Page 1
4(ii)(b) LRB-2026-12 LRB-2026-12 - Review of Condition 4 of planning permission 25/01754/FLL (Erection of dwellinghouse and garage at land 40 metres south of 104 Willoughby Street, Lintibert Road, Muthill, Crieff, PH5 2AE) Planning Decision Notice Report of Handling Reference Documents
Page 2
No embedded text on this page.
Page 3
Mr John Kane c/o Paper Igloo Ltd Mhairi Grant Ostro Fintry Road Kippen FK8 3HL 2 High Street Perth PH1 5PH Date of Notice: 25th February 2026 Town and Country Planning (Scotland) Acts (as amended) Planning, etc. (Scotland) Act 2006 (as amended) Application Number 25/01754/FLL I am directed by the Planning Authority under the Town and Country Planning (Scotland) Acts currently in force, to grant your application registered on 8th December 2025 for planning permission for Erection of dwellinghouse and garage at Land 40 Metres South Of 104 Willoughby Street Lintibert Road Muthill Crieff PH5 2AE subject to any undernoted conditions. Kristian Smith Development Management & Building Standards Service Manager Conditions 1 This planning permission will last only for three years from the date of this decision notice, unless the development has been lawfully started within that period. Reason - This is a Planning Permission in terms of Section 58 of the Town and Country Planning (Scotland) Act 1997, as amended by Section 32 of the Planning (Scotland) Act 2019.
Page 4
Page 2 of 7 2 Prior to the commencement of the development hereby approved, a detailed landscaping and planting scheme for the site shall be submitted for the written agreement of the Council as Planning Authority. The scheme shall include details of the height and slopes of any mounding or recontouring of the site, full details of all hard landscaping proposals including materials and installation methods and, species, height, size and density of trees and shrubs to be planted. The scheme as subsequently approved shall be carried out and completed within the first available planting season (October to March) after the completion or bringing into use of the development, whichever is the earlier, and the date of Practical Completion of the landscaping scheme shall be supplied in writing to the Council as Planning Authority within 7 days of that date. The scheme as agreed and implemented shall thereafter be maintained to the satisfaction of the Council as Planning Authority. Reason - In the interests of visual amenity and to ensure the satisfactory implementation of the proposed planting scheme. 3 Prior to the completion or occupation of the building hereby approved, whichever is the earlier, two bat and two bird nesting boxes shall be provided on the completed building. All the boxes shall be installed and sited in accordance with the recommendations and guidance offered by the Scottish Wildlife Trust. After installation, all the boxes shall be retained in a usable condition. Reason - In the interests of protecting environmental quality and of biodiversity. 4 Prior to occupation of the development hereby approved, pedestrian visibility splays of 2.4mx2.4m shall be formed and no obstruction greater than 0.6m in height shall be permitted within the visibility splay envelope. The proposed 1.8-metre-high fence on the northern boundary shall be positioned and maintained so that it does not obstruct the required visibility splay and shall be a maximum height of 0.6 metres where it falls within the splay envelope. Thereafter, the pedestrian visibility splays should be maintained for the lifetime of the development. Reason - in the interest of road safety. 5 Prior to the occupation of the development hereby approved, the 1st floor window on the west elevation, shall be installed with obscure glazing and this will remain in place in perpetuity. Reason-In order to minimise any overlooking onto neighbouring properties Justification The proposal is in accordance with the Development Plan and there are no material reasons which justify departing from the Development Plan.
Page 5
Page 3 of 7 Informatives 1 Under section 27A of the Town and Country Planning (Scotland) Act 1997 (as amended) the person undertaking the development is required to give the planning authority prior written notification of the date on which it is intended to commence the development. A failure to comply with this statutory requirement would constitute a breach of planning control under section 123(1) of that Act, which may result in enforcement action being taken. Please use the form attached herewith. 2 As soon as practicable after the development is complete, the person who completes the development is obliged by section 27B of the Town and Country Planning (Scotland) Act 1997 (as amended) to give the planning authority written notice of that position. Please use the form attached herewith. 3 No work shall be commenced until an application for building warrant has been submitted and approved. 4 The vehicle access must meet the standards of the Road Authority. The applicant has indicated that the vehicular access has already been formed as per planning consent 24/01628/FLL (VA Consent Reference: VA10307). As this is a separate procedure under Section 56 of the Roads (Scotland) Act 1984, the applicant should provide confirmation to the Planning Authority once Roads Network Management have formally signed off VA10307. 5 The presence of protected species, and the extent to which they could be affected by the proposed development, should be established before works commence. Should protected species be identified within the site the developer should ensure that all appropriate measures required to comply with the relevant legislation are carried out. 6 Existing trees and vegetation may contain nesting birds between 1st March and 31st August inclusive. The applicant is reminded that, under the Wildlife and Countryside Act 1981, as amended (section 1), it is an offence to remove, damage or destroy the nest of any wild bird while that nest is in use or being built. Planning permission for a development does not provide a defence against prosecution under this Act. 7 The Air Source Heat Pump shall be certificated in accordance with Microgeneration Certification Scheme 007 and installed by an installation company certificated in accordance with Microgeneration Installation Standard 3005 and in compliance with the calculation procedure contained in Table 2 of Microgeneration Certification Scheme Planning Standards (MCS 020), confirming that the permitted development noise limit of 42 dB LAeq, 5 mins will be met. In addition, the Air Source Heat Pump shall be so enclosed, attenuated and/or maintained such that any noise therefrom shall not exceed Noise Rating 35 between 0700 and 2300 hours daily, or Noise Rating 25 between 2300 and 0700 hours daily, within any neighbouring residential property, with all windows slightly open, when measured and/ or calculated and plotted on a rating curve chart. 8 The applicant is advised that Perth and Kinross Council have a charging scheme for recycling and waste bins for new build properties and newly created dwellings. Further information can be found at: https://www.pkc.gov.uk/binrequests
Page 6
Page 4 of 7 Accordance with Approved Plans and Conditions You are reminded that development must progress in accordance with the plans approved under, and any conditions attached to, this permission. You must not deviate from this permission without consent from the Planning Authority (irrespective of any changes that may separately be requested at the Building Warrant stage or by any other Statutory Authority). Any pre-commencement conditions (those requiring certain works, submissions etc. prior to starting the approved development) must be complied with in full prior to work starting on site. Failure to adhere to this permission and meet the requirements of all conditions may invalidate your permission or result in formal enforcement action. The plans and documents which form part of this decision are listed below and are displayed as ‘approved’ on Perth and Kinross Council’s website at www.pkc.gov.uk “Online Planning Applications” page Plan and Document Reference 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 17 Should you require further information regarding the decision please contact either developmentmanagement@pkc.gov.uk or call 01738 475300, quoting the above planning reference number, and you’ll be directed to the most appropriate person.
Page 7
REPORT OF HANDLING DELEGATED REPORT Ref No 25/01754/FLL Ward No P7- Strathallan Due Determination Date 7th February 2026 Extended to 27th February 2026 Draft Report Date 23rd February 2026 Report Issued by Adam Cairns Date 24th February 2026 PROPOSAL: Erection dwellinghouse and garage LOCATION: Land 40 Metres South Of 104 Willoughby Street Lintibert Road Muthill Crieff PH5 2AE SUMMARY: This report recommends approval of the application as the development is considered to comply with the relevant provisions of the Development Plan and there are no material considerations apparent which outweigh the Development Plan. BACKGROUND AND DESCRIPTION OF PROPOSAL The proposal is for an erection of a dwellinghouse and garage on land 40 metres south of 104 Willoughby Street (“Highfield”). The site was previously utilised as domestic garden ground for 104 Willoughby Street. The site appears to be derelict and there are a number of unused sheds, a greenhouse and an above ground gas tank. The site was recently subject to previous application for the erection of a dwellinghouse (24/01628/FLL), which was approved in January 2025. The proposal site is located within Muthill Conservation Area. SITE HISTORY 93/01488/FUL Alterations to form at sun lounge/conservatory and porch at 24 Nov 1993 Application Approved
Page 8
94/01835/FUL Change of use from part of garden to motor sales at 23 Jan 1995 Application Refused 07/01600/FUL Proposed construction of 5 holiday apartments and a garage with workshop and woodstore 06 August 2007 Withdrawn 07/01816/FUL Erection of 5 no holiday rental apartments, garage with workshop, woodstore and conservatory and formation of new vehicular accesses 20 Nov 2007 Withdrawn 09/00076/FUL Erection of dwellinghouse 07 April 2009 Application Refused 09/00225/FUL Erection of a garage, conservatory and fence 30 March 2009 Application Refused 09/02148/FLL Erection of a garage, conservatory and hard landscaping 26 February 2010 Application Approved 12/00622/FLL Variation of consent - (09/02148/FLL) - to alter roof finish on garage 04 June 2012 Application Approved 12/01264/FLL Erection of a retaining wall (in retrospect) within rear garden 05 September 2012 Withdrawn 12/01638/FLL Erection of a retaining wall (in retrospect) 31 October 2012 Application Approved 19/01442/TW Tree Works 19 September 2019 Application Approved 22/00069/LAW Installation of air source heat pump system (proposed) 22 March 2022 Application Refused 24/01399/FLL Alteration to garage, installation of air source heat pumps and erection of fencing 14 Nov 2024 Application Approved 24/01628/FLL Erection of a dwellinghouse 29 January 2025 Application Approved 25/00260/TW Tree Work 01 April 2025 Application Approved PRE-APPLICATION CONSULTATION Pre application Reference: No formal pre-application consultation was undertaken.
Page 9
DEVELOPMENT PLAN The Development Plan for the area comprises National Planning Framework 4 (NPF4) and the Perth and Kinross Local Development Plan 2 (2019) (LDP2). National Planning Framework 4 The National Planning Framework 4 (NPF4) is the Scottish Government’s long-term spatial strategy with a comprehensive set of national planning policies. This strategy sets out how to improve people’s lives by making sustainable, liveable and productive spaces. NPF4 was adopted on 13 February 2023. NPF4 has an increased status over previous NPFs and comprises part of the statutory development plan. The Council’s assessment of this application has considered the following policies of NPF4: Policy 1: Tackling the Climate and Nature Crises Policy 3: Biodiversity Policy 7: Historic Assets and Places Policy 9: Brownfield, Vacant and Derelict Land and Empty Buildings Policy 13: Sustainable Transport Policy 14: Design, Quality and Place Policy 16: Quality Homes Policy 22: Flood Risk and Water Management Perth and Kinross Local Development Plan 2 – Adopted November 2019 The Local Development Plan 2 (LDP2) is the most recent statement of Council policy and is augmented by Supplementary Guidance. The principal policies are: Policy 1A: Placemaking Policy 1B: Placemaking
Page 10
Policy 5: Infrastructure Contributions Policy 6: Settlement Boundaries Policy 17: Residential Areas Policy 28A: Conservation Areas New Development Policy 32: Embedding Low & Zero Carbon Generating Technologies in New Development Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and Development Policy 41: Biodiversity Policy 53B: Water Environment and Drainage: Foul Drainage Policy 53C: Water Environment and Drainage: Surface Water Drainage Policy 60B: Transport Standards and Accessibility Requirements: New Development Proposals Statutory Supplementary Guidance Supplementary Guidance - Developer Contributions & Affordable Housing (adopted in 2020) Supplementary Guidance - Placemaking (adopted in 2020) OTHER MATERIAL CONSIDERATIONS Non-Statutory Guidance Planning Guidance - Planning & Biodiversity Conservation areas National Guidance The Scottish Government expresses its planning policies through, Planning Advice Notes, Creating Places, Designing Streets, National Roads Development Guide and a series of Circulars.
Page 11
Creating Places 2013 Creating Places is the Scottish Government’s policy statement on architecture and place. It sets out the comprehensive value good design can deliver. It notes that successful places can unlock opportunities, build vibrant communities and contribute to a flourishing economy and set out actions that can achieve positive changes in our places. National Roads Development Guide 2014 This document supports Designing Streets and expands on its principles and is considered to be the technical advice that should be followed in designing and approving of all streets including parking provision. Local Place Plans Local Place Plans are community-led plans setting out proposals for the development and use of land and set out a community’s aspirations for its future development. There are no Local Place Plans currently adopted for the area. CONSULTATION RESPONSES Scottish Water: No objection. Transportation and Development: No objection subject to conditions relating to vehicular access and pedestrian visibility splays. Please note that the condition relating to the vehicular access was deemed more appropriate as an informative. Environmental Health (Contaminated Land): No objection. Initially requested further information regarding justification of sampling regime within Phase 2 Geotechnical Report and updating the report with a reference to latest sampling guidance. Development Contributions Officer: No contribution required.
Page 12
REPRESENTATIONS One objection was received. The main issues raised were: Loss of daylight or sunlight Additional Statements Received: Screening Opinion Not Required Environmental Impact Assessment (EIA): Environmental Report Not Required/Not applicable Appropriate Assessment under Habitats Regulations AA Not Required Design Statement or Design and Access Statement Not Required Report on Impact or Potential Impact eg Flood Risk Assessment Not Required APPRAISAL Sections 25 and 37 (2) of the Town and Country Planning (Scotland) Act 1997 require that planning decisions be made in accordance with the development plan unless material considerations indicate otherwise. The Development Plan comprises NPF4 and the Perth and Kinross Local Development Plan 2019. The relevant policy considerations are outlined in the policy section above and are considered in more detail below. In terms of other material considerations, involving considerations of the Council’s other approved policies and supplementary guidance, these are discussed below only where relevant. In this instance, section 14(2) of the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997 places a duty on planning authorities in determining such an application as this to have special regard to the desirability of preserving the building or its setting or any features of special architectural or historic interest which it possesses. Section 64(1) of the Planning (Listed Buildings and Conservation Areas) (Scotland) Act 1997 is relevant and requires planning authorities to pay special attention to the desirability of preserving or enhancing the character or appearance of the designated conservation area. The determining issues in this case are whether; the proposal complies with development plan policy; or if there are any other material considerations which justify a departure from policy.
Page 13
Principle NPF4 Policy 16 (Quality Homes) aims to facilitate the delivery of high-quality homes in the right locations. Other relevant policies include LDP2 Policy 17 (Residential Areas), LDP Policies 1A and 1B (Placemaking) and NPF4 Policy 14 (Design, Quality and Place) which seeks to deliver well designed development. LDP2 Policy 17 identifies areas of residential uses where new development will only be acceptable where the use proposed is compatible with existing residential uses and will not adversely affect the character or amenity of the existing area. Additionally, NPF4 Policy 9 (Brownfield, Vacant and Derelict Land and Empty Buildings) states that development proposals that will result in the sustainable reuse of brownfield land including vacant and derelict land and buildings, whether permanent or temporary, will be supported. In determining whether the reuse is sustainable, the biodiversity value of brownfield land which has naturalised should be taken into account. The applicant is seeking to establish the erection of a dwellinghouse within an area where residential development is generally considered to be acceptable. The principle of development has already been established by the 2025 permission. It is considered that the principle of residential development is in accordance with the identified LPD2 and NPF4 policies as the use as residential would be compatible with neighbouring land uses in an area which is predominantly residential and would result in an appropriate reuse of former garden ground which is currently derelict and underutilised. Design and Layout/Conservation Considerations The proposed three-bedroom dwellinghouse is formed of 1.75 storeys and is gable- ended in form. The building is contemporary, utilising white render, natural slate, larch timber cladding and aluminium- clad windows and doors. A double garage and two car parking spaces are proposed at the northern section of the site. In terms of zero- carbon technologies, the dwellinghouse will be built to Passivhaus standard and will utilise south-facing photovoltaic panels, battery storage, an EV charging point, mechanical ventilation system with heat recovery (MVHR) and an air source heat pump. The plot is situated on the edge of the Muthill Conservation Area. The proposed north and east elevations fronting both Lintibert Terrace & Lintibert Road are relatively restrained in terms of façade articulation and massing, representing a dilution of the previously approved scheme, which was more mainstream and conventional in its architectural approach. The current proposal presents a simplified and less visually dominant form, resulting in a reduced overall presence within the streetscape, which despite being characterised by range of building typologies, is fairly uniform in appearance. The site’s existing condition, comprising of dense and unmanaged
Page 14
vegetation, offers an opportunity of visual improvement for this corner plot location on the periphery of the conservation area. The proposed north elevation is more articulated, incorporating slate roofed wall-head dormers, large ground floor glazed openings and timber larch cladding, which offers a contrast to its dominant white render finish and harmonises with the stone built, slate-roofed property at 104 Willoughby Street to the north. Overall, the proposal is considered to be acceptable in terms of layout and character and therefore complies with policies LDP2 Policy 1A and B and NPF4 Policy 14. The proposals are also considered appropriate and sympathetic to the appearance, character and setting of the Muthill Conservation Area. Residential Amenity Loss of Daylight An objector who occupies the neighbouring property at 2 Lintibert Terrace has raised concerns that the proposed development will lead to a loss of natural daylight and sunlight to their conservatory. There is an approximate 4.4-metre separation distance between the proposed dwellinghouse and the conservatory at 2 Lintibert Terrace, located to the west. While it is acknowledged that the proposal will result in some reduction of daylight to the conservatory, and that the site rises approximately 3.5m from north to south, the submitted elevational and section drawings demonstrate that retaining works are proposed at the southern end to avoid the dwelling sitting excessively high relative to neighbouring properties. Additionally, daylight and sunlight levels to the neighbouring conservatory is already constrained by the presence of a tall Cypress Leylandi boundary hedge along the site’s southern boundary. Furthermore, the elevational profile features a single gable with a ridge height of approximately 7.6 metres at its apex. Either side of this, the roofline slopes down to substantially lower eaves, resulting in reduced wall heights and thereby limiting an overbearing impact. It is also relevant to note that the proposed ridge height sits approximately 470mm below that of 2 Lintibert Terrace, further reducing the potential of an over-dominant relationship. While the tallest part of the gable may restrict daylight at certain times of day, this effect is confined to a limited portion of the elevation and will be intermittent due to the pitched roof profile. Moreover, when compared with the 2025 permission, the current proposal is approximately the same height at its apex. However, any marginal difference in height is offset by the improved spatial relationship with the neighbouring property, as the separation distance has increased from approximately 3.8 metres to 4.4 metres.
Page 15
Taking account of the existing site constraints, the design established by the previous approval, and the proposed retaining works and roof profile, the proposal is unlikely to result in a materially greater loss of daylight than is currently experienced. Overlooking/Loss of Privacy A single window is proposed on the west elevation, which will be utilised as an escape route from the 1st floor bedroom. It is proposed that this window is fitted with obscure glazing to prevent overlooking of the adjacent garden. All the remaining windows achieve a separation distance of more than 18 metres from neighbouring windows, with exception of those on the east elevation, which are approximately 15.5 metres away. However, overlooking is normal and expected within the context of a public road. Roads and Access A new vehicle access is proposed on Lintibert Road. The applicant has reported that the vehicle access has already been formed as per prior planning consent 24/01628/FLL (VA consent reference: 10370). The proposed 1.8m high fence proposed to be erected to the north boundary should not obstruct the pedestrian visibility splay onto the footway. As such, a condition has been recommended in relation to pedestrian visibility splays and controlling the height of the proposed fence at the northern boundary. Drainage and Flooding The site is not at risk from surface water or river flooding, as indicated by SEPA flood maps. A soakaway is proposed within the rear garden ground to manage any surface run-off. Natural Heritage and Biodiversity NPF4 Policy 3 (Biodiversity) states proposals for local development will include appropriate measures to conserve, restore and enhance biodiversity. LDP2 Policy 40B (Trees, Woodland and Development) requires a tree survey to accompany proposals where there are existing trees which may be affected. It is proposed that an overgrown Cypress Leylandii hedge which predominately lies at the southern edge of the site is to be removed. A tree works application (25/01220/TW) to remove the hedge was approved in September 2025. New tree and hedge planting is proposed within the garden ground. A condition has been imposed below in relation to the submission of a detailed landscaping and planting scheme for the site. Compensatory planting will be secured through this condition and shall contribute
Page 16
towards biodiversity enhancement. Additionally, a condition has also been recommended below relating to the installation of bat and bird boxes on the completed dwelling. Developer Contributions Affordable Housing With reference to the above planning application the Council’s Affordable Housing Policy requires that 25% of the total number of houses, above a threshold of 5 units, for which planning consent is being sought is to be in the form of affordable housing. The proposed development is under the threshold and therefore an Affordable Housing developer contribution is not required. Primary Education With reference to the above planning application the Council Developer Contributions Supplementary Guidance requires a financial contribution towards increased primary school capacity in areas where a primary school capacity constraint has been identified. A capacity constraint is defined as where a primary school is operating at over 80% and is likely to be operating following completion of the proposed development, extant planning permissions and Local Development Plan allocations, at or above 100% of total capacity. This proposal is within the catchment of Muthill Primary School. Education & Children’s Services have no capacity concerns in this catchment area at this time. A Primary Education developer contribution is therefore not required. Economic Impact The economic impact of the proposal is likely to be minimal and limited to the construction phase of the development. VARIATION OF APPLICATION UNDER SECTION 32A This application was not varied prior to determination, in accordance with the terms of section 32A of the Town and Country Planning (Scotland) Act 1997, as amended.
Page 17
PLANNING OBLIGATIONS AND LEGAL AGREEMENTS None required. DIRECTION BY SCOTTISH MINISTERS None applicable to this proposal. CONCLUSION AND REASONS FOR DECISION To conclude, the application must be determined in accordance with the Development Plan unless material considerations indicate otherwise. In this respect, the proposal is considered to comply with NPF4, and the adopted Local Development Plan 2 (2019). Account has been taken of the relevant material considerations, and none has been found that would justify overriding the Development Plan. Accordingly, the proposal is approved subject to the following conditions. Conditions and Reasons 1. This planning permission will last only for three years from the date of this decision notice, unless the development has been started within that period. Reason- This is a Planning Permission in terms of Section 58 of the Town and Country Planning (Scotland) Act 1997, as amended by Section 32 of the Planning (Scotland) Act 2019. 2. Prior to the commencement of the development hereby approved, a detailed landscaping and planting scheme for the site shall be submitted for the written agreement of the Council as Planning Authority. The scheme shall include details of the height and slopes of any mounding or recontouring of the site, full details of all hard landscaping proposals including materials and installation methods and, species, height, size and density of trees and shrubs to be planted. The scheme as subsequently approved shall be carried out and completed within the first available planting season (October to March) after the completion or bringing into use of the development, whichever is the earlier, and the date of Practical Completion of the landscaping scheme shall be supplied in writing to the Council as Planning Authority within 7 days of that date. The scheme as agreed and implemented shall thereafter be maintained to the satisfaction of the Council as Planning Authority.
Page 18
Reason - In the interests of visual amenity and to ensure the satisfactory implementation of the proposed planting scheme. 3. Prior to the completion or occupation of the building hereby approved, whichever is the earlier, two bat and two bird nesting boxes shall be provided on the completed building. All the boxes shall be installed and sited in accordance with the recommendations and guidance offered by the Scottish Wildlife Trust. After installation, all the boxes shall be retained in a usable condition. Reason - In the interests of protecting environmental quality and of biodiversity. 4. Prior to occupation of the development hereby approved, pedestrian visibility splays of 2.4mx2.4m shall be formed and no obstruction greater than 0.6m in height shall be permitted within the visibility splay envelope. The proposed 1.8- metre-high fence on the northern boundary shall be positioned and maintained so that it does not obstruct the required visibility splay and shall be a maximum height of 0.6 metres where it falls within the splay envelope. Thereafter, the pedestrian visibility splays should be maintained for the lifetime of the development. Reason – in the interest of road safety. 5. Prior to the occupation of the development hereby approved, the 1st floor window on the west elevation, shall be installed with obscure glazing and this will remain in place in perpetuity. Reason-In order to minimise any overlooking onto neighbouring properties Justification The proposal is in accordance with the Development Plan and there are no material reasons which justify departing from the Development Plan. Informatives 1. Under section 27A of the Town and Country Planning (Scotland) Act 1997 (as amended) the person undertaking the development is required to give the planning authority prior written notification of the date on which it is intended to commence the development. A failure to comply with this statutory requirement would constitute a breach of planning control under section 123(1) of that Act, which may result in enforcement action being taken.
Page 19
2. As soon as practicable after the development is complete, the person who completes the development is obliged by section 27B of the Town and Country Planning (Scotland) Act 1997 (as amended) to give the planning authority written notice of that position. 3. No work shall be commenced until an application for building warrant has been submitted and approved. 4. The vehicle access must meet the standards of the Road Authority. The applicant has indicated that the vehicular access has already been formed as per planning consent 24/01628/FLL (VA Consent Reference: VA10307). As this is a separate procedure under Section 56 of the Roads (Scotland) Act 1984, the applicant should provide confirmation to the Planning Authority once Roads Network Management have formally signed off VA10307. 5. The presence of protected species, and the extent to which they could be affected by the proposed development, should be established before works commence. Should protected species be identified within the site the developer should ensure that all appropriate measures required to comply with the relevant legislation are carried out. 6. Existing trees and vegetation may contain nesting birds between 1st March and 31st August inclusive. The applicant is reminded that, under the Wildlife and Countryside Act 1981, as amended (section 1), it is an offence to remove, damage or destroy the nest of any wild bird while that nest is in use or being built. Planning permission for a development does not provide a defence against prosecution under this Act. 7. The Air Source Heat Pump shall be certificated in accordance with Microgeneration Certification Scheme 007 and installed by an installation company certificated in accordance with Microgeneration Installation Standard 3005 and in compliance with the calculation procedure contained in Table 2 of Microgeneration Certification Scheme Planning Standards (MCS 020), confirming that the permitted development noise limit of 42 dB LAeq, 5 mins will be met. In addition, the Air Source Heat Pump shall be so enclosed, attenuated and/or maintained such that any noise therefrom shall not exceed Noise Rating 35 between 0700 and 2300 hours daily, or Noise Rating 25 between 2300 and 0700 hours daily, within any neighbouring residential property, with all windows slightly open, when measured and/ or calculated and plotted on a rating curve chart. 8. The applicant is advised that Perth and Kinross Council have a charging scheme for recycling and waste bins for new build properties and newly created dwellings. Further information can be found at: https://www.pkc.gov.uk/binrequests
Page 20
Procedural Notes Not Applicable. PLANS AND DOCUMENTS RELATING TO THIS DECISION 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 17
Page 21
Page 1 of 8 Pullar House 35 Kinnoull Street Perth PH1 5GD Tel: 01738 475300 Email: onlineapps@pkc.gov.uk Applications cannot be validated until all the necessary documentation has been submitted and the required fee has been paid. Thank you for completing this application form: ONLINE REFERENCE 100735105-001 The online reference is the unique reference for your online form only. The Planning Authority will allocate an Application Number when your form is validated. Please quote this reference if you need to contact the planning Authority about this application. Type of Application What is this application for? Please select one of the following: * Application for planning permission (including changes of use and surface mineral working). Application for planning permission in principle. Further application, (including renewal of planning permission, modification, variation or removal of a planning condition etc) Application for Approval of Matters specified in conditions. Description of Proposal Please describe the proposal including any change of use: * (Max 500 characters) Is this a temporary permission? * Yes No If a change of use is to be included in the proposal has it already taken place? Yes No (Answer ‘No’ if there is no change of use.) * Has the work already been started and/or completed? * No Yes – Started Yes - Completed Applicant or Agent Details Are you an applicant or an agent? * (An agent is an architect, consultant or someone else acting on behalf of the applicant in connection with this application) Applicant Agent Erection of new build dwelling and garage at land south of Highfield bordering Lintibert Road and Lintibert Terrace.
Page 22
Page 2 of 8 Agent Details Please enter Agent details Company/Organisation: Ref. Number: You must enter a Building Name or Number, or both: * First Name: * Building Name: Last Name: * Building Number: Address 1 Telephone Number: * (Street): * Extension Number: Address 2: Mobile Number: Town/City: * Fax Number: Country: * Postcode: * Email Address: * Is the applicant an individual or an organisation/corporate entity? * Individual Organisation/Corporate entity Applicant Details Please enter Applicant details Title: You must enter a Building Name or Number, or both: * Other Title: Building Name: First Name: * Building Number: Address 1 Last Name: * (Street): * Company/Organisation Address 2: Telephone Number: * Town/City: * Extension Number: Country: * Mobile Number: Postcode: * Fax Number: Email Address: * Paper Igloo Ltd. Mr Mhairi John Grant Kane Fintry Road Ostro FK8 3HL Scotland Kippen
Page 23
Page 3 of 8 Site Address Details Planning Authority: Full postal address of the site (including postcode where available): Address 1: Address 2: Address 3: Address 4: Address 5: Town/City/Settlement: Post Code: Please identify/describe the location of the site or sites Northing Easting Pre-Application Discussion Have you discussed your proposal with the planning authority? * Yes No Site Area Please state the site area: Please state the measurement type used: Hectares (ha) Square Metres (sq.m) Existing Use Please describe the current or most recent use: * (Max 500 characters) Access and Parking Are you proposing a new altered vehicle access to or from a public road? * Yes No If Yes please describe and show on your drawings the position of any existing. Altered or new access points, highlighting the changes you propose to make. You should also show existing footpaths and note if there will be any impact on these. 492.00 Current use: vacant ground. Previously: garden ground to Highfield. Perth and Kinross Council Land south of Highfield bordering Lintibert Road and Lintibert Terrace. 716584 286992
Page 24
Page 4 of 8 Are you proposing any change to public paths, public rights of way or affecting any public right of access? * Yes No If Yes please show on your drawings the position of any affected areas highlighting the changes you propose to make, including arrangements for continuing or alternative public access. How many vehicle parking spaces (garaging and open parking) currently exist on the application Site? How many vehicle parking spaces (garaging and open parking) do you propose on the site (i.e. the Total of existing and any new spaces or a reduced number of spaces)? * Please show on your drawings the position of existing and proposed parking spaces and identify if these are for the use of particular types of vehicles (e.g. parking for disabled people, coaches, HGV vehicles, cycles spaces). Water Supply and Drainage Arrangements Will your proposal require new or altered water supply or drainage arrangements? * Yes No Are you proposing to connect to the public drainage network (eg. to an existing sewer)? * Yes – connecting to public drainage network No – proposing to make private drainage arrangements Not Applicable – only arrangements for water supply required Do your proposals make provision for sustainable drainage of surface water?? * Yes No (e.g. SUDS arrangements) * Note:- Please include details of SUDS arrangements on your plans Selecting ‘No’ to the above question means that you could be in breach of Environmental legislation. Are you proposing to connect to the public water supply network? * Yes No, using a private water supply No connection required If No, using a private water supply, please show on plans the supply and all works needed to provide it (on or off site). Assessment of Flood Risk Is the site within an area of known risk of flooding? * Yes No Don’t Know If the site is within an area of known risk of flooding you may need to submit a Flood Risk Assessment before your application can be determined. You may wish to contact your Planning Authority or SEPA for advice on what information may be required. Do you think your proposal may increase the flood risk elsewhere? * Yes No Don’t Know Trees Are there any trees on or adjacent to the application site? * Yes No If Yes, please mark on your drawings any trees, known protected trees and their canopy spread close to the proposal site and indicate if any are to be cut back or felled. Waste Storage and Collection Do the plans incorporate areas to store and aid the collection of waste (including recycling)? * Yes No 0 2
Page 25
Page 5 of 8 If Yes or No, please provide further details: * (Max 500 characters) Residential Units Including Conversion Does your proposal include new or additional houses and/or flats? * Yes No How many units do you propose in total? * Please provide full details of the number and types of units on the plans. Additional information may be provided in a supporting statement. All Types of Non Housing Development – Proposed New Floorspace Does your proposal alter or create non-residential floorspace? * Yes No Schedule 3 Development Does the proposal involve a form of development listed in Schedule 3 of the Town and Country Yes No Don’t Know Planning (Development Management Procedure (Scotland) Regulations 2013 * If yes, your proposal will additionally have to be advertised in a newspaper circulating in the area of the development. Your planning authority will do this on your behalf but will charge you a fee. Please check the planning authority’s website for advice on the additional fee and add this to your planning fee. If you are unsure whether your proposal involves a form of development listed in Schedule 3, please check the Help Text and Guidance notes before contacting your planning authority. Planning Service Employee/Elected Member Interest Is the applicant, or the applicant’s spouse/partner, either a member of staff within the planning service or an Yes No elected member of the planning authority? * Certificates and Notices CERTIFICATE AND NOTICE UNDER REGULATION 15 – TOWN AND COUNTRY PLANNING (DEVELOPMENT MANAGEMENT PROCEDURE) (SCOTLAND) REGULATION 2013 One Certificate must be completed and submitted along with the application form. This is most usually Certificate A, Form 1, Certificate B, Certificate C or Certificate E. Are you/the applicant the sole owner of ALL the land? * Yes No Is any of the land part of an agricultural holding? * Yes No Are you able to identify and give appropriate notice to ALL the other owners? * Yes No Certificate Required The following Land Ownership Certificate is required to complete this section of the proposal: Certificate B Standard bin store has been shown on plans. 1
Page 26
Page 6 of 8 Land Ownership Certificate Certificate and Notice under Regulation 15 of the Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 I hereby certify that (1) - No person other than myself/the applicant was an owner [Note 4] of any part of the land to which the application relates at the beginning of the period of 21 days ending with the date of the accompanying application; or – (1) - I have/The Applicant has served notice on every person other than myself/the applicant who, at the beginning of the period of 21 days ending with the date of the accompanying application was owner [Note 4] of any part of the land to which the application relates. Name: Address: Date of Service of Notice: * (2) - None of the land to which the application relates constitutes or forms part of an agricultural holding; or – (2) - The land or part of the land to which the application relates constitutes or forms part of an agricultural holding and I have/the applicant has served notice on every person other than myself/himself who, at the beginning of the period of 21 days ending with the date of the accompanying application was an agricultural tenant. These persons are: Name: Address: Date of Service of Notice: * Signed: Mhairi Grant On behalf of: Mr John Kane Date: 03/12/2025 Please tick here to certify this Certificate. * Mr Chris Flower 104, Willoughby St, Muthill, Scotland, PH5 2AE 03/12/2025
Page 27
Page 7 of 8 Checklist – Application for Planning Permission Town and Country Planning (Scotland) Act 1997 The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 Please take a few moments to complete the following checklist in order to ensure that you have provided all the necessary information in support of your application. Failure to submit sufficient information with your application may result in your application being deemed invalid. The planning authority will not start processing your application until it is valid. a) If this is a further application where there is a variation of conditions attached to a previous consent, have you provided a statement to that effect? * Yes No Not applicable to this application b) If this is an application for planning permission or planning permission in principal where there is a crown interest in the land, have you provided a statement to that effect? * Yes No Not applicable to this application c) If this is an application for planning permission, planning permission in principle or a further application and the application is for development belonging to the categories of national or major development (other than one under Section 42 of the planning Act), have you provided a Pre-Application Consultation Report? * Yes No Not applicable to this application Town and Country Planning (Scotland) Act 1997 The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013 d) If this is an application for planning permission and the application relates to development belonging to the categories of national or major developments and you do not benefit from exemption under Regulation 13 of The Town and Country Planning (Development Management Procedure) (Scotland) Regulations 2013, have you provided a Design and Access Statement? * Yes No Not applicable to this application e) If this is an application for planning permission and relates to development belonging to the category of local developments (subject to regulation 13. (2) and (3) of the Development Management Procedure (Scotland) Regulations 2013) have you provided a Design Statement? * Yes No Not applicable to this application f) If your application relates to installation of an antenna to be employed in an electronic communication network, have you provided an ICNIRP Declaration? * Yes No Not applicable to this application g) If this is an application for planning permission, planning permission in principle, an application for approval of matters specified in conditions or an application for mineral development, have you provided any other plans or drawings as necessary: Site Layout Plan or Block plan. Elevations. Floor plans. Cross sections. Roof plan. Master Plan/Framework Plan. Landscape plan. Photographs and/or photomontages. Other. If Other, please specify: * (Max 500 characters) Tree Removal Consent and Dropped Kerb Consents issued by Perth and Kinross Council have both also been provided.
Page 28
Page 8 of 8 Provide copies of the following documents if applicable: A copy of an Environmental Statement. * Yes N/A A Design Statement or Design and Access Statement. * Yes N/A A Flood Risk Assessment. * Yes N/A A Drainage Impact Assessment (including proposals for Sustainable Drainage Systems). * Yes N/A Drainage/SUDS layout. * Yes N/A A Transport Assessment or Travel Plan Yes N/A Contaminated Land Assessment. * Yes N/A Habitat Survey. * Yes N/A A Processing Agreement. * Yes N/A Other Statements (please specify). (Max 500 characters) Declare – For Application to Planning Authority I, the applicant/agent certify that this is an application to the planning authority as described in this form. The accompanying Plans/drawings and additional information are provided as a part of this application. Declaration Name: Ms Mhairi Grant Declaration Date: 03/12/2025 Payment Details Pay Direct Created: 03/12/2025 12:39
Page 29
THIS IS AN EXTRACT FROM THE ORDNANCE SURVEY COPY CROWN COPYRIGHT AND DATABASE RIGHTS (2025). REPRODUCED WITH THE PERMISSION OF THE ORDNANCE SURVEY UNDER END USER LICENSE FOR DATA PRODUCTS 0 20 40 60 80 METRES JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 001 / B LOCATION PLAN 1:1250 @ A3 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: A: LINTIBERT TERRACE A822 WILLOUGHBY STREET QUEENSFERRY ROAD LINTIBERT ROAD LINTIBERT ROAD PLOT NORTH BOUNDARY AMENDED 21.11.25 HIGHFIELD 2 B: SCALE CORRECTED 07.12.25
Page 30
89.50 90.00 90.50 91.00 91.50 92.00 92.50 89.00 88.50 2 1 DALVEY 3 HIGHFIELD LINTIBERT ROAD 0 METRES 4 8 JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 002 / A BLOCK PLAN AS EXISTING 1:200 @ A3 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: A: 2 MARRICH LINTIBERT TERRACE CRAIGPARK SHED PLOT HIGHFIELD GARAGE FENCE OVERGROUND GAS TANK GREENHOUSE SHED FENCE OVERGROWN HEDGE HEDGE OVERGROWN MIXED FLORA (WEED, ETC) TO WEST BOUNDARY APPLE TREE CONSERVATORY FRONT GREEN EXISTING DROPPED KERB FOR HIGHFIELD GRAVEL AREA LAMP POST LAMP POST BT POLE LAYOUT & NOTES AMENDED 24.11.25 B: ADDRESS AMENDED & BOUNDARY WALL 28.11.25
Page 31
92.00 90.75 92.50 89.50 90.00 89.00 88.50 90.796 1000 0 METRES 1 2 JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 040 / C GROUND FLOOR PLAN AS PROPOSED 1:50 @ A1 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: 2500 3000 5000 1144 1583 500 500 LINTIBERT ROAD 5855 600 GROUND FLOOR PLAN AS PROPOSED UP GROUND GRADES UP 1 ENTRANCE DOOR 2 COAT AND BOOTS 3 TIMBER POSTS / SCREEN 4 STAIRCASE 5 ACCESSIBLE SHOWER ROOM 6 STORE UNDER STAIR 7 PLANT 8 REAR DOOR 9 UTILITY ROOM 10 KITCHEN 11 DINING ROOM 12 LIVING ROOM 13 SNUG 14 HIGH UNITS / OVENS 15 SLIDING DOOR 16 DECK 17 BIN STORE 18 RAMP 19 LEVEL ACCESS WITH CANOPY ABOVE 20 CAR PARKING 21 EV CHARGER LOCATION 22 BATTERIES HOUSED WITHIN NEW GARAGE 23 PEDESTRIAN ACCESS GATE FORMED IN STONE WALL 24 PERIMETER HEDGE TO BE TRIMMED BACK TO FORM MANAGED BOUNDARY PLANTING 25 DROPPED KERB TO FORM VEHICULAR ACCESS 26 MVHR 27 HWC 28 NEW HEDGE TO WEST BOUNDARY 29 GABION RETENTION 30 EXISTING STONE WALL RETAINED 31 MASTER BEDROOM 32 BEDROOM 2 33 BEDROOM 3 34 WARDROBE 35 WALK-IN WARDROBE 36 ROOFLIGHT ABOVE 37 DORMER WINDOW 38 FIXED ROOF - WALL WINDOW 39 DRESSING TABLE 40 BATHROOM 41 ENSUITE 42 MVHR DUCT RISER 43 HALL 44 LINE OF 1.5M HEADROOM 45 LINE OF 2.0M HEADROOM 46 NEW SINGLE STOREY GARAGE 47 SOAKAWAY FOR SURFACE WATER (>5M FROM BOUNDARY OR BUILDING) 48 EXISTING 150MM DIA. MAIN SEWER PIPE (AS PER SCOTTISH WATER RECORDS) 49 NEW UNDERGOUND SOIL CONNECTION TO MAINS DRAINAGE IN STREET (LAYOUT INDICATIVE) 1 GROUND FLOOR FOOTPRINT: 87.5M2 2 GROSS GROUND FLOOR INTERNAL AREA: 70.6M2 3 BUILDING TOTAL TFA: 120.5M2 900 3000 1503 1200 1246 1200 HIGHFIELD GARAGE 3555 3490 6600 4600 20 23 24 25 17 29 30 30 28 28 21 22 46 STEP >5M >5M47 >5M >5M 48 GROUND GRADES UP 49 24 IC IC 90.75 90.796 2000 9447 7710 2000 UP 2127 3327 3360 1047 UP 3327 10421 3327 1200 900 1825 4 7 1 2 3 569 10 11 12 13 15 16 18 1926 27 14 8 RWPRWP RWPRWP 200 90.946 FFL: 90.946 RWP RWP BT POLE A B C D A B C D A: LAYOUT & NOTES AMENDED 24.11.25 B: ADDRESS AMENDED 28.11.25 800 MIN 11351 C: BOUNDARY WALL CORRECTED 01.12.25
Page 32
1 ENTRANCE DOOR 2 COAT AND BOOTS 3 TIMBER POSTS / SCREEN 4 STAIRCASE 5 ACCESSIBLE SHOWER ROOM 6 STORE UNDER STAIR 7 PLANT 8 REAR DOOR 9 UTILITY ROOM 10 KITCHEN 11 DINING ROOM 12 LIVING ROOM 13 SNUG 14 HIGH UNITS / OVENS 15 SLIDING DOOR 16 DECK 17 BIN STORE 18 RAMP 19 LEVEL ACCESS WITH CANOPY ABOVE 20 CAR PARKING 21 EV CHARGER LOCATION 22 BATTERIES HOUSED WITHIN NEW GARAGE 23 PEDESTRIAN ACCESS GATE FORMED IN STONE WALL 24 PERIMETER HEDGE TO BE TRIMMED BACK TO FORM MANAGED BOUNDARY PLANTING 25 DROPPED KERB TO FORM VEHICULAR ACCESS 26 MVHR 27 HWC 28 NEW HEDGE TO WEST BOUNDARY 29 GABION RETENTION 30 EXISTING STONE WALL RETAINED 31 MASTER BEDROOM 32 BEDROOM 2 33 BEDROOM 3 34 WARDROBE 35 WALK-IN WARDROBE 36 ROOFLIGHT ABOVE 37 DORMER WINDOW 38 FIXED ROOF - WALL WINDOW 39 DRESSING TABLE 40 BATHROOM 41 ENSUITE 42 MVHR DUCT RISER 43 HALL 44 LINE OF 1.5M HEADROOM 45 LINE OF 2.0M HEADROOM 46 NEW SINGLE STOREY GARAGE 47 SOAKAWAY FOR SURFACE WATER (>5M FROM BOUNDARY OR BUILDING) 48 EXISTING 150MM DIA. MAIN SEWER PIPE (AS PER SCOTTISH WATER RECORDS) 49 NEW UNDERGOUND SOIL CONNECTION TO MAINS DRAINAGE IN STREET 0 METRES 1 2 JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 041 / C FIRST FLOOR PLAN AS PROPOSED 1:50 @ A2 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: A: 1144 7710 FIRST FLOOR PLAN AS PROPOSED 500 A B C D A B C D 16 17 1 GROUND FLOOR FOOTPRINT: 87.5M2 2 GROSS GROUND FLOOR INTERNAL AREA: 70.6M2 3 BUILDING TOTAL TFA: 120.5M2 3327 3327 700 900 700 700 1800 500 622 500 500 2460 1800 3856 3855 18251338 900 32 36 36 33 34 34 34 31 36 363636 36 3737 38 39 40 41 42 43 4444 44 44 4 28 RWPRWP RWPRWP RWP RWP LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25 19 C: BOUNDARY WALL CORRECTED 01.12.25
Page 33
91.50 91.00 88.50 92.00 92.50 89.50 90.00 89.00 2 1 DALVEY 3 HIGHFIELD LINTIBERT ROAD 0 METRES 4 8 JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 005 / B BLOCK PLAN AS PROPOSED 1:200 @ A3 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: A: 2 MARRICH LINTIBERT TERRACE CRAIGPARKREAR GARDEN PARKING GATE FRONT GREEN NEW DROPPED KERB PATH DECK EXISTING DROPPED KERB FOR HIGHFIELD FENCE PERMEABLE SURFACE BINS PROPOSED NEW GARAGE EXISTING HEDGE RETAINED AND TRIMMED BACK FLORA RETAINED AT CORNER OF PLOT NEW TREE PLANTING NEW TREE PLANTING NEW HEDGE TO WEST BOUNDARY FLORA RETAINED AT CORNER OF PLOT CONSERVATORY HIGHFIELD GARAGE GRAVEL AREA LAMP POST LAMP POST 90.750 90.915 1.8M HIGH FENCE ERECTED TO NORTH BOUNDARY BT POLE LAYOUT & NOTES AMENDED 24.11.25 B: LAYOUT ADJUSTED & ADDRESS AMENDED 28.11.25
Page 34
0 2 4 METRES JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 047 / D EAST ELEVATION AS PROPOSED 1:100 @ A3 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: A: BOUNDARY 2000 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD BOUNDARY 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 1 3 2 4 1 NATURAL SLATE ROOF 2 WHITE RENDER 3 LIGHT GREY TRIPLE GLAZED ALU-CLAD WINDOWS AND DOORS 4 DARK GREY ALUMINIUM RAINWATER GOODS 5 DARK GREY RECESSED RENDERED PLINTH 6 DARK GREY QUADRUPLE GLAZED ROOFLIGHTS 7 BORDER HEDGING 8 EXISTING STONE WALL 9 NEW GATE FOR ACCESS FROM LINTIBERT ROAD 10 FIXED ROOF TO WALL WINDOW 11 UNTREATED RAINSCREEN LARCH TIMBER CLADDING 12 MVHR EXHAUST & INTAKE 13 SOIL VENT ON GABLE 14 PV PANELS 15 TIMBER CLAD COVERED ENTRANCE CANOPY 8 7 7 9 1 2 4 7 7 3 3 3 5 LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25 15 C: DASH DOT LINE OF PORCH ADJUSTED 01.12.25 EAST ELEVATION AS PROPOSED - FROM PLOT D: DRAWING TITLES ADDED 07.12.25 EAST ELEVATION AS PROPOSED - FROMM LINTIBERT ROAD
Page 35
BOUNDARY 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD 0 2 4 METRES JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 049 / B WEST ELEVATION AS PROPOSED 1:100 @ A3 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: WEST ELEVATION AS PROPOSED 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 2 1 4 5 7 9 12 13 A: LAYOUT & NOTES AMENDED 24.11.25 800 B: WINDOW OBSCURED & WINDOW REMOVED 28.11.25 16 1 NATURAL SLATE ROOF 2 WHITE RENDER 3 LIGHT GREY TRIPLE GLAZED ALU-CLAD WINDOWS AND DOORS 4 DARK GREY ALUMINIUM RAINWATER GOODS 5 DARK GREY RECESSED RENDERED PLINTH 6 DARK GREY QUADRUPLE GLAZED ROOFLIGHTS 7 BORDER HEDGING 8 EXISTING STONE WALL 9 NEW GATE FOR ACCESS FROM LINTIBERT ROAD 10 FIXED ROOF TO WALL WINDOW 11 UNTREATED RAINSCREEN LARCH TIMBER CLADDING 12 MVHR EXHAUST & INTAKE 13 SOIL VENT ON GABLE 14 PV PANELS 15 TIMBER CLAD COVERED ENTRANCE CANOPY 16 OBSCURED GLASS
Page 36
0 2 4 METRES JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 046 / B SOUTH ELEVATION AS PROPOSED 1:100 @ A3 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD BOUNDARY BOUNDARY SOUTH ELEVATION AS PROPOSED 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 1 14 6 66 2 3 4 77 8 2 3 4 A: LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25 1 NATURAL SLATE ROOF 2 WHITE RENDER 3 LIGHT GREY TRIPLE GLAZED ALU-CLAD WINDOWS AND DOORS 4 DARK GREY ALUMINIUM RAINWATER GOODS 5 DARK GREY RECESSED RENDERED PLINTH 6 DARK GREY QUADRUPLE GLAZED ROOFLIGHTS 7 BORDER HEDGING 8 EXISTING STONE WALL 9 NEW GATE FOR ACCESS FROM LINTIBERT ROAD 10 FIXED ROOF TO WALL WINDOW 11 UNTREATED RAINSCREEN LARCH TIMBER CLADDING 12 MVHR EXHAUST & INTAKE 13 SOIL VENT ON GABLE 14 PV PANELS 15 TIMBER CLAD COVERED ENTRANCE CANOPY
Page 37
0 2 4 METRES JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 048 / A NORTH ELEVATION AS PROPOSED 1:100 @ A3 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD BOUNDARYBOUNDARY NORTH ELEVATION AS PROPOSED 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 800 2 1 9 8 7 7 3 444 5 10 3 3 3 11 A: LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25 1 NATURAL SLATE ROOF 2 WHITE RENDER 3 LIGHT GREY TRIPLE GLAZED ALU-CLAD WINDOWS AND DOORS 4 DARK GREY ALUMINIUM RAINWATER GOODS 5 DARK GREY RECESSED RENDERED PLINTH 6 DARK GREY QUADRUPLE GLAZED ROOFLIGHTS 7 BORDER HEDGING 8 EXISTING STONE WALL 9 NEW GATE FOR ACCESS FROM LINTIBERT ROAD 10 FIXED ROOF TO WALL WINDOW 11 UNTREATED RAINSCREEN LARCH TIMBER CLADDING 12 MVHR EXHAUST & INTAKE 13 SOIL VENT ON GABLE 14 PV PANELS 15 TIMBER CLAD COVERED ENTRANCE CANOPY 15
Page 38
JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 042 / B SECTION A-A AS PROPOSED 1:50 @ A2 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: 0 METRES 1 2 2350 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD 800 1600 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 SECTION A-A AS PROPOSED BOUNDARY APPROX PROFILE OF NEIGHBOURING HOUSE AT 2 LINTIBERT TERRACE. CIRCA 470 APPEX OF HOUSE UNDER PREVIOU APPROVAL 24/01628/FUL 1884 2350 2855 2500 800 2100 1300 900 200 1000 1600 A: LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25
Page 39
JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 043 / B SECTION B-B AS PROPOSED 1:50 @ A2 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: A: 0 METRES 1 2 2350 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD 800 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 SECTION B-B AS PROPOSED BOUNDARY CIRCA 470 APPEX OF HOUSE UNDER PREVIOU APPROVAL 24/01628/FUL 2855 2500 700 LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25 APPROX PROFILE OF NEIGHBOURING HOUSE AT 2 LINTIBERT TERRACE.
Page 40
JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 104 / B SECTION C-C AS PROPOSED 1:50 @ A2 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: A: 0 METRES 1 2 2350 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 SECTION C-C AS PROPOSED BOUNDARY CIRCA 470 APPEX OF HOUSE UNDER PREVIOU APPROVAL 24/01628/FUL 2855 2500 2000 1800 LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25 APPROX PROFILE OF NEIGHBOURING HOUSE AT 2 LINTIBERT TERRACE.
Page 41
JOB NO. : DRAWING NO. / REVISION : DRAWING TITLE : SCALE : DRAWN BY : ISSUE : CLIENT : ADDRESS : JOB DESCRIPTION : 214 045 / B SECTION D-D AS PROPOSED 1:50 @ A2 M MCCRAE PLANNING JOHN & ROSEMARY KANE HIGHFIELD PLOT, LINTIBERT ROAD, MUTHILL, CRIEFF, PH5 2AH NEW BUILD DWELLING REV: AMENDMENT THESE DRAWINGS ARE FOR INFORMATION PURPOSES ONLY. ALL EXISTING DIMENSIONS TO BE CHECKED ON SITE PRIOR TO COMMENCEMENT OF WORKS OR MANUFACTURING OF COMPONENTS. ANY DISCREPANCIES TO BE BROUGHT TO THE ATTENTION OF THE ARCHITECT - IF IN DOUBT, ASK. THIS DRAWING IS THE COPYRIGHT PROPERTY OF PAPER IGLOO LTD - NO COPYING OR DISTRIBUTION OF THIS DRAWING OR ANY PART THEREOF IS PERMITTED WITHOUT PRIOR WRITTEN PERMISSION. DATE: 0 METRES 1 2 2350 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD 800 1600 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 SECTION D-D AS PROPOSED BOUNDARY CIRCA 470 APPEX OF HOUSE UNDER PREVIOU APPROVAL 24/01628/FUL 1884 2350 1100 2855 2500 A: LAYOUT & NOTES AMENDED 24.11.25 B: WINDOW REMOVED & ADDRESS AMENDED 28.11.25 APPROX PROFILE OF NEIGHBOURING HOUSE AT 2 LINTIBERT TERRACE.
Page 42
Design Statement - A Land 40 Metres South of 104 Willoughby Street Muthill, Crieff 02 December 2025
Page 43
Introduction The following Design Statement describes a Full Planning Application for a new build detached dwelling on a plot in the village of Muthill, near Crieff. The site that has undergone multiple historic applications, and most recently was given Full Planning Consent for a new home in January 2025. This new planning application proposes a revised design to suit the spatial needs of our clients, whilst also complying with the rigorous energy reduction demands of the Passivhaus Standard.
Page 44
3 of 22 Design Statement Paper Igloo Limited Section 1 - Planning Section 2 - Design Analysis Section 3 - Design Response Section 4 - Conclusion Section 5 - Appendices Contents
Page 45
Section One Planning
Page 46
5 of 22 Design Statement Paper Igloo Limited Section One Planning Planning History There have been the following historic applications for the site: 93/01488/FUL - 24 Nov 1993 Alterations to form at sun lounge/conservatory and porch - Application Approved 94/01835/FUL - 23 Jan 1995 Change of use from part of garden to motor sales - Application Refused 07/01600/FUL - 06 August 2007 Proposed construction of 5 holiday apartments and a garage with workshop and woodstore (Withdrawn) 07/01816/FUL - 20 Nov 2007 Erection of 5 no holiday rental apartments, garage with workshop, woodstore and conservatory and formation of new vehicular accesses (Withdrawn) 09/00076/FUL - 07 April 2009 Erection of dwelling house - Application Refused 09/00225/FUL - 30 March 2009 Erection of a garage, conservatory and fence - Application Refused 09/02148/FLL - 26 February 2010 Erection of a garage, conservatory and hard landscaping - Application Approved 12/00622/FLL - 04 June 2012 Variation of consent - (09/02148/FLL) - to alter roof finish on garage - Application Approved 12/01264/FLL - 05 September 201 Erection of a retaining wall (in retrospect) within rear garden 2 (Withdrawn) 12/01638/FLL - 31 October 2012 Erection of a retaining wall (in retrospect) - Application Approved 19/01442/TW - 19 September 2019 Tree Works - Application Approved 22/00069/LAW - 22 March 2022 Installation of air source heat pump system (proposed) - Application Refused 24/01399/FLL - 14 Nov 2024 Alteration to garage, installation of air source heat pumps and erection of fencing - Application Approved 24/01628/FLL - 29 January 2025 Erection of Dwellinghouse - Application Approved Location Plan 0 20 40 60 80 METRES LINTIBERT TERRACE A822 WILLOUGHBY STREET QUEENSFERRY ROAD LINTIBERT ROAD LINTIBERT ROAD PLOT
Page 47
6 of 22 Design Statement Paper Igloo Limited Section One Planning Planning Policy For reference these were noted in the most recent Report of Handling as follows: NPF4: - Policy 3: Biodiversity - Policy 7: Historic Assets and Places - Policy 9: Brownfield, Vacant and Derelict Land and Empty Buildings - Policy 13: Sustainable Transport - Policy 14: Design, Quality and Place - Policy 16: Quality Homes - Policy 22: Flood Risk and Water Management The Local Development Plan 2 (LDP2): - Policy 1A: Placemaking - Policy 1B: Placemaking - Policy 5: Infrastructure Contributions - Policy 6: Settlement Boundaries - Policy 17: Residential Areas - Policy 28A: Conservation Areas New Development - Policy 32: Embedding Low & Zero Carbon Generating Technologies in New Development - Policy 40B: Forestry, Woodland and Trees: Trees, Woodland and Development - Policy 41: Biodiversity - Policy 53C: Water Environment and Drainage: Surface Water Drainage - Policy 58A: Contaminated Land - Policy 60B: Transport Standards & Accessibility Requirements: New Development The changes we are proposing still comply with these policies, and go further in relation to energy demand reduction and sustainable construction. 89.50 90.00 90.50 91.00 91.50 92.00 92.50 89.00 88.50 0 METRES 4 8 2 Block Plan Existing
Page 48
7 of 22 Design Statement Paper Igloo Limited Section One Planning Planning Analysis Given that the core principles of the scheme - that is to say, the principle of a detached dwelling of a similar size and massing - have already received planning approval, this document does not revisit the detailed policy analysis underpinning the original consent, as those considerations remain valid. The core aim of all of the relevant LDP and NPF4 policies is to ensure that all new development is of a high quality and respects the environment in which it is contained. The policies aim to help tackle the causes and impacts of climate change, reduce resource use and moderate the impact of development on the environment. We see no reason why these aspirations cannot be achieved on this site with the construction of a single dwelling, following the established pattern of development. Conservation Area The site is located within the Muthill Conservation Area. It is not adjacent to any Listed Buildings, or Scheduled Ancient Monuments. Any design must therefore sit comfortably within the surrounding context, and not be detrimental to the character and quality of the Conservation Area. The Site Historically this land was additional garden ground to the property at 104 Willoughby Street; the plot is now under the new ownership of our clients. The site is starting to become overgrown, with many self-seeded weeds and other vegetation, and if left without intervention, will fall further into a state of wilderness. Around the site there are a variety of house types, sizes and architectural styles, however the predominant form is one of an essentially rectangular plan, with a longer elevation addressing the road. The plot is essentially a corner gap site fronting both Lintibert Road and Lintibert Terrace - and so represents an opportunity to infill between the existing adjacent dwellings, and complete an established pattern of individual dwellings sitting in appropriately sized gardens, within the village boundary. This infill approach is supported via numerous Policies, and specifically in NPF4 Policy 9, where opportunities to support development for the sustainable reuse of vacant and derelict land are to be supported. Residential Amenity As was established in the previous consent from 2025, a single detached dwelling can be consented on this site without compromising the residential amenity of the surrounding dwellings. Additionally, the site is of a size that adequate garden ground would remain for the new property. Current Site
Page 49
Section Two Design Analysis
Page 50
9 of 22 Design Statement Paper Igloo Limited Section Two Design Analysis Site Location & Context The site is semi-rural and, due to the setting within the small historic village of Muthill, the context is predominantly housing. The further landscape is defined by views over farmland towards the Ochil Hills to the south-east, the Grampians Foothills to the west, and northwards towards Creif. Land Use & Site Boundaries The site is currently vacant, overgrown ground. The boundary to Lintibert Road is defined by a low stone wall with a slightly overgrown hedge. To the north is the boundary to ‘Highfield’ - defined by a simple timber fence - and to the west the boundary to the neighbouring semi-detached dwellings on Lintibert Terrace is a mix of various overgrown weeds and other flora. To the southern boundary there is currently a series of evergreen trees (Cyprus Leylandi), which are tall and densely planted, separating the plot from the street. Permission has now been obtained from the Council to remove this overgrown hedge (reference: 25/01220/TW). Settlement Patterns The settlement pattern is that of rows of houses on the same axes as the streets they front. The southern end of the plot terminates the row of houses on Lintibert Terrace whereas the longer, eastern perimeter of the site addresses Lintibert Road. This provides the opportunity to continue the massing of the dwellings on the Terrace, but place the entrance facing the Road, thereby enlivening both streets. Topography The site area itself slopes upwards from north to south over a height of 3.5m. This slope will require some retaining works at the southern end of the plot to prevent the dwelling sitting too high on the site in relation to the neighbouring properties. Access There is currently a vehicular entrance on Lintibert Road to access the garage at Highfield. Due to the topography, Lintibert Road is a sensible location for a new vehicular access to the site. Permission has now been granted by the Council for the new dropped kerb (reference: VA/10370). Flood Risk Management The site is not at risk from surface water or river flooding, as indicated by SEPA flood maps. Sense of Place & Landscape Character The character of the site is relatively typical of a Scottish Conservation village location. Defined by traditional stone and rendered buildings, and wide views to the surrounding farmland and hills, there is a sense of openness to the landscape beyond. Trees, Ecology & Biodiversity There are some small trees dotted over the site but the majority of the flora is overgrown mixed species hedging to the eastern boundary, with a considerable number of undesirable weeds to the western edge. There are no known special or protected flora or fauna on the site. Current Site
Page 51
Section Three Design Response
Page 52
11 of 22 Design Statement Paper Igloo Limited Section Three Design Response Opportunities & Constraints With the approval of the application 24/01628/FLL, a precedent has now been established for a new 1.75 storey dwelling on the site. We have therefore developed the essence of this past proposal in response to our client’s specific brief. The siting in the Conservation Area is a material consideration in terms of form and materials. The Brief This revised proposal builds on the most recently approved planning application for a new dwelling. The focus has been on refining both the layout of the dwelling, in conjunction with a detailed assessment of the energy performance, and using both to inform the design. The new dwelling is proposed on the same position on the site but with a footprint reduced by c.25%. Our clients aspire to build a low energy home to a measurable and verified standard - therefore the exemplary Passivhaus Standard has been chosen (which our office specialises in). The aim is for the dwelling to receive full certification. Site Planning The overall site layout remains largely unchanged - pedestrian access to the site would still be directly from the pavement on Lintibert Road, with vehicular access further north adjacent to the boundary with Highfield. The new dwelling would be located on the higher, southern end of the plot in order to visually terminate the semi-detached dwellings on Lintibert Terrace. Primary access to the dwelling has been positioned on the gable end to allow for a more direct connection to the access from Lintibert Road - and a more usable layout on the ground floor - with the focus on balancing solar gain and a direct connection to the garden for the primary living spaces. In addition, the proposals utilise the optimum location for a south facing photo-voltaic array for on-site electrical generation, battery storage and a two car garage at the lower end of the site adjacent to the car parking. Vehicular Access & Parking Requirements for vehicular access to the site, parking and visibility splays at the road entrance are all exactly as those consented in application 24/01628/FLL, and the more recent dropped kerb consent (reference: VA/10370). Waste Water & Surface Water Strategies Similarly, there are no changes to the principles of the previously consented waste water and surface water management proposals. Percolation testing has been undertaken with satisfactory results. Site Boundaries It is proposed that the overgrown mixed flora to the western site boundary is removed and a managed mixed-species hedge planted here. On the eastern boundary, the existing overgrown hedge is to be trimmed yet retained for privacy and screening, whist the existing low stone wall is to be retained. To the south, the overgrown hedge / trees are to be removed and to the north, a 1.8m high fence is proposed. Block Plan Proposed 91.50 91.00 88.50 92.00 92.50 89.50 90.00 89.00 88.50 0 METRES 4 8 2
Page 53
12 of 22 Design Statement Paper Igloo Limited Section Three Design Response Building Proportion, Massing & Scale The overall massing of the building has been simplified to give a more favourable form-factor to mitigate unnecessary heat loss. The ridge height is consistent with the previous approval; this is still c.470mm below the ridge height of the neighbouring property at 2 Lintibert Terrace. The form compliments the existing pitched roof typologies within the locality. A Fabric First Approach in a Semi-Rural, Village Context The starting point for the revised design was to maintain a simple, pared-back dwelling of contemporary design that would sit comfortably within the Conservation Area, but with the potential to meet the Passivhaus Institut’s rigorous Passivhaus low-energy standard – additionally prioritising low-carbon, natural insulation materials wherever possible. The form, fabric, and detailing of the building have been carefully optimised; the heating and ventilation systems have been fully integrated at this early design stage to reduce energy demand and maximise the potential for on-site energy generation and storage. The revised design retains the original overall form of the previous building but simplifies it by removing unnecessary (and expensive) projections - the integrated porch, the bay window and two of the dormers. Simultaneously we have incorporated key technical improvements to the building fabric. Detailed analysis of energy performance of this design has proven that Passivhaus Certification is possible. A Low Carbon Approach The proposed superstructure construction materials have been selected for their inherently low embodied carbon - delivered in a naturally insulated, pre-fabricated timber frame to reduce waste and on-site construction time. External Materials The proposal seeks to compliment the existing dwellings within the Conservation Area but acknowledges that methods of construction and detailing have developed and progressed. The materials and finishes chosen are contemporary whilst alluding to, and being sympathetic to, the neighbouring properties. An off-white render has been chosen for the majority of the walls with a small section of naturally weathered, untreated timber cladding (for low maintenance) to the north, garden-facing elevation providing a subtle and softer contrast. Natural slate is utilised for both roof pitches in acknowledgement of a common roofing material of the locality. Two slate roofed wall-head dormers provide additional headroom on the rear north facing elevation and capture the distance view to the hills. Windows & Rooflights All windows and doors would be high performance triple glazed, timber frame, alu-clad. Window designs are predominately vertical emphasis, and where wider openings are created these are located on the private side of the dwelling, and subdivided with a central division. The street- Ground Floor Plan Proposed 1000 2500 3000 5000 1144 1583 500 500 5855 600 900 3000 1503 1200 1246 1200 3555 3490 6600 4600 >5M >5M >5M >5M 2000 9447 7710 2000 2127 3327 3360 1047 3327 10421 3327 1200 900 1825200 800 MIN 11351
Page 54
13 of 22 Design Statement Paper Igloo Limited Section Three Design Response facing windows are of a more modest size, whereas larger openings are again reserved for the rear, more private elevation. Solar gains and shading have been modelled using the PHPP software, and these calculations – alongside the spatial planning – have directly informed decisions about where to introduce openings on the elevations. Rooflights are solely on the south facing roof slope to maximise solar gain within the property. The result is a carefully balanced glazing strategy that supports energy performance, enhances the quality of internal spaces, and contributes to the overall coherence of the external architecture. It is worth noting that there is one window proposed on the west elevation - required for escape from the upper bedroom. Although this window is less than the ‘9m to boundary’ general rule, we propose the window would be obscured to prevent overlooking into the adjacent garden. All other windows are greater than 18m from other neighbouring windows, with the exception of those on the east elevation (15.5m). However, the ground floor windows here would be concealed by the tall hedge and the single upper floor window looks directly between the houses Marrich and Craigpark, so is offset from direct overlooking. Construction Detailing The detailing remains modern and refined, in keeping with the overall architectural approach. Minimal roof overhangs help resist wind uplift, while aluminium-clad window and door frames ensure long-term durability with minimal maintenance. Material choice coupled with contemporary detailing allows the dwelling to sit comfortably within the Conservation Area without resorting to pastiche. Internal Layout & Aspect The layout involves balancing the need for sunlight, daylight and a connection to nature, the garden and the wider outdoors. The balance of these on this plot is complicated by the main garden being north facing and the southern elevation being partially sunken in relation to the road. Locating the primary open-plan living space longitudinally along the north elevation, adjacent to the garden, gives direct access and visual connection to the spaces frequented by family life. Secondary, more cellular spaces have been arranged to front the road where there is access from the utility room via what is conceived as the “back” door. Primary ingress is via a main door on the east gable and a hall that intersects the two halves of the plan. A minimal covered entrance gives shelter on approach. On the first floor, the master bedroom benefits from an outlook over the garden and long views towards the hills to the north. Sunlight is directed into this space by strategically positioned rooflights that provide natural warmth and heat. The other two bedrooms feature either a southern orientation or similarly, a direct garden connection. The centre of the plan features a multi-functional hall with an integrated home working space overlooking the garden via a fixed feature window. South Elevation Proposed BOUNDARYBOUNDARY 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 800 BOUNDARY 2000 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD BOUNDARY 92.00 AOD 91.50 AOD 91.00 AOD 90.50 AOD 90.00 AOD 89.50 AOD 89.00 AOD 88.50 AOD 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 2855 GROUND FFL: 90.946 FIRST FFL GATE FGL: 90.750 East Elevation Proposed
Page 55
Section Four Conclusion
Page 56
15 of 22 Design Statement Paper Igloo Limited Section Four Conclusion This new dwelling has been carefully designed to sit within its semi-rural village context in a subtle yet meaningful way. The design choices outlined in this document support the ambition that contemporary, low-energy buildings can inhabit the same streetscape as traditional and older constructions whilst being being respectful of the vernacular. The architecture offers a modern interpretation of the Scottish vernacular - a simply formed, linear building with a symmetrically pitched roof and vertically proportioned openings that does not look out of place within a Conservation Area. These new proposals respond thoughtfully to the character of the site without resorting to pastiche or imitation, allowing for the creation of a contemporary, sustainable dwelling that is both respectful of its setting and rooted in the present. North Elevation ProposedSouth Elevation Proposed
Page 57
Section Five Appendices
Page 58
17 of 22 Design Statement Paper Igloo Limited Section Five Appendices Appendix 1 - Site Photographs Appendix 2 - Energy Statement - Policy Energy Statement - The Passivhaus Standard Appendix 3 - Precedent
Page 59
18 of 22 Design Statement Paper Igloo Limited Appendix 1 Site Photographs Key 1. Southern Boundary showing overgrown Cypress Leylandi hedge 2. View South West towards rear and gable of 2 Lintibert Terrace 3. View South within plot 4. View South within plot towards Highfield 5. View South towards Highfield from south boundary 1. 2. 5. 3. 4.
Page 60
19 of 22 Design Statement Paper Igloo Limited Appendix 2 Energy Statement - Policy In accordance with the ongoing carbon reduction and low energy aims of the Scottish Government the following aspects have been carefully considered to take advantage of the site climate and comply with current Policy regarding reducing energy in buildings. - The building shape, size and orientation - The built fabric and design - The space heating, hot water and ventilation systems design The Climate Change Act Section 72 of the Climate Change (Scotland) Act 2009 introduced Section 3F into the Town and Country Planning (Scotland) Act 1997, which requires that “all developments [should] ... be designed so as to ensure that all new buildings avoid a specified and rising proportion of the projected greenhouse gas emissions from their use ... through the installation and operation of low and zero-carbon generating technologies.” The 2024 New Build Heat Standard As part of the Heat in Buildings Strategy, the Scottish Government is committed to ensuring that, from 2024, new buildings must use heating systems which produce zero direct emissions at the point of use. Fabric improvements within the regulations are also ongoing. Low and Zero Carbon Buildings Policy National Planning Policy - NPF4 - requires that all development should support the use of renewable, low-carbon and zero emissions technologies whenever possible and / or appropriate. This national framework intends to “encourage, promote and facilitate development that addresses the global climate emergency and nature crisis.” Policy 1 suggests that significant weight will be given to proposals that meet this goal. Policy 2 notes that: (a) Development proposals will be sited and designed to minimise lifecycle greenhouse gas emissions as far as possible. (b) Development proposals will be sited and designed to adapt to current and future risks from climate change. (c) Development proposals to retrofit measures to existing developments that reduce emissions or support adaptation to climate change will be supported. Policy 11 additionally notes that “In considering these impacts, significant weight will be placed on the contribution of the proposal to renewable energy generation targets and on greenhouse gas emissions reduction targets.” Local Planning Policy requires proposals to reduce Greenhouse gas emissions by: - Using sustainable construction materials and methods. - Designing energy and heat efficient buildings that maximise passive environmental gains (solar, shelter, water use, etc.). - Where feasible, meet energy and heating needs through on-site renewables or local energy networks. Technologies Used Below we note which low or zero carbon technologies we believe could be appropriate on this site, and which would accord with the national policy noted opposite. - Photovoltaic Panels & potentially battery storage These have been shown on the drawings. - EV Charging Point Any new dwelling should now have the capability to fit an EV charging point either at completion, or in the future. This has also been noted on the drawings. - Mechanical Ventilation system with Heat Recovery (MVHR) An MVHR system is centralised, which means that a single, central unit quietly manages airflow throughout the building, using a built-in heat exchanger to capture warmth from outgoing air and transfer it to the fresh air coming in. This means warmth already generated inside isn’t wasted. When properly designed and installed, MVHR systems are highly efficient – often recovering over 80% of the heat – while using very little electricity. Fresh air is delivered to every living space, and stale air is extracted from kitchens, bathrooms, and other ‘wet’ rooms through a carefully planned duct layout. The result is a steady flow of pre- warmed, filtered air throughout the home, supporting excellent indoor air quality – all with barely a sound. - Air Source Heat Pump Modern heat pumps are highly efficient, with a Coefficient of Performance (CoP) of up to 4 – meaning they can deliver four units of heat for every unit of electricity used. This efficiency can further reduce the already low energy demand of a low energy building, covering both space heating and hot water. Compliance Through these means the building will comply with the goals set out in the Climate Change (Scotland) Act 2009, and those outlined in both national and local Planning Policy.
Page 61
20 of 22 Design Statement Paper Igloo Limited Appendix 2 Energy Statement - The Passivhaus Standard We care deeply about designing and creating genuinely durable and resilient architecture. That’s why we design to the voluntary Passivhaus Standard whenever we can, and often go even further with our own set of rigorous sustainability standards. Passivhaus buildings These are defined as those that have extremely low energy demand, and meet high standards for thermal comfort and good indoor air quality – even in very cold weather, like a Scottish winter that can get as low as -10°C. The word ‘passive’ is used because the aim is to eliminate the need for an extensive ‘active’ heating system. Instead, Passivhaus buildings utilise internal heat gains and solar energy entering through the glazed windows and doors, while simultaneously minimally heating the incoming fresh air. This reduces the demand for heating energy to its lowest level – no matter where the home is built. It’s a fabric-first approach. The idea is to optimise the building’s inherent qualities, reducing the need for expensive or energy intensive ‘bolt-on’ technologies. The building fabric itself must perform to a very high standard first and foremost – even when renewable systems are incorporated into the design. And that’s exactly what Passivhaus certified builds ensure. For other new buildings which cannot meet the criteria of the Passivhaus Standard for one reason or another - such as a north facing site - there is also the PHI Low Energy Building Standard. For renovations of existing buildings, the Passive House Institute has developed the EnerPHit Standard - a certification for highly energy-efficient retrofits based on Passivhaus principles. These Standards are regulated by the Passivhaus Institut who are based in Darmstadt, Germany. The Process The design process for a Passivhaus building is a little different. Instead of treating it as an afterthought, a Passivhaus design integrates energy efficiency at every stage - from initial concept, all the way through to construction. Traditional building regulations can sometimes fall short, with a noticeable gap between what's designed on paper and how a building actually performs. In contrast, the Passivhaus approach brings precision to the forefront. Thanks to its robust certification process, every element is carefully planned, tested, and verified – ensuring the finished building lives up to its promises. The Principles There are five set principles that define a Passivhaus building - all designed to maximise energy efficiency and comfort: - Super insulation - Airtightness - High performance windows and doors - Excellent indoor air quality - Thermal bridge free construction. Key Components A Passivhaus building pays close attention to the fundamentals. Key elements – like the insulation of walls and roofs, how windows and doors are installed, the ventilation system, and both the airtight and wind tight barriers – are all carefully considered and precisely detailed. Rather than looking at these components in isolation, the Passivhaus standard takes a whole-building approach. Using the Passivhaus Planning Package (PHPP), a detailed energy model is created, tailored to the site and specific design. Everything is factored in – from heat loss through the envelope to the energy used by everyday appliances. The result is a building that’s ‘built tight and ventilated right’ – a proven route to low energy use and a reliable way to close the gap between design intent and real-world performance. These physical features work together to deliver the exceptional thermal comfort that defines a Passivhaus. High levels of insulation keep internal temperatures stable throughout the day, meaning surfaces stay close to room temperature and every corner of the building remains comfortable and usable. Airtight construction removes unwanted draughts, while heat recovery ventilation ensures that warm air isn’t wasted – so energy spent on heating stays where it’s needed. The Criteria Space heating demand: ≤ 15kWh/(m2.a) or Heating Load: ≤ 10W/m2 Airtightness level: 0.6 ach/hr at 50Pa Frequency of overheating: ≤ 10% of the year at 25°C ‘Classic’ Passivhaus: Primary energy Renewable: ≤ 60kWh/(m2.a) There are also 2 further ‘classes’ - Plus and Premium - both of which require maximising renewable energy made on site - but to keep with the fabric first approach, they require even less total energy to be used in the first place. The criteria for an EnerPHit renovation vary a little, to account for the difficulty in working around an existing form or window arrangement, however the ethos and principles of the Passivhaus Standard remains consistent. With over a decade of experience, we know how to handle the technical aspects - all while delivering beautiful architectural design. You can read more about all of this on our website: www.paperigloo.com/sustainability- passivhaus/
Page 62
21 of 22 Design Statement Paper Igloo Limited Appendix 3 Precedent Key 1. New build passivhaus with white render & slate in historic village - Paper Igloo 2. Slate roof with integrated PV system - Paper Igloo 3. Contemporary entrance canopy - example 4. Contemporary entrance canopy- example 5. Naturally weathered horizontal timber cladding - Mary Arnold Foster 6. Contemporary white render - K-Rend 6. 5 1. 2. 3 4
Page 63
Paper Igloo Limited Ostro, Fintry Road, Kippen, Scotland FK8 3HL SC 302888 info@paperigloo.com +44 (0) 1786 870 539 www.paperigloo.com
Page 64
Cert No. 10312 PHASE 1 DESK STUDY 1853 – 104 Willoughby Street, Muthill John Kane
Page 65
Document History and Status Revision Date issued Reviewed by Approved by Date approved Revision type R0.1 19.3.2025 JC JC 18.3.2025 FINAL Distribution of copies Revision Copy no Quantity Issued to R0.1 Electronic 1 John Kane Name of project: 104 Willoughby Street, Muthill Client: John Kane Project number: 1853 Author: Max Fuller BSc (Hons) MSc Checked: John Curran BEng (Hons) MBA MCIOB CEnv
Page 66
CONTENTS
Page 67
Contents 1. EXECUTIVE SUMMARY .......................................................................................................... 2 2. INTRODUCTION ....................................................................................................................... 4 2.1 Background ...................................................................................................................... 4 2.2 Objectives and Scope of Work ................................................................................. 4 2.3 Proposed Development ............................................................................................... 4 2.4 References ........................................................................................................................ 4 3. SETTING ...................................................................................................................................... 6 3.1 Location ............................................................................................................................. 6 3.2 Site Description ............................................................................................................... 6 3.3 Site Vicinity ...................................................................................................................... 6 3.4 Planning History .............................................................................................................. 6 3.5 Investigation History ..................................................................................................... 6 3.6 Geology ............................................................................................................................. 6 3.6.1 Strata .............................................................................................................................. 6 3.6.2 Faulting........................................................................................................................... 7 3.6.3 Borehole Records ................................................................................................... 7 4. SITE HISTORY ...................................................................................................................... 9 4.1 Map Review ...................................................................................................................... 9 5. ENVIRONMENTAL SENSITIVITY ....................................................................................... 12 5.1 Radon ................................................................................................................................ 12 5.2 Geological Hazards ....................................................................................................... 12 5.3 Mining ................................................................................................................................ 12 5.3.1 Non-Coal Extractions .............................................................................................. 12 5.3.2 Coal Mining.................................................................................................................. 12 5.4 Contaminated Land ...................................................................................................... 12 5.5 Water Environment ...................................................................................................... 12 5.5.1 Hydrogeology ............................................................................................................ 12 5.5.2 Hydrology .................................................................................................................... 12 5.5.3 Flooding ....................................................................................................................... 13 5.5.4 Water Abstractions .............................................................................................. 13 5.5.5 Discharge Consents ................................................................................................. 13 5.5.6 Pollution Incidents .................................................................................................... 13 5.6 Waste Sites ...................................................................................................................... 13 5.7 Licensed Industrial Activity ....................................................................................... 13 5.7.1 Licensed Sites ............................................................................................................ 13 5.7.2 Current Industrial Activities .................................................................................. 13
Page 68
5.7.3 Fuel Stations and Tanks ......................................................................................... 13 5.8 Sensitive Land Uses ...................................................................................................... 14 5.9 Data Integrity Assessment ......................................................................................... 14 6. CONCEPTUAL SITE MODEL ............................................................................................... 16 6.1 Site Setting ...................................................................................................................... 16 6.2 Preliminary Conceptual Site Model (PCSM)......................................................... 16 6.3 Potential Contamination Sources ............................................................................ 17 6.3.1 On-site .......................................................................................................................... 17 6.3.2 Off-site .......................................................................................................................... 17 6.4 Pathways .......................................................................................................................... 17 6.5 Receptors ......................................................................................................................... 17 7. CONCLUSIONS ........................................................................................................................ 21 7.1 Conclusions ..................................................................................................................... 21 7.2 Recommendations ........................................................................................................ 21 8. REFERENCES .......................................................................................................................... 23 Index of Tables Table 1: Table summarising geology on-site. .......................................................................... 7 Table 2: Table summarising borehole records from the site and surrounding area. 7 Table 3: Table summarising site history from historical mapping. ................................. 9 Table 4: Table summarising geological hazards on and off-site. ................................... 12 Table 5: Table summarising the hydrogeology on-site. .................................................... 12 Table 6: Table summarising nearby surface water features. ........................................... 12 Table 7: Table showing current industrial activities within 250m. ................................ 13 Table 8: Table showing fuel stations listed within 250m. ................................................. 13 Table 9: Table showing tanks listed within 250m. .............................................................. 14 Table 10: Table summarising the geo-environmental setting of the site. ................... 16 Table 11: Table summarising tiered assessment hierarchy. .............................................. 16 Table 12: Sources identified on-site. ......................................................................................... 17 Table 13: Pathways identified. .................................................................................................... 17 Table 14: Receptors identified. ................................................................................................... 17 Table 15: Table summarising severity and probability for risk assessment model. . 18 Table 16: Table summarising overall risk for assessment model. .................................. 18 Table 17: Table summarising preliminary conceptual site model................................... 19 Table 18: Table detailing contaminants tested for during laboratory testing. .......... 21
Page 69
Appendices APPENDIX I Figures Site Location Plan Site Boundary Plan Proposed Development Plan APPENDIX II Groundsure Report APPENDIX III Historical Mapping Limitations This report was produced by Soilutions Ltd for John Kane as the Phase 1 Geo- Environmental Desk Study Report for land to the south of 104 Willoughby Street, Muthill to provide a preliminary assessment of potential ground related development constraints and to support a planning application. This report may not be used by any person other than John Kane and must not be relied upon by any other party without the explicit written permission of Soilutions Ltd. In any event, Soilutions Ltd accepts no liability for any costs, liabilities or losses arising as a result of the use or reliance upon the contents of this report by any person other than John Kane, or the client if payment in full has not been received. All parties to this report do not intend any of the terms of the Contracts (Rights of Third Party Act 1999) to apply to this report. Please note that this report does not purport to provide definitive legal advice. The findings of the desk study are based on the available published information at the time of the production of the report.
Page 70
1 EXECUTIVE SUMMARY
Page 71
2 1. EXECUTIVE SUMMARY Soilutions has been commissioned by John Kane to provide a Phase 1 Geo-environmental Desk Study report. The purpose of the report is to collate background historical and geo- environmental data to address where possible land contamination within Planning Policy Guidance and geo-environmental constraints for development. The site is located at the corner of Lintibert Road and Lintibert Terrace, approximately 0.5 km south east of Muthill centre. The approximate National Grid Reference for the centre of the site is (NGR) 286995, 716587. It is proposed to construct a new house with associated gardens and car parking area. A soakaway is proposed in the north of the site. The site was part of a field until the early 20th century when a building is shown in the north of the site and the site has become part of a garden. The building was demolished by 2003. The surrounding area was agricultural to the east, south and west with the village of Muthill to the north. A petrol station is shown 75m to the north from the 1950s. Made Ground is not indicated within the site boundary on the published geological mapping. Made ground is likely to be present on site associated with the demolition of the building in the north. The site is underlain by bedrock of the Cromlix Mudstone Formation. Superficial deposits comprising Glacial Till are expected across the site. The superficial deposits are likely to be fine grained and unlikely to be suitable for soakaway drainage. The bedrock geology is designated as a moderate productivity aquifer. The superficial deposits are classified as a low productivity aquifer. The Preliminary Conceptual Site Model indicates a Moderate/Low that harm could arise to a designated receptor from identified hazards. A ground investigation is recommended to assess the geo-environmental constraints identified on site by this desk study. Infiltration drainage testing should be carried out to determine the feasibility of soakaway drainage. Soil samples should be taken from the infiltration test pits for laboratory testing to determine the risk to human health and proposed flora. The executive summary contains an overview of key findings and conclusions. However, no reliance should be placed on the executive summary until the whole of the report has been read. Other sections of the report may contain information which puts into context the findings noted within the executive summary.
Page 72
3 INTRODUCTION
Page 73
4 2. INTRODUCTION 2.1 Background Soilutions were commissioned by John Kane (the Client) to conduct a Phase 1 Geo-environmental Desk Study for their site at land to the south of 104 Willoughby Street, Muthill (the site). The Phase 1 Desk Study report has been prepared in general accordance with the Environment Agency’s Land Contamination Risk Management (LCRM) guidance and BS10175 (Code of Practice for the Investigation of Potentially Contaminated Sites). BS10175 recommends that a Preliminary Investigation includes data collection, qualitative interpretation and reporting. Data collection includes documentary research, to: • Formulate an initial conceptual site model • Assess need for, and scope of, further investigation; and • Provide a preliminary risk assessment in a final report. If the Phase 1 Desk Study identifies potentially significant risks to human health and/or the environment, a subsurface ground investigation may be required to characterise ground conditions at the site. The investigation would determine if contaminative substances are indeed present at or around the site and help quantify the risk to human health and/or the environment. 2.2 Objectives and Scope of Work The scope and aims of the Phase 1 report, in accordance with BS10175, are to: • Review historic information and the environmental setting of the site; • Identify the geology and hydrogeology beneath the site, and within a buffer zone of 250m around the site, using information from the BGS and other sources; • Review an environmental data report, online and published sources to determine if site specific geo-environmental and geotechnical risks to the site pose a potentially significant risk to development; • Formulate an initial conceptual site model and preliminary risk assessment (PRA) which identifies possible pollution linkages between contamination sources and receptors via plausible migration and exposure pathways; • Design an intrusive investigation if the PRA concludes potentially significant risks may be present. 2.3 Proposed Development It is proposed to construct a new house in an area of garden in the south of the site. There will be associated gardens and car parking. A soakaway is proposed in the south of the site. A proposed development plan is included in APPENDIX I. 2.4 References A full reference list is included in section 8. Key sources of information used in the production of this report include: • Groundsure Historical Mapping ref. GS-B46-R3G-T72-OB5 • Groundsure Enviro and Geo Insight Report ref. GS-UCE-SE5-F7U-D8M • British Geological Survey. (BGS) Geology of Britain Map Viewer www.bgs.ac.uk • Department of the Environment Industry Profiles.
Page 74
5 SETTING
Page 75
6 3. SETTING 3.1 Location The site is located at the corner of Lintibert Road and Lintibert Terrace, 0.5km south east of Muthill centre. The site is rectangular in shape and approximately 0.05 ha in area. The approximate national grid reference is 286995, 716587. A site location plan is included in APPENDIX I. 3.2 Site Description The site is currently part of the garden of 104 Willoughby Street. The site forms the southernmost extent of the garden and is mostly covered by lawn. In the south west of the site is a small enclosure. In the north of the site are a woodstore, shed and greenhouse. In the west of the site is an above ground liquid petroleum gas (LPG) tank. The site is bound by hedges in the west, south and east. The northern boundary is not clearly defined. No pollution sources have been identified at the site. The above ground LPG tank is not considered a plausible source of contamination – any leaks would present themselves as gas rather than liquids and would disperse to air rather than contaminate the soil. Vegetation at the site comprises grass across the majority of the site. A group of immature conifers is present along the southern boundary. A vegetable patch is present in the south west of the site. The hedges bounding the site are a mix of beech and holly. A specialist ecologist should be consulted if required to confirm the presence or absence of invasive species. The topography of the site slopes downwards to the north. Levels on the topographical survey are between 88.50 and 92.00 metres above Ordnance Datum (mAOD). Vehicle access at the site is via a parking area to the north of the site. 3.3 Site Vicinity The area around the site is occupied by: North House and gardens with residential area and petrol station beyond East Houses with arable fields beyond South Residential area West Residential area 3.4 Planning History The local authority’s planning portal has been consulted. No previous applications for the site have been identified. 3.5 Investigation History No previous reports have been provided by the client. 3.6 Geology 3.6.1 Strata The BGS mapping for the site (Ref 1) indicates that the geology at the site comprises:
Page 76
7 Table 1: Table summarising geology on-site. Unit Name BGS Description Anthropogenic Not shown N/A Superficial Glacial Till Diamicton Bedrock Cromlix Mudstone Formation Characteristically soft, bright red to dull brownish- red, maroon or purplish-brown, with green reduction spots in the north-eastern Midland Valley, generally massive but often thinly laminated, poorly-sorted, fine-grained silty sandstones, sandy siltstones, siltstones and mudstones Made ground is not shown at the site or in the vicinity. Made ground may be present associated with the demolition of a former building in the north of the site. The glacial till is likely to be clay and is unlikely to be suitable for a soakaway. Any made ground present under the former building, which is roughly in the proposed soakaway location, will not be suitable for soakaway drainage. Infiltration testing should be carried out to determine the infiltration rate of the soil for soakaway design and to check for the presence of made ground. 3.6.2 Faulting No faults have been identified in the vicinity of the site. 3.6.3 Borehole Records The following BGS borehole records have been reviewed (Ref 15): Table 2: Table summarising borehole records from the site and surrounding area. BGS Reference Drilled By Method Strata Distance (m) Direction Depth (m) Description NN81NE30 BAM Ritchies Rotary 0.00-0.25 Soil and clay 500 E 0.25-1.85 CLAY 1.85-5.00 SANDSTONE
Page 77
8 SITE HISTORY
Page 78
9 4. SITE HISTORY 4.1 Map Review A summary of the information obtained from the available historical maps and aerial photographs are presented in the table below. Copies of the historic maps are provided in APPENDIX III. Table 3: Table summarising site history from historical mapping. Date Scale Map Observations 1864- 1866 1:2,500 1:10,560 On Site The site is shown as part of an open field. Off Site (within 250m) A house and garden are shown adjacent to the north. The area to the north west is predominantly residential, with a school 50m to the north west. Lintibert, a farmyard, is shown 200m to the north east. The area to the east, south and west is covered by fields. 1901 1:2,500 1:10,560 On Site A small building is shown in the south of the site. Off Site (within 250m) The house adjacent to the north has been demolished and replaced with the present-day 104 Willoughby Street.
Page 79
10 1954- 2025 1:1,250 1:2,500 1:10,000 1:10,560 On Site The building on site is not shown on the 1:10,000 or 1:10,560 maps but is shown on the 1:2,500 maps until 2003. Off Site (within 250m) Residential development has taken place to the east, south and west of the site. A petrol station is shown 75m to the north.
Page 80
11 ENVIRONMENTAL SENSITIVITY
Page 81
12 5. ENVIRONMENTAL SENSITIVITY 5.1 Radon The site is not recorded to be within a radon affected area as <1 % of properties are above the action level. Radon protection measures are not required in any new buildings at the site. 5.2 Geological Hazards The following ground stability hazard ratings for the site are detailed in the Groundsure report: Table 4: Table summarising geological hazards on and off-site. Hazard Direction Hazard Rating Potential for Shrinking or Swelling Clay Ground Stability Hazards On site Very low Potential for Running Sand Ground Stability Hazards On site Very low Potential for Compressible Ground Stability Hazards On site Negligible Potential for Collapsible Rocks Stability Hazards On site Very low Potential for Landslide Ground Stability Hazards On site Very low Potential for Ground Dissolution Stability Hazards On site Negligible 5.3 Mining 5.3.1 Non-Coal Extractions No records of non-coal mining activity are recorded within 250m of the site. The BGS notes that vein minerals are present in the area but that the potential for difficult ground conditions is unlikely and need not be considered. 5.3.2 Coal Mining The site does not lie within a Mining Remediation Authority Reporting Area. 5.4 Contaminated Land No sites in the vicinity are identified as Contaminated Land under Part 2A of the Environmental Protection Act 1990 (Ref 11). 5.5 Water Environment 5.5.1 Hydrogeology The following aquifer classifications have been identified for the site: Table 5: Table summarising the hydrogeology on-site. Unit Name Aquifer Classification Superficial Glacial Till Low Productivityc Bedrock Cromlix Mudstone Formation Moderate Productivityb aEnvironment Agency Classification (Ref 18) bSEPA Classification (Ref 12) cMcDonald et Al Classification (Ref 17) 5.5.2 Hydrology The closest surface water features to the site are detailed below: Table 6: Table summarising nearby surface water features. Name Orientation Classification Depth *(m) Distance (m) Direction Issues/Drain S-N N/A NR 107 NE aEnvironment Agency Classification bSEPA Classification *at time of site walkover There are numerous drains and issues in the area which eventually reach the River Earn, 2.15km to the north east.
Page 82
13 5.5.3 Flooding The site lies within an area at negligible risk from coastal, river or surface flooding. Although the report provides information on flood risk this does not constitute a flood risk assessment for the site. The flood risk information does not account for flooding from sources such as blockages in drainage systems, artificial water features and overland flow. A separate Flood Risk Assessment may be required for the site. 5.5.4 Water Abstractions No groundwater abstraction licenses are listed in the Groundsure report within 2km of the site. No surface water abstraction licenses are listed in the Groundsure report within 250m of the site. 5.5.5 Discharge Consents No SPRI surface water discharge consents are listed on the Scotland’s Environment website within 250m of the site. 5.5.6 Pollution Incidents No SEPA incidents are listed within 250m of the site in their online Disclosure Log or in the Groundsure report. 5.6 Waste Sites No records of historic or current landfills or other waste sites are listed in the Groundsure report within 250m of the site. 5.7 Licensed Industrial Activity 5.7.1 Licensed Sites No Integrated Pollution Prevention and Controls, Environment Agency or Local Authority Integrated Pollution Controls, Environmental Permits or Enforcements are listed in the Groundsure report within 250m of the site. No Radioactive Substance Licenses are listed in the Groundsure report within 250m of the site. No Part A(2) or Part B activities are listed in the Groundsure report within 250m of the site. 5.7.2 Current Industrial Activities Three records of industrial activity are recorded within 250m of the site. The closest industrial activities to the site are: Table 7: Table showing current industrial activities within 250m. Site Name Activities Active? Distance (m) Direction Viewfield or Sweeney’s Garage Petrol and fuel stations, vehicle repair, testing, servicing and cleaning Yes 74 N Electricity sub-station Electrical features Yes 131 S The sub-station is shown from the 1950s so may be a source of PCBs, however it is sufficiently far from the site that it is unlikely to pose a plausible risk of contamination. 5.7.3 Fuel Stations and Tanks The following petrol filling station records are listed in the Groundsure report within 250m of the site. Table 8: Table showing fuel stations listed within 250m. Site Name Active? Distance (m) Direction Viewfield Garage Yes 72 N
Page 83
14 The petrol station is downslope of the site by around 2.00m. The topography in the area slopes downwards to the north and east towards the River Earn and the petrol station is to the north of the site. This suggests that the hydraulic gradient of the groundwater around the site is to the north east, away from the site, and the petrol station is unlikely to pose a risk of contamination to the groundwater beneath the site. The following records of tanks are listed in the Groundsure report within 250m of the site. Table 9: Table showing tanks listed within 250m. Site Name Tank Type Date Distance (m) Direction Lintibert Unspecified 1971 211 N The tank appears to be a silo at Lintibert farm an is likely to have stored grain and so is not considered a plausible source of contamination. 5.8 Sensitive Land Uses No records of sensitive land use (nitrate vulnerable zones, ancient woodland, Sites of Special Scientific Interest, greenbelt etc.) are listed in the Groundsure report within 250m of the site. 5.9 Data Integrity Assessment The data has been collated from information supplied by third parties. While the data is understood to be contemporary, some changes to land-use may have occurred since the time of data collection. However, it is considered that any changes in land-use will not have any detrimental impact to the property on the basis that potentially contaminating land- uses are regulated in a manner that reduces potential for impact. No evidence has been presented during this study that indicates that historic or contemporary data is inaccurate and as such may be relied upon to provide reasonable evidence of potential risk as it relates to the proposed development.
Page 84
15 CONCEPTUAL SITE MODEL
Page 85
16 6. CONCEPTUAL SITE MODEL 6.1 Site Setting The geo-environmental setting of the site, determined by the information detailed in sections 2, 3 and 4, is summarised below. Table 10: Table summarising the geo-environmental setting of the site. Site Description The site is part of the garden of 104 Willoughby Street. The site is largely covered by lawn, with a vegetable patch in the south west. There is a shed and greenhouse in the north of the site and an LPG tank in the west. Site History The site was part of a field until the early 20th century when a building is shown in the north of the site and the site has become part of a garden. The building was demolished by 2003. The surrounding area was agricultural to the east, south and west with the village of Muthill to the north. A petrol station is shown 75m to the north from the 1950s. Geology Made Ground Made ground is not shown on the BGS mapping. Made ground may be present associated with the demolition of the building in the north of the site. Superficial Superficial deposits comprising Glacial Till are expected at the site. Bedrock Bedrock deposits comprising Cromlix Mudstone Formation are expected at the site. Water Environment Aquifers The bedrock deposits are classified as a moderate productivity aquifer. The superficial deposits are a low productivity aquifer. Surface Water The closest surface water feature is a drain 107m to the north east. At this stage, the following uncertainties exist due to gaps in the available data: • The infiltration rate of the soil for soakaway design is unknown. • No chemical data is available for the site. • No data on groundwater levels is available. • The depth and nature of made ground is unknown. 6.2 Preliminary Conceptual Site Model (PCSM) A preliminary conceptual site model has been prepared for the site based on the guidance given Environment Agency’s Land Contamination Risk Management (LCRM) guidance (Ref 19). The basis of this approach is the development of a conceptual site model (CSM) to represent the source-pathway-receptor pollutant linkages which form the basis of the assessment of risk. The production of the risk assessment follows the principles given in LCRM, using a tiered assessment hierarchy. Table 11: Table summarising tiered assessment hierarchy. Tier 1 Identification of possible pollutant linkages and creation of PCSM Tier 2 Non-site-specific assessment of chemical data using generic assessment criteria (GAC) Tier 3 Site-specific assessment of chemical data using site specific assessment criteria (SSAC) where GAC are not available or applicable. This report comprises a Tier 1 assessment. No site investigation has taken place and so the source-path-receptor linkage has been identified using the information included in the
Page 86
17 Groundsure report, Department of the Environment Industry Profiles (Ref 3) and other sources detailed in the reference list. 6.3 Potential Contamination Sources 6.3.1 On-site Table 12: Sources identified on-site. Source Contaminants S1: Made Ground Source of heavy metals, phenols, polyaromatic hydrocarbons (PAHs), total petroleum hydrocarbons (TPHs) and asbestos 6.3.2 Off-site No plausible off-site sources of contamination have been identified. 6.4 Pathways Table 13: Pathways identified. Pathway P1: Human Uptake • Dermal contact with soils and dust • Ingestion of soils and dust • Inhalation of soils, dust and vapour • Ingestion of homegrown produce and soil adhered to it P2: Migration in solution through groundwater P3: Migration along preferential pathways via underground services and drainage runs (pipes, culverts and granular material) P4: Migration by surface run off P5: Ground gas and vapour migration P6: Root uptake 6.5 Receptors Table 14: Receptors identified. Source Details R1: End Users A residential development is proposed. R2: Groundwater The bedrock deposits are classified as a moderate productivity aquifer. The superficial deposits are a low productivity aquifer. R3: Surface Water The closest surface water feature is a drain 107m to the north east. R4: Property Services (e.g. drinking water supply pipes) and structures/buildings (concrete used in foundations) R5: Adjacent Property Residential properties to the north and west. R6: Proposed Flora and Fauna Gardens are shown in the proposed development plan. The conceptual site model is present in the table below. The risk assessment has been produced using the risk model in Table 15 and Table 16, adapted from CIRIA C552, “Contaminated Land Risk Assessment- A Guide to Good Practice” (Ref 9):
Page 87
18 Table 15: Table summarising severity and probability for risk assessment model. Category Definition Potential Severity Severe Acute risks to human health, catastrophic damage to buildings/property, major pollution of controlled waters Medium Chronic risk to human health, pollution of sensitive ecosystems or species, significant damage to buildings or structures. Mild Pollution of non-sensitive waters, minor damage to buildings/property. Minor Requirement for protective equipment during site works to mitigate health effects, damage to non-sensitive ecosystems or species. Probability of Risk High Likelihood Pollutant linkage may be present and risk is almost certain to occur in long term, or there is evidence of harm to the receptor. Likely Pollutant linkage may be present and it is probable that the risk will occur over the long term. Low Likelihood Pollutant linkage may be present and there is a possibility of the risk occurring, although there is no certainty that it will do. Unlikely Pollutant linkage may be present but the circumstances under which harm would occur are improbable. Table 16: Table summarising overall risk for assessment model. Potential Severity Severe Medium Mild Minor Probability of Risk High Likelihood Very High High Moderate Moderate/Low Likely High Moderate Moderate/Low Low Low Likelihood Moderate Moderate/Low Low Negligible Unlikely Moderate/Low Low Negligible Negligible The preliminary conceptual site model is produced on the following page (Table 17).
Page 88
19 Preliminary Conceptual Site Model Table 17: Table summarising preliminary conceptual site model. Source Pathway Receptor Severity Probability Risk Comments Proposed Investigation On-Site P1 Human uptake R1 End Users Medium Low Moderate/Low End users may interact with the soils through leisure or maintenance activities. Contamination associated with the demolition of a building in the north of the site may be present at the site. The risk to human health is Moderate/Low. Soil samples should be taken from the trial pits excavated for soakaway testing to determine the risk to human health. S1 Made Ground P2 Migration in solution through groundwater R2 Groundwater Medium Unlikely Low The site is underlain by bedrock of the Cromlix Mudstone Formation, which is classified as a moderate productivity aquifer. Superficial deposits at the site are a low productivity aquifer. Contamination associated with the demolition of a building in the north of the site may be present at the site. The groundwater assessment point is 250m from site as the site is in a built-up area. It is likely that any contamination will be attenuated, diluted or disperse over this distance. In addition, any made ground present is likely to be a thin veneer and infiltration will not introduce significant amounts of contamination to groundwater. Based on the information available, the risk to groundwater is considered to be Low. No further work required. P3 Migration through preferential pathways P4 Migration by surface run off P2 Migration in solution through groundwater R3 Surface Water Medium Unlikely Low The nearest surface water feature is a drain 107m to the north. The nearest natural watercourse is the River Earn, 2.15km to the north east. Contamination associated with the demolition of a building in the north of the site may be present at the site. Due to the distance from site, it is unlikely that contamination will reach the surface water feature by overland flow. Based on the information available, the risk to surface water is considered to be Low. No further work required. P3 Migration through preferential pathways P4 Migration by surface run off P2 Migration in solution through groundwater R1 End Users Medium Unlikely Low Made ground and the underlying natural geology may contain hazardous ground gases that could migrate along preferential natural structures as well as man-made pathways. No plausible sources of ground gas have been identified in the vicinity of the site. The risk is considered to be Low. No further work required. P3 Migration through preferential pathways P5 Ground gas and vapour migration P2 Migration in solution through groundwater R4 Property Medium Unlikely Low Made ground and the underlying natural geology may contain contaminants that could migrate along preferential natural structures as well as man-made pathways. It is possible that made ground and natural deposits may contain sulphates and therefore present a risk to buried concrete and water pipes. At this stage, the risk to buried structures is considered to be Low. The water supplier may require full UKWIR testing which should be carried out in the construction phase. P3 Migration through preferential pathways P4 Migration by surface run off R5 Adjacent Property P5 Ground gas and vapour migration P6 Root uptake R6 Proposed Flora and Fauna Medium Low Moderate/Low The plans indicate gardens which may include vegetable planting or fruit bearing trees in soft landscaping. Contamination associated with the demolition of a building in the north of the site may be present at the site. Provided this remains the case the risk of uptake to proposed flora and fauna is Moderate/Low. Soil samples should be taken from the trial pits excavated for soakaway testing to determine the risk to proposed flora.
Page 89
20 CONCLUSIONS
Page 90
21 7. CONCLUSIONS 7.1 Conclusions Based on the information obtained and reviewed as part of this investigation and the Conceptual Site Model and Pollutant Linkage Assessment, it is concluded that the soils at the site present a potentially significant risk to site users, contractors or the wider environment and that no significant risk from off-site contamination is present at the site. The constraints to the development include: • Fine soils which are unlikely to be suitable for soakaway drainage. • Possible made ground which is unsuitable for soakaway drainage. • Contamination associated with the demolition of a building in the north of the site may be present at the site which poses a potentially significant risk to human health 7.2 Recommendations A ground investigation is recommended at the site to address the constraints identified by this desk study. Trial pits should be excavated for infiltration testing for soakaway design. Soil samples should be taken from the trial pits to determine the risk to human health and proposed flora. The scope of the investigation should be designed in conjunction with the civil engineer for the project to ensure the testing meets their requirements for soakaway design. The ground investigation should be carried out in accordance with BS5930:2015, “Code of Practice for Site Investigations” (Ref 5). Locations may need to be relocated based on the location of services – service plans have not been consulted in the design of this investigation and should be reviewed before any intrusive investigation is carried out. Chemical samples should be taken at a rate of every change of strata in the top 1.00m, with a minimum of two samples. The exact specification of the laboratory testing should be determined following the site investigation. As a minimum, the environmental testing should test for those detailed in Table 18. Table 18: Table detailing contaminants tested for during laboratory testing. Material Contaminants Soil Metals Inorganics/Other Arsenic Lead pH Aluminium Manganese Asbestos Identification Boron (Water Soluble) Mercury Cyanide, total and free Cadmium Nickel Total Organic Carbon Chromium (III and VI) Selenium Organic Matter Copper Zinc Sulphide and Sulphate as SO4 Total Phenol Speciated and Total Petroleum Hydrocarbons (TPHs) Speciated Polycyclic Aromatic Hydrocarbons (PAHs)
Page 91
22 REFERENCES
Page 92
23 8. REFERENCES 1. BRITISH GEOLOGICAL SURVEY. 1888. Crieff. Scotland Sheet 047. Drift and Solid Geology 1:50,000 (Keyworth, Nottingham: British Geological Survey). 2. British Geological Survey Lexicon Search - http://www.bgs.ac.uk/lexicon/ 3. Department of the Environment Industry Profiles. 4. Site Investigation in Construction, Volume 3, Specification for Ground Investigation 2nd Edition. 5. BS 5930:2015 Code of Practice for Site Investigations. 6. BS 8576:2013 Guidance on investigations for ground gas. Permanent gases and Volatile Organic Compounds (VOCs) 7. BS10175:2011 +A2:2017 Investigation of Potentially Contaminated Sites - Code of Practice. 8. BS 8004:2015 Code of practice for foundations 9. CIRIA C552: Contaminated land risk assessment - a guide to good practice 10. Department of the Environment: Industry Profiles, 1995. 11. Environmental Protection Act, 1990 (Amended Scotland, 2001). 12. Scottish Environmental Protection Agency: Water Classification Hub. https://www.sepa.org.uk/data-visualisation/water-classification-hub/ 13. NHBC & RSK Group Plc, March 2007. Guidance on evaluation of development proposals on sites where methane and carbon dioxide are present. Ed 4. 14. CIRIA C665 ‘Assessing Risks Posed by Hazardous Ground Gases to Buildings’ 15. British Geological Survey: Online Borehole Records. https://www.bgs.ac.uk/data/boreholescans/home.html 16. The Mining Remediation Authority: Interactive Map Viewer. https://datamine-cauk.hub.arcgis.com/ 17. MACDONALD, A.; ROBINS, N.; BALL, D. and O DOCHARTAIGH, B. E., ‘An Overview of Groundwater in Scotland’, Scottish Journal of Geology 41, 3-11 18. Department for Environment, Food and Rural Affairs Magic Map - https://magic.defra.gov.uk/MagiCMap.aspx 19. ENVIRONMENT AGENCY. Land contamination risk management (LCRM). https://www.gov.uk/government/publications/land-contamination-risk-management- lcrm, 18 November 2024
Page 93
APPENDIX I Figures Site Location Plan Site Boundary Plan Proposed Development Plan
Page 94
Boundary LEGEND
Page 95
Boundary LEGEND
Page 96
No embedded text on this page.
Page 97
APPENDIX II Groundsure Report
Page 98
Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Order Details Date: 06/03/2025 Your ref: 1853MTF Our Ref: GS-UCE-SE5-F7U-D8M Site Details Location: 286995 716587 Area: 0.05 ha Authority: Perth and Kinross Council ↗ © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Summary of findings p. 2 > OS MasterMap site plan p.12 > Aerial image p. 7 > Insight User Guide ↗ Contact us with any questions at: info@groundsure.com ↗ 01273 257 755
Page 99
Summary of findings Page Section Past land use > On site 0-50m 50-250m 250-500m 500-2000m 13 > 1.1 > Historical industrial land uses > 0 0 0 4 - 14 > 1.2 > Historical tanks > 0 0 1 0 - 14 > 1.3 > Historical energy features > 0 0 1 1 - 15 > 1.4 > Historical petrol stations > 0 0 1 0 - 15 > 1.5 > Historical garages > 0 0 0 1 - 15 1.6 Historical military land 0 0 0 0 - Page Section Past land use - un-grouped > On site 0-50m 50-250m 250-500m 500-2000m 16 > 2.1 > Historical industrial land uses > 0 0 0 5 - 17 > 2.2 > Historical tanks > 0 0 1 0 - 17 > 2.3 > Historical energy features > 0 0 2 1 - 18 > 2.4 > Historical petrol stations > 0 0 2 0 - 18 > 2.5 > Historical garages > 0 0 0 2 - Page Section Waste and landfill On site 0-50m 50-250m 250-500m 500-2000m 19 3.1 Active or recent landfill 0 0 0 0 - 19 3.2 Historical landfill (BGS records) 0 0 0 0 - 19 3.3 Historical landfill (LA/mapping records) 0 0 0 0 - 19 3.4 Licensed waste sites 0 0 0 0 - 19 3.5 Historical waste sites 0 0 0 0 - Page Section Current industrial land use > On site 0-50m 50-250m 250-500m 500-2000m 20 > 4.1 > Recent industrial land uses > 0 0 4 - - 21 > 4.2 > Current or recent petrol stations > 0 0 1 1 - 21 4.3 Electricity cables 0 0 0 0 - 21 4.4 Gas pipelines 0 0 0 0 - 21 4.5 Sites determined as Contaminated Land 0 0 0 0 - 22 4.6 Control of Major Accident Hazards (COMAH) 0 0 0 0 - 22 4.7 Regulated explosive sites 0 0 0 0 - Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 2
Page 100
22 4.8 Hazardous substance storage/usage 0 0 0 0 - 22 4.9 Part A(1), IPPC and Historic IPC Authorisations 0 0 0 0 - 22 4.10 Part B Authorisations 0 0 0 0 - 23 4.11 Pollution inventory substances 0 0 0 0 - 23 4.12 Pollution inventory waste transfers 0 0 0 0 - 23 4.13 Pollution inventory radioactive waste 0 0 0 0 - Page Section Hydrogeology On site 0-50m 50-250m 250-500m 500-2000m 24 5.1 Superficial aquifer None (within 500m) 25 > 5.2 > Bedrock aquifer > Identified (within 500m) Page Section Hydrology > On site 0-50m 50-250m 250-500m 500-2000m 26 > 6.1 > Water Network (OS MasterMap) > 0 0 9 - - 27 > 6.2 > Surface water features > 0 0 7 - - Page Section River flooding 28 7.1 River flooding Negligible (within 50m) Page Section Coastal flooding 29 8.1 Coastal flooding Negligible (within 50m) Page Section Surface water flooding 30 9.1 Surface water flooding Negligible (within 50m) Page Section Groundwater flooding > 31 > 10.1 > Groundwater flooding > Low (within 50m) Page Section Environmental designations > On site 0-50m 50-250m 250-500m 500-2000m 32 > 11.1 > Sites of Special Scientific Interest (SSSI) > 0 0 0 0 1 33 11.2 Conserved wetland sites (Ramsar sites) 0 0 0 0 0 33 11.3 Special Areas of Conservation (SAC) 0 0 0 0 0 33 11.4 Special Protection Areas (SPA) 0 0 0 0 0 33 11.5 National Nature Reserves (NNR) 0 0 0 0 0 34 11.6 Local Nature Reserves (LNR) 0 0 0 0 0 34 > 11.7 > Designated Ancient Woodland > 0 0 0 1 17 35 11.8 Biosphere Reserves 0 0 0 0 0 Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 3
Page 101
35 11.9 Forest Parks 0 0 0 0 0 35 11.10 Marine Conservation Zones 0 0 0 0 0 Page Section Visual and cultural designations > On site 0-50m 50-250m 250-500m 500-2000m 36 12.1 World Heritage Sites 0 0 0 - - 37 12.2 Area of Outstanding Natural Beauty 0 0 0 - - 37 12.3 National Parks 0 0 0 - - 37 > 12.4 > Listed Buildings > 0 0 32 - - 39 > 12.5 > Conservation Areas > 1 0 0 - - 39 12.6 Scheduled Ancient Monuments 0 0 0 - - 39 12.7 Registered Parks and Gardens 0 0 0 - - Page Section Agricultural designations > On site 0-50m 50-250m 250-500m 500-2000m 41 > 13.1 > Agricultural Land Classification > Grade 3.2 (within 250m) Page Section Geology 1:10,000 scale > On site 0-50m 50-250m 250-500m 500-2000m 42 > 14.1 > 10k Availability > Identified (within 500m) 43 14.2 Artificial and made ground (10k) 0 0 0 0 - 44 14.3 Superficial geology (10k) 0 0 0 0 - 44 14.4 Landslip (10k) 0 0 0 0 - 45 14.5 Bedrock geology (10k) 0 0 0 0 - 45 14.6 Bedrock faults and other linear features (10k) 0 0 0 0 - Page Section Geology 1:50,000 scale > On site 0-50m 50-250m 250-500m 500-2000m 46 > 15.1 > 50k Availability > Identified (within 500m) 47 15.2 Artificial and made ground (50k) 0 0 0 0 - 47 15.3 Artificial ground permeability (50k) 0 0 - - - 48 > 15.4 > Superficial geology (50k) > 1 0 0 0 - 49 > 15.5 > Superficial permeability (50k) > Identified (within 50m) 49 15.6 Landslip (50k) 0 0 0 0 - 49 15.7 Landslip permeability (50k) None (within 50m) 50 > 15.8 > Bedrock geology (50k) > 1 0 0 0 - 51 > 15.9 > Bedrock permeability (50k) > Identified (within 50m) Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 4
Page 102
51 15.10 Bedrock faults and other linear features (50k) 0 0 0 0 - Page Section Boreholes On site 0-50m 50-250m 250-500m 500-2000m 52 16.1 BGS Boreholes 0 0 0 - - Page Section Natural ground subsidence > 53 > 17.1 > Shrink swell clays > Very low (within 50m) 54 > 17.2 > Running sands > Very low (within 50m) 55 > 17.3 > Compressible deposits > Negligible (within 50m) 56 > 17.4 > Collapsible deposits > Very low (within 50m) 57 > 17.5 > Landslides > Very low (within 50m) 58 > 17.6 > Ground dissolution of soluble rocks > Negligible (within 50m) Page Section Mining and ground workings > On site 0-50m 50-250m 250-500m 500-2000m 60 18.1 BritPits 0 0 0 0 - 61 18.2 Surface ground workings 0 0 0 - - 61 18.3 Underground workings 0 0 0 0 0 61 18.4 Underground mining extents 0 0 0 0 - 61 18.5 Historical Mineral Planning Areas 0 0 0 0 - 61 > 18.6 > Non-coal mining > 1 0 0 0 0 62 18.7 JPB mining areas None (within 0m) 62 18.8 The Coal Authority non-coal mining 0 0 0 0 - 62 18.9 Researched mining 0 0 0 0 - 63 18.10 Mining record office plans 0 0 0 0 - 63 18.11 BGS mine plans 0 0 0 0 - 63 18.12 Coal mining None (within 0m) 63 18.13 Brine areas None (within 0m) 63 18.14 Gypsum areas None (within 0m) 64 18.15 Tin mining None (within 0m) 64 18.16 Clay mining None (within 0m) Page Section Ground cavities and sinkholes On site 0-50m 50-250m 250-500m 500-2000m 65 19.1 Natural cavities 0 0 0 0 - Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 5
Page 103
65 19.2 Mining cavities 0 0 0 0 0 65 19.3 Reported recent incidents 0 0 0 0 - 65 19.4 Historical incidents 0 0 0 0 - Page Section Radon > 67 > 20.1 > Radon > Less than 1% (within 0m) Page Section Soil chemistry > On site 0-50m 50-250m 250-500m 500-2000m 69 > 21.1 > BGS Estimated Background Soil Chemistry > 2 0 - - - 69 21.2 BGS Estimated Urban Soil Chemistry 0 0 - - - 69 21.3 BGS Measured Urban Soil Chemistry 0 0 - - - Page Section Railway infrastructure and projects On site 0-50m 50-250m 250-500m 500-2000m 70 22.1 Underground railways (London) 0 0 0 - - 70 22.2 Underground railways (Non-London) 0 0 0 - - 70 22.3 Railway tunnels 0 0 0 - - 70 22.4 Historical railway and tunnel features 0 0 0 - - 70 22.5 Royal Mail tunnels 0 0 0 - - 71 22.6 Historical railways 0 0 0 - - 71 22.7 Railways 0 0 0 - - 71 22.8 Crossrail 2 0 0 0 0 - 71 22.9 HS2 0 0 0 0 - Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 6
Page 104
Recent aerial photograph N Aerial photography supplied by Getmapping PLC. © Copyright Getmapping PLC 2025. All Rights Reserved. Capture Date: 20/04/2023 Site Area: 0.05ha Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 7
Page 105
Recent site history - 2020 aerial photograph N Aerial photography supplied by Getmapping PLC. © Copyright Getmapping PLC 2025. All Rights Reserved. Capture Date: 01/06/2020 Site Area: 0.05ha Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 8
Page 106
Recent site history - 2010 aerial photograph N Aerial photography supplied by Getmapping PLC. © Copyright Getmapping PLC 2025. All Rights Reserved. Capture Date: 20/10/2010 Site Area: 0.05ha Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 9
Page 107
Recent site history - 2005 aerial photograph N Aerial photography supplied by Getmapping PLC. © Copyright Getmapping PLC 2025. All Rights Reserved. Capture Date: 14/05/2005 Site Area: 0.05ha Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 10
Page 108
Recent site history - 2001 aerial photograph N Aerial photography supplied by Getmapping PLC. © Copyright Getmapping PLC 2025. All Rights Reserved. Capture Date: 17/09/2001 Site Area: 0.05ha Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 11
Page 109
OS MasterMap site plan N © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Area: 0.05ha Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 12
Page 110
1 Past land use © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Historical industrial land uses Historical tanks Historical energy features Historical petrol stations Historical garages 1.1 Historical industrial land uses Records within 500m 4 Potentially contaminative land use features digitised from historical Ordnance Survey mapping at 1:10,000 and 1:10,560 scale, intelligently grouped into contiguous features. To prevent misrepresentation of the size of historical features at any given time, features are only grouped if they have similar geometries within immediately preceding or succeeding map editions. See section 2 for a breakdown of grouping if required. Grouped and the original un-grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use map on page 13 > ID Location Land use Dates present Group ID 4 268m W Telephone Exchange 1973 84244 Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 13
Page 111
ID Location Land use Dates present Group ID 6 379m N Police Station 1973 84295 7 416m NW Nursery 1864 83130 8 420m E Cemetery 1954 - 1973 87164 This data is sourced from Ordnance Survey / Groundsure. 1.2 Historical tanks Records within 500m 1 Tank features digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale, intelligently grouped into contiguous features. To prevent misrepresentation of the size of historical features at any given time, features are only grouped if they have similar geometries within immediately preceding or succeeding map editions. See section 2 for a breakdown of grouping if required. Grouped and the original un- grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use map on page 13 > ID Location Land use Dates present Group ID 3 211m N Unspecified Tank 1971 8690 This data is sourced from Ordnance Survey / Groundsure. 1.3 Historical energy features Records within 500m 2 Energy features digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale, intelligently grouped into contiguous features. To prevent misrepresentation of the size of historical features at any given time, features are only grouped if they have similar geometries within immediately preceding or succeeding map editions. See section 2 for a breakdown of grouping if required. Grouped and the original un- grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use map on page 13 > ID Location Land use Dates present Group ID 2 130m S Electricity Substation 1971 4567 9 458m NW Electricity Substation 1971 4275 This data is sourced from Ordnance Survey / Groundsure. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 14
Page 112
1.4 Historical petrol stations Records within 500m 1 Petrol stations digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale, intelligently grouped into contiguous features. To prevent misrepresentation of the size of historical features at any given time, features are only grouped if they have similar geometries within immediately preceding or succeeding map editions. See section 2 for a breakdown of grouping if required. Grouped and the original un- grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use map on page 13 > ID Location Land use Dates present Group ID 1 60m N Filling Station 1971 293 This data is sourced from Ordnance Survey / Groundsure. 1.5 Historical garages Records within 500m 1 Garages digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale, intelligently grouped into contiguous features. To prevent misrepresentation of the size of historical features at any given time, features are only grouped if they have similar geometries within immediately preceding or succeeding map editions. See section 2 for a breakdown of grouping if required. Grouped and the original un- grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use map on page 13 > ID Location Land use Dates present Group ID 5 310m NW Garage 1971 1482 This data is sourced from Ordnance Survey / Groundsure. 1.6 Historical military land Records within 500m 0 Areas of military land digitised from multiple sources including the National Archives, local records, MOD records and verified other sources, intelligently grouped into contiguous features. This data is sourced from Ordnance Survey / Groundsure / other sources. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 15
Page 113
2 Past land use - un-grouped © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Historical industrial land uses Historical tanks Historical energy features Historical petrol stations Historical garages 2.1 Historical industrial land uses Records within 500m 5 Potentially contaminative land use features digitised from historical Ordnance Survey mapping at 1:10,000 and 10,560 scale. Any records shown are available intelligently grouped in section 1. Grouped and the original un- grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use - un-grouped map on page 16 > ID Location Land Use Date Group ID 2 268m W Telephone Exchange 1973 84244 3 379m N Police Station 1973 84295 4 416m NW Nursery 1864 83130 Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 16
Page 114
ID Location Land Use Date Group ID D 420m E Cemetery 1973 87164 D 420m E Cemetery 1954 87164 This data is sourced from Ordnance Survey / Groundsure. 2.2 Historical tanks Records within 500m 1 Tank features digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale. Any records shown are available intelligently grouped in section 1. Grouped and the original un-grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use - un-grouped map on page 16 > ID Location Land Use Date Group ID 1 211m N Unspecified Tank 1971 8690 This data is sourced from Ordnance Survey / Groundsure. 2.3 Historical energy features Records within 500m 3 Energy features digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale. Any records shown are available intelligently grouped in section 1. Grouped and the original un-grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use - un-grouped map on page 16 > ID Location Land Use Date Group ID B 130m S Electricity Substation 1971 4567 B 131m S Electricity Substation 1971 4567 5 458m NW Electricity Substation 1971 4275 This data is sourced from Ordnance Survey / Groundsure. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 17
Page 115
2.4 Historical petrol stations Records within 500m 2 Petrol stations digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale. Any records shown are available intelligently grouped in section 1. Grouped and the original un-grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use - un-grouped map on page 16 > ID Location Land Use Date Group ID A 60m N Filling Station 1971 293 A 62m N Filling Station 1971 293 This data is sourced from Ordnance Survey / Groundsure. 2.5 Historical garages Records within 500m 2 Garages digitised from historical Ordnance Survey mapping at high-detail 1:1,250 and 1:2,500 scale. Any records shown are available intelligently grouped in section 1. Grouped and the original un-grouped features can be cross-referenced across sections 1 and 2 using the 'Group ID'. Features are displayed on the Past land use - un-grouped map on page 16 > ID Location Land Use Date Group ID C 310m NW Garage 1971 1482 C 312m NW Garage 1971 1482 This data is sourced from Ordnance Survey / Groundsure. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 18
Page 116
3 Waste and landfill 3.1 Active or recent landfill Records within 500m 0 Active or recently closed landfill sites under Scottish Environment Protection (SEPA) regulation. This data is sourced from the Scottish Environment Protection Agency. 3.2 Historical landfill (BGS records) Records within 500m 0 Landfill sites identified on a survey carried out on behalf of the DoE in 1973. These sites may have been closed or operational at this time. This data is sourced from the British Geological Survey. 3.3 Historical landfill (LA/mapping records) Records within 500m 0 Landfill sites identified from Local Authority records and high detail historical mapping. This data is sourced from the Ordnance Survey/Groundsure and Local Authority records. 3.4 Licensed waste sites Records within 500m 0 Active or recently closed waste sites under Scottish Environment Protection Acency (SEPA) regulation. This data is sourced from the Scottish Environment Protection Agency. 3.5 Historical waste sites Records within 500m 0 Waste site records derived from Local Authority planning records and high detail historical mapping. This data is sourced from Ordnance Survey/Groundsure and Local Authority records. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 19
Page 117
4 Current industrial land use © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Recent industrial land uses Current or recent petrol stations 4.1 Recent industrial land uses Records within 250m 4 Current potentially contaminative industrial sites. Features are displayed on the Current industrial land use map on page 20 > ID Location Company Address Activity Category A 74m N Viewfield Garage Willoughby Street, Muthill, Crieff, Perth and Kinross, PH5 2AE Petrol and Fuel Stations Road and Rail A 75m N Sweeneys Garage 103, Willoughby Street, Muthill, Crieff, Perth and Kinross, PH5 2AE Vehicle Repair, Testing and Servicing Repair and Servicing A 75m N Viewfield Garage 103-105, Willoughby Street, Muthill, Crieff, Perth & Kinross, Perth and Kinross, PH5 2AE Vehicle Cleaning Services Personal, Consumer and Other Services Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 20
Page 118
ID Location Company Address Activity Category 1 131m S Electricity Sub Station Perth and Kinross, PH5 Electrical Features Infrastructure and Facilities This data is sourced from Ordnance Survey. 4.2 Current or recent petrol stations Records within 500m 2 Open, closed, under development and obsolete petrol stations. Features are displayed on the Current industrial land use map on page 20 > ID Location Company Address LPG Status A 72m N UNBRANDE D 103-105, Willoughby Street, Muthill, Crieff, Perth & Kinross, PH5 2AE No Open 2 285m NW UNBRANDE D 1, Thornhill Street, Muthill, Crieff, Perth & Kinross, PH5 2AD Not Applicable Obsolete This data is sourced from Experian. 4.3 Electricity cables Records within 500m 0 High voltage underground electricity transmission cables. This data is sourced from National Grid. 4.4 Gas pipelines Records within 500m 0 High pressure underground gas transmission pipelines. This data is sourced from National Grid. 4.5 Sites determined as Contaminated Land Records within 500m 0 Contaminated Land Register of sites designated under Part 2a of the Environmental Protection Act 1990. This data is sourced from Local Authority records. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 21
Page 119
4.6 Control of Major Accident Hazards (COMAH) Records within 500m 0 Control of Major Accident Hazards (COMAH) sites. This data includes upper and lower tier sites, and includes a historical archive of COMAH sites and Notification of Installations Handling Hazardous Substances (NIHHS) records. This data is sourced from the Health and Safety Executive. 4.7 Regulated explosive sites Records within 500m 0 Sites registered and licensed by the Health and Safety Executive under the Manufacture and Storage of Explosives Regulations 2005 (MSER). The last update to this data was in April 2011. This data is sourced from the Health and Safety Executive. 4.8 Hazardous substance storage/usage Records within 500m 0 Consents granted for a site to hold certain quantities of hazardous substances at or above defined limits in accordance with the Planning (Hazardous Substances) Regulations 2015. This data is sourced from Local Authority records. 4.9 Part A(1), IPPC and Historic IPC Authorisations Records within 500m 0 Records of Part A installations regulated for the release of substances to the environment. This data is sourced from the Scottish Environment Protection Agency. 4.10 Part B Authorisations Records within 500m 0 Records of Part B installations regulated for the release of substances to the environment. This data is sourced from the Scottish Environment Protection Agency. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 22
Page 120
4.11 Pollution inventory substances Records within 500m 0 The pollution inventory (substances) includes reporting on annual emissions of certain regulated substances to air, controlled waters and land. A reporting threshold for each substance is also included. Where emissions fall below the reporting threshold, no value will be given. The data is given for the most recent complete year available. This data is sourced from the Environment Agency and the Scottish Environment Protection Agency. 4.12 Pollution inventory waste transfers Records within 500m 0 The pollution inventory (waste transfers) includes reporting on annual transfers and recovery/disposal of controlled wastes from a site. A reporting threshold for each waste type is also included. Where releases fall below the reporting threshold, no value will be given. The data is given for the most recent complete year available. This data is sourced from the Environment Agency and the Scottish Environment Protection Agency. 4.13 Pollution inventory radioactive waste Records within 500m 0 The pollution inventory (radioactive wastes) includes reporting on annual releases of radioactive substances from a site, including the means of release. Where releases fall below the reporting threshold, no value will be given. The data is given for the most recent complete year available. This data is sourced from the Environment Agency and the Scottish Environment Protection Agency. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 23
Page 121
5 Hydrogeology - Superficial aquifer 5.1 Superficial aquifer Records within 500m 0 Records of groundwater classification within superficial geology. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 24
Page 122
Bedrock aquifer © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Highly productive - fissures/discontinuities Highly productive - intergranular Moderately productive - fissures/discontinuities Moderately productive - intergranular Low productive - fissures/discontinuities Low productive - intergranular No significant groundwater 5.2 Bedrock aquifer Records within 500m 1 Records of groundwater classification within bedrock geology. Features are displayed on the Bedrock aquifer map on page 25 > ID Location Description Flow Summary Rock descriptio n 1 On site Moderately productive aquifer Flow is virtually all through fractures and other discontinuities Sandstones, in places flaggy, with siltstones, mudstones and conglomerates and interbedded lavas locally yield up to 12 L/s in parts of Strathmore. STRATHM ORE GROUP This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 25
Page 123
6 Hydrology © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Water Network (OS MasterMap) Surface water features (wider than 5m) Surface water features (narrower than 5m) 6.1 Water Network (OS MasterMap) Records within 250m 9 Detailed water network of Great Britain showing the flow and precise central course of every river, stream, lake and canal. Features are displayed on the Hydrology map on page 26 > ID Location Type of water feature Ground level Permanence Name A 107m NE Inland river not influenced by normal tidal action. On ground surface Watercourse contains water year round (in normal circumstances) - Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 26
Page 124
ID Location Type of water feature Ground level Permanence Name A 169m NE Inland river not influenced by normal tidal action. Underground Watercourse contains water year round (in normal circumstances) - A 172m NE Inland river not influenced by normal tidal action. On ground surface Watercourse contains water year round (in normal circumstances) - B 201m NW Inland river not influenced by normal tidal action. On ground surface Watercourse contains water year round (in normal circumstances) - C 203m E Inland river not influenced by normal tidal action. On ground surface Watercourse contains water year round (in normal circumstances) - B 210m NW Inland river not influenced by normal tidal action. On ground surface Watercourse contains water year round (in normal circumstances) - 1 211m E Inland river not influenced by normal tidal action. Underground Watercourse contains water year round (in normal circumstances) - D 214m E Inland river not influenced by normal tidal action. On ground surface Watercourse contains water year round (in normal circumstances) - B 243m NW Inland river not influenced by normal tidal action. On ground surface Watercourse contains water year round (in normal circumstances) - This data is sourced from the Ordnance Survey. 6.2 Surface water features Records within 250m 7 Covering rivers, streams and lakes (some overlap with OS MasterMap Water Network data in previous section) but additionally covers smaller features such as ponds. Rivers and streams narrower than 5m are represented as a single line. Lakes, ponds and rivers or streams wider than 5m are represented as polygons. Features are displayed on the Hydrology map on page 26 > This data is sourced from the Ordnance Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 27
Page 125
7 River flooding 7.1 River flooding Highest risk on site Negligible Highest risk within 50m Negligible This is an assessment of flood risk for rivers in Scotland produced using modelled data, provided by Ambiental Risk Analytics. It also takes account of flood defence information provided by the Scottish Environment Protection Agency (SEPA). It shows the chance of flooding from rivers presented in the following categories: 1 in 30 year (3.33%) 1 in 100 year (1%) 1 in 250 year (0.4%) and 1 in 1,000 year (0.1%) The data shown on the map and in the table above shows the highest likelihood of flood events happening at the site. Lower likelihood events may have greater flood depths and hence a greater potential impact on a site. The table below shows the maximum flood depths for a range of return periods for the site. Return period Maximum modelled depth 1 in 1000 year Negligible 1 in 250 year Negligible 1 in 100 year Negligible 1 in 30 year Negligible This data is sourced from Ambiental Risk Analytics. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 28
Page 126
8 Coastal flooding - Coastal flooding 8.1 Coastal flooding Highest risk on site Negligible Highest risk within 50m Negligible This is an assessment of coastal flood risk in Scotland produced using modelled data, provided by Ambiental Risk Analytics. It also takes account of flood defence information provided by the Scottish Environment Protection Agency (SEPA). It shows the chance of coastal flooding presented in the following categories: 1 in 30 year (3.33%) 1 in 100 year (1%) 1 in 250 year (0.4%) and 1 in 1,000 year (0.1%) The data shown on the map shows the highest likelihood of flood events happening at the site. Lower likelihood events may have greater flood depths and hence a greater potential impact on a site. The table below shows the maximum flood depths for a range of return periods for the site. Return period Maximum modelled depth 1 in 1000 year Negligible 1 in 250 year Negligible 1 in 100 year Negligible 1 in 30 year Negligible This data is sourced from Ambiental Risk Analytics. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 29
Page 127
9 Surface water flooding 9.1 Surface water flooding Highest risk on site Negligible Highest risk within 50m Negligible Ambiental Risk Analytics surface water (pluvial) FloodMap identifies areas likely to flood as a result of extreme rainfall events, i.e. land naturally vulnerable to surface water ponding or flooding. This data set was produced by simulating 1 in 30 year, 1 in 100 year, 1 in 250 year and 1 in 1,000 year rainfall events. Modern urban drainage systems are typically built to cope with rainfall events between 1 in 20 and 1 in 30 years, though some older ones may flood in a 1 in 5 year rainfall event. The data shown on the map and in the table above shows the highest likelihood of flood events happening at the site. Lower likelihood events may have greater flood depths and hence a greater potential impact on a site. The table below shows the maximum flood depths for a range of return periods for the site. Return period Maximum modelled depth 1 in 1000 year Negligible 1 in 250 year Negligible 1 in 100 year Negligible 1 in 30 year Negligible This data is sourced from Ambiental Risk Analytics. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 30
Page 128
10 Groundwater flooding © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) High Moderate - High Moderate Low Negligible 10.1 Groundwater flooding Highest risk on site Low Highest risk within 50m Low Groundwater flooding is caused by unusually high groundwater levels. It occurs when the water table rises above the ground surface or within underground structures such as basements or cellars. Groundwater flooding tends to exhibit a longer duration than surface water flooding, possibly lasting for weeks or months, and as a result it can cause significant damage to property. This risk assessment is based on a 1 in 100 year return period and a 5m Digital Terrain Model (DTM). Features are displayed on the Groundwater flooding map on page 31 > This data is sourced from Ambiental Risk Analytics. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 31
Page 129
11 Environmental designations © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Sites of Special Scientific Interest (SSSI) Designated Ancient Woodland 11.1 Sites of Special Scientific Interest (SSSI) Records within 2000m 1 Sites providing statutory protection for the best examples of UK flora, fauna, or geological or physiographical features. Originally notified under the National Parks and Access to the Countryside Act 1949, SSSIs were re- notified under the Wildlife and Countryside Act 1981. Improved provisions for the protection and management of SSSIs were introduced by the Countryside and Rights of Way Act 2000 (in England and Wales) and (in Scotland) by the Nature Conservation (Scotland) Act 2004 and the Wildlife and Natural Environment (Scotland) Act 2010. Features are displayed on the Environmental designations map on page 32 > ID Location Name Data source - 1817m NW Drummond Lochs Scottish Natural Heritage Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 32
Page 130
This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 11.2 Conserved wetland sites (Ramsar sites) Records within 2000m 0 Ramsar sites are designated under the Convention on Wetlands of International Importance, agreed in Ramsar, Iran, in 1971. They cover all aspects of wetland conservation and wise use, recognizing wetlands as ecosystems that are extremely important for biodiversity conservation in general and for the well-being of human communities. These sites cover a broad definition of wetland; marsh, fen, peatland or water, whether natural or artificial, permanent or temporary, with water that is static or flowing, fresh, brackish or salt, and even some marine areas. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 11.3 Special Areas of Conservation (SAC) Records within 2000m 0 Areas which have been identified as best representing the range and variety within the European Union of habitats and (non-bird) species listed on Annexes I and II to the Directive. SACs are designated under the EC Habitats Directive. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 11.4 Special Protection Areas (SPA) Records within 2000m 0 Sites classified by the UK Government under the EC Birds Directive, SPAs are areas of the most important habitat for rare (listed on Annex I to the Directive) and migratory birds within the European Union. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 11.5 National Nature Reserves (NNR) Records within 2000m 0 Sites containing examples of some of the most important natural and semi-natural terrestrial and coastal ecosystems in Great Britain. They are managed to conserve their habitats, provide special opportunities for scientific study or to provide public recreation compatible with natural heritage interests. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 33
Page 131
11.6 Local Nature Reserves (LNR) Records within 2000m 0 Sites managed for nature conservation, and to provide opportunities for research and education, or simply enjoying and having contact with nature. They are declared by local authorities under the National Parks and Access to the Countryside Act 1949 after consultation with the relevant statutory nature conservation agency. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 11.7 Designated Ancient Woodland Records within 2000m 18 Ancient woodlands are classified as areas which have been wooded continuously since at least 1600 AD. This includes semi-natural woodland and plantations on ancient woodland sites. 'Wooded continuously' does not mean there is or has previously been continuous tree cover across the whole site, and not all trees within the woodland have to be old. Features are displayed on the Environmental designations map on page 32 > ID Location Name Woodland Type 1 305m SE Muir Of Spot Wood Long-Established (of plantation origin) 2 528m SW Unknown Long-Established (of plantation origin) 3 621m E Unknown Long-Established (of plantation origin) 4 707m S Barnes Wood Long-Established (of plantation origin) 5 723m SW Newra Wood Long-Established (of plantation origin) 6 760m N Wood Of Muthill Long-Established (of plantation origin) 7 995m NE Sallyardoch Wood Long-Established (of plantation origin) 8 1195m W Unknown Long-Established (of plantation origin) 9 1253m SE Unknown Long-Established (of plantation origin) - 1341m W Newra Wood Long-Established (of plantation origin) - 1372m E Pirnhall Plantation Long-Established (of plantation origin) - 1450m S Upper Lairochs Wood Long-Established (of plantation origin) - 1544m S Lower Lairochs Wood Long-Established (of plantation origin) - 1681m N Unknown Long-Established (of plantation origin) - 1802m SE Crofthead/drumness Woods Long-Established (of plantation origin) - 1814m W Anmore Wood Long-Established (of plantation origin) Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 34
Page 132
ID Location Name Woodland Type - 1887m NE Unknown Long-Established (of plantation origin) - 1915m N Unknown Long-Established (of plantation origin) This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 11.8 Biosphere Reserves Records within 2000m 0 Biosphere Reserves are internationally recognised by UNESCO as sites of excellence to balance conservation and socioeconomic development between nature and people. They are recognised under the Man and the Biosphere (MAB) Programme with the aim of promoting sustainable development founded on the work of the local community. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 11.9 Forest Parks Records within 2000m 0 These are areas managed by the Forestry Commission designated on the basis of recreational, conservation or scenic interest. This data is sourced from the Forestry Commission. 11.10 Marine Conservation Zones Records within 2000m 0 A type of marine nature reserve in UK waters established under the Marine and Coastal Access Act (2009). They are designated with the aim to protect nationally important, rare or threatened habitats and species. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 35
Page 133
12 Visual and cultural designations © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Listed buildings Conservation areas Conservation areas - no data Registered parks and gardens National Parks Areas of Outstanding Natural Beauty Scheduled Monuments World Heritage Sites 12.1 World Heritage Sites Records within 250m 0 Sites designated for their globally important cultural or natural interest requiring appropriate management and protection measures. World Heritage Sites are designated to meet the UK's commitments under the World Heritage Convention. This data is sourced from Historic England, Cadw and Historic Environment Scotland. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 36
Page 134
12.2 Area of Outstanding Natural Beauty Records within 250m 0 Areas of Outstanding Natural Beauty (AONB) are conservation areas, chosen because they represent 18% of the finest countryside. Each AONB has been designated for special attention because of the quality of their flora, fauna, historical and cultural associations, and/or scenic views. The National Parks and Access to the Countryside Act of 1949 created AONBs and the Countryside and Rights of Way Act, 2000 added further regulation and protection. There are likely to be restrictions to some developments within these areas. This data is sourced from Natural England, Natural Resources Wales and Scottish Natural Heritage. 12.3 National Parks Records within 250m 0 In England and Wales, the purpose of National Parks is to conserve and enhance landscapes within the countryside whilst promoting public enjoyment of them and having regard for the social and economic well- being of those living within them. In Scotland National Parks have the additional purpose of promoting the sustainable use of the natural resources of the area and the sustainable social and economic development of its communities. The National Parks and Access to the Countryside Act 1949 established the National Park designation in England and Wales, and The National Parks (Scotland) Act 2000 in Scotland. This data is sourced from Natural England, Natural Resources Wales and the Scottish Government. 12.4 Listed Buildings Records within 250m 32 Buildings listed for their special architectural or historical interest. Building control in the form of 'listed building consent' is required in order to make any changes to that building which might affect its special interest. Listed buildings are graded to indicate their relative importance, however building controls apply to all buildings equally, irrespective of their grade, and apply to the interior and exterior of the building in its entirety, together with any curtilage structures. Features are displayed on the Visual and cultural designations map on page 36 > ID Location Name Grade Reference Number Listed date A 52m NW Far Hills, Willoughby Street, Muthill, Perth And Kinross C 352102 05/10/1971 A 65m NW Willoughby House, Willoughby Street, Muthill, Perth And Kinross B 352055 05/10/1971 A 74m NW Dunbrae, Willoughby Street, Muthill, Perth And Kinross C 352056 05/10/1971 A 78m NW Viewfield, Willoughby Street, Muthill, Perth And Kinross C 352101 05/10/1971 A 81m NW Bayton, Willoughby Street, Muthill, Perth And Kinross C 352057 05/10/1971 Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 37
Page 135
ID Location Name Grade Reference Number Listed date A 89m NW Rona, Willoughby Street, Muthill, Perth And Kinross C 352100 05/10/1971 A 92m NW Dunbett, Willoughby Street, Muthill, Perth And Kinross C 352099 05/10/1971 A 94m NW Arrascote, Willoughby Street, Muthill, Perth And Kinross C 352058 05/10/1971 A 99m NW Myrtle Cottage, Willoughby Street, Muthill, Perth And Kinross C 352059 05/10/1971 A 101m NW Cottage Claire, 97 Willoughby Street, Muthill, Perth And Kinross C 352097 05/10/1971 A 105m NW Belmont, 95 Willoughby Street, Muthill, Perth And Kinross C 352098 05/10/1971 A 106m NW Leanna Cottage, Willoughby Street, Muthill, Perth And Kinross C 352060 05/10/1971 A 118m NW Ingleneuk, Willoughby Street, Muthill, Perth And Kinross C 352061 05/10/1971 A 135m NW Auchindair, Willoughby Street, Muthill, Perth And Kinross C 352062 05/10/1971 A 139m NW Greenbrae East And West, Pitkellony Street, Muthill, Perth And Kinross C 352063 05/10/1971 A 140m NW Glenorchy, 85 Willoughby Street, Muthill, Perth And Kinross C 352096 05/10/1971 A 148m NW 83 Willoughby Street, Muthill, Perth And Kinross C 352095 05/10/1971 A 158m NW Crossways, Pitkellony Street, Muthill, Perth And Kinross B 352064 05/10/1971 A 167m NW St John's Cottage, 81 Willoughby Street, Muthill, Perth And Kinross C 352094 05/10/1971 A 171m NW Oak Cottage, Pitkellony Street, Muthill, Perth And Kinross C 352065 05/10/1971 A 172m NW Parkview, 79 Willoughby Street, Muthill, Perth And Kinross C 352093 05/10/1971 A 173m NW Dog Head Well, Highlandman's Park, Muthill, Perth And Kinross B 352068 05/10/1971 A 181m NW Birch Cottage, Pitkellony Street, Muthill, Perth And Kinross C 352066 05/10/1971 A 186m NW 75-77 Willoughby Street, Muthill, Perth And Kinross C 352092 05/10/1971 A 189m NW House, Pitkellony Street, Muthill, Perth And Kinross C 352067 05/10/1971 A 199m NW Little Culdees, 73 Willoughby Street, Muthill, Perth And Kinross B 352091 05/10/1971 A 216m NW Park House, 71 Willoughby Street, Muthill, Perth And Kinross C 352090 05/10/1971 1 219m NW Retaining Wall And Dyke, Highlandman's Park, Muthill, Perth And Kinross C 352069 05/10/1971 A 221m NW Greenfield House, 67-69 Willoughby Street, Muthill, Perth And Kinross C 352089 05/10/1971 Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 38
Page 136
ID Location Name Grade Reference Number Listed date 2 228m W The Croft, Muthill, Perth And Kinross B 352070 05/10/1971 A 242m NW Struthill, 65 Willoughby Street, Muthill, Perth And Kinross C 352088 05/10/1971 A 246m NW Newra House, Willoughby Street, Muthill, Perth And Kinross C 352087 05/10/1971 This data is sourced from Historic England, Cadw and Historic Environment Scotland. 12.5 Conservation Areas Records within 250m 1 Local planning authorities are obliged to designate as conservation areas any parts of their own area that are of special architectural or historic interest, the character and appearance of which it is desirable to preserve or enhance. Designation of a conservation area gives broader protection than the listing of individual buildings. All the features within the area, listed or otherwise, are recognised as part of its character. Conservation area designation is the means of recognising the importance of all factors and of ensuring that planning decisions address the quality of the landscape in its broadest sense. Features are displayed on the Visual and cultural designations map on page 36 > ID Location Name District Date of designation A On site MUTHILL PERTH & KINROSS 2010-11-26 This data is sourced from Historic England, Cadw and Historic Environment Scotland. 12.6 Scheduled Ancient Monuments Records within 250m 0 A scheduled monument is an historic building or site that is included in the Schedule of Monuments kept by the Secretary of State for Digital, Culture, Media and Sport. The regime is set out in the Ancient Monuments and Archaeological Areas Act 1979. The Schedule of Monuments has c.20,000 entries and includes sites such as Roman remains, burial mounds, castles, bridges, earthworks, the remains of deserted villages and industrial sites. Monuments are not graded, but all are, by definition, considered to be of national importance. This data is sourced from Historic England, Cadw and Historic Environment Scotland. 12.7 Registered Parks and Gardens Records within 250m 0 Parks and gardens assessed to be of particular interest and of special historic interest. The emphasis being on 'designed' landscapes, rather than on planting or botanical importance. Registration is a 'material consideration' in the planning process, meaning that planning authorities must consider the impact of any Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 39
Page 137
proposed development on the special character of the landscape. This data is sourced from Historic England, Cadw and Historic Environment Scotland. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 40
Page 138
13 Agricultural designations © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Grade 1 - excellent quality Grade 2 - very good quality Grade 3 - good to moderate quality Grade 4 - good quality Grade 5 - moderate quality Grade 6 - poor quality Grade 7 - very poor quality 13.1 Agricultural Land Classification Records within 250m 2 Classification of the quality of agricultural land taking into consideration multiple factors inclusing climate, physical geography and soil properties. It should be noted that the categories for the grading of agricultural land are not consistent across England, Wales and Scotland. Features are displayed on the Agricultural designations map on page 41 > ID Location Classification Description 1 On site Grade 3.1 Land Suited to Arable Cropping 3 43m S Grade 3.2 Land Suited to Arable Cropping This data is sourced from the James Hutton Institute. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 41
Page 139
14 Geology 1:10,000 scale - Availability © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Full coverage Partial coverage No coverage 14.1 10k Availability Records within 500m 1 An indication on the coverage of 1:10,000 scale geology data for the site, the most detailed dataset provided by the British Geological Survey. Either 'Full', 'Partial' or 'No coverage' for each geological theme. Features are displayed on the Geology 1:10,000 scale - Availability map on page 42 > ID Location Artificial Superficial Bedrock Mass movement Sheet No. 1 On site No coverage No coverage No coverage No coverage NoCov This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 42
Page 140
Geology 1:10,000 scale - Artificial and made ground 14.2 Artificial and made ground (10k) Records within 500m 0 Details of made, worked, infilled, disturbed and landscaped ground at 1:10,000 scale. Artificial ground can be associated with potentially contaminated material, unpredictable engineering conditions and instability. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 43
Page 141
Geology 1:10,000 scale - Superficial 14.3 Superficial geology (10k) Records within 500m 0 Superficial geological deposits at 1:10,000 scale. Also known as 'drift', these are the youngest geological deposits, formed during the Quaternary. They rest on older deposits or rocks referred to as bedrock. This data is sourced from the British Geological Survey. 14.4 Landslip (10k) Records within 500m 0 Mass movement deposits on BGS geological maps at 1:10,000 scale. Primarily superficial deposits that have moved down slope under gravity to form landslips. These affect bedrock, other superficial deposits and artificial ground. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 44
Page 142
Geology 1:10,000 scale - Bedrock 14.5 Bedrock geology (10k) Records within 500m 0 Bedrock geology at 1:10,000 scale. The main mass of rocks forming the Earth and present everywhere, whether exposed at the surface in outcrops or concealed beneath superficial deposits or water. This data is sourced from the British Geological Survey. 14.6 Bedrock faults and other linear features (10k) Records within 500m 0 Linear features at the ground or bedrock surface at 1:10,000 scale of six main types; rock, fault, fold axis, mineral vein, alteration area or landform. Features are either observed or inferred, and relate primarily to bedrock. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 45
Page 143
15 Geology 1:50,000 scale - Availability © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Geological map tile 15.1 50k Availability Records within 500m 1 An indication on the coverage of 1:50,000 scale geology data for the site. Either 'Full' or 'No coverage' for each geological theme. Features are displayed on the Geology 1:50,000 scale - Availability map on page 46 > ID Location Artificial Superficial Bedrock Mass movement Sheet No. 1 On site No coverage Full Full No coverage SC047_Crieff_v4 This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 46
Page 144
Geology 1:50,000 scale - Artificial and made ground 15.2 Artificial and made ground (50k) Records within 500m 0 Details of made, worked, infilled, disturbed and landscaped ground at 1:50,000 scale. Artificial ground can be associated with potentially contaminated material, unpredictable engineering conditions and instability. This data is sourced from the British Geological Survey. 15.3 Artificial ground permeability (50k) Records within 50m 0 A qualitative classification of estimated rates of vertical movement of water from the ground surface through the unsaturated zone of any artificial deposits (the zone between the land surface and the water table). This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 47
Page 145
Geology 1:50,000 scale - Superficial © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Landslip (50k) Superficial geology (50k) Please see table for more details. 15.4 Superficial geology (50k) Records within 500m 1 Superficial geological deposits at 1:50,000 scale. Also known as 'drift', these are the youngest geological deposits, formed during the Quaternary. They rest on older deposits or rocks referred to as bedrock. Features are displayed on the Geology 1:50,000 scale - Superficial map on page 48 > ID Location LEX Code Description Rock description 1 On site SUPNM- UKNOWN SUPERFICIAL THEME NOT MAPPED [FOR DIGITAL MAP USE ONLY] UNKNOWN/UNCLASSIFIED ENTRY This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 48
Page 146
15.5 Superficial permeability (50k) Records within 50m 1 A qualitative classification of estimated rates of vertical movement of water from the ground surface through the unsaturated zone of any superficial deposits (the zone between the land surface and the water table). Location Flow type Maximum permeability Minimum permeability On site Mixed High Low This data is sourced from the British Geological Survey. 15.6 Landslip (50k) Records within 500m 0 Mass movement deposits on BGS geological maps at 1:50,000 scale. Primarily superficial deposits that have moved down slope under gravity to form landslips. These affect bedrock, other superficial deposits and artificial ground. This data is sourced from the British Geological Survey. 15.7 Landslip permeability (50k) Records within 50m 0 A qualitative classification of estimated rates of vertical movement of water from the ground surface through the unsaturated zone of any landslip deposits (the zone between the land surface and the water table). This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 49
Page 147
Geology 1:50,000 scale - Bedrock © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Bedrock faults and other linear features (50k) Bedrock geology (50k) Please see table for more details. 15.8 Bedrock geology (50k) Records within 500m 1 Bedrock geology at 1:50,000 scale. The main mass of rocks forming the Earth and present everywhere, whether exposed at the surface in outcrops or concealed beneath superficial deposits or water. Features are displayed on the Geology 1:50,000 scale - Bedrock map on page 50 > ID Location LEX Code Description Rock age 1 On site CXF-MDSI CROMLIX MUDSTONE FORMATION - MUDSTONE AND SILTSTONE EMSIAN This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 50
Page 148
15.9 Bedrock permeability (50k) Records within 50m 1 A qualitative classification of estimated rates of vertical movement of water from the ground surface through the unsaturated zone of bedrock (the zone between the land surface and the water table). Location Flow type Maximum permeability Minimum permeability On site Fracture Moderate Low This data is sourced from the British Geological Survey. 15.10 Bedrock faults and other linear features (50k) Records within 500m 0 Linear features at the ground or bedrock surface at 1:50,000 scale of six main types; rock, fault, fold axis, mineral vein, alteration area or landform. Features are either observed or inferred, and relate primarily to bedrock. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 51
Page 149
16 Boreholes 16.1 BGS Boreholes Records within 250m 0 The Single Onshore Boreholes Index (SOBI); an index of over one million records of boreholes, shafts and wells from all forms of drilling and site investigation work held by the British Geological Survey. Covering onshore and nearshore boreholes dating back to at least 1790 and ranging from one to several thousand metres deep. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 52
Page 150
17 Natural ground subsidence - Shrink swell clays © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) No data Negligible Very low Low Moderate High 17.1 Shrink swell clays Records within 50m 1 The potential hazard presented by soils that absorb water when wet (making them swell), and lose water as they dry (making them shrink). This shrink-swell behaviour is controlled by the type and amount of clay in the soil, and by seasonal changes in the soil moisture content (related to rainfall and local drainage). Features are displayed on the Natural ground subsidence - Shrink swell clays map on page 53 > Location Hazard rating Details On site Very low Ground conditions predominantly low plasticity. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 53
Page 151
Natural ground subsidence - Running sands © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) No data Negligible Very low Low Moderate High 17.2 Running sands Records within 50m 1 The potential hazard presented by rocks that can contain loosely-packed sandy layers that can become fluidised by water flowing through them. Such sands can 'run', removing support from overlying buildings and causing potential damage. Features are displayed on the Natural ground subsidence - Running sands map on page 54 > Location Hazard rating Details On site Very low Running sand conditions are unlikely. No identified constraints on land use due to running conditions unless water table rises rapidly. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 54
Page 152
Natural ground subsidence - Compressible deposits © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) No data Negligible Very low Low Moderate High 17.3 Compressible deposits Records within 50m 1 The potential hazard presented by types of ground that may contain layers of very soft materials like clay or peat and may compress if loaded by overlying structures, or if the groundwater level changes, potentially resulting in depression of the ground and disturbance of foundations. Features are displayed on the Natural ground subsidence - Compressible deposits map on page 55 > Location Hazard rating Details On site Negligible Compressible strata are not thought to occur. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 55
Page 153
Natural ground subsidence - Collapsible deposits © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) No data Negligible Very low Low Moderate High 17.4 Collapsible deposits Records within 50m 1 The potential hazard presented by natural deposits that could collapse when a load (such as a building) is placed on them or they become saturated with water. Features are displayed on the Natural ground subsidence - Collapsible deposits map on page 56 > Location Hazard rating Details On site Very low Deposits with potential to collapse when loaded and saturated are unlikely to be present. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 56
Page 154
Natural ground subsidence - Landslides © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) No data Negligible Very low Low Moderate High 17.5 Landslides Records within 50m 1 The potential for landsliding (slope instability) to be a hazard assessed using 1:50,000 scale digital maps of superficial and bedrock deposits, combined with information from the BGS National Landslide Database and scientific and engineering reports. Features are displayed on the Natural ground subsidence - Landslides map on page 57 > Location Hazard rating Details On site Very low Slope instability problems are not likely to occur but consideration to potential problems of adjacent areas impacting on the site should always be considered. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 57
Page 155
Natural ground subsidence - Ground dissolution of soluble rocks © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) No data Negligible Very low Low Moderate High 17.6 Ground dissolution of soluble rocks Records within 50m 1 The potential hazard presented by ground dissolution, which occurs when water passing through soluble rocks produces underground cavities and cave systems. These cavities reduce support to the ground above and can cause localised collapse of the overlying rocks and deposits. Features are displayed on the Natural ground subsidence - Ground dissolution of soluble rocks map on page 58 > Location Hazard rating Details On site Negligible Soluble rocks are either not thought to be present within the ground, or not prone to dissolution. Dissolution features are unlikely to be present. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 58
Page 156
This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 59
Page 157
18 Mining and ground workings © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) BritPits Surface ground workings Underground workings Underground mining extents Historical mineral planning areas TCA non-coal mining Non Coal Mining Sporadic underground mining of restricted extent possible Localised small scale underground mining possible Small scale mining possible Underground mining known or likely within or in close proximity Underground mining known within or in very close proximity 18.1 BritPits Records within 500m 0 BritPits (an abbreviation of British Pits) is a database maintained by the British Geological Survey of currently active and closed surface and underground mineral workings. Details of major mineral handling sites, such as wharfs and rail depots are also held in the database. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 60
Page 158
18.2 Surface ground workings Records within 250m 0 Historical land uses identified from Ordnance Survey mapping that involved ground excavation at the surface. These features may or may not have been subsequently backfilled. This is data is sourced from Ordnance Survey/Groundsure. 18.3 Underground workings Records within 1000m 0 Historical land uses identified from Ordnance Survey mapping that indicate the presence of underground workings e.g. mine shafts. This is data is sourced from Ordnance Survey/Groundsure. 18.4 Underground mining extents Records within 500m 0 This data identifies underground mine workings that could present a potential risk, including adits and seam workings. These features have been identified from BGS Geological mapping and mine plans sourced from the BGS and various collections and sources. This data is sourced from Groundsure. 18.5 Historical Mineral Planning Areas Records within 500m 0 Boundaries of mineral planning permissions for England and Wales. This data was collated between the 1940s (and retrospectively to the 1930s) and the mid 1980s. The data includes permitted, withdrawn and refused permissions. This data is sourced from the British Geological Survey. 18.6 Non-coal mining Records within 1000m 1 The potential for historical non-coal mining to have affected an area. The assessment is drawn from expert knowledge and literature in addition to the digital geological map of Britain. Mineral commodities may be divided into seven general categories - vein minerals, chalk, oil shale, building stone, bedded ores, evaporites and 'other' commodities (including ball clay, jet, black marble, graphite and chert). Features are displayed on the Mining and ground workings map on page 60 > Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 61
Page 159
ID Location Name Commodity Class Likelihood 1 On site Not available Vein Mineral A Underground mine workings are uncommon, although the geology is similar to that worked elsewhere. Potential for difficult ground conditions are unlikely and are at a level where they need not be considered. This data is sourced from the British Geological Survey. 18.7 JPB mining areas Records on site 0 Areas which could be affected by former coal and other mining. This data includes some mine plans unavailable to the Coal Authority. This data is sourced from Johnson Poole and Bloomer. 18.8 The Coal Authority non-coal mining Records within 500m 0 This data provides an indication of the potential zone of influence of recorded underground non-coal mining workings. Any and all analysis and interpretation of Coal Authority Data in this report is made by Groundsure, and is in no way supported, endorsed or authorised by the Coal Authority. The use of the data is restricted to the terms and provisions contained in this report. Data reproduced in this report may be the copyright of the Coal Authority and permission should be sought from Groundsure prior to any re-use. This data is sourced from The Coal Authority. 18.9 Researched mining Records within 500m 0 This data indicates areas of potential mining identified from alternative or archival sources, including; BGS Geological paper maps, Lidar data, aerial photographs (from World War II onwards), archaeological data services, websites, Tithe maps, and various text/plans from collected books and reports. Some of this data is approximate and Groundsure have interpreted the resultant risk area and, where possible, specific areas of risk have been captured. This data is sourced from Groundsure. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 62
Page 160
18.10 Mining record office plans Records within 500m 0 This dataset is representative of Mining Record Office and/or plan extents held by Groundsure and should be considered approximate. Where possible, plans have been located and any specific areas of risk they depict have been captured. This data is sourced from Groundsure. 18.11 BGS mine plans Records within 500m 0 This dataset is representative of BGS mine plans held by Groundsure and should be considered approximate. Where possible, plans have been located and any specific areas of risk they depict have been captured. This data is sourced from Groundsure. 18.12 Coal mining Records on site 0 Areas which could be affected by past, current or future coal mining. This data is sourced from the Coal Authority. 18.13 Brine areas Records on site 0 The Cheshire Brine Compensation District indicates areas that may be affected by salt and brine extraction in Cheshire and where compensation would be available where damage from this mining has occurred. Damage from salt and brine mining can still occur outside this district, but no compensation will be available. This data is sourced from the Cheshire Brine Subsidence Compensation Board. 18.14 Gypsum areas Records on site 0 Generalised areas that may be affected by gypsum extraction. This data is sourced from British Gypsum. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 63
Page 161
18.15 Tin mining Records on site 0 Generalised areas that may be affected by historical tin mining. This data is sourced from Groundsure. 18.16 Clay mining Records on site 0 Generalised areas that may be affected by kaolin and ball clay extraction. This data is sourced from the Kaolin and Ball Clay Association (UK). Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 64
Page 162
19 Ground cavities and sinkholes 19.1 Natural cavities Records within 500m 0 Industry recognised national database of natural cavities. Sinkholes and caves are formed by the dissolution of soluble rock, such as chalk and limestone, gulls and fissures by cambering. Ground instability can result from movement of loose material contained within these cavities, often triggered by water. This data is sourced from Stantec UK Ltd. 19.2 Mining cavities Records within 1000m 0 Industry recognised national database of mining cavities. Degraded mines may result in hazardous subsidence (crown holes). Climatic conditions and water escape can also trigger subsidence over mine entrances and workings. This data is sourced from Stantec UK Ltd. 19.3 Reported recent incidents Records within 500m 0 This data identifies sinkhole information gathered from media reports and Groundsure's own records. This data goes back to 2014 and includes relative accuracy ratings for each event and links to the original data sources. The data is updated on a regular basis and should not be considered a comprehensive catalogue of all sinkhole events. The absence of data in this database does not mean a sinkhole definitely has not occurred during this time. This data is sourced from Groundsure. 19.4 Historical incidents Records within 500m 0 This dataset comprises an extract of 1:10,560, 1:10,000, 1:2,500 and 1:1,250 scale historical Ordnance Survey maps held by Groundsure, dating back to the 1840s. It shows shakeholes, deneholes and other 'holes' as noted on these maps. Dene holes are medieval chalk extraction pits, usually comprising a narrow shaft with a number of chambers at the base of the shaft. Shakeholes are an alternative name for suffusion sinkholes, most commonly found in the limestone landscapes of North Yorkshire but also extensively noted around the Brecon Beacons National Park. Not all 'holes' noted on Ordnance Survey mapping will necessarily be present within this dataset. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 65
Page 163
This data is sourced from Groundsure. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 66
Page 164
20 Radon © Crown copyright and database rights 2025. Ordnance Survey licence 100035207 Site Outline Search buffers in metres (m) Greater than 30% Between 10% and 30% Between 5% and 10% Between 3% and 5% Between 1% and 3% Less than 1% 20.1 Radon Records on site 1 The Radon Potential data classifies areas based on their likelihood of a property having a radon level at or above the Action Level in Great Britain. The dataset is intended for use at 1:50,000 scale and was derived from both geological assessments and indoor radon measurements (more than 560,000 records). A minimum 50m buffer should be considered when searching the maps, as the smallest detectable feature at this scale is 50m. The findings of this section should supersede any estimations derived from the Indicative Atlas of Radon in Great Britain (1:100,000 scale). Features are displayed on the Radon map on page 67 > Location Estimated properties affected Radon Protection Measures required On site Less than 1% None Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 67
Page 165
This data is sourced from the British Geological Survey and UK Health Security Agency. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 68
Page 166
21 Soil chemistry 21.1 BGS Estimated Background Soil Chemistry Records within 50m 2 The estimated values provide the likely background concentration of the potentially harmful elements Arsenic, Cadmium, Chromium, Lead and Nickel in topsoil. The values are estimated primarily from rural topsoil data collected at a sample density of approximately 1 per 2 km2. In areas where rural soil samples are not available, estimation is based on stream sediment data collected from small streams at a sampling density of 1 per 2.5 km2; this is the case for most of Scotland, Wales and southern England. The stream sediment data are converted to soil-equivalent concentrations prior to the estimation. Location Arsenic Bioaccessible Arsenic Lead Bioaccessible Lead Cadmiu m Chromium Nickel On site 15 mg/kg - 100 mg/kg 60 mg/kg No data 60 - 90 mg/kg 15 - 30 mg/kg On site 15 mg/kg - 100 mg/kg 60 mg/kg No data 60 - 90 mg/kg 15 - 30 mg/kg This data is sourced from the British Geological Survey. 21.2 BGS Estimated Urban Soil Chemistry Records within 50m 0 Estimated topsoil chemistry of Arsenic, Cadmium, Chromium, Copper, Nickel, Lead, Tin and Zinc and bioaccessible Arsenic and Lead in 23 urban centres across Great Britain. These estimates are derived from interpolation of the measured urban topsoil data referred to above and provide information across each city between the measured sample locations (4 per km2). This data is sourced from the British Geological Survey. 21.3 BGS Measured Urban Soil Chemistry Records within 50m 0 The locations and measured total concentrations (mg/kg) of Arsenic, Cadmium, Chromium, Copper, Nickel, Lead, Tin and Zinc in urban topsoil samples from 23 urban centres across Great Britain. These are collected at a sample density of 4 per km2. This data is sourced from the British Geological Survey. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 69
Page 167
22 Railway infrastructure and projects 22.1 Underground railways (London) Records within 250m 0 Details of all active London Underground lines, including approximate tunnel roof depth and operational hours. This data is sourced from publicly available information by Groundsure. 22.2 Underground railways (Non-London) Records within 250m 0 Details of the Merseyrail system, the Tyne and Wear Metro and the Glasgow Subway. Not all parts of all systems are located underground. The data contains location information only and does not include a depth assessment. This data is sourced from publicly available information by Groundsure. 22.3 Railway tunnels Records within 250m 0 Railway tunnels taken from contemporary Ordnance Survey mapping. This data is sourced from the Ordnance Survey. 22.4 Historical railway and tunnel features Records within 250m 0 Railways and tunnels digitised from historical Ordnance Survey mapping as scales of 1:1,250, 1:2,500, 1:10,000 and 1:10,560. This data is sourced from Ordnance Survey/Groundsure. 22.5 Royal Mail tunnels Records within 250m 0 The Post Office Railway, otherwise known as the Mail Rail, is an underground railway running through Central London from Paddington Head District Sorting Office to Whitechapel Eastern Head Sorting Office. The line is 10.5km long. The data includes details of the full extent of the tunnels, the depth of the tunnel, and the depth to track level. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 70
Page 168
This data is sourced from Groundsure/the Postal Museum. 22.6 Historical railways Records within 250m 0 Former railway lines, including dismantled lines, abandoned lines, disused lines, historic railways and razed lines. This data is sourced from OpenStreetMap. 22.7 Railways Records within 250m 0 Currently existing railway lines, including standard railways, narrow gauge, funicular, trams and light railways. This data is sourced from Ordnance Survey and OpenStreetMap. 22.8 Crossrail 2 Records within 500m 0 Crossrail 2 is a proposed railway linking the national rail networks in Surrey and Hertfordshire via an underground tunnel through London. This data is sourced from publicly available information by Groundsure. 22.9 HS2 Records within 500m 0 HS2 is a proposed high speed rail network running from London to Manchester and Leeds via Birmingham. Main civils construction on Phase 1 (London to Birmingham) of the project began in 2019, and it is currently anticipated that this phase will be fully operational by 2026. Construction on Phase 2a (Birmingham to Crewe) is anticipated to commence in 2021, with the service fully operational by 2027. Construction on Phase 2b (Crewe to Manchester and Birmingham to Leeds) is scheduled to begin in 2023 and be operational by 2033. This data is sourced from HS2 ltd. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 71
Page 169
Data providers Groundsure works with respected data providers to bring you the most relevant and accurate information. To find out who they are and their areas of expertise see https://www.groundsure.com/sources-reference ↗. Terms and conditions Groundsure's Terms and Conditions can be accessed at this link: www.groundsure.com/terms-and-conditions- april-2023/ ↗. Plot at rear of 104 Willoughby St, Muthill, PH5 2AE Ref: GS-UCE-SE5-F7U-D8M Your ref: 1853MTF Grid ref: 286995 716587 HOME Contact us with any questions at: info@groundsure.com ↗ 01273 257 755 Date: 6 March 2025 72
Page 170
APPENDIX III Historical Mapping
Page 171
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 County Series 1866 1:2,500 1:2,500 06 March 2025
Page 172
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 County Series 1900 1:2,500 1:2,500 06 March 2025
Page 173
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 1971 1:2,500 1:2,500 06 March 2025
Page 174
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 1971 1:2,500 1:2,500 06 March 2025
Page 175
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 1990-1995 1:2,500 1:2,500 06 March 2025
Page 176
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 1995 1:2,500 1:2,500 06 March 2025
Page 177
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 LandLine 2003 1:1,250 1:1,250 06 March 2025
Page 178
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 County Series 1864 1:10,560 1:10,560 06 March 2025
Page 179
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 County Series 1901 1:10,560 1:10,560 06 March 2025
Page 180
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 Provisional 1954 1:10,560 1:10,560 06 March 2025
Page 181
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 1973 1:10,000 1:10,000 06 March 2025
Page 182
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 2001 1:10,000 1:10,000 06 March 2025
Page 183
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 2010 1:10,000 1:10,000 06 March 2025
Page 184
Production date: Map legend available at: www.groundsure.com/sites/default/files/groundsure_legend.pdf © Crown copyright and database rights 2024 Ordnance Survey 100035207 Site Details: Client Ref: Report Ref: Grid Ref: Map Name: Map date: Scale: Printed at: Produced by Groundsure Insights T: 08444 159000 E: info@groundsure.com W: www.groundsure.com N EW S Plot at rear of 104 Willoughby St, Muthill, PH5 2AE 1853MTF GS-B46-R3G-T72-OB5 286995, 716587 National Grid 2025 1:10,000 1:10,000 06 March 2025
Page 185
Report Limitations The comments given in the report and the opinion expressed herein are based on the information sourced by the desk study and other published information. Third party information was therefore used in the preparation of this report and Soilutions Limited cannot guarantee the accuracy or completeness of this information. There may be other sources of information not included in those listed that hold data relevant to the Desk Study undertaken at the site that could materially affect the conclusions made in this report. The interpretation of the maps and/or other data commented on in this report is subjective. During site clearance works where previously unidentified contaminated materials are encountered, this must be noted by the contractor and reported to Soilutions in order to determine whether the risk assessment and remediation strategies for the site require amendment. The conclusions in this report represent our professional opinion, these conclusions have been drawn up with the greatest care to ensure that all apparent issues were addressed properly in accordance with applicable UK guidance and accepted practice.
Page 186
T: 0800 0209 307 T: +44 131 538 8456 E: info@soilutions.co.uk W: soilutions.co.uk Soilutions Ltd, Torridon House, Torridon Lane, Rosyth KY11 2EU
Page 187
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation At: 104 Willougby Street Muthill Perthshire PH5 2AE For: Mr John Kane Date: July 2025 Our Ref: 10202-25
Page 188
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE ii Contents 1 Introduction .................................................................................................................... 1 2 Purpose and Aims ........................................................................................................... 1 3 Review and Summary ...................................................................................................... 1 4 Environmental Setting ..................................................................................................... 2 4.1 Site Walkover ......................................................................................................... 2 4.2 Geology .................................................................................................................. 2 4.3 The Coal Authority .................................................................................................. 3 4.4 UK Radon ............................................................................................................... 3 4.5 Ecological & Archaeological Considerations ............................................................ 3 5 Intrusive Site Investigation Methodology .......................................................................... 3 5.1 Trial Pits ................................................................................................................. 3 5.2 Boreholes ............................................................................................................... 3 5.3 Targeted (Judgmental) Soil Sampling ....................................................................... 3 5.4 Gas Risk Assessment ............................................................................................. 3 5.5 Sample Depths / Frequency .................................................................................... 3 5.6 Sample Collecting, Storing & Transportation ............................................................ 4 5.7 Onsite Observations ............................................................................................... 4 5.8 Ground Conditions ................................................................................................. 4 5.9 Porosity Testing ...................................................................................................... 4 6 Results ........................................................................................................................... 5 6.1 Generic Assessment Criteria (GAC) for Soils ............................................................ 5 6.2 Soil Samples .......................................................................................................... 5 6.3 Asbestos ................................................................................................................ 5 6.4 pH Values .............................................................................................................. 5 7 Development of Revised Conceptual Site Model .............................................................. 6 7.1 Introduction ........................................................................................................... 6 7.2 Pathways ............................................................................................................... 6 7.3 Receptors .............................................................................................................. 7 7.4 Preliminary Conceptual Site Model ......................................................................... 7 7.5 Description of Risks ................................................................................................ 7 7.6 Risk Definitions ...................................................................................................... 8 8 Conclusion and Recommendations ............................................................................... 10
Page 189
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE iii Tables Table 1: Sample Collection Details Table 2: Revised CSM Appendices Appendix 1 – Site Layout Plan (Sampling Plan) Appendix 2 – TP Log & Site Photographs Appendix 3 – Results & Analysis (Soil Sampling) Appendix 4 – Revised Conceptual Site Model (CSM) Document Properties Revision Details Issue Date 00 Draft 28/07/2025 01 First Issue 30/07/2025 Prepared by: Kris Given BEng, MSc (Eng), GMICE Checked by: Hugh Campbell BSc (Eng), CEng, MICE, MIStructE For and on behalf of Campbell of Doune Limited 30 July 2025
Page 190
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 1 1 Introduction This report provides results of analysis of the intrusive site investigation carried out at 104 Willoughby Street, Muthill, Perthshire, following recommendations by Soilutions Phase 1 Desk Study dated 19/03/2025. The site considered within this report is currently part of the garden of 104 Willoughby Street. The entire site is approximately 0.05 hectares (ha) in size and located at an approximate elevation of 86.6m above Ordnance Datum (mAOD) with a sloped topography. The proposed development involves the erection of a new domestic dwelling. The investigation was carried out to determine ground conditions across the site and assess the potential for ground contamination. 2 Purpose and Aims This Phase 2 report is concerned with the results obtained from the on-site intrusive investigation to determine the possible presence and extent of on-site ground contamination. This information will allow for the evaluation of the previously carried out conceptual site model (CSM) which will determine if any site remedial actions are required. The general objectives of this phase 2 report are to: • Establish if any contamination has occurred during previous industrial processes on site • Establish if the site would be suitable for development and if any remediation measures are required. • Provide infiltration results for soakaway design. 3 Review and Summary A Phase I Desk Top Study and Site Investigation Report has been completed for the site by Soilutions Ltd. It is recommended that both reports are read in conjunction. Details of Soilutions Ltd report is included below: • Phase I Desk Study Report, Project Ref: 1853, Dated 18th March 2025 The main potential pollutant linkages that were identified in the conceptual site model that require to be considered further are • End users may interact with the soils through leisure or maintenance activities. Contamination, associated with the demolition of a building in the north of the site, may be present at the site. The risk to human health is Moderate/Low.
Page 191
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 2 • Gardens may include vegetable planting or fruit bearing trees in soft landscaping. Provided this remains the case the risk of uptake to proposed flora and fauna is Moderate/Low. This Phase II report will allow for the conceptual site model to be revised upon evaluation of all intrusive investigation results. If any pollutant linkages remain, remediation proposals and further monitoring will be provided and justified where required. 4 Environmental Setting 4.1 Site Walkover The site walkover and exploratory investigation was undertaken on the 23rd June 2025 by Kris Given of Campbell of Doune Ltd. The site area is currently part of the garden of 104 Willoughby Street. The site forms the southernmost extent of the garden and is mostly covered in turf and topsoil. In the southwest of the site is a small enclosure. A woodstore, shed and greenhouse are located to the north of the site. An above ground LPG tank is in the west of the site. The site is bounded by hedges in the west, south and east. The northern boundary is not clearly defined. Vegetation at the site comprises of grass across the majority of the site. A group of immature conifers is present along the southern boundary. A vegetable patch is present in the southwest of the site The topography of the site slopes downwards to the north. Vehicle access at the site is via a parking area to the north of the site. 4.2 Geology The British Geological Survey (BGS) Geology of Britain Viewer and the BGS borehole records were consulted to get a general understanding of the geological conditions at the site. According to information from BGS mapping, the geology of the site is as follows. • Bedrock: Cromlix Mudstone Formation – Mustone and Siltstone. Sedimentary bedrock formed between 407.6 and 393.3 million years ago during the Devonian period. • Superficial: Till – Diamicton. Sedimentary superficial deposit formed between 2.588 million years ago and the present during the Quaternary period.
Page 192
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 3 4.3 The Coal Authority The site is not within a coal mining reporting area as confirmed by the Coal Authority. No further action required. 4.4 UK Radon The site is not within a radon action area as confirmed by UK Radon. No further action required. 4.5 Ecological & Archaeological Considerations There are no known ecological or archaeological considerations within the site or its surrounding area 5 Intrusive Site Investigation Methodology 5.1 Trial Pits 1 No. trial pits was excavated on 24th June 2025 using a 2-tonne JCB hydraulic excavator to a depth of 1.5 meters below ground level (mbgl). Trial pit log and accompanying site photographs are attached as Appendix 2. 5.2 Boreholes No boreholes were excavated during this intrusive investigation. 5.3 Targeted (Judgmental) Soil Sampling Targeted or judgemental sampling involves sampling at locations that are selected on the basis of known or suspected sources or an area of possible contamination in accordance with BS 10175. The excavated trial pit was taken close to the previously demolished building to the north of the site and at the proposed soakaway location. The sampling plan for this investigation can be found as Appendix 1. 5.4 Gas Risk Assessment No source of potential gas was identified during the site investigation. Original subsoils across the site were encountered, therefore, no gas monitoring was undertaken. It is concluded that gas is unlikely to be a Contaminant of Concern (COC) or pose a significant risk at this site. No further assessment required. 5.5 Sample Depths / Frequency The exact depths of sample retrieval were determined from the site-specific geological detail, including depth to natural deposits. Samples were collected from each distinct soil horizon and, where possible, in the capillary zone. This sampling strategy will allow risks to human health and the environment to be quantified.
Page 193
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby Street Muthill Perthshire PH5 2AE 4 5.6 Sample Collecting, Storing & Transportation All collected soil samples were taken in accordance with British Standards BS ISO 18400-302:2018 and were stored in appropriate containers and kept in cold storage during transport to a UKAS and MCERTS accredited laboratory (DETS). The samples were taken on 24th June 2025 and collected for analysis on 26th June 2025. Details of the samples collected can be observed in Table 1. Table 1: Sample Collection Details 5.7 Onsite Observations The topography of the site slopes downwards to the north. No pollution sources were identified on site and no rubble material was visible from the previously demolished building to the north of the site. 5.8 Ground Conditions The materials encountered in the excavated trial pits indicate that ground conditions across the site area are uniform in both makeup and consistency. The site area is surfaced in a layer of topsoil to a depth of 300mm. Below this, original subsoils of medium dense, slightly clayey gravelly sand with abundant sun-angular cobbles were encountered. No ground contamination was encountered or suspected during the intrusive investigation. No groundwater was encountered during the intrusive ground investigation. 5.9 Porosity Testing Porosity testing was undertaken following section 3.9.1 of the Technical Standards at TP1 at a depth of 1400mm. Trial Pit Test No. Depth Below Ground Level (m) Depth of Water (mm) Time Taken Between 75% and 25% Full (sec) Percolation Value (Vp) (mm/s) 1 1 1.4 300 3090 20.6 1 2 1.4 300 4122 27.5 Average Results (VP) = 24.05mm/s The infiltration rate figures suggest that a soakaway or filter drains will be suitable for drainage of the proposed development. TP / Sample ID Sample Depth (m) Testing Sample Date TP1 0.400 Full Soil Spectrum Suite 24-06-25 TP1 1.100 Full Soil Spectrum Suite 24-06-25
Page 194
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 5 6 Results All sample testing was carried out by Normec DETS Limited. DETS operate a UKAS and ISO 17025 accredited laboratory. 6.1 Generic Assessment Criteria (GAC) for Soils UK Soil Guideline Values (SGV) are GAC for assessing chronic risks to human health from long-term exposure to contaminated soils produced by the Environmental Agency (2009). SGV are trigger values ensuring that land does not pose any unacceptable risks to health of the intended users. SGV are derived using established Health Criteria Values (HCV). The HCV of a chemical is the level of exposure at which long-term exposure to the chemical in soil is tolerable or poses minimal risk. The SGV are derived using the Generic Assessment Criteria for Human Health Risk Assessment Comparison where residential with homegrown produce limits were used for this comparison. Exceeding SGV typically requires remediation or further investigation and evaluation of the risk. 6.2 Soil Samples 2 soil samples were analysed using a full spectrum suite and hydrocarbon analysis. This testing suite incorporates all the main potential contaminants that may be present on site. All recorded test results for contaminants were measured against CL:AIRE, S4UL and C4SL soil guideline values (SGV). The analytical results for all tested samples raise no concerns in regard to onsite contamination. All recorded test results for contaminants of concern fall well below the SGV action limits with many tests failing to reach level of detection. All soil analytical results are presented in Appendix 3. 6.3 Asbestos No asbestos was visually observed or detected in any of the analysed soil samples. All collected samples were analysed by DETSC 1101 using polarised light microscopy in accordance with HSG248 and documented in house methods. 6.4 pH Values Recorded pH values show the soils to have a predominantly neutral value (6.9 – 7.0). It is therefore concluded that the neutral recorded pH values will not affect the binding properties or cause any long-term adverse effect on any future concrete structural elements that may be formed on site.
Page 195
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 6 7 Development of Revised Conceptual Site Model 7.1 Introduction The information obtained on the site and surrounding area requires to be collated and evaluated to formulate the revised conceptual site model (CSM); the CSM is then refined during subsequent phases of investigation, which is an essential part of the risk assessment process. The CSM is “a description and/or representation of the site, incorporating what is known about the ground and groundwater conditions; the actual and potential contamination; the physical conditions and environmental setting; the receptors; and potential pathway linkages between contamination sources and receptors.” (BS 10175:2011). Where plausible source-pathway-receptor relationships exist, this is termed a pollutant linkage. Where potential pollutant linkages (PPL) are identified, a qualitative assessment of the risks is undertaken to ascertain whether there is the potential for ‘significant harm’ or the ‘significant possibility of such harm’ to human health and/or whether ‘significant pollution of the water environment is being or is likely to be caused’. This process involves: • Identification of any potential sources, pathways, and receptors. • Estimation of the likelihood, nature, and extent of exposure to a hazard and the risk of adverse effects. • Assessment of the likely pollutant linkages and the degree of risk and • Evaluation of the need for controlling the identified risk The outcome of this process is the identification of potentially significant pollutant linkages (SPL) which may require further investigation. 7.2 Pathways Within a qualitative risk assessment, consideration is given to the method by which potential risks associated with any individual contaminant at a source may be transferred to a potential receptor. The following potential pathways have been considered to assess the risk to people and the local environment. Consideration of these pathways alongside the potential hazards and potential receptors shall form the basis of the risk assessment. • Ingestion / dermal contact of soils / materials on site which may contain contaminates. • Inhalation of soil gas. • Infiltration & migration of contaminants in groundwater. • Direct contact of utilities with potentially contaminated soils / groundwater. • Gas migration from made ground.
Page 196
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 7 7.3 Receptors Potential receptors are those which may be impacted by any of the contaminants of concern identified, and including the following: • Current & future users of the site • Construction workers • Groundwater • Surface waters • Material construction of buildings and infrastructure • Neighbouring properties & occupants 7.4 Preliminary Conceptual Site Model All the relevant information obtained within this report has been collated to develop the preliminary CSM to identify potential pollutant linkages (PPL), and to undertake a qualitative risk assessment of each PPL to assess whether further assessment is warranted. A risk rating has been provided for each PPL, which is based on an assessment of the probability of an effect occurring against the consequence, or magnitude of that effect, in accordance with the matrices shown. For those risks identified as moderate or severe, further assessment is warranted. 7.5 Description of Risks Very High Risk – there is a high probability that severe harm could arise to a designated receptor from an identified hazard, OR there is evidence that severe harm to a designated receptor is currently happening. High Risk – harm is likely to arise to a designated receptor from an identified hazard. Moderate Risk – it is possible that harm could arise to a designated receptor from an identified hazard. However, it is either relatively unlikely that any such harm would be severe, or if any harm were to occur, it is more likely that the harm would be relatively mild. Low Risk – it is possible that harm could arise to a designated receptor from an identified hazard, but it is likely that this harm, if realised, would at worst normally be mild. Very Low Risk – there is a low possibility that harm could arise to a receptor. In the event of such harm being realised, it is not likely to be severe.
Page 197
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 8 7.6 Risk Definitions The definitions of probability, consequence and risk have been adapted from CIRIA C552 ‘Contaminated land risk assessment – A guide to good practice’ (2001). 7.6.1 Probability Probability Definition in context High likelihood An event appears either very likely in the short term and almost inevitable in the long term, or there is evidence at the receptor of harm or pollution. Likely It is probable that an event will occur; although circumstances are such an event is not inevitable, but possible in the short term and likely in the long term. Low likelihood It is possible that an event could occur; however, it is not certain that even over a longer period such an event would take place and is less likely in the shorter term. Unlikely It is improbable that an event would occur even in the very long term. 7.6.2 Consequence to Receptor Human Health Water Environment Buildings/Services Severe Acute or chronic permanent impact on human health Significant pollution of water environment Catastrophic collapse Moderate Chronic permanent impact on human health Gradual pollution of water environment Degradation of materials Mild Chronic temporary impact on human health Gradual pollution of water environment Noticeable change, non-structural Negligible No impact No impact No impact 7.6.3 Risk Rating Probability Consequences Negligible Mild Moderate Severe Unlikely Near zero Low Medium/Low High/Medium/Low Low likelihood Near zero Low Medium/Low High/Medium Likely Near zero Low Medium High High likelihood Near zero Medium/Low High High A revised conceptual site model and qualitative risk assessment is provided in table 7.
Page 198
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 9 7.6.4 Risk Assessment Table 2: Revised Conceptual Site Model and Qualitative Risk Assessment Receptor Group Min. risk Max. risk Action Comments / Actions End Users (Human Uptake from Made Ground) Low Low None No made ground was encountered during the exploratory ground investigation of the site. The analytical results for all tested samples raise no concerns in regard to onsite contamination. All recorded test results for contaminants of concern fall well below the SGV action limits with many tests failing to reach level of detection. This risk can therefore be categorised as ‘low’ due to the absence of any site contamination. Flora & Fauna (Root Uptake from Made Ground) Low Low None The analytical results for all tested samples raise no concerns in regard to onsite contamination. All recorded test results for contaminants of concern fall well below the SGV action limits with many tests failing to reach level of detection. This risk can therefore be categorised as ‘low’ due to the absence of any site contamination.
Page 199
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 10 8 Conclusion and Recommendations From evidence obtained from the intrusive site investigation and the chemical analysis of soil samples, it is determined that there is no risk posed by any historic contamination of the proposed site area from past activities on site. Sampling was carried out at the proposed soakaway location which is also in close proximity to the previously demolished building where samples were collected from each distinct horizon. No visual or olfactory contamination was encountered during the instructive ground investigation. Good site cleanliness and hygiene standards around site and encouragement of hand washing of all site workers should be implemented to reduce the risk of any ingestion / inhalation/ dermal contact of any potential contaminants. Good quality gloves should be encouraged to be worn when handling any soils and equipment within the site. Gas Risk Assessment No source of potential gas was identified during the site investigation. All made ground encountered during the exploratory ground investigation. Therefore, no gas monitoring was undertaken, and it is concluded that gas is unlikely to be a contaminant of concern (COC) or pose a significant risk at this site. No further assessment is required. General This Phase II site investigation has not identified any significant sources of contamination at this site which would require further assessment or remediation. No evidence of contamination was found within the proposed area of development. No made ground was encountered during the exploratory ground investigation, with original subsoils of medium dense, slightly clayey SAND encountered to termination of all excavations. The revised CSM and risk assessment identify no potential pollutant linkages that should be considered and mitigated during development and future use of the site. It is however recommended that construction workers wear appropriate PPE and adopt suitable Health and Safety procedures whilst working onsite to control any risks during the construction period. In conclusion, Campbell of Doune can confirm that the site area is suitable for its proposed end use of a domestic dwelling.
Page 200
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 11 Appendix 1 – Site Layout
Page 201
TP & Porosity Location
Page 202
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 12 Appendix 2 – Tril Pit Log & Site Photographs
Page 203
Campbell of Doune Ltd Clan House Muthil Road Crieff Project 104 Willoughby Street, Muthill, PH5 2AE Job no. 10202-25 Calcs for TP Log Start page no./Revision 1 Calcs by KG Calcs date 28/07/2025 Checked by Checked date Approved by Approved date TRIAL PIT LOG Trial pit reference TP1 Sheet 1 of 1 W ater Reduced Level (m) Legend Depth (m) Description 0.00 X X X (0.30) TOPSOIL -0.30 X X 0.30 : - : - : - Medium dense slightly clayey SAND with Abundent Sub-Angular Cobbles - : - : - : : - : - : - (1.10) - : - : - : : - : - : - -1.40 - : - : - : 1.40 Trial pit ends Not shown to scale Additional notes: ;
Page 204
Image 1 & 2: Porosity Testing at TP1 Image 3 & 4: Original Subsoils Excavated from TP1
Page 205
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 13 Appendix 3 – Results & Analysis (Soil Sampling)
Page 206
Project No: 10202-25 Project Title: Contaminants of Concren No. of Samples No. of Non- Minimum Maximum Location of GAC - Residentual No. of GAC (COC) Analysed Detects Concentration Concentration Max. Concentration (Plant Uptake) Exceedences Asbestos ID ID - 2 0 2 - - NAD Presence - 0 Oraganic Matter 0.1 % 2 2 0 1 1.9 TP1 - - - pH - - 2 2 0 6.9 7 TP1 - - 0 Cyanide, Total 0.1 mg/kg 2 2 0 0.1 0.3 TP1 0 Sulphate 10 mg/l 2 2 0 16 20 TP1 - S4UL 0 Metals Arsenic 0.2 mg/kg 2 2 0 6.44.8 6.4 TP1 37 S4UL 0 Cadmium 0.1 mg/kg 2 1 1 < 0.1 0.1 TP1 11 S4UL 0 Chromium (Hexavalent) 0.2 mg/kg 2 2 0 33 29 TP1 910 S4UL 0 Copper 0.2 mg/kg 2 2 0 11 13 TP1 2,400 S4UL 0 Lead 0.3 mg/kg 2 2 0 26 43 TP1 200 C4SL 0 Beryllium 0.2 mg/kg 0 0 0 0 0 - Boron (Water Soluble) 0.2 mg/kg 2 0 2 < 0.2 < 0.2 - 290 S4UL 0 Mercury 0.05 mg/kg 2 0 2 < 0.05 < 0.05 - 40 S4UL 0 Selenium 0.5 mg/kg 2 1 1 < 0.5 0.5 TP1 250 S4UL 0 Nickel 1 mg/kg 2 2 0 17 33 TP1 180 S4UL 0 Zinc 1 mg/kg 2 2 0 58 66 TP1 3,700 S4UL 0 Petroleum Hydrocarbons All Aliphatic C5-C35 0 All Aromatic C5-C35 0 TPH Ali/Aro Total C5-C35 10 mg/kg 2 0 2 < 10 < 10 - 1100 LQM 0 PAHs Naphthalene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 2.3 LQM 0 Acenaphtylene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 170 LQM 0 Acenaphthene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 210 LQM 0 Fluorene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 170 LQM 0 Phenanthrene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 95 LQM 0 Anthrecene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 2,400 LQM 0 Fluoranthene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 280 LQM 0 Pyrene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 620 LQM 0 Benzo(b)fluoranthene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 2.6 LQM 0 Benzo(k)fluoranthene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 77 LQM 0 Benzo(a)pyrene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 2.2 LQM 0 Indeno(1,2,3-c,d)pyrene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 27 LQM 0 Dibenzo(a,h)anthracene 0.1 mg/kg 6 0 2 < 0.1 < 0.1 - 0.24 LQM 0 Benzo(g,h,i)perylene 0.1 mg/kg 2 0 2 < 0.1 < 0.1 - 320 LQM 0 PAH 16 Total 1.6 mg/kg 2 0 2 < 1.6 < 1.6 - - LQM 0 Phenols Phenol - Monohydric 0.01 mg/kg 2 0 2 < 0.3 < 0.3 - 280 LQM 0 All Tested Samples for Aliphatic Petroleum Hydrocarbons Do Not Exceed SGV Limits with ALL Samples Failing to Reach Level of Detection (LOD) All Tested Samples for Aromatic Petroleum Hydrocarbons Do Not Exceed SGV Limits with ALL Samples Failing to Reach Level of Detection (LOD) GAC Source 104 Willoughby Street, Muthill, Perthshire, PH5 2AE Soil Sample Chemical Analysis LOD Units No. of Detects
Page 207
Certificate Number 25-14589 Issued: 15-Jul-25 Client Our Reference Client Reference ~ Order No ~ Contract Title ~ Description Date Received Date Started Date Completed Test Procedures Notes Approved By Louise Cook Contracts Manager 2 Soil samples. 27-Jun-25 27-Jun-25 15-Jul-25 Identified by prefix DETSn (details on request). Opinions and interpretations are outside the laboratory's scope of ISO 17025 accreditation. This certificate is issued in accordance with the accreditation requirements of the United Kingdom Accreditation Service. The results reported herein relate only to the material supplied to the laboratory. This certificate shall not be reproduced except in full, without the prior written approval of the laboratory. Certificate of Analysis Campbell of Doune Ltd Clan House Muthill Road Crieff PH7 4HQ 25-14589 10202-25 (not supplied) John Kane Symbol key at end of report Normec DETS Limited Unit 2, Park Road Industrial Estate South, Consett, Co Durham, DH8 5PY Tel: 01207 582333 • email: info-dets@normecgroup.com • normecdets.com Page 1 of 5 .
Page 208
Summary of Chemical Analysis Soil Samples Our Ref 25-14589 Client Ref ~ 10202-25 Contract Title ~ John Kane Lab No 2530130 2530131 Sample ID ~ TP1 TP2 Depth ~ 0.40 1.10 Other ID ~ Sample Type ~ SOIL SOIL Sampling Date ~ 24/06/2025 24/06/2025 Sampling Time ~ n/s n/s Test Method LOD Units DETSC 2301# 0.2 mg/kg 4.8 6.4 DETSC 2311# 0.2 mg/kg < 0.2 < 0.2 DETSC 2301# 0.1 mg/kg 0.1 < 0.1 DETSC 2301# 0.15 mg/kg 29 33 DETSC 2301# 0.2 mg/kg 11 13 DETSC 2301# 0.3 mg/kg 26 43 DETSC 2325# 0.05 mg/kg < 0.05 < 0.05 DETSC 2301# 1 mg/kg 17 33 DETSC 2301# 0.5 mg/kg 0.5 < 0.5 DETSC 2301# 1 mg/kg 66 58 DETSC 2008# pH 6.9 7.0 DETSC 2130# 0.1 mg/kg 0.3 0.1 DETSC 2002# 0.1 % 1.9 1.0 DETSC 2024* 10 mg/kg 16 20 DETSC 2321# 0.01 % 0.04 0.01 DETSC 3321* 0.01 mg/kg < 0.01 < 0.01 DETSC 3321* 0.01 mg/kg < 0.01 < 0.01 DETSC 3321* 0.01 mg/kg < 0.01 < 0.01 DETSC 3521# 1.5 mg/kg < 1.50 < 1.50 DETSC 3521# 1.2 mg/kg < 1.20 < 1.20 DETSC 3521# 1.5 mg/kg < 1.50 < 1.50 DETSC 3521# 3.4 mg/kg < 3.40 < 3.40 DETSC 3521* 10 mg/kg < 10.00 < 10.00 DETSC 3321* 0.01 mg/kg < 0.01 < 0.01 DETSC 3321* 0.01 mg/kg < 0.01 < 0.01 DETSC 3321* 0.01 mg/kg < 0.01 < 0.01 DETSC 3521# 0.9 mg/kg < 0.90 < 0.90 DETSC 3521# 0.5 mg/kg < 0.50 < 0.50 DETSC 3521# 0.6 mg/kg < 0.60 < 0.60 DETSC 3521# 1.4 mg/kg < 1.40 < 1.40 DETSC 3521* 10 mg/kg < 10.00 < 10.00 DETSC 3521* 10 mg/kg < 10.00 < 10.00 DETSC 3321# 0.01 mg/kg < 0.01 < 0.01 DETSC 3321# 0.01 mg/kg < 0.01 < 0.01 DETSC 3321# 0.01 mg/kg < 0.01 < 0.01 DETSC 3321# 0.01 mg/kg < 0.01 < 0.01 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 Metals Inorganics Petroleum Hydrocarbons PAHs Naphthalene Acenaphthylene Aromatic C5-C35 TPH Ali/Aro Total C5-C35 Benzene Ethylbenzene Toluene Xylene Aromatic C7-C8 Aromatic C8-C10 Aromatic >EC10-EC12 Aromatic >EC12-EC16 Aromatic >EC16-EC21 Aromatic >EC21-EC35 Aliphatic >EC10-EC12 Aliphatic >EC12-EC16 Aliphatic >EC16-EC21 Aliphatic >EC21-EC35 Aliphatic C5-C35 Aromatic C5-C7 Organic matter Sulphide Sulphate as SO4, Total Aliphatic C5-C6 Aliphatic C6-C8 Aliphatic C8-C10 Mercury Nickel Selenium Zinc pH Cyanide, Total Arsenic Boron, Water Soluble (2.5:1) Cadmium Chromium Copper Lead Symbol key at end of report Page 2 of 5
Page 209
Summary of Chemical Analysis Soil Samples Our Ref 25-14589 Client Ref ~ 10202-25 Contract Title ~ John Kane Lab No 2530130 2530131 Sample ID ~ TP1 TP2 Depth ~ 0.40 1.10 Other ID ~ Sample Type ~ SOIL SOIL Sampling Date ~ 24/06/2025 24/06/2025 Sampling Time ~ n/s n/s Test Method LOD Units DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 0.1 mg/kg < 0.10 < 0.10 DETSC 3301 1.6 mg/kg < 1.6 < 1.6 DETSC 2130# 0.3 mg/kg < 0.3 < 0.3 Phenols Benzo(a)pyrene Indeno(1,2,3-c,d)pyrene Dibenzo(a,h)anthracene Benzo(g,h,i)perylene PAH 16 Total Phenol - Monohydric Fluoranthene Pyrene Benzo(a)anthracene Chrysene Benzo(b)fluoranthene Benzo(k)fluoranthene Acenaphthene Fluorene Phenanthrene Anthracene Symbol key at end of report Page 3 of 5
Page 210
Summary of Asbestos Analysis Soil Samples Our Ref 25-14589 Client Ref ~ 10202-25 Contract Title ~ John Kane Lab No Sample ID Material Type Result Comment* Analyst 2530130 TP1 0.40 SOIL NAD none Josh Best 2530131 TP2 1.10 SOIL NAD none Josh Best Crocidolite = Blue Asbestos, Amosite = Brown Asbestos, Chrysotile = White Asbestos. Anthophyllite, Actinolite and Tremolite are other forms of Asbestos. Samples are analysed by DETSC 1101 using polarised light microscopy in accordance with HSG248 and documented in-house methods. NAD = No Asbestos Detected. Where a sample is NAD, the result is based on analysis of at least 2 sub-samples and should be taken to mean 'no asbestos detected in sample'. Key: * -not included in laboratory scope of accreditation. Symbol key at end of report Page 4 of 5
Page 211
Information in Support of the Analytical Results Our Ref 25-14589 Client Ref ~ 10202-25 Contract ~ John Kane Containers Received & Deviating Samples Lab No Sample ID ~ Date Sampled ~ Containers Received Holding time exceeded for tests Incorrect container for tests 2530130 TP1 0.40 SOIL 24/06/25 GJ 60ml, PT 1L 2530131 TP2 1.10 SOIL 24/06/25 GJ 250ml, GJ 60ml, PT 1L Soil Analysis Notes Inorganic soil analysis was carried out on a dried sample, crushed to pass a 250µm sieve Organic soil analysis was carried out on an 'as received' sample. Organics results are corrected for moisture and expressed on a dry weight basis. The Loss on Drying, used to express organics analysis on an air dried basis, is carried out at a temperature of 28°C +/-2°C. Disposal From the issue date of this test certificate, samples will be held for the following times prior to disposal :- Soils - 1 month, Liquids - 2 weeks, Asbestos (test portion) - 6 months Key: ~ Sample details are provided by the client and can affect the validity of the results * -not accredited. # -MCERTS (accreditation only applies if report carries the MCERTS logo). $ -subcontracted. n/s -not supplied. I/S -insufficient sample. U/S -unsuitable sample. t/f -to follow. nd -not detected. End of Report Ver 25.03.07 Key: G-Glass P-Plastic J-Jar T-Tub Normec DETS cannot be held responsible for the integrity of samples received whereby the laboratory did not undertake the sampling. In this instance samples received may be deviating. Deviating Sample criteria are based on British and International standards and laboratory trials in conjunction with the UKAS note 'Guidance on Deviating Samples'. All samples received are listed above. However, those samples that have additional comments in relation to hold time, inappropriate containers etc are deviating due to the reasons stated. This means that the analysis is accredited where applicable, but results may be compromised due to sample deviations. If no sampled date (soils) or date+time (waters) has been supplied then samples are deviating. However, if you are able to supply a sampled date (and time for waters) this will prevent samples being reported as deviating where specific hold times are not exceeded and where the container supplied is suitable. Symbol key at end of report Page 5 of 5
Page 212
Phase 2 Geoenvironmental Risk Assessment & Exploratory Ground Investigation 104 Willougby StreetMuthill Perthshire PH5 2AE 14 Appendix 4 – Revised Conceptual Site Model (CSM)
Page 213
Campbell of Doune Ltd Consulting Civil and Structural Engineers 78 King Street, Crieff, Perthshire, PH7 3HB Registered Office: Macfarlane Gray Accountants, Macfarlane Gray House, FOR AT REVISION: Registered in Scotland No. 277704 Tel: 01764 655459 DATE: A family business since 1860 q BS5502 Class II Agricultural q BS5950 Industrial BUILDING DESIGN CLASSIFICATION q Domestic q Other DESIGN CHECK LEVEL q DCL1 - Self Check q DCL2 - Simple Check q DCL3 - Intermediate Check q DCL4 - Extended Check e-mail: info@campbellofdoune.co.uk Castlecraig Business Park, Springburn Road, Stirling, FK7 7WT www.campbellofdoune.co.uk DRAWN SCALE DRAWING No.DATE PAPER SIZE CONTACT WEB Job No. Drawing Status 10202-25 Phase 1 Risk Assessment - Proposed Domestic Dwelling - 104 Willoughby Street, Muthill, Perthshire, PH5 2AE Mr John Kane CONCEPTUAL SITE MODEL SOURCE - PATHWAY - RECEPTOR KG AS Noted 28/07/25 001 A3 X X R1 P2 P1 R2 SOURCE S1 = Made Ground PATHWAY P1 = Human Uptake P2 = Root Uptake RECEPTOR R1 = Onsite Users / Site Workers R2 = Flora & Fauna KEY Topsoil & Grass Vegetation = Subsoils = Water Table = Pathway = S1
Page 214
No embedded text on this page.