Appendix 1 - General Fund Capital Budget 2024-25 – 2027-28

Perth and Kinross Council · 28 February 2024
Back to Perth and Kinross Council — 28 February 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

APPENDIX I
APPENDIX 1(i)
Capital Capital Capital Capital Capital
Resources Resources Resources Resources Resources
2024/25 2025/26 2026/27 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000)
Revised Revised Revised Revised Revised
Budget Budget Budget Budget Budget
Capital Grants
Cycling, Walking & Safer Routes (CWSR) 200 200 200 200 800
Recycling Improvement Fund 0 0 0 0 0
Cross Tay Link Road - Transport Scotland 0 0 0 0 0
Inspiring School Age Childcare Spaces 0 0 0 0 0
General Capital Grant 13,847 12,639 12,150 12,150 50,786
Total Capital Grants 14,047 12,839 12,350 12,350 51,586
General Capital Receipts
General Fund - Capital Receipts 278 694 250 250 1,472
General Fund - Ring Fenced Receipts 352 352 902 1,047 2,653
Total General Capital Receipts 630 1,046 1,152 1,297 4,125
Commercial Property Receipts
Capital Receipts brought-forward 616 1,120 1,550 1,550 616
Commercial Property Capital Receipts 712 430 0 1,088 2,230
Capital Receipts carried-forward (1,120) (1,550) (1,550) (2,638) (2,638)
Total Commercial Property Receipts Applied 208 0 0 0 208
Contributions
Tay Cities Deal 999 550 505 2,946 5,000
Third Party Contributions 658 0 2,000 3,000 5,658
Developer Contributions 2,300 2,367 2,600 2,600 9,867
Revenue Budget Contributions 124 125 125 0 374
Total Contributions 4,081 3,042 5,230 8,546 20,899
Capital Borrowing Requirement 180,129 80,325 54,077 41,385 355,916
TOTAL CAPITAL RESOURCES/
GROSS BUDGET EXPENDITURE 199,095 97,252 72,809 63,578 432,734

Page 2

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF  GROSSCAPITAL EXPENDITURE 2024/25 to 2027/28
APPENDIX I
APPENDIX 1 (ii)
Current Current Current Current Current
Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget
31-Jan-24 31-Jan-24 31-Jan-24 31-Jan-24 31-Jan-24
2024/25 2025/26 2026/27 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000)
EDUCATION AND CHILDREN'S SERVICES
Blairgowrie Recreation Centre - Replacement 13,150 4,003 0 0 17,153
Schools Modernisation Programme
Investment in the Learning Estate 10,388 8,550 8,650 6,823 34,411
Free School Meal Expansion Programme 2,000 0 0 0 2,000
Methven Primary School Refurbishment 140 0 0 0 140
Kirkmichael Primary School Upgrades 32 0 0 0 32
New Primary School at Bertha Park Site 0 500 7,500 15,400 23,400
Technology Upgrades 1,016 250 0 0 1,266
Perth Academy - Refurbishment 2,500 1,650 1,650 0 5,800
Perth Grammar School - Upgrade Programme Phase 3 2,120 1,500 504 0 4,124
Perth High School - New School Investment 31,500 10,600 3,600 0 45,700
Harris Academy/Invergowrie - Extension 150 0 0 0 150
TOTAL: EDUCATION AND CHILDREN'S SERVICES 62,996 27,053 21,904 22,223 134,176
COMMUNITIES
Traffic & Road Safety
Road Safety Initiatives (20mph Zones etc..) 446 362 362 361 1,531
Additional Road Safety - Pedestrian Crossings 175 175 175 0 525
20mph Signage Programme - Schools 119 0 0 0 119
Cycling Walking & Safer Routes (CWSR) 200 200 200 200 800
Car Parking Investment - Pitlochry 150 0 0 0 150
Sub-Total 1,090 737 737 561 3,125
Asset Management - Roads & Lighting
Structural Maintenance 9,498 9,498 9,706 7,500 36,202
Footways 410 370 410 410 1,600
Investment in Local Footpaths 0 100 100 0 200
Sub-Total 9,908 9,968 10,216 7,910 38,002
Asset Management - Bridges
Bridge Refurbishment Programme 2,458 1,914 2,213 2,897 9,482
Vehicular Bridge Parapets Programme - Assess & Upgrade 29 0 0 0 29
Old Perth Bridge - Strengthening 10 2,369 0 0 2,379
Perth Queens Bridge - Strengthening 60 70 2,153 0 2,283
Garry Viaduct 300 300 1,900 1,790 4,290
Sub-Total 2,857 4,653 6,266 4,687 18,463
Improvement Schemes
Cross Tay Link Road (CTLR) 26,213 0 0 0 26,213
A977 Upgrades 190 0 0 0 190
Sub-Total 26,403 0 0 0 26,403
Rural Flood Protection Schemes
Comrie Flood Protection Scheme 16,841 0 0 0 16,841
Milnathort Flood Protection Scheme 1,590 0 0 0 1,590
South Kinross Flood Protection Scheme 1,168 1,787 0 0 2,955
Scone Flood Protection Scheme 76 601 0 0 677
Sub-Total 19,675 2,388 0 0 22,063
Perth & Kinross Place-making
Perth & Kinross Lighting Action Plan 677 0 0 0 677
Sub-Total 677 0 0 0 677
Other Planning Projects
Perth Eco-Innovation Park at Perth West 23,800 9,017 0 0 32,817
Sub-Total 23,800 9,017 0 0 32,817
City Centre Developments
PH2O 30,000 25,000 20,000 15,000 90,000
Sub-Total 30,000 25,000 20,000 15,000 90,000

Page 3

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF  GROSSCAPITAL EXPENDITURE 2024/25 to 2027/28
APPENDIX I
Current Current Current Current Current
Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget
31-Jan-24 31-Jan-24 31-Jan-24 31-Jan-24 31-Jan-24
2024/25 2025/26 2026/27 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000)
Community Greenspace
Play Areas - Improvements Implementation Strategy 963 611 150 150 1,874
3G Pitch, Blairgowrie 117 0 0 0 117
Settlement/Neighbourhood Parks 379 0 0 0 379
Countryside Sites 139 0 0 0 139
Community Greenspace Sites 627 682 682 678 2,669
Community Greenspace Bridges 31 0 0 0 31
Cemetery Extensions 60 229 225 375 889
Sub-Total 2,316 1,522 1,057 1,203 6,098
Support Services
PC Replacement & IT Upgrades
Hardware 15 15 14 14 58
Licenses 112 95 71 71 349
Sub-Total 127 110 85 85 407
Commercial Property Investment Programme
Broxden Drainage Mitigation Works 866 0 0 0 866
Sub-Total 866 0 0 0 866
Prudential Borrowing Projects
Wheeled Bin Replacement Programme - Domestic Bins 200 200 200 200 800
Wheeled Bin Replacement Programme - Commercial Bins 20 20 20 20 80
Recycling Containers, Oil Banks & Battery Banks Replacement Programme80 65 65 65 275
Litter Bins 50 50 50 50 200
Vehicle Replacement Programme 2,800 2,800 2,800 2,500 10,900
Street Lighting Renewal - LED & Column Replacement 888 825 541 592 2,846
Land Purchase & Development (Hotel Development) 950 950 0 0 1,900
Sub Total 4,988 4,910 3,676 3,427 17,001
Housing Projects
New Gypsy Traveller Site 0 1,990 0 0 1,990
Sub Total 0 1,990 0 0 1,990
TOTAL: COMMUNITIES 122,707 60,295 42,037 32,873 257,912
Health & Social Care
Occupational Therapy Equipment 250 250 250 250 1,000
Technology Enabled Telecare 1,537 1,000 1,000 1,000 4,537
Moving & Handling Office Refurbishment 29 0 0 0 29
Software Licences 53 53 53 69 228
Developing Supported Tenancies 229 0 0 0 229
TOTAL: HEALTH & SOCIAL CARE 2,098 1,303 1,303 1,319 6,023
CORPORATE AND DEMOCRATIC SERVICES
Property Services
DDA Adaptation & Alteration Works Programme 200 200 200 200 800
Property Compliance Works Programme 400 650 650 650 2,350
Capital Improvement Projects Programme 1,800 1,800 1,800 894 6,294
Decarbonisation - Prudential Borrowing Programme (PB) 1,300 0 0 0 1,300
Energy Conservation & Carbon Reduction Programme (PB) 150 150 150 150 600
Information Systems & Technology
ICT Infrastructure Replacement and Upgrade Programme 4,207 4,079 3,017 2,903 14,206
Data & Analytics 839 738 761 784 3,122
Supporting Digital 855 878 901 926 3,560
Software Licences (Revenues & Benefits) 51 51 51 51 204
School Audio-Visual (AV) Equipment Replacement Programme 173 35 35 605 848
Mosaic - Swift Social Work System Replacement 1,319 20 0 0 1,339
TOTAL: CORPORATE AND DEMOCRATIC SERVICES 11,294 8,601 7,565 7,163 34,623
TOTAL COMPOSITE GROSS EXPENDITURE 199,095 97,252 72,809 63,578 432,734