Perth And Kinross Council 
Council Committee 
4 December 2024 
SOUTH KINROSS FLOOD PROTECTION SCHEME 
Report by Strategic Lead – Environment and Infrastructure 
(Report No. 24/346) 
1. PURPOSE 
1.1 This report provides an update on the progress of the South Kinross Flood
Protection Scheme and proposes that the Council takes a preliminary
decision under the Flood Risk Management (Scotland) Act 2009 to confirm
the proposed Scheme without modification. 
2. RECOMMENDATIONS 
2.1 It is recommended that Council: 
(i) Notes the valid objections and the Environmental Impact, as outlined in
this report;
(ii) Makes a preliminary decision to confirm the proposed South Kinross
Flood Protection Scheme without modification as outlined in this report;
and
(iii) Authorises the Strategic Lead - Environment and Infrastructure to carry
out all necessary steps to progress the statutory process, including: 
a) Giving notice of the preliminary decision to confirm the Scheme to
those landowners who submitted an objection and to the Scottish
Ministers;
b) Participating in a public local enquiry or to arrange a local authority
hearing as directed by the Scottish Ministers.
c) Bringing a further report to Committee once b) has been concluded. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background/Main Issues 
• Section 5: Proposals 
• Section 6: Conclusion 
• Appendices

Page 2

4. BACKGROUND / MAIN ISSUES 
4.1 The approach to tackling flooding in Scotland has changed in recent years.
Under the Flood Risk Management (Scotland) Act (the 2009 Act), SEPA and
lead local authorities publish Flood Risk Management (FRM) Plans and Local
FRM Plans. These documents set out a range of actions that SEPA and
responsible authorities will take to manage and, where possible, reduce the
risk of flooding over the following six-year period. 
4.2 Although public authorities are expected to take a proactive role in managing
and, where achievable, lowering flood risk, the primary responsibility for
avoiding or managing flood risk still remains with land and property owners.
The 2009 Act does not alter this. Individuals, businesses and communities
must, therefore, play a critical role in making themselves more resilient and
helping to reduce the impact of flooding. 
4.3 The Climate Change & Sustainability Committee approved the publication of
the updated (or Cycle 2) Forth Estuary Local FRM Plan on 19 December 2022
(Report 22/307 refers). The published Forth Estuary Local FRM Plan can be
viewed at the following link: http://www.pkc.gov.uk/frmplans 
4.4 Since the publication of the FRM Plans and Local FRM Plans, the Council has
been moving forward with the implementation of the actions set out therein. 
4.5 The 2009 Act provides local authorities with discretionary powers to promote
new flood protection schemes. Only those flood schemes which have been
included in the published FRM Plans, the Local FRM Plans, and the national
priority list will be taken forward in each six year period. 
4.6 One of the key actions included within the Forth Estuary Local FRM Plan is to
implement a flood protection scheme in South Kinross. The flood scheme was
included as the 28th highest scheme on the national priority list. 
4.7 The Scheme, therefore, attracts capital grant assistance. In general, the
Scottish Government will provide 80% of the project cost (at tender stage)
with the Council contributing the remaining 20%. 
4.8 The Scottish Government and COSLA have set a funding deadline for flood
protection schemes. All Cycle 1 flood schemes must have a contractor
appointed by 31 March 2026 to continue to attract capital grant assistance.
However, Schemes that are subject to objection/s will not be disadvantaged
from the point a preliminary decision is notified to Scottish Ministers. The
clock will stop at this stage until the conclusion of either a public local enquiry
or local authority hearing; a contractor will only need to be appointed as soon
as practicable after the valid objections have been addressed. 
Flood Risk Management in South Kinross 
4.1 Kinross is located in the River Leven catchment within Potentially Vulnerable
Area (PVA) 02/10/03.

Page 3

There are three watercourses in this area - the South Queich, the Gelly Burn
and the Clash Burn – which all flow into Loch Leven to the east. There has
been a history of flooding in the town, and it is estimated that 194 businesses
and residential properties are currently at risk of flooding. 
4.2 Perth and Kinross Council engaged consulting engineers to investigate and
promote a flood protection scheme for South Kinross. The progress of the
Scheme has been periodically reported to the former Environment, Enterprise
and Infrastructure Committee and more recently the Environment and
Infrastructure Committee. A full list of relevant committee papers is provided
at the end of this report. 
4.3 On 27 November 2023, the Council’s Climate Change & Sustainability
Committee was provided with an update on the progress of the South Kinross
Flood Protection Scheme (Report 23/332 refers). Amongst other matters, the
Committee approved that: 
i) The recommended proposals were adopted as the Council’s preferred
flood scheme
ii) The recommended scheme be published under the Flood Risk
Management (Scotland) Act 2009 and, subject to obtaining statutory
approval and funding remaining in place, progress to detailed design and
construction. 
Preferred Flood Scheme 
4.4 The preferred scheme involves the construction of flood walls and
embankments along the South Queich, culvert improvements on the Clash
Burn and a flood storage embankment adjacent to the M90 motorway services
at Turfhills. Property flood resilience measures will be adopted for a small
number of properties next to Loch Leven. 
4.5 The preferred scheme has been designed, as a minimum, to protect existing
properties up to the predicted 1 in 200-year flood event (the flood that has a
0.5% chance of occurring in any one year). 
4.6 A plan of the preferred flood scheme is shown in Appendix A and as
published, can also be viewed on the Council’s website at
https://www.pkc.gov.uk/southkinrossfloodschemedocs 
4.7 A public exhibition was held in Kinross on 28 September and 5 October 2023
and the local community was invited to view details of the flood scheme
proposals and record their views. A total of 41 people attended the public
exhibition, and 12 comment forms were submitted. The response to the
community public exhibition was generally positive with the majority of the
community being supportive of the proposed outline design for the flood
scheme. Further details are provided in the Section 4 of Annex in this report.

Page 4

Scheme Publication 
4.8 The notice for the South Kinross Flood Protection Scheme was published
under the Flood Risk Management (Scotland) Act 2009 on 26 March 2024. 
4.9 Those affected by the Scheme were notified and information (including an
Environmental Impact Assessment Report (EIAR)) was made available for
public inspection on 26 March 2024. The 2009 Act requires that a period of 28
days from the date of publication is allowed for objections; this period being
slightly increased to 30 days in relation to the EIAR. It is important to note that
late objections can still be submitted where it is ‘reasonable’ for the objection
to be made after the deadline. 
4.10 Two valid objections and three submissions were received. The three
submissions were from statutory consultees providing technical advice on the
EIAR and outlining any future environmental requirements or considerations.
The objections (both from landowners) were received by the Council within
the 28-day period. 
4.11 Officers have held extensive discussions with the two landowners, but their
objections have not been withdrawn. 
5. PROPOSALS 
5.1 As stated above, the Council has received two valid objections to the South
Kinross Flood Protection Scheme. Therefore, the Council must make a
decision under Paragraph 5 of Schedule 2 of the Flood Risk Management
(Scotland) Act 2009 to either: - 
a) Confirm the proposed Scheme without modification,
b) Confirm the proposed Scheme with modifications, or
c) Reject the proposed Scheme. 
5.2 Prior to making the above decision, the Council must consider: - 
a) the valid objections – these can be viewed in Appendix B.
b) The scheme’s environmental impact as set out within the EIAR. The
EIAR is available online at
https://www.pkc.gov.uk/southkinrossfloodschemedocs 
5.3 It is proposed that the Council make a preliminary decision to confirm the
proposed Scheme without modification. Once the preliminary decision has
been made, the Council is required to notify every person who submitted an
objection and the Scottish Ministers. 
5.4 Within 28 days, the Scottish Ministers will advise the Council if they will
‘consider’ the proposed Scheme (note that this period may be extended). If
this proves to be the case, then a public local enquiry will be held. If not, then
the Council will be required to hold a local authority hearing.

Page 5

5.5 This will either result in the Scottish Ministers or the Council taking a further
final decision to either:  
a) Confirm the proposed Scheme without modification,
b) Confirm the proposed Scheme with modifications, or
c) Reject the proposed Scheme. 
5.6 A notice of the final decision must be given to every person originally notified
when the scheme was ‘published’, every relevant objector, and as otherwise
required by the 2009 Act. 
5.7 A period of 6 weeks is then allowed for an appeal to be lodged by any person
affected by the confirmed Scheme. If no appeals are lodged, the Scheme
would become operative after this 6-week period. If an appeal is lodged this
would be presented to the Sheriff Court for litigation. The estimated timescale
for the process to be concluded would be approximately 4-5 months from the
date an appeal was lodged. It is anticipated that an appeal would be generally
limited in scope to incorrect factual material or errors in law. 
5.8 Subject to the Scheme being confirmed, consulting engineers will commence
the necessary detailed design work. Opportunities will be sought to offset the
delays addressing objections by undertaking limited detailed design work as
soon as practicable. Construction is anticipated to commence beginning 2027
(earlier if possible), assuming no further delay to the statutory process and the
detailed design programme. However, the lengthier statutory process set out
above will delay this. 
5.9 The 2009 Act does not require a separate planning application for flood
protection schemes. If such schemes are confirmed under the 2009 Act, then
the Scottish Ministers must also direct that planning consent is deemed to
have been granted. 
5.10 The proposal for a new formal Flood Protection Scheme is founded on the
principle of protecting existing assets. Any proposed development is covered
under planning legislation and is not considered in the determination of a
proposed flood scheme. 
5.11 It is, therefore, proposed that further work be undertaken when the Scheme is
confirmed towards writing to the Scottish Government setting out proposed
planning conditions and requesting that planning permission shall be deemed
to be granted and be subject to those conditions. 
6. CONCLUSION   
6.1 The purpose of the flood protection scheme is to manage flood risk in Kinross. 
6.2 The Scheme was published on 26 March 2024 and received two objections.
The objections have not been withdrawn following consultation.

Page 6

6.3 This report proposes that the Council consider the valid objections, the
Scheme's environmental Impact, and make a preliminary decision to confirm
the proposed Scheme without modification. 
6.4 The report also seeks the Council’s approval to authorise the Strategic Lead –
Environment and Infrastructure to carry out all necessary steps to complete
the statutory process. 
6.5 A further report will be brought before Committee once the statutory process
has been concluded. 
Authors
Name  Designation Contact Details
Russell Stewart
Rory Stuart
Senior Engineer
Engineer
01738 475000
EPLCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
Fraser Crofts  Strategic Lead (Environment
and Infrastructure)
25 November 2025 
APPENDICES 
• Appendix A – Plan of the Proposed Scheme
• Appendix B – Summary of Objections

Page 7

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  Yes 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This report supports the following priorities within the Community Plan 2022-
27. 
(i) Mental and physical wellbeing
(ii) Employability 
Corporate Plan 
1.2 This report supports the following objectives within the Corporate Plan:- 
(ii) People and businesses are increasingly able to prosper in a local 
economy which support low carbon ambitions and offers opportunities  
for all; 
(iii) People can achieve their best physical and mental health and have 
access to quality care and support when they need it; 
(iv) Communities are resilient and physically, digital and socially    
connected; 
(v) Perth and Kinross is a safe and vibrant place, mitigating the impact of 
climate and environmental change for this and future generations.

Page 8

2. Resource Implications 
Financial 
2.1 The 2009 Act requires the Scottish Government to have regard to the FRM
Plans and Local FRM Plans when allocating funds to SEPA and responsible
authorities. The Scottish Government, CoSLA and SEPA agreed the
distribution of capital funding to the actions identified nationally in the Cycle 1
FRM Strategies and Local FRM Plans. The following general arrangements
currently apply: 
1) Only works and schemes that are prioritised in the FRM Plans and Local
FRM Plans are eligible for capital funding. 
2) Flood protection schemes attract capital grant assistance of up to 80% of
their estimated project cost at tender stage from the Scottish
Government. Local authorities are required to fund the remainder of the
cost of flood schemes. 
3) The Scottish Government allocates capital funding to local authorities
engaged in flood risk management across Scotland. 80% of this capital
funding will continue to be allocated to flood protection schemes with the
remaining 20% to other actions within the FRM Plans, as detailed in the
Local FRM Plans. This 20% is distributed to the 32 Scottish local
authorities based on the number of properties at risk of flooding and the
estimated annual average flood damages. 
2.2 At present, the allocated capital grant is adjusted as flood scheme proposals
are developed. The estimated costs of flood schemes across Scotland will
therefore continue to be reported to the Scottish Government by local
authorities on an annual basis. 
2.3 These arrangements will come to an end in 2026/27 and are currently under
on-going review by the Scottish Government and CoSLA, due to the current
projected costs of Cycle 1 flood schemes across the country, and the
available funding. 
2.4 In the meantime, the Scottish Government and COSLA Leaders introduced
two deadlines to this process: 
• Any Cycle 1 schemes not published by 31 March 2024 will no longer be
funded - the South Kinross Scheme was published on 26 March 2024
and met this deadline.
• Any Cycle 1 schemes that haven’t appointed a main works contractor
by 31 March 2026 will no longer be funded. However, Schemes that
are subject to objection/s will not be disadvantaged from the point a
preliminary decision is notified to Scottish Ministers. The clock will stop
at this stage until the conclusion of either a public local enquiry or local
authority hearing.

Page 9

2.5 The conclusion of the national review into capital funding for flood schemes is
awaited. In the meantime, COSLA leaders have confirmed that it is expected
that the Local Government General Capital Grant will continue to include
resources allocated for flooding projects, and decisions on quantum and
distribution will be taken by Scottish Ministers and COSLA Leaders nearer the
time. 
2.6 The South Kinross Flood Protection Scheme has been prioritised in the
published Forth Estuary Flood Risk Management (FRM) Plan and Local FRM
Plan. The flood scheme is therefore receiving Scottish Government capital
grant assistance, and this will continue up to 80% of its value at tender stage
(provided the above deadlines are met). The Council is required to fund the
remainder of the cost of the scheme, assuming it remains economically viable. 
2.7 It should also be noted that the implementation of the flood scheme will be
some time away. On conclusion of the statutory process described above, the
detailed design of the preferred scheme will be progressed before the
necessary tender process to appoint a contractor to construct the scheme.
Construction is anticipated to commence beginning 2027 (earlier if possible),
assuming no further delay to the statutory process and the detailed design
programme. However, the lengthier statutory process set out in this report
may delay this. 
Capital 
2.8 The estimated cost of the scheme increased from £3.713M to £15.027M,
through the 2024/25 budget process and approved by the Perth and Kinross
Council committee on the 28 February 2024. The uplift of £11.314M was
approved with the expectation that the Scottish Government will fund 80% of
the additional cost £9.051M, if the grant terms and conditions are met. Perth
and Kinross Councils 20% match funding of £2.263M was approved at this
time. 
2.9 South Kinross FPS remains a Cycle 1 project with set timescales to secure
the 80% match funding once the construction tender price is known, any delay
due to the statutory process which impedes the Scottish Government Cycle 1
timescales, will impact upon the future of the scheme. 
Revenue 
2.10 The on-going maintenance costs for the scheme are estimated at £0.038M
per annum. 
2.11 The additional cost will require to be considered through the Council’s budget
process once the scheme has been completed.

Page 10

Workforce 
2.12 The project management of the flood scheme will be undertaken by the
Council’s Flooding Team. There will be a resource implication for Legal and
Property Services for technical assistance required throughout the remaining
duration of the project. 
Asset Management (land, property, IT) 
2.13 In order to construct the proposed scheme, there will be a requirement to
purchase land and/or provide compensation to relevant landowners. Estates
have been consulted on the scheme and a landownership plan has been
produced to inform future negotiations with relevant landowners.  
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups. Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.
The Equality Impact Assessment undertaken in relation to this report can be
viewed clicking here. 
3.2 The proposals in this report have been considered under the Corporate
Equalities Impact Assessment process (EqIA) with the following outcome: 
(i) Assessed as relevant and actions taken to reduce or remove the
following negative impacts: 
• The construction works could temporarily have a greater impact of
mobility impaired, sight impaired, blind people or disabled people, on
children and the elderly and infirm, and on pregnant women or
nursing mothers, in relation to adverse psychological, physical and
health impacts. Appropriate mitigation measures will be adopted to
minimise disruption, noise, dust and vibration and to ensure
adequate safe access throughout the construction works. 
(ii) Assessed as relevant and the following positive outcomes expected
following implementation: 
• The flood scheme will have the same positive impact for all equality
groups as the reduction in flood risk to Kinross will provide benefits
for all (improved safety, health & wellbeing through avoidance of
flood impacts and damages) in the long-term.

Page 11

Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
2.4 The matters presented in this report were considered under the Environmental
Assessment (Scotland) Act 2005 and no further action is required as it does
not qualify as a PPS as defined by the Act and is therefore exempt. 
2.5 As outlined in this report, an Environmental Impact Assessment Report (EIAR)
was produced for the Scheme. The EIAR identified that the Scheme does not
have any potentially significant impacts that would arise as a result of the
construction and future use of the Scheme. The only recommendation from
the EIAR was to consider construction time periods relative to the nesting bird
season to minimise disruption. In addition, there is an outstanding action to
identify and assess all groundwater abstractions within the extents of the
Scheme. 
2.6 At the time of publishing the notice for the flood scheme under the 2009 Act,
the EIAR was submitted to statutory and non-statutory consultees for their
consideration. Any additional requirements will be actioned in the timescales
required or added as conditions into the deemed planning consent for action
during the detailed design or construction of the Scheme. 
Sustainability 
3.7 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• in the way best calculated to delivery of the Act’s emissions reduction
targets;
• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable. 
3.8 Following an assessment using the Integrated Appraisal Toolkit, it has been
determined that the proposal is likely to contribute positively to the following
corporate sustainable development principles: 
(i) Climate Change
Efficient use of resources now and in the future in the built environment
and service provision (e.g. energy efficiency, land, water resources,
flood defence, waste minimisation) (Principle 2)
Mitigation and adaptation to manage the impact of climate change &
reduce the production of greenhouse gases (Principle 3).

Page 12

Justification:
The flood scheme proposed in this report will significantly reduce flood
risk in Kinross and will therefore help in tackling the effects of climate
change. 
(ii) Fairer Communities
Creating a sense of place (e.g. a place with a positive ‘feeling’ for
people, and local distinctiveness) (Principle 22) 
Justification:
The flood scheme will help to make the local community safer and
more sustainable for residents, through a reduction in flood risk. This
will help the community to thrive in the longer term despite the
temporary construction impacts. 
3.9     Following an assessment using the Integrated Appraisal Toolkit, it has been
determined that the proposal is likely to contribute negatively to the following
corporate sustainable development principles: 
(iii) Consumption and Production
Efficient use of resources now and in the future in the built environment
and service provision (e.g. energy efficiency, land, water resources,
flood defence, waste minimisation) (Principle 2)
Mitigation and adaptation to manage the impact of climate change &
reduce the production of greenhouse gases (Principle 3) 
Justification:
There will be a short term increase in the use of materials and
resources during construction of the flood scheme, but a future
reduction due to reduced flood risk. 
Mitigation:
The Environmental Impact Assessment and eventual Construction
Environmental Management Plan will consider energy consumption
and waste management practices during construction. 
Legal and Governance 
3.10 The Strategic lead – Legal and Governance has been consulted on this
report. 
3.11 Scheme of Administration authorises the Climate Change and Sustainability
Committee delegated powers to exercise the Council’s functions in relation to
matters concerning The Flood Risk Management (Scotland) Act 2009 for
which this report is applicable. However, given the current circumstances this
matter is brought to the Council for consideration.

Page 13

Risk 
3.12 Risks associated with the proposal will be managed through appropriate
communication and project management. 
4. Consultation 
Internal 
4.1 The Strategic Lead - Legal and Governance and The Strategic Lead –
Finance and Business Support have been consulted in the preparation of this
report. 
4.2 At the time of publishing the notice for the flood scheme under the 2009 Act,
all relevant sections of the Council were notified including, but not limited to:
local elected members, Planning, Property, Land Quality, Environmental
Health, Structures Team, Community Greenspace, the Council’s Biodiversity
Officer and Legal. 
External 
4.3 All relevant landowners and occupiers, SEPA, Kinross-shire Local Committee,
Kinross Community Council, Kinross Flood Resilience Group, Loch Leven
Fisheries, NatureScot, Transport Scotland, Historic Environment Scotland, the
Public Utilities and all other relevant organisations were consulted during the
development of the proposals. 
4.4 A public exhibition was held in Kinross on 28 September and 5 October 2023.
The aim of the public exhibition was to provide the community with further
information on: 
• The risk of flooding in Kinross;
• The Council’s proposals for the flood scheme; and
• Other actions to raise awareness of flood risk and improve flood resilience. 
4.5 A letter was issued to elected members, the Community Council and the
Kinross Flood Resilience Group summarising the work carried out by the
consulting engineers and how flood risk will be managed in the future. 352
letters were sent to local residents and businesses within the community to
advertise the events, and posts were made on the council’s Social Media
accounts. Approximately 41 people attended the public exhibition over the two
days. 
4.6 The public exhibition included a central display, a presentation and a series of
plans of the scheme options. Representatives from the Council’s flooding
team, design consultants (RPS), and the Scottish Flood Forum were available
to answer questions and provide further information. Those attending were
given an opportunity to record their views and questions on comment forms, or
via the Council’s website and Consultation Hub. 12 comment forms were
returned to the Council after the public exhibition.

Page 14

4.7 The response to the community public exhibition was generally positive with
the majority of the community being supportive of the proposed outline design
for the flood scheme 
4.8 The Council issued a public consultation report to the local community to
answer any questions raised during the public exhibition or on comment forms. 
4.9 The public consultation materials used at the public exhibition and public
consultation report can still be viewed on the Council’s website at
http://www.pkc.gov.uk/southkinrossfloodscheme. 
4.10 All relevant Landowners and occupiers, SEPA, Kinross-shire Local Committee,
Kinross Community Council, Kinross Flood Resilience Group, Loch Leven
Fisheries, NatureScot, Transport Scotland, Historic Environment Scotland, the
Public Utilities and all other relevant organisations were notified of the flood
scheme under the 2009 Act. 
5. Communication 
5.1 The communication arrangements to date were as noted in Section 4 above. 
5.2 A newsletter is issued periodically to the local community and relevant
consultees in order to update them on the progress of the Scheme. Full
details of the scheme are also available to view on the Council’s website.
http://www.pkc.gov.uk/southkinrossfloodscheme. 
5.3 The Council will continue to communicate with the local community, statutory
consultees, local landowners and other stakeholders as the detailed design of
the scheme is developed. The above noted website will continue to be
updated and further letters and newsletters will be issued to the local 
community as appropriate. 
2. BACKGROUND PAPERS 
2.1 The following background papers, as defined by Section 50D of the Local
Government (Scotland) Act 1973 (and not containing confidential or exempt
information) were relied on to a material extent in the preparation of the above
report; 
• PKC – Enterprise and Infrastructure Committee – 24 October 2007, Flood
Mitigation Schemes and Flood Studies (Report No 07/681)
• PKC – Environment Committee – 30 January 2008, Biennial Report on
Flood Prevention Responsibilities 2007 (Report No 08/41)
• PKC – Environment Committee – 4 November 2009, Biennial Report on
Flood Prevention Responsibilities 2009 (Report No 09/504)
• PKC – Environment Committee – 21 March 2012, Biennial Report on Flood
Prevention (Report No 12/135)
• PKC – Environment Committee – 20 November 2013, Progress Report
Flood Risk Management (Scotland) Act 2009 (Report No 13/544)
• PKC – Environment Committee – 12 November 2014, The Flood Risk

Page 15

Management (Scotland) Act 2009, Short List of Potential Measures to
Manage Flood Risk (Report No 14/483)
• PKC – Environment Committee – 9 September 2015, The Flood Risk
Management (Scotland) Act 2009, Selected Actions and Prioritisation
(Report No 15/359)
• PKC – Environment Committee – 1 June 2016, The Flood Risk
Management (Scotland) Act 2009, Publication of Local Flood Risk
Management Plans (Report No 16/241)
• PKC – Environment and Infrastructure Committee – 23 January 2019, The
Flood Risk Management (Scotland) Act 2009 Publication of Interim Report
(Report No 19/16)
• PKC – Climate Change and Sustainability Committee – 19 May 2021, The
Flood Risk Management (Scotland) Act 2009: Second Cycle of Flood Risk
Management Plans (Report No 21/60)
• PKC – Climate Change and Sustainability Committee – 19 December 2022,
The Flood Risk Management (Scotland) Act 2009: Publication of Final
Reports (Cycle 1) & Local Flood Risk Management Plans (Cycle 2) (Report
No 22/307)
• PKC – Climate Change and Sustainability Committee – 27
November 2023, South Kinross Flood Protection Scheme (Report No 23/332)