Climate Change Annual Report
YEAR 2
PERTH AND KINROSS COUNCIL
Appendix A

Page 2

APPENDIX A                                           
Introduction
The extreme weather events of 2023 have further highlighted
this year the urgency for all to play their part in addressing
climate change and building resilience to the climatic changes
already upon us.  The cost-of-living crises experienced by so
many of our residents and businesses has highlighted the need
to deliver solutions that address these twin crises. 
Perth and Kinross Council (PKC) in December 2022
recognised ‘Tackling climate change and supporting
sustainable places’ a one of the key corporate priorities
identified in the new Corporate Plan.  This further strengthens
PKC’s commitment to addressing the climate and ecological
emergency, as outlined in its Climate Change Strategy and
Action Plan (CCSAP).
The CCSAP was unanimously approved in December 2021
and then updated as part of the annual reporting process in
November 2022. This report provides the update on PKC’s
climate action, covering the second year of delivery, from
October 2022 – September 2023.
It highlights the commitment to climate change and good
progress the Council has made in the second year of delivery
of the Strategy and Action Plan to lay down the foundations
through the development of crucial strategies, organisational
development and the implementation of specific solutions. 
It also recognises that while the area carbon emissions are
positively lower than 2019 levels, the value is 10% higher than
what is required to be on trajectory for the 2030 target and not
in compliance with the 2021 target. There are therefore many
challenges to overcome and to meet our statutory targets and
organisational commitments. There needs to be an increase in
pace and scale of action next year and years going forward
from individuals, communities, businesses, private and public
organisations all working together.  
The CCSAP is divided into long-term objectives, Council
Commitments and eight thematic plans. 
Progress
The Council has made noticeable progress this year against all
six of our overarching objectives and 36 Commitments, the
highlights of which are shown in Figure 1. 
Our performance data has highlighted that progress is made,
there is the need for all to accelerate the pace of action to
remain aligned to the Paris Agreement and the Scottish
Government targets. 
Action Plans
An action plan split into eight key climate action sectors
updated annually
Council Commitments
27 commitments by the Council necessary to achieve the
outcomes
Long-term Outcomes
6 overarching objectives

Page 3

APPENDIX A                                           
Perth and Kinross Council’s Climate change strategy 
1. Achieving Net
Zero aligned with
the Paris Agreement
and the Scottish
Government
Targets, with the
ambition of
achieving them
sooner. 
2. Building a more
resilient Perth and
Kinross 
3. Delivering a fair
transition and a
green recovery 
4. Preventing an
ecological
emergency and
enhancing
biodiversity 
5. Engaging and
empowering our
children and young
people 
6. Empowering our
communities in line
with the Perth and
Kinross Offer 
• Decarbonising our
operations 
• Aligning our
investments 
• Allocating
appropriate capital
and revenue
funding 
• Delivering on our
priority themes 
• Continuing to
develop our base
evidence 
• Reviewing our
climate change
plan annually 
• Demonstrating our
collaborative
working 
• Mainstreaming
climate resilience
into asset reviews 
• Managing climate
change risks
proactively 
• Assessing and
reviewing the
strategic climate risk
assessment 
• Continuing to raise
awareness with
communities 
• Promoting land use
practices that
contribute to natural
flood management 
• Taking action to
reduce fuel, food
and transport
poverty 
• Ensuring climate
action addresses
rural and urban
climate
challenges 
• Improving the
energy efficiency
of social housing 
• Working with
businesses to
identify and
address skills
shortages to
support the green
economy 
• Declaring an
ecological
emergency, as well
as a climate one, and
sign the Edinburgh
Declaration 
• Accelerating PKC
biodiversity
strategies and
actions to keep pace
with the UK and
Scottish Government
Biodiversity
Strategies and Action
Plans 
• Strengthening our
capacity to
implement nature-
based solutions 
• Monitoring  the
impact of a changing
climate on our
ecosystems and take
appropriate action 
• Listening to our
young people,
encouraging them to
have their say and
acting on their views,
ideas and priorities 
• Continuing to ensure
the curriculum
supports learning
about climate change 
• Leading by example
through, minimising
emissions through
best practice in
energy, waste and
transport 
• Utilising school
grounds to promote
biodiversity, food
growing and healthy
eating 
• Working in
partnership with
our residents,
businesses and
community
partners to
support them to
make
transformational
change 
• Acting as an
enabler for
community-based
climate change 
• Providing and
signposting our
communities to
trusted sources of
advice and
funding 
Overarching
Objectives
Council Commitments
Figure 1: Objectives and commitments

Page 4

APPENDIX A                                           
Overall Highlights on achieving objectives 
1. Achieving Net Zero aligned with the Paris Agreement
and the Scottish Government Targets, with the ambition of
achieving them sooner. 
• Achieving a 14% year-on-year emissions reductions for the
Council’s non-domestic estate. (Buildings & Energy)
• Developing decarbonisation strategies including our Local
Heat and Energy Efficiency Strategy and EV Charging
Strategy. (Buildings & Energy)
• Opening Riverside Primary School – Perth and Kinross’s
first Passivhaus Primary School, which will save an
estimated 71 tCO2e per annum (Buildings & Energy)
• Delivering the £2.7M Recycling Improvement Fund to
include City Centre food recycling to 1000 properties and
introduction of a twin-stream recycling service across Perth
and Kinross (Waste and Circular Economy)
2. Building a more resilient Perth and Kinross
• Undertaking a comprehensive Climate Change Risk and
Opportunity Assessment that looks at risks and
opportunities to both Perth & Kinross and PKC operations.
(Resilience) 
• Approval of 2 Flood Risk Management projects by the
Council in December 2022. (Resilience)
• Working with community groups and volunteers on our
award-nominated Ponds for Puddocks project (Resilience) 
3. Delivering a fair transition and a green recovery
• Expanding provision of home energy advice services with
our partners the HEAT Project and SCARF to over 880
households this year and supporting numerous others to
access funding sources. (Buildings & Energy)
• Green Business Grants - 24 businesses have been paid a
total of £439,847.61 from the Capital Green Recovery
Grant scheme (Business & Industry);
• Running the Keep Cosy this Winter campaign in Winter
2022/23 focused on promoting energy savings tips and
resources.  
4. Preventing an ecological emergency and enhancing
biodiversity 
• Working with the Scottish Invasive Species Initiatives and
over 30 community volunteers to develop and deliver a
comprehensive Invasive and Non-Native Species Initiative
for the River Almond Catchment (Land Use)
• Supporting Blairgowrie to become Scotland’s first
Biodiversity Town. (Land Use)
• Declaring of a climate and biodiversity emergency in
November 2022. (Governance)

Page 5

APPENDIX A                                           
5. Engaging and empowering our children and young
people 
• Hosting a successful second annual Youth Climate
Conference in October 2023 (Education & Engagement). 
• Energy Sparks – Working with 12 PKC schools on reducing
their energy consumption using an engaging platform
(Education & Engagement)
• Developing a Climate Action Plan template and guidance
for schools to develop their own action plans for students,
teachers and staff (Education & Engagement)
6. Empowering our communities in line with the Perth and
Kinross Offer
• Successful completion of an IUK funded Dialogue to
Accelerate the Net Zero Transition Project in Tulloch,
Aberfeldy and Blairgowrie & Rattray (Education &
Engagement)
• Continuation of comms and social media with over 90,000
views across our PKClimateAction Webpage and Social
Media sites (Education & Engagement)
• Targeted engagement with 165 businesses identified as
having heat and power demand above 0.5Mwh and/or as
large employers. (Business & Industry)
• Council’s officers’ engagement in working groups, along
with specific community activities such as Biodiversity
Ambassadors

Page 6

APPENDIX A                                           
Challenges and barriers 
Specific challenges and barriers for each theme of the action
plan, but there are several common challenges and barriers
• To identify and unlock funding opportunities to ensure
future targets are achieved
• Resource and skills gap within the Council and supply
chain to be able to scale up at pace to meet Net Zero
targets
• Challenges in recruiting and retaining internal staff with
the required skills, knowledge and experience
• Limits to emissions that are under the direct control of
the Council
• Need to accelerate the pace of action  
Performance 
The Council has developed eight thematic action plans with
176 overall actions.  In 2022, the Council agreed 25 priority
actions focused on the most important actions for achieving
area-wide emissions reduction, Council emissions reduction
and building resilience. 
Progress has been made for all 25 actions.   
Table 1 2023 KPI Data 
KPI  Target 
Current
value
%
change
over
previous
year
Comment on
performance 
Perth and Kinross
Area-wide territorial
greenhouse gas
emissions (kt CO2e) 
75% reduction on
1990 levels by
2030 and zero net
emissions by
2045.  
1306.1
(2021) +7.6%
Increase in comparison
to artificially low
emissions in 2020
(1213.6) – decrease
with respect to 2019 
Perth and Kinross
Area-wide territorial
greenhouse gas per
Capita emissions (t
CO2e) 
75% reduction on
1990 levels by
2030 and zero net
emissions by
2045.  
8.5
(2021) +6.2% 
As above 2020 (8) 
Perth and Kinross
Area-wide CO2
emissions (kt CO2e) 
376kt CO2e by
2030 (75%
reduction on 1990
levels) 
731
(2021) +13.7% 
As above 2020 (643) 
Perth and Kinross
Council Scope 1,2,
and 3 emissions (t
CO2e)  Net zero by 2045 
39,798
(2022/23) +10.5%
Increase due to
inclusion of additional
Scope 3 category. 4.5%
decrease when
comparing like-for-like
emissions. 21/22
(36,008) 
Carbon Disclosure
Project (City Score)  ‘A’ by 2024  B Better
C in 2021 
% of Climate
Change Indicators
showing positive
change*  100%  46% N/A
Without including the
KPIs related to the 2021
BEIS data this increase
to 55% 
Climate Change
Grant Funding
secured (£k)
No target set
£1,768,10
2
(2022/23) +174%
Excludes Flooding
grants from the SG and
large capital building
grants. 21/22 (646K) 
* Due to many KPIs being new in 2022, this KPI only has only been calculated
from 2023 onwards

Page 7

APPENDIX A                                           
Perth and Kinross Area-wide territorial greenhouse
gas emissions (ktCO2e) 
Figure  shows territorial emissions by sectors with Transport
and Agriculture sectors as the largest emitters. 
Figure 1 GHG Territorial Emissions for Perth and Kinross, BEIS 20231 
Figure 2 shows recorded greenhouse gas emissions between
2005 and 2021. This shows that as expected after the transport
emission reductions observed in 2020, that there was a year-
on-year emissions increase, primarily associated with
Transport emissions. 
1 Note: as the Scottish government has not yet released the Perth
and Kinross 1990 baseline for either the full suite of GHGs or CO2, a
Perth and Kinross target figure for 2030 has been estimated for these
two indicators assuming Perth and Kinross followed the Scottish
trends1 between 1990 and 2005 when data first became
available.  Data is released by BEIS approximately 18 months after
year end, so 2021 is the most recent data available. 
While emissions in 2021 had decreased from the pre-Covid
2019 level, the decrease was not sufficient to match the
estimated trajectory needed to reach the Scottish Government
target of 75% reduction by 2030.  Currently the GHG emissions
in Perth and Kinross are 19% higher than a trajectory aligned
to Scottish Government targets. It is important to note that as
the Council’s climate change action plan was approved in
December 2021, any changes in performance associated with
this plan are yet to be reflected in the data. 
Figure 2 GHG Territorial Emissions for Perth and Kinross, BEIS 20232 
2 Note: as the Scottish government has not yet released the Perth
and Kinross 1990 baseline for either the full suite of GHGs or CO2, a
Perth and Kinross target figure for 2030 has been estimated for these
two indicators assuming Perth and Kinross followed the Scottish
trends2 between 1990 and 2005 when data first became
available.   Data is released by BEIS approximately 18 months after
year end, so 2021 is the most recent data available.

Page 8

APPENDIX A                                           
Perth and Kinross Area-wide territorial greenhouse
gas per Capita emissions (tCO2e) 
As shown in Figure , since 2005, per capita greenhouse gas
emissions in Perth and Kinross have steadily reduced until the
increase in 2021, following the trend for Scotland but have
continued to remain higher than the Scottish average as would
be expected for a local authority with a more rural population. 
The year-on-year increase shown this year is the reflection of
recovery from artificial Covid-related emissions reductions from
2020 and shows a decrease from 2019 emissions albeit not on
trajectory.     
Figure 3 Per Capita GHG Emissions (BEIS, 2023) 
Perth and Kinross Area-wide CO2 emissions
(ktCO2e) 
Figure  shows a steady reduction in recorded CO2 emissions
from 2005 until 2020. It shows that while there was a steady
downwards trend, only the significant Covid related emissions
reductions in 2020 brought the emissions down to a level that
complies with the Scottish Government’s interim emission
target for 2020 of 56%. The 2021 data, however, shows a
13.7% increase from 2020 levels.   While this is positively lower
than 2019 levels, the value is 10% higher than what is required
to be on trajectory for the 2030 target and not in compliance
with the 2021 target.  
Figure 4 Perth and Kinross CO2 emissions (BEIS,2023) 
0
2
4
6
8
10
12
14
16
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
tCO2e
Per Capita Perth and Kinross territorial
greenhouse gas emissions tCO2e
Perth and Kinross Scotland

Page 9

APPENDIX A                                           
Perth and Kinross Council Scope 1,2, and 3
emissions (tCO2e) 
Since 2015/16, the Council has reported its Scope 1, 2 and 3
emissions as part of the statutory Public Bodies Climate
Change Duties Compliance Reporting process. 
Scope 1 emissions are direct emissions from sources owned or
controlled by the Council - e.g. emissions from fleet or oil-fired
boilers. 
Scope 2 emissions are from the generation of purchased
electricity. 
Scope 3 emissions are all other indirect emissions which relate
to the Council’s activities, including waste, homeworking, staff
travel to/from work. 
Due to an increase in Scope 3 data able to be reported, it is
difficult to compare year-on-year total footprint.  As can be
seen in Figure , in 2022/23 a carbon footprint of 39,798 tCO2e
was recorded. This shows a 2.8% increase on the 2015/16
baseline and 4% year-on-year increase. This associated with
the addition of the Scope 3 staff commuting emissions for the
first time. A staff travel and homeworking survey was used to
estimate the carbon footprint of Council staff travelling to/from
work was 5,369 tCO2e (13.5%). Without the inclusion of these
emissions, the Council’s footprint would total to 34,429 tCO2e,
a 11% decrease from the 2014/15 baseline and a 4.5% year-
on-year decrease. Further progress will be required to meet our
Statutory targets. 
Figure 5 Perth and Kinross Council Combined Scope 1,2 and 3 emissions  
Carbon Disclosure Project (CDP) City Score 
The CDP City Score is an independently audited assessment
of climate action progress  to assist organisations in measuring
and managing their risks and opportunities on climate change.
In 2022, Perth and Kinross Council was assessed as having a
city score of ‘B – Management level’. This shows improvement
on the previous year (C) and indicates the Council has begun
to manage the impacts of climate change across Perth and
Kinross while it also begins to undertake work to understand
how to best adapt to these impacts. 
0
10,000
20,000
30,000
40,000
50,000
Perth & Kinross Council Scope 1, 2 and 3
emissions (tCO2e)
Scope 1 Scope 2 Scope 3

Page 10

APPENDIX A                                           
% of Climate Change Indicators showing positive
change 
46% of the Climate Change indicators show positive change. It
should be noted, however, that due to the data delay for a
number of indicators, some of the data being reported on is still
related to pre-Strategy performance.  If these indicators were to
be removed, the value would increase to 55%.  As this year is
the first year data is available for a number of the Council’s
Climate Change indicators, this percentage figure only relates
to the indicators where past data is available for comparison. 
Climate Change Grant Funding secured (£k) 
In 2022/23 the Council secured £1,748,000 of Climate Change
related grant funding. This is a significant increase on the
£646k in 2021/22. There is significant grant funding available
and further efforts are being made to increase this amount and
meet our aspirations.

Page 11

APPENDIX A                                           
Theme 1 Transport
Transport work progressed the actions against all key areas in
the Climate Action Plan. These include:
• Increase active transport across Perth and Kinross
• Accelerate the EV transition
• Reduce vehicles in town centres
• Improve public transport provision. 
Highlights
Highlights this year are set out in table 2 and include:
• Supporting Greener Glenfarg develop a successful and
transformative community run minibus scheme and
helping pilot an expansion of community bus services in
Highland Perthshire.
• Development and approval of a Perth & Kinross-wide
EV charging expansion strategy that has currently been
submitted to the Scottish Government for funding.
• Development of the Main Issues Report for the Perth &
Kinross Mobility Strategy and progress developing the
draft Strategy.
• Anti-idling enforcement and an associated public
awareness campaign was launched to help reduce both
vehicle emissions and improve air quality. 
Action  Action RAG
Status
Comments
T1 Develop
comprehensive
Mobility
Strategy for
Perth and
Kinross
G Work ongoing, main issues and objectives
being developed alongside draft Strategic
Action Plan. Estimated date to Council
Committee early 2024. Work being done in
collaboration with Regional Transport
Partnership. 
T18 Development of
Park and Ride
sites
A Discussions ongoing with Developers at
West Kinfauns and Bertha Park. Parka and
Ride at Bertha Park may be incorporated as
part of the wider Perth Transport Futures
Phase 3 work. 
T7 Develop a
strategy for the
expansion of
EV charging
infrastructure 
Complete Strategy and Action Plan are now
developed. Working in collaboration with
Scottish Futures Trust and bid submitted to
the Electric Vehicle Infrastructure Fund. Key
element of work is the role of the Private
Sector and provision of EV infrastructure in
residential areas. Additional £250k allocated
in 2023/24 council budget to accelerate
short term roll out in rural areas. 
T10 Develop and
implement a
strategy to
transform the
Council’s fleet
to electric and
alternative fuel
vehicles
A Council have been purchasing EV vehicles
when funding is available. There still
remains a lack of infrastructure so internal
combustion engine vehicles remain still in
use. Work has commenced with Urban
Foresight to set out the future vision for the
Council fleet. The Council is also working
with TACTRAN about HGV fleet transition to
hydrogen and total cost of ownership. 
Table 2: Key transport actions from 2023

Page 12

APPENDIX A                                           
Delivery 
Review of progress of Top Priority Actions:
Delivery challenges
• Grid capacity and the timeframe for required upgrades
and connections is a limiting factor for EV expansions;
• Timescales for getting funding agreed and released,
along with getting multi-year funding
agreements arranged to be able to progress projects and
appropriately resource them, which increases reliance on
external consultants.
Delivery opportunities
• Significant increase in sustainable and active travel
funding available from Transport Scotland and Sustrans
over the near-term future.
• Continued partnership working across the TACTRAN
region to maximise available resources
• Linking transport choices, climate, safety and health
and equity
Outcomes
Positive outcomes as a result of Priority Actions:
• Clear strategic priorities being developed and appraised
using an evidence-based approach. 
• Increased utilisation of EV infrastructure supporting the
rising ownership and usage rates of low carbon
vehicles. 
Progress against Statutory Targets
There are several statutory targets in relation to the
decarbonisation of the Transportation sector as follows. 
I. Transport Sector emissions reduced by 75% by 2030:
Status: Off-track - 16% reduction in emissions between
2005 and 2021 
II. 20% reduction in vehicle kilometres required across
Scotland by 2030 compared to 2019 levels: 
Status: On-track - 9% reduction in car kilometres
between 2019 and 2022/23 (important to note that large
part of period referenced was during Covid restrictions)
III. Decarbonisation of public sector fleets (no new ICE light
fleet by 2025, heavy fleet by 2030): 
Status: On-track – while there has been negative
performance this year, the Council has plans for full
implementation ahead of the 2025 deadline. 
IV. Establish Low Emission Zones (LEZ) to transform
towns and cities into cleaner, healthier places, to live,
work and visit by 2023 
Status: On-track – no longer applicable due to the
improvements in air quality in the Council’s two Air
Quality Management Areas, which has meant that they
are now below the threshold where an LEZ is required.
However, improvements are still required.

Page 13

APPENDIX A                                           
Key Performance Indicators 
Table 3 2023 KPI data
KPI Previous
Value
Current
Value
Target
Transport
emissions CO2
(kt CO2e) 
468  508.6
75% reduction in Transport
emissions by 2030
% Journeys to
school by active
transport 
50.3% 49.8% To be set as part of the P&K
Mobility Strategy (under
development) 
% Journeys to
work by
sustainable
mode of
transport
27% 20% To be set as part of the P&K
Mobility Strategy (under
development)
Total car kms
(millions)
1477.3 1718.6 20% reduction on 2019 levels
by 2030 – 2095 million km 
Public EV
charging
devices per
100,000
population
88.2 125.5 To be set as part of the P&K
Mobility Strategy (under
development)
Council fleet
vehicles that are
zero direct-
carbon 
5% 4% 100% new light fleet from
2025 and heavy fleet from
2030 
Focus for upcoming year
The focus for the upcoming year is to continue to deliver the
actions in the plan. The priority actions for next year include: 
• Continued roll out of public EV infrastructure
• Accelerating the design and implementation of active
and sustainable travel options
• Public consultation and adoption of new mobility
strategy and strategic action plan for Perth & Kinross
• Increased communications on behaviour change on
travel

Page 14

APPENDIX A                                           
Theme 2 – Buildings and Energy 
The Buildings and Energy work of the Climate Change Strategy
and Action Plan has been progressing in relation to the
following categories:
• Non-domestic Perth & Kinross Council properties
• Non-domestic Perth and Kinross area properties
• Domestic Perth & Kinross Council properties
• Domestic Perth and Kinross area properties (non-
Council)
• LHEES development
It is important to note that a ‘Fabric first’ approach (ie reducing
buildings heat loss) should always will be used. 
Highlights
While good progress has been made across the theme, a few
highlights of the year include: 
• Supporting over 880 households with free home energy
and extending this provision of this with SCARF and the
HEAT Project to the end of March 2024 for energy
efficiency advice and support for tenants and residents,
and for support in delivery of programmes relating to
HEEPS-ABS and ECO4.
• Progressing with consultancy work as part of the
Council’s Local Heat & Energy Efficiency Strategy
(LHEES) which also allows for more detailed planning
for decarbonising the Council’s Non-Domestic &
Domestic estate.
• Achieving a 14% reduction in the Scope 1 and 2
emissions in the Council’s Non-Domestic estate
between Apr 22 and Mar 23. In March 23, PKC
allocated an additional £2M of capital funding to further
accelerate the decarbonisation of our non-domestic
estate. 
• Completion and occupation of Perth and Kinross
Council’s (and Scotland’s) first certified Passivhaus
primary school - Riverside Primary School in North
Muirton, Perth which will save an estimated 71 tCO2e
per annum which equates to an annual reduction of
more than 50% from the previous gas heated facilities
and designed to meet the energy target of 67
kWh/sqm/pa for core use. Work has also started on the
replacement Perth High School, also being build to
Passivhaus standards. 
Figure 6 New Riverside Primary School

Page 15

APPENDIX A                                           
Delivery
The Buildings and Energy Action Plan contains 23 actions – 3
are Complete or Green Status, 14 are Amber status indicating
delayed progress and 6 are classified as Red.  
Review of progress of Top Priority Actions:
The top 25 Climate Action Plan Actions were agreed by
Members as part of the Year 1 review process.  Of these, 6 of
them are within the Buildings & Energy Theme, the progress of
which is shown in table 4 below.
Table 4 Progress of Top Priority Buildings and Industry Actions
Action
Number
Action RAG
Status
Comments
B1 Develop and deliver the Local Heat and
Energy Efficiency Strategy (LHEES)
G Work being undertaken by the team and ARUP to meet statutory
requirements by December 2023 outlined in LHEES guidance (draft).
B2 Develop and deliver a programme to ensure
all existing Council houses are brought up
to EPC B by 2032
A On-going consultancy work with ARUP as part of LHEES obligation
develop an estate decarbonisation plan for both Domestic and Non-
domestic estates.  On-track to be completed by March 2024.   
Work to improve EPC levels in existing Housing stock - being tackled
from a variety of different angles, with a priority on getting Band E &F
Properties up to at least the required Band D. 
B11 Develop options, costs and funding
avenues for PKC Estate Portfolios to reduce
greenhouse gas emissions
A As per B2   
B12 All non - domestic buildings considered for
refurbishment must have improved energy
efficiency and performance, adopting the
'fabric first' approach and incorporating non-
direct emissions heat sources 
R Being considered as part of LHEES and estate wide decarbonisation
project.
B13 Develop and invest in local district
heat/communal heat/electricity networks
where viable which use alternative non-
direct emissions heat sources 
A Feasibility study for Perth City Centre completed. PKC duties under the
Scottish Government Heat Network Regulations and associated
Building Assessment Reports (BAR) on-going.   
B21 Replace all Oil-fired heating systems with
non- direct emissions heat source 
R Initial projects being undertaken using £2M of internal funding for estate
decarbonisation. All remaining sites require additional funding to meet
targets.

Page 16

Delivery challenges for both Domestic and Non-
Domestic buildings
• To identify and unlock funding opportunities to ensure
future targets are achieved.
• Resource and skills gap within the supply chain to be
able to scale up at pace to meet Net Zero targets.
• Challenges in recruiting and retaining internal staff with
the required skills, knowledge and experience.
Opportunities
• Future funding opportunities through grant funding as
part of “Public Sector Heat Decarbonisation Fund” for
Non – Domestic buildings.  A total of £20M is available
across the entire fund for all Public Sector bodies and
Local Authorities.
• Power Circle/CAN DO Innovation Green Heat Feasibility
to be explored. 
• Exploring possible pilot projects with IRT thermal
imaging and DReam retrofitting carbon reduction
software.
• Consideration of possible solutions utilising private
funding opportunities.  
Outcomes
The following positive outcomes as a result of Priority Actions
include:
• Significantly reduced Scope 1 and 2 emissions within
the Non-Domestic PKC estate, including optimising use
of Building Management Systems
• HEEPS-ABS grant funding award received from
Scottish Government for 2023/24 for Domestic privately
owned properties.
• Reduction in number of PKC Domestic properties at
EPC Bands E and F.  
Progress against statutory targets and key KPI’s 
I. 68% reduction in emissions from buildings by 2030 with
respect to 2020 levels: on-track 13.4% reduction in
2022/23 from 2021/22
II. Decarbonisation of the Public Sector Estate by 2038:
off-track 11.9% increase in 2021 from 2020 levels 
III. Social housing to be EPC D by 2026 and EPC B by
2032: on-track 8.2% increase in 2023/24 from 2022/23
IV. Development of Local Heat & Energy Efficiency
Strategies (Strategy & Delivery Plan) by end of 2023:
on-track, baseline report and consultation complete by
October 2023. Final Strategy & Delivery Plan to be
presented to Council in November.

Page 17

APPENDIX A                                           
Key Performance Indicators
KPI Previous
Value
Current
Value
Target
Total area-wide carbon
dioxide ktCO2 
emissions from
domestic sources
252.6  265.9
(2021) 
Estimated 115 ktCO2
based on 75% reduction
in domestic emissions
by 2030 in relation to
1990 levels.
Scope 1 and 2
emissions from
Council Estate (tonnes
CO2)
10,658  9,226 Annual emissions of
4,396 tonnes CO2 by
2030
Heating oil
consumption in PKC
non-domestic estate
(kWh)
2,164,774  1,943,066 All sites with oil as a
heat source to be
removed by 2030
Renewable energy
generated across the
PKC estate, including
from Low Carbon Heat
Sources (MWh)
2534  2226 Renewable energy shall
be installed where
feasible to maximise
production
% of Council housing
meeting the Energy
Efficient Standard 2 for
social housing
(minimum EPC B)
6.1%  6.6% EESSH2 standards of
100% of Council
Housing to meet EPC B
by 2032
Number of P&K
households provided
with energy efficiency
and/or low carbon
heating advice (PKC
funded)
424  884 2022/23 - 500 
3 The Heat Networks (Heat Network Zones and Building Assessment
Reports) (Scotland) Regulations 2023
Focus for upcoming year
The focus for the upcoming year is to continue to deliver the
actions in the plan including completion of the following: 
• LHEES and associated delivery plan, and transition to
focusing on plan implementation;
• Provided a detailed and costed decarbonisation plan for
the Council’s Domestic and Non-Domestic Estate.
• Work toward targets indicated in aforementioned
Corporate Key Performance Indicators (KPI).
• Comply with Heat Network Regulations3 and identify
areas suitable for the development of heat networks,
designating heat network zones (HNZ) where
favourable. 
• Undertake statutory duty in relation to public sector Non-
Domestic buildings and the compilation of Building
Assessment Reports (BAR) in accordance with Heat
Network Regulations. 
• Increased communications on behaviour change by all
on heat and energy. 
Table 5: 2023 KPI data

Page 18

APPENDIX A                                           
Theme 3 - Business and Industry 
Building and industry work progressed the actions against all
key areas in the Climate Action Plan. These include:
• Data & Strategic targeting
• Engagement, empowerment, and awareness
• Strategic Actions
• Measuring performance
Highlights 
• Data, business & intelligence and strategic engagement
has improved. Approximately 165 businesses have
been identified as having heat and power demand
above 0.5Mwh and/or as large employers.
Communication has targeted these businesses to build
and strengthen engagement. This contributes to the
Council’s business relationship management. 
• Progress has been made in developing Perth Eco-
Innovation Park – PKC has agreed its inclusion in the
Capital Programme and borrowing capacity of £10m has
been agreed. The Outline Business Case has been
revised to secure Tay Cities Deal funding. There is a
new dedicated Project Board to help increase pace of
delivery going forward. 
• A Smart Local Energy Systems investment decision toolkit
to develop business cases for private/public projects has
been developed and is currently being disseminated.
• Improved integration with other themes: Circular
Economy, Food waste Strategy (Waste), Mobility
Strategy and strategic action plan (Transport), energy
strategies/plan (Buildings and Energy). 
Delivery
The Business & Industry Action Plan currently has 17 actions
on the plan.  Of these, two are completed, 10 are green and 5
are Amber.  This theme had one Priority Action - the progress
of which is shown in Table .
Review of progress of Top Priority Actions:
There was only one Priority Action selected by Council as Top
Priority as shown in the Table below.
Table 6 Review of Building and Industry Top Priority Action(s)
Action
Number
Action RAG
Status
Comments
B&I 14 Develop Perth
West and Perth
Eco-Innovation
Park as a
national net zero
exemplar for
decarbonisation
of transport and
energy - Full
Business Case to
be developed
and supported at
Scottish and UK
levels.
A Outline Business
Case is being
finalised with funding
strategy for
consideration by
Council in February
2024. External
Funding to be
explored. Target
completion date:
March 2028.

Page 19

APPENDIX A                                           
Delivery challenges and opportunities
• Skills/Jobs: Although more intelligence is being
developed e.g. ‘Tay Cities Clean Growth Skills Report’,
it is still a challenge to access statistics and establish
baseline on ‘green’ skills and jobs. Actions are therefore
fragmented and small-scale. The importance of
Developing the Young Workforce and other activities in
schools around future careers is needed.
• Funding for Perth Eco-Innovation Park: a growth
opportunity, but a fully funded strategy is requested, and
external funding opportunities are pursued and active
engagement with investors to attract private funding. 
• Funding for Energy Investment Programme: a growth
and investment opportunity, but needs engagement with
possible strategic partners to bring expertise and
funding. 
Positive outcomes as a result of Priority Actions: 
The Tay Cities Clean Growth platform is growing in strength
and reach with 121 members from 112 organisations
https://taycitiescleangrowth.scot/ and list 19 clean growth
projects across the region.  
The Council has pledged financial support for Perth Eco-
innovation Park and a Project Board is well established and
progressing the planning and design aspects of the scheme.
The Council is exploring with the support of Scottish Futures
Trust the development of a Strategic Energy Partnership which
would help deliver a range of renewable energy and
decarbonised heating projects across Perth & Kinross
£10M has been allocated by the Council from its Capital
Programme to support the development of Perth Eco-
Innovation Park.  A bid to the Levelling Up Fund Round 3 (due
to be launched by UKG) is also being prepared.
Progress against statutory targets and key KPIs
The table below details the key performance indicators aiming
to measure progress towards the reduction of overall carbon
emissions from industrial and commercial sources. 
They are around support to businesses and to sectors greening
the economy, focusing on businesses which have the greatest
impact on emissions and maximising access to green skills and
green jobs opportunities. 
After reviewing what data was regularly available and reliable,
the Business and Industry KPI list has been reduced this year
to four key KPIs.
It is important to note the increase in carbon emissions from
industrial and commercial sources which shows a concerning
trend.

Page 20

APPENDIX A                                           
Table 7 2023 KPI data 
Looking ahead 
Actions this year will primarily focus on:
• Perth Eco-Innovation Park: development of a fully
funded strategy and start delivery in March 2024 for
completion in March 2028.
• Energy Investment Programme: development of
business cases to create a pipeline of projects to attract
investment and assessing the benefits of developing a
Strategic Energy Partnership working with Building and
Energy group.
• Strengthen engagement with 165 identified businesses
via targeted activities (e.g. case studies, events)
including incentives such as Green Recovery Capital
Fund to support business carbon reduction plan.
• Skills/Jobs: use analysis from reports to identify
strategic actions in partnership with Perth College UHI,
Skills Development Scotland, Developing Young
Workforce, Tay Cities Clean Growth Initiative and Tay
Cities Skills Partnership.
• Circular economy: Development of Circular Economy
route map working in partnership with Waste Theme.
• Supporting Business engagement around the
development of strategic transport corridors.  
KPI Previous
Value
Current
Value
Target
Total area-wide Carbon
dioxide emissions (kt CO2)
from industrial and
commercial sources  104.8 123.9    
Number of registered
businesses in energy
(including renewables)
growth sector  140 145 
+10% per
year
% of businesses (250+
employees or largest energy
demand (+0.5MW) with a set
target for reducing carbon
emissions 
17% 
(base 24)
7% 
(base 165) 
100% by
2027
Number of businesses
supported through PKC
Green Recovery Capital
Fund  3 16 
c. 20 per
year

Page 21

APPENDIX A                                           
Theme 4 – Waste and Circular Economy 
Waste and Circular Economy work progressed this year action
against all five key areas of action in the Climate Action Plan.
These include to: 
• Ensure alignment with the Scottish Government Climate
Change Route map
• Promoting a rapid transition to a Circular Economy
• Developing and delivering thematic action plans for the
high carbon emissions materials
• Improving our recycling services
• Maximise value from waste by reducing waste sent to
landfill
Highlights
• The Council has awarded a significant 10-year contract
worth £50 million to treat residual waste and turn it into
energy. The contract commenced on 1 August 2023.
The Council has appointed Paprec Energies Binn Ltd
and both will work in partnership to manage the waste
through a thermal treatment, energy recovery and
recycling solution. 
• The Council secured funding of £2.72M from the
Scottish Government Recycling Improvement Fund
(RIF) to roll out two significant projects: -
Project 1 - Service Expansion – City Centre Recycling which
was the first project affording the opportunity to expand
recycling services to circa 1,000 properties in Perth City Centre
that do not currently have access to kerbside collections for
Food Waste or dry mixed recycling, this part of the project was
completed in November 2022. 
Project 2 – Service Development – Twin Stream Recycling -
The second project is the modification of the existing kerbside
dry mixed recycling collection into two distinct material streams.
The blue bin will continue to be collected containing paper and
cardboard, with the introduction of a grey bin to collect cans,
cartons and plastics. The grey bin will also now allow for
recycling of tin foil and soft plastics such as films and flexible
packaging. The introduction of this new kerbside arrangement
will also ensure PKC is brought into line with the national
Household Waste & Recycling Charter. The new service
commenced on 30 October 2023. 
Table 8: Key Waste and Circular Economy Actions
W12 Develop & Maximise
Recycling Services by  
1. Implementing in
November 2022
expansion of recycling
services (Food/DMR) in
Perth City Centre. 
2. Implementing in
November 2023,
expanding PKC recycling
services to include
flexible plastic packaging
and hard rigid plastics
(as market conditions
allow). 
G 2. As per W3 
£2.72m in RIF funding
awarded.
Fourth bin deliveries on
track for
commencement of
service change 1st
November 2023.
Expansion of materials
accepted

Page 22

Progress of Top Priority Actions:
Table 9: Waste and Circular Economy top priority actions 
Action
Number
Action RAG
Status
Comments 
W3 Food Waste: Gather data to create a baseline
of knowledge, participation and barriers.
A Food Waste Survey completed April 2022.
Food Waste Reduction and Recycling Campaign held from May 2022 to April 2023.
City Centre Food Waste Hubs commenced November 2022. Approximately an
additional 1000 households now having access.
Trial – 11 Rural Food Waste Hubs in Crieff (5), Auchterarder (2), Blairgowrie (3), and
Scone (1) commenced July 2023. Additional areas to be identified for roll out in
2024.
In 2024, further action to explore the feasibility of kerbside caddy collection in a trial
area (subject to operational capacity availability).
Resource issues due to staff being deployed on service change with twin stream. 
Due to restart 2024 for creation of baseline. 
W5  Review how the Deposit Return Scheme
(DRS) and Extended Producer Responsibility
can be introduced effectively in Perth and
Kinross & regionally 
A DRS
Meetings with Dundee City Council, Angus Council and Tayside Contracts were
undertaken late in 2022 into 2023 to determine a collaborative approach.
Perth & Kinross Council and Zero Waste Scotland (ZWS) met in June 2023 to
review the DRS model.
Implementation date changed to October 2025 from August 2023. 
Meetings will be scheduled from 2024.
EPR
Delayed until October 2025. 
Draft Regulations published, consultation being conducted by DEFRA on behalf of
the UK Government, closes 9th October 2023
Waste Services attending regular DEFRA LA Engagement Sessions.
W17 Asset Management Review of Waste and
Recycling Infrastructure
G Work commenced on the asset management review of waste & recycling
infrastructure with building conditions surveys and suitability assessments
undertaken. A consultant has been appointed to compile the information collated
and present in a Strategic Outline Business Case report and this will be used to
inform the Council’s overall asset management approach going forward.

Page 23

Delivery challenges and opportunities 
Deadlines set by Scottish & UK Governments have proved
challenging as projects have had time devoted with multiple
internal and external parties, then dates have been significantly
altered. This approach results in massive difficulties and
uncertainties moving forward to accommodate appropriate
levels of staffing, vehicles, financial information (costs, income,
potential savings or additional expenditure, etc), relevant
equipment (if applicable). 
This also has meant a significant amount of time has been
focused on areas such as DRS which would have been spent
on other work and projects to progress them further. 
Positive outcomes as a result of Priority Actions:
The Residual Waste Contract will treat the non-recyclable
waste stream, with a new Energy from Waste facility currently
being developed at Binn Eco Park in Glenfarg. The facility is
due to open in 2026. Once operational the facility will generate
energy (heat & electric power). The heat from the facility will
also supply heat-using processes at the Eco Park including
advanced horticultural systems. In addition to adding capacity
to the existing private renewable energy grid at the Binn Eco
Park, it has the potential to power an extended private
renewable energy grid into Perth. 
Delivery of Action W12, expansion of kerbside recycling, has
resulted in an increase in quantity of recyclable material
captured which increases recycling rate, reduces waste
arisings and contributes to the net zero agenda by reducing
carbon emissions through capturing food and plastics. 
Through extensive engagement work, there has been
increased participation and positive behavioural change by
residents evidenced through:
• Improvement in recyclate material quality 
• Alignment with Household Waste & Recycling
Charter & national policies and legislative targets
and the Perth and Kinross Council Waste
Management Plan and Climate Change Strategy &
Action Plan
• Consistent Kerbside Collection Service for residents
in Perth & Kinross 
Progress against national targets and key KPIs
National Targets:
I. Reduce tonnes of total waste arising to 15% against
2011 baseline by 2025: on-track total waste generated
has been decreasing since 2011 – 11.6% in 2022
II. Reduce the percentage of all waste sent to landfill to
5% by 2025: off-track waste sent to landfill increased by
2.8% in 2022 from 2021
III. Recycle 70% of all waste by 2025: off-track as currently
recycling significant less than interim target values
IV. Reduce food waste by 33% from the 2013 baseline by
2025: on-track, food waste collected decreased by 40%
in 2022.

Page 24

Performance  
Table 10: 2023 KPI data
KPI Previous Value Current Value Target
Area-wide territorial GHG emissions estimate - Waste 
(kt CO2e)
72.2  81.5 TBC
Total household waste generated (tonnes) and
household waste generated per person (kg)
77340 tonnes;
510kg/per person 
70604 tonnes;
459kg/person 
By 2025, reduce tonnes of total waste
arising to 15% against 2011 baseline
(69,730 tonnes)
Total household waste recycled/composted as % of all
household waste
50.1%   49.2% Recycle 70% of all waste by 2025 
Carbon impact of household waste per person (tonnes
CO2e)
1.02
(2021) 
1.1
(2022)
Reduce carbon impact to 0.7 tonnes
CO2e per person by 2026 
Whole Life Cycle Emissions for Perth & Kinross Council
Collected Waste 
(kt CO2e)
154.4 (2021)  138.9 (2022)  
Quantity of food waste collected in residual waste
(Kg/HH/week) 
1.69 1.64 Reduce food waste by 33% from the
2013 baseline by 2025 
Dry Mixed Recycling contamination rate (%) 21.2%
(2021/22) 
22.6% (2022/23) Reduce to minimum of 20% by 2022/23
and 15% by 2023/24

Page 25

APPENDIX A                                           
Looking ahead 
Actions this year will primarily focus on:
• Developing the Food Waste Action Plan and actions
therefrom.
• Single Use Policy and how Perth & Kinross Council can
further address this area in relation to reducing the
quantities of single items used and explore any
additional measures that can be identified from
Procurement stage.
• Developing an action plan for circular textiles.
• Developing re-use activities throughout Perth & Kinross,
looking at areas where collaborative working is
achievable and working with internal and external
parties to introduce re-use opportunities, expand
networking opportunities and explore additional funding
sources.
• Recommencing DRS planning later in 2024 in
anticipation of the rescheduled introduction due October
2025.
• Continue planning for EPR in anticipation of the
introduction due October 2025. 
• Asset Management – taking forward recommendations
from the Strategic outline Business Case to future proof
operational depots and HWRC’s 
• Continuation of working with Education – Waste
Analysis of Schools to be undertaken Feb/March 2024.
• Digital Waste Tracking - SEPA and the Scottish
Government have been working with UK partners to
develop a digital waste tracking system that will be
adopted by all four nations. This mandatory tracking will
transform how waste and resources flow; tackle waste
crime; and prioritise regulatory activities. From April
2025 legislation will come into force across the UK
making use of the waste tracking service mandatory.  
• Good Food Project Officer has been appointed to
support development of a Good Plan including an
action to support the Food Share Network model being
developed by Giraffe. This looks to redivert food
destined for landfill to community food organisations
across Perth and Kinross and to produce meals for the
community in the Giraffe Community Kitchen. 
• Engagement with Scottish Government and LA and
sector contacts in relation to the priority actions set out
in the Circular Economy Bill and Circular Economy and
Waste Route Map and input to ongoing national
consultation.
• The management of Persistent Organic Pollutants
(POPs) in bulky residual waste
•  Increased communications on behaviour change by all
on waste.

Page 26

APPENDIX A                                           
Theme 5 – Land Use 
Land Use work progressed this year action against all four key areas of action in the Climate Action Plan. These include: 
• Strengthening Planning
• Rural Land Use and Carbon Sequestration
• Biodiversity 
• Greenspace 
Highlights
There were several highlights this year associated with the land use theme.
• Receiving over £700k of Scottish Government Nature Restoration Funding from 2021 that has enabled more than 30 projects to be
successfully delivered by PKC and community groups, with a further 18 on-going in 2023/24
• Building a successful partnership with the Scottish Invasive Species Initiative and local landowners to deliver a catchment scale approach
to INNS control project on the River Almond.
• Successful roll out on 42 sites of trials for managed grassed areas for climate change and biodiversity.  
• Significant expansion of “no mow” is being planned on most of the Council’s managed greenspaces for 2024/25
• Networking and relationship building ongoing by Council’s Good Food Nation Project Officer, working towards developing a Good Food
Nation Strategy.
• ‘Upper Tay Catchment Communities - Almond Headwaters’ project bid was successful in receiving a ‘Riverwoods – Investment
Readiness Pioneers Award and grant of £124,000. 
• Successful designation of Scotland’s first Biodiversity Town at Blairgowrie and Rattray, and two Biodiversity Villages (St. Madoes and
Guildtown).

Page 27

APPENDIX A                                           
Delivery
Table 11: Review of progress of Top Priority Actions
Action
Number
Action RAG
Status
Comments
L1 Develop a landscape scale pilot project in conjunction with partners
(Perthshire Nature Connections Partnership (PNCP) to support
private landowners to facilitate and encourage forestation and
peatland restoration.
G • ‘Upper Tay Catchment Communities – Almond Headwaters’
project awarded £124,000 in grant funding. 
• Work now involves 3 neighbouring estates in landscape
restoration.
• Work progressing on Breadalbane Species Rich Grassland
(SRG) Priority looking at opportunities and constraints to 3
farms management of SRG.
L11 Review current planning policy framework to determine their strength
in terms of delivering on climate change, biodiversity, and net zero
commitments. Update, enhance and enforce more rigorously where
required.
A • Relevant regulations and guidance have now been published.
• LDP3 project plan timelines currently being further refined to
ensure delivery within expected 5 year period.
• NPF4 sets the national policy framework for planning
decisions, LDP3 will include new local policies where it
deemed appropriate and necessary.
L14 Consider as part of the review any potential policy amendments to
help the planning system better support the implementation of carbon
reduction measures. Develop advice and guidance if appropriate.
A • As per above for L11

Page 28

APPENDIX A                                           
Delivery challenges 
• Reduction in on street weed control – currently no
financial resources available to trial other alternative
methods to the use of herbicides. 
• Lack of viable battery powered alternatives for industrial
level activities. 
• Community concerns regarding some of the grassland
maintenance trials being rolled out under the agreed
Managing Grassed Areas for Climate Change and
Biodiversity Programme.   Additional resources needed
to help raise awareness within communities, and to
share knowledge and information about the various
associated benefits these grassland areas can bring.  
Additional cut and lift machinery needed to significantly
expand the “no mow”.  
• Lack of staffing resources in Community Greenspace
Team  has resulted in the review of the Council’s Sports
Pitch Strategy being put on hold. 
• The Planning (Scotland) Act 2019, its associated
Regulations and Guidance, and National Planning
Framework 4 have introduced a significant number of
new additional asks of Planning Authorities in the
preparation of their Local Development Plans.  A large
number of the asks are major projects in their own right,
which require significant staff resources to deliver, and
all at the same time, which is going to be a real
challenge over the next 2–3 years. 
Delivery opportunities 
• Potential funding awaiting confirmation of  to expand
the Biodiversity Towns and Villages Project and
develop the Biodiversity Industrial Estates Project.
Positive outcomes as a result of Priority Actions:
• Approval of additional staff resources to undertake
Open Space Quality Audits, complete Local Nature
Conservation Sites surveys, and the creation of a new
Climate Change Landscape Restoration Officer post.
• Annual tree planting plans for the Council’s parks and
open spaces are being developed and implemented
based on the principal of ‘the right tree in the right
place’ to provide a range of benefits, including carbon
sequestration.
• Westbank Nursery currently growing native trees and
shrubs from cuttings and seeds to support increased
planting of native species. 
• Significant reduction in the use of pesticides at
Westbank Nursery, with the move to more pollinator
plant production.  Expected to continue to be
minimised.
• Cessation in annual application of selective herbicide to
all sports pitches. Only applied where required. 
• Successful roll out on 42 sites of trials for managed
grassed areas for climate change and biodiversity. 
Significant expansion of “no mow” is being planned on
most of the Council’s managed greenspaces for
2024/25.

Page 29

APPENDIX A                                           
• Networking and relationship building ongoing by
Council’s Good Food Nation Project Officer, working
towards developing a Good Food Nation Strategy.
• Further botanical survey work has been undertaken for
three farms as part of the Perthshire Nature
Connections Partnership Breadalbane Species Rich
Grassland Priority Project.  The results will help to
further refine any future possibilities. 
Progress against statutory targets and key KPIs
The Scottish Government has set several targets related to
land use. These are primarily at the national level rather than
local authority level, though local authority action will be
required to meet these targets.
These include:
• National target to increase forest and woodland cover
to 21% of total area of Scotland by 2032 – Perth and
Kinross is currently at 18% (a decrease from 2018).
• Peatland Restoration – 250,000 ha of degraded
peatland by 2030.  The Perth and Kinross area has
approximately 10% of Scotland’s peatland resource. 
• National target for at least 80% of designated natural
features to be in favourable condition by 2016 – Not
met but improving:  SSSI at 75% and Protected Nature
Sites at 75.5%.

Page 30

APPENDIX A                                           
Table 12: 2023 KPI data
KPI   Previous
Value 
Current
Value
Target
% of the total land area of Perth and Kinross covered by
woodland 
18.8% of the
total 
18.8% (no
recent data
updates)
National target to increase forest and woodland cover to 21%
of total area of Scotland by 2032  
Total LULUCF emissions (ktCO2e) 561.7   559.2 Target still to be set
Total LULUCF sequestration (ktCO2e)  -710.8 -704.7 Target still to be set
Species and Statutory Species Distribution 
% of all 1km grid squares in Perth and Kinross had
recordings of protected species 
51.4% 
(2020) 
51.4% (no
recent data
updates)
National Target to protect at least 30% of Scotland’s land for
nature by 2030
National target for at least 80% of designated ‘features’ in
favourable condition by 2016
% Of Protected Biological and Mixed SSSI Sites in
Favourable Condition 
75.3% 
(June 2022)
TBC National target for at least 80% by 2016. 
% Of Protected Nature Site Features in Favourable
Condition 
75.5% 
(2022)
TBC National target for at least 80% by 2016
Number of trees planted on Council land and maintained
open space 
South Inch -
37 total
planted  
TBC Net increase on carbon capture from tree planting, method of
measure to be identified.
Number of community volunteering hours in biodiversity
related projects 
1420 1786.5 
Area grassland managed for biodiversity improvement
objectives (ha) 
- 21.72 
Vol. of Herbicide Used (L – undiluted quantity) 1117 (2021) 1216 (2022) The commitments within the Edinburgh Declaration require a
national reduction of 50% by 2030

Page 31

APPENDIX A                                           
Looking ahead  
Actions this year will primarily focus on continuing work on: 
• Review and revise our Forestry and Woodland Strategy
(FWS) as part of LDP3 process. Consider how the FWS
can support and encourage private landowners to plant
“the right tree, in the right place” to help tackle the
climate and biodiversity crises.  
• Identification of and awarding of successful bids to the
current round of the Nature Restoration Fund.  
• Undertake an Open Space Quality Audit as the
evidence base to support the development of the
Council’s Open Space Strategy.
• Identify the Strategic Green Networks either wholly or
partially within Perth and Kinross and opportunities for
their enhancement.
• Reviewing the existing planning policy framework within
the context of National Planning Framework 4’s suite of
National Planning Policy and identify where a local
policy response is appropriate and necessary.
• Exploring in collaboration with the Riverwoods Project
Study, the development of a potential methodology for
developer contributions/ offsetting via planning
applications.
• Continuing Local Nature Conservation Sites survey
work programme.
• Continuing progress on achieving the Sustainable Food
Places Bronze Award and developing a Good Food
Nation Strategy.
• Further roll out of the Biodiversity Villages,
Neighbourhoods and Towns Initiative across Perth and
Kinross.
• Increase dialogue and engagement with landowners
and farmers

Page 32

APPENDIX A                                           
Theme 6: Climate Resilience
Our climate resilience work this year progressed action against
all five key areas of action in the Climate Action Plan. These
include:
• Resilient organisations
• Resilient and empowered communities
• Resilient ecosystems
• Resilient infrastructure
• Flood risk management 
Highlights 
Delivery
The Action Plan identified 40 Resilience Actions, with progress
made against almost all of them.  Highlights this year include:
Completion of Perth & Kinross’s first Climate Change Risk and
Opportunity Assessment, which looked at risks and
opportunities to both the Perth & Kinross Council Area and
PKC services and operations; Approval of the Council’s Flood
Risk Management Cycle 2 Projects in December 2022 and on-
going progress delivering nine Cycle 1 and Cycle 2 Flooding
Schemes.
• The Tayside Biodiversity Partnership’s Ponds for
Puddock’s community SUDS project has successful 
completed Year 2 and was shortlisted for the Nature of
Scotland Awards 
Review of progress of Top Priority Actions:
As can be seen from Table 13, of the five Priority Actions
identified for Resilience, one is complete, two are green and
two are amber 
Delivery challenges and opportunities
• Resources – both the attraction and retention of
suitable staff and the significant inflation in the
construction sector has impacted on delivery progress,
particularly for flooding with inflationary pressures of
upwards of 50% on major planned schemes.
• While the awareness for and priority of resilience and
adaptation measures is rising, this strand of action still
has lower profile and focus than mitigation.
• There is a challenge to bring together the different key
areas of resilience, land use, transport and planning. 
Outcomes
Positive outcomes as a result of progressing the Priority
Actions:
There has been an increased awareness of the current and
future climate impacts on Perth & Kinross to stakeholders and
the wider public
The work progressing flooding and scour schemes is helping to
protect infrastructure and communities from extreme weather
events.

Page 33

APPENDIX A                                           
Table 13 Summary of Progress of Resilience Priority Actions
Action
Number
Action RAG
Status
Comments
R6
Undertake a strategic climate change risk and
opportunity assessment for Perth and Kinross
Council Area Complete
Published on the Climate Action Website
R11
Develop updated roads development guide to
resolve conflicts with adoption criteria for SUDS
with roads maintenance requirements as well as
providing wider resilience benefits (e.g. shading
and biodiversity corridors and protection)
A
Initial discussions have taken place with Transportation officers who
are scoping out some of the issues to be considered as part of the
review, including extensive internal stakeholder liaison. It is likely given
the scale of the work that the Council will procure consultancy support
to take forward the work. 
R12
Develop and implement scour bridge protection
programme
G
Scour Assessment programme underway with climate change
accounted for. Long term project. Results from Scour Assessments will
be used to inform on backlog of high priority works and also Roads
Asset Management Plan identifying capital pressures as required.
R24-
R34 
Continued delivery of Flood Risk Management
Cycle 1 Projects and commence Cycle 2
projects.
A
Flood Risk Management 2 projects were approved by the Council in
December 2022.  Work has been continuing on a number of flooding
schemes and design of further schemes, but cost inflation and staff
pressures are impacting on overall delivery
R14
Explore the feasibility of a pilot natural flood
management site in the Upper Leven Catchment.  G
Being progressed with the Forth Rivers Trust as part of the Loch Leven
LENS group with an expected completion date of March 2024

Page 34

APPENDIX A                                           
Progress against statutory targets and key KPIs
Under the Climate Change Act (2019), we have a duty to
contribute to the delivery of the Scottish Climate Change Action
Programme 2, which the actions in the action plan have been
developed to align with.  This plan does not pose specific
targets applicable to local authorities. 
Flooding is one of the main physical climate risks to Perth and
Kinross. Under the Flood Risk Management Act (2009). We
have a duty to deliver Flood Risk Management Plans and
report our progress every three years. In December 2022, we
assessed 85% of the PKC actions in the flood risk plan are
completed or on track.
Table 14 2023 KPI data
KPI  Previous
value
Current
value
Target
Annual Scotland
Adapts Capability
Framework score
3.33/12  8.2/12 Mature organisation
- 9/12 by 2026
Number of community
groups engaged in
proactive climate
resilience work
27 27 53 
(a minimum of one
per Community
Council Area)
Percentage of PKC’s
flood risk management
plan actions classified
on track or completed 
85%
(2019)
85%
(2022)
Not set
Number of Bridge
Scour Assessments
Undertaken
N/A N/A Currently putting
together a
programme of
scour assessments
which will allow
targets and
baseline values to
be set 
Looking ahead
Actions this year primarily focus on continuing work on the
projects in the initial action plan. These include:
• Delivery of Cycle 1 & Cycle 2 Flooding Schemes;
• Progression with bridge scour assessments;
• Further development and promotion of Natural Flood
Management in Perth & Kinross;
• Embedding the recommended actions from the Climate
Change Risk and Opportunity Assessment into Council
operations and contributing to the development of the
Scottish Climate Change Adaptation Programme 3.
It is proposed that three actions are removed from the action
plan in Year 3.  R10, R13 and R31 due to overlap with other
actions in the Resilience and Land Use Action Plans.

Page 35

APPENDIX A                                           
Theme 7: Education and Engagement 
Highlights 
Delivery
Significant progress made with staff Carbon Literacy training
sessions and certification: 
• 121 Council’s Officers completing the days training
• 79 achieving full certification through pledge
submission.
Ongoing work with Elected Members to have some level of
climate training in place. Short Climate Emergency training
delivered by KSB. PKC trainer is in talks to arrange full Carbon
Literacy for Elected Members. 
Ongoing work in schools through a sub-group and considering
various themes (waste, active travel, energy reduction)
including:
• Creation of monitoring forms to assist with energy
efficiency practices, waste and recycling containers and
active travel
• New Climate Action Plan template created and
circulated to Head Teachers
• Presentations for self-delivery created and shared
• New Employee Resource and Information page
launched with links to internal and external support
• Waste composition analysis to be tendered and
completed Feb/Mar 
The second annual Youth Climate Conference, held on 25
October, was a success. 80 pupils from 9 high schools were in
attendance. Conference will return next year as a regular
annual fixture.
In 2023, the Team participated in the Innovate UK Net Zero
Living Project. Phase 1 of the project involved engagement
with communities in Aberfeldy and Tulloch, Perth
Phase 2 project bid submitted for funding to demonstrate how
the ideas in Phase 1 would work.
Internal awareness raising through the Staff Climate Cafes is
ongoing and dynamic, with a mix of events, guest speakers
and workshops.
Review of progress of High Priority Actions:
Action
Number
Action RAC
Status
Comments
E6 Develop dedicated CC Hub G Launched
E8 Ensure CC is embedded in
school curriculum
A Some progress but
requires further attention to
ensure continuity across
schools
E5 Develop staff and elected
member training
G Good progress with Staff
Carbon Literary training
sessions and certification;
ongoing work with elected
members
E19 Deliver Youth Climate
Conference
G Successful event in 2022
and to be repeated October
2023
E17 Input to Corporate
campaigns on cost-of-living
and energy saving
G Frequent input via
corporate Comms
E14 Maintain presence on
social media platforms
G Web-site running and being
developed; regular outputs
on FB and X (twitter)
E21 General public engagement
via attendance at Market
events, Winter Festival etc
G Ongoing involvement via
Events Team

Page 36

APPENDIX A                                           
Action
Number
Action RAC
Status
Comments
E4 Deliver Climate
Literacy training to staff
and elected members
G Successful and
ongoing
E19 Youth Climate
Conference
G Second annual event
took place on 25,
October 2023
E9 Work with schools on
carbon emissions and
waste
G Ongoing work
between CC reps and
ECS to deliver
information and
materials on the
ground and in-person
E10 Public engagement G Successful delivery of
IUK Phase 1 project in
Aberfeldy and Tulloch,
Perth; regular
attendance at events
(Winter Festival, Earth
Day market) 
Delivery challenges
• Resourcing for in-person events, generally
evenings/weekends
• Looking for means to get behaviour change information
and good practice through the body of other messaging
Opportunities
• Use of Climate Cafes and Carbon Literacy Training as a
means of building general staff awareness and activity
• Giving young people a voice at their own event(s)
• Sharing our good practice with other Local Authorities
via expanding networks
Positive outcomes as a result of Priority Actions:
• Increasing number of Council staff with Carbon Literacy
qualification and increased awareness
• Providing youngsters with a platform to speak, act and
engage with CC staff
• Ability to assist during the cost-of-living crisis by
providing public engagement events (such as Earth Day
Market) and practical support 
• The youth conference was well received by pupils and
teachers that got involved. Attendees expressed their
positive feedback on the Council taking action to
combat climate change while valuing the views of
young people. 
Progress against statutory targets and key KPI’s
KPI  Previous
value
Current
value
Target
(April 2023)
Views on Climate Change
Webpage
14000 22000 28000
Views on Social Media channels -
Facebook
15700 39511 37680 
Views on Social Media channels -
Twitter
14400 16300 34560 
Table:15 Progress of high priority actions

Page 37

APPENDIX A                                           
Focus for upcoming year
• IUK Phase 2 – if successful will either receive £3.2m for
full Demonstrators project or £150k for Pathfinders
project. 
• Further public engagements, through events and
working with the wider communities team including
Participatory Budgeting 
• Youth conference - evolving the conference in line with
the wants of the pupils to make it even more engaging.
• Increased communications focusing on behaviour
changes  
Views on Social Media
channels – Instagram
4695 11451 11268 
Views on Social Media
channels – TikTok
1779 n/a account
closed
4269 
Number of community groups
active on climate change
related projects 
139  140 
Number of PKC owned schools
with eco-school’s green flag
status
27 27 45 (April
2024)
Staff who have completed the
climate change eLearning
module
1233 1824 5834
Table 16: 2023 KPI data

Page 38

APPENDIX A                                           
Theme 8: Governance
Our Governance work this year progressed action against all
four key areas of action in the Climate Action Plan. These
include:
• Governance and accountability
• Business and performance management
• Objective and target setting
• Sustainable Procurement
Highlights
The Action Plan identified 26 Governance Actions, with
progress made against several of them, with some delays
associated with the changes to the Council’s organisation
structure and Procurement Transformation processes.  
Highlights this year include:
• Development of the Impact and Value Assessment Tool
for screening the Council’s Reports – helping to identify
the full suite of potential opportunities as well as
impacts for proposals being developed.
• Launch of the staff Climate Literacy Training
Programme, which has of October 2023 seen 121 staff
trained, with 79 receiving full certification. 
• Development of a new Council Procurement Strategy
that includes Climate Change and embedding Climate
Change into the Council’s Procurement Transformation
Programme.
• Regular meetings of Climate Change Board and
working groups monitoring actions and facililating cross-
learning  
Delivery
There are three Top Priority Actions within the Governance
Theme. Two are currently Green and one is Amber.   More
widely, of the overall 26 Governance Actions, 11 are status
Green, 8 status Amber and 7 status red. 
Review of progress of Top Priority Actions:
Table 17: Governance top priority actions
Action
Number
Action RAG
Status
Comments
G2 Mainstream climate
change into
committee procedures
and council
operations
G Good progress made
in 2023, following
finalisation of the
internal audit and the
completion of the
PKC leadership
review, Governance
procedures will need
to reviewed
G7 Measure and develop
action plan for our
Scope 3 carbon
footprint
G Analysis undertaken
of the Council’s
20/21, 21/22, and
22/23 procurement
spend. Final
consultant results
due in November
2023.
G20 Build capacity of
procurement and
contract management
staff around ensuring
climate change is
appropriately
considered in
procurement and
delivery processes
A Progressed as
possible with limited
resources

Page 39

APPENDIX A                                           
Delivery challenges and opportunities
• The Council is currently undergoing a leadership
transformation that is both a challenge and an
opportunity.  It has delayed the embedding of certain
processes and procedures, but once it is completed
including appointing a strategic climate change lead,
the revised structure and clear definition of roles should
allow for improved climate action accountability.
• The new Impact and Value Assessment Tool has the
potential to be transformative in terms of capturing
climate change opportunities and mitigating potentially
negative impacts on climate change.  This will require
an operational change to use it has a proposal
development tool rather than a post-development
screening tool.
• Procurement national legislative framework is out of
synch with climate change ambition; with more of a
focus on cost saving than carbon saving targets.
• There is an opportunity for the Council to be more
creative and confident in designing procurement
processes that give greater weighting to sustainability –
test the norms and demonstrate what a successful
sustainable procurement project looks like via case
study development and promote this to a wider
audience to act as influence as was done for the new
Residual Waste Tender or the Cross Tay Link Road. 
Outcomes
Positive outcomes as a result of Priority Actions:
• Increased staff training and capacity with respect to
Climate Change;
• Increased ability to monitor the impact of climate
change proposals;
• Improved organisational capacity around Climate
Change 
Progress against statutory targets and key KPIs 
There are no statutory targets related to the Governance
theme, but there are statutory reporting duties through the
Public Sector Reporting Duty related to Scope 3 emissions
from procurement for which  a mechanism to measure them is
being finalised. An assessment tool has been developed to link
climate change into budget and financial procedures.

Page 40

APPENDIX A                                           
KPI
Previous
Value
Current
value
Target
Scope 3 Emissions –
Procured goods and
services and capital
works
Not yet
measured
Not yet
measured 
To be set
% of Members and
senior officers who have
undertaken Climate
Literacy training
Not yet
measured
20%  100% by
September
2023
% of staff who have
undertaken climate
change awareness
training (in person or
online)
21% 36%  80% by
September
2023
% of staff who have
climate change included
in job description
1%
(2022)
1%
(2023) 
No target set
Climate Change
Assessment Tool
(CCAT) Overall Score 
51%
(2022)
61%
(2023)
85% by 2026 
Looking ahead
There are several priority actions for next year. These include:
• Continuing to mainstream climate change into
committee procedures and council operations, with a
particular focus on adapting measures post-Leadership
review and embedding the Impact and Value and
Assessment Tool.
• Using the results of the Scope 3 Purchased Goods &
Services to help identify and develop priority areas for
procurement changes.
• Using the Corporate Procurement Strategy refresh to
build in more on sustainable assessment and build
capacity within the Procurement team and also build
this into job descriptions for procurement post
• Using the Climate Change Strategy to be a pilot
strategy for early inclusion into the new corporate
performance management system