Argyll and Bute Council
Development & Economic Growth   
Committee Planning Application Report and Report of Handling as required by
Schedule 2 of the Town and Country Planning (Development Management Procedure)
(Scotland) Regulations 2013 relative to applications for Planning Permission or
Planning Permission in Principle 
Reference No: 21/01102/PP
Planning Hierarchy: Local
Applicant: Isle of Gigha Heritage Trust
Proposal: Erection of 3 dwellinghouses and 2 flats. Installation of air source
heat pumps, formation of access and parking arrangements and
associated landscaping.
Site Address:  Field adjacent to Playpark, Ardminish, Isle of Gigha    
DECISION ROUTE 
Local Government Scotland Act 1973 
(A)  THE APPLICATION 
(i) Development Requiring Express Planning Permission
 Erection of 3 dwellinghouses and 2 flats (total five new dwelling units);
 Formation of new vehicular access;
 Formation of 10 parking spaces;
 Formation of refuse collection/bin store;
 Installation of air source heat pumps;
 Installation of private foul drainage treatment plant and soakaway;
 Landscape and boundary treatment. 
(ii) Other specified operations
 Connection to public water supply; 
(B) RECOMMENDATION: 
Recommend that planning permission be granted subject to the conditions and
reasons attached. 
(C) CONSULTATIONS:   
ABC Roads (17.12.2021 & 31.03.2022) – No objections subject to conditions in
relation to the layout of the junction with the public road, provision of visibility splays,
and provision of onsite parking and turning to meet the requirements of the new
development.

Page 2

Scottish Water (17.12.2021) – No objections with confirmation that there is sufficient
capacity in the Gigha Water Treatment Works to service the development, and
confirmation that there is no public sewer in the vicinity of the development site. 
Health & Safety Executive (05.01.2022) – No objections. 
Gigha Community Council (17.02.2022) – Highlight that this currently undeveloped
area provides a green space adjacent to an existing playpark and is utilised as an
extension to the playpark for ball games. Development of this location will result in
the loss of a valued play space. It is also highlighted that noise from the use of the
adjacent existing playpark may impact upon the amenity of the residents of the new
development. It is suggested that alternative locations may be better suited for
development. 
(D) HISTORY:   
06/02516/COU – Change of Use of Agricultural Land to Form Play Area – PER –
30.01.2007 
This detailed planning permission relates to the provision of a play park at an
amended location to details previously approved under 04/01466/DET, and for the
formation of a putting green on the lower part of the site. The play area has been
implemented the putting green has not, however this permission must be considered
to be ‘live’ by means of a material commencement of works. The current proposal
does not affect the site of the existing play park but would occupy the entire site
previously identified for development of the putting green. 
04/01466/DET – Erection of 18 dwellinghouses, associated drainage, play area and
footpath – PER – 25.11.2004 
This detailed planning permission relates to a housing development that has now
been implemented in full. The current application site is located on land that was
identified in this permission for provision of a playpark, alternative arrangements
have however subsequently been approved (06/02516/COU) and implemented. 
(E) PUBLICITY:   
The application has been advertised under Reg. 20 for the purpose of vacant land.
Published 17th December 2021 – expired 28th January 2022. 
(F) REPRESENTATIONS:   
(i) Representations received from: 
The proposal has been subject to objection from the 10 individual third parties listed
below: 
Rhona Martin, 9 Grianan, Isle of Gigha (28.01.22, 28.01.22, & 24.02.22)
Tony Philpin, Tighcruinn, Isle of Gigha (28.01.22)
John MacDonald, Cnoc An Lein, Isle of Gigha (24.01.22)
Willie McSporran, 10 Ardminish, Isle of Gigha (21.01.22)
Malcolm Henderson, North Drumachro, Isle of Gigha (20.01.22)

Page 3

Karen Durnin, 7 Ardminish, Isle of Gigha (19.01.22)
Keith Helm, Gigulum, Isle of Gigha (19.01.22)
Tracy Helm, Gigulum, Isle of Gigha (19.01.22)
Audrey Dickie, Gigulum Cottage, Isle of Gigha (18.01.22)
Jacqueline Cochrane, North drumachro, Isle of Gigha (17.01.22) 
(ii) Summary of issues raised: 
Representations are published in full on the Public Access planning application file. The
issues raised are summarised as follows: 
Requirement for Housing Development 
 It is contended that there is no requirement for additional housing on
Gigha. It is identified that there are a number of vacant properties on the
island at this time. It is contended that these 5-7 properties include
buildings owned by the Trust and Fyne Homes that could potentially
accommodate 20 people, which would equate to around 12% of the
current population of the island. 
 The applicant has not demonstrated a socio-economic or housing land
supply case in support of the development. 
 It is contended that there are currently limited employment opportunities
on the island and that the provision of more housing will exacerbate this
problem. 
Comments: The proposal is for a ‘small scale’ development that is
consistent with the scales of housing development generally supported
by the LDP within the context of Ardminish. There is no requirement for
the applicant to be able to demonstrate a specific requirement for the
development in this instance. 
Concern about activity/actions of the applicant (Isle of Gigha Heritage
Trust) 
 Concern is raised that there has been no opportunity for members (of the
Isle of Gigha Heritage Trust) and residents of Gigha to discuss the
proposals and the requirement for housing on the island. Concern is
raised that the Trust have not followed due democratic process in
deciding to take forward their proposals without first engaging with the
island community. It is noted that Trust members meetings have been
impacted by Covid. 
 Concern is expressed that the Trust have previously sold property that
has been renovated with Government funding. It is contended that had
they retained these assets the current development would not be
required. 
Comments: It is advised that the proposal is a ‘local’ scale development
and accordingly does not require statutory pre-application consultation
with stakeholders/community.

Page 4

The constitutional arrangements of the Isle of Gigha Heritage Trust and
any requirement that this places upon the applicant to engage with
members/residents of Gigha is not a material planning consideration. 
Concern about notification procedures 
 Concern is raised that the only properties served neighbour notification
by the Council were in the ownership of the applicant. 
Comment: It is confirmed that the Council has served neighbour
notification in accordance with the requirements of the Development
Management Procedure (Scotland) Regulations 2013. In this instance
this has involved direct postal notification issued to the
owner/occupier/lessee of 4 properties falling within the notifiable distance
and placement of an advertisement in the local press in respect of ‘vacant
land’. 
Concern relating to the site/design of the development 
 Concern is raised that the proposed development will adversely impact
on the rural qualities of Ardminish/Isle of Gigha. 
 Concern is expressed that the proposal will impact adversely on the
“environment and topography” of Gigha. 
 Concern is expressed that the development will occupy a green space
that provides separation between existing nodes of development within
Ardminish, and that the land would be better used for play
space/biodiversity. It is identified that Ardminish is a linear settlement with
green spaces between clusters of buildings; concern is expressed that
this development shall result in clusters being merged and a cumulative
scale of development that is out of keeping with the rural locale. 
 It is contended that the proposal does not respect the landscape
character of the area and is contrary to Policy LDP STRAT 1 (h) and (i). 
Comment: An assessment of the suitability of the siting and design of the
proposed development in relation to the receiving environment and
requirements of relevant policy provisions is contained within Appendix
A. 
 Concern is expressed that the loss of this open aspect will impact on the
amenity of adjacent residential properties, including loss of view. 
Comments: The enjoyment obtained by neighbouring properties of the
currently undeveloped/open aspect of the development site is a ‘free’
amenity and does not in itself preclude a landowner’s ability to develop
the site. 
The site is currently in agricultural use and does not form part of any
formally recognised play space or open space protection area.

Page 5

Loss of view from private residential premises is not a material planning
consideration. 
The proposed development is sufficiently removed from existing
residential property that it is not expected to have any significant impact
upon loss of daylight or privacy. 
 Concern is expressed that the proposal is not environmentally
sustainable and in particular it is intimated that the use of air source heat
pumps will not be effective within the building design proposed and may
give rise to significant energy costs to heat the properties. It is also noted
that the proposal does not include solar water or solar PV provision built
into the design, or future proofed insulation requirements. 
 Concern is expressed that the proposal does not include water
conservation measures within the project design. 
Comments: The Argyll and Bute LDP 2015 does not include any policy
requirement stipulating the inclusion of renewable energy within new
development. The energy efficiency of new buildings is however a matter
that will be considered in detail through subsequent Building Warrant
requirements. 
 Concern is expressed that the development will require street lighting that
will cause light pollution.
Comment: The details presented do not indicate the intention to install
street lighting on the private road serving the site. 
Concern about road safety 
 Concern is expressed at the potential increase on traffic on the single
track public road both during construction and the residential occupation
of the development. 
Comment: The Council’s Roads Officer has not raised objection to the
proposal subject to conditions relating to access arrangements. 
(G) SUPPORTING INFORMATION 
Has the application been the subject of: 
(i) Environmental Statement: No  
(ii) An appropriate assessment under the
Conservation (Natural Habitats) Regulations
1994:   
No  
(iii) A design or design/access statement:    No  
(iv) A report on the impact of the proposed
development eg. Retail impact, transport
No

Page 6

impact, noise impact, flood risk, drainage
impact etc:     
(H) PLANNING OBLIGATIONS 
Is a Section 75 agreement required:   No   
(I) Has a Direction been issued by Scottish Ministers in terms of Regulation 30,
31 or 32:  No    
(J) Section 25 of the Act; Development Plan and any other material considerations
over and above those listed above which have been taken into account in the
assessment of the application 
(i)  List of all Development Plan Policy considerations taken into account
in assessment of the application. 
‘Argyll and Bute Local Development Plan’ Adopted March 2015 
LDP STRAT 1 – Sustainable Development 
LDP DM 1 – Development within the Development Management Zones 
LDP 3 – Supporting the Protection Conservation and Enhancement of our
Environment 
LDP 8 – Supporting the Strength of our Communities 
LDP 9 – Development Setting, Layout and Design 
LDP 10 – Maximising our Resources and Reducing our Consumption 
LDP 11 – Improving our Connectivity and Infrastructure 
‘Supplementary Guidance to the Argyll and Bute Local Plan 2015’ (Adopted
March 2016) 
Natural Environment 
SG LDP ENV 1 – Impact on Habitats, Species and our Biodiversity 
Landscape and Design 
SG LDP ENV 14 – Landscape 
Historic Environment and Archaeology 
SG LDP ENV 16(a) – Impact on Listed Buildings 
General Housing Development 
SG LDP HOU 1 – General Housing Development Including Affordable Housing
Provision 
Sustainable Siting and Design 
SG LDP Sustainable – Sustainable Siting and Design Principles

Page 7

Resources and Consumption 
SG LDP SERV 1 – Private Sewage Treatment Plants & Wastewater Systems
SG LDP SERV 2 – Incorporation of Natural Features / SuDS
SG LDP SERV 5(b) – Provision of Waste Storage & Collection Facilities within New
Development
SG LDP SERV 8 – Development in the Vicinity of Notifiable Installations
SG LDP SERV 9 – Safeguarding Better Quality Agricultural Land 
Transport (Including Core Paths) 
SG LDP TRAN 1 – Access to the Outdoors
SG LDP TRAN 2 – Development and Public Transport Accessibility
SG LDP TRAN 4 – New & Existing, Public Roads & Private Access Regimes
SG LDP TRAN 6 – Vehicle Parking Provision 
(ii)  List of all other material planning considerations taken into account in
the assessment of the application, having due regard to Annex A of
Circular 3/2013. 
 Scottish Planning Policy 
Argyll and Bute proposed Local Development Plan 2 (November 2019) – The
unchallenged policies and proposals within pLDP2 may be afforded significant material
weighting in the determination of planning applications at this time as the settled and
unopposed view of the Council. Elements of the pLDP2 which have been identified as
being subject to unresolved objections still require to be subject of Examination by a
Scottish Government appointed Reporter and cannot be afforded significant material
weighting at this time. The provisions of pLDP2 that may be afforded significant weighting
in the determination of this application are listed below: 
 Policy 35 – Design of New and Existing, Public Roads and Private
Access Regimes
 Policy 36 – New Private Accesses
 Policy 39 – Construction Standards for Private Access 
(K) Is the proposal a Schedule 2 Development not requiring an Environmental
Impact Assessment:  No    
(L) Has the application been the subject of statutory pre-application consultation
(PAC):  N/a 
(M) Has a sustainability check list been submitted:  No 
(N) Does the Council have an interest in the site:  No 
(O) Requirement for a hearing: No

Page 8

There is a total of 10 no. objections to the application.
However, the land-use planning related issues raised are not
considered to be unduly complex and, as such, it is considered
that a fully informed assessment and determination can be
made with reference to this report. 
On this basis, and having regard to the approved guidelines
for hearings, it is considered that a hearing would not add value
to this assessment.  
(P) Assessment and summary of determining issues and material considerations 
The proposal seeks detailed planning permission for a development comprising three
dwellinghouses and two flatted dwellings located within the ‘settlement area’ of
Ardminish, Isle of Gigha. 
The proposal is considered to be of appropriate location, scale, design and finishes,
and does not give rise to any concern in relation to infrastructure, services or, to its
compatibility with surrounding land uses. The proposal is accordingly considered to
be consistent with the relevant provisions of policies LDP DM 1, LDP 3, LDP 8, LDP
9, LDP 10, LDP 11, SG LDP and relevant supporting Supplementary Guidance. 
The application has however been subject to representation from ten individuals who
have raised objection to the proposals, and also concern raised by Gigha Community
Council about the prospective loss of land used for recreational purposes. 
(Q) Is the proposal consistent with the Development Plan: Yes 
(R) Reasons why Planning Permission or Planning Permission in Principle Should
be Granted: 
The proposal is considered to be consistent with the relevant provisions of the
Development Plan, and there are no other material considerations of sufficient
significance to indicate that it would be appropriate to withhold planning permission
having regard to s25 of the Act. 
(S) Reasoned justification for a departure to the provisions of the Development
Plan 
N/a 
(T) Need for notification to Scottish Ministers or Historic Environment Scotland:
No   
Author of Report: Peter Bain Date: 2nd June 2022 
Reviewing Officer: Sandra Davies Date: 6th June 2022 
Fergus Murray

Page 9

Head of Development & Economic Growth

Page 10

CONDITIONS AND REASONS RELATIVE TO APPLICATION REF. NO. 21/01102/PP 
1. The development shall be implemented in accordance with the details specified on the
application form dated 25th May 2021 supporting information and, the approved
drawings listed in the table below unless the prior written approval of the planning
authority is obtained for an amendment to the approved details under Section 64 of
the Town and Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date Received
Location Plan LO_001  09.12.2021
Existing Site Plan PL_100  09.12.2021
Proposed Site Plan GA_100_C C 28.03.2022
Proposed
Elevations
EL_001  09.12.2021
Proposed Floor
Plans
GA_001 B 
Proposed Roof
Plan
GA_102  26.05.2021
Proposed
Drainage Layout
20.0276 – 5000 E 28.03.2022
Proposed Site
Levels & Grading
Layout
20.0276 – 7000 D 28.03.2022
Visibility Splay
Layout
20.0276 – SK01 A 28.03.2022
3D Visualisation SK_01  09.12.2021
ASHP
Specification
MSZ-LN50VG
R/B/V/W 
09.12.2021 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details.  
2. Notwithstanding the provisions of Condition 1, the proposed access shall be formed in
accordance with the Council’s Roads Standard Detail Drawing SD08/004 rev A (min.
access width 5.5m) and visibility splays of 2.5 metres to point X by 75.0 metres to point
Y from the centre line of the proposed access. The access shall be surfaced with a
bound material in accordance with the stated Standard Detail Drawing. Prior to work
starting on site the access hereby approved shall be formed to at least base course
standard and the visibility splays shall be cleared of all obstructions such that nothing
shall disrupt visibility from a point 1.05 metres above the access at point X to a point
0.6 metres above the public road carriageway at point Y. The final wearing surface on
the access shall be completed prior to the development first being brought into use
and the visibility splays shall be maintained clear of all obstructions thereafter. 
Reason: In the interests of road safety.  
3. The parking and turning area shall be laid out and surfaced in accordance with the
details shown on the approved plans prior to the development first being occupied and
shall thereafter be maintained clear of obstruction for the parking and manoeuvring of
vehicles. 
Reason: In the interest of road safety.

Page 11

4. The refuse collection area shall be laid out and surfaced in accordance with the details
shown on the approved plans prior to the development first being occupied and shall
thereafter be maintained as such. 
Reason: In the interest of road safety.  
5. Notwithstanding the provisions of Condition 1, no development shall commence until
details of the intended means of surface water drainage to serve the development
have been submitted to and approved in writing by the Planning Authority. 
The duly approved scheme shall be implemented in full concurrently with the
development that it is intended to serve and shall be operational prior to the
occupation of the development and maintained as such thereafter. 
Reason: To ensure the provision of an adequate surface water drainage system and
to prevent flooding.  
6. No development shall commence until a scheme of boundary treatment, surface
treatment and landscaping has been submitted to and approved in writing by the
Planning Authority. The scheme shall comprise a planting plan and schedule which
shall include details of: 
i) Existing and proposed ground levels in relation to an identified fixed
datum;
ii) Existing landscaping features and vegetation to be retained;
iii) Location design and materials of proposed walls, fences and gates;
iv) Proposed soft and hard landscaping works including the location,
species and size of every tree/shrub to be planted;
v) A programme for the timing, method of implementation, completion and
subsequent on-going maintenance. 
Planting proposals shall include additional hedge planting along the northern boundary
of the site in so far as this might practicably be accommodated on the land available. 
All of the hard and soft landscaping works shall be carried out in accordance with the
approved scheme unless otherwise approved in writing by the Planning Authority. 
Any trees/shrubs which within a period of five years from the completion of the
approved landscaping scheme fail to become established, die, become seriously
diseased, or are removed or damaged shall be replaced in the following planting
season with equivalent numbers, sizes and species as those originally required to be
planted unless otherwise approved in writing by the Planning Authority. 
Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity.  
7. Notwithstanding the effect of Condition 1, no development shall commence until
written details of the type and colour of materials to be used in the construction of
external walls, roofs, windows and doors have been submitted to and approved in
writing by the Planning Authority. The development shall thereafter be completed
using the approved materials or such alternatives as may be agreed in writing with the
Planning Authority. 
Reason: In order to integrate the development into its surroundings.

Page 12

NOTE TO APPLICANT 
 This planning permission will last only for three years from the date of this decision
notice, unless the development has been started within that period [See section 58(1)
of the Town and Country Planning (Scotland) Act 1997 (as amended).] 
 In order to comply with Sections 27A(1)  of the Town and Country Planning (Scotland)
Act 1997, prior to works commencing on site it is the responsibility of the developer to
complete and submit the attached ‘Notice of Initiation of Development’ to the Planning
Authority specifying the date on which the development will start. Failure to comply with
this requirement constitutes a breach of planning control under Section 123(1) of the
Act. 
 In order to comply with Section 27B(1) of the Town and Country Planning (Scotland) Act
1997 it is the responsibility of the developer to submit the attached ‘Notice of Completion’
to the Planning Authority specifying the date upon which the development was
completed. 
Advice from ABC Roads: 
 A Road Opening Permit under the Roads (Scotland) Act 1984 must be obtained from
the Council’s Roads Engineers prior to the formation/alteration of a junction with the
public road. 
 The access shall be constructed and drained to ensure that no surface water is
discharged onto the public road. 
 Existing public road drainage ditch to be cleaned out to establish correct invert level in
preparation for the new filter drain. Filter drain to be installed in existing public road ditch,
along the frontage of the development. 
 Headwalls and inspection chambers to be constructed where required. Details to be
submitted for written approval by Roads & Infrastructure Services, prior to any work
starting on site. 
 Surface water drainage investigation to be carried out to ensure the existing road
drainage system can cope with the surface water drainage proposal. Details to be
submitted for written approval by Roads &Infrastructure Services, prior to any work
starting on site.

Page 13

APPENDIX A – RELATIVE TO APPLICATION NUMBER: 21/01102/PP 
PLANNING LAND USE AND POLICY ASSESSMENT 
A. Settlement Strategy 
The proposal seeks detailed planning permission for a residential development of three
dwellinghouses and two flats. The application site is located within the ‘settlement area’
of the Key Rural Settlement of Ardminish wherein the provisions of policies LDP DM 1,
LDP 8, and SG LDP HOU 1 set out support in principle for development of up to and
including ‘medium scale’ on appropriate sites subject to compliance with all other
relevant provisions of the Development Plan, including the overarching aims of policy
LDP STRAT 1 which are reflected in the assessment below. 
Scales of Housing Development are identified under policy SG LDP HOU 1, within this
context the proposal would fall within the category of ‘small scale’ housing
development. 
Gigha Community Council have raised some concern that the proposed development
will result in the loss of open space that is currently utilised for recreational purposes
in association with an existing equipped play park. It is however highlighted that the
site itself is currently in agricultural use and is not identified in the LDP as either a
formal recreational facility or an Open Space Protection Area that would have afforded
some protection against loss of recreational land to other uses. 
The scale and location of the proposed is considered to be consistent with the
relevant provisions of policies LDP DM 1, LDP 8 and and SG LDP HOU 1. 
B. Location, Nature and Design of Proposed Development 
Policies LDP 9 and SG LDP Sustainable seek an appropriately high standard of design,
and provide guidance on the setting, scale, design and finishes of new development. 
The application site relates to an area of just under 0.3ha located to the immediate
north of the Isle of Gigha Craft Workshops and Gigha Hotel. The land is bounded to
the east by the public road, and to the west by an existing equipped play area and
gently rising agricultural land beyond. The land to the north of the site is also in
agricultural use and will provide an open space buffer of approx. 40m between the
boundary of the proposed development and an existing residential development to the
north (approx. 60m building to building). 
The existing site is an open area of rough grazing bounded by a post and wire fence.
The existing site slopes up gently from its boundary with the public road increasing in
height by between 2.0 and 3.5m across a distance of approx. 55m. An existing field
access crosses the northern part of the development site running east to west with
parallel power lines route. 
The settlement of Ardminish consists of several dispersed clusters of development that
generally occupy the lower lying land adjacent to the public road. Whilst the settlement
is linear in nature it is also punctuated by open green spaces of undeveloped farmland
that help to emphasise the rural nature of the settlement and its surrounds. Previously
great care has been taken to preserve an element of space between the individual
nodes of development and this is evident in particular with the design and layout of the

Page 14

relatively modern Fyne Homes development that was split into two nodes of
development either side of the Gigha Hotel. The current proposal will reinforce the
existing node of development around the Hotel/CraftWorkshop but would still leave a
substantial area of open space between this and existing to the north and as such it is
considered that the development would not be out of character with the existing
settlement pattern. 
The proposed development is shown as a single ‘L-shaped’ footprint with the short
section addressing the public road. The developer has however made considerable
effort to break up the scale and massing of the development and whilst the
development comprises a single block of buildings, visually this is broken down into a
number of distinct elements through the use of stepped floor levels and ridge heights
that makes effective use of existing site topography and will result in a grouping of
buildings that are similar in design, scale, massing and appearance to existing
residential development in the immediate locale. 
The east elevation (road facing frontage) will comprise a two storey element containing
two 1 bedroom flats (Units 4 & 5) with a proposed finished ground floor level of 12.8m
AoD, and an attached 2 bedroom single storey dwelling (Unit 3) with a proposed
finished floor level of 13.3m AoD and lower hipped roof. Units 1 and 2 are attached to
the rear elevation of Unit 3 with the principle elevations (front door) facing north, these
are also two bedroom single storey units but step up the slope with respective finished
floor levels of 14.1m AoD and 13.5m AoD, and staggered roof lines to match. The main
living apartments in Units 1 and 2 are located within the rear of the property to ensure
a south facing aspect. 
Externally it is proposed to finish the buildings in vertical timber cladding, and profile
metal sheet roofing. The proposed materials are generally considered to be
appropriate and compatible with the rural nature of this location however further detail
on the exact specifications to be utilised in external finishes and window/doors should
be secured and subject to further approval by means of planning condition. Air Source
Heat Pumps will also be located externally to the rear of each property. 
The layout of the proposed development will afford an appropriate standard of privacy
and daylight to the occupants of the new properties. The proposal is well removed from
existing residential development and will not give rise to any substantive loss of privacy
or impact upon daylight to the established amenity of those properties. 
The submitted details show the use of hedgerows / post and wire fencing to the north,
east and west boundaries of the development, and use of a 1.2m high timber fence on
the southern boundary adjoining the Craft Workshops. Individual gardens that appear
to be finished in grass and slabbed paths will be provided adjacent to the eastern and
southern elevations of the building. Block paved communal parking and the site access
will be provided to the north. It would be appropriate to secure additional detail of
landscape, boundary and surface treatment by condition, the provision of additional
hedgerow planting along the northern boundary of the development site would also
partially screen and soften the visual impact of the access road and parking area when
viewed from the north. 
Having regard to the above the location, siting, design and finishes of the
proposed development are considered to be consistent with the requirements of
policies LDP 9 and SG LDP Sustainable. 
C. Natural Environment

Page 15

The provisions of policies LDP 3 and SG LDP ENV 1 set out general considerations
for the impact of new development on habitats, species and biodiversity. 
The proposal is not located within any area designated for nature conservation
purposes. The application site relates to an existing area of rough grazing and is
unlikely to give rise to any significant impact through loss of habitat or other impact
upon biodiversity, including any loss of connectivity between green spaces. 
The proposal is considered to be consistent with the relevant provisions of
policy LDP 3 and SG LDP ENV 1. 
D. Built Environment 
There are no built/cultural heritage designations or constraints relating to the
development site itself. 
Policy LDP 3 and SG LDP ENV 16a would seek to resist development that has an
adverse impact upon a listed building or upon the setting of a listed building. 
The Gigha Hotel to the south is a category B listed building; it is however noted that
the proposed development will be located some 50m north of this property on the
opposite side of the Craft Workshop. The proposed development is set back from the
public road and is not considered to have any significant or adverse impact upon the
setting of the listing. 
The proposal is considered to be consistent with policies LDP 3 and SG LDP
ENV 16a. 
E. Access to Countryside. 
The public road forms part of the identified Core Path routes but will not be impacted
by the development. The application site currently contains an existing field access
that provides access to fields further to the west, the submitted details indicate that this
will be retained on its current alignment. 
The proposals also indicate that the development will not impact on pedestrian access
to the existing playpark which will be retained via connection to the Craft Workshop
carpark area. 
The proposal is considered to be consistent with policies LDP 11 and SG LDP
TRAN 1. 
F. Landscape Character 
The development is not located within any formal landscape designations. The
provisions of policies LDP 3 and SG LDP ENV 14 set out that the Council will resist
development where its scale, location or design would have a significant adverse
impact on the character of the landscape. 
The proposed development will be viewed within the context of the existing settlement
area of Ardminish and will be open to view from both the public road and also at
significant distance from the West Kintyre coast. As noted in section B above, the

Page 16

development is considered to be of appropriate location, scale, design and finish to
blend well within the immediate townscape context and its surrounding landscape
setting. 
The proposal is considered to be consistent with policies LDP 3 and SG LDP
ENV 14.   
G. Road Network, Parking and Associated Transport Matters. 
The provisions of policies LDP 11, SG LDP TRAN 4, and SG LDP TRAN 6 seek to
ensure that new development is served by satisfactory access and parking
arrangements. The provisions of policies LDP 10 and SG LDP SERV 5(b) seeks to
ensure that new development includes appropriate provision for the management of
any waste that it will generate. 
The site is currently served by an existing field access which connects to the adopted
public road. The proposed development includes for the formation of a new private
access road and turning area that will be constructed to the south of the existing field
access with provision of a service layby within the public road verge. The proposal
includes for the provision of 10 parking spaces, and for a roadside refuse collection
point. 
The Council’s Roads Officer has not raised objection to the development subject to the
imposition of planning conditions to ensure that the means of access, turning and
parking are delivered to the specification shown and in a timely manner, and to ensure
that surface water drainage is dealt with appropriately to avoid any adverse impact on
road safety. 
The proposal is considered to be consistent with the relevant provisions of
policies LDP 10, LDP 11, SG SERV 5(b), SG LDP TRAN 4, and SG LDP TRAN 6. 
The provisions of proposed LDP2 policies 35, 36 and 39 are also relevant to the
assessment of the current application. These provisions however operate very much
in the same manner as the current LDP and do not give rise to conflict in this instance. 
H. Infrastructure 
Water supply will be by connection to the public water main; Sottish Water have not
raised objection to the proposal and confirmed that capacity is currently available. 
Foul drainage shall be to a new private wastewater treatment system which discharges
to a ground based soakaway within the boundary of the application site. Scottish Water
have confirmed that there is no public sewer within the vicinity of the development to
provide a connection. 
The proposal includes details showing discharge of surface water from the
development to an existing drainage ditch with provision of attenuation to restrict the
outfall. ABC Roads have advised that further investigation is required in relation to the
design of surface water drainage proposals however this can be adequately secured
by planning condition. 
The proposal is considered to be consistent with policies LDP 10, SG LDP SERV
1, SG LDP SERV 2, and SG LDP SERV 6