Our vision is a Perth and Kinross where everyone can live life
well, free from poverty and inequality  
___________________________________________________________________  
Committee or Board:  Perth and Kinross Council 
Date of Meeting:  10 December 2025 
Report Title:  ‘The Heiton’ - 1-5 High Street Hotel Development. 
Report Number:  25/355 
Report Author:  Jonathan Janes, Estates and Commercial Investment
Team Leader  
Organisational Lead:  Lisa Simpson, Strategic – Lead, Legal and
Governance and Serge Merone, Strategic Lead –
Economy, Development and Planning 
___________________________________________________________________ 
1. Purpose 
1.1 The purpose of this report is to seek Council approval to nominate Lock
Terrace Ltd and its directors as the developer for the proposed ‘Heiton’ hotel
at 1–5 High Street, Perth. This recommendation follows a recent due diligence
review, prompted by changes in the status of the previously preferred bidder,
ahead of the building’s planned redevelopment. 
1.2 Sections 
1. Purpose
2. Recommendations
3. Background/Context
4. Proposals
5. Conclusion
6. Impact Value Assessment
7. Appendices 
2. Recommendations 
The Council is asked: 
2.1 To agree to nominate Lock Terrace Ltd and its directors as the developer and
to approve the revised proposed ‘Heiton’ hotel development at 1-5 High
Street, Perth.

Page 2

2.2 To note the due diligence review in the report. 
2.3 To agree that Strategic Lead – Economy, Development and Planning provides
a progress update at a future meeting. 
3. Background/Context 
3.1 The building at 1–5 High Street, Perth, was constructed in 1879 and is
category ‘B’ listed. It was previously used as Council offices and was declared
surplus to requirements in 2008. The Council has continued to incur costs for
the maintenance of the building estimated at 143,000 per annum since then.
The building was marketed for disposal and to be transformed into a hotel. 
3.2 On 30 July 2020, the Council agreed (Report 20/128 refers) to confirm Henley
Homes Group as the preferred bidder for the sale of 1-5 High Street, Perth to
allow officers to commence negotiation on the terms of disposal. 
3.3 There was an associated offer of a grant of £1.9m to help offset some of the
heritage-related costs identified in the viability assessment. The grant funding
was deemed essential to making the scheme viable, which was consistent
with the opinion of our external experts given the complexity of the building
lay-out and its historic and architectural significance. The grant was also
conditional on maintaining public access in recognition of the local heritage
significance of the building, in addition to covering the extra heritage
expenses. The Council proposes to borrow from the Public Works Loan Board
to fund the grant, with the loan charges being met from the current operating
budget. This approach will still deliver a net reduction in the Council’s annual
expenditure on the building. For clarification, it is not intended that the
development company be required to repay the grant as the grant funding
was considered essential to ensure the scheme’s viability. Upon completion
and opening of the hotel, ownership will transfer to the development company,
and the Council will have no further responsibility for the building ending its
existing liability for the maintenance and repair of the building. 
3.4 On 27 April 2022, the Council agreed (Report 22/107) to conclude a
development lease with the preferred bidder. 
3.5 Henley Homes Group Ltd was a well-regarded organisation with a strong track
record in regeneration and design, having received over 50 industry awards.
The group comprised a range of businesses involved in manufacturing,
design, construction, and development across both mixed-use and hotel
sectors. 
3.6 Following the Council’s initial decision, significant changes occurred in both
the economic environment and the internal structure of the preferred bidder.
Early delays were largely due to the uncertainty caused by the Covid-19
pandemic, which affected the economy at both local and global levels. As a
result, the developer was unable to enter into a legally binding agreement with
the Council.

Page 3

In response, the Council agreed to pause the process to allow time for market
conditions to stabilise and for the developer to reassess their position. 
3.7 During this pause, a major development occurred: Henley Homes Group
entered administration in April 2023. Consequently, Henley Homes Group and
its construction arm, Henley Construct Ltd, were dissolved. 
3.8 In February 2023, Lock Terrace Ltd was established by two former
shareholders of Henley Homes Group—Tariq Usmani MBE and Kashif
Usmani.  
3.9 Lock Terrace Ltd and its directors remain fully committed to delivering the
proposed 74-key hotel in Perth, to be named The Heiton in honour of the
original architect. The business model has evolved from the original concept
which included restaurants and bar on-site. The proposed business model is
designed around good quality serviced accommodation with limited on-site
provision. It will allow guests to spend more outside the hotel and support
local restaurants, bars and other leisure and wellbeing services. The design
and concept of The Heiton Hotel (see Appendix 1 & 2) will closely mirror the
style of the recently completed Wellington Hotel in Glasgow and Hobson in
Cambridge. As part of the design, Lock Terrace Ltd has requested the use of
the single storey garage located at the rear (see Appendix 7) and it is
proposed to investigate the feasibility of accommodating this request. This
would be dependent upon a Perth Common Good Fund consultation and
approval process. 
3.10 The directors are keen to ensure that the challenges faced by Henley Homes
Group do not hinder progress on this exciting new project. They have shown
their commitment to the Perth development by taking forward the planning
application which was approved by the Planning and Placemaking Committee
meeting held on 5 November 2025 (Refers 24/01613/FLL). As there was an
objection from SEPA, the decision was referred to Scottish Ministers for
consideration. A separate Listed Buildings Consent application is also being
progressed. For information, planning condition 24 states that prior to
completion or occupation of the development hereby approved, whichever is
the earlier, details of managed tours of the building to facilitate public access
to the historic interior should be submitted to and agreed by the Council as
Planning Authority. The details as agreed shall be implemented in full. 
4. Proposals 
4.1 Considering the history, a due diligence review was carried out on Lock
Terrace Ltd and its directors. The review was structured around reputational,
financial, and project governance and operational delivery risks to the Council
and the project. The review and risks are detailed below.

Page 4

Reputational risks 
4.2  We asked a series of questions in relation to reputational risks and the
responses have been reviewed. 
Q- Who are the Directors of Lock Terrace Ltd, what are their backgrounds and
core areas of expertise?
A-The Directors of Lock Terrace Ltd are Tariq Usmani MBE and Kashif
Usmani. Lock Terrace corporate brochures (See Appendix 3 and 4) provide
useful context for their experience in hospitality and mixed-use developments.
Tariq Usmani leads on investment, planning, and acquisitions, while Kashif
Usmani oversees construction and project delivery. In 2011, they were co-
founders of the Better Community Business Network (BCBN), a grant-giving
charity which also acts as a networking forum for government, business
professionals and charities. BCBN has raised over £1.3M in funds for UK
community causes, and both directors remain active Trustees. Tariq Usmani
is also Chair of the Feltham Community Chaplaincy Trust (a registered charity
working out of Feltham Young Offenders’ Institution providing mentoring and
support towards reducing re-offending rates), and Vice-Chair of West London
Islamic Centre, Ealing. He is a lay person on the Ministry of Justice strategic
interview panel. Tariq Usmain awarded an MBE in the 2017 New Year’s
Honours list for his services in community cohesion. 
Q-Can you provide an overview of companies that the Directors of Lock
Terrace Ltd are or have been involved with and the circumstances
surrounding the dissolution of Henly Homes Group and related companies? 
A- A full list of companies has been provided which provides a clear
understanding of the past and current positions of the directors of Lock
Terrace Ltd. Legal and Finance have reviewed the circumstances surrounding
the dissolution of Henley Homes Group and are satisfied with their version of
events leading to the inception of Lock Terrace Ltd.  
Q-What are the most recent and relevant completed projects by the directors
of Lock Terrace Ltd? 
A- The directors of Lock Terrace Ltd have successfully delivered a number of
projects. These completed developments reflect the directors’ continued
commitment to quality and delivery. The directors have demonstrated the
expertise required to refurbish and complete complex hotel and residential
schemes. These include: 
• The Hobson, Cambridge (by Hobson Cambridge Ltd): a 56-key hotel,
completed and sold.
• The Wellington, Glasgow (by RC3P Ltd): a 98-key hotel, completed
and sold.
• The Gilbert, Kensington (by Essential Kensington Ltd): an 84-key hotel,
completed and sublet to Sonder, a Marriott Hotels company.
• Rembrandt House, Watford (by Cameron West Ltd): seven residential
flats, completed and sold.
• 106 Grove Vale, East Dulwich, London (by OBH2 Ltd): three
residential flats, completed and sold.

Page 5

Q-Have any directors been involved in failed developments or insolvencies?
A-No failed developments in past or insolvencies prior to 2023/24. 
Q-Are any directors disqualified or under investigation by regulatory bodies?
A–No 
Q-Are there any ongoing or past legal disputes involving the company or
Directors of Lock Terrace Ltd?
A-No 
4.3 Based on the review of the information provided, we consider that the
reputational risks to the Council and the project are medium. There are still
reputational risks due to the circumstances surrounding the dissolution of
Henley Homes Group. It is proposed to mitigate the risks by the due diligence
process leading to the inclusion of various conditions in the development
agreement which will be kept under close review. 
Financial risks 
4.4 We asked a series of questions in relation to financial risks and the responses
have been reviewed. 
Q-Please provide a statement on the reasons for the liquidation of Henley
(and the various group) and the status of the debtors/unpaid debt?
A-A statement has been provided, and liquidators reports have been
reviewed. Finance is content with the contents of these reports. 
Q-Can you provide recent Lock Terrace Ltd annual accounts even if not
audited? Please provide recent annual accounts for the other companies
involved in the development.
A-Annual accounts for the companies have been provided and have been
reviewed by Finance. The information is limited due to the infancy of the
company. The accounts that have been provided are acceptable. 
Q- Are there any contingent liabilities or legal claims against the companies?
A-No 
Q- What are the key financial threats to the project and what measures are in
place / planned to mitigate these?
A-All elements have been properly costed, based on real-time cost
information and factoring in inflationary allowances and contingency. The
biggest threat is planning. Planning consent has been approved by Planning
and Placemaking Committee on 5 November 2025. As there was an objection
from SEPA, the decision was referred to Scottish Ministers for consideration
with 28 days from the referral. When planning has been completed, the lender
details include financing could be progressed. 
Q-Can you please provide an updated independently assessed Development
Appraisal for the full scheme? This will require measurement in terms of gross
development value, construction costs and your profit on cost return.

Page 6

A- A viability report has been provided by the Company, but will need to be
independently assessed prior to the development agreement being signed. 
Q-How is this project being financed (equity, loans, joint ventures)? What is
your current debt-to-equity ratio?
A-Finance has not been arranged yet until planning process is completed. 
Q- Are you planning to seek a buyer after a few years of operations?
A- The company strategy is to continue the building of its hotel portfolio. As
such, they have no intention of selling any of their assets in the near or the
mid-term. 
4.5 Based on the review of the information provided, we consider that the financial
risks to the Council and the project are medium. It is proposed to mitigate the
risks by requesting a full independent viability assessment by a third party,
including market analysis of gross development value, development cost
breakdown, professional fee review, and profit margin evaluation. Other
measures to mitigate the financial risk will include the submission of evidence
confirming full project funding, including proof of equity aligned with the
proposed debt-to-equity ratio and the establishment of a stage payment
agreement to ensure £1.9m grant funding is released only upon verified
expenditure by the developer. This will include proof of payment to
subcontractors as part of the audit process. 
Project Governance and Operational Delivery risks 
4.6 We asked a series of questions in relation to project governance and
operational delivery risks, and the responses have been reviewed. 
Q-Please advise which companies will be involved in redevelopment of 1 to 5
High Street and their role in the development and provide details of Directors
and key officers for each company involved. Please provide details of the
company that will be operating the hotel.
A-The following information has been provided:
Property Company: ‘Heiton Hotel Ltd’ – Directors: Tariq Usmani and Kashif
Usmani. 
Operating Company: ‘Essential Hotel Management Ltd’ - Directors Tariq
Usmani and Kashif Usman. The ‘Rogue City Hotel’ Brand will be used.  
Q- How does the director set up differ from that of Henley Homes Ltd prior to
their insolvency?
A-Lock Terrace is agile and efficient, leveraging Artificial Intelligence and
other technology. It has retained key members of the Henley Group team,
who have been with the directors for between 12 and 25 years, thus retaining
its intellectual capital.

Page 7

Q-Who are your key contractors, consultants, and suppliers?
A-The appointed main contractor for the redevelopment is Reach CM Ltd,
owned by Aaron Usmani. He was previously the construction director at
Henley Construct Ltd prior to its dissolution alongside Henley Homes Group.
Reach CM is an experienced contractor, having specialised both in hotels and
listed buildings. Reach CM holds the following accreditations: ISO9001,
ISO14001, ISO45001, CHAS Elite, Constructionline Gold, and are members
of the Considerate Contractors Scheme. They are registered with ICW as their
new homes warranty provider. Reach is also registered on numerous public
sector procurement frameworks. They have recently been awarded
Commercial Project of the Year by the London Construction Awards 2025 for
their delivery of The Hobson. They were also a finalist for The Wellington in
the same category. The judges “…were highly impressed by Reach CM’s
sensitive and thoughtful conversion of a listed building, which beautifully
restores its historic features while introducing bold, contemporary elements.
Every design choice adds value, celebrating the building’s heritage while
modernising it with incredible attention to detail.” Reach CM has a strong
supply chain in Scotland. Other than specialist/bespoke items, Reach CM is
responsible for procuring all other sub-contractors and materials (See
Appendix 5). 
4.7 The proposed primary consultants are: 
• Architect: Convery Prenty Shields, Glasgow 
• Structural Engineers: Harley Haddow, Edinburgh 
• Mechanical & Electrical Consultant: Butler Consulting, Glasgow 
Q-What is the detailed project timeline with key milestones and
dependencies? 
A- A master programme and a critical path programme were provided. These
assume a start on site date of 2 February 2026, with a practical completion
date of June 2027. 
Q-What is your contingency plan for cost overruns or delays? 
A-The programme is based on extensive knowledge and experience of large-
scale mixed-use developments, with specific understanding of listed buildings
and the complexities inherent within hotel infrastructure. 
Cost over-run: a contingency is included within the programme. Programme
delays: a two-month contingency has been built in the master programme.
The development is managed by the master programme, which cannot be
extended without prior approval. The contractor is heavily incentivised to
deliver in accordance with budget and programme. To manage programme
delivery, a further three look-ahead programmes: three months, 6 weeks and
1 week have been included to gives visibility. A competent and reliable supply
chain in Scotland has been identified to assist in delivery with a very tight
control over the procurement programme.

Page 8

Q-How do you manage community engagement and planning risk? 
A-The developers have managed several complex major applications. These
include large-scale developments, listed buildings, and change of use
applications, all of which involved stakeholders with complex and competing
needs, along with political and press interest. The community engagement
would be managed by a PR team. However, in sensitive situations, directors
would manage stakeholder engagement to fully understand the importance
and sensitivities. This is managed by running community outreach events to
explain plans in detail, to answer any questions, and to address any concerns
before they turn into objections. 
Q-How do you ensure compliance with building regulations and environmental
standards? 
A-To ensure compliance with building regulations and environmental
standards, the directors engage at an early stage with the design team
(including architect, building control, M&E consultants, structural engineers
and fire consultants) to set the performance standards required, and
incorporate these standards into the final design. This enables the design to
be compliant with the relevant legislation, ensuring the safety and structural
integrity of the building. A building control tracker is created and maintained
with the building control consultant monitoring progress against key tasks.
Sustainable practices are embedded into specification, procurement and
construction methods. Low-impact materials are favoured, as well as off-site
manufacture, and energy-efficient equipment. Habitat disruption will be
minimised. A project-specific waste management plan will be developed
enabling site waste to be separated into channels for recycling or correct
disposal. Performance will be monitored regularly to promote transparency
and accountability. Materials will be chosen that are fit for purpose, which
have robust characteristics suitable for the building, and longevity. The project
at Perth will discreetly integrate high levels of technology to prioritise low
energy use, such as those offered by Nonius Technology.
This would be sensor-based to enable heating and lighting to automatically
shut off in unused spaces, for example. This holistic strategy ensures that
construction progresses responsibly, with minimal environmental footprint. 
Q-What types of insurance are in place for the project (e.g. professional
indemnity, construction risk)? 
A-Reach CM holds Employers Liability, Public Liability, Products Liability,
Professional Indemnity, and Contractors All Risks policies. These are then
reviewed and further tailored for each project, to ensure that there are no gaps
in cover. 
Q- What governance structures do you have in place for project oversight,
including board composition, frequency of meetings, and reporting
mechanisms? 
A-The following information has been provided:
Design & specification: this element is substantially complete and includes
furniture specification.

Page 9

Project oversight: this is delivered by monthly diarised project review
meetings, which look critically at construction progress against programme,
cost to date, and cost to complete. Procurement programme and any risks or
liabilities that have become apparent in the last month will also be monitored.
The meetings will be attended by board directors and senior site-based staff.
The business conducts a weekly all-hands meeting as an information share
platform. A software programme called Asana is used throughout the
business and is also integrated into Reach CM as the contractor. Asana
enables daily task and project management, offers top-down oversight, and
generates project reports. Asana manages tasks that may be overdue but is
also used to identify risk and how that risk is managed and mitigated on a
daily and weekly basis. 
Q-How do you ensure transparency and accountability in decision-making?
How are key stakeholders (e.g. investors) engaged in governance and
oversight? 
A-Transparency and accountability are managed through the reporting
structures and effective oversight of the business using the appropriate tools.
The operations will be with a ‘single point of responsibility’ mindset, which
offers autonomy, accountability, and a strong focus on delivery. The business
is focussed on measuring what matters, and it uses the Objectives and Key
Results (OKR) model, which provides objective transparency. Generally, the
lenders are the major stakeholders, and a strong positive relationship is
maintained throughout. Depending on the project, there may also be other
statutory authorities who would also adopt this position. The developers have
worked extensively with local authorities, and with listed and heritage building
organisations. They indicated that they are a details-oriented business with
effective communication, trusted by stakeholders and that trust is based on
transparency, with high quality data delivered in anticipation of their needs. 
4.8 Based on the review of the information provided, we consider that the project
governance and operational delivery risks to the Council and the project are
low. It is proposed mitigate the risks by requesting that full planning
permission, building warrant and all necessary consents be secured. In
addition, clear communication and monitoring mechanisms will be established
to ensure transparency in relation to costs, investment, and supply chain
during the construction delivery phase. 
Overall assessment 
4.9 Based on the information provided by Lock Terrace Ltd and its directors, the
overall risk to the Council and the proposed development is assessed as
medium. To address and manage these risks effectively, a series of mitigation
measures will be embedded within the development agreement. These
measures will be tied to key milestones that must be achieved prior to the
granting of a development lease for construction works and which
development lease will provide for the transfer of title on successful
completion.

Page 10

The required milestones include: 
- Securing full planning permission.
- Obtaining a Building Warrant.
- Acquiring all other necessary statutory consents.
- Completion of a full independent viability assessment by a third party,
including market analysis of gross development value, development cost
breakdown, professional fee review, and profit margin evaluation.
- Submission of evidence confirming full project funding, including proof of
equity aligned with the proposed debt-to-equity ratio.
- Establishment of a stage payment agreement to ensure £1.9m grant
funding is released only upon verified expenditure by the developer. This
will include proof of payment to subcontractors as part of the audit
process.
- Establishment of communication and monitoring mechanisms to ensure
transparency in relation to costs, investment, and supply chain during
the construction delivery phase. 
4.10 Based on Lock Terrace Ltd and its directors’ experience in this sector allied
with their commitment and willingness to proceed, we believe that they are
capable of delivering this project to its conclusion. 
4.11 Based on the due diligence review and the proposed mitigation measures, it is
recommended that the Council agree to nominate Lock Terrace Ltd and its
directors as the developer for the proposed ‘Heiton’ hotel development at 1-5
High Street, Perth. 
5. Conclusion 
5.1 The building at 1–5 High Street, Perth, previously used as Council offices, has
been declared surplus to requirements. Its proposed transformation into a
hotel represents a strategic opportunity to enhance Perth’s tourism
infrastructure, stimulate local economic growth, and preserve a historically
significant asset within the city centre. The redevelopment is expected to
generate new employment opportunities, increase visitor footfall, and support
surrounding businesses. 
Although initial progress was delayed due to the Covid-19 pandemic and
changes in the status of the original preferred bidder, a comprehensive due
diligence review has now been completed. It is therefore recommended that
the Council nominate Lock Terrace Ltd and its directors to take forward the
‘Heiton’ hotel development, unlocking the site’s full economic potential. 
6. Impact Value Assessment 
Appendix 6

Page 11

7. Appendices  
Appendix 1: Brochure of ‘The Heiton’
Appendix 2: Floor Plans of ‘The Heiton’
Appendix 3: Brochure Lock Terrace
Appendix 4: Brochure Lock Terrace Listed Buildings
Appendix 5: Brochure Reach CM
Appendix 6: Impact Value Assessment
Appendix 7: Committee Report (20/128) Revised Plan