Strategic Investment and Composite Capital Budget Update 2025/26 - 2030/31

Perth and Kinross Council · 26 February 2025
Back to Perth and Kinross Council — 26 February 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PERTH AND KINROSS COUNCIL
Our vision is a Perth and Kinross where everyone can live life
well, free from poverty and inequality
___________________________________________________________________
Committee or Board: Perth and Kinross Council
Date of Meeting: 26 February 2025
Report Title: Strategic Investment and Composite Capital Budget
Update 2025/26 to 2030/31
Report Number: 25/37
Report Author: John Jennings, Senior Accountant
Gregor Walker, Asset Management Officer
Organisational Lead: Scott Walker, Chief Finance Officer
___________________________________________________________________
1. Purpose
1.1 The purpose of this Report is to outline the proposed budget for the
Composite Capital Programme for the six years from 2025/26 to 2030/31.
1.2 Sections
1. Purpose
2. Recommendations
3. Background
4. Asset Management Plans and Strategy
5. Capital Budget 2025/26 to 2029/30
6. Capital Budget 2030/31
7. Funding Strategy
8. Impact Value Assessment
9. Appendices
2. Recommendations
2.1 It is recommended that the Council:
(i) Approves the adjustments to the existing Capital Budget from 2025/26 to
2029/30 set out in Section 5.
(ii) Approves the estimated new capital resources available for the year
2030/31, as detailed at Section 6 of this report and included in
Appendix I.

Page 2

(iii) Approve the proposed Composite Capital Budget for 2030/31 outlined in
Section 6
(iv) Approve the six-year Composite Capital Budget for 2025/26 to 2030/31
as shown at Appendix II of this report.
3. Background
Historic Information/Context
3.1 At its meeting on 28 February 2024, the Council approved the six-year
Composite Capital Budget for 2024/25 to 2029/30 (Report 24/64 refers). The
Finance and Resources Committee subsequently approved updates to this
programme throughout the year. In order to maintain a six-year budget,
proposals for 2030/31 are now required to be developed. The estimated
resources and the process for this year are outlined below.
3.2 This report outlines the estimated resources available for the Composite
Capital Budget and details the proposed Composite Capital Programme for
the years 2025/26 to 2030/31, thus maintaining a six-year programme.
4. Asset Management Plans and Strategy
4.1 In January 2024, Council approved the Corporate Asset Management
Framework (Report 24/18 refers). This included an overarching Corporate
Asset Management Policy and Strategy which set out the corporate approach
to the management of assets to deliver the Council’s strategic priorities.
4.2 This is supported by 5 stream asset management plans covering:
 Community Greenspace
 Fleet
 ICT
 Property
 Roads
4.3 The asset plans describe how individual asset streams adhere to the
corporate policy and provide an assessment of the 30-year investment
requirement for each asset stream based upon life cycle planning for the
existing asset base and existing levels of service. The asset plans are
intended to be iterative documents and will be updated on an annual basis to
incorporate additional investment and disinvestment decisions.
4.4 Asset management strategy and planning for the Council’s social housing
stock is undertaken through the separate Strategic Housing Investment
Programme (SHIP) which is developed in consultation with Council tenants
and funded through the Housing Revenue Account.
4.5 The critical importance for service delivery of the Council’s assets and
infrastructure is reflected within the 5 stream asset management plans.

Page 3

The asset plans also highlight the long-term financial challenge presented
through investing in and operating these assets.
4.6 Detailed information on each asset stream was set out within the Corporate
Asset Management Framework (Report 24/18 refers).  This position has been
updated and the total investment required, based on existing service levels,
not updated for inflation, is now £3.324 billion which is set out in Table 1
below:
Table 1: Corporate Asset Management Overview and Life Cycle Planning
Investment Projections (30 Year Plan) (2025/26 -2053/54)
Asset Stream Current Asset
Base
Lifecycle Planning Investment
Projections (30 Year Plan)
Community
Greenspace
1,649 greenspace
sites
£0.123 billion
Fleet 2,535 items of fleet
and mechanical
equipment
£0.102 billion
Information and
Communication
Technology (ICT)
23,025 items of
hardware and all
corporate software
£0.220 billion
Property 970 sites within the
property estate
£2.202 billion
Roads 1,548 miles of
carriageway and
related
infrastructure
£0.677 billion
Total £3.324 billion
4.7 The Corporate Asset Management Plan and Strategy underlines the
importance of the Council committing a significant element of its available
Capital resources on a recurring basis towards investment in our existing
assets and infrastructure.
4.8 It is anticipated that the Strategic Investment Advisory Group (SIAG) will take
part in a workshop late this year. The purpose of this session will be to
provide an overview of how the Council can take steps to address the gap
between the investment requirements and funding. This may involve both
investment and disinvestment in assets. Furthermore, the SIAG will consider
future capital investment / expenditure plans. Any future proposals for future
capital investment will be presented to future meetings of the Finance and
Resource Committee or the Council for final decisions.

Page 4

5. Capital Budget 2025/26 To 2029/30
Adjustments to Resources
5.1 Following receipt of the latest funding information from the Scottish
Government, there are several adjustments affecting the resources in the
current approved programme.
5.2 With the Scone Flood Protection Scheme no longer being included in the
Scottish Government priority list, no further grant funding is available for the
scheme. Consequently, the Capital Grant settlement for 2025/26 includes the
removal of grant for the Scone scheme, with only historic expenditure
receiving grant (at 80%), together with some rephasing of grant for the other
schemes.
5.3 It is therefore proposed to remove the Scone Flood Protection Scheme from
the approved programme, with a reduction of budgeted expenditure of
£767,000 and grant income of £576,000 in the years 2024/25 to 2028/29,
resulting in a net saving of £191,000. This amount has therefore been added
to the total available resources for the Programme outlined at Section 6
below.
5.4 Surface drainage works are currently being investigated at Scone in
conjunction with the Flood Protection works, and it is also anticipated that a
revised scheme will be submitted for consideration for inclusion in a future
Capital Budget once it has been further developed.
5.5 The Scottish Government Capital Grant settlement for 2025/26 also includes
£665,000 of ring-fenced grant for Active Travel. This is an increase of £65,000
from the amount previously assumed for 2025/26, and it is therefore proposed
to increase the Active Travel programme by this amount.
6.6 However, the General Capital Grant for 2025/26 is £255,000 lower than
previously assumed, and this has also been incorporated into the overall
available resources outlined at Section 6.
6.7 A summary of the adjustments to the previously assumed Resources in the
current programme are shown in Table 2 below:
Table 2 – Reduction in Assumed Resources 2025/26 to 2029/30
£’000
Reduction in Grant - Scone Flood Protection Scheme (576)
Reduction in General Capital Grant (255)
Reduction in Budgeted Expenditure – Scone Flood Protection
Scheme
767
Reduction in Available Resources 2025/26 to 2029/30 (64)

Page 5

Adjustments to Approved Budgets
6.8 The Finance and Resources Committee approved the last Capital Monitoring
report for the Composite programme at its meeting on 5 February 2025
(Report 25/25 refers), covering the period up to 2029/30. It is proposed to
make one further adjustment to the current approved Programme, before the
remaining available resources as outlined at Section 6 below are allocated.
6.9 Technology Enabled Telecare was added to the Programme in 2022/23 in
order to allow for the replacement of the old analogue Community Alarm
system and equipment which were no longer being supported, with digital
equipment. This was included as an annual programme, with the refreshment
of digital equipment required in later years. However, it was not included
within the Capital Budget report in February 2024, therefore there is currently
no allocation for 2029/30. It is therefore proposed to include £1 million in
2029/30 to ensure the programme can continue across all years.
7. Capital Budget 2030/31
Resources
7.1 It is currently estimated that the Council will have total new capital resources
of £40.750 million available for the Composite Programme in 2030/31 which
is summarised in Table 3 below.
Table 3 - Estimated New Resources 2030/31
2030/31
£m
Long Term Borrowing 26.000
General Capital Grant 12.150
Ring Fenced Grant – Active Travel 0.600
Developer Contributions 2.000
Property Disposals 0.000
TOTAL RESOURCES 40.750
7.2 Under the Local Government in Scotland Act 2003 and the Prudential Code,
the Council is required to determine how much it can afford to allocate each
year for capital expenditure. This includes determining how much it can afford
to borrow, based on its Loan Charge Budgets and forecasts of interest rates.
Based on the approved Loans Fund and Capital Fund Strategy within the
Medium-Term Financial Plan, including the top-slicing of 1.25% of Council Tax
to increase the Loan Charges budget, it has been determined that £26 million
of new borrowing is available to support the 2030/31 Capital Programme.
7.3 The level of General Capital Grant for 2030/31 has been estimated at £13.75
million. After allowing for the annual amount which is applied in the Revenue
Budget (£1.6 million), the balance of £12.15 million is available for the
Capital Programme, and included in Table 2. These amounts are based on
recent allocations, with no inflationary uplift applied.

Page 6

It has also been assumed that the ring-fenced Capital Grant for Active Travel
will continue in the years to 2030/31 at an assumed level of £600,000 each
year. However, it should be noted that the Scottish Government has not
announced allocations for Capital Grants beyond 2025/26, therefore there
remains uncertainty over the actual level to be received in each subsequent
year to 2030/31.
7.4 Developer Contributions of £2 million have also been assumed in 2030/31.
This is slightly lower than estimates included each year in the current Capital
Programme, however the amounts receivable are uncertain and variable, and
are dependent on the rate of local house building. There are no Third Party
and Revenue Contributions assumed at this stage. This reflects the
expenditure proposals outlined in Section 6 relating to annual programmes
only. Contributions may therefore be identified once specific work
programmes are developed over time.
7.5 There are also no receipts assumed at this stage from property disposals,
with fewer surplus properties being identified in recent years. This will also be
kept under review over the coming years.
7.6 In addition, Third Party Developer Contributions of £1 million and receipts of
£650,000 have been included in the programme for 2030/31 in relation to the
Perth Eco-Innovation Park at Perth West. These are part of the original
funding strategy for this project, with receipts forecast for several years
beyond the end of current budgeted 6-year programme. Therefore, these
receipts are ring-fenced for this project and are not available for distribution
and have not been included in the New Resources in Table 2 above, however
they have been included in the total Resources at Appendix I.
Expenditure
7.7 Given the constrained resources available, it is proposed that the available
funds are allocated only to ongoing annual rolling programmes in 2030/31 in
line with recent annual allocations, with no further adjustments for new
projects. The proposed annual allocations are set out in Table 4 as follows:
Table 4 - Proposed Allocation of Resources
2030/31
£m
Structural Maintenance 9.500
Bridges and Parapet Refurbishments 1.500
Footways 0.400
Road Safety 0.450
Traffic Signals 0.120
Street Lighting 0.600
Play Area Improvements 0.500
Community Greenspace 0.250
Cemetery Extensions 0.200
ICT Infrastructure 5.000
Supporting Digital and Data Analytics 1.650

Page 7

Schools Audio Visual Equipment 0.200
Property (including School Estate) 11.000
Health and Social Care – OT Equipment 0.300
Health and Social Care Telecare 1.000
IT Licences (HSC and ex-Communities) 0.170
TOTAL 32.840
7.8 The Scottish Government ring-fenced Capital Grant for Active Travel projects
(previously Cycling Walking and Safer Streets) has also been included in
2030/31. Any differences in the actual amount of grant allocated in each year
will be adjusted once the allocations are announced.
7.9 A summary of the overall proposed allocations from the available resources
are shown in Table 5 below:
Table 5 – Summary of the Allocation of new Resources
£ million
Annual Allocation for Programmes 2030/31 (Section 6.7) 32.840
Active Travel – Ring Fenced Expenditure 2030/31 (Section 6.8) 0.600
Increase in Technology Enabled Telecare 2029/30 (Section 5.9) 1.000
Reduction in Resources 2025/26 to 2029/30 (Section 5.7) 0.064
Unallocated Resources 2030/31 (see Section 6.10 below) 6.246
TOTAL NEW RESOURCES 2030/31 (Section 6.1) 40.750
7.10 The Finance and Resources Committee on 5 February 2025 (Report 25/25
refers) approved the principle of retaining any budget savings as Unallocated
Resources, pending the identification and consideration of future priorities. It
is proposed that this principle is extended, with the balance of available
resources of £6.246 million added to the Unallocated Resources in 2030/31.
7.11 In addition to the programmes above, it is proposed to include several projects
in 2030/31 funded by “Prudential Borrowing”, and the proposed projects are
as follows:
 Fleet Vehicle Replacement Programme - £3.5 million for Vehicle
Purchases, less £350,000 of estimated vehicle disposals.
 Wheeled Bin Replacement Programme - £255,000 for Domestic wheeled
Bins and £25,000 for Commercial Wheeled Bins.
 Recycling Skips and Containers - £75,000
 Litter Bins - £55,000
 Energy Conservation and Carbon Reduction - £150,000 for each year
2028/29, 2029/30 and 2030/31.
7.12 All the above projects are included in the proposed Composite Capital Budget
for 2025/26 to 2030/31 shown at Appendix II. This shows that the Council’s
proposed total gross investment on the Composite Capital Programme in the
six years to 2030/31 amounts to over £503.628 million.

Page 8

8. Funding Strategy.
8.1 The funding of the Composite programme will be managed by the
continuation of the Capital Fund Strategy over the medium to long term. This
includes continuing the top-slicing of 1.25% of the Council Tax each year to
increase the Loan Charges Budget. Updated Loan Charge estimates will be
included in the proposed Prudential Indicators within the Annual Treasury
Strategy report to be considered by the Council on 5 March 2025, whilst
updated Loans Fund and Capital Fund estimates show that the proposed
capital plans in this report are affordable, prudent and sustainable.
9. Impact Value Assessment
Strategic Investment and Composite Capital Budget Update 2025/26 to
2030/31
10. Appendices
Appendix I   – Capital Resources 2025/26 to 2030/31
Appendix II  – Proposed Composite Capital Budget 2025/26 to 2030/31