Appendix A
Transformation and Change Programme – Phase Two Programme Update
Project Title Project Overview and expected
outcomes
Progress Update / Key Milestones
Customer
Services
Consolidation
To develop a new model for customer
services by adoption of a customer-
centric approach to customer contact
management which will substantially
simplify our current arrangements;
enrich jobs and empower customer
service staff to satisfy most requests
at first point of contact. The model will
provide the opportunity to blend digital
customer channels, assist vulnerable
citizens by an appropriate channel,
operate more effectively in and across
localities, to achieve more with less
resources, less effort, and less
bureaucracy. 
We carried over some final actions of
the consolidation of customer services
into phase two, for example moving
housing repairs customer service to
consolidated service and ensure
training programmes are in place for
this transition. Further development of
customer service programme for all
PKC employees – following on from
‘Eyes and Ears of PKC which will align
with our cultural change programme. 
Leadership
Phase 2
Finance
Consolidation
The programme will pick up on the
Leadership Phase one work including
the senior leadership restructure,
consolidation of key corporate
services and cultural change.
Carrying over consolidation into full
service redesign projects in areas
such as Strategy, People and
Performance, Finance & Business
Support and Property. Includes
organisational cultural change
programme including workstreams to
strengthen the five foundations of
leadership. 
Key workstreams are being progressed
and on track in terms of workforce
planning and service redesign with
workshops and support being provided
to ensure consistency and progress. 
Full cultural change plan for phase two
is in development after the success of
the Employee Offer Experience and
Leadership Development initiatives.
Working
Smarter 
The Working Smarter programme has
a number of different projects all
related to the strategic and integrated
approach of people, technology and
crucially, property – looking to improve
how we integrate all three for the best
outcomes in relation to facilitating
better productivity, embracing
technology, more effectively using our
estate and buildings and enhancing
employees experience through
flexible operating models. 
This programme includes all of the work
which has been underway to secure
Pullar House as a hub for different
organisations and looking at how we
purchase this property with a view to
taking over from September 2025.
Members will be fully aware of detailed
progress in this area.
In addition, the project team have also
been working on a number of other
projects including the planning and
refurbishment of other city centre office
space with a consultant appointed to
agree a scope and set out options. A
project to take forward the ownership
and associated actions around Kinnoull
St Car Park which requires agreement

Page 2

on policy for parking as well as
considering other aspects of this
property. This project also covers all of
the Hybrid working arrangements in
place and the communication and
engagement required to implement and
embed.   
Digital
Transformation
This programme of work consists of
two main projects: 1. Artificial
Intelligence (AI) which is intended to
position PKC at the forefront of digital
transformation, driving efficiency,
enhancing service delivery and
fostering innovation.  2. Business
Systems Rationalisation to review all
council business systems and
applications and give an overview of
current management arrangements,
resources required, support and
development needed and make
recommendations for a new Digital
operating model in future. 
The AI project is underway and a full
EM briefing is scheduled for 10 March
2025. A pilot has been carried out,
extensive training has taken place with
Senior Officers and agreement for
further pilot licences in selected teams
is being rolled out.
In relation to the business systems
rationalisation project, this has been
ongoing since mid 2023 with all
baseline evidence collated and
workshop sessions with system owners
ongoing. It also encompasses the
FLARE system replacement
workstream and this is now at the
design stage with timescales being met
on progress.
Additional
Support Needs
To transform ASN provision in
education to deliver best value linked
to best practice, establish clear ASN
pathways, develop availability of ASN
provision at all levels across all areas
of the authority, create capacity for
increase of future PKC placements,
reduce the number of pupils placed
out with PKC ASN provision, design a
sustainable transport process, and
provide regular reporting to help
monitor the financial position, help to
comply with legal requirements placed
on the local authority, and ensure
quality provision is delivered. 
This is a five year programme with fully
developed workstreams and a number
of actions currently in progress. Regular
meetings with our PMO has established
clearly defined outcomes and critical
success factors with a planned
completion date of 31 October 2028.
The project is currently in the
‘Discovery’ phase with most current
workstream tasks due for completion in
the spring. In line with our service
design approach, we will shortly move
to the design and delivery stage 
Whole Family
Wellbeing
programme
The WFWB programme will ensure an
increase in universally accessible
early help and support, delivered
where and when it meets families'
needs.  Aiming for a better collective
awareness of available support and
how to access it, for both families and
professionals, it will aim to provide
support as "joined up" and limit the
number of professionals and services
individually involved with families. It
will also look to provide families with
choice about support ensuring they
This project has been ongoing since
mid 2023 and has also been the subject
of an Elected Member briefing in
November 2024 which allowed for
discussion on progress and ongoing
workstreams. There are five
established workstreams already
making good progress with positive
outcomes being experienced including; 
1. Children and families at the
centre (engagement,
empowerment, co-design)

Page 3

are involved in decisions that affect
them and that there is increased
collaboration between services and
organisations that support families
(including adult services and third
sector).
Encourage increased engagement
with, and participation from children,
young people and families in
designing and developing services
and support, ensuring a clear and
shared understanding of the needs of
families across the whole system
Embed the key principles of holistic
family support and early intervention
and prevention within structures and
systems (stigma-free, needs-based,
rights-led), encouraging and
empowering staff to develop
innovative family support solutions in
conjunction with the families they
support.
Improving capacity within the
workforce to respond to the needs of
families in a holistic way, through
effective signposting and support. 
2. Access to services (mapping of
service provision, FORT referral
system and development of
services directory)
3. Service delivery (upscaling
existing services, developing
new services and influencing
partners)
4. Systems leadership (links with
other policy areas and funding,
culture, vision, sharing good
practice)
5. Support for the workforce
(training, capacity building,
developing networks and
upskilling) 
Public Transport To develop a plan for a transport
model that meets the needs of all our
communities which is affordable,
sustainable, efficient and effective.
This model will cover the provision of
local bus services, mainstream home
to school transport, ASN home to
school transport, HSCP and children
and families transport. 
This project is on track and a number of
workstreams progressing.
A Project Steering Group has been
implemented and consultants appointed
who are undertaking a baseline
assessment of current needs, taking
into consideration feedback from
stakeholders and communities. There
are also a number of workshops
scheduled to ensure that all areas of
PKC who deal with transport
(education, children’s services etc) are
included, and a strategic approach is
being adopted. 
Community
Engagement
Combining the multi-disciplinary
locality working (MDLW) programme
and our community engagement
transformation project to strengthen
the efficiency and effectiveness of
community engagement and
empowerment across the Council.
This will allow us to find new ways for
the Council to deliver services in a
more joined up and flexible way, being
more responsive to the needs within
local communicates. Working together
in partnership to address needs of our
There are a number of workstreams
within this project and the MDLW has
been ongoing for some time and
making good progress with Scottish
government funding awarded, current
recruitment for a new project manager
underway and a renewed focus in
terms of workstreams. In addition,
workshops are being held to start
planning a new community engagement
aspect which builds on the foundations
of all of the involvement and
participation with communities, families

Page 4

communities with a clear focus on
early intervention and prevention will
allow us to keep working to tackle
discrimination and prejudice,
promoting equal opportunities for all
and creating a fairer P&K. 
and individuals which is part of the
Councils day to day role.  A workshop
was held in early Feb to develop plans
for an inclusive engagement event in
March 2025 to determine a strategy
and action plan moving forward over
the next few years. 
Employability To develop an implementation plan to
deliver a strategic and co-ordinated
employability service for PKC.
Designing a new model that makes
best use of the current expertise, skills
and resources to ensure a more
cohesive and effective service. This
will involve maximising the reach and
impact of our collective resources and
delivery of services and operating in a
more connected and integrated way
putting people and their needs at the
centre of the redesign. 
This project is on track in relation to
research, baseline data and
benchmarking work. There is still some
progress to be made in relation to our
engagement and redesign workstreams
which will get underway in February
2025 with a designer’s workshop and
will be followed on with a full design
event before the end of the financial
year. 
Zero Waste &
Operations
A review of waste strategy and waste
management arrangements to deliver
national initiatives, improved
outcomes and realise best value and
service efficiencies. This programme
has a number of workstreams
including: Operations resourcing;
commercialisation review; circular
economy strategy and service design
beyond twin stream; schools recycling
improvement, fleet transformation and
operational asset review. 
This is a phase two project which was
initiated in 2024 once the new Strategic
Lead and key senior manager roles
were all in place with induction
underway. A project proposal form has
been developed with Project Managers
taking forward action plans in the
various workstreams. The
commercialisation project is on track
and some short term service
improvement has already been
identified as well as savings in other
areas of the programme. A full
scheduled workplan is currently being
developed with realistic timescales and
milestones being identified. 
ALEO Review
Project
To find the best model of delivering
leisure and culture services to people
across Perth and Kinross within
current financial climate.
• To recommend a future
delivery model best suited to
future needs for ALEO’s that is
capable of:
Optimising PKC investment in
leisure and culture services.
• Increasing back-office
efficiencies, including with
other partners where
appropriate (for example Perth
and Kinross Heritage Trust,
This project is on track with the
following progress being made: 
Joint Project Group in place with
representation from all ALEO’s and a
collaborative approach to the review
and workstreams associated
An options appraisal of new structural
model for ALEO’s looking to secure
future financial sustainability is due to
be started late March 2025 
Regular updates and reports to full
Council with an options appraisal and
recommendations due in September
2025.

Page 5

Pitlochry Festival Theatre).
Growing and diversifying new
income streams.
• Recommending an appropriate
constitutional/governance
structure for any new delivery
model on the basis of options
appraisal (sole member, SCIO,
mutual etc). 
Tayside
Contracts
Review
The review will consist of looking
across the whole Tayside Contracts
portfolio and reviewing the efficiency
and effectiveness of service provision,
delivery and considering alternative
options. 
This project is part of our phase two
programme, from late 2024 and is
currently being developed with a
number of significant areas of work to
be considered and explored including:
SLA Review, (soft services – school
meals, cleaning, crossing patrollers,
facilities management, roads and
flooding. Progress will be reported as
part of Transformation & Change
updates. 
Commissioning
& Procurement
Consolidation
(Third Sector
Review)
To design and implement a new
operating model for strategic
procurement and commissioning to
improve efficiency and optimise the
value and benefits of our purchasing
power. 
Helping us to better align spend with
need and address pressures of
changing demands. 
Optimising the public value of the
procurement function and
consolidated relevant skills and
expertise across the organisations. 
This project is reporting the following
achievements to date:
• New five-year Sustainable
Procurement Strategy approved
• Design of new “test of change”
operating model
• Contract and Supplier
Management Toolkit
implemented
• Digital Category Strategy
developed (awaiting
Procurement and
Commissioning Board approval)
• Plans in place to develop
Business Partnership model
• Development of PowerBI
reporting tools (Spend Analysis
and Management Information
Platform Scotland (MIPS))
• Schools Savings Working Group
created to work on delivering
cost savings and efficiencies. 
Completion of a number of mini-
projects under this including
janitorial supplies product
rationalisation and award of
commitment contract.
• Identification of £30k of savings
related to third sector funding.