PERTH & KINROSS COUNCIL APPENDIX IV
COMPOSITE CAPITAL BUDGET 2026/27 to 2031/32
SUMMARY OF NET EXPENDITURE
Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
Budget
2025/26-
SERVICE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
ENVIRONMENT & INFRASTRUCTURE 41,504 44,861 23,688 20,243 16,960 17,803 19,230 142,785
HOUSING & COMMUNITIES 5,958 1,563 2,129 1,558 1,558 1,050 1,200 9,058
ECONOMY, DEVELOPMENT & PLANNING 24,054 12,384 12,480 10,250 (2,436) 1,186 (1,650) 32,214
PROPERTY SERVICES 33,923 36,424 46,254 39,606 42,150 40,997 11,150 216,581
CUSTOMER & DIGITAL SERVICES 4,127 4,850 11,104 6,214 6,030 12,256 6,029 46,483
HEALTH & SOCIAL CARE 953 1,345 1,256 1,435 1,290 1,446 1,420 8,192
UNALLOCATED CAPITAL RESOURCES 0 4,474 0 0 0 0 8,684 13,158
TOTAL NET BUDGET 110,519 105,901 96,911 79,306 65,552 74,738 46,063 468,471

Page 2

PERTH & KINROSS COUNCIL APPENDIX IV
COMPOSITE CAPITAL BUDGET 2026/27 to 2031/32
Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
ENVIRONMENT & INFRASTRUCTURE Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Traffic & Road Network
Road Safety Initiatives (20mph zones etc.) 732 548 361 400 400 450 450 2,609
Scottish Government Grant (530) 0 0 0 0 0 0 0
Road Safety Initiatives - A94 Safety Improvements 84 0 0 0 0 0 0 0
Active Travel - Traffic & Road Safety Schemes 1,823 810 600 600 600 600 600 3,810
Third Party Contribution (1,050) 0 0 0 0 0 0 0
20mph Signage Programme 0 120 0 0 0 0 0 120
Additional Road Safety - Pedestrian Crossings 246 153 0 0 0 0 0 153
Traffic Signal Renewals & Upgrades 200 0 100 100 100 95 125 520
Investment in Local Footpaths 0 120 0 0 0 0 0 120
Car Parking Investment - Pitlochry 7 0 0 0 0 0 0 0
Revenue Contribution (1) 0 0 0 0 0 0 0
A977  Upgrades 0 177 0 0 0 0 0 177
Brioch Road, Crieff - Road Realignment & Safety Measures 18 0 0 0 0 0 0 0
Street Lighting Partnership
Street Lighting 0 0 0 600 600 600 600 2,400
Road Maintenance Partnership
Structural Maintenance 10,257 9,867 8,964 8,320 8,320 9,500 11,000 55,971
Third Party Contributions (513) 0 0 0 0 0 0 0
Footways 359 368 368 341 341 400 425 2,243
Third Party Contributions (2) 0 0 0 0 0 0 0
Perth Flood Protection Scheme (South Inch Culvert Reinstatement) 9 0 0 0 0 0 0 0
Asset Management - Bridges
Bridge Refurbishment Programme 1,682 2,020 1,836 2,259 2,259 2,603 2,500 13,477
Old Perth Bridge - Strengthening 38 235 2,216 0 0 0 0 2,451
TOTAL CARRIED FORWARD 13,359 14,418 14,445 12,620 12,620 14,248 15,700 84,051

Page 3

Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
ENVIRONMENT & INFRASTRUCTURE Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
TOTAL BROUGHT FORWARD 13,359 14,418 14,445 12,620 12,620 14,248 15,700 84,051
Perth Queens Bridge - Strengthening 81 179 192 1,850 0 0 0 2,221
Culteuchar Culvert 5 0 0 0 0 0 0 0
Garry Viaduct 393 183 1,195 1,755 786 25 0 3,944
Bolfrack River Retaining Wall 521 0 0 0 0 0 0 0
Bridge of Tilt 285 965 0 0 0 0 0 965
Corb Bridge Culvert, Kinross 398 0 0 0 0 0 0 0
Blairgowrie Bridge 200 175 1,000 0 0 0 0 1,175
Vehicular Bridge Parapets Programme - Assess & Upgrade 10 24 0 0 0 0 0 24
Rural Flood Mitigation Schemes
Comrie Flood Protection Scheme 17,730 13,093 0 0 0 0 0 13,093
Milnathort Flood Protection Scheme 331 0 0 0 0 0 0 0
South Kinross Flood protection Scheme 480 10,517 3,099 75 0 0 0 13,691
Flood Mitigation Measures - Dunkeld and Buckie Braes 282 88 153 338 129 0 0 708
Investment in Surface Water Management Scheme - Leaky Dam, Rattray 3 48 44 255 0 0 0 347
Coastal Change Adaptation 0 59 0 0 0 0 0 59
Climate Change
Climate Change Programme 215 530 200 0 0 0 0 730
Climate Change - Unallocated 329 0 0 0 0 0 0 0
Nature Restoration 199 0 0 0 0 0 0 0
Prudential Borrowing
Wheeled Bin Replacement Programme - Domestic Bins 279 200 200 220 220 225 225 1,290
Wheeled Bin Replacement Programme - Commercial Bins 71 20 20 25 25 25 25 140
Capital Receipts - Disposal (3) 0 0 0 0 0 0 0
Recycling in Schools - Waste Bin Purchases 18 84 0 0 0 0 0 84
TOTAL CARRIED FORWARD 35,186 40,583 20,548 17,138 13,780 14,523 15,950 122,522

Page 4

Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
ENVIRONMENT & INFRASTRUCTURE Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
TOTAL BROUGHT FORWARD 35,186 40,583 20,548 17,138 13,780 14,523 15,950 122,522
Recycling Containers, Oil Banks & Battery Banks - Replacement Programme99 163 105 70 70 75 75 558
Capital Receipts - Disposal (7) 0 0 0 0 0 0 0
Litter Bins 8 107 50 55 55 55 55 377
Vehicle Replacement Programme 5,800 3,751 2,692 3,311 3,394 3,500 3,500 20,148
Capital Receipts - Vehicle Disposals (547) (294) (269) (331) (339) (350) (350) (1,933)
Street Lighting Renewal - LED & Column Replacement 965 551 562 0 0 0 0 1,113
TOTAL 41,504 44,861 23,688 20,243 16,960 17,803 19,230 142,785

Page 5

PERTH & KINROSS COUNCIL APPENDIX IV
COMPOSITE CAPITAL BUDGET 2026/27 to 2031/32
Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
HOUSING & COMMUNITIES Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Community Greenspace
Community Greenspace Sites 0 25 894 700 700 250 500 3,069
Play Areas - Improvements Implementation Strategy 1,039 1,395 582 500 500 500 500 3,977
Third Party Contribution (19) 0 0 0 0 0 0 0
Revenue Contribution (50) 0 0 0 0 0 0 0
3G Pitch, Blairgowrie 34 0 0 0 0 0 0 0
Countryside Sites 0 0 139 0 0 0 0 139
Community Greenspace Bridges 106 0 0 0 0 0 0 0
Core Path Implementation 92 0 0 0 0 0 0 0
Third Party Contribution (92) 0 0 0 0 0 0 0
Kinoull Hill 24 0 0 0 0 0 0 0
Third Party Contribution (16) 0 0 0 0 0 0 0
Crematorium Access Road 50 0 0 0 0 0 0 0
Cemetery Extensions 7 143 514 358 358 300 200 1,873
Improvements
New Gypsy Traveller Site 1,942 0 0 0 0 0 0 0
Parking, Public Transport Unit & Civil Contingencies
Community Transport Iniatives 27 0 0 0 0 0 0 0
Bus Infrastructure Fund Expenditure 374 0 0 0 0 0 0 0
Community Learning, Development and Equalities
Community-Led Asset Transfers 75 0 0 0 0 0 0 0
Prudential Borrowing Projects
Community Transport Vehicles 115 0 0 0 0 0 0 0
Kinnoull Street Car Park - Purchase & Upgrade 2,250 0 0 0 0 0 0 0
TOTAL 5,958 1,563 2,129 1,558 1,558 1,050 1,200 9,058

Page 6

PERTH & KINROSS COUNCIL APPENDIX IV
COMPOSITE CAPITAL BUDGET 2026/27 to 2031/32
Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
ECONOMY, DEVELOPMENT & PLANNING Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Roads Infrastructure
A9/A85 Road Junction Improvements (PTF Phase 1) 14 0 0 0 0 0 0 0
Destiny Bridge and New Kingsway (PTF Phase 2) 5,785 314 0 0 0 0 0 314
Bertha Park Link Road (PTF Phase 3) 10,598 4,462 0 0 0 0 0 4,462
Third Party Contribution 0 0 0 0 0 (1,064) 0 (1,064)
Perth Eco-Innovation Park at Perth West 1,724 3,921 16,000 10,500 0 0 0 30,421
Third Party Contribution - Tay Cities Deal 0 (1,055) (3,945) (500) (956) 0 0 (6,456)
Other Third Party Contributions 0 (2,000) (3,000) (1,000) (1,000) (1,000) (1,000) (9,000)
Capital Receipts - Ring-Fenced Land Disposals 0 (550) (725) (650) (680) (650) (650) (3,905)
Tourism, Culture & Place
Perth City Improvements (PTF Phase 4) 0 3,642 0 0 0 0 0 3,642
City Greening 31 0 0 0 0 0 0 0
Perth & Kinross Lighting Action Plan 1,175 0 0 0 0 0 0 0
Adapt Your Property - Vacant Town & City Centre Space 390 300 300 0 0 0 0 600
Glover Street, Perth Master Plan 0 750 0 0 0 0 0 750
Less Ring-Fenced Capital Receipt 0 (750) 0 0 0 0 0 (750)
Commercial Property Investment Programme
Broxden Business Park - Additional Infrastructure 17 0 0 0 0 0 0 0
Merican Buildings, Shore Road, Perth 451 0 0 0 0 0 0 0
Crioch Business Centre, Crieff 316 0 0 0 0 0 0 0
Northfield Business Park 2,027 0 0 0 0 0 0 0
Northfield Business Park (Phase 2) 0 0 0 800 0 0 0 800
Northfield Business Park (Site 6) 0 0 1,500 0 0 0 0 1,500
Plot 4, Kinross West 1,526 0 0 0 0 0 0 0
Welton Road SBU's, Blairgowrie 0 200 1,400 0 0 0 0 1,600
TOTAL CARRIED FORWARD 24,054 9,234 11,530 9,150 (2,636) (2,714) (1,650) 22,914

Page 7

Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
ECONOMY, DEVELOPMENT & PLANNING Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
TOTAL BROUGHT FORWARD 24,054 9,234 11,530 9,150 (2,636) (2,714) (1,650) 22,914
Burnside Street SBU's, Pitlochry 0 600 0 0 0 0 0 600
Depot SBU's, Blackford 0 0 0 0 200 1,400 0 1,600
SBU's Inveralmond Road, Perth 0 900 0 0 0 0 0 900
Land at South Turfhills Depot, Kinross 0 0 0 1,100 0 0 0 1,100
Aldour Business Centre, Pitlochry 0 0 0 0 0 900 0 900
Borlich Business Centre, Aberfdeldy 0 0 0 0 0 1,600 0 1,600
Aberfeldy SBU's 0 700 0 0 0 0 0 700
Prudential Borrowing Projects
Land Purchase & Development 0 950 950 0 0 0 0 1,900
TOTAL 24,054 12,384 12,480 10,250 (2,436) 1,186 (1,650) 32,214

Page 8

PERTH & KINROSS COUNCIL APPENDIX IV
COMPOSITE CAPITAL BUDGET 2026/27 to 2031/32
Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
PROPERTY SERVICES Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Property Services - Project support
Investment in the Learning Estate 1,900 2,506 6,823 0 0 0 0 9,329
Braco Primary School Upgrade 150 350 3,000 5,000 0 0 0 8,350
School Toilet Upgrade Programme 600 600 600 0 0 0 0 1,200
Methven Primary School Refurbishment 700 2,970 0 0 0 0 0 2,970
North/West Perth - New Primary School 341 7,672 15,400 0 0 0 0 23,072
Perth Academy - Refurbishments 1,621 49 0 0 0 0 0 49
Perth Grammar School - Upgrade Programme (Phase 3) 600 1,628 819 0 0 0 0 2,447
Perth High School - New School Investment 11,718 4,900 0 0 0 0 0 4,900
Pitlochry High School Extension (Pitlochry Leisure Review) 200 750 5,000 2,750 0 0 0 8,500
Blairgowrie Recreation Centre - Replacement 832 1,700 0 0 0 0 0 1,700
Technology Upgrades 250 483 519 0 0 0 0 1,002
Community School of Auchterarder (FSM) 0 250 750 2,511 0 0 0 3,511
Community Campus Access Adaptations 25 0 0 0 0 0 0 0
Roof Upgrade Programme 500 0 0 0 0 0 0 0
Property Service Manager
DDA Adaptation & Alteration Works Programme 250 303 200 0 0 0 0 503
Property Compliance Works Programme 609 650 400 0 0 0 0 1,050
Capital Improvement Projects Programme (including School Estate) 1,866 1,800 894 10,000 7,700 11,000 11,000 42,394
Pitlochry High School - Upgrade Programme 20 0 0 0 0 0 0 0
Friarton Depot - Waste Transfer Station 2,300 221 0 0 0 0 0 221
TOTAL CARRIED FORWARD 24,482 26,832 34,405 20,261 7,700 11,000 11,000 111,198

Page 9

Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
PROPERTY SERVICES Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
TOTAL BROUGHT FORWARD 24,482 26,832 34,405 20,261 7,700 11,000 11,000 111,198
Energy Efficiency Works - Various Properties 12 0 0 0 0 0 0 0
Revenue Contribution (Salix Reserve) (12) 0 0 0 0 0 0 0
Letham Wellbeing Hub 338 0 0 0 0 0 0 0
PH2O 300 1,700 2,000 10,000 30,000 29,847 0 73,547
Bells Sports Centre 414 1,500 1,500 3,500 3,000 0 0 9,500
Kinross Commuity Campus Sports Facilities 0 900 5,000 1,000 0 0 0 6,900
Crieff Commuity Campus Sports Facilities 0 0 1,000 4,000 1,300 0 0 6,300
Crieff Drummond Armsa - Regeneration 750 2,192 0 0 0 0 0 2,192
Perth Concert Hall 200 1,000 1,000 695 0 0 0 2,695
Perth Museum 113 0 0 0 0 0 0 0
Prudential Borrowing Projects
Decarbonisation 178 350 0 0 0 0 0 350
Energy Conservation & Carbon Reduction Programme 189 150 150 150 150 150 150 900
Third Party Contribution (41) 0 0 0 0 0 0 0
Pullar House - Purchase & Repurposing 7,000 1,800 1,199 0 0 0 0 2,999
TOTAL 33,923 36,424 46,254 39,606 42,150 40,997 11,150 216,581

Page 10

PERTH & KINROSS COUNCIL APPENDIX IV
COMPOSITE CAPITAL BUDGET 2026/27 to 2031/32
Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
CUSTOMER & DIGITAL SERVICES Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Customer & Digital Services
ICT Infrastructure & Replacement & Upgrade Programme 2,079 2,987 8,666 3,940 3,550 9,487 2,956 31,586
Data & Analytics 675 718 850 900 804 845 995 5,112
Supporting Digital 681 966 1,106 1,063 1,230 1,085 1,077 6,527
Software Licences (Revenues & Benefits) 50 80 82 85 87 90 105 529
School Audio-Visual (AV) Equipment Replacement Programme 27 26 27 226 359 749 896 2,283
Swift Social Work System Replacement (Mosaic) 659 197 497 0 0 0 0 694
Revenue Contribution (124) (124) (124) 0 0 0 0 (248)
Case Management System 80 0 0 0 0 0 0 0
TOTAL 4,127 4,850 11,104 6,214 6,030 12,256 6,029 46,483

Page 11

PERTH & KINROSS COUNCIL APPENDIX IV
COMPOSITE CAPITAL BUDGET 2026/27 to 2031/32
Revised Approved Approved Approved Approved Approved Approved Approved
Budget Budget Budget Budget Budget Budget Budget Total
HEALTH & SOCIAL CARE Budget
2025/26-
PROJECT/NATURE OF EXPENDITURE 2025/26 2026/27 2027/28 2028/29 2029/30 2030/31 2031/32 2030/31
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Occupational Therapy Equipment 250 250 150 250 100 256 350 1,356
Technology Enabled Telecare 650 1,042 1,037 1,115 1,120 1,120 1,000 6,434
Software Licences 53 53 69 70 70 70 70 402
TOTAL 953 1,345 1,256 1,435 1,290 1,446 1,420 8,192