Democracy Spraffa

Draft Corporate Delivery and Improvement Plan 2024-25

Perth and Kinross Council · 4 October 2023
Back to Perth and Kinross Council — 4 October 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Perth And Kinross Council 
4 October 2023 
DRAFT CORPORATE DELIVERY AND IMPROVEMENT PLAN 2024/25 
Report by the Chief Executive
(Report No. 23/266) 
1. PURPOSE
1.1 This report presents the draft Corporate Delivery and Improvement Plan
(CDIP) for 2024/25 for consideration. It is being brought alongside the
Medium-Term Financial Plan to strengthen the alignment between the
priorities set in our Corporate Plan, improvement activity, and budget and
resource allocation. This approach will enable elected members to better
consider organisational priorities and improvements alongside budget
setting. The final CDIP will be brought back to Council for approval after the
final 2024/25 budget is set next year. This will enable any adjustments
following the budget to ensure improvement activity is aligned with the
funded priorities set by Council.
1.2 To support a robust approach to reporting on the Council’s Corporate Plan
this report also highlights four amended, replacement or new key
performance indicators and seeks approval for these to be added to
monitoring for future annual performance reports. 
2. RECOMMENDATIONS 
2.1 It is recommended that the Council:
• approves the draft Corporate Delivery and Improvement Plan for 2024/25.
• approves the proposed amendments to the key performance indicators for
the Corporate Plan priorities as set out in Appendix 2.
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4:  Background
• Section 5: Summary Information
• Section 6: Key Performance Indicators
• Appendix 1: Draft Corporate Delivery and Improvement Plan 2024/25
• Appendix 2:  Proposed amendments to key performance indicators for
the Corporate Plan

Page 2

4. BACKGROUND
4.1 The Corporate Delivery and Improvement Plan (CDIP) is a new element of
the Council’s strategic planning and performance framework. Introduced
this year as part of new performance reporting and strategic planning
arrangements, it complements the Annual Performance Report approved
by Council in August (Report No. 23/234) by setting out key proposed
improvement activity for the year ahead. 
4.2 This replaces the service-by-service approach to identifying improvements
which was previously in place through Business Management and
Improvement Plans. Presenting improvements at an organisational level
gives Council the opportunity to see the overall areas of focus for the year
ahead more easily. By bringing the final CDIP for approval at the start of
the financial year it also means Council will have sight of in-year
improvement activity at the start of the new financial year, rather than at the
end of the first quarter, or sometimes later, as was the case with the
previous approach. 
4.3 The CDIP is intended to be read in conjunction with the Annual
Performance Report for 2022/23 and details improvement activity intended
to address areas for development identified in the Annual Performance
Report (APR) and demonstrate our duty to deliver Best Value. The APR
acts as our annual look back at how we have delivered on the priorities of
the Corporate Plan, while the CDIP is our look forward to what we will focus
on doing to achieve the priorities of the Corporate Plan in the year ahead. 
4.4 Linking improvement activity to previous performance and aligning this to the
delivery of the Corporate Plan are key to maintaining a robust and effective
performance management framework. This is critical to the success of the
Council in delivering and improving outcomes for individuals and our
communities.
5. SUMMARY INFORMATION 
5.1 The draft Corporate Delivery and Improvement Plan for 2024/25 sets out key
strategic improvement activities which officers have identified to address
previous performance or introduce new activity which will contribute to the
delivery of the Council’s key priorities. It does not represent all of the work
which is ongoing to meet our statutory duties or to maintain existing areas
which are performing well. Given the scope of the Council’s responsibilities
these would be too much to contain in any one single document, but the
impact of this ‘business as usual’ work is demonstrated through the
performance measures agreed as part of the Corporate Plan.

Page 3

5.2 The proposed improvement activity identified within the CDIP has been
developed with service leads by cross-referencing the Corporate Plan
priorities with areas for improvement identified in the Annual Performance
Report for 2022/23 and our supplementary report on performance aligned to
the Best Value themes. It also includes areas for improvement, where they
link to delivery of our Corporate Plan priorities, which have been identified
through customer feedback, self-evaluation, benchmarking, and other
strategic documents. 
5.3 The draft CDIP sets out proposed improvement activity for elected members
to consider as the Council approaches planning for the 2024/25 budget setting
cycle. It has been brought to Council on the same agenda as the Medium-
Term Financial Plan (MTFP), so that elected members can consider the
proposed improvement activity within the context of the financial planning
information provided within the MTFP. 
5.4 Engagement with elected members on the proposed improvement activities
will form part of the budget preparation process. Engagement with local
people will be undertaken alongside our annual consultation on budget
priorities and will be reported to councillors as normal to be considered when
setting the final budget. Appendix D of Report No. 23/27 shows how this was
presented for the 2023/24 budget cycle. 
5.5 Once the final budget for 2024/5 has been set in early 2024, the agreed and
funded improvement areas will be updated within the CDIP and reported back
to Council for final approval.   
6. KEY PERFORMANCE INDICATORS 
6.1 When the Council agreed the Corporate Plan in December 2022 (Report No.
22/311 refers) we committed to “regularly review and monitor our performance
against each of the key priorities to ensure that they are still relevant and
effectively contribute to our vision”. As part of this, while producing the Annual
Performance Report 2022/23 we identified a small number of key performance
indicators which are not providing the level of information intended. 
6.2 Of the four indicators: 
• two changes are proposed to bring them in line with indicators within the
Local Housing Strategy 2022-27
• one change is proposed because the existing indicator does not present
the most realistic position on the availability of business land
• one is an additional indicator to supplement and more fully represent the
impact of our Welfare Rights Team 
6.3 Appendix 2 sets out the existing indicators (where relevant) including
performance and targets, alongside the proposed replacement indicators so
that Council can consider how the alternative indicator would impact on
performance reporting.

Page 4

6.4 If agreed, these updated performance indicators will be used for reporting on
the current years’ performance when the Annual Performance Report for
2023/24 is brought to Council next year. 
Authors
Name Designation Contact Details
Charlene Guild Head of Innovation cguild@pkc.gov.uk 
Approved
Name Designation Date
Clare Mailer Director (Strategy, People &
Resources)
8 September 2023 
APPENDICES 
Appendix 1 - Draft Corporate Delivery and Improvement Plan 2024/25 
Appendix 2 - Proposed amendments to key performance indicators for the Corporate
Plan

Page 5

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  None
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment None
Strategic Environmental Assessment None
Sustainability (community, economic, environmental) None
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications  
Community Plan / Corporate Plan 
1.1 This report sets out improvement activity to be undertaken to support the
delivery of the Council Corporate Plan 2022-27. 
2. Resource Implications 
Financial 
2.1 There are no financial implications arising from this report. 
Workforce 
2.2 There are no workforce implications arising from this report. 
Asset Management (land, property, IT) 
2.3 There are no asset management implications arising from this report.

Page 6

3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups. Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 This report has been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. no further action is required as it does not qualify as a PPS as
defined by the Act and is therefore exempt. 
Sustainability 
3.4 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• in the way best calculated to delivery of the Act’s emissions reduction
targets;
• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable. 
3.5 The information contained within this report has been considered under the
Act. However, no action is required as the Act does not apply to the matters
presented in this report. 
Legal and Governance 
3.6 Not applicable. 
Risk 
3.7 Not applicable.

Page 7

4. Consultation 
Internal 
4.1 The Executive Leadership Team, Service Senior Management Teams and the
Performance, Planning and Risk Group were consulted during the preparation
of this report. 
External 
4.2 Not applicable. 
5. Communication 
5.1 Not applicable. 
2. BACKGROUND PAPERS 
2.1 None.