffing allows for operational efficiency and enhancing
customer and staff satisfaction. The model looks to align staffing with customer
needs and operational demands, to enable enhanced service quality, efficiency
improvements, and drive business success. The model reduces weekly staff costs
from £9,963 to £7,228. These new models show the staffing for the full reinstatement
of Bell’s. The principles for the models are consistent across all six options.

Page 22

21 | P a g e
3. Options 
There are 6 options under consideration for this project. Each option is appraised
against the baseline financial and usage performance of August 2022 to July 2023.
Option 1 - Full Closure of Bell’s and Relocation of Fitness to Dewars Centre:
This option explores the complete closure and stopping of all activities at Bell's
Sports Centre with the gym and group exercise classes being relocated to the
Dewars Centre. 
Option 2 - Reinstate Bell’s in Full: 
Under this proposal, Bell's Sports Centre would be fully restored to its pre-closure
operating status. All areas and facilities would be reinstated and be fully operational
as they were prior to the flood. 
Option 3 - Reinstate Bell’s in Part:
This option proposes the partial reinstatement of Bell's Sports Centre. The gym and
fitness classes would be fully reinstated at Bell’s. The Arena would be partly
reinstated with 8 – 10 courts. Squash would be retained with 1 - 2 courts.
Option 4 – Reinstate Bell’s in Part with Relocation of Fitness to Dewars Centre:
This option considers relocating the gym and fitness classes to the Dewars Centre.
The main arena at Bell’s would be partly reinstated with 8 – 10 courts. Squash would
be retained with 1 - 2 courts.
Option 5 – Wild Card: Reinstate Bell’s in Part with Relocation of Fitness to a
non-LAL facility:
This approach suggests locating fitness facilities at a non-LAL facility, presenting a
unique set of logistical and partnership considerations. The main arena at Bell's
would be partially reinstated, similar to other options, with 8 to 10 courts and Squash
would be retained with 1 - 2 courts.
Option 6 – Reinstate Fitness Only at Bell’s:
The final option focuses solely on the reinstatement of the gym and studios for
fitness classes at their existing locations within Bell's Sports Centre.

Page 23

22 | P a g e
3.1 Option 1 - Full Closure of Bell’s Sports Centre and
Relocation of Fitness to Dewars Centre 
Impact on Income
With the full closure of Bell’s, all income and costs are zeroed, fitness is moved to
Dewars along with the associated income and costs. As the arena and squash
courts would remain closed, Sport Go Play income of £216,941 is removed as clubs
and activities cannot be relocated to Dewars. The events income of £118,514 also
stops as events will not continue. The full income for gym provision, fitness classes,
personal training and wellbeing move to Dewars. Since the closure of Bells, the
membership has declined by 20%, therefore all six options show membership
income at 80% due to the reduced membership count, this reduces it to £441,202.
These substantial streams, along with smaller ones create an overall forecasted
drop in income of £473,253. The combined Income of Bells and Dewars would
reduce from £1,318,685 to £845,432 shown in Table 3.1. 
Table 3.1: Financial Baseline compared to Option 1 
Impact on Expenditure
Expenditure at Bell's drops to zero, Dewars incurs increased costs, albeit not to the
level previously experienced at Bell's. No mothballing costs are assumed for Bell’s.
There is a significant decrease in expenditure, with most notable reductions in staff
costs which are nearly halved from £1,197,777 to £637,770 in part due to the arena
closure. 
Aug 22 - July 23 Baseline Option 1
Account Centre Bell’s  Dewars Bell’s  Dewars
Income Total -£1,045,333 -£273,352 £0 -£845,432
Cost of Sales £697 £0 £0 £697
Staff Costs £888,922 £308,855 £0 £637,770
Property Costs £238,801 £229,869 £0 £251,493
Supplies &
Services £307,869 £78,424 £0 £368,403
Expenditure Total £1,436,289 £617,148 £0 £1,258,362
Net Expenditure £390,956 £343,796 £0 £412,930
Combined Net
Expenditure £734,752 £412,930
Baseline
Comparison   £321,822

Page 24

23 | P a g e
A proportion of property costs; electricity, repairs and maintenance and cleaning,
which allow for the gym and fitness classes to be delivered are transferred to
Dewars. 79.3% of supplies and services costs are moved to Dewars including the
full corporate services recharge of £245,377, fitness class delivery, equipment,
membership expenses, printing and subscriptions and licencing. 
Impact on Net Expenditure
Net Expenditure, when compared to the baseline (Table 3.1), shows a £321,822
saving. Option One presents the most significant saving across all options.
Impact on Staffing Structures
The Bell’s management structure is reduced, and a Deputy Manager is added at
Dewars to continue community hall management and to manage the team that will
service customers of the gym and fitness classes. As the arena and squash remain
closed the structure doesn’t include leisure staff. Fitness staff move to Dewars,
following the same labour optimisation principles that are detailed within Section 2.6,
which reduces staffing in-line with customer usage. The staffing structure flexes to
mirror fitness user patterns with a fitness team member opening the gym, an
additional team member joining prior to the morning increase in usage and then
further increases from 4pm to accommodate the evening peaks in demand.
Impact on Usage and Demand 
Option 1 has the largest negative impact on usage of the six options. Relocating
fitness to Dewars would entail the complete cessation of bowling as the gym would
be location in the current bowling hall location.
Members: Due to the decrease in membership since the closure and the
assumption that some of these members will now have formed new routines the
predicted demand shows a drop of 20%. However, the new gym and fitness classes
at the central location of Dewars could deliver stronger membership demand and
growth that predicted. There is potential to recover lost members and attract new
ones at Dewars.
Usage at Bell’s for August 2022 to July 2023 was 310,274 for all areas and activities
as can be seen in Table 3.2 below.

Page 25

24 | P a g e
Table 3.2: Usage comparison for Baseline and Option 1
Usage Aug 22 - July 23 Baseline Option 1
Cost Centre Bell`s  Dewars Bell`s  Dewars
Education 15,124  1,138  -  1,138 
Events 45,897  -  -  - 
Fitness Classes 47,534  -  -  42,781 
Fitness Gym 107,349  -  -  96,614 
Fitness Personal 1,812  -  -  1,631 
Fun Coached 18,237  502  -  9,621 
Miscellaneous 25  -  -  - 
Non Sport Venue Hire 13,728  16,473  -  7,773 
Sport Go Play 40,790  22,344  -  22,344 
Steps Coached 13,797  5  -  5 
Wellbeing 5,981  -  -  5,981 
Usage Total 310,274  45,462  -  187,887 
Combined Usage 355,736   201,587 
Usage Variance   -162,849 
Clubs: In addition to the complete cessation of bowling, the closure of Bell’s arena
would mean 162,849 annual uses from the 26 clubs, groups, casual bookings and
events would be looking for new locations to continue their activities. In the time that
Bell’s has been closed a small number of clubs have been temporarily rehomed to
other locations. The impact on these clubs and their customers would be significant.
Full closure of Bell’s has the largest negative impact on usage of the six options. The
meeting rooms at Dewars would be converted to studios for fitness classes,
therefore impacting use by clubs.
The usage for bowling at Dewars is, on average, 143 unique users each month
during the bowling season as can be seen in Table 3.3 below. Bowling would not
continue with Option 1.
Table 3.3: Bowling Unique Users September 2022 - April 2023

Page 26

25 | P a g e
Perthshire Rugby Football Club use of Bell’s as a clubhouse and the changing
facilities would require to be considered.
Events: Due to the closure of Bell’s in Option 1, events would move elsewhere and
no usage is forecasted for events at Bell’s. Annual events are held in the two halls at
Dewars that the relocation of fitness there would impact. In line with baseline dates
the income generated was £21,821, of the 10 events, 6 are not returning for
2024/25. If fitness were at Dewars the income from these events would be £5,222.
As noted, when considering Clubs, the meeting rooms would be converted to studios
therefore impacting bookings for events.
Capital Costs 
Capital costs for relocation of the gym and fitness classes to Dewars are forecasted
as £902,277. No mothballing costs are assumed for Bells.
Table 3.4: Capital Costs for Option 1  
Option 1
Bell’s  Dewars
All Areas    
Main Arena    
Main Gym   £302,277
Build Costs    £600,000    
£902,277
Total £902,277
The capital costs include converting the bowling hall at Dewars into a gym, the
conversion of the first floor meeting rooms into three fitness studios and the updating
and refurbishment of the male and female changing rooms. Creating a new home at
Dewars for the fitness members.

Page 27

26 | P a g e
3.2 Option 2 – Reinstate Bell’s in Full 
Impact on Income
The full reinstatement of Bell’s shows a forecasted 20% drop in income from
£1,045,333 to £899,478 as seen in Table 3.5 below. 
The events income has reduced by 30% from £118,514 to £82,960. The assumption
is that some events will have arranged new locations and would return at a rate of
70%. As with all options the membership income is forecasted to reduce by 20%
from £551,503 to £441,202. All other income streams are assumed at pre-closure
levels.
Table 3.5: Financial comparison of Baseline to Option 2  
Reinstate Bells in full  
Aug 22 - July 23 Baseline Option 2
Account Centre Bell’s Dewars Bell’s Dewars
Income Total -£1,045,333 -£273,352 -£899,478 -£273,352
Cost of Sales  £697 £0 £697 £0
Staff Costs £888,922 £308,855 £756,004 £308,855
Property Costs £238,801 £229,869 £238,801 £229,869
Supplies & Services £307,869 £78,424 £307,869 £78,424
Expenditure Total £1,436,289 £617,148 £1,303,371 £617,148
Net Expenditure £390,956 £343,796 £403,892 £343,796
Combined Net
Expenditure £734,752 £747,688
Baseline
Comparison   -£12,936
Impact on Expenditure
This option sees the Bell’s expenditure forecast reduce by 9% overall from
£1,436,289 to £1,303,371. This reduction is from labour optimisation savings of 15%
within staff costs. Property costs and supplies and services remain in line with pre-
closure levels.
Impact on Net Expenditure
Net Expenditure, when compared to the baseline (Table 3.5), shows an increase of
£12,936 to £747,688.

Page 28

27 | P a g e
Impact on Staffing Structures
Through considering aligning staffing to usage, opportunities to reduce costs while
maintaining service levels and staff satisfaction were apparent. A reduction of 15%
of staffing costs are suggested within Option 2. The Bell’s management expenditure
is forecasted to reduce by having a facility manager, a part time administrator, one
duty manager and two senior leisure attendants. The reception is forecasted to be
managed by one receptionist at a time, allowing for management to covers breaks.
With the continuing move to online bookings and communications there could be
less reliance on receptionists. The fitness gym staffing levels remain similar to
baseline gym staffing figures. The fitness staff rota patterns align with usage patterns
with opening staff, additional member of staff at 9am, increasing to three for the peak
times from early evenings Monday to Friday. Leisure attendants reduce to mirror
usage with one staff member during the day, supported by a duty manager or senior
leisure attendant if required, increasing to two after school. The cleaning costs are
only slightly reduced. The staff costs for gymnastics and group fitness instructors all
remain the same as the baseline figures.
Impact on Usage and Demand
The forecasted drops in income for events and membership flow through to usage
as seen in Table 3.6. The events usage is forecasted to drop by 30%. Gym, fitness
classes and personal training are all forecasted to drop by 10%. This allows for
fitness casual usage at pre-closure levels, potentially higher, as prospective
members use the facilities on a casual basis prior to joining. As membership count is
forecasted to reduce this impacts on usage, however usage forecast shows only a
10% decline (not matching the 20% membership decline) as the membership will be
excited to return to their routines in new facilities, so usage is forecasted to reflect
this.
Table 3.6: Usage comparison of Baseline to Option 2 
Aug 22 - July 23 Baseline Option 2
Cost Centre Bell’s Dewars Bell’s Dewars
Education                      15,124  1,138  15,124  1,138 
Events                      45,897  -    32,128  -   
Fitness Classes                      47,534  -    42,781  -   
Fitness Gym                   107,349  -    96,614  -

Page 29

28 | P a g e
Fitness Personal                         1,812  -    1,631  -   
Fun Coached                      18,237  502  18,237  502 
Miscellaneous                                 25  -    25  -   
Non Sport Venue Hire                      13,728  16,473  13,728  16,473 
Sport Go Play                      40,790  22,344  40,790  22,344 
Steps Coached                      13,797  5  13,797  5 
Wellbeing                         5,981  -    5,981  -   
Usage Total                   310,274  40,462  280,835  40,462 
Combined Usage 350,736 321,297
Baseline Comparison  -29,439   
Capital Costs
The capital costs for the full reinstatement of Bell’s are £1,968,047. The most
significant cost is £829,715 on building and fabric including the new flooring
throughout. With the discovery of reinforced autoclaved aerated concrete (RAAC) in
the ceiling, costs to remove and reinstate the ceiling have been included at
£590,000. Fitness is reinstated with new equipment, entry gates and fire door link
up. The arena seating is dismantled and reinstalled and electrical and mechanical
works are included. This allows for all areas of Bell’s to be reinstated in full.
Table 3.7: Capital Costs for Option 2  
Option 2  
Bell’s Dewars
All Areas £865,655  
Main Arena £213,315  
Main Gym £299,077  
RAAC removal and ceiling
reinstatement  £590,000    
£1,968,047 £0
Total £1,968,047

Page 30

29 | P a g e
3.3 Option 3 – Reinstate Bell’s in Part 
Option 3 sees the partial reinstatement of Bell’s with fitness, 8 – 10 badminton courts
and 2 squash courts. The fitness offer is returning to pre-closure scale with the gym,
classes and personal training and the arena sees a decrease in number of courts.
With all facilities being offered at Bell’s, this prevents the situation of having to
relocate fitness if PH20 goes ahead in the future.
Impact on Income
Table 3.8 below shows, total income is forecasted to reduce by 24% against the
baseline from £1,045,333 to £794,569. The events income of £118,514 is removed
with the focus of Option 3 being reinstating the facility for primarily Perth and Kinross
community usage. Membership income is forecasted to reduce by 20% from
£551,503 to £441,202. Option 3 has a reduced number of courts going from 17
badminton courts to 8-10 or from three arenas to two. With less than a third of the
courts, gymnastics income is reduced by 50% with the assumption that the
programmes will continue in their current locations, although they come with
compromises as short-term solutions. In line with the reduction of activities in the
arena, the food vending is forecasted to reduce by 20%. There is predicted growth of
20% in the Sport Go Play income line as the removal of events allows for the growth
of local clubs, additional coaching programmes and casual use at weekends. There
is the potential to return to Sport Go Play income levels of 2019-2020, 42% higher
than pre-closure figures.
Table 3.8: Financial comparison of Baseline to Option 3 
Partial Reinstatement (Fitness, 8-10
badminton courts and 2 squash)  
Aug 22 - July 23 Baseline Option 3
Account Centre Bell’s Dewars Bell’s Dewars
Income Total -£1,045,333 -£273,352 -£794,569 -£273,352
Cost of Sales  £697 £0 £697 £0
Staff Costs £888,922 £308,855 £646,050 £308,855
Property Costs  £238,801 £229,869 £213,801 £229,869
Supplies & Services £307,869 £78,424 £307,324 £78,424
Expenditure Total £1,436,289 £617,148 £1,167,872 £617,148
Net Expenditure £390,956 £343,796 £373,303 £343,796
Combined Net
Expenditure £734,752 £717,099

Page 31

30 | P a g e
Baseline
Comparison   £17,653 
Impact on Expenditure
Staff costs see a further 15% reduction from Option 2, full reinstatement of Bell’s,
and a 27% reduction against the baseline. With reduced facilities to operate and
reduced usage the staff costs are reduced to match. Cost of sales remain
unchanged against the baseline. Property costs show an 10% reduction to £213,
801 from the baseline of £238,801. These savings come from a decrease in cleaning
materials, gas and electricity used in the reduced facility operation. Supplies and
services see a small reduction in expenditure on removing the specific event booking
costs. The total expenditure forecast is £1,167,872 compared to the baseline of
£1,436,289, a 19% reduction.
Impact on Net Expenditure
Net Expenditure is forecasted at £717,099 a reduction of £17,653 from £734,752.
(Table 3.8)
Impact on Staffing Structure
Following the labour optimisation principles that are detailed within Section 2.6,
staffing is forecasted to reduce in-line with customer usage. Option 3 shows a 27%
reduction against the baseline and 14% further reduction against Option 2, full
reinstatement of Bell’s. The further reduction against Option 2 is due to the reduced
facility size, operation and usage.
Impact on Usage and Demand
Member: Fitness gym, classes and personal training all see a 10% reduction in
usage as seen in all options due to the forecasted membership decline. However,
factors such as returning to where they chose to join and all activities being in one
location may help to increase usage. One location may make it more convenient for
families, while children are in club activities in the arena parents can use the gym or
go to a class increasing the likelihood to join or exercise through convenience.
Clubs: In reducing from three arenas to two, the gymnastics usage follows inline
with the 50% reduction in income and is forecasted to continue in the venues

Page 32

31 | P a g e
arranged while closed. The usage for Sport Go Play and Steps Coached returns to
pre-closure levels. Without large scale events and the associated set up there will be
the ability to develop Friday evening through to Sunday evening activities which
would allow for new opportunities to be explored.
Events: Option 3 sees the large events moving elsewhere, with this in mind no
usage is forecasted for events. However, with the proposal of growing local
community and club use there is significant potential to grow a localised Perth and
Kinross events business. 
Table 3.9: Usage comparison of Baseline to Option 3
Usage Aug 22 - July 23 Baseline Option 3
Cost Centre Bell’s Dewars Bell’s Dewars
Education                      15,124  1,138  15,124  1,138 
Events                      45,897  -    -    -   
Fitness Classes                      47,534  -    42,781  -   
Fitness Gym                   107,349  -    96,614  -   
Fitness Personal                         1,812  -    1,631  -   
Fun Coached                      18,237  502  9,119  502 
Miscellaneous                                 25  -    25  -   
Non Sport Venue Hire                      13,728  16,473  -    16,473 
Sport Go Play                      40,790  22,344  40,790  22,344 
Steps Coached                      13,797  5  13,797  5 
Wellbeing                         5,981  -    5,981  -   
Usage Total                   310,274  40,462  225,861  40,462 
Combined Usage
Total 350,736 266,323
Baseline
Comparison   -84,413
Capital Costs
To reinstate Bell’s in part with fitness, 8 – 10 badminton courts and 2 squash courts
the forecasted capital costs are £1,630,176.
These include building and fabric costs of £491,844 a reduction against full
reinstatement due to the reduced courts space. As with Option 2, with the discovery

Page 33

32 | P a g e
of RAAC, costs to remove and reinstate the ceiling have been included at £590,000.
The removal and then reinstatement of the seating units is forecasted at £111,332
which may merit consideration if the large scale events do not return to Bell’s. The
reinstatement of the gym equipment is £264,887. 
Table 3.10: Capital Costs for Option 3  
Option 3  
Bell’s Dewars
All Areas £527,784  
Main Arena £213,315  
Main Gym £299,077  
RAAC removal and
ceiling reinstatement  £590,000    
£1,630,176 £0
Total £1,630,176

Page 34

33 | P a g e
3.4 Option 4 – Reinstate Bell’s in Part with Fitness at
Dewars
Option 4 sees the relocation of fitness to Dewars and the partial reinstatement of
Bell’s arena with 8 – 10 badminton courts and 2 squash courts.
Impact on Income
Table 3.11 below shows the combined operating income of Bell’s and Dewars is
forecasted to decrease by 20% from £1,295,680 to £1,047,954. As with Option 1 the
gym, fitness classes and personal training income streams move to Dewars at pre-
closures levels. Membership income is transferred to Dewars at 80% of baseline
levels. Food vending, fun coached and merchandise income are all retained at 50%
at Bell’s.
Table 3.11: Financial comparison of Baseline to Option 4 
Relocate fitness to Dewars -
reinstate 8-10 badminton
courts and 2 squash  
Aug 22 - July 23 Baseline Option 4
Account Centre Bell’s Dewars Bell’s Dewars
Income Total -£1,045,333 -£273,352 -£251,870 -£796,084
Cost of Sales £697 £0 £697 £0
Staff Costs £888,922 £308,855 £260,151 £559,320
Property Costs £238,801 £229,869 £137,722 £269,869
Supplies & Services £307,869 £78,424 £140,024 £244,769
Expenditure Total £1,436,289 £617,148 £538,593 £1,073,958
Net Expenditure £390,956 £343,796 £286,723 £277,873
Combined Net
Expenditure £734,752 £564,597
Baseline
Comparison   £170,155 
Impact on Expenditure
As with all options the staff costs are reduced and in line with Option 1 Dewars
incurs increased costs. Fitness staff and group fitness instructors are transferred to
Dewars. A proportion of property costs; electricity, repairs and maintenance and
cleaning, which allow for the gym and fitness classes to be delivered are also
transferred to Dewars. Property costs for Bell’s and Dewars are £407,591 a 13%

Page 35

34 | P a g e
reduction from the baseline. This allows for additional electricity, repairs and
maintenance and water costs at Dewars. Reductions are projected at Bell’s due to
the smaller spaces that will be operated. Savings are projected in electricity and gas
for Bell’s. Supplies and services are maintained at pre-closure amounts with
reallocation of most lines to Dewars at 50% including the corporate services
recharge and others where the full cost is transferred including fitness class delivery.
Impact on Net Expenditure
The net expenditure is £564,597 compared to £734,752, a forecasted expenditure
reduction of £170,155. (Table 3.11)
Impact on Usage and Demand
Option 4 has similar predicted impact on usage as Option 3. The usage of 257,623
visits would be spread over Bell’s and Dewars. This is a drop of 93,113 uses against
the pre-closure baseline lost from events, gymnastics and 10% for fitness products.
In addition, relocating fitness to Dewars would entail the complete cessation of
bowling, as detailed for Option 1, the usage is on average 143 unique users each
month during the season of October to March.
Members: The members are forecasted to use Dewars for the gym, fitness classes
and PT at a reduced rate of 10%. Option 4 will have a new gym, studios and
updated changing rooms with strong potential for attracting new and ex-members to
the new facilities.
Clubs: Gymnastics usage is reduced by 50% with the assumption that gymnastics
programmes will continue in their new locations. As with Option 3, Sport Go Play and
Steps Coached usage returns to pre-closure levels. Without large scale events and
the associated set up there will be the ability to develop Friday evening through to
Sunday evening activities which would allow for new opportunities to be explored. As
with option 1, the meeting rooms at Dewars would be converted to studios for fitness
classes, therefore impacting use by clubs. 
Events: Option 4, as with Option 3, sees the large events moving elsewhere, no
usage is forecasted for events. With the proposal of growing local community and
club use there is significant potential to grow a localised Perth and Kinross events
business. At Dewars, as with Option 1, the annual events held in the two halls at
would be impacted reducing the income to £5,222. As noted, when considering

Page 36

35 | P a g e
Clubs, the meeting rooms would be converted to studios therefore impacting
bookings for events.
Table 3.12: Usage comparison of Baseline to Option 4
Usage Aug 22 - July 23 Baseline Option 4
Cost Centre Bell’s Dewars Bell’s Dewars
Education                      15,124  1,138  15,124  1,138 
Events                      45,897  -    -    -   
Fitness Classes                      47,534  -    -    42,781 
Fitness Gym                   107,349  -    -    96,614 
Fitness Personal                         1,812  -    -    1,631 
Fun Coached                      18,237  502  9,119  502 
Miscellaneous                                 25  -    25  -   
Non Sport Venue Hire                      13,728  16,473  -    7,773 
Sport Go Play                      40,790  22,344  40,790  22,344 
Steps Coached                      13,797  5  13,797  5 
Wellbeing                         5,981  -    -    5,981 
Usage Total                   310,274  40,462  78,855  178,769 
Combined Usage
Total 350,736 257,623
Baseline Comparison   -93,113 
Capital Costs
Capital costs for Option 4 are £2,185,537. Those are higher than Option 3 due to the
additional costs caused by relocation of fitness to Dewars. They include building,
fabric, electrical and mechanical reinstatement costs of £693,260 to return Bell’s to
an operational state with the reduced court offer. As with Options 2 and 3, the
discovery of RAAC incurs costs to remove and reinstate the ceiling at £590,000. 
Fitness reinstatement costs are £302,277 plus £600,000 to relocate the gym to the
bowling hall at Dewars, along with the meeting rooms being converted to studios and
upgrading the changing rooms.
Table 3.13: Capital Costs for Option 4

Page 37

36 | P a g e
Option 4  
Bell’s Dewars
All Areas £479,945  
Main Arena £213,315  
Main Gym   £302,277
RAAC £590,000 
Build Costs   £600,000 
£1,283,260 £902,277
Total £2,185,537

Page 38

37 | P a g e
3.5 Option 5 – Wild Card Option
Option 5 sees Bell’s reinstated in part and the relocation of all fitness to a non-LAL
facility. The main arena at Bell's would be partially reinstated, similar to other
options, with 8 - 10 courts and squash retained with 1 - 2 courts.
The Wild Card option was added to consider fitness at a different location due to the
ongoing flood risk, inability to insure Bell’s and uncertainty for the future of fitness at
Dewars due to the potential of PH20.
Impact on Income
Table 3.14 below shows the impact on income is forecasted to be similar to Option 3
due to the arena reinstatement also being 8 – 10 badminton courts and 2 squash
court along with fitness and membership mirroring Option 3 but at a new venue
instead of Bell’s.
Table 3.14: Financial comparison of Baseline to Option 4 
Wild Card - Partial reinstatement of
Bell’s and new venue  
Aug 22 - July 23 Baseline Option 5
Account Centre Bell’s Dewars Bell’s Dewars New Venue
Income Total -£1,045,333 -£273,352 -£251,870 -£273,352 -£539,331
Cost of Sales £697 £0 £697 £0 £0
Staff Costs £888,922 £308,855 £274,889 £308,855 £300,044
Property Costs £238,801 £229,869 £137,722 £229,869 £223,920
Supplies & Services £307,869 £78,424 £136,695 £78,424 £170,670
Expenditure Total £1,436,289 £617,148 £550,002 £617,148 £694,633
Net Expenditure £390,956 £343,796 £298,132 £343,796 £155,301
Combined Net
Expenditure £734,752 £797,229
Baseline
Comparison   -£62,477 
Impact on Expenditure
Property costs see additional costs of £223,920 for the new venue. Supplies and
services remain consistent with other options. The staff costs are forecasted for
Bell’s and the new venue combined at £574,932, this is lower than the staff costs in

Page 39

38 | P a g e
Option 3 as savings have been made within management costs and the removal of
receptionists. The expenditure total for the three venues is forecasted as £1,861,782
compared to baseline at £2,053,437 and against Option 2, full reinstatement at
£1,920,519.
When comparing the wild card to full reinstatement the net expenditure is higher at
£797,229 compared to £747,688 due mainly to the higher property costs which
includes rates and rental and partly to less income. The wild card has lower staff
costs but overall, the worst financial baseline comparison.
Impact on Net Expenditure
The net expenditure of this option would be the highest of all options, higher than the
baseline and full reinstatement. (Table 3.14)
Impact on Usage and Demand
Wild card usage figures are forecasted to be the same as Option 3. The arena and
squash usage is also forecasted to be the same as all options that consider 8 – 10
badminton courts and 2 squash courts. The fitness usage remains the same but is
moved to a new venue. Overall, the usage is forecasted at 266,323 annual visits, a
reduction of 84,413 against pre-closure levels. 
Table 3.15: Usage comparison of Baseline to Option 5
Usage
Aug 22 - July 23
Baseline Option 5
Cost Centre Bell`s Dewars Bell`s Dewars New Venue
Education                                   15,124  1,138  15,124  1,138  -   
Events                                   45,897  -    -    -    -   
Fitness Classes                                   47,534  -    -    -    42,781 
Fitness Gym                                107,349  -    -    -    96,614 
Fitness Personal                                      1,812  -    -    -    1,631 
Fun Coached                                   18,237  502  9,119  502  -   
Miscellaneous                                              25  -    25  -    -   
Non Sport Venue Hire                                   13,728  16,473  -    16,473  -   
Sport Go Play                                   40,790  22,344  40,790  22,344  -   
Steps Coached                                   13,797  5  13,797  5  -

Page 40

39 | P a g e
Wellbeing                                      5,981  -    -    -    5,981 
Usage Total                                310,274  40,462  78,855  40,462  147,007 
Combined Total
Usage                                                                    350,736  266,323
Baseline Comparison   -84,413
The benefit of the wild card would be in the event of any future flooding the gym
equipment and operation would be protected at a new venue. Similarly, if PH20
proceeds the members that moved from Bell’s to Dewars would then be moved
again into a temporary fitness location while PH20 is built causing significant
customer interruption. The new venue could allow for consistent fitness operation
and customer service.
Capital Costs
The wild card capital costs are £1,585,537. These allow for £693,260 at Bell’s to
partially reinstate the arena with 8 – 10 badminton courts and 2 squash courts,
mirroring the Bell’s costs for Option 4. As with Option 2, 3 and 4, with the discovery
of RAAC, costs to remove and reinstate the ceiling have been included. They also
include £302,277 as an estimate to set up fitness in the new venue allowing for new
equipment and entry gates.
Table 3.16: Capital Costs for Option 5   
Option 5  
Bells Sports Centre Dewars New Venue
All Areas £479,945    
Main Arena £213,315    
Main Gym     £302,277
RAAC £590,000    
£1,283,260 £0 £302,277
Total £1,585,537

Page 41

40 | P a g e
3.6 Option 6 – Reinstate Fitness Only at Bell’s
Option 6, the final option, evaluates the potential of fitness only being reinstated at
Bell’s. The impact considers the fitness spaces being reinstated in pre-closure
locations.
Impact on Income
Table 3-17 shows the forecasted income total for Bell’s is £591,970 a 43% reduction
on the baseline. This impact is caused by the closure of the arena and the loss of
three significant income streams; Sport Go Play £120,152, Events £118,515 and
Steps Coached £50,752. However, a proportion of this may move to other LAL sites
or schools. Membership income is forecasted at 80% and fitness income streams
are predicted to continue at Bells. As with other options the gymnastics income for
the programmes that were rehomed when closed is still shown in the Bells income
and expenditure lines.
Table 3-17: Financial comparison of Baseline to Option 6  
Fitness only in Bells  
Aug 22 - July 23 Baseline Option 6
Account Centre Bell’s Dewars Bell’s Dewars
Income Total -£1,045,333 -£273,352 -£591,970 -£273,352
Cost of Sales £697 £0 £697 £0
Staff Costs £888,922 £308,855 £464,722 £308,855
Property Costs £238,801 £229,869 £119,401 £229,869
Supplies & Services £307,869 £78,424 £298,723 £78,424
Expenditure Total £1,436,289 £617,148 £884,048 £617,148
Net Expenditure £390,956 £343,796 £292,078 £343,796
Combined Net
Expenditure £734,752 £635,874
Baseline
Comparison  £98,878 
Impact on Expenditure
No mothballing costs are assumed for the arena and other areas at Bell’s. Staff
costs see a significant reduction of 48% against pre-closure costs and are second
only to Option 1 due to maintaining reduced operations at Bells in addition to

Page 42

41 | P a g e
Dewars. Property costs reduce to £119,401; these reduced costs are second only to
Option 1 with a 50% reduction against the baseline. These forecasted reductions are
due to the arena, squash courts and other areas remaining closed. There is a 50%
reduction in cleaning, electricity, gas, repairs and maintenance. 
Impact on Net Expenditure
Net expenditure of Option 6 is £635,369, a reduction of £99,383 on the baseline.
However, it is higher than Options 1 and 4. Similarly, the baseline financial
comparison shows Option 6 could operate with the third lowest expenditure.
Impact on Usage and Demand
Operating only fitness at Bell's shows a drop in usage of 154,149 against pre-closure
figures. The only variation against Option 1 is due to the gym at Dewars being
located in the hall that generated usage through non sport venue hire. The pre-
closure usage was 350,736 annually, option 6 would allow for annual usage of
196,587.
Table 3.18: Usage comparison of Baseline to Option 6
Usage Aug 22 - July 23 Baseline Option 6
Cost Centre Bell`s  Dewars Bell`s  Dewars
Education                                   15,124  1,138  -    1,138 
Events                                   45,897  -    -    -   
Fitness Classes                                   47,534  -    42,781  -   
Fitness Gym                                107,349  -    96,614  -   
Fitness Personal                                      1,812  -    1,631  -   
Fun Coached                                   18,237  502  9,119  502 
Miscellaneous                                              25  -    -    -   
Non Sport Venue
Hire                                   13,728  16,473  -    16,473 
Sport Go Play                                   40,790  22,344  -    22,344 
Steps Coached                                   13,797  5  -    5 
Wellbeing                                      5,981  -    5,981  -   
Usage Total                                310,274  40,462  156,125  40,462 
Combined Total
Usage 350,736 196,587

Page 43

42 | P a g e
Baseline
Comparison  -154,149
As with Option 1, Perthshire Rugby Football Club use Bell’s as a clubhouse and the
changing facilities. This is a situation that would need to be addressed.
Capital Costs
The reinstatement of fitness only at Bell’s reflects lower capital costs than Options 2-
5 as the large-scale costs to reinstate the arena in full or part are not incurred. The
costs shown in Table 3.19 allow for fitness operations to be reinstated in pre-closure
locations.
Table 3.19: Capital Costs for Option 6  
Option 6  
Bell’s Dewars
All Areas £115,591  
Main Arena    
Main Gym £299,077  
RAAC  £590,000    
£1,004,667 £0
Total £1,004,667

Page 44

4. Options Appraisal
Table 4.1 shows an appraisal of each of the options under consideration across a range of important criteria which reflect the key project
objectives. 
Option 1 - Full Closure of Bell’s and Relocation of Fitness to Dewars Centre: This option results in a significant decrease in income and
expenditure, improving net expenditure by £321,822. A notable downside is the significant decrease in usage, dropping at Bell’s by 162,849
compared to the baseline, the highest decline of all options. Dry side activities may or may not find capacity to relocate to schools, since
Bell’s closure the relocation of clubs and groups has been low, events and bowling would cease. This option involves a modest capital
investment with a 3 year return on investment (ROI). 
Option 2 - Reinstate Bell’s in Full: While income decreases slightly, this option incurs high capital costs and offers a marginal increase in
net expenditure. The increase in net expenditure would mean that there is no payback achieved. 
Option 3 - Reinstate Bell’s in Part with Fitness and reduced courts: This approach sees a decrease in income by £250,764 and a
reduction in expenditure by £268,417. The net expenditure improves by £17,653. The usage decreases by 84,413, however this option
allows for clubs and groups to return to Bell’s with the opportunity to increase the usage and grow local events. The capital costs for partial
reinstatement are set at £1,630,176, with a projected return on investment in 92 years. 
Option 4 - Reinstate Bell’s in Part with Relocation of Fitness to Dewars Centre: Here, the income falls by £270,731, and expenditure
reduces by £440,886. This leads to an improvement in net expenditure of £170,155. There's a decline in usage by 93,113, however, as with
Option 3 it allows for groups and clubs to recommence with the opportunity to increase usage and local events. Capital costs are
£2,185,537, with a return on investment estimated at 13 years.

Page 45

44 | P a g e
Option 5 - Wild Card: Reinstate Bell’s in Part with Relocation of Fitness to a non-LAL facility: Unique among options, it shows a
potential cost saving in net expenditure and comparable capital costs to Option 3, but this option will not show a ROI due to the rental and
rates costs of an additional venue.
Option 6 - Reinstate Fitness Only at Bell’s: The income decline is significant at £453,363, while the expenditure sees the most
considerable reduction of £552,746. The net expenditure improves by £99,383. This option also leads to a large decrease in usage and
demand (154,149 less than the baseline). The capital costs are comparatively lower at £1,004,667, with a return on investment of 10 years.
Harder to measure factors that will impact future membership growth or decline, and usage include the look and feel of each option. When
considering fitness at Dewars the investment into the design of the gym and studios will influence the appeal to different demographics and
potential member groups. Similarly, partial reinstatement of 8 – 10 courts at Bell’s arena would open up additional areas to be exploited for
other purposes to create fun and engaging spaces to be used by all ages and abilities such as a soft play structure that could be rehomed at
a later date, a jogging or toddler cycling and scooting loop. Capital costs provided by LAL include costs to reinstate operations. Allocation for
decoration, marketing and launch or relaunch plans to encourage community buy in and successful pre-sale membership uptake should be
considered. 
Accommodating fitness members at alternative LAL facilities and various gyms throughout Perth and Kinross is a viable option. It is also
crucial to identify appropriate new venues for the diverse array of Bell’s arena users. This includes those involved in both competitive and
social sports, individuals with disabilities, and a range of community groups spanning from youth to older adults. Additionally, securing
suitable venues for events to maintain the continuity and inclusivity of the services offered.

Page 46

45 | P a g e
Table 4.1: Options Appraisal Matrix
Criteria Option 1 Option 2 Option 3 Option 4 Option 5 Option 6
Impact on Income v Baseline -£473,253 -£145,855 -£250,764 -£270,731 -£254,132 -£453,363
Impact on Expenditure v Baseline -£795,075 -£132,918 -£268,417 -£440,886 -£886,287 -£552,746
Net Expenditure v Baseline  £321,822 -£12,936 £17,653 £170,155 -£62,477 £99,383
Usage & Demand v Baseline -162,849 -29,439 -84,413 -93,113 -84,413 -154,149
Capital Costs £902,277 £1,968,047 £1,630,175 £2,185,537 £1,585,537 £1,004,667
Return in Investment (years) 3 yrs. N/A 92 yrs. 13 yrs. N/A 10 yrs.
Facilities Reinstated:
Gym
Fitness Classes
Badminton Courts
Squash Courts 
Y
Y
N
N
Y
Y
Y (17 courts)
Y (3 courts) 
Y
Y
Y (8-10 courts)
Y (1-2 courts) 
Y
Y
Y (8-10 courts)
Y (1-2 courts) 
Y
Y
Y (8-10 courts)
Y (1-2 courts) 
Y
Y
N
N

Page 47

5. Recommendations
Based on the options appraisal and considering the strategic future of Bell's Sports
Centre, the following recommendations are proposed:
• Primary Recommendation - Option 1 (Full Closure and Relocation of Fitness to
Dewars Centre):
o Despite the significant decrease in usage at Bell's, this option stands out
financially, with a substantial improvement in net expenditure of £321,822
and a modest capital investment offering a 3 year ROI.
o The challenge of accommodating displaced users, particularly those from
community clubs and groups, must be addressed through concerted efforts
to find alternative venues within Perth and Kinross.
o Option 1 has the largest negative impact on usage of the six options.
Programming and planning at a strategic level across Perth and Kinross
would be required to identify appropriate alternative venues for the diverse
array of existing Bell’s arena users. This includes those involved in both
competitive and social sports, individuals with disabilities and a range of
community groups spanning from youth to older adults. It necessitates
strategic planning to address the displacement of other services and
programmes, review of facility booking processes, opening discussions on
access to school facilities during the day and a need for clubs to be
prioritised.
• Secondary Recommendation – Option 4 (Reinstate Bell’s in Part with
Relocation of Fitness to Dewars Centre): 
o Offering a balanced improvement in net expenditure and a 13 year ROI, this
option allows community groups to recommence activities at Bell's,
supporting local events and usage.
o The PH²0 project timescales are likely to impinge upon a 13 year payback
period which would mean it is unlikely to be achieved.
In conclusion, while Option 1 is recommended for its financial benefits and rapid
ROI, careful planning and community engagement are essential to address the
considerable decrease in usage and ensure a smooth transition for Bell's diverse
user groups. Option 4 serve as a viable alternative, offering a blend of financial

Page 48

47 | P a g e
prudence and community service continuity but may be impacted by PH²0 project
timescales.

Page 49

48 | P a g e
6. Appendices

Page 50

Table 6-1 Options Assumptions Summary Table 
Option  Income and Usage Staff Costs Property Costs Supplies and Services
All +/-‘s are with reference to a baseline. The existing usage/financial baseline is set from Aug. 2022 to July 2023 
Option 1  All Facility based activity at Bells
stops, so no income or usage
assumed. 
New Fitness staff rota implemented
focussing on customer usage
patterns. 
No mothballing costs for Bells
currently assumed. 
Full Corporate Services Recharge
moved over to Dewars. 
Gymnastics continues in School’s at
50% of usage.  Income moved to
Dewars. 
Fitness staff costs moved to
Dewars. 
Increase Dewars electricity by
£20K for gym equipment. 
50% of Bells equipment budget
moved to Dewars. 
Gym and fitness classes (3 studio’s)
moves to Dewars.  PAYG fitness
income returns to 100%, membership
income returns to 80%, Health &
fitness usage returns to 90%. 
Deputy Manager moved to Dewars
to manage community halls, North
Inch and Glenearn. 
Dewars Gas remains at normal
levels as no heating supplied for
fitness areas. 
All fitness class delivery costs
moved to Dewars. 
All Wellness activity moved to
Dewars. 
50% of Gymnastics staff retained,
costs moved to Dewars. 
50% of Bells repairs and
Maintenance moved to Dewars to
cover fitness equipment and
additional throughput. 
50% Bells printing and stationery
moved to Dewars. 
No LAL income/Usage assumed for
activity re-located to schools. 
All other Bells staff costs assumed
at 0. 
£10K added to Dewars water for
shower usage (approx. 50% of
Bells current costs). 
50% of Bells subscriptions and
licencing moved to Dewars. 
£5K added to cleaning at Dewars.   
Option 2  PAYG Fitness income returns to
100%, membership income returns to
80%, Health & Fitness usage returns
to 90%.  New staffing model implemented,
reducing staff levels across the
board. 
All Bells and Dewars costs are
assumed at existing baseline
level. 
All Bells and Dewars costs are
assumed at existing baseline level.  Bells events recovery assumed at
70% due to loss of existing events,
some of which won’t return. 
All other usage/income returns to
100% of baseline level.

Page 51

50 | P a g e
Option 3  PAYG Fitness income returns to
100%, membership income returns to
80%, Health & Fitness usage returns
to 90%. 
New staffing model implemented,
reducing staff levels across the
board. 
Bells cleaning reduced by £5k due
to reduced space. 
Corporate Service Recharge
assumed at current level. 
Assumed no provision of Bells events
space, so events income and usage
at 0%. 
Dry side staffing reduced from
option 2 due to reduced hireable
space. 
Bells electricity and gas reduced
by £10K each through
reconfiguration of available public
area’s and required heating and
lighting. 
Bells event specific booking costs
reduced to 0%. 
Gymnastics continues in School’s at
50% of usage.  50% of Gymnastics staff retained.     
Bell’s Sport Go Play income and
usage assumed to increase by 20%
due to increased availability caused
by hosting no or minimal events. 
Option 4  Gymnastics continues in School’s at
50% of usage. 
New staffing model implemented,
reducing staff levels across the
board. 
£50k reduction in Bells electricity,
£30K reduction in Bells gas. 
50% of Bells corp. services
recharge moved to Dewars. 
Gym and fitness classes (3 studio’s)
moves to Dewars.  PAYG fitness
income returns to 100%, membership
income returns to 80%, Health &
fitness usage returns to 90%. 
Skeleton staff at Bells report to
Management team at Dewars 
Add £20k to Dewars Electricity for
gym equipment. 
Fitness class delivery costs moved
to Dewars. 
Assumed no provision of events
space, so events income at 0%. 
Deputy Manager retained at Bells to
manage community halls, North
Inch and Glenearn. 
Reduce Bells maintenance by
50% and add £10k to Dewars to
cover fitness equipment. 
50% of Bells equipment budget
moved to Dewars. 
Bell’s Sport Go Play income and
usage assumed to increase by 20%
due to increased availability caused
by hosting no or minimal events. 
All Fitness staff relocated to
Dewars. 
Reduce Bells water by 50% and
add £10k to Dewars to account for
fitness users in Dewars. 
Move £2K of other delivery costs
from Bells to Dewars 
All Wellness activity moved to
Dewars.     
Reduce Subscriptions by £2.5k at
Bells and add £1k to Dewars. 
Option 5  Gymnastics continues in School’s at
50% of usage. 
New staffing model implemented,
reducing staff levels across the
board. 
£50k reduction in Bells electricity,
£30K reduction in Bells gas. 
All Supplies and services split
equally between Bells and new

Page 52

51 | P a g e
Gym and fitness classes (3 studio’s)
moves to new venue.  PAYG fitness
income returns to 100%, membership
income returns to 80%, Health &
fitness usage returns to 90%. 
Skeleton staff at Bells to cover
reduced Dry side. 
Add £20k to New Venue
Electricity for gym equipment, and
£10k to new venue gas. 
venue, including corporate services
recharge. 
Assumed no provision of bell’s
events space, so events income at
0%. 
Fitness and cleaning staff for new
venue. 
Reduce Bells maintenance by
50% and add £10k to New
Venue. 
Bell’s Sport Go Play income and
usage assumed to increase by 20%
due to increased availability caused
by hosting no or minimal events. 
Manager only retained at Bells to
look after new venue in addition to
reduced Bells provision, Community
Halls, Glenearn and north Inch. 
Reduce Bells water by 50% and
add £10k to New Venue 
All Wellness activity moved to new
venue.   
New Venue Rent/Rates included
at £170,000 per year.  Based on
£10sp/ft rental costs and 80%
reduction in rates at £20K. 
Option 6  All Arena based activity at Bells
stops, so no income or usage
assumed. 
New staffing model implemented,
reducing staff levels across the
board. 
All property costs reduced by
50% 
Equipment, medical supplies, other
delivery costs and subscriptions all
reduced by 50% 
Gymnastics continues in School’s at
50% of usage. 
Fitness staff supported by 1 Senior
LA and cleaner.  No duty
managers. 
All other costs as per baseline,
including corporate services
recharge 
PAYG fitness income returns to
100%, membership income returns to
80%, H&F usage returns to 90%. 
Manager only retained at Bells to
look after fitness in addition to
reduced Bells provision, Community
Halls, Glenearn and north Inch. 
Assumed no provision of events
space, so events income at 0%.     
All Sport Go Play and Steps Coached
income/usage assumed at 0%.