Climate Change Annual Report
YEAR 3
PERTH AND KINROSS COUNCIL
Appendix A
Page 1 of 42

Page 2

Introduction 
This report highlights Perth and Kinross Council’s commitment
to climate change and reports back on the delivery of third year
of the Climate Change Strategy and Action Plan.  
This year we completed or are in finalisation of several of key
pieces of work – our Mobility Strategy, our Local Heat and
Energy Efficiency Strategy coupled with our Local Area Energy
Plan, our estate decarbonisation plans.  These provide the
necessary roadmap for our just climate transition.
Complementarily, our organisational approach has also
matured. Over the three years of the strategy delivery, our
approach to tackling area-wide emissions has progressed from
a ‘CDP D’ score to a CDP ‘A’ score.  This was two years ahead
of our target.
We have started to see the impact of the delivery actions too. 
The introduction of twin stream recycling and transition away
from landfilling waste has reduced PKC’s emission footprint by
31%, we have provided free home energy advice to over 2,205
households, and we have improved the energy efficiency of
over 250 social homes.
While we are making progress, we recognise there are still
many challenges to overcome.  To meet our statutory targets
and organisational commitments, there needs to be an
increase in pace and scale of action next year and years going
forward.   
Climate Change Strategy and Action Plan 
The Climate Change Strategy and Action Plan (CCSAP) was
unanimously approved in December 2021 and then updated as
part of the annual reporting process in November 2022. This
report provides the update on PKC’s climate action, covering
the third year of delivery, from October 2023 – September
2024. 
Perth and Kinross Council (PKC) in December 2022
recognised ‘Tackling climate change and supporting
sustainable places’ a one of the key corporate priorities
identified in the new Corporate Plan.  This further strengthens
PKC’s commitment to addressing the climate and ecological
emergency, as outlined in its (CCSAP).
The CCSAP is divided into long-term objectives, Council
Commitments and eight thematic plans. 
Action Plans
An action plan split into eight key climate action sectors
updated annually
Council Commitments
27 commitments by the Council necessary to achieve the
outcomes
Long-term Outcomes
6 overarching objectives
Page 2 of 42

Page 3

Table 1 Objectives and commitments 
Perth and Kinross Council’s Climate Change Strategy 
1. Achieving Net
Zero aligned with the
Paris Agreement and
the Scottish
Government Targets,
with the ambition of
achieving them
sooner. 
2. Building a more
resilient Perth and
Kinross 
3. Delivering a fair
transition and a
green recovery 
4. Preventing an
ecological
emergency and
enhancing
biodiversity 
5. Engaging and
empowering our
children and young
people 
6. Empowering our
communities 
• Decarbonising our
operations 
• Aligning our
investments 
• Allocating
appropriate capital
and revenue
funding 
• Delivering on our
priority themes 
• Continuing to
develop our base
evidence 
• Reviewing our
climate change
plan annually 
• Demonstrating our
collaborative
working 
• Mainstreaming
climate resilience
into asset reviews 
• Managing climate
change risks
proactively 
• Assessing and
reviewing the
strategic climate risk
assessment 
• Continuing to raise
awareness with
communities 
• Promoting land use
practices that
contribute to natural
flood management 
• Taking action to
reduce fuel, food
and transport
poverty 
• Ensuring climate
action addresses
rural and urban
climate challenges 
• Improving the
energy efficiency
of social housing 
• Working with
businesses to identify
and address skills
shortages to support
the green economy 
• Declaring an
ecological emergency,
as well as a climate
one, and sign the
Edinburgh Declaration 
• Accelerating PKC
biodiversity strategies
and actions to keep
pace with the UK and
Scottish Government
Biodiversity Strategies
and Action Plans 
• Strengthening our
capacity to implement
nature-based
solutions 
• Monitoring the impact
of a changing climate
on our ecosystems
and take appropriate
action 
• Listening to our young
people, encouraging
them to have their say
and acting on their
views, ideas and
priorities 
• Continuing to ensure
the curriculum
supports learning
about climate change 
• Leading by example
through, minimising
emissions through
best practice in
energy, waste and
transport 
• Utilising school
grounds to promote
biodiversity, food
growing and healthy
eating 
• Working in
partnership with
our residents,
businesses and
community
partners to support
them to make
transformational
change 
• Acting as an
enabler for
community-based
climate change 
• Providing and
signposting our
communities to
trusted sources of
advice and funding 
Overarching
Objectives
Council Commitments
Page 3 of 42

Page 4

Overall Highlights
The Council has made noticeable progress this year against all
six of our overarching objectives and 27 Strategic
Commitments, the highlights of which are shown in Table 1.
1. Achieving Net Zero aligned with the Paris Agreement
and the Scottish Government Targets, with the ambition of
achieving them sooner. 
• Developing of key decarbonisation strategies including our
new Mobility Strategy (Transport) and the Local Area
Energy Plan (Buildings & Energy)
• Development of our Scope 3 Works, Purchased Goods &
Services carbon emissions footprint to understand the full
scale of the Council’s impact.  We are one of the first local
authorities in Scotland to have done this (Governance)
• Achieving the prestigious CDP ‘A’ score for our approach to
tackling area-wide emissions
• The contract award and commencement of a long-term
solution ahead of the ban on landfilling municipal waste. 
This has resulted this year in the diversion of approximately
39,000 tonnes of non-recyclable waste from landfill,
reducing carbon emissions by an estimated 11,868 tCO2e.
(Waste & Circular Economy) 
2. Building a more resilient Perth and Kinross
• We screened all 865 of our road bridges for Scour potential
and completed the detailed assessment for the ten bridges
considered most likely to have scour issues have had a
detailed scour assessment completed. (Resilience)
• A contractor has been appointed to build the £40.8m
Comrie Flood scheme designed to protect 189 homes and
businesses. (Resilience)
• Developing a plan to address the significant risk of Ash
Dieback to Perth & Kinross. (Resilience)
3. Delivering a fair transition and a green recovery
• Directly improving the energy efficiency of struggling
households, using ECO4 Funding of £3.1M to install 506
individual measures.  These measures contribute to the
decarbonisation of privately owned properties across the
wider Perth & Kinross area. (Buildings and Energy)
• Green Business Grants - 22 businesses have been paid a
total of £380,000 from the Capital Green Recovery Grant
scheme (Business & Industry).
• Publication of the Perth & Kinross Council Design Guide for
New Build housing in November 2023 to help ensure high
quality and energy efficient homes are delivered. (Buildings
& Energy)
• Hosting the Perth and Kinross Circular Economy Business
Opportunities seminar in June 2024, part of progressing the
development of a Circular Economy Plan for Perth and
Kinross for low carbon transitioning and economic. (Waste
& Circular Economy) 
4. Preventing an ecological emergency and enhancing
biodiversity 
• The Council funded a restoration plan for the lower South
Quiech Catchment to address high phosphorus runoffs into
Loch Leven. 
Page 4 of 42

Page 5

• With our Nature Restoration Fund (NRF) allocation, 18
projects were successfully delivered in Year 3 by both the
Council and our communities.
• Grassland management (Grow Wild) trial area has been
expanded out to 157 sites within central Perth and Kinross
for Year 1. 
• Biodiversity Towns and Villages – Our innovative
Biodiversity Towns and Villages programme received UK
Shared Prosperity Funding this year to enable expansion of
the initiative to up to 20 new communities. 
5. Engaging and empowering our children and young
people 
• Hosting a successful third annual Youth Climate
Conference in November 2024 (Education & Engagement). 
• Conducting Climate Change and energy workshops for kids
in Madderty Primary School and Auchtergaven Primary
School to encourage energy saving beyond retrofits
through behavioural change and energy monitoring.
• Developing a video on Madderty Primary School’s energy-
saving journey and the transition from electric storage
heating to heat pumps. The Video was shared across
schools to build awareness.
• Conducting school holiday Switch-off campaigns -
Summer/October holiday switch-off posters were created
and sent to all the schools to participate followed by energy
audit and results poster shared across the schools.
6. Empowering our communities 
• Expanding provision of home energy advice services with
our partner SCARF to over 2200 households this year and
supporting numerous others to access funding sources.
(Buildings & Energy)
• Continuing to work with communities to explore innovative
ways of delivering Public Transport, building on the award
winning Glenfarg Community Bus project which has
provided new travel opportunities for residents in the
Glenfarg and Kinross-shire area (Transport) 
• Delivery of the PKC Green Living Fund, a Participatory
Budgeting (PB) process to support projects that tackle both
the Cost-of-Living crisis and Climate Change. £226k was
distributed across 38 Community Groups.
Climate Action Plan Progress
Our Climate Action Plan for meeting our Strategic
Commitments has 204 actions spread across the eight
thematic areas.  The status of these is shown in Figure 1. 
There is an improvement on September 2023, with nine actions
moving out of the red category and 19 additional actions being
completed (Note: a large portion of the actions are on-going or
long multi-year actions so would not be expected to reach a
complete status.)  The Removed Actions are primarily actions
that this year have been consolidated into other actions to
ensure consistency in what is classified as a strategic or
supporting action across all the themes. 
Page 5 of 42

Page 6

Figure 1 Full PKC CCSAP Action RAG Status as of 30 September 2024 
To ensure that the most important actions were prioritised, the
Council designated 25 top priority actions. These focus on
achieving area-wide emissions reduction, the Council’s
emissions reduction and building resilience to climate change.
The overall progress of these actions is shown in Figure 2, with
details of the progress of each action detailed in the relevant
thematic section. 
Figure 2 Top 25 Priority Action RAG Status 
Challenges and barriers 
Several cross-cutting challenges or barriers applicable to the
wider programme delivery have been identified:
• Shifting and uncertainty of government targets and the
associated regulatory requirements has an impact on the
ability to align work and convince others to act. 
• The need to identify and unlock funding opportunities to
ensure future targets are achieved, in an uncertain funding
landscape.  This often requires the Council to have
developed projects to a ‘shovel ready’ stage prior to bidding
and often only cover capital costs.  This positively has
started to change recently in recent funding schemes from
IUK and others. 
74, 36%
55, 27%
25, 12%
28, 14%
22, 11%
Status of CCSAP 2023/24 Actions
A G R Complete Removed
10, 40%
11, 44%
4, 16%
Top 25 Actions RAG Status
Green Amber Complete
Page 6 of 42

Page 7

• Resource and skills gap within both the Council and wider
supply chain to be able to scale up at pace to meet Net
Zero targets.
• Challenges in recruiting and retaining internal staff with the
required skills, knowledge and experience has been time
consuming and led to delivery delays.
• Data timeliness and availability is a challenge to understand
the effectiveness of our actions and make appropriate
adjustments.  Several of the key datasets have 1-2 year
compilation windows. 
• How do we accelerate our pace of action and increase
our scale of impact to meet the necessary targets,
while dealing with the above challenges. 
In addition to these, specific challenges and barriers for each
theme of the action plan are discussed in the relevant thematic
section later in this report. 
Performance 
Seven high-level key performance indicators (KPIs) have been
established to give an overview of the Council’s progress
towards net zero.  All KPIs showed year-on-year improvement.
It should be noted that due to the lag of the data sources being
published, the values for the first three KPIs are for 2022, the
first year of the action plan, so reflect only limited changes due
to implementation of the Climate Action Plan. 
Our performance data has highlighted is that while we are
trending in the right direction, the need to accelerate the pace
of action to remain aligned to the Paris Agreement and national
targets. 
Table 1 2023 KPI Data 
KPI  Target 
Current
value 
%
change
over
previous
year 
Perth and Kinross Area-wide
territorial greenhouse gas
emissions (kt CO2e) 
75% reduction on 1990
levels by 2030 and zero
net emissions by 2045.  
1258.2
(2022)  2.9% 
Perth and Kinross Area-wide
territorial greenhouse gas per
Capita emissions (t CO2e) 
75% reduction on 1990
levels by 2030 and zero
net emissions by 2045.  
8.3 
(2022)  1.2% 
Perth and Kinross Area-wide
CO2 emissions (kt CO2e) 
376kt CO2e by 2030
(75% reduction on 1990
levels) 
707.6
(2022)  2.8% 
Perth and Kinross Council
Scope 1,2, and 3 emissions (t
CO2e)  Net zero by 2045 
27,947
(23/24)  31%
Carbon Disclosure Project
(City Score)  ‘A’ by 2024   A (2023)  B
% of Climate Change
Indicators showing positive
change 100% 
65%
(23/24)  41% 
Climate Change Grant
Funding secured (£k)  No target set   £3,263
(23/24)  185%   
Page 7 of 42

Page 8

Perth and Kinross Area-wide territorial greenhouse
gas emissions (ktCO2e) 
Figure 3 shows recorded greenhouse gas emissions between
2005 and 2022. This shows a 2.9% decrease in emissions year
on year, which continues the downward trend since 2005, the
first year comparative data is available.  This matched the
overall Scottish trend.  There were decreases in Commercial
emissions (19%), domestic energy emissions (13%). While
some of this will be attributed to lasting property improvements
and behavioural change, it is also partially attributed to
affordability of energy linked to the 2022 energy and cost of
living crisis. There was a 7.9% rise in transport emissions
linked to further increases in travel and commuting post-Covid,
but it is still below 2019 transport emissions levels. 
While emissions in 2022, the emissions continued to decrease
we are still significantly above the estimated trajectory needed
to reach Perth and Kinross Council target of 75% reduction by
2030 and currently we have achieved a 43% reduction on 1990
levels. It is important to note that as the Council’s climate
change action plan was approved in December 2021, so any
changes attributed to this plan are likely to only minorly be
reflected in the data. 
1 Note: as the Scottish government has not yet released the Perth
and Kinross 1990 baseline for either the full suite of GHGs or CO2, a
Perth and Kinross target figure for 2030 has been estimated for these
Figure 3 GHG Territorial Emissions for Perth and Kinross, BEIS 20241 
Perth and Kinross Area-wide territorial greenhouse
gas per Capita emissions (tCO2e) 
As shown in Figure 4, since 2005, per capita greenhouse gas
emissions in Perth and Kinross have been steadily reducing
since 2005, with the exception being 2021 (Covid recovery). 
This follows the trend for Scotland but have continued to
remain higher than the Scottish average as would be expected
for a local authority with a more rural population. 
two indicators assuming Perth and Kinross followed the Scottish
trends1 between 1990 and 2005 when data first became
available.   Data is released by BEIS approximately 18 months after
year end, so 2022 is the most recent data available.
0
500
1000
1500
2000
2005200720092011201320152017201920212023202520272029
Perth and Kinross Area-wide territorial
greenhouse gas emissions (kt CO2e)
actual 2030 75% emissions reduction target trajectory
Page 8 of 42

Page 9

Figure 4 Per Capita GHG Emissions (BEIS, 2024) 
Perth and Kinross Area-wide CO2 emissions
(ktCO2e) 
Figure 5 shows a steady reduction in recorded CO2 emissions
from 2005 until the Covid recovery bump in 2021, back into a
2.8% decrease in 2022. With decreases similarly linked to
commercial and domestic energy decreases as overall
emissions.  Emission levels are currently 19% higher than they
would need to be on trajectory for a 75% reduction by 2030. 
Figure 5 Perth and Kinross CO2 emissions (BEIS,2024) 
Perth and Kinross Council Scope 1,2, and 3
emissions (tCO2e) 
As can be seen in 
Figure 6, in 2023/24 a carbon footprint of 27,947 tCO2e was
recorded. This shows a 30.8% year-on-year decrease. This
largely attributed to Scope 3 waste emissions linked with the
introduction of twin-stream recycling and the new residual
waste contract, but there were smaller decreases in Energy
and Transport emissions. 
0
5
10
15
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
tCO2e
Per Capita Perth and Kinross territorial
greenhouse gas emissions tCO2e
Perth and Kinross Scotland
0
200
400
600
800
1000
1200
1400
1600
1990 1995 2000 2005 2010 2015 2020 2025 2030
Perth and Kinross Estimated and Target
CO2 levels (ktCO2e)
Target CO2 levels Actual CO2 levels
Page 9 of 42

Page 10

Since 2015/16, the Council has reported its Scope 1, 2 and 3
emissions as part of the statutory Public Bodies Climate
Change Duties Compliance Reporting process and the
emissions reported are as per those annual reports. There
were no changes to the reporting scope for 23/24, but beyond
this one year it is hard to compare emissions trends. 
Figure 6 Perth and Kinross Council Combined Scope 1,2 and 3 emissions 
Carbon Disclosure Project (CDP) City Score 
PKC reached the illustrious ‘A’ ranking in 2023 (2024 data not
yet released), one year ahead of target. The CDP City Score is
an independently audited assessment of climate action
progress to assist organisations in measuring and managing
their risks and opportunities on climate change. In 2022, Perth
and Kinross Council was assessed as having a city score of ‘B
– Management level’. 
% of Climate Change Indicators showing positive
change 
65% of the Climate Change indicators show positive change. 
This is a significant improvement on Year 2, when only 46%
showed positive impact.  In addition, a further 6.1% not
expected to change due to data publication timeframes. 
Climate Change Grant Funding secured (£k) 
In 2023/24 the Council secured £ 3.26M of Climate Change
related grant funding. This is nearly double the £1.77M
received in 2022/23.  A significant percentage of this was the
£2.36M from the Recycling Improvement Fund which enabled
our Twin-Stream recycling transformation. Additional funding
covered nature restoration, unlocking barriers to climate action,
0
10000
20000
30000
40000
50000
Perth and Kinross Council Scope 1, 2 and 3
emissions (tcO2e)
Scope 1 Scope 2 Scope 3
Page 10 of 42

Page 11

air quality improvements, energy efficiency improvements,
active travel, etc. While there some uncertainty over the
funding landscape, further efforts should be made to increase
this amount to help meet our aspirations.
Looking ahead
We are looking forward to delivering Year 4 of the action
plan.  Due to the completion of several key strategies over
Years 2 and 3, the focus of our work has shifted to
delivery– trying to realise the quick wins, while also
developing the strategic, shovel-ready projects. This will
lead to a significant shift in resource requirements over
the coming years.  Much of this need the Council is
currently not in a position to independently resource.
External funding options – both traditional routes and
innovative funding mechanisms will be explored to help us
realise our ambitions.
To ensure we are concentrating are efforts on the most
important and impactful efforts, the Council has identified
25 Top Priority Actions for 2025.  These have been
selected to balance our need to address area-wide
emissions, the council’s own emissions and the need to
build resilience and adapt to future changes. 
Page 11 of 42

Page 12

Governance
Strong climate change governance within the Council provides
the necessary foundations for achieving our climate action
ambitions and embedding climate action into business as usual
within our operations. The 2023/24 PKC corporate restructure
has provided clearer accountability and management
responsibility for climate action. 
Our governance theme focuses on six key areas:
• Accountability
• Business and Performance Management
• Decision Making
• Finance
• People
• Procurement
Highlights
Highlights this year include:
• Embedding climate change into the job family
Behaviour Requirements for over 4,000 staff. PKC use
the job family framework to identify Knowledge & Skills
and Behaviours required for all non-education based
roles in the Council. To monitor delivery on this, Climate
Change and Biodiversity have also become embedded
as a question of the new Performance and
Development Discussion Framework.
• Development of our Scope 3 Works, Purchased Goods
& Services carbon emissions footprint to understand the
full scale of the Council’s impact.  We are one of the
first local authorities in Scotland to have done this and
have been sharing our learning with other public bodies
as well as using the results to influence our action plan
priorities.
• Continued rollout of our Impact and Value Assessment
Toolkit to enable early identification of climate change,
sustainable development, equalities, finance and legal
risks and opportunities.
• Publication of our first Sustainable Procurement
Strategy to help embed climate action and wider
sustainability in our operations. 
Page 12 of 42

Page 13

Delivery
The 2023/24 Action Plan identified 25 Governance Actions. As
of 30 September 2024, 80% of the actions can be classified as
Complete, Green or Amber in terms of progress. 
While Governance actions have a comparatively low resource
need with respect to other thematic areas, there are several
challenges linked to changing the culture, mindset, policies and
procedures of a large organisation. These include staff capacity
and prioritisation, appreciation of how climate action relates to
a wider number of services and workstreams, as well as the
lengthy processes involved in changing Council policies and
procedures. 
Review of Top Priority Actions
From PKC’s Top 25 climate priorities, three are associated with
the Governance Theme as follows:
Action
No 
Action  RAG
Status 
Comments 
G2  Mainstream climate
change into
committee
procedures and
council operations
Mainstream climate
change into
committee
procedures and
council operations
G  The introduction of the
IVA will play a key role in
mainstreaming climate
change in the committee
process.  Additionally
this year, we embedded
climate mitigation and
adaptation into the new
Corporate Asset
Management
Framework. 
G7 Measure and develop
action plan for our
Scope 3 carbon
footprint tackling
single use items. 
Complete  Footprint was completed
in early 2024 and a
briefing paper was taken
to the CC&S Committee
in October 2024.
G20 Build capacity of
procurement and
contract management
staff around ensuring
climate change is
appropriately
considered in
procurement and
delivery processes
A Sustainable
Procurement Strategy
was a necessary first
key step, and all
Procurement Staff will
have completed Carbon
Literacy Training by
December 2024. 
Outcomes
As Governance is an enabler to other delivery focused themes,
it is more challenging to identify direct outcomes. However, two
positive outcomes as a result of Delivery of the Climate Action
Plan Actions include:
• PKC being assessed as ‘A’ Grade by the CDP, one of
only three local authorities in Scotland to Achieve this
top grade.
• Embedding climate change into key major contracts
including the new Residual Waste Contract and the
Cross Tay Link Road.
Page 13 of 42

Page 14

Progress against Statutory Targets
There are no statutory targets applicable to the Governance
Theme.  PKC has completed the statutory Public Bodies
Climate Change Reporting Duty every year since 2015. 
Key Performance Indicators
The Key Performance Indicators for Governance are shown in
the table below. As indicated in the table – two new targets
have been set.  With contractual arrangements, it is not
currently feasible to modify job profiles for school-based staff,
so have been excluded from the target setting. 
KPI Previous
Value
Current
Value
Target and comment
Scope 3 Emissions –
Procured goods and
services and capital
works
125,945
(2021/22)
152,126
(2022/23)
On a three-year
footprinting cycle so not
yet calculated for
2023/24
% of Members and
senior officers who have
undertaken Climate
Literacy training
21%
Elected
Member 
18% ELT
42%
Elected
Members 
13% SLT
100% of Elected
Members by September
2023 
Proposed to extend
target to 50% of
Strategic Leadership
Forum by September
2025 and 100% by
September 2026
% of staff who have
climate change included
in job description
1%
(2022/23)
71%
(2023/24)
Proposed target: 100%
of non-school staff
(71% overall staff) 
Climate Change
Assessment Tool
(CCAT) Overall Score
(%)
69%
(2022/23)
71%
(2023/24) 
74% by 2024
85% by 2026 
Performance improved,
but below KPI target. 
Plan in place to get
back on target in 2025. 
Looking ahead
Our Scope 3 supply chain emissions are the largest emissions
source for the council. As such, one of our main focuses for the
year is delivering our Sustainable Procurement Strategy and
embedding climate action into our procurement and contract
management operations.  
Ensuring our leaders and decision makers fully understand the
climate implications of their roles is important, so we will be
focusing our carbon literacy training to reach elected members
and our strategic leadership forum members.   
Two Governance Actions are within the Council’s top 25 priority
actions for next year: 
• G2 Mainstream climate change into committee
procedures and council operations
• G22 Develop category strategies for high emission
categories that consider climate change.
Page 14 of 42

Page 15

Education & Engagement
In 2023/24, the Education & Engagement theme has been
strengthened through improved internal and external
communication. This has been done through a mix of in-person
and online events including networking such as the Staff
Climate Café and Induction Markets, community events such
as the Summer Biodiversity Market and training through the
Carbon Literacy programme. 
Highlights 
Highlights this year include:  
• Continued roll-out of our Carbon Literacy programme
with an additional 108 staff and 8 elected members now
certified Carbon Literate.
• Delivery of the PKC Green Living Fund, a Participatory
Budgeting (PB) process that transferred the decision-
making of how public money is spent to local people.
The fund was themed to support projects that tackle
both the Cost-of-Living crisis and Climate Change and
£226k was distributed across 38 Community Groups.
• Successful second annual Youth Climate Conference in
October 2023, with 80 pupils from 9 local secondary
school attending. The students expressed their worry
and concern about climate action, but also that they
were determined, optimistic and passionate about
taking action. 
• Securing Phase 2 funding from Innovate UK to further
explore rural transport challenges and to develop a
retrofit one-stop-shop home retrofit service for Perth
and Kinross in partnership with Nicki Souter Associates,
the HEAT Project and University of Edinburgh. 
• Redevelopment of our Schools & Youth Engagement
working group with the inclusion of teachers, a business
manager and representatives working with young
people not in education. 
Page 15 of 42

Page 16

Delivery 
The 2023/24 Action Plan identified 26 Education and
Engagement Actions. As of 30 September 2024, 63% of the
actions can be classified as Green or Amber in terms of
progress.  
The main challenges associated with delivering Education and
Engagement are:  
• Finding availability for elected members and senior
officers to complete in carbon literacy training has been
challenging. 
• Engagement levels across the wider learning estate are
varied and further work is required to develop a more
structured approach to climate related action.
• Internal and external engagement and behaviour
change with those less interested in climate change
and/or with less capacity to engage due to other
pressing issues. 
Review of Top Priority Actions 
From PKC’s Top 25 climate priorities, two are associated with
the Education & Engagement Theme as follows:
Action
No 
Action  RAG
Status
Comments 
E9 Review school
operations and
practices to ensure
G  The ECS contracts team
added to schools sub-
group; Practices to be
our schools lead by
example
reviewed.  Funding secured
for a waste minimisation
officer to have a dedicated
focus on schools.
E13 Deliver community
and householder
education and
engagement
G • Supporting Local
Communities Team
through the Green
Living Fund application
process 
• Continuing to engage
via different mediums.
• Supporting the setup of
Climate Connect, the
community climate hub
for P&K. 
• Hosting summer
biodiversity market in
Civic Hall. 
• Sharing community
events and information. 
• Enabling networking of
groups in environment
sector  
Outcomes 
Positive outcomes as a result of Delivery of the Climate Action
Plan Actions include:  
• Securing of funding for Innovate UK Pathfinders Project
(our share £53k) to engage and co-design community-
based projects. 
Page 16 of 42

Page 17

• Over 2,000 members of the public voted to award
money to 38 community projects through the Green
Living Fund application process, helping to establish a
new crop of climate based, cost-of-living projects.
Progress against Statutory Targets 
There are no statuary targets related to our Education and
Engagement Theme.
Key Performance Indicators 
The Education and Engagement KPIs are shown in Table 2. 
Views on the webpage and social media were down year-on-
year linked to reduced staff capacity for engagement during 23-
24 and prioritisation of staff on project delivery.
Table 2 Education and Engagement KPIs
KPI  Previous
Value 
Current
Value 
Target and
comment 
Views on Climate
Change Webpage 
22,000 
(2022/23) 
15,900 
(2023/24) 
Increase website
reach by 10%
annually (financial
year) – 24200 by
March 2024 
Views on Social
Media channels -
Facebook 
39,511 
(2022/23) 
35,600 
(2023/24) 
Increase social
media reach by
10% annually
(financial year) –
43462 by March
2024 
KPI  Previous
Value 
Current
Value 
Target and
comment 
Views on Social
Media channels -
Twitter 
16,300 
(2022/23) 
3,991 
(2023/24) 
Increase social
media reach by
10% annually
(financial year) – 
Views on Social
Media channels -
Instagram 
11,451 
(2022/23) 
6,655 
(2023/24) 
Increase social
media reach by
10% annually
(financial year) – 
Number of
community groups
active on climate
change related
projects 
140 
(2022/23) 
142 
(2023/24) 
No target
Number of PKC
owned schools with
eco-school’s green
flag status 
27 
(2022) 
27 
(2023) 
Target of 45
schools by April
2024
Staff who have
completed the
climate change
eLearning module 
1824 
(2022) 
1990 
(2023) 
All staff (5111
FTE in 2023/24) 
Staff who have
undertaken Carbon
Literacy Training
N/A 119 Year on year
improvement 
Page 17 of 42

Page 18

Focus for upcoming year 
The focus areas for the upcoming year are:
• Expand public engagement - Continue to utilise
communication platforms and keep them up to date with
relevant and engaging material. 
• Support the development and expansion of the Perth
and Kinross Climate Change Commission (SHIFT) and
Climate Hub.  
• Deliver community and householder education and
engagement. Continue to find ways to engage existing
and new audiences. Ensure multiple mechanisms are
used, e.g. online, in-person, through community groups
and organisations, through leaflets, videos and guides.
• Develop an engagement plan and platforms for schools
and young people. Continue building relationships with
the school communities to embed Climate Change in
the curriculum. Continue to give young people a voice
via Youth Climate Conference and youth positions on
SHIFT. 
• Continue to make links of co-benefits giving tangible
results which benefit our communities. 
• Create and deliver one-stop-shop for home retrofit in
Perth and Kinross - Continue with the appraisal of
potential models for one-stop-shop and work to develop
the local supply chain and green growth opportunities.
Launch a PKC Knowledge Hub as part of IUK project
ensuring it fits with requirement under LHEES. 
Two Education & Engagement actions are within the Council’s
top 25 priority actions for next year:  
• E13 Deliver community and householder education and
engagement.
• E9 Review school operations and practices to ensure
our schools lead by example.
Page 18 of 42

Page 19

Energy & Buildings 
Energy makes up the largest share of PKC’s own direct emissions
(44%) and 12% of Perth & Kinross’s overall emissions. Our work is
focused on both the Council’s own domestic and non-domestic
estate and helping our residents and businesses to decarbonise
and drive the energy transition. 
Within the Energy and Buildings theme, work against the key
themes identified within the Climate Change Strategy and Action
Plan has been progressing over the past year including:
• Setting out the Local Heat and Energy Efficiency Strategy
(LHEES) and Local Area Energy Plan (LAEP) for the wider
Perth & Kinross area
• Improving energy efficiency in housing stock area wide
• Developing a high-level decarbonisation plan for the
Council’s Domestic and Non- Domestic estate portfolio
• Progressing energy efficiency and decarbonisation projects
using existing budget allocation.
Highlights
While good progress has been made across the wider theme, a few
highlights of the year include:
• Supporting over 2,205 households with free home energy
advice and support for tenants and residents by working
with SCARF; a new contract has been agreed that will
continue this support to the end of March 2026. SCARF will
also continue to provide support in delivery of programmes
relating to HEEPS-ABS and ECO4.
• ECO4 workstream delivering energy efficiency measures
utilised ECO Funding of £3.1M and installed 506 individual
measures.  These measures contribute to the
decarbonisation of privately owned properties across the
wider Perth & Kinross area.
• Completion, adoption and final publication of LHEES and
LAEP documents in July 2024.  Several delivery actions are
already underway including the Heat Network Support Unit
funded strategic Heat Network development, exploration of
Strategic Energy Partner.  These actions continue to support
the detailed planning for decarbonising the Council’s Non-
Domestic & Domestic estate. 
• Publication of the Perth & Kinross Council Design Guide for
New Build housing in November 2023.  
• PKC allocated an additional £2M of capital funding to further
accelerate the decarbonisation of our non-domestic
estate.  Works are progressing for several projects using
this funding stream including a joint funded project with the
Scottish Government's at Auchtergaven Primary School.
This project involved replacing the oil-fired heating system
with a new non-direct emissions air source heat pump.  The
project team secured £324.5k through the Public Sector
Heat Decarbonisation fund.
• Secured £100k of external funding for an 18 month Innovate
UK project working in partnership with Integrated
Environmental Solutions (IES), Edinburgh University and the
HEAT project to develop and deliver a decarbonisation
toolkit.  This project is of particular interest as it showcases
the needs and benefits of public/private partnership working.
• Completion and occupation of Perth and Kinross Council’s
(and Scotland’s) first certified Passivhaus primary school -
Riverside Primary School in North Muirton. Recent analysis
Page 19 of 42

Page 20

has shown that the schools energy performance is currently
40 kWh/sqm/pa which is well below the energy target of 67
kWh/sqm/pa for core use. Construction is also underway for
a further two Passivhaus projects for the replacement of
Perth High School and Blairgowrie Recreation centre. 
Delivery
The 2023/24 Action Plan identified 23 Energy and Buildings actions
as of 30 September 2024.
• 1 (4.3%) is Complete, 
• 6 (26.1%) are Green Status, 
• 12 (52.2%) are Amber status and 
• 4 (17.4%) are classified as Red.  
In terms of progress, 82.6% of the actions can be classified as
Complete, Green or Amber. 
The main challenges associated with delivering the Energy and
Buildings actions are: 
• To identify and unlock funding opportunities to ensure future
targets are achieved. 
• Resource and skills gap within the supply chain to be able to
scale up at pace to meet Net Zero targets. 
• Challenges in recruiting and retaining internal staff with the
required skills, knowledge and experience. 
• Uncertainty due to changes in legislation not yet being
agreed.  Consultation on the replacement for EESSH2 –
known as the Social Housing Net Zero Standard (SHNZS)
and consultation on the Heat in Buildings Bill both closed in
November 2023; and no further guidance has been provided
at this time.  
Page 20 of 42

Page 21

Review of Top Priority Actions
There were six Top Priority Actions for 2023/24 from the Buildings
and Energy Theme.
Action
Number 
Action  RAG 
Status 
Comments 
B1  Develop and
deliver the Local
Heat and Energy
Efficiency Strategy
(LHEES) 
G LHEES completed and
adopted 27 November 2023;
submitted for Scottish
Government review and final
version of LHEES and LAEP
was published July 2024. 
Several delivery actions
already underway including
strategic heat network
development, exploring a
Strategic Energy Partner,
establishing governance and
digital publication of evidence 
B2  Develop and
deliver a
programme to
ensure all existing
Council houses
are brought up to
EPC B by 2032 
G Draft Report on workstream
was provided in August
2024.  Review of report is
ongoing and  an Action Plan
will be prepared. 
Pilot projects are being
developed for two archetypes
from the existing housing
stock to trial potential
measures to decarbonise
these. 
The properties that have
EPC's of Bands E & F (we
have no Band G properties)
have been split into
categories and are being
addressed; a proportion have
had measures carried out but
require updated EPC's;
others require a single
measure to achieve a Band
D and others require more
than one measure and are
being programmed into the
energy efficiency programme
to install the measures
required to upgrade the
properties to EPC Band D.  
B11  Develop options,
costs and funding
avenues for PKC
Estate Portfolios to
reduce
greenhouse gas
emissions 
A Lot 4 work with ARUP is also
covering the PKC non-
domestic properties and
information relating to these
will be picked up through the
reporting on this in
November 2024. 
B12  All non - domestic
buildings
considered for
refurbishment must
have improved
energy efficiency
and performance,
adopting the 'fabric
first' approach and
Complete This action is complete as
the improved energy
performance of
refurbishment projects is a
requirement for updated
Scottish Building Standards,
Heat in Buildings Bill and
identified as part of the LOT
4 decarbonisation plan. Any
Page 21 of 42

Page 22

incorporating non-
direct emissions
heat sources  
residual items have been
adsorbed into other actions
within the Buildings and
Energy area of this Action
Plan.
B13  Develop and invest
in local district
heat/communal
heat/electricity
networks where
viable which use
alternative non-
direct emissions
heat sources  
A Strategic Heat Network Unit
funding (Scottish
Government) awarded to
build a programme and work
to support the procurement
of a partner to deliver heat
networks within a wider
energy system to be
delivered by May 2025.  
B21  Replace all Oil-
fired heating
systems with non-
direct emissions
heat source,  
A Secured £2M of internal
funding which has been
phased between 2023 to
2025 to undertake initial non-
direct Emissions heat source
projects. External SG funding
has also been secured from
Public Sector Heat
Decarbonisation fund in
24/25. for one of these
projects. 
2 There was a refresh of EPC certificates at the same time, so the
numbers may reflect some properties where the EPCs were just out of
date.
Outcomes
The following positive outcomes as a result of Priority Actions
include: 
• Over 3,500 households have received Council-funded free
home energy advice over the first three years of the plan. 
• Reduced Scope 1 and 2 emissions within the Non-Domestic
PKC estate, including a 22% reduction in heating oil used.
• Reduction in number of PKC Domestic properties at EPC
Bands E and F by over 200 and increase in properties with
EPC Bands B and above by over 70 helping to reduce the
energy burden on our tenants and residents2. 
Progress against Statutory Targets
There are several statutory targets in relation to the decarbonisation
of the Energy & Buildings theme as follows. 
I. 68% reduction in emissions from buildings by 2030 with
respect to 2020 levels: needs acceleration - 24% reduction
from 2020 levels, with a 0.4% reduction in 2023/24 from
2022/23 
II. Decarbonisation of the Public Sector Estate by 2038: 13.2%
reduction in 2022 from 2021 levels across all public bodies
in Perth & Kinross (DESNZ, 2024). 
III. Social housing to be EPC D by 2026 and EPC B by 2032:
on-track. 
Page 22 of 42

Page 23

• Increase in EPC Band B and above properties from
6.2% in 2022/23 to 7.07% of housing stock in
2023/24. 
• Decrease in EPC Bands E, F & G properties from
6.5% in 2022/23 to 3.9% in 2023/24.
IV. Development of Local Heat & Energy Efficiency Strategies
(Strategy & Delivery Plan) by end of 2023: this target has
been met. 
Key Performance Indicators
KPI  Previous
Value 
Current
Value 
Target and comment 
Total area-wide CO2
emissions from
domestic sources
(ktCO2e) 
232.6 
(2022) 
253.4 
(2021) 
Estimated 115
ktCO2e 
Based on 75%
reduction in domestic
emissions by 2030 in
relation to 1990 levels 
Scope 1 and 2
emissions from
Council Estate (tonnes
CO2) 
9,264 
(2022/23) 
9,226 
(2023/24) 
Annual emissions of
4,396 tonnes CO2 by
2030 
There was an
increase in energy
emissions factors this
year that masks a
decrease in energy
consumption.
Heating oil
consumption in PKC
non-domestic estate
(kWh) 
1,943,066 
(2022/23) 
1,806,372 
(2023/24) 
All sites with oil as a
heat source to be
removed by 2030 
Renewable energy
generated across the
PK estate, including
from Low Carbon Heat
Sources (MWh) 
2226.43 
(2022/23) 
2381.08 
(2023/24) 
Renewable energy
shall be installed
where feasible to
maximise production 
% of Council housing
meeting the Energy
Efficient Standard 2 for
social housing
(minimum EPC B) 
6.6 
(2023) 
7.07 
(2024) 
EESSH2 standards of
100% of Council
Housing to meet EPC
B by 2032 
Number of P&K
households provided
with energy efficiency
and/or low carbon
heating advice (PKC
funded) 
884 
(2022/23) 
2205 
(2023/24) 
2023/24 - 500 
Target significantly
exceeded 
Focus for upcoming year
The focus for the upcoming year is the delivery of the actions in the
plan that will include the following:
• Transition LHEES delivery plan into focussed
implementation of the actions.  
Page 23 of 42

Page 24

• Provide a detailed and costed decarbonisation plan for the
Council’s Domestic and Non-Domestic Estate; plan should
take into account lessons learned from pilot project delivery.
• Comply with Heat Network Regulations and identify areas
suitable for the development of heat networks, designating
heat network zones (HNZ) where favourable.  
• Undertake statutory duty in relation to public sector non-
domestic buildings and the compilation of Building
Assessment Reports (BAR) in accordance with Heat
Network Regulations. 
PKC has received external funding to help deliver our future work:
• HEEPS-ABS grant funding award of £1.94M received from
Scottish Government for 2024/25 for delivery of energy
efficiency measures in Domestic privately owned
properties. 
• CAN DO Green Heat Retrofit Innovation Challenge funding
awarded by Scottish Enterprise to the value of £50k to
undertake a Feasibility Study to develop a project for a
pioneering green heat solution. 
• Strategic Heat Network Unit funding of up to £100,000 has
been awarded by the Scottish Government to PKC to
procure a partner to deliver heat networks. 
Five Buildings & Energy actions are within the Council’s top 25
priority actions for next year: 
• B2 Develop and deliver a programme to ensure all existing
Council houses are brought up to EPC B by 2032
• B1 Transition LHEES delivery plan into focussed
implementation of the actions
• B11 - Develop options, costs and funding avenues for PKC
Estate Portfolios to reduce greenhouse gas emissions. 
• B13 Comply with Heat Network Regulations and identify
areas suitable for the development of heat networks,
designating heat network zones (HNZ) where favourable.  
• B21 Replace all Oil-fired heating systems with non- direct
emissions heat source, adopting a fabric first approach to
reduce heat demand. Increase local energy generation and
improve heating control systems.
Page 24 of 42

Page 25

Transport 
Progress continues to be made with key transport related projects.
Crucially, the Council’s Climate Change and Sustainability
Committee approved the Council’s first Mobility Strategy and Action
Plan on 23 October 2023. 
This provides a pivotal step in shaping the future of transportation
and mobility in our area and offers a comprehensive proposal to
guide the management and development of our transport network
over the next 15 years, including contributing to achieving ambitious
climate change related targets. 
Two of the fundamental Transport Planning Objectives of the
strategy directly relate to taking Climate Action which will ensure
that future actions and projects are appraised against these
objectives. 
Figure 7 Mobility Strategy Priorities 
In addition to the completion of the Mobility Strategy, there
continues to be ongoing work across the Council and through
collaborative work with partners to deliver on key areas: 
• Increasing active transport across Perth and Kinross
• Accelerating the EV transition
• Improving public transport provision
• Reducing vehicles in town centres
• Ensuring resilient transport systems. 
Highlights
There were several Transport highlights this year, which include:
• Approval of the Council’s first Mobility Strategy and Action
Plan setting the delivery framework for key transport
interventions over the next 15 years. The Mobility Strategy
aligns closely with national and regional strategies as well
as the Council’s Climate Change
Strategy and Corporate Plan. 
• Continuing to work with
communities to explore
innovative ways of delivering
Public Transport, building on the
award winning Glenfarg Community Bus
project which has provided new travel
opportunities for residents in the Glenfarg and Kinross-shire
area. 
Page 25 of 42

Page 26

• Collaborative working with other Local Authorities and key
agencies to progress the expansion of the public EV
charging network across the Council area in partnership with
the private sector. This work aims to secure multi-million-
pound funding that will enable the continued transition to low
carbon vehicles.  
• Work on the Perth Transport Futures Cross Tay Link Road
progressing with an expected opening in Spring 2025. This
transformational capital project is a key enabler for reducing
vehicles in Perth, proposals for which will be developed
through the Perth Circulation Plan.   
Delivery
The main challenges associated with delivering transport related
projects are primarily around ongoing resources constraints both to
develop and deliver projects. Ongoing changes to national funding
arrangements have yet to be fully implemented leading to
uncertainty on future priorities. 
Progress against Statutory Targets
There are several statutory targets in relation to the decarbonisation
of the Transport sector as follows. 
I. Transport Sector emissions reduced by 75% by 2030:
Offtrack emissions have reduced by 9.3% between 2005
and 2022.  Year on emissions rose this year, attributed to
post-covid travel increases (2022 data). Significant increase
in progress will be required to meet targets.
II. 20% reduction in vehicle km by 2030 (against 2019 levels)
Offtrack- Vehicle km rose again year-on-year in 2023, with
vehicle kms now down only 6% against 2019 levels. 
Key Performance Indicators
Several of the Transport indicators showed negative progress this
year – this is largely attributed to the societal re-mobilisation post-
Covid.
KPI Previous
Value
Current
Value
Target and comment
Transport emissions CO2
(kt CO2e)
458.7
(2021)
498.3
(2022)
75% reduction in
Transport emissions by
2030
% journeys to school by
active transport
49.9
(2022)
49.8
(2023)
To be set as part of the
P&K Mobility Strategy
Monitoring & Evaluation
Framework (under
development)
% journeys to work by
sustainable mode of
transport
20
(2021)
22
(2022)
To be set as part of the
P&K Mobility Strategy
Monitoring & Evaluation
Framework (under
development)
Total car kms (millions) 1718.6
(2022)
1759.4
(2023)
20% reductio on 2019
levels by 2030 – 1496
million km
Public EV charging
devices per 100,000
population
125.5
(2023)
133.9
(2024)
23/24 target set in PKC
Corporate Plan of 469 –
longer term targets to be
set
Council fleet vehicles that
are zero direct-carbon
(%)
4%
(2023)
4%
(2024)
100% new light fleet
from 2025 and heavy
fleet from 2030
Number of public road
closures due to flooding
or other climate change
impacts 
99
(23/24)
45
(22/23
No target set
Page 26 of 42

Page 27

Focus for upcoming year
The focus for the upcoming year is to look to secure external
funding to deliver key projects and start to deliver the actions within
the approved Mobility Strategy. 
Five Transport actions are within the Council’s top 25 priority
actions for next year: 
• T18 Further development of the Park and Choose at Bertha
Park, Walnut Grove
• T3 Update the existing Active Travel Strategy that works for
everyone in line with Transport Scotland’s Active Travel
Strategy Guidance and develop comprehensive
active travel network in association with mobility strategy.
• T7a Deliver the P&K wide EV Charging Expansion
Programme
• T32 Develop a Public Transport Strategy to guide the
development of the public transport system across the
region for the benefit of those visiting, working and living in
Perth and Kinross.
• T10 Develop and implement a strategy to transform the
Council’s fleet to electric and alternative fuel vehicles. 
Page 27 of 42

Page 28

Waste and Circular Economy
The Council’s waste and recycling services undertook a major
service change within 2023/24 with the twin stream recycling roll
enabling wider service provision, out along with the procurement,
award and mobilisation of the residual waste contract both of which
are pivotal undertakings to meet our climate goals going forward. 
Within Perth & Kinross Council, work against the key waste related
themes identified in the Climate Change Strategy has progressed
over the past year in relation to: 
• Recycling Services 
• High Carbon Materials 
• Asset Management  
• Circular Economy 
Highlights 
Highlights this year include: 
• Residual Waste
Contract Award: The
award of a long-term
solution ahead of the
ban on landfilling
municipal waste before
December 2025.  This
has resulted in the
diversion of
approximately 39,000 tonnes of non-recyclable waste being
sent to landfill, reducing carbon emissions, by an estimated
11,868 tCO2e, in the first year of the contract. On completion of
the new Energy from Waste facility at BINN EcoPark, this will
also generate energy, adding capacity to the existing private
renewable energy grid and deal with waste in the local area. 
• Twin Stream Roll Out: The Council secured a successful bid
for £2.72m from the Scottish Government (Recycling
Improvement Fund) resulting in a 4th bin being rolled out to
73,000 households. This has resulted in a more equitable
service, better quality materials, less contamination and
additional waste materials being collected kerbside for
recycling. 
• Asset Management:  Production of the Strategic Business
Case to provide an assessment of PKC’s operational
infrastructure to provide a programme which seeks to
develop sustainable, affordable and fit for purpose facilities
to support Operation and Waste provisions/activities going
forward.  
• Circular Economy Business Opportunities: Commencement
of work being undertaken to progress the development of a
Circular Economy Plan for Perth and Kinross for low carbon
Page 28 of 42

Page 29

transitioning and economic regeneration and in line with the
Circular Economy, including hosting the Perth and Kinross
Circular Economy Business Opportunities seminar in June
2024 (Scotland) Act 2024. 
Delivery 
The 2023/24 Action Plan identified 21 Waste and Circular Economy
Actions. As of 30 September 2024, 67% of the actions can be
classified as Green or Amber in terms of progress, with two marked
as complete, 9%. 
The main challenges associated with delivering Waste actions are
that national priorities and implementation dates have changed over
the period. This has resulted in a considerable level of abortive
work for Council staff and the wider waste industry.  Recent
examples include the Deposit Return Scheme (DRS), Extended
Producer Responsibility (EPR) and potential changes to Garden
Waste collections. This uncertainty also impacts on financial and
resource planning considerations. 
Review of Top Priority Actions 
The Top Priority Actions for 23/24 were: 
Action
No 
Action  RAG
Status 
Comments 
W12  Develop & Maximise
Recycling Services
by (1) expanding
PKC recycling
services to include
flexible plastic
packaging, aluminium
Complete  Twin Stream Roll out
complete January 2024
to 73,000 households
throughout Perth &
Kinross. 
foil and hard rigid
plastics (2) Expand
recycling services
(Food/DMR) in Perth
City Centre 
W15  Review PKC
procurement
processes to embed
circular economy
principles to reduce
consumption of
products and
materials and make
better use of existing
products including
tackling single use
items. 
A  Within the existing
Scotland Excel
Framework responses
from catering suppliers
included a commitment
from recommended
bidders to collect and
recycle 95% of packing
and 100% of delivery
packaging comprising
recycled material. 
Outcomes 
Positive outcomes as a result of the delivery of the Climate Change
Action Plan include: 
• PKC being awarded the ‘Striving for Excellence’ Bronze
(APSE) award in the Waste & Recycling category for the
efforts in delivering the twin stream roll out. 
• The collection of flexible plastics and foil means less
materials going into the green residual waste bin, and the
volume of non-recyclable waste thereby reducing by 3.2%. 
• Contamination rate in the blue bin prior to twin stream was
18.7%, with this now averaging at around 2.9%.  
Page 29 of 42

Page 30

• Perth & Kinross’s general waste moving from a landfill to an
Energy from Waste contract meaning the amount of
methane gas has reduced from emissions from landfill. The
contract will also bring added Community Benefits with the
creation of a Community Benefit Fund and the creation for
local jobs. 
• Working with Third Sector organisations relating to the
development of reuse activities. We currently have 4 (public
bring-to) reuse containers situated at our Recycling Centres
which has diverted 137 tonnes from landfill by entering the
reuse network. Along with this there were 41 tonnes of
bicycles which were either repaired and sold or stripped for
reuse or recycling.    
Progress against Statutory Targets 
There are several statutory targets in relation to the decarbonisation
of the Waste sector as follows.  
• The target of recycle 60% of household waste by 2020
progressing to 65% of municipal waste by 2035 has been
dropped in 2024 by the Scottish Government, however
PKC’s figure for 2023 was 51.7%. 
• Recycle 70% of all waste (includes commercial & industrial)
by 2025 - 
• Ban on biodegradable waste going to landfill (date was
2021, now 2025) – Met through the new EfW refuse
contract.
• No more than 5% of waste going to landfill by 2025 – Met
through the new EfW refuse contract.  
Key Performance Indicators 
KPI  Previous
Value 
Current
Value 
Target and
comment 
Area-wide territorial
GHG emissions
estimates – Waste
(ktCO2e) 
82.7 
(2021) 
73.7 
(2022) 
TBC 
Total household waste
generated (tonnes) and
household waste
generated per person
(kg) 
70,604 
459 
(2022) 
71,373 
473 
(2023) 
By 2025, reduce
tonnes of total
waste arising to
15% against 2011
baseline (69,730) 
Total household waste
recycled/composted as
% of all household
waste. Note this KPI
has now been removed
by the Scottish
Government. 
49.2 
(2022) 
51.7 (2023)  Recycle 70% of all
waste by 2025 
Carbon impact of
household waste per
person (tonnes CO2e) 
1.1 
(2022) 
0.90
(2023) 
Reduce carbon
impact to 0.7
tonnes CO2e per
person by 2026 
Whole Life Cycle
Emission for Perth and
Kinross Council
138.9 
(2022) 
135.6
(2023) 
Baseline 160,780
tonnes CO2e
(2020) 
Page 30 of 42

Page 31

Collected Waste
(ktCO2e) 
Quantity of food waste
collected in residual
waste (Kg/HH/week) 
1.64 
(2022) 
1.67 (2024)  Reduce food waste
by 33% from the
2013 baseline by
2025 
Dry Mixed Recycling
contamination rate (%) 
22.6 
(2022/23) 
16.05 
(2023/24) 
Reduce to
minimum of 20%
by 2022/23 and
15% by 2023/24 
Focus for upcoming year 
The focus for the upcoming year is: 
• Develop a Circular Economy Strategy, incorporating the
Waste Management Plan updates, along with a Fly-tipping
Strategy (this year and priority for next year). This will be in
line with the Circular Economy (Scotland) Bill 2024 
• Review the Food Waste Action Plan and reinstate working
group (this year and priority for next year). 
• Continue to progress with actions relating to the
development of the Asset Management Plan (this year and
priority for next year). 
• Commence the Recycling in Schools Project (this year &
priority for next year). 
• Continue with the work being undertaken in conjunction with
the Resource Management Association Scotland to
progress the Circular Economy Business opportunities (this
year and a priority for next year). 
• Review bin collection schedules to ascertain optimal
collections for waste streams. 
Two Waste & Circular Economy actions are within the Council’s top
25 priority actions for next year:  
• W21 Develop a Waste & Circular Economy Strategy to align
with the Circular Economy Bill.
• W17 Undertake an Asset Management Review of Waste &
Recycling Infrastructure. 
Page 31 of 42

Page 32

Business and Industry 
Emissions from business and industry is an area that the Council
has limited direct influence over, but plays an enabling and
influencing role.  Positively overall CO2 emissions from industrial
and commercial sources in Perth and Kinross are reducing.  
Our work this year had a significant focus on collating information
and targeting key emitters. Key actions included:
• Collating information on carbon reduction plans from key
employers;
• Promoting advice, tools and grants to SMEs wishing to
reduce carbon emissions;
• Promoting joint strategic projects with the Transport Group
to decarbonise transport;
• Promoting joint strategic projects with the Building and
Energy Group to decarbonise fixed and mobile assets;
Highlights
Highlights this year include:
• Promoting a Race to Zero campaign with local businesses
• Promoting the Perth Eco-Innovation Park as a net zero
exemplar 
• Identifying and promoting green job opportunities with key
employers and their supply chains
Delivery
The 2023/24 Action Plan identified 17 Business and Industry
Actions. As of 30 September 2024, 70% of the actions can be
classified as Completed or Green and 30% as Amber. 
The main challenges associated with delivering Business and
Industry are:
• Engagement with smaller businesses for whom current
economic conditions are not favourable in terms of costs of
materials and pressures caused by increased energy prices.
• The lack of available incentives in terms of support from UK
Government or Scottish Government grant schemes for
energy efficiency or renewables generation
• The need to present a coordinated approach across the
Council in terms of services supporting businesses.
Review of Top Priority Actions
There was one Top Priority Action for 23/24 from the Business &
Industry Theme:
Action
No 
Action  RAG
Status 
Comments 
B14  Develop Perth West
and Perth Eco-
Innovation Park as a
national net zero
exemplar for
decarbonisation of
transport and energy
A  Perth Innovation
Highway Outline
Business Case which is
part of the funding
sources has been
approved in July 2024.
Design works have
started in September
2024. Negotiations are
progressing with
landowners.
Page 32 of 42

Page 33

Outcomes
Positive outcomes as a result of Delivery of the Climate Action Plan
Actions include:
• Continued decrease in CO2 emissions from business and
industry.
• In 2023/2024, 22 businesses have benefited for an amount
of over £380,000 from the PKC Green Capital Fund financial
support. 
• Heightened awareness of the need to take action though
initiatives like the ‘Race to Zero’ campaign
Progress against Statutory Targets
There are several statutory targets in relation to the decarbonisation
of the Business and Industry sector as follows. 
Key Performance Indicators
KPI Previous
Value
Current
Value
Target and comment
Total area-wide CO2
emissions from industrial
and commercial sources
(ktCO2e)
142.6
(2021)
129.5
(2022)
No target set
Number of registered
businesses in energy
(including renewables)
growth sector
145
(2022)
140
(2023)
+10% per year target 
This 4% decrease is
above the Scottish
Average of 7%
decrease
% of businesses (250+
employees or largest
energy demand
(+0.5MW) with a set
target for reducing
carbon emissions
17
(2022)
17
(2023)
100% by 2027
Number of businesses
supported through PKC
Green Recovery Capital
Fund
24
(2022/23)
22
(2023/24)
c. 20 per year
Focus for upcoming year
The focus for the upcoming year is:
• To continue with the design and development of the Perth
Innovation Highway;
• To continue to engage with business and industry through
co-optees to the Group so that it can benefit from ‘real world’
experience
• Target work areas around the priority sectors in terms of
CO2 emissions 
• Provide further support to smaller businesses to help reduce
emissions.
One Business and Industry action is within the Council’s top 25
priority actions for next year:
• B14 Develop Perth West and Perth Eco-Innovation Park as
a national net zero exemplar.
Page 33 of 42

Page 34

Land Use 
Land Use Land Use Change and Forestry (LULUCF) is a major
emissions source and sink across Perth and Kinross. It accounted
for 53.6% (675kt CO2) of the total area-wide greenhouse gas
emissions while it was responsible for sequestering -834kt CO2e.
(2022 – latest data) Also falling under the category of land use,
agriculture accounted for 21% of total area wide carbon dioxide
emissions (150.2 kt CO2e).  There was a 7.8% reduction in
agriculture emissions between 2021 and 2022.  
Within Perth and Kinross Council, work against the key land use
themes identified in the Climate Change Strategy has progressed
over the past year in relation to:
• Strengthening Planning 
• Rural Land Use and Carbon Sequestration
• Biodiversity
• Greenspace 
Highlights
Highlights this year include:
• Reviewing existing policy framework – The Council prepared
and consulted on a series of 31 background Topic Papers
covering the suite of national planning policies in NPF4,
which have a stronger focus on tackling the dual climate and
nature crises.  These papers set out the data and
information the Council will use to help produce our Local
Development Plan (LDP3), along with a summary of likely
implications of that evidence on the development of the
Proposed Plan.   
• Nature Restoration Fund – With our Nature Restoration
Fund (NRF) allocation, 18 projects were successfully
delivered in Year 3.  Projects include restoring riparian
habitats to reduce flooding and erosion risks, creating green
corridors that enable species to move and adapt to changing
climates, and enhancing greenspaces to improve urban
cooling in the face of rising temperatures.
• Food Growing Strategy – An annual allotment report has
been produced, and progress is being made on allotment
regulations and working with a number of community
groups. 
Page 34 of 42

Page 35

• Open Space Audit – A survey of over 500 accessible open
spaces has been carried out to inform the Council’s Open
Space Quality Audit (OSQA). The surveyed sites are those
open spaces within or adjacent to settlements or designated
for open space in LDP2.   The next steps are the review and
confirmation of the survey results to allow the OSQA to be
finalised and used to inform the development of the
Council’s Open Space Strategy. 
• Grassland Management Trials - Trial area has been
expanded out to 157 sites within central Perth and Kinross
for Year 1 with the view to expand to all sites excluding
burial grounds in Year 2.  Mapping of the main sites has
been completed and uploaded onto the website. 
Interpretation signage for our main sites is being worked on
currently. Smaller site mapping will be carried out but there
is currently no timeframe on this.  New machinery bought
following a successful Nature Restoration Fund bid is being
used to cut existing “No Mow” locations across the trial area.
• Biodiversity Towns and Villages – Our innovative
Biodiversity Towns and Villages programme received UK
Shared Prosperity Funding this year to enable expansion of
the initiative to up to 20 new communities. 
Delivery
The 2023/24 Action Plan identified 21 Land Use Actions. As of 30
September 2024, 76% of the actions can be classified as Green or
Amber in terms of progress. 
A number of the measures within the land use, land use change
and forestry sector take many years to deliver their full benefits. 
The actions which are currently not on track are mainly linked to
staff resourcing and capacity challenges.  
In particular, the Planning (Scotland) Act 2019, its associated
Regulations and Guidance, and National Planning Framework 4
have introduced a significant number of new additional asks of
planning authorities in the preparation of their Local Development
Plans. A large number of the asks are major projects in their own
right, which require significant staff resources to deliver, and all at
the same time, which is going to continue to be a real challenge
over the next 2–3 years.
Page 35 of 42

Page 36

Review of Top Priority Actions
The Top Priority Actions for 23/24 were:
Action
Number
Action RAG
Status
Comments
L1 Develop a
landscape scale
pilot project in
conjunction with
partners
(Perthshire Nature
Connection
Partnership
(PNCP)) to
support private
landowners to
facilitate and
encourage
afforestation and
peatland
restoration.
A • PNCP work ongoing
with a focus on three
priorities.
• Work continuing
between PNCP and
PKC Developer
Obligations Officer,
along with a
consultant to develop
a potential
methodology to allow
developer
contributions linked to
nature solutions to be
sought.
L11 and
L14
Review existing
planning policy
framework and
prepare a suite of
enhanced policies
for inclusion in
LDP3.  
A • Development Plans
Team has reviewed
LDP2 policies against
NPF4 national policy
suite to identify which
policies have been
superseded by NPF4,
which are in
conformity with but
provide a local
response, and where
there is conflict.   
Work is now
Action
Number
Action RAG
Status
Comments
progressing on
Evidence Report to be
submitted to Scottish
Ministers early 2025.   
Outcomes
Positive outcomes as a result of the delivery of the Climate Action
Plan Actions include:
• The Council was able to plant over 2,500 new trees this year.
• Increased community volunteering, with nearly 2000 hours this
past year.
• Grassland Management Trials have been extended to 157 sites
across the Perth and Kinross Area.
• The Council’s planning policy framework has been reviewed and
is being brought into alignment with the new suite of national
planning policies in NPF4, which will bring a stronger focus to
tackling the dual climate and nature crises across the PKC Area. 
• A Draft PKC Tree Strategy is due to be published for internal
circulation during Autum 2024.
Progress against Statutory Targets
The Scottish Government has set several statutory targets related
to land use.  These are mainly at a national level rather than at a
local authority level, with the Council having varying degrees of
influence over them.  However, local authority action will be
required to meet these targets. 
Page 36 of 42

Page 37

The national targets include:
• Creation of 18,000 Hectares of new woodlands annually by 2032
- Perth and Kinross is currently at 18.5% which is the same as
our baseline year value (2018).
• 250,000 Hectares of peatland restored by 2030 – Perth and
Kinross has approximately 10% of Scottish peatland.
• At least 20,000 Hectares of peatland restored annually by 2032.
• At least 80% of designated natural site features to be in
favourable condition by 2016 – Not met but improving: 76.5% of
protected biological and mixed SSSIs site features, and 78% of
protected nature site features.
Key Performance Indicators
KPI Previous
Value
Current
Value
Target and comment
% of the total land
area of Perth and
Kinross covered by
woodland
18.5%
(2019/20)
18.5%
(2020/21)
National target to
increase forest and
woodland cover to
21% of total area of
Scotland by 2032 
Total LULUCF
emissions (ktCO2e)
679.6
(2021)
675
(2022)
Target still to be set
Total LULUCF
sequestration
(ktCO2e)
-841.1
(2021)
-834.4
(2022)
Target still to be set
Total Agriculture
emissions (ktCO2e)
162.9
(2021)
150.2
(2022)
Target still to be set
Amount of land
protected for nature
within Perth and
Kinross Council
boundary
33.5%
(2022/23)
33.5%
(2023/24)
National target for
protection of at least
30% of Scotland
(land and sea) by
2030. 
% Of Protected
Biological and Mixed
SSSI Sites in
Favourable Condition
75.3
(2023)
76.5
(2024)
National target for at
least 80% by 2016.
% Of Protected
Nature Site Features
in Favourable
Condition
75.5
(2023)
78
(2024)
National target for at
least 80% by 2016
Number of trees
planted on Council
land and maintained
open space
670
(2022/23)
2512
(2023/24) 
Number of
community
volunteering hours in
biodiversity related
projects
1786.5
(2023)
1934
(2024) 
Area grassland
managed for
biodiversity
improvement
objectives (ha)
21.72
(2022/23)
21.72
(2023/24) 
Vol. of Herbicide
Used (L – undiluted
quantity
1216
(2022/23)
1182
(2023/24)
The Council’s
commitments within
the Edinburgh
Declaration require a
national reduction of
50% by 2030 (547
litres) 
Page 37 of 42

Page 38

Focus for upcoming year
Actions this year will primarily focus on continuing our work on:
• Progressing work on the development of our new Local
Development Plan (LDP3) and embedding the necessary spatial
and policy framework to support our on-going climate action
ambitions.  This includes reviewing our Forest and Woodland
Strategy and publishing our draft Open Space Audit and Strategy
for consultation.
• Publication of a Draft PKC Tree Strategy for consultation, with a
view to publishing a final strategy in 2025.
• Continue to monitor Grassland Management Trials – Grow Wild
implementation. 
• Complete site survey programme for Local Nature Conservation
Sites to enable designation to take place. 
• Continue to work in partnership with Perthshire Nature
Connections Partnership to develop methodology for seeking
developer contributions towards nature-based solutions. 
• Deliver our innovative Biodiversity Towns and Villages and
Green Industrial Parks Projects to increase community
involvement in biodiversity. 
Five Land Use actions are within the Council’s top 25 priority
actions for next year:
• L11/L14 Review existing LDP planning policy framework
and prepare a suite of enhanced policies for inclusion in
LDP3.  
• L24 -Review and revise our Forestry and Woodland
Strategy for incorporation within LDP3 (now a statutory
requirement under the Planning (Scotland) Act 2019)
• L22 Identify and develop Nature Networks for Perth &
Kinross 
• L10 Biodiversity Villages, Neighbourhoods and Towns
Initiative – work with local communities to develop
Biodiversity Action Plans, supporting biodiversity and
climate change mitigation and adaption 
• L9 - Accelerate delivery of Tayside LBAP - Work across
services to maximise opportunities for the Council to
achieve actions set out in the Tayside Local Biodiversity
Action Plan 2016-26.
Page 38 of 42

Page 39

Resilience and Adaptation
The climate is already changing in Perth and Kinross – precipitation
patterns have started to alter; temperatures have risen, and more
extreme weather events have an increased likelihood of occurring.
The Council is working to build resilience to future events and adapt
to the current and expected climatic changes.
The Council’s climate resilience and adaptation work has
progressed in relation to the five key areas:
• Resilient organisations
• Resilient and empowered communities
• Resilient ecosystems
• Resilient infrastructure
• Flood risk management.
Highlights
Highlights of our Resilience work this year include:
• The Council’s structures team are making steady progress
on identifying and quantifying the risks posed to PKC owned
bridges due to scour action. Ten bridges considered most
likely to have scour issues have had a detailed scour
assessment completed, with a further thirteen assessments
underway. As
expected, these have
identified bridges
where scour
protection works will
be required and the
first major scour
protection scheme is
expected to be
implemented in 2025. 
• A contractor has been appointed to build the £26.8m Comrie
Flood scheme designed to protect 189 homes and
businesses. The scheme will significantly reduce the flood
risk from three rivers; the River Earn, the River Lednock and
the Water of Ruchill. 
• The Council funded a restoration plan for the lower South
Quiech Catchment to address high phosphorus runoffs into
Loch Leven. This was part of the Council supporting the
Loch Leven LENS project, which aims to be investment
ready by the end of 2024 with projects starting to be
delivered mid-2025.
Delivery
The 2023/24 Action Plan identified 33 Resilience and adaptation
Actions. As of 30 September 2024, only one action can be
classified as Red, while 29 actions (85%) can be classified as
Green or Amber in terms of progress. Two actions have been
marked as complete and two new actions have been added. 
There are several challenges associated with delivering our
Resilience actions. Resourcing is a key challenge – most notable
the lack of clarity from the Scottish Government over the funding of
flooding schemes impacting on delivery of both Cycle 1 and 2
schemes. The multi-million-pound cost identified this year to
address ash dieback is also a significant new pressure. On the
staffing side, both staff capacity and available technical skillsets are
limiting delivery.
Building individual and community ownership for resilience is
another challenge. While the Council has significant role to play,
especially through the delivery of key schemes, we also need
Page 39 of 42

Page 40

individuals to play their part by taking property level action.  These
complementary scales of action are needed to minimise the risk
that anyone in Perth & Kinross will experience the devastating
impacts associated with flooding or other extreme events. 
Review of Top Priority Actions
The Top Priority Actions for 23/24 were:
Action
Number
Action RAG
Status
Comments
R6 Undertake a
strategic climate
change risk and
opportunity
assessment for
Perth and
Kinross Council
Area
Completed  • Completed in 2023
• Council is currently
developing an online
StoryMap to make
the data more
accessible to the
wider public. 
R11 Develop updated
roads
development
guide to resolve
conflicts with
adoption criteria
for SUDS with
roads
maintenance
requirements as
well as providing
wider resilience
benefits
G Delivery was initially
delayed, but the roads
development guide
has now been drafted
and is currently going
through internal
consultation
R12 Develop and
implement scour
bridge protection
programme
G All of PKC’s bridges
have been screened
at a high level and this
year 10 no. of the
highest risk bridge
scour assessments
have been completed. 
Continuing
contribution and
support to the
delivery of
Nature Rich
Leven and other
catchment
management
approaches
G The Council funded
the development of a
catchment
management plan for
the South Queich
catchment to address
phosphorus pollution
in Loch Leven
R24 Continued
delivery of Flood
Risk
Management
Cycle 1 Projects
and commence
Cycle 2 projects
A Mixture of projects on
track (e.g. Comrie
Flood scheme &
SWMP development)
and projects delayed
due to previous
staffing shortages and
uncertainty about
funding (e.g. Scone,
Milnathort, South
Kinross). 
Outcomes
Positive outcomes as a result of Delivery of the Climate Action Plan
Actions include:
• The Council continues to support and develop community
resilience forums - the number of community resilience
groups increased this year from 27 to 33, resulting in
proactive and preventative measures. 
• As a result of the Nature Restoration Fund (NRF), 18
projects were successfully delivered in Year 3.  Projects
Page 40 of 42

Page 41

include restoring riparian habitats to reduce flooding and
erosion risks, creating green corridors that enable species to
move and adapt to changing climates, and enhancing
greenspaces to improve urban cooling in the face of rising
temperatures.
Progress against Statutory Targets
Under the Climate Change (Scotland) Act 2009, Perth and Kinross
Council (as a listed public body) has a legal duty to contribute to the
delivery of the Scottish National Adaptation Plan 3 (SNAP3) and its
objectives. SNAP3 does not include specific targets applicable to
local authorities, however, it sets the vision for a well-adapted and
climate resilient Scotland by introducing the following five
outcomes:
1. Nature connects across our land, settlements, coasts and
seas;
2. Communities are creating climate-resilient, healthy and
equitable places;
3. Public services are collaborating in effective and inclusive
adaptation action;
4. Economies and industries are adapting and realising
opportunities in Scotland’s Just Transition;
5. Scotland’s international role supports climate justice and
enhanced global action on adaptation;
Flooding is one of the main physical climate risks to Perth and
Kinross. Under the Flood Risk Management Act 2009, we have a
duty to deliver Flodd Risk Management Plans and report on our
progress every three years. In December 2022, we assessed 85%
of the PKC actions in the flood risk plan are completed or on track.
The next progress report is due in 2025.
Key Performance Indicators
The Resilience KPIs are shown in the Table below. Improvement
was seen for all three KPIs that new data was available for.
A new target was added this year for Bridge Scour Assessments, a
target of 100 assessments by 2030 is proposed. This is based on a
high-level review of scour susceptibility indicates that there are
approximately 400 bridges (out of a total of 865) where scour may
be a problem, however, it is not expected that all these bridges will
be high risk or require a detailed scour assessment to be carried
out. At present it is estimated that detailed scour assessments will
be required on approximately 100 bridges however this target will
be reviewed as work continues. 
KPI Previous
Value
Current
Value
Target and comment
Annual Scotland Adapts
Capability Framework
score
8.2/16
(2022/23)
9/16
(2023/24)
Mature organisation –
12/16 by 2026 
On track
Number of community
groups engaged in
proactive climate
resilience work
27
(2022)
33
(2023)
53 (a minimum of one
per Community Council
Area)
Percentage of PKC’s
flood risk management
plan actions classified
on track or completed
85%
(2019)
85%
(2022)
Will be next reported on
in 2025
Number of Bridge Scour
Assessments
Undertaken
0 11 New target: 100
completed scour
assessments by 2030. 
Page 41 of 42

Page 42

Focus for upcoming year
This year we will continue with our important and established
programmes of work on scour, flooding and nature restoration, but
will also expand to some new focus areas including the
development and implementation a landslip assessment
programme to identify the risks that these potential pose to our
infrastructure and communities and addressing ash dieback.
In line with SNAP3’s focus on Regional Partnerships, the Scottish
Government have funded Scotland Adapts to assist us in the
development of Tayside Adapts – a Tayside adaptation partnership
together with Angus Council and Dundee City Council.
Three Resilience actions are within the Council’s top 25 priority
actions for next year: 
• R24 Continued delivery of Flood Risk Management Cycle 1
Projects and commence Cycle 2 projects.
• R12 Develop and implement scour protection programme
for key Council assets.
• R20 Support community resilience groups to build proactive
resilience. 
Page 42 of 42