Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality
___________________________________________________________________
Committee or Board: Perth and Kinross Council
Date of Meeting: 4 March 2026
Report Title: Strategic Planning and Transformation Update and
2026/27 to 2028/29 General Fund Revenue Budget
Report Number: 26/54
Report Authors: Scott Walker, Chief Finance Officer
Charlene Guild, Strategic Lead – Projects and
Programmes
Greg Boland, Strategic Lead – Strategic Planning,
People and Performance
Organisational Lead: Scott Walker, Chief Finance Officer
__________________________________
1. Purpose
1.1 This report provides Council with an update on the delivery of its ongoing
strategic transformation and change programme and alignment with the
Medium-Term Financial Plan approved by Council on 10 December 2025.
1.2 The report focuses on delivering the Council’s vision of tackling poverty and
inequality in areas of greatest need and the protection, within available
resources, of services which deliver for individuals, families and communities
across Perth and Kinross.
1.3 Thereafter, the report presents the Provisional Revenue Budgets for 2026/27,
2027/28 and 2028/29 which seeks to allow the Council to continue its
commitment to achieving its vision and corporate priorities.
2. Recommendations
It is recommended that Council:
2.1 Approves the 2026/27, 2027/28 and 2028/29 Provisional Revenue Budgets as
set out in Appendix B – see paragraph 6.18.
2.2 Agrees a Council Tax collection rate of 98.25% in 2026/27, 2027/28 and
2028/29 – see paragraph 6.24.

Page 2

2.3 Approves the Council Tax bases set out in Table 7 - see paragraph 6.25.
2.4 Approves Band D Council Tax levels (see paragraph 6.31) of: –.
 2026/27 – £1,652.32 (final)
 2027/28 – £1.714.28 (indicative)
 2028/29 – £1.769.99 (indicative)
2.5 Approves a contribution of £120.956 million to Perth and Kinross Integration
Joint Board in the 2026/27 Provisional Revenue Budget with a further £1 million
earmarked in Reserves – see paragraph 6.47.
2.6 Maintains a prudent approach to the application of Reserves, in line with the
Council’s Financial Principles, and earmarks the General Fund balances of
£38.361 million identified in Appendix G – see paragraph 7.10.
2.7 Approves that uncommitted Reserves are maintained at between 2% and 4% of
the 2026/27 Revenue Budget which equates to £10.552 million to £21.104
million – see paragraph 7.17.
3. Structure of the Report
3.1 This report is structured over the following sections:
4. Strategic Context
5. Scottish Government Budget
6. 2026/27, 20276/28 and 2028/29 Provisional Revenue Budgets
7. Reserves Strategy
8. Risk Assessment
9. Conclusions
10. Impact Value Assessment
11. Appendices
4. Strategic Context
4.1 Perth and Kinross Council’s three-year Revenue Budget (2026/27–2028/29) will
be set within a challenging operating environment characterised by the
complexity of delivering services in a predominantly rural/remote area and the
associated cost premium, demographic changes, rising service demands,
increasing levels of need for additional support, cost of living crisis and
sustained financial constraints.
4.2 Despite the challenging context, Perth and Kinross Council has continued to
deliver progress against its Corporate Plan corporate priorities. The Council’s
Annual Performance Report 2024/2025 (Report No 25/275 refers) evidences
these achievements, such as:
 Reducing the child poverty rate to 3.8% below the national average,
nearly double the previous gap of 2%.

Page 3

 Narrowing the poverty related attainment gap for primary-age literacy
from 27% to 21%, and for secondary school leavers with a reduction from
40% to 28% in the gap between those leaving with at least one Level 6
qualification, and from 28% to 19% for those leaving with at least one
Level 5 qualification.
 Maintaining stability in the number of families in temporary
accommodation despite sustained pressure on housing and
homelessness services. Our Home First approach has ensured stability
for families requiring temporary accommodation. Between 2020 and 2024,
the number of households in temporary accommodation remained steady
- 6 households (15 children) in March 2025 compared with 8 households
(16 children) in March 2024 - minimising disruption for children, which is
critical to their development and wellbeing. Over the same period, the
national figure increased by 36%.
 Reducing re-let times and void levels in direct response to the national
housing emergency.  Average re-let times reduced from 37.8 days in
2023/24 to 24.87 days in 2024/25, while the number of void properties
also reduced from 136 to 95. This improvement has increased the
availability of homes for people in urgent need.
 Delivering 264 new affordable homes which includes 234 social rented
homes and 30 mid-market rent properties, while achieving a balanced
geographic spread of new supply: 53% urban / 47% rural. This strong
performance places Perth and Kinross as 7th in Scotland for per-capita
growth in housing stock.
 Delivering strong economic performance, attracting investment, and
supporting over 250 new business start-ups and over 250 micro-
enterprises through local partnerships, with Perth and Kinross recognised
by Growth Flag for the second successive year, as the Local Authority in
the UK with the strongest growth potential amongst its businesses.
 Improving employability through targeted programmes helping adults
and young people, and increased visitors to Perth and Kinross by 25%.
 Planting 3,142 trees in our open spaces and working with new and
established community groups to plant native herbaceous, wildflower and
pollinators to enrich local greenspaces.

Page 4

4.3 The IJB Annual Performance Report 2024/25 and in-year reporting
demonstrate very positive trends over time including:
 Delivery of reablement support and care at home which has improved
significantly. This has led to a large reduction in unmet need by around
800 hours since August 2024 and a sustained reduction in the number of
people experiencing a delayed discharge from hospital, where 97.6% of
all adults are now discharged from hospital without delay.
 People are now waiting less time for the support they need to live
independently from the time they are identified as requiring social care
support (both from hospital and in the community). This is ensuring that
they get the right care at the right time, before their circumstances
deteriorate and they require higher levels of personal care.
 The average time that a person spends in hospital is significantly
trending down.  Prolonged periods in hospital can lead to significant
physiological, psychological and functional decline also known as
“deconditioning syndrome”. This can mean that people take much longer
to recover their previous capabilities, if at all, and can unfortunately require
greater care and support.
 The number of people experiencing a delay in their discharge has been
reducing over time and the Health and Social Care Partnership has
maintained high performance in this measure with the local position
consistently below the nationally determined rate.
4.4 Despite these achievements Perth and Kinross Council is not complacent and
recognises the increasing needs within sections of our communities, the many
challenges we currently face and those that lie ahead. The Annual Performance
Report recognised some of these challenges and the work that we are doing to
make Perth and Kinross a place to live life well, free from poverty and
inequality.
National Context
4.5 “Despite increased funding in 2024/25, the financial outlook for Scotland's
councils presents substantial challenges. The costs of delivering services
continues to rise, debt is increasing, reserve levels are falling and there is a
continued reliance on non-recurring measures to close significant budget gaps.
This all raises concerns around councils’ medium-term sustainability.” Accounts
Commission January 2026
4.6 Like all local authorities, Perth and Kinross Council has made significant
savings but continues to see the costs of and demand (need) for services rising
faster than the available funding. There are limitations as to how we can
address these challenges due to ringfenced funding and statutory
commitments. In addition, national policy reforms across education, social care,
climate change and child poverty continue to shape local priorities.

Page 5

These limitations and challenges will see an increasing requirement to consider
the impact on the deliverability of our existing levels of universal services and
the ability to target resources to those in greatest need.
4.7 Workforce pressures persist across key roles and national pay bargaining
remains a significant cost driver. More widely, the pressure of continuing to try
to deliver on all of the Council’s priorities while maintaining levels of service is
taking its toll on our workforce with reports of lower motivation, higher absence
levels in some key areas, and staff survey feedback highlighting concerns
about how valued staff feel. In many cases, the delivery of services and the
mitigation of cost increases continues to rely on significant levels of unpaid
discretionary effort from our workforce.
4.8 Additionally, crosscutting national priorities such as digital transformation, early
intervention, prevention, wellbeing, and net zero, continue to influence service
redesign and investment decisions. Moving forward, services will require
significant changes to remain sustainable, and the continued transformation
and re-design of services will be key levers to mitigating and addressing these
challenges more ambitiously and effectively. Officers are developing proposals
for phase three of our Transformation, Change and Improvement programme
focussing on these crosscutting priorities and ensuring alignment with our own
key corporate priorities. In addition, national and regional collaborative working
will continue to contribute to transformation and change, enabling councils to
pool resources, share expertise and deliver services more efficiently, where
there is a political commitment to do so.
Local Context
4.9 Perth and Kinross Council operates within the strategic framework of the
Corporate Plan. This is underpinned by a commitment to the overarching vision
for “a Perth and Kinross where everyone can live life well, free from
poverty and inequality”.  During this year the Council will commence
engagement on its new Corporate Plan which is due for renewal in 2027. This
will consider our vision and corporate priorities to ensure they meet with our
collective ambitions for Perth and Kinross Council and the people we serve.
4.10 The Local Outcomes Improvement Plan (LOIP) 2022–2032 also reinforces this
ambition by setting out shared commitments across the Community Planning
Partnership. The Best Value thematic review of the Council reinforces the
importance of clear strategic priorities, strong governance, and alignment
between plans and resources.
4.11 The Corporate Plan vision is delivered through seven corporate priorities:
 Tackling poverty
 Tackling climate change and supporting sustainable places
 Developing a resilient, stronger and greener local economy
 Enabling our children and young people to achieve their full potential
 Protecting and caring for our most vulnerable people
 Supporting and promoting physical and mental wellbeing

Page 6

 Working in partnership with communities
4.12 These corporate priorities identify where resources must be focused to deliver
the ambition set out in the organisational vision. The need for clear prioritisation
is particularly acute in a period of tightening financial resources, when limited
capacity must be directed towards those activities that will have the greatest
impact on achieving the vision.
4.13 This focus on prioritising limited resources to achieve the Council’s vision forms
the basis of the Council’s financial principles and the approach taken to our
medium-term planning. As we seek to continue to work within our available
resources, prioritisation and a requirement to reduce and/or stop certain
activities not aligned to Council priorities is likely to be increasingly necessary
and will impact on our ability to provide existing levels of some universal
services.
4.14 Needs led budgets, including social care, additional support needs, transport,
and homelessness, continue to exceed historic trends. These factors contribute
to significant funding challenges, and continue to require sustained
transformation, careful prioritisation, and a disciplined approach to financial
stewardship.
4.15 The Council is continuing to progress a programme of transformation aligned to
its seven strategic priorities. This includes modernising service delivery,
strengthening prevention and early intervention, investing in digital capability,
improving the use of data and evidence, refocusing the estate to better match
future need, and enhancing workforce sustainability.
4.16 Collaborative working with communities, third sector and partners, NHS
Tayside, Police Scotland, and the wider public sector remains central to
delivering better outcomes for the residents of Perth and Kinross.
Health and Social Care
4.17 The Council’s Revenue Budget for 2025/26 approved a contribution to the
Integration Joint Board (IJB) which included additional funding of £6.7 million
to protect and support the delivery of social care services, based on mid-level
demand assumptions. In setting the Revenue Budget however, there was an
acknowledged risk that the higher-level assumptions could result in additional
costs of £5 million over and above the assumed mid-range figure. That risk
materialised within the financial year. In recognition of the fact that the IJB’s
financial reserves were already depleted through efforts to manage and meet
increasing complexity and demand arising mainly in the post pandemic period,
Council approved an additional non-recurring allocation of up to £4.180
million to the IJB in October 2025 (Report No. 25/278 refers). This allocation
was to meet existing costs associated with high service demand (need) and to
complete work outlined in the financial recovery plan.

Page 7

4.18 The Health and Social Care Partnership continues to perform well against its
performance comparators and the Scottish average. This performance directly
supports the Integration Joint Board’s Strategic Plan for 2024-2027 and is
aligned to the vision and priorities set out in the Council’s Corporate Plan.  This
is contributing positively to prevention, early intervention and avoiding failure
demand across multiple points in the health and social care system.
4.19 A programme of transformation within the Health and Social Care Partnership is
focused on shifting the balance of care, addressing needs arising from
demographic change, increasing equality of access and addressing unmet
need in the community.
Strategic Challenges
4.20 Despite a strong strategic framework, the combined demographic and
geographic factors of the area present significant pressures. Demographic
change remains one of the most critical challenges. The area continues to
experience a growing population of older people, with a 78% projected
increase in residents aged 75 between 2001 and 2028, placing sustained
pressure on health and social care, housing support, and community services.
At the same time a growth in additional support needs continues to place
pressure on Education and Learning Services.
4.21 The rural nature of Perth and Kinross presents significant challenges and
additional costs in delivering services across a 5,286km2 area with a lower-
than-average population density of 29 people per square kilometre (compared
to a Scottish average of 70). This presents a distinct rurality challenge for
Perth and Kinross and other geographically similar local authorities which is not
fully reflected in current national funding models. 70.6% of residents live in
rural areas, with parts of Perth and Kinross representing some of the most
access-deprived in Scotland, affecting over 31,000 people. This affects daily
living and access to education, employment, digital and transport connectivity
and essential health, care and support services. For the Council the dispersed
nature of the area impacts on and increases the cost and limits the efficiency of
delivering core services including home-to-school transport, school meal
provision, social care, waste management, housing services, roads and winter
maintenance. The rural poverty premium further intensifies demand and cost
pressures.
4.22 These pressures have also been recognised in recent reporting by national
bodies. In January the Accounts Commission’s report on delayed discharges
recognised the exacerbating challenges in rural areas caused by greater
difficulties recruiting and retaining carers, and the limited availability of
appropriate housing to meet people’s long-term care needs in rural areas.
Earlier this month the Scottish Parliament’s Equalities, Human Rights and Civil
Justice Committee published a report on human rights, equalities and access to
services in rural Scotland, which recognised the need for targeted action to
recognise that national policy frameworks do not fully account for rural realities.

Page 8

4.23 The Council Leader has also written to COSLA on behalf of the Council, to
highlight the need for greater recognition of rural delivery factors within the
allocation of funding and as an intensifying factor on demographic projections.
COSLA has confirmed a willingness to examine these issues and has
welcomed Perth and Kinross’s support in working with other local authorities to
do so. It is hoped that with COSLA’s support there will be progress to reflect the
growing urgency of ensuring rurality is properly accounted for in future funding
distribution.
4.24 Rurality remains a significant factor, alongside demographic projections, in
balancing the Council’s statutory duties, financial planning, and determining the
scale of savings required in the 2026–2029 period.
4.25 The medium-term challenge is shaped by a combination of structural and
emerging pressures:
 Rising demand associated with increasing levels of need: increased
volume and complexity across social work services for all ages, adult
social care, and additional support needs.
 Workforce constraints: recruitment difficulty, retention challenges, future
skills requirements, and reliance on temporary staffing in specific roles
and the wellbeing impact of continuing demand pressures within teams as
we seek to maintain current services levels.
 Cost pressures: uplifted contract and utilities costs, transport inflation,
and asset maintenance backlogs.
 Demographic change: significant population ageing and changing
household patterns.
 Asset and estate limitations: ageing buildings, decarbonisation
pressures and digital infrastructure requirements, with the need to
consider the best use of all of our estate, corporate, educational, leisure
and other, to best meet the needs of communities whilst balancing the
financial challenges.
 External uncertainty: volatility in government funding, policy change and
broader economic risks.
4.26 At the same time, a comparatively static or declining working age population
restricts labour market capacity and creates recruitment challenges across key
frontline services and professional roles. These demographic shifts also
intensify cost pressures in areas such as additional support needs, child
protection, complex adult social care, and homelessness services.
4.27 Together, these pressures create an unsustainable trajectory without the help
of strategic transformation and multiyear financial planning. As part of that
planning it will be necessary to continue to ensure that resources are directed
towards supporting those who most need it, based on evidence and aligned to

Page 9

organisational priorities. This will require a review of some universal services
to determine where performance, standards of service delivery or frequency
may be reduced, while continuing to meet statutory responsibilities. This
approach will be necessary to support the reallocation or targeting of finite
resources to where investment is most needed, and improving outcomes for
vulnerable people, families and communities.
4.28 Put bluntly we cannot continue to deliver everything we currently do, in the way
we do, with the available resources.
Strategic and Transformation Opportunities
4.29 We have continued to make good progress with our phase two Transformation
and Change Programme, and a full update will be presented at Finance and
Resources Committee in April 2026. Key highlights over the past year include:
 Audit Scotland best value audit on Transformation: How councils are
redesigning their services to deliver services more efficiently was carried
out in Perth and Kinross Council in 2025 and highlighted several areas of
good practice including clear vision, strategy and programme and savings
made as a result of transformation projects.  Another area of strength was
the regular, clear and open communication and reporting to Elected
Members on progress. Recommendations were few and have all been
addressed.
 Secured Fairer Futures funding to expand the Fairer Communities for all
programme into 2026/27 and beyond based on past successes.
 Development of Career Long Professional Learning Pathways and three
additional Intensive Support Units through our Additional Support Needs
programme and improvement of support and guidance for 16+ transitions.
 Launch of the Copilot Pathfinder Programme to integrate Microsoft Copilot
and enhance productivity.
 Options appraisal for a future ALEO model presented to full Council in
October 2025 with a new Strategic Alliance between three ALEOs and
Perth and Kinross due to start in April 2026 (subject to Council approval)
to improve collaboration, focus on shared services, efficiencies and
improved outcomes, workforce planning and income growth.
4.30 While much of the Council’s transformation work is visible through redesigned
services and improved processes, a substantial part of its impact is hidden in
the costs which have been avoided by making these changes. By redesigning
processes, consolidating services and teams and focusing on early
intervention, we have avoided pressures that many other councils are now
facing. Examples include:
 Preventing and tackling homelessness through the Home First (and other)
initiatives, which meant that while homelessness is a growing challenge

Page 10

for all local authorities, Perth and Kinross continues to perform well
comparatively.
 The introduction of REACH to support young people who may otherwise
have been placed in external residential placements, meant that while
complex cases have risen post-COVID, the baseline number of
placements in Perth and Kinross was lower than it would otherwise have
been.  We perform exceptionally well nationally, in the balance of care for
children and young people who are looked after in a community setting.
 Using technology to re-design Care at Home, using mapping tools to show
where packages are needed and introducing a new contract model where
providers can be more flexible and responsive to where demand is,
increasing the number of hours available to provide care. While the growth
in demand for older people’s services has been significant, it would have
been even more difficult to manage without these transformation
improvements.  The costs per hour for home care in Perth and Kinross
continues to be one of the lowest in Scotland as reported in the Local
Government Benchmarking Framework.
4.31 The above examples and others are estimated to be saving the Council millions
of pounds through cost of avoidance / mitigation.  We also recognise that our
committed workforce provide a level of discretionary effort which also mitigates
and avoids further cost pressures.
4.32 Work to improve productivity, speed up service delivery, reduce waiting times,
and ensure that projects are focused on delivering the Council’s priorities,
hasn’t always resulted in cashable savings. However, these measures have
contributed to avoiding failure demand, improving customer experience,
reducing duplication, and ensuring that costs are managed within existing
budgets.
4.33 We recognise that there are still more opportunities to further transform
and redesign services, to consider cross cutting national challenges within
this context and encourage a renewed focus on strengthening sustainability and
efficiency. This will align with the national programme for Transformation and
Change led by Improvement Scotland and SOLACE which is driving
collaborative reform across all 32 councils. Areas of national and local focus
are:
 Digital and Automation: accelerating end to end process redesign and
digital self-service.
 Service Redesign and Prevention: shifting resources to early
intervention and outcomes focused models.
 Regional Collaboration: joint commissioning, partnership working and
shared services with neighbouring authorities and local partners.

Page 11

 Asset Optimisation: rationalising the estate, improving energy efficiency
and supporting net zero objectives.
 Income and Commercial Opportunities: reviewing charging models,
expanding traded services, and maximising external funding.
4.34 These opportunities will underpin the future direction of the Transformation and
Improvement Programme, from June 2026. Phase three will sharpen the
Council’s strategic focus on a targeted approach to change, building on the
proven impact of place-based approaches such as Fairer Communities and
Fairer Futures. By using local data and insight as a driver to identify need and
opportunities, and working closely with our community partners and with
residents, our Strategic Leadership Team will champion the need to
increasingly consider provision through more focused lens - enabling solutions
that better reflect the needs and priorities of communities and individuals most
in need, and improve outcomes where pressures are greatest.
4.35 This renewed focus will be supported by a strengthened organisational
approach to productivity, efficiency and the prevention of failure demand,
including the integration of the Transformation and Business Improvement
teams, and even closer alignment with digital transformation and organisational
development.
4.36 Together with a wider programme of leadership development with our middle
managers to understand these drivers for change and their role in improving
productivity, preventing failure demand, and improving efficiencies we will
ensure that finite resources are directed to where they make the greatest
difference, that transformation is rooted in evidence and place, and that the
Council can deliver sustainable and evidence-based improvements across
Perth and Kinross.
4.37 This requires increased pace across a streamlined Transformation Programme
with a strengthened focus on improvement outcomes, cross service delivery
and collaboration.
Budget Consultation
4.38 Between 5 December 2025 and 16 January 2026, the Council carried out an
online survey exercise to gauge resident views on budget issues and priorities.
4.39 Overall, there were 946 responses received to the online survey. This is an
improvement on the 761 responses received to the survey undertaken for the
2024/25 budget. Appendix A provides an overview of the responses received
with comparisons to previous years where relevant.
4.40 While this report summarises the comments made by respondents, the full text
comments (apart from minimal redactions to remove any personally identifiable
information) was shared with elected member Budget Review Groups to
support their considerations.

Page 12

4.41 The budget survey responses provide feedback on priorities and themes that
are important to residents. While comments vary and do not provide detail on
the extent to which respondents use universal or specific Council services, the
key theme which emerges is that residents want to see essential services
protected and a focus on efficiency and the streamlining of processes.
While definitions of essential services will vary by what individuals use and
need, the broad position of respondents is to focus on services which support
the most vulnerable and at-risk people, recognise the additional challenges
of living in rural areas (particularly in relation to transport access), and the
importance of community and social wellbeing.
4.42 Officers recognise that limitations of the budget survey process means that the
responses received represent only a relatively small proportion of residents and
communities. Work is planned during 2026 to review how consultation and
engagement insight is captured, shared and informs strategic decisions across
Council services, including the proposed development of a Citizen’s Panel with
the flexibility to work at both an area-wide level and be targeted at communities
where voices are often not heard in existing consultation activities. This
approach will inform how and where engagement to inform future Council
budgets, and the development of the next Corporate Plan, is undertaken. These
measures and consultation responses also need to be included alongside other
qualitative feedback from service users on the quality and value of services to
those who make greatest need of have the highest levels of reliance on council
services.
Impact of this context
4.43 The three-year Revenue Budget proposals have been developed within the
local, national and strategic context set out in this section, and with the aim of
ensuring that the Council’s finite resources are directed towards activities that
most effectively support the strategic priorities and deliver the vision of a Perth
and Kinross where everyone can live life well, free from poverty and
inequality.
4.44 This proposed budget balances ambition with realism, acknowledging the
pressures ahead while reaffirming the Council’s commitment to improving
outcomes, reducing inequalities, and sustaining high quality public services for
the residents of Perth and Kinross, particularly those with the highest levels of
identified needs.
5. Scottish Government Budget
5.1 The Scottish Budget 2026/27 and Local Government Finance Circular 1/2026
were published on 13 January 2026 which was significantly later than previous
years.

Page 13

Local Government Finance Circular 1/2026
5.2 Local Government Finance Circular 1/2026 includes the provisional financial
settlement for 2026/27 at an individual Council level. The information provided
in January 2026 only related to 2026/27.
5.3 The Circular provides details of the provisional total Revenue and Capital
funding allocations for 2026/27, as well as the latest information on funding
redeterminations for 2025/26. The Circular also provides details on a range of
Non-Domestic Rates measures, including the proposed 2026/27 poundages
and changes to certain reliefs.
5.4 The provisional total funding allocations form the basis for the annual
consultation between the Scottish Government and COSLA ahead of the Local
Government Finance (Scotland) Order 2026 being presented to the Scottish
Parliament. This is currently scheduled for the end of February 2026.
5.5 The Circular sets out a national funding package of almost £15.7 billion and
includes the following.  Where the amount for the Council is known, this is
shown in italics.
 a further £773.8 million of funding has now been baselined as General
Revenue Grant.
 additional General Revenue Grant of £253.9 million to support local
priorities
 an additional £3 million to support free school meals
 £160 million for adult social care workers in commissioned services
(£4.612 million)
 An additional £11 million to improve pay for early learning and childcare
workers in commissioned services (£316,000)
 £11 million to support development of people working in children’s social
work
 £7 million to support provision of free personal and nursing care
 £20 million to tackle the climate emergency
 £40 million to improve active travel infrastructure
 An additional £11.4 million (revenue) and £15.5 million (capital) to
improve inter-island connectivity.
 £20 million announced for the Real Living Wage
5.6 As has been the case in previous years, Finance Circular 1/2026 also
contained information on undistributed revenue funding, part of which has been
distributed, with the remainder following during the financial year.
5.7 Based on Finance Circular 1/2026 (updated), the total Revenue funding being
made available by the Scottish Government to Perth and Kinross Council in
2026/27 is £390.527 million (see Table 1 below).

Page 14

Table 1: Scottish Government Grant Funding – Perth and Kinross Council
2026/27 2025/26 Movement
£m £m £m
General Revenue Funding 311.825 304.896
Non-Domestic Rates 71.661 63.537
Ring-Fenced Grants 3.896 1.967
TOTAL REVENUE FUNDING 387.382 370.400
Subsequent Announcements 3.145 -
UPDATED REVENUE FUNDING 390.527 370.400 20.127
Source: Finance Circular 1/2025 – 27 February 2025
Finance Circular 1/2026 – 13 January 2026
5.8 The 2026/27 Scottish Government provisional funding allocation of £390.527
million represents a £20.127 million increase in absolute cash terms from the
allocation for 2025/26 (or 5.4%).
5.9 However, the 2026/27 provisional funding allocation includes £15.356 million
where there is an expectation or requirement for the Council to apply funding
for a stated purpose (most notably 2025/26 and 2026/27 pay awards,
employer’s national insurance contributions and social care (real living wage).
5.10 Therefore, on a like for like basis, the provisional Scottish Government funding
allocation for 2026/27, represents a £4.771 million cash increase (or 1.3%)
over the equivalent position for 2025/26.
5.11 Table 2 summarises the movements in the total funding package from the
Scottish Government to facilitate a comparison of the 2026/27 provisional
allocation with 2025/26 on a comparable basis.
Table 2: Cash movements between 2026/27 and 2025/26 (on a comparable
basis)
£m
2025/26 – Finance Circular 1/2025 370.400
2026/27 – Finance Circular 1/2026 (updated) 390.527
Year on year cash increase in funding 20.127
Year on year % increase in cash funding +5.4%
Less funding directed to service delivery/commitments (15.356)
£ cash increase (on a comparable basis) 4.771
% cash increase 1.3%

Page 15

Implications for the Capital Budget
5.12 Finance Circular 1/2026 also includes provisional Capital Grant allocations for
2026/27. The impact of these allocations is included within the Strategic
Investment and Capital Budget 2026/27 – 2031/32 (Report No. 26/55 refers)
which is on the agenda for this Council meeting.
Non-Domestic Rates
5.13 Finance Circular 1/2026 also includes the Non-Domestic Basic Rate poundage
for 2026/27 of 48.1 pence, a reduction 1.7 pence from 2025/26. Two additional
rates are levied on properties with rateable values over £51,000 (53.5 pence,
reduction of 1.9 pence) and £100,000 (54.8 pence, reduction of 2 pence).
5.14 A new 15% relief will be available in 2026/27 to 31 March 2029 for retail,
hospitality and leisure premises with a rateable value up to and including
£100,000 (capped at £110,000 per ratepayer per year).
5.15 Revaluation transitional relief will be available for the three years (2026/27 to
2028/29) which is set out in Table 3 below.  This will cap increases in gross
rates liabilities for those seeing the highest increases in rateable values at
revaluation.
Table 3: Year on Year Revaluation Transitional Relief Caps (%)
– 2026/27 to 2028/29
2026/27 2027/28 2028/29
Small (rateable value up to £20,000) 15% 22% 38%
Medium (rateable value £20,001 to
£100,000)
30% 44% 75%
Large (rateable value over £100,000) 50% 75% 113%
6. 2026/27, 2027/28 and 2028/29 Provisional Revenue Budgets
Background
6.1 The Council first approved the 2026/27 Provisional Revenue Budget on 28
February 2024, (Report No. 24/63 refers).  On 26 February 2025, the 2026/27
Provisional Revenue Budget was updated and the 2027/28 Provisional
Revenue Budget was set for the first time (Report No. 25/36 refers).
6.2 In setting the 2026/27 and 2027/28 Provisional Revenue Budgets, the Council
has previously agreed the expenditure pressures and budget reductions set out
in Table 4.
Table 4: Council Decisions 28 February 2024 and 26 February 2025
2026/27 2027/28 Total
Expenditure Pressures £5.696m £2.879m £8.575m
Budget Reductions £(4.806)m £(1.283)m £(6.089)m

Page 16

6.3 Furthermore, in agreeing the Medium Term Financial Plan in December 2025,
the Council agreed indicative Council Tax levels of 7.5%, 3.75% and 3.25% for
2026/27, 2027/28 and 2028/29 respectively (Report No. 25/356 refers).
6.4 These decisions are the basis for the updated 2026/27 and 2027/28 Provisional
Revenue Budgets, and for the 2028/29 Provisional Revenue Budget that is
being considered by Council at this meeting.
Process for Updating the 2026/27 and 2027/28 Provisional Revenue
Budgets
6.5 Adjustments to the 2026/27 and 2027/28 Provisional Revenue Budgets are
included in the Executive Summaries set out in detail in Appendix C.
6.6 The Executive Summaries include an assessment of the potential impact of
budget reductions against the following criteria:
 Fairness – including the potential socio-economic impact on vulnerable
individuals and groups.
 Workforce – including general commentary on the workforce implications.
 Customers – including information on the effect on all customers
/stakeholders (both external and internal).
 Equalities/Diversity – ensuring that any statutory equalities issues are
considered.
 Outcome and Performance – identifying any significant impact on the
Local Outcomes Improvement Plan and/or Service Business Management
and Improvement Plans.
 Climate Change – including positive and negative impact
6.7 Where workforce implications are identified within the Appendix C, the
Council’s positive and proactive approach to workforce management is
designed to mitigate the impact on its people, including investment in skills for
the future, retraining, support to take on new job roles, career coaching and
building resilience.
6.8 Equality and Fairness Impact Assessments for individual expenditure pressures
and reductions were prepared which facilitated the preparation of a cumulative
impact assessment.
6.9 The Executive Summaries set out in Appendix C have been subject to scrutiny
by Elected Member Budget Review Groups.
6.10 The detailed analysis of these expenditure pressures and reduction proposals
are set out in Appendix C. Total updated expenditure pressures of £40.545
million and total budget reductions / funding of £23.085 million, are included in
Table 5.

Page 17

6.11 Also included Table 5 is the impact on 2028/29 of decisions taken in previous
financial years.  The most significant adjustment is the unwinding of the last
tranche of the Service Concession scheme when “funding” of £1 million ends. 
In addition, the consequences of other decisions (predominantly the ending of
non-recurring expenditure proposals) helps to reduce the gap in 2028/29 by
£124,000.  The impact of these adjustments is shown in Table 5 below.
Table 5: Updated Expenditure Pressures and Budget Reductions
2026/27
£m
2027/28
£m
2028/29
£m
Total
£m
Expenditure Pressures 20.740 7.361 12.444 40.545
Budget Reductions (20.740) (1.746) (0.599) (23.085)
Balance (per Appendix C) - 5.615 11.845 17.460
Other 2028/29 Pressures (net) - - 0.876 0.876
2027/28 and 2028/29 Gap - 5.615 12.721 18.336
6.12 The Council is required under statute to set a balanced revenue budget for the
year ahead (i.e. 2026/27) and the proposals set out in Appendix C meet that
requirement.  However, looking ahead into 2027/28 and 2028/29, there is a
cumulative funding gap of £18.336 million – see Table 5.
6.13 As Elected Members will be aware the timeline for the 2026/27 budget process
has been particularly challenging due to the dates of the UK Government
budget and the subsequent impact Scottish Government budget
announcements. Given the cumulative funding gap for the next two years, it is
essential that work to address this begins as soon as possible, including early
engagement with elected members and communities. Learning from what has
worked well and what could have been better in this year’s budget preparation
process and the feedback which will and has been received from elected
members will inform the approach to this.
6.14 Elected Members are reminded that the position summarised in Table 5, is
based upon the assumption that all expenditure pressures and all reductions
within the Executive Summaries attached as Appendix C, and those in
previous years are approved. In addition, it is based on the Council Tax
Strategy approved by Council on 10 December 2025. Furthermore, this position
is subject to the current known funding available from Government.
6.15 As set out above, the 2026/27 Provisional Revenue Budget is based on an
increase in Council Tax of 7.5%.  Should the final level of Council Tax vary,
then this would either allow the Council to reject more cuts or require it to
identify more cuts.  For illustrative purposes, Table 6 sets out the implications of
a range of Council Tax levels.

Page 18

Table 6: Implications of Changes to Council Tax Levels for 2026/27
5% 6% 7.5% 8% 9% 9.5%
-£2.917m -£1.750m - +£0.583m +£1.750m +£2.333m
6.16 The 2026/27, 2027/28 and 2028/29 Provisional Revenue Budgets have been
prepared based upon the information currently available, both in terms of
financial resources and anticipated service delivery pressures. The analysis
reflects the judgement of Council officers, a focus on Council priorities and
financial principles, however, there is a significant risk that these assumptions
may require to be revised as part of the ongoing monitoring of Council
expenditure and income.
6.17 Finally, the Council is recognised by external auditors for its prudent approach
to financial management. Given the level of uncertainty over the short to
medium term in relation to additional expenditure, reduced income, the
previously approved use of Reserves, and the unknown impact of the cost of
living on local communities and the local economy, Council is advised to adopt
a cautious and prudent approach towards the application of Reserves. Council
has already agreed the principle of not funding recurring activity from general
fund Reserves.
6.18 ACTION: The Council is asked to approve the 2026/27, 2027/28 and
2028/29 Provisional Revenue Budgets as set out in Appendix B –
RECOMMENDATION 2.1.
6.19 The Council is also advised that there may be delays implementing some
additional expenditure proposals, to allow lead in arrangements to be
established. This may result in some activity slipping into future financial years.
Any additional projects introduced through the Revenue Budget Motion/
Amendments, must reflect the Council’s priorities and approved financial
principles, including a focus on need rather than responding to demand and be
based on evidence and data. Delivery of new proposals may also require a
commensurate increase in staffing capacity which may delay implementation as
appropriately skilled officers are recruited.
Council Tax Collection Rate
6.20 In February 2025, the Council agreed a Council Tax collection rate of 98.25%.
This target, whilst remaining challenging, was supported by the Council’s
collection performance over recent years and represents a realistic budgeted
collection over time.
6.21 Elected members receive regular updates on Council Tax collection through
reporting to the Finance and Resources Committee.
6.22 Despite the challenges facing households, Council Tax collection is holding up.
It is therefore proposed that the collection rate of 98.25% is maintained for
2026/27, 2027/28 and 2028/29.  It should, however, also be noted that there

Page 19

remains a risk to collection levels due to the economic environment, changes in
legislation in relation to debt recovery and welfare reform. The cost-of-living
challenges and its impact on household incomes may also continue to have a
significant impact.
6.23 It usually takes on average around six years to reach or exceed a collection
level of 98.25%. The Council remains committed to sustaining and improving
performance in respect of all its income recovery activities.
6.24 ACTION: The Council is asked to agree a Council Tax collection rate of
98.25% in 2026/27, 2027/28 and 2028/29 – RECOMMENDATION 2.2.
Council Tax Base
6.25 The number of chargeable band D equivalent dwellings for Council Tax
purposes, the Council Tax base (after adjusting for assumed non-collection of
1.75%), is estimated to be as follows:
Table 7: Council Tax – Number of Band D Equivalent Properties
2026/27 75,910
2027/28 76,600
2028/29 77,456
6.26 The Council’s tax base is regularly reviewed, based upon an analysis of recent
trends, and adjusted for anticipated growth in the number of dwellings as well
as increases in the number of discounts and exempt dwellings.
6.27 ACTION: The Council is asked to approve the Council Tax bases set out in
Table 7 – RECOMMENDATION 2.3.
Council Tax Rates
6.28 Consistent with the decision of Council on 10 December 2025, the 2026/27,
2027/28 and 2028/29 Provisional Revenue Budgets have been constructed on
the basis of Council Tax increases of 7.5%, 3.75% and 3.25% respectively.
6.29 For illustrative purposes, Table8 sets out the impact of the proposed increases
on a monthly, weekly and annual basis for a Band D Council Tax payer.
Table 8: Impact of Council Tax Rises
Weekly Increase Monthly Increase Annual Increase
2026/27 £2.22 £9.61 £115.28
2027/28 £1.19 £5.16 £61.96
2028/29 £1.07 £4.64 £55.71
6.30 Any proposal to deviate from this position will have either positive or negative
implications on the Council’s financial position depending on the final decision.

Page 20

6.31 ACTION: The Council is asked to approve Council Tax levels as follows –
RECOMMENDATION 2.4.
 2026/27 – £1,652.32 (final)
 2027/28 – £1,714.28 (indicative)
 2028/29 – £1,769.99 (indicative)
6.32 The 2027/28 and 2028/29 indicative Council Tax levels will be confirmed when
setting the final Revenue Budgets in February/March 2027 and 2028
respectively.
6.33 Again, consistent with the previous Council decision on 4 December 2024,
1.25% of future Council Tax income per year will be ringfenced and applied to
supporting the Capital Budget to ensure delivery of key infrastructure projects
and supporting programmes such as roads, bridges and IT investment.
6.34 In the event that future Council Tax increases are restricted or prohibited, a
corresponding amount from the Revenue Budget would be applied to Loan
Charges in order to ensure the sustainability of the Capital Budget in the
medium and longer term.
Fees and Charges
6.35 The proposals set out in Appendix C include the financial implications of
increases to existing levels of charges in 2026/27. Full details of recommended
charges for 2026/27 are set out in Appendix D.
6.36 The annual review of charges considers several factors including an
assessment of previous year’s income levels, trends in user demand,
inflationary pressures, savings targets, alternative charging structures and the
potential impact on vulnerable groups.
6.37 All fees and charges should be set in line with the approved individual charging
policy and fall into one of the following categories set out in Table 9 below.

Page 21

Table 9: Charging Categories
Charging Strategy Objective
Commercial Charges The Council aims to cover the cost of
providing the service and make a surplus.
Full Cost Recovery The Council aims to cover the cost of providing
the service from those who use it.
Subsidised The Council wishes users of the service to
contribute to the costs of provision. This might
meet a service objective or allow competition
with other providers.
Free The Council chooses to make the service
available at no charge to meet a service
objective.
Statutory Charges are determined in line with legal
requirements.
Perth and Kinross Integration Joint Board
6.38 The Public Bodies (Joint Working) (Scotland) Act 2014 introduced joint working
with NHS (Tayside) in the form of an Integrated Joint Board (IJB) for the
strategic planning of community health and social care across Perth and
Kinross.
6.39 The Perth and Kinross IJB has an approved Strategic Plan for 2024-2027 and a
series of Strategic Delivery Plans to deliver on its objectives for vulnerable
adults who rely upon community health and social care for daily living. The IJB
has issued directions to the Council to deliver social work and social care
services for adults which are in line with integration principles for community
health and social care, and, to support transformation in key priority areas such
as older people services including care at home; expansion of support and
independent living for people with a learning disability service and securing
better outcomes in community mental health and wellbeing.
6.40 The IJB approved a financial strategy for 2024-2027 which includes a drive for
greater efficiency and transformation to build best practice in health and social
care provision and ensuring an integrated, whole system approach to meeting
needs and improving outcomes.   The HSCP, supported by the Council’s
Executive Leadership Team continues to implement transformational
approaches aimed at building on best practice in health and social care
provision.
6.41 The Local Government Finance Circular confirmed that funding would be
provided to increase the Living Wage for adult social care workers in
commissioned services, and to increase the rate of Free Personal and Nursing
Care.

Page 22

Correspondence was subsequently received on 12 February 2025 that
confirmed additional funding to “meet the uplift to the Real Living Wage in full
across adult social care, children social care and early learning and childcare”.
6.42 The 2026/27 Provisional Revenue Budget assumes the Council will pass on its
full share of the funding included in the local government funding settlement
from the Scottish Government.
6.43 The IJB has requisitioned an uplift of £10.046 million from 2026/27 and a total
Recurring Budget Required £121.956 million to address pressures arising from
the increasing needs of the population, which is included in the Council 2026/27
Provisional Revenue Budget. This will support an adjusted financial scenario
planning nuanced to demand pressures in different service areas/care groups.
There is a risk that these assumptions are underestimated.
6.44 The Council has made provision for £120.956 million in the 2026/27 Revenue
Budget with a further £1 million earmarked in Reserves.
6.45 At this stage work remains underway on the IJB Budget for 2027/28 and
2028/29.
6.46 The IJB is scheduled to meet on 18 March 2026 to consider its budget for
2026/27. This budget will consider the funding received from each Partner Body
alongside the pressures which have been identified for 2026/27. The IJB will
require to make decisions in relation to savings to deliver a balanced budget for
2026/27 in line with those presented in the attached summaries. Until both NHS
Tayside and the Council confirm their 2026/27 Revenue Budget, there is a risk
to the delivery of the IJB Strategic Plan.
6.47 ACTION: The Council is requested to approve the contribution of £120.956
million to Perth and Kinross Health and Social Care Partnership in the
2026/27 Provisional Revenue Budget with a further £1 million earmarked
in Reserves – RECOMMENDATION 2.5.
Scottish Water Charges
6.48 The Council has received notification from Scottish Water that domestic water
supply and wastewater collection charges for 2026/27 will increase by 8.67%.
This results in a band D equivalent charge for water and waste from Scottish
Water of £652.32, an increase of £51.93 (£600.39 in 2025/26).
6.49 Scottish Water charges for water and wastewater continue to be charged using
the Council Tax multiplier that was in place prior to 1 April 2017.
7. Reserves Strategy
7.1 In accordance with the existing statutory and regulatory framework, the Chief
Finance Officer, as Responsible Financial Officer (or “Proper Officer”), is
responsible for advising the Council on the level of Reserves it should hold.

Page 23

7.2 In determining Medium Term Financial Plans and preparing budgets, the
Council needs to consider the establishment and maintenance of Reserves in
accordance with its statutory powers. Reserves can be held for three main
purposes:
 Working balances to help cushion the impact of uneven cash flows and
avoid unnecessary temporary borrowing – this forms part of General
Reserves.
 A contingency to cushion the impact of unexpected events or emergencies
– this also forms part of General Reserves.
 A means of building up funds often referred to as Earmarked Reserves, to
meet known or predicted liabilities.
7.3 LAAP Bulletin 99 also provided guidance on the further categories of
Earmarked Reserve that the Council is permitted to hold including insurance,
unspent grants and school balances.
7.4 The audited 2024/25 Annual Accounts included £68.284 million of General
Fund Reserves. More details on the levels of cash backed Reserves are set out
in Appendix E. When the earmarked Reserves of £49.569 million (see
Appendix G) were removed, there was an uncommitted balance of £18.715
million which equates to 4% at 31 March 2025.
Proposals to Earmark Reserves
7.5 Revenue Budget 2025/26 - Update No 3, which was considered by the Finance
and Resources Committee on 4 February 2026 (Report No. 25/24 refers),
included the projected outturn for the Council’s 2025/26 General Fund Revenue
Budget. These projections have been further refined to recognise several
adjustments which are required in closing the Council’s 2025/26 Annual
Accounts and represent material changes to the projected outturn.
7.6 The impact of these projections on the level of balances is summarised in
Appendix F, which indicates a projected General Fund (excluding HRA)
balance of £55.431 million at 31 March 2026. Of this projected balance,
£38.361 million is earmarked for the specific purposes as set out in Appendix
G with a projected uncommitted balance of £17.070 million.
7.7 As is the case in previous years, there remain some areas of uncertainty in
relation to the projected level of balances at 31 March 2026 including the final
impact of weather-related events or additional grant income.
7.8 Based on the Council’s existing financial and policy commitments and the work
undertaken in preparing the Provisional Revenue Budgets, it is proposed that
the amounts included in Appendix G be earmarked against the projected
General Fund balance.

Page 24

7.9 The balances of £38.361 million identified in Appendix G above and described
in more detail in Appendix H will be monitored as part of the revenue
monitoring process. Any proposals to make use of the balances will be subject
to approval by either the Finance and Resources Committee or Council.
7.10 ACTION: The Council is asked to maintain a prudent approach to the
application of Reserves and earmark the General Fund Balances of
£38.361 million identified in Appendix G – RECOMMENDATION 2.6.
Proposed Approach to Managing Unearmarked General Fund Reserves
7.11 To assess the adequacy of unearmarked General Fund Reserves, it is
necessary to take account of the strategic, operational and financial risks facing
the Council, which are set out in Section 8 of this report.
7.12 In addition, Councils are expected to retain the equivalent of 0.2% of their
annual Net Revenue Budget to deal with unforeseen emergencies (£902,502 in
2025/26 for Perth and Kinross Council) before being eligible for support through
the Bellwin Scheme.
7.13 Taking account of all the risks and historical experience in Perth and Kinross
since 1996, it is recommended that the targeted level of uncommitted non-HRA
General Fund Reserves continues to be in the range of 2% to 4% of the
Council’s Net Revenue Budget in the medium term.
7.14 Based on the Net Provisional Revenue Budget for 2026/27 of £527.619 million
as detailed in Appendix B, this would mean a level of uncommitted Reserves
of between approximately £10.552million and £21.104 million for 2026/27.
7.15 The Council has targeted a level of uncommitted Reserves between 2% and
4% range for several years. Whilst this range is still considered to be
appropriate, it should be noted that the level of risk involved in managing the
Council’s Revenue Budget is significant. There is currently no confirmation of
the Council’s Scottish Government funding beyond 2026/27, and it is
anticipated that Council services will continue to operate in a challenging
financial environment in future years.
7.16 Based on the level of Earmarked Reserves of £38.361 million as set out in
Appendix G, the level of unearmarked Reserves is £17.070 million which
equates to 3.24%.
7.17 ACTION: The Council is asked to approve that uncommitted Reserves are
maintained at a minimum of 2% to 4% of the 2026/27 Net Revenue Budget
which equates to £10.552 million to £21.104 million – RECOMMENDATION
2.7.
7.18 In the event that any use of General Fund Reserves is made in determining the
2026/27, 2027/28 and/or 2028/29 Revenue Budgets, this should only be done
on the basis of a sustainable strategy, which ensures that future years’
Revenue Budgets are not dependent upon the continuing use of Reserves.

Page 25

7.19 Appendix I to the report shows the contributions to and from Reserves
recommended in setting the Provisional Revenue Budget for 2026/27 and
anticipated in 2027/28 and 2028/29.
8. Risk Assessment
8.1 Determining the Revenue Budget and Reserves Strategy requires
consideration of the strategic, operational, financial and non-financial risks
potentially facing the Council.
8.2 The General Fund Reserves Strategy is integral to supporting the Council’s
approach to the management of financial risk. Both the uncertainty of future
events and resource constraints make it impractical to mitigate against all
potential risks. In developing its medium-term financial plan, the Council must
also be aware of the sustainability of its expenditure proposals. Significant risks,
which are of relevance are outlined below.
Financial Risks
Uncertainty in National and Local Government Funding
8.3 There remains significant uncertainty over future funding levels from the
Scottish Government. The Medium-Term Financial Plan highlights ongoing
volatility in the fiscal environment, which affects the Council’s capacity to plan
with confidence over multiple years.  A commitment to providing multi year
settlements from the Scottish Government would assist with financial planning.
Constraints on national budgets, distribution methodology, and emerging policy
commitments continue to represent a major risk to financial planning.
Inflationary and Economic Pressures
8.4 High inflation and wider economic pressures continue to drive up the cost of
delivering services, including construction, contracts, utilities, and supplies.
Current economic conditions, particularly in the construction sector, are
weakening the reliability of cost assumptions underpinning both revenue and
capital budgets.  Global uncertainty adds further levels of risk in this area.
8.5 Income streams, such as planning fees, council tax, rents, and commercial
returns, also remain sensitive to wider economic conditions.
Pay Awards and Workforce Costs
8.6 Future pay awards remain a substantial financial risk. Budget assumptions
include pay increases of around 3% annually, however recent agreements have
exceeded the budgeted provision. Without additional funding to offset these
pressures, this represents a material risk to the Council’s financial position.

Page 26

Delivery of Approved Savings
8.7 There is a risk that due to capacity constraints, workforce shortages, and rising
demand in statutory service areas, there are delays and challenges in
delivering approved savings.  Where savings rely on transformation, service
redesign, or partnership working, timelines and deliverability may slip, affecting
in year and future year budget positions.
Social Care Pressures
8.8 The Health and Social Care Partnership continue to experience rising levels of
need and structural funding challenges. Coupled with the demographic
projections that show significant levels of growth in the number of older people,
this places significant pressures on resources.
Reserves and Financial Resilience
8.9 The Council’s ability to manage financial shocks depends on the adequacy of
its level of both earmarked and unearmarked reserves.  Within the Reserves
Strategy, £1 million has been earmarked to provide additional capacity to
support social care activity should projections exceed the mid-range scenario
that has been developed.
Non-Financial Risks
Demographic Change and Rising Service Demand
8.10 Population ageing continues to drive increased demand in social care, health,
and community-based services. Shifts in need intensity, particularly for older
people and vulnerable adults, pose significant service and financial challenges.
Changes in population distribution also affect school rolls, transport demand,
and infrastructure planning-based services.
Workforce Availability and Recruitment Challenges
8.11 The ability to recruit and retain staff with the right skills is a growing risk,
particularly in social care, technical roles, digital services, and specialist areas.
Workforce shortages can affect service performance, reduce organisational
capacity, and impede the delivery of transformation programmes and savings.
8.12 We are reviewing options for our lowest paid workers to maintain pay
differentials and establish an entry-level rate that differs from the current
grading structure. Our plan is to explore these options and work with the unions
to address pressures from the Real Living Wage (RLW) and implement any
changes once this year's RLW announcement is made, which is expected in
October 2026, with any proposed changes effective from 1 November 2026.

Page 27

Staff Resilience
8.13 The Council’s most recent Employee Engagement Survey indicates a
significant reduction in the proportion of staff who believe that their wellbeing is
a priority for the organisation, with a 10.5% reduction compared to the 2024
survey. While full survey analysis is still underway, early insights from open
text comments highlight that workload pressures and staffing levels are the
primary factors influencing this decline.
8.14 Feedback suggests that many employees are providing considerable
discretionary effort to mitigate the impact of staffing reductions, support
service delivery, and manage slippage against targets. Although the Council
does not yet have a quantified measure of the extent to which this discretionary
effort is sustaining performance, work is being planned to assess this. Early
indications are that such reliance is contributing to the maintenance of some
service areas, but that this position is unlikely to be sustainable in the long
term.
8.15 Reduced perceptions of wellbeing, alongside employee commitment to
maintaining public services in challenging circumstances, present a risk to the
organisation. These factors may affect workforce resilience, recruitment and
retention, service quality, and the Council’s ability to deliver its transformation
ambitions at pace. As part of ongoing workforce planning and risk mitigation,
this area will remain under close review.
Climate Change and Severe Weather Events
8.16 Climate change increases the frequency and severity of extreme weather
events, placing pressure on roads, flood prevention, and emergency response
services. These events can cause unplanned expenditure and disrupt service
delivery.
Transformation and Change Delivery Risks
8.17 The Council’s transformation programme is essential for long-term financial
sustainability. However, transformational change carries inherent risks,
including dependency on partner organisations, consultation requirements,
service redesign complexities, and the need for robust change management.
Slippage or redesign failures could impact both budget savings and service
outcomes.
Partnership and Third Sector Dependencies
8.18 External partners and voluntary sector organisations play a critical role in
delivering community services. Reductions in grant funding or changes in
commissioning may impact service continuity. Dependencies on third sector
providers also carry risks if organisations face financial fragility.

Page 28

Legislative and Policy Changes
8.19 New statutory duties, changes to national policy (including education, health
and social care reform, and environmental regulations), and potential
alterations to local taxation frameworks could increase demand, create
additional responsibilities, or reduce flexibility in local decision-making.
Technology, Cybersecurity, and Digital Reliance
8.20 Increasing reliance on technology to deliver services introduces risks relating to
cyber-security, system failure, and data protection compliance. A significant
cyber incident could disrupt operations and require substantial investment in
system restoration and security enhancement.
General Risk
8.21 Officers have deliberately minimised the level of expenditure pressures that
were introduced into the revenue budget.  Should there be increases in levels
of demand (need) across the range of Council functions, this may have a direct
impact on service delivery and the ability to work within the financial plan set
out within this report.
8.22 The Council faces a complex risk environment characterised by increasing
demand pressures, financial uncertainty, escalating workforce challenges, and
external volatility. Effective mitigation will require:
 Robust medium term financial planning and regular review of assumptions
 Continued focus on transformation to deliver sustainable service models
 Strengthening of reserves and risk based decision making based
 Close monitoring of economic, policy, and demographic trends
 Strong partnership working across public, private, and third sector
stakeholders
8.23 Finally in relation to risk, a lack of organisational willingness to respond to the
challenges we face, to consider data and evidence, consider the requirement to
review all services, statutory, non statutory, universal or targeted will impact on
our ability to continue to deliver a balanced budget and the Council’s stated
corporate priorities.
9. Conclusions
9.1 The Strategic Planning and Revenue Budget Report sets out a clear and
evidence based approach to how Perth and Kinross Council will navigate a
period of sustained demographic, financial and operational pressure while
maintaining a strong focus on its vision: a Perth and Kinross where everyone
can live life well, free from poverty and inequality.
9.2 The three year Provisional Revenue Budgets for 2026/27 to 2028/29 are
framed within this ambition.

Page 29

They balance the requirement for financial sustainability with the need to
protect and invest in services that support individuals, families and communities
experiencing the greatest need.  They balance the requirement for financial
sustainability with the need to protect and invest in services that support
individuals, families and communities experiencing the greatest need.
9.3 Despite a cash increase in the Scottish Government’s funding package for
2026/27, much of this is directed toward nationally determined commitments.
9.4 Significant cost pressures, rising demand in social care and education,
workforce constraints, inflationary impacts, and increasing statutory obligations
continue to shape complex choices for the Council.
9.5 The Council’s strong track record of prudent financial management, as
recognised by external audit, underpins the proposed approach. The Reserves
Strategy ensures appropriate levels of both earmarked and uncommitted
balances, supporting resilience against future uncertainty while avoiding
reliance on reserves to fund recurring expenditure.
9.6 At the same time, the Transformation and Improvement Programme continues
to deliver real benefits - modernising services, driving prevention and early
intervention, strengthening partnership working, and maintaining a disciplined
approach to prioritisation.
9.7 Looking ahead, the financial outlook beyond 2026/27 remains challenging, with
a projected funding gap emerging in 2027/28 and 2028/29. Addressing this gap
will require early and meaningful engagement with elected members,
communities and partners to reshape services, focus resources on what
matters most, and continue the pace of transformation across the organisation.
9.8 Overall, this report demonstrates that while the scale of challenge should not be
underestimated, Perth and Kinross Council remain committed to:
 delivering on its Corporate Plan priorities
 supporting those with the greatest need
 protecting frontline services where possible
 investing in innovation, prevention and long-term sustainability
 working collaboratively with partners to improve outcomes for local people
9.9 Through strong governance, clear strategic focus and disciplined financial
stewardship, the Council can continue to meet the needs of its communities
and uphold its commitment to working together towards a Perth and Kinross
where everyone can live life well, free from poverty and inequality.
10. Impact Value Assessment
Impact and Value Assessment

Page 30

11. Appendices
A. Budget Survey Results - Summary Report
B. 2026/27, 2027/28 and 2028/29 Provisional Revenue Budgets
C. Executive Summaries
D. 2026/27 Fees and Charges
E. Summary Cash Backed Reserves – 2024/25 Actual and 2025/26
Projected
F. Projected General Fund Balance at 31 March 2026
G. Earmarked Reserves at 31 March 2026
H. Summary of Earmarked Reserves at 31 March 2026
I. Summary of Projected Use of General Fund Balances 2026/27, 2027/28