Update on Perth and Kinross Projects Under Tay Cities Region Deal Programme - Update on Local Growth Fund and Regional Economic Partnership Arrangements

Perth and Kinross Council · 25 February 2026
Back to Perth and Kinross Council — 25 February 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality
___________________________________________________________________
Committee or Board: Perth and Kinross Council
Date of Meeting: 25 February 2026
Report Title: Update on Perth and Kinross Projects Under Tay
Cities Region Deal Programme - Update on Local
Growth Fund and Regional Economic Partnership
Arrangements
Report Number: 26/51
Report Author: Steve MacDonald, Economic Development Manager –
Business, Place and Investment
Organisational Lead: Serge Merone, Strategic Lead – Economy,
Development and Planning
___________________________________________________________________
1. Purpose
1.1 The purpose of this report is to give an update on the process of Reshaping
the Tay Cities Deal (TCD), including the status of existing projects and
possible new projects.  The report also seeks to position Perth and Kinross
Council in relation to forthcoming regional investment decisions associated
with the Local Growth Fund, announced by the UK Government in January
2026 and evolving Regional Economic Partnership arrangements.
1.2 Sections
1. Purpose
2. Recommendations
3. Main Issues
4. Proposals
5. Conclusion
6. Impact Value Assessment
7. Appendices

Page 2

2. Recommendations
It is recommended that the Council:
2.1 consider and comment on the contents of the report including the scale of
funding opportunities from Tay Cities Deal Programme Strand 2 and Local
Growth Fund.
2.2 agree that Council priorities are clearly articulated and promoted through the
Tay Cities Regional Economic Partnership in relation to Strand 2 projects,
taking into account Tay Cities Deal and Local Growth Fund criteria.
2.3 agree that the Leader of the Council and the Chief Executive engage with Tay
Cities partners and other local authorities to understand and assess the
implications of emerging Scottish and UK Government approaches to
Regional Economic Partnerships for local authorities, the Tay Cities Regional
Economic Partnership and Perth and Kinross Council.
2.4 agree that Strategic Lead – Economy, Development and Planning provide a
further update on projects at a future meeting.
3. Main Issues
Tay Cities Regional Deal Programme
3.1 This report presents the Perth and Kinross Tay Cities Deal projects which we
are required to appraise under the ‘Reshaping the Tay Cities Deal
Programme’.  This was considered by the Council on 7 May 2025 (Report
25/111) and on 10 September 2025 (Report 25/223).
3.2 The Tay Cities Region Deal Joint Committee has agreed an approach to
reshape the Tay Cities Programme at this halfway stage.  This involves an
assessment of all projects currently in development within each local authority
area.  This means confirming with project owners whether the projects
continue unchanged (Strand 1A), projects continue with agreed changes
(Strand 1B) and new projects replacing decommitted funding (Strand 2).
3.3 A new refreshed programme will be agreed with partners and governments
between June and September 2026 for the last four years of the programme.
The process and the agreed timetable are outlined in more detail in Appendix
1 of this report.
3.4 Officers have engaged with partners and project owners for the projects being
proposed in Perth and Kinross over the past months to assess the viability of
projects (Strand 1A and Strand 1B) to allow this to be fed into the overall
review of the programme.
3.5 All existing Strand 1A and Strand 1B projects have now been assessed by the
Tay Cities groups and actions and milestones have been identified.

Page 3

3.6 A summary of the current position of the Strand 1A and Strand 1B projects
after assessment is given below.
PROGRAMME/PROJECT FUNDING
(000’s)
STRAND 1A & 1B
(by 28 February 26)
Funding reallocated
to STRAND 2
Perth Bus and Rail Station
(PKC) 
15,000 Y
Low Carbon Transport Active
Travel Hub (Phase 2) (PKC)
1,265 Y
Regional Skills Programme 16,500 Y
Perth Innovation Highway (PKC) 5,000 Y
Innerpeffray Library (IL Trust) 100 Y
Aerospace Kinross (Aerospace
Kinross)
1,600 Y
Project Beacon (Binn Eco Park) 5,200 Y
Low Carbon Transport -
Hydrogen Refuelling Station
(Phase 3) (PKC)
1,446 N 1,446
Aviation Academy for Scotland 8,100 N 8,100
Crieff International Highland
Centre
1,000 N 1,000
Tay Adventures
Pontoons/Accommodations
1,067 N 1,067
Total Strand 1 retained 44,665
Total reallocated to Strand 2 11,613
3.7 The following projects were deemed at Stage 1A on track to continue as
entered in the Deal:
- Perth Bus and Rail Station – Options Appraisal carried out and Outline
Business Case being developed. 
- Low Carbon Transport (Phase 2 - Active Travel) – Integrated to Perth
Bus and Rail Station Outline Business Case.
- Innerpeffray Library – Business Justification Case due for submission.
- Perth Innovation Highway – Integrated to Perth Eco-Innovation Park
project at Perth West with detailed design and planning application
currently being developed.
- Regional Skills Programme – Revised programme approved.
3.8 The following projects were deemed at Strand 1B to be on track to continue
as agreed in the Deal with change requests due to various alterations in the
projects:
- Project Beacon (Plastics Recycling).  Issues related to subsidy control –
new delivery model and Outline Business Case being developed to
inform change request.
- Aerospace Kinross.  Change of location site – new site agreed with PKC
and change request in progress.
3.9 All Strand 1A and Strand B existing projects have been given the deadline of
28 February 2026 to demonstrate progress towards agreed actions and
milestones to remain in the programme.

Page 4

3.10 The following projects were deemed not on track to continue as entered in the
Deal and have been decommitted:
- Low Carbon Transport (Phase 3 - Hydrogen Refuelling Station).  Change
of location and public accessibility did not align anymore with the agreed
Low Carbon Travel Programme funded by the Scottish Government.
- Aviation Academy for Scotland.  The project was led by UHI Perth and
linked closely to Air Service Training which went into liquidation.  No
alternative project has been identified. Funding was provided by UK
Government for a capital project, supporting skills development in a
specific sector.
- Crieff International Highland Centre.  The project had a funding gap
which was not resolved, and the project promoter withdrew the project.
- Tay Adventures (pontoons and accommodation projects).  The project
promoter, Tay and Earn Trust, withdrew the projects due to land
ownership and deliverability issues.
3.11 In total, it is estimated that £30m has been decommitted at regional level and
will be available across the region for new projects under Strand 2.
Local Growth Fund
3.12 The UK Government set up the Local Growth Fund, a £140 million initiative
supporting economic growth across the UK.  It has been presented as a
replacement of the UK Shared Prosperity Fund (UKSPF) running alongside
the Pride in Place Programme and the existing City Region Deals.
3.13 On 8 January 2026, the UK Government announced the funding allocation for
the Local Growth Fund for Scotland from 2026 to 2029.  The funding is
allocated through the Regional Economic Partnership and Tay Cities Regional
Economic Partnership will receive £19.5m over the three years, split between
revenue £6.045m (31%) and capital £13.455m (69%).  For information,
UKSPF was allocated at local authority level and the Perth and Kinross
allocation for 2025/26 was £1.877m split between Capital £532K (28%) and
Revenue £1.345m (72%).
3.14 The UK Government has still to provide detailed information on the new
investment themes and interventions framework, as well as governance and
delivery arrangements - including how delivery through Regional Economic
Partnerships is expected to work in practice.  However, it is understood that
the funding would not be split between local authorities but would support
regional programme and activities.
3.15 Discussions have taken place between UK Government officials and officers
within the Tay Cities region.  The shift from local authority-allocated UKSPF
funding to regionally-managed Local Growth Fund investment represents both
a risk to locally delivered revenue programmes and an opportunity to secure
investment in Perth and Kinross.  There is a risk of reduced revenue funding
to employability activities at local authority level.

Page 5

The role of the Regional Economic Partnership and related governance
arrangements to channel the Local Growth Fund are not yet known.  There
would be a need for early influence the focus of the Local Growth Fund which
seems to be driven by investment themes around Infrastructure, Business
support and Skills and how these relate to the Tay Cities Regional Economic
Strategy and Perth and Kinross Economic Action Plan.  
Regional Economic Partnerships
3.16 The Scottish Government has signalled its intention to strengthen the role of
Regional Economic Partnerships (REPs), including potential future legislation
to be introduced in the next Parliament, subject to the election outcome, to
expand their strategic capacity and devolved competencies in areas such as
skills, economic development and planning.
3.17 This approach reflects UK Government expectations that REPs lead the
development of tailored regional investment plans as promoted through the
Local Growth Fund.
3.18 The Tay Cities Regional Economic Partnership was established in 2021 as
part of the Scottish Government REP framework.  It is the collaborative
regional body responsible for driving inclusive, sustainable economic growth
across the Tay Cities Region, covering Angus, Dundee City, North-East Fife,
and Perth & Kinross.  Through a Joint Committee, it brings together local
authorities, the private sector, universities and colleges, enterprise and skills
agencies, and the third sector to align investment and delivery around shared
regional priorities. The Council is represented by three elected members on
the Joint Committee.
3.19 The Partnership builds on the Tay Cities Region Deal agreed in 2020, a £700
million long term investment programme jointly supported by the Scottish and
UK Governments, aimed at creating more and better paid jobs, boosting
productivity, and reducing inequalities across the region.  The partnership
provides the strategic leadership and governance needed to coordinate this
investment and maximise its economic impact.
3.20 It is guided by the Tay Cities Regional Economic Strategy (2019–2039) and
the Prospectus for Regional Growth (2025-2035) which focuses on growing a
knowledge led economy, increasing innovation, supporting business growth,
and improving access to opportunity and fair work.  Key opportunity areas
include life sciences, advanced manufacturing, clean energy and the net zero
transition, food and drink, research and innovation, and digital and creative
industries.
4. PROPOSALS
Tay Cites Regional Deal Programme
4.1 It is proposed that officers continue to work with the Strand 1A and 1B existing
project owners.

Page 6

4.2 Following the Tay Cities Joint Committee meeting on 12 December 2025, a
call for new projects was launched under Strand 2.  Interested parties have
been asked to submit a Strategic Outline Case by 13 March 2026.  They have
also been asked to register an interest with their local authority to discuss
their proposals.  The minimum funding ask from Tay Cities Deal is £5m and it
is for capital-only.
4.3 The Tay Cities Deal Strategic Outline Case guidance and template (TCRD -
Strategic Outline Case Guidance) state several criteria against which
proposals will be assessed. The main ones are detailed below:
- This funding opportunity is for new projects only and not for current
projects or to extend current projects within the Deal.
- The prospective new projects should align with the aims and vision of
the Deal Document, the Tay Cities Regional Economic Strategy  and
Region Prospectus for Regional Growth.  There are 10 key commitments
for the Deal, although projects may have identified additional outputs
and benefits in addition to these.  All Projects are expected to contribute
to the delivery of at least one of the agreed key commitments/benefits.
These are:
- New Jobs
- Construction Jobs
- Jobs Protected
- Training Places
- Journey Time Savings
- Development Space Unlocked
- Number of Visitors
- Start-Ups
- SME’s Supported
- Leverage
- In addition, subsidy control, deliverability and the use of HMRC 5 case
model methodology will also be key assessment criteria.
4.4 Officers have engaged with interested external parties while also developing
Council-led proposals.  These proposals are progressing at different stages
and are being led by a mix of private and voluntary sector organisations. 
They cover several sectors, including food and drink innovation, clean growth
innovation, mobility or culture and tourism.
4.5 In addition, under the existing Tay Cities Tourism programme, a Tourism
Challenge Fund may be launched. The Council will support this approach,
including the development of the criteria that would underpin the fund.
4.6 It is proposed that the Council notes the Tay Cities Deal criteria and
associated commitments which will be used to assess proposals.  As it is an
open call, the Council cannot prevent interested parties from applying.

Page 7

However, it is proposed that Council’s support for the development or delivery
of any project would be guided by the Tay Cities Deal criteria outlined above,
alongside the Council’s corporate priorities. The Council asks that officers
continue to work with interested parties to bring forward Strategic Outline
Cases under Strand 2, and to support interested parties, including through
any Tourism Challenge Fund, should it be approved.
Local Growth Fund
4.7 It is proposed that officers continue to liaise with UK Government officials and
with their local authority counterparts either directly or through established Tay
Cities groups to maximise benefits to Perth and Kinross.
4.8 Officers will also work to create a strong pipeline of projects aligned with Tay
Cities Regional Economic Strategy and Prospectus and Perth and Kinross
Economic Action Plan to maximise funding opportunities from the Local
Growth Fund.
Regional Economic Partnerships
4.9 It is proposed that the Leader of the Council and the Chief Executive engage
with Tay Cities partners and other local authorities to understand and assess
the implications of emerging Scottish and UK Government approaches to
Regional Economic Partnerships for local authorities, the Tay Cities Regional
Economic Partnership and Perth and Kinross Council, and to report back to
the Council.
5. Conclusions
5.1 The Reshaping of the Tay Cities Deal process is a necessary exercise to
ensure that both UK Government and Scottish Government funding and any
leverage are used efficiently and effectively and contribute to deliver the
agreed economic, environmental and social outcomes.
5.2 The Deal was signed on 17 December 2020.  The circumstances of individual
projects and organisations have changed over this period.  Therefore, a
reshaping exercise is being carried out.  Project promoters and the Council
are working hard to retain the funding allocated to Perth and Kinross area
either through existing projects or new projects.
5.3 The UK Government has announced a Tay Cities allocation of £19.5m for the
Local Growth Fund over three years to be channelled through Tay Cities
Regional Economic Partnership.  Further details are expected to understand
how this funding would be used and will be shared in due course.
5.4 Both Scottish and UK Governments are intending to strengthen the role of
Regional Economic Partnerships (REPs) and this would have implications at
national, Tay Cities and Perth and Kinross levels.

Page 8

6. Impact and Value Assessment
6.1 This report has been classified as being an operational report and as such
does not require a full Impact and Value Assessment. 
7. Appendices
7.1 Appendix 1:  Reshaping the Tay Cities Deal – activities and timetable