4(ii)(c) 
LRB-2023-39 
LRB-2023-39
23/00532/FLL - Erection of a dwellinghouse and associated
works, land north of 31 Main Street, Keltybridge 
REPRESENTATIONS

Page 2

No embedded text on this page.

Page 3

No embedded text on this page.

Page 4

No embedded text on this page.

Page 5

No embedded text on this page.

Page 6

No embedded text on this page.

Page 7

No embedded text on this page.

Page 8

No embedded text on this page.

Page 9

No embedded text on this page.

Page 10

No embedded text on this page.

Page 11

No embedded text on this page.

Page 12

No embedded text on this page.

Page 13

No embedded text on this page.

Page 14

No embedded text on this page.

Page 15

No embedded text on this page.

Page 16

No embedded text on this page.

Page 17

No embedded text on this page.

Page 18

No embedded text on this page.

Page 19

No embedded text on this page.

Page 20

No embedded text on this page.

Page 21

No embedded text on this page.

Page 22

No embedded text on this page.

Page 23

No embedded text on this page.

Page 24

No embedded text on this page.

Page 25

No embedded text on this page.

Page 26

No embedded text on this page.

Page 27

No embedded text on this page.

Page 28

No embedded text on this page.

Page 29

No embedded text on this page.

Page 30

No embedded text on this page.

Page 31

No embedded text on this page.

Page 32

No embedded text on this page.

Page 33

No embedded text on this page.

Page 34

No embedded text on this page.

Page 35

No embedded text on this page.

Page 36

No embedded text on this page.

Page 37

No embedded text on this page.

Page 38

No embedded text on this page.

Page 39

No embedded text on this page.

Page 40

No embedded text on this page.

Page 41

No embedded text on this page.

Page 42

No embedded text on this page.

Page 43

No embedded text on this page.

Page 44

No embedded text on this page.

Page 45

No embedded text on this page.

Page 46

No embedded text on this page.

Page 47

No embedded text on this page.

Page 48

No embedded text on this page.

Page 49

No embedded text on this page.

Page 50

No embedded text on this page.

Page 51

No embedded text on this page.

Page 52

Mr Cameron Hunter (Objects) 
Comment submitted date: Thu 18 May 2023 
I firmly object to this proposal based on the following areas of concern: 
- This directly contravenes the original basis upon which the planning for the two
adjacent properties was granted. The revised application for the two dwellings, dated
11th February 2020 stated that the area of ground related to the application "should
be allowed to re-wild and vegetate naturally". I do not see a reasonable means by
which PKC can grant this application, as this would involve directly revoking their
own stipulations made previously. 
- Approval of this application would see the removal of the only remaining green
space within Keltybridge, which is itself a conservation area and is steeped in history,
and should be subjected to controls due its historical value. At a time where the
harmful environmental effects of the UK's diminishing biodiversity are being regularly
highlighted nationally, this application, if approved, unnecessarily exacerbates a
known and serious problem caused by over development. 
- There is an existing commitment from the applicant to make the land good,
returning it to its natural state following the previously approved works relating to the
three recently built properties. A commitment which has yet to be fulfilled, as the land
has been used a storage site for building waste and machinery thus far. Little to no
effort has been made to meet this commitment throughout what has been a
disruptive 2 years of works, which often restricted road access, causing residents
significant day-to-day disruption. 
- The area itself, is by far too small in its scale to host a dwelling house. This would
lead to over intensive development of the area, with a disproportionate density of
buildings eroding its character.

Page 53

No embedded text on this page.

Page 54

No embedded text on this page.

Page 55

No embedded text on this page.

Page 56

No embedded text on this page.

Page 57

No embedded text on this page.

Page 58

No embedded text on this page.

Page 59

Town & Country Planning (Scotland) Act 1997
The Town & Country Planning (Schemes of Delegation & Local Review
Procedure) (Scotland) Regulations 2013
Application Ref: 23/00532/FLL - Erection of a dwellinghouse and associated
works, land north of 31 Main Street, Keltybridge
Written Submission from Mr. G. and Mrs J. Simpson, .
Thank you for notifying us of the above APPEAL. We have confidence the members of the Local Review
Body (LRB) will study all of the relevant documents leading to the Planning Officer’s Delegated Report
of Handling and including our original terms of objection. Therefore, we do not find it necessary to go
over such terms again but rather seek to highlight the following material considerations in planning: 
The appellant’s focus: the appellant has listed no less than 13-formal planning submissions for this
land; 25- policies; 5-Supplementary Guidance; 3-national Guidance. It is not necessary to focus on
such an exhaustive listing. We demonstrate why below. 
The Planning Unit: the planning unit in this case relates to the site of planning applications
13/02177/FLL and 20/00201/FLL. The former granted planning permission with 9 conditions for the
erection of two houses on the land and Condition 7 related to landscaping of the plot of land. 
Condition 7   The approved landscaping and planting scheme shall be fully implemented within six
months of the completion of the development and thereafter maintained by the applicants or
their successors to the satisfaction of the Planning Authority. 
Reason - In the interests of visual amenity and environmental quality.
The 2020 submission only sought to update some of the architectural details of the houses by way of
amendment. The Planning Officer’s report did however state as below:
Landscape 
Landscaping plans have previously been included as part of the site
design but have not been submitted with this application.  The area
to the north contains an existing septic tank associated with
housing on the other side of the road. This was originally going to
be removed and the area landscaped.   Following correspondence with
the agent it is noted that the septic tank is not to be removed and
that it is proposed that this area is largely to be left to re-
vegetate naturally.  As limited information has been provided as to
how this affects the previously approved landscape plan it is
proposed to request landscaping detail by condition.  
(COPY EXTRACT FROM OFFICER’S DELEGATED REPORT 20/00201/FLL)
Condition 3 was imposed: 3    Prior to 31st July 2020 full details of the
landscaping and planting scheme for the site shall be submitted for
the further written agreement of the Council as Planning Authority. 
The scheme shall include full details of all hard and soft
landscaping including materials and installation methods and,
species, height, size and density of trees and shrubs to be planted. 
The scheme as subsequently approved shall be carried out and
completed within the first available planting season (October to
March) after the completion or bringing into use of the development,
whichever is the earlier, and the date of Practical Completion of
the landscaping scheme shall be supplied in writing to the Council

Page 60

as Planning Authority within 7 days of that date.  The approved
scheme shall thereafter be maintained, with any planting which fails
to become established within five years being replaced in the following
planting season with others of a size and species as previously approved. 
Reason - To ensure a satisfactory standard of development and environmental
quality and to reserve the rights of the Planning Authority.
The above clearly shows the subject of this APPEAL is part of the ‘planning unit’ approved with
conditions for two houses and which are now built. NB A landscape and planting plan was submitted
in May 2017, but it is not clear if this was approved or not.
The Current proposal: It is most disconcerting so much of this is set aside by the appellant and to the
extent that planning matters and contexts are often conflated and subject to rhetoric and mere
rebuttal of the Council’s determination. More importantly we place our full confidence in the terms
of the Report of Handling which after detailed consideration, recommended refusal with clear and
comprehensive reasons given. 
Please note the plot ratio if this appeal were upheld means that the resultant plot ratio for the existing
two houses is “over-development”. 
Landscaping and the planning unit: 
NMV LANDSCAPE AND SITE PLAN was submitted in May 2017 under 13/02177/7, however it is not
clear if this was approved or not.
When purchasing our property, we were advised by the Developer of the plan to place a locked gate
at the entrance to the adjacent land, together with the clear intention to plant wildflowers and allow
rewilding of this area. It seemed clear then when the build of the two approved houses was near
completion, that landscaping of the land north of 31 Main Street was to begin. This has never
happened, the land was piled high of building materials and waste for over a year, with a ‘Portaloo’
toilet sited immediately outside our living room window.  
The appellant is looking to build a third property when it was made clear under planning reference
13/002177 as amended that two houses could be built, on the condition the remaining land was
rewilded, landscaped and set aside as green space. We call on the Local Review Body to uphold the
decision made by Planning professionals, set out in what is a carefully considered Report of Handling,
to secure that the landscape quality of the site is enhanced and delivered in the way already approved
and for the compelling reasons asserted. The full extent of land subject of this APPEAL is part of our
planning unit. 
Since it is not clear whether the appellant is willing to carry out the landscaping required, we humbly
suggest or request that the LRB determines that the Council, as planning authority, asserts an
emergency TPO on the land and to thereafter register same in accord with the processes under
Planning Circular 1/2011 - Tree Preservation Orders. REASON: To safeguard the long-term visual
amenity and nature value of the land that is in the public realm. 
We thank the Local Review Body for taking time to read and consider our submission.

Page 61

CDS Planning Local Review Body
From:
Sent: 08 November 2023 07:53
To: CDS Planning Local Review Body
Subject: Re: LRB-2023-39
CAUTION: This email originated from an external organisation. Do not follow guidance, click links, or open
attachments unless you have verified the sender and know the content is safe.
Thank you for your email concerning the appeal against your decision with regard to planning application
Application Ref: 23/00532/FLL - Erection of a dwellinghouse and associated works, land north of 31
Main Street, Keltybridge
I have no further objections but would like to take this opportunity to fully support the robust refusal the application
has already received and to say that I see nothing in the appeal that justifies an overturn of the original decision.
Kind regards
Yours faithfully
Sarah Joice