4(ii)(a)
LRB-2025-10
LRB-2025-10
24/01954/FLL – Installation of solar panels and cabinet,
South Lodge, Ballindean, Inchture, Perth, PH14 9SF
Papers Submitted
By The
Applicant

Page 2

No embedded text on this page.

Page 3

Page 1 of 4
NOTICE OF REVIEW 
UNDER SECTION 43A(8) OF THE TOWN AND COUNTRY PLANNING (SCOTLAND) ACT
1997 (AS AMENDED)IN RESPECT OF DECISIONS ON  LOCAL DEVELOPMENTS 
THE TOWN AND COUNTRY PLANNING (SCHEMES OF DELEGATION AND LOCAL REVIEW
PROCEDURE) (SCOTLAND) REGULATIONS 2013 
THE TOWN AND COUNTRY PLANNING (APPEALS) (SCOTLAND) REGULATIONS 2008 
IMPORTANT: Please read and follow the guidance notes provided when completing this
form. Failure to supply all the relevant information could invalidate your notice of review. 
Use BLOCK CAPITALS if completing in manuscript 
Applicant(s) 
Name Graham Ritchie     
Address 
Postcode 
Contact Telephone 1
Contact Telephone 2       
E-mail* 
Agent 
Name       
Address             
Postcode       
Contact Telephone 1      
Contact Telephone 2       
E-mail*       
Mark this box to confirm all contact should be
through this representative: 
*Do you agree to correspondence regarding your review being sent by e-mail? Yes 
Planning Authority    Perth and Kinross 
Planning authority’s application reference number 24/01954/FLL 
Site address South Lodge, Ballindean, Inchture, Perthshire, PH14 9SF 
Description of proposed development 
Installation of solar panels and cabinet South Lodge Ballindean Inchture Perth PH14 9SF 
Date of application 20/12/2024 Date of decision (if any) 19/02/2025 
Note. This notice must be served on the planning authority within three months of the date of the
decision notice or from the date of expiry of the period allowed for determining the application.

Page 4

Page 2 of 4
Nature of application 
1. Application for planning permission (including householder application) 
2. Application for planning permission in principle 
3. Further application (including development that has not yet commenced and where
a time limit has been imposed; renewal of planning permission; and/or modification,
variation or removal of a planning condition) 
4. Application for approval of matters specified in conditions 
Reasons for seeking review 
1. Refusal of application by appointed officer 
2. Failure by appointed officer to determine the application within the period allowed
for determination of the application 
3. Conditions imposed on consent by appointed officer 
Review procedure 
The Local Review Body will decide on the procedure to be used to determine your review and
may at any time during the review process require that further information or representations be
made to enable them to determine the review.  Further information may be required by one or a
combination of procedures, such as: written submissions; the holding of one or more hearing
sessions and/or inspecting the land which is the subject of the review case.   
Please indicate what procedure (or combination of procedures) you think is most appropriate for
the handling of your review. You may mark more than one box if you wish the review to be
conducted by a combination of procedures. 
1. Further written submissions 
2. One or more hearing sessions 
3. Site inspection 
4. Assessment of review documents only, with no further procedure 
If you have marked box 1 or 2, please explain here which of the matters (as set out in your
statement below) you believe ought to be subject of that procedure, and why you consider further
submissions or a hearing are necessary: 
Site inspection 
In the event that the Local Review Body decides to inspect the review site, in your opinion: 
1. Can the site be viewed entirely from public land? No 
2. Is it possible for the site to be accessed safely, and without barriers to entry? Yes 
If there are reasons why you think the Local Review Body would be unable to undertake an
unaccompanied site inspection, please explain here:

Page 5

Page 3 of 4 
Statement 
You must state, in full, why you are seeking a review on your application.  Your statement must
set out all matters you consider require to be taken into account in determining your review. 
Note: you may not have a further opportunity to add to your statement of review at a later date.  It
is therefore essential that you submit with your notice of review, all necessary information and
evidence that you rely on and wish the Local Review Body to consider as part of your review.   
If the Local Review Body issues a notice requesting further information from any other person or
body, you will have a period of 14 days in which to comment on any additional matter which has
been raised by that person or body. 
State here the reasons for your notice of review and all matters you wish to raise.  If necessary,
this can be continued or provided in full in a separate document.  You may also submit additional
documentation with this form. 
Please see the attached document entitled 24_01954_FLL_Appeal_statement.docx 
Have you raised any matters which were not before the appointed officer at
the time the determination on your application was made?  Yes  No 
If yes, you should explain in the box below, why you are raising new material, why it was not
raised with the appointed officer before your application was determined and why you consider it
should now be considered in your review. 
Although we are not presenting any expansion or change in the scope of the planning request in
this appeal we felt we needed to provide more background and context to our decision to
investigate a renewal energy solution. We also think a fuller verbal and visual description of the
property may help to put the it's future energy needs in balance with its historical nature. These
are detailed in the first half of the attached statement followed by our comments on the refusal
reasons after that. 
List of documents and evidence 
Please provide a list of all supporting documents, materials and evidence which you wish to
submit with your notice of review and intend to rely on in support of your review. 
24_01954_FLL_Appeal_statement.docx
Pic_1_view_from _South_approach.jpg
Pic_2_view_from East_approach.jpg
Pic_3_view_from_west_approach.jpg
Pic_4_view from_in_garden_west.jpg
Pic_5_Neighbours_Solar_panels_to_NW.jpg
Other documents such as elavation plans and location plans can be found with the original
application. I have been advised by P&K council planning that I will not need to resubmit these. 
Note. The planning authority will make a copy of the notice of review, the review documents and
any notice of the procedure of the review available for inspection at an office of the planning

Page 6

Page 4 of 4
authority until such time as the review is determined.  It may also be available on the planning
authority website. 
Checklist 
Please mark the appropriate boxes to confirm you have provided all supporting documents and
evidence relevant to your review: 
Full completion of all parts of this form 
Statement of your reasons for requiring a review 
All documents, materials and evidence which you intend to rely on (e.g. plans and drawings
or other documents) which are now the subject of this review. 
Note. Where the review relates to a further application e.g. renewal of planning permission or
modification, variation or removal of a planning condition or where it relates to an application for
approval of matters specified in conditions, it is advisable to provide the application reference
number, approved plans and decision notice from that earlier consent. 
Declaration 
I the applicant hereby serve notice on the planning authority to review the application as
set out on this form and in the supporting documents. 
Signed: Graham Ritchie Date: 17/04/2025

Page 7

Appeal Statement
The following statement is an appeal to review the refusal of our planning application to Perth and
Kinross Council Planning Department, reference number 24/01954/FLL (and associated number
24/01955/LBC) entitled “Installation of solar panels and cabinet South Lodge Ballindean Inchture
Perth PH14 9SF”.
Property description:
South Lodge is a single storey gate lodge building at the South entrance to the former Ballindean
House estate. It was originally built around 1832 in stone with a Scots slate roof. It more recently has
had a substantial ‘in-keeping’ modern brick and harled extension with Welsh Slate roof added to the
rear or the building in 1985. This more than doubled the size of the property however none of this
extension is visible when viewing the property from the original front elevation. A conservatory of
modern white PVC construction was added to this extension in 1990. Both the extension and the
conservatory have been through planning approval with the latter available to view online with
reference number 90/01342/FUL.
The building was B-Listed in 1971 as “Ballindean South Lodge and Gates” reference LB11761. This
listing was made before the above additions but by default covers the new extension to the building
in the listing. This was confirmed by Historic Environment Scotland.
My partner and I have owned the building since 2017, although it has been in the Ritchie family since
1989 when my parents retired there. The family have always lived locally having been farmers in the
Carse of Gowrie for many generations. It is our intention to look after and preserve the property as
much as we possibly can. 
Having informally spoken the planning department and looking at online guidance we realised we
would need planning permission and listed building consent for the solar panels so we have followed
the required planning application process to date. 
Background to the reasons for a Solar Panel system:
The main heating and hot water system for the property is currently a gas combi boiler for central
heating and hot water, fuelled by LPG gas which is delivered and stored in an on-site LPG gas tank.
The central heating system dates back to the 1990’s with narrow microbore piping and with the
current boiler being a replacement from back in 2012. This whole system is nearing end of life and
has been subject to much recent repair and we are told we will potentially require at a new LPG gas
boiler in the coming 1 to 3 years.
We want to move away from gas fuel for a number of reasons:
• Firstly, to follow Scottish and UK government advice to move away from fossil fuels to a
cleaner and more sustainable energy solution. 
• The cost of delivered LPG gas is expensive and has almost doubled in price from 39p to 75p
per Litre in the last 5 years so we now ration its use where we can.
• The cost of maintaining the boiler and heating system is increasing with the age of the
system.
• There is also the presence of an on-site LPG gas tank requiring protected space around it and
heavy delivery tankers having to reverse onto the property to get near to the tank.

Page 8

When looking at the options for replacing the current LPG heating system within a limited budget we
started in 2019 to invest in infrared heating units in several rooms in order to gain the following
advantages:
• Firstly, moving away from fossil fuels as mentioned above.
• To use mains electricity from the national grid that should be utilising renewable resources
more and more into the future.
• At the time we had an expectation of longer term stable and potentially cheaper electricity
prices with national renewables. This has not been the case so far.
• Low unit, installation and maintenance cost of infrared heaters.
• Infrared heaters are ceiling mounted and therefore we can eventually free up space from
decommissioned conventional radiators.
• Perceived health benefits from infrared heat together with reduced dust circulation due to
the non-convectional heating process.
However, with electricity unit prices having more than doubling since 2021, the cost of mains
electricity solely from the grid is now very expensive and we turned to looking at our own long term
renewable domestic solution hence the solar panel and storage battery application. This kind of
system would have the following benefits and characteristics:
• More affordable installation compared to other alternatives (see below*) 
• Minimal installation consisting of mainly internal cabling in the attic and several external roof
mounting points without altering any structural components of the building.
• The installation would be easily reversable in years to come as no structural changes will
have been made. The only external work after solar panel removal would be some slate
reinstatement.
• We would have the ability to generate and store our own electricity to power our electric
heaters and other electrical needs.
• We would not be so exposed to changes in electricity prices, for example our January 2021
bill was £73 whereas in January 2025 it was £147.
• We would feed back into the national grid any surplus capacity using the government’s Smart
Export Guarantee therefore “providing the local grid with more clean, green energy, as the
UK bids to become a net zero emissions economy”.
• We could also benefit from new technology to provide direct hot water using a separate
battery storage electric boiler for that purpose.
• Potential for renewable electric car charging in the future when we may eventually get an
electric car.
*We had considered other heating options but the following issues made them less cost effective
and desirable for us.
For example, air source heating would not just require the external air source heat pump but the
complete renewal of the pipe system and the replacement considerably larger radiators. Also, the
routing of larger pipes throughout and between the old part of the building and the extension part
would require substantial upheaval and some concrete removal just below floor level. Although the
cost of installation may be comparable to solar but the invasive nature of the installation throughout
the old and new parts of the building made us uncomfortable as did the prospect of relying solely on
mains electricity.

Page 9

Electric storage heaters were also considered but we feel we have already invested heavily in infrared
electric heaters for heating purposes. Plus, the storage heaters have a larger radiator footprint like
the air source heating radiators mentioned above.
The fallback is to replace the LPG boiler and continue to use LPG tank gas for the foreseeable but we
want to avoid this if we can.
It should be noted also that the company we engaged to plan a cost-efficient solar panel installation
had stated during the on-site survey that a roof mounted solution was the only suitable efficient
option for us. They also informed us that even if there were a suitable ground site, which they could
not readily identify on the property, then there would be unknown cost of ground mounting the
solar panels and the required earthworks and underground cabling. This may be cost prohibitive for
us.
We would also like to point out that we are a couple just a few years away from our retirement ages
and have a limited ‘working’ budget just now and will have less of a ‘retirement’ budget in the
future. So, we are currently trying to plan a sustainable energy strategy for the house and our future. 
Our Comments on the Refusal reasons
There appear to be 4 reasons stated in the 24/01954/FLL main application and a single reason in the
associated 24/01955/LBC application which duplicates the second reason in the main application. 
Reasons 1 and 2 - Detriment to the traditional character of the building:
Using the main 24/01954/FLL application the first two 2 reasons for refusal were for the similar
reason that the Solar panels on the roof would be detrimental to the traditional character of the
application property. The first reason appears not to do with the fact that the building is listed
whereas the second reason directly references it as a category B listing building. Given that we are
aware that the planning permission application for a solar panel installation would not have been
required for a non-listed building then we are struggling to understand why there is a first reason at
all?
The second reason is due to the fact that this is a category B listing building and we do appreciate the
nature of such a building and the need to protect its original features and character. Both my partner
and myself are currently working or have worked in the government heritage sector and are more
than sympathetic to this point. However, we hope to show by making the following points that there
is a balance to be struck in this case and that this installation can be progressed without adversely
affecting the traditional character or indeed the fabric of any part the building, original or otherwise. 
• As shown on the application plans the site of the panels would be on the modern extension
part of the building and would not affect any part of the original lodge and therefore the
listing description would remain accurate: Single-storey harled with stone dressings; porch
and bay window features; upper sashes have arched tops with radial glazing bars; low
pitched roof octagonal shafted chimneys; tapered gatepiers.
• On approach via the public road from Inchture, the solar panels would not be visible from
the front south facing aspect of the original listed property (see Pic_1_view_from
_South_approach.jpg).  Visitors using the driveway to the Ballindean House estate to the east

Page 10

of the property can only see the south and east elevations of the lodge so again the solar
panels would not be visible (see Pic_2_view_from East_approach.jpg). 
• The solar panels would only be partially visible from the public road to the west, depending
on the time of year and vegetation (see Pic_3_view_from_west_approach.jpg).
• The installation of mounting points on the slate roof would be non-structural and completely
reversable in the future, possibly at a time of decommissioning or replacing of the system.
• The low profile and dark colouring of the panels gives minimal contrast between the
installation and the slate roof.
• There is an existing modern white PVC conservatory already attached to the external wall of
the extension. It would to us seem strange to conclude that dark low profile, low contrast
solar panels on the roof would be more of a detriment to the traditional character of the
building than this previously approved conservatory. (see Pic_4_view
from_in_garden_west.jpg)
• There are two other residential buildings approximately 350 metres North West of this
property which, although not listed themselves, have been built to be in keeping with their
adjacent B-listed walled gardens (LB13463 and LB13480). These properties have low profile
solar panel installations that are also visible from the public road. (see
Pic_5_Neighbours_Solar_panels_to_NW.jpg) 
Reasons 3 - Lack of a bat survey:
Our original application was compiled by our architect as we were advised by Perth and Kinross
planning that accurate professional plans would be required. We also engaged the architect act as
agent to submit the application as we had no experience of planning and applications. However, the
necessity for bat welfare was not relayed to us although I can now see that it is clearly stated in the
pre-application’s guidance notes.
Therefore, in hindsight and given that if a bat survey is required, we would be happy to commission
one. We are already aware that we have had bat activity around the house in the summer months in
recent years. 
However, we would respectfully ask if the bat survey itself could be a required condition for an
otherwise potentially successful appeal. We ask this as the cost of a bat survey appears to range from
hundreds of pounds to several thousand pounds depending on requirements. 
Reason 4 – Summary of the above refusal reasons:
The 4th Reason for Refusal appears to be a combination of the above reasons but with 2 different
policy references. I assume these references refer to the previous historic and biodiversity reasons in
a ‘combined’ sense, hence the sole need for this 4th reason. 
In summary:
We would hope that these above points, in conjunction with our domestic and national green energy
aspirations, would give us hope that in this case a compromise could be reached to allow us to
proceed with our installation.

Page 11

I would like to add that we were disappointed that no actual visit was made to the property as part
of the planning decision as we believe that submitted maps, plans and any online resources can only
go so far as to understanding the nature of this property in its environment. We do understand and
respect that it is a building of historic significance but we also think it now has modern aspects and
future sustainability needs that we want to address and maintain. This is so that we can be part of
the preservation of the building to ensure that ourselves and the generations to come can enjoy both
the benefits of the building’s history and also its environmentally responsible future.
As mentioned previously, and now in hindsight, it may be that we should have been more involved in
the initial planning application especially if any of the above contextual information would have
made the application clearer to planners when given more of the background detail. However, as our
planning application knowledge was limited, we felt at the time that an agent would be able to
provide the level of detail, beyond plans and maps, that would be required.
Thank you for your consideration.

Page 12

Picture 1 – View from south approach

Page 13

Picture 2 – View from east approach

Page 14

Picture 3 - View from west approach

Page 15

Picture 4 - View from in garden west

Page 16

Picture 5 – Neighbours solar panels to NW