Appendix 4 
Perth & Kinross Council 
28 February, 2024 
Perth West
Enabling Infrastructure at Perth Eco-Innovation Park
Background paper
Purpose
This paper provides Members with an update on the Perth West development.
To secure future industrial and commercial occupiers at the proposed Perth
EcoInnovation Park (PEIP) investment in enabling infrastructure is required. This
infrastructure will also enable new housing development (including the proposed net
zero carbon Lamberkine Village) and therefore the greater proportion of the enabling
infrastructure costs will be recovered through future developer contributions. The
paper therefore also updates on the funding position and indicative income streams
to offset the estimated expenditure. 
Background information
It is difficult for private developers to raise finance for upfront infrastructure
investment because there is no obvious return to a lender. Such infrastructure is
normally provided by the public sector with a long-term legal obligation on
developers to meet a reasonable and proportionate cost through developer
contributions. Without public intervention at Perth West, the employment land at the
PEIP will not be provided in advance of housing development, weakening Perth’s
competitiveness given the undersupply of available, serviced industrial and
commercial plots. 
Perth West will support the delivery of key Council’s strategies: 
• PKC Corporate Plan: develop a resilient, stronger and greener economy,
tackle climate change and support sustainable places, and tackle poverty. 
• PK Climate Change Strategy and Action Plan: a national net zero exemplar
for decarbonisation of transport and energy.
• Tay Cities Regional Economic Strategy and the emerging Perth and Kinross
Economy Action Plan: create better paid and higher skilled jobs and high
value economic outputs in energy and clean technologies, support an
enterprising mindset.
• Perth City Plan: make Perth a carbon-neutral city by 2040. 
• Perth and Kinross Local Development Plan 2 (LDP2): promote the sustainable
economic growth of the area to the year 2029. 
LDP2 allocated 262.3ha for residential, commercial and community uses at Perth
West (Site MU70). The southern part of Perth West allocation is promoted by the
landowner, the John Dewar Lamberkine Trust (JDLT) (see Appendix 1). Planning

Page 2

Permission in Principle was granted in November 2023 (application reference
20/00667/IPM). It includes 1,500 homes (Lamberkine Village) up to 26ha of
commercial development (PEIP) and other community infrastructure (see Appendix
2).
Because of the short supply of available employment land in the Perth area (and
indeed across the wider Council area), and the need to diversify Perth’s economy,
the strategic rationale is to start with the provision of employment land in advance of
residential development. This requires investment in enabling infrastructure to
access the site and deliver the first phase of the development: Specifically, the
enabling infrastructure will:
• Deliver an underpass under the A9 to access the site and establish active travel
infrastructure from Perth West into Perth City. This will minimise the impact of
traffic generated by the development and support sustainable transport choices. 
• Deliver a commercial business park with of 11ha of serviced employment land
(PEIP Phase 1). 
• Support business growth and create high value jobs in the clean growth sector.
Approximately 1000 jobs could be created when the PEIP is fully developed and
occupied over both phases. 
• Create a national exemplar of net zero carbon development. Phase 1 will
incorporate a smart local energy system, where energy can be generated, stored
and used locally.
A second, longer-term phase will provide up to 15ha of employment land and 500
homes, subject to further private sector infrastructure provision.
Progress 
A Project Board and Project Team have been established and are meeting regularly
to progress several workstreams critical to the development of the site: 
• Now that JDLT has vacant possession of the tenanted farm, land transfer of 11
ha for PEIP Phase 1 and the related road infrastructure is being negotiated with
JDLT.
• Heads of Terms with JDLT for the transfer of PEIP Phase 1 are being drafted.
• In terms of appropriate contributions toward enabling infrastructure delivery costs,
preparatory works to identify a methodology for the apportionment of costs is
underway, and discussions will continue with JDLT to incorporate this into a legal
agreement/contract which will require to be in place before any construction
contract is let.
• A Section 75 agreement (Planning Obligation) has been signed with JDLT
relating to the Planning Permission in Principle (application ref: 20/00667/IPM).
Contributions are agreed for primary education mitigation, land or equivalent
financial sum for healthcare facility, relevant sports and play facilities to serve the
development, contribution toward Transport Scotland’s Broxden Roundabout

Page 3

improvement works, and financial contribution for Perth Transport Futures
Phases 1 and 2.
• A planning consent was issued to JDLT in November 2023.  Detailed planning
applications (Approval of Matters Specified in Conditions) will have to be
submitted before any development can commence.
• A Procurement Strategy was prepared for design work for the underpass and
related works and a contractor selected, but the contract for this early-stage work
cannot be awarded pending the Council’s capital budget consideration.
Financing and Revenue Generation 
Table 1 below shows the estimated costs (derived from cost consultant estimates) for
Phase 1.  For clarity this has been broken down into sections and varying ranges of
Optimism Bias (OB) applied and shown as a percentage. The initial cost estimates
included an OB of 30% given that only outline designs have been prepared, but
those that generally apply to roads infrastructure (23% structures, 15% roads) have
also been included. The selection of OB will depend on how much risk the Council
would be willing to accept. The costs make an assumption on inflation, but do not
include land purchase costs.
The enabling infrastructure could be delivered in sections. Section 1 will only take
the road beyond the underpass and would rely on future developer-led investment to
deliver sections 2 and 3, without any certainty that the employment land would be
provided within a reasonable timeframe.  In addition, there would be no Tay Cities
Deal grant which is attached to embedded smart road infrastructure.  Section 2 will
take the road up to the entrance of PEIP and initial housing development.  Section 3
will platform sites and provide connecting services at the PEIP, allowing site
marketing and occupation.
Table 1: Estimated costs
Section  Cost (£m)
30% OB
Cost (£m)
23% OB
Cost (£m)
15% OB
1 Underpass + Tweed Place Link 18.78 17.77 16.62
2 Underpass + Innovation
Highway Link to PEIP
25.20 23.86 22.31
3 Underpass + Innovation
Highway Link to PEIP +
Platforming + Utilities
32.84 31.35 29.65 
In March 2023 (Report 23/73), the Council approved funding of £10m towards the
cost of delivering the enabling infrastructure for Phase 1 of Perth West development
from the balance of its investment capacity and remitted officers with reflecting the
remaining cost of the enabling infrastructure as part of the development of an
updated Capital funding strategy for consideration in 2024. 
An application to the UK Levelling Up Fund for £10m was submitted at Round 2 but
was unsuccessful, and based on feedback a revised application was under
preparation for Round 3 when Ministers opted not to call for any new or revised

Page 4

applications. The UK Government remains interested in the project but to date has
not offered any alternative grant funding solution. Dialogue continues. 
Table 2 below shows indicative income from developer and occupier contributions,
plot sale receipts and grants to offset the Council’s costs for Phase 1. It is intended
that the contributions from developers and occupiers will be apportioned based on
the use of enabling infrastructure by commercial and residential users. More detailed
work is required to complete this income projection in advance of the capital budget
setting.
Table 2:  Indicative income 
Sources  Income
(£m)
Sale of 90% of employment land (11ha =27 acres) @ £190,000/acre 5
Developers’ contributions from residential use of enabling
infrastructure still to be negotiated but based on development of
1,000 residential units. 
Developers/business occupiers’ contributions from employment use
of enabling infrastructure based on 11 ha.
13
(indicative)
Tay Cities Deal grant towards additional innovative solutions to be
embedded in the enabling infrastructure (Perth Innovation Highway)
5
TOTAL 23 
Receipts of c£5m from sales of serviced employment land have been based on
estimated market prices. There is strong interest from businesses in the transport,
logistics and energy sector to occupy the PEIP and develop innovative uses, for
example Stagecoach is interested in developing a state-of-the-art Electric Vehicle
facility. 
Members need to be aware that contributions from developers/occupiers have still to
be negotiated and are therefore not secured. Work is ongoing to identify potential
target sums for such contributions towards Phase 1. The contributions are focusing
on the development of 1,000 residential units for which a plan has been produced by
JDLT, and 11 ha for PEIP, although the level of contributions will not be agreed
before Council’s meeting on 28 February 2024.  It is also anticipated that a second
planning application, by Muir Homes, will be submitted during 2024 and associated
developer contributions will also be required, potentially spreading the cost between
two private developers rather than solely obligating JDLT. An indicative amount of
£13m has been included in table 2.
However, an estimated £3m of pre-construction expenditure, mostly related to site
investigation and design cannot be commenced because this is not a fully committed
capital project. As it stands even with budget agreement, Phase 1 is unlikely to be
completed before 2028.  
A Tay Cities Deal grant of £5m has been earmarked for Perth Innovation Highway
which is the innovation element of the enabling infrastructure involving the
installation of digital infrastructure and Intelligent Transport Systems to manage
transport in and around the site and the corridor between the site and Perth city

Page 5

centre. A Full Business Case (in preparation) needs to be approved by the Tay Cities
Region Joint Committee mid-2024.

Page 6

Benefits 
Perth West will deliver a new neighbourhood for Perth and is central to meeting the
Council’s housing and employment land supply.  The PEIP has the potential to be a
net zero carbon employment site of national significance in terms of driving regional
productivity and a just transition to net zero.  The benefits include:
• Creation of net zero neighbourhood (Lamberkine Village) supporting a large
portion of Perth’s new housing requirements.
• Enhance sustainable connectivity through walking and cycling and innovation. 
• Generate net zero energy and support decarbonisation including transport. 
• Generate additional tax revenues.
More specifically, the benefits generated by the PEIP would include:
• Increased productivity by increasing employment in high productivity, high skills
and wage sectors. 
• Catalyse further development and private investment in the city. 
• Attract innovative businesses in new clean growth sectors. 
• Diversify Perth’s economy to broaden job opportunities, raise skills levels, and
average earnings. 
Risks
Though a solution is being worked on with the landowners, the Council does not yet
have formal commitment from any developers in terms of contributions, leading to a
potential financial and reputational risk. However, these risks are mitigated in that no
construction contract would be awarded until all legal agreements are in place. 
The Council does not yet have formal commitment from any potential PEIP business
occupiers, leading to a potential financial and reputational risk. The challenge for
businesses is that they cannot commit without certainty of delivery. This conundrum
is the principal driver of market failure in the provision of employment land in many
parts of the country.  
Timetable
An indicative timeline, should the budget be approved by Council in February 2024,
would be: 
• Design Consultant appointed by April 2024
• Infrastructure planning and concept design works commenced by April 2024 
• Planning permission granted by March 2026  
• Contractor in place by March 2027 
• Construction starts by March 2027 
• Main construction completed by December 2028.
It should be noted that there may be an opportunity to accelerate this programme
through early identification of opportunities and collaborative working from all parties
who are engaged to deliver the contract.

Page 7

Appendix 1: Extent of Perth West JDLT area (planning ref: 20/00667/IPM)

Page 8

Appendix 2: Indicative phasing plan and land uses (planning ref: 20/00667/IPM)