Appendix 1 - Reshaping the Tay Cities Deal - Activities and Timetable
Perth and Kinross Council · 25 February 2026
Back to Perth and Kinross Council — 25 February 2026 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
Appendix 1 Reshaping the Tay Cities Deal – activities and timetable Key Activities and Actions for the Reshaping of the Tay Cities Region Deal Programme Deadline Date Approach presented and agreed at March Management Group. 6th March Partnership approach shared with both Governments. 14th March Partnership Annual Conversation with both Governments. 20th March Approach and Annual Performance Report presented to Joint Committee Members for consideration and approval. 21st March Updated approach, reshaping timetable and supporting documentation to be shared at April Management Group for consideration and approval. 17th April Output commitments workshop with Partners (Management Group (inc. Heads of Economic Development Group Chair) and Finance Directors Group). 24th April Development of Approach All key documentation to be shared with the local authority leads and Thematic Boards. 30th April The lead local authority Directors to obtain and submit assurance that the Programmes, Fund and Projects can be fully delivered as entered into Deal, following liaison with the relevant Thematic Boards. 23rd June 2025 Assessment and Recommendations from Strand 1A presented in a report to Management Group and Finance Directors Group. 28th August 2025 Strand 1A Assurance of Existing Projects Joint Committee informed of progress of Strand 1A work. 3rd October 2025 The lead local authority Directors will identify and submit substantive changes, via change request process, for existing projects following liaison with the relevant Thematic Boards. 15th October 2025 Review and assessment by Partnership Review Panel. w/c 17th November 2025 Assessment and Recommendations from Strand 1A and 1B existing projects presented in a report to Management Group and Finance Directors Group. 27th November 2025 Joint Committee informed of progress of Strand 1A and 1B work and agreed Strand 2 process and call for new projects. 12th December 2025 Strand 1B Substantive Changes to Existing Projects Existing projects from Strand 1A and 1B to complete agreed actions. 28th February 2026 New Projects SOC submission. 13th March 2026 Review and assessment by Partnership Review Panel. 13th April 2026 Report provided to Finance Directors Group ahead of Management Group. 14th May 2026 Assessment and Recommendations from Strand 2 presented to Management Group. 28th May 2026 Partnership engagement with Governments with outcome of Strands June 2026 Strand 2 New Projects Update to Joint Committee on outcome of reshaping work. 19th June 2026
Page 2
The revised Programme, and any new projects identified in Strand 2, will need to seek and secure Ministerial approval. It has been indicated that this would typically take 8-12 weeks. The Partnership will need to provide a formal submission with supporting evidence for this request. The detailed breakdown will be set out in a later version of the timetable. Formal Engagement with Governments to Confirm New Programme Report to Joint Committee (potential for special Joint Committee date if Partnership are in a position to have an agreed Programme earlier). June - September 2026 (Ministers - subject to availability) *pre-election end of March - May and Summer recess June - end of August will impact on Government Civil Servant and Ministerial availability