MINUTES of MEETING of PLANNING, PROTECTIVE SERVICES AND LICENSING COMMITTEE
held BY MICROSOFT TEAMS on WEDNESDAY, 28 SEPTEMBER 2022 
Present: Councillor Kieron Green (Chair) 
Councillor John Armour
Councillor Jan Brown
Councillor Amanda Hampsey
Councillor Graham Hardie
Councillor Fiona Howard
Councillor Willie Hume 
Councillor Mark Irvine
Councillor Andrew Kain
Councillor Liz McCabe
Councillor Luna Martin
Councillor Peter Wallace 
Attending: Stuart McLean, Committee Manager
Peter Bain, Development Manager
Alan Morrison, Regulatory Services and Building Standards Manager
Matt Mulderrig, Development Policy and Housing Strategy Manager
Howard Young, Area Team Leader (Bute & Cowal/Helensburgh & Lomond)
Arlene Knox, Senior Planning Officer
David Moore, Senior Planning Officer
Norman Shewan, Planning Officer
Derek Wilson, Development Management Officer
Steven Gove, Planning Officer
Kim de Buiteleir, Design and Conservation Officer
Donna Lawson, Traffic and Development Officer 
1. APOLOGIES FOR ABSENCE 
Apologies for absence were received from Councillors Audrey Forrest, Daniel Hampsey
and Paul Kennedy. 
2. DECLARATIONS OF INTEREST 
Councillor Mark Irvine declared a non-financial interest in planning application reference
21/01943/PP as he had submitted representations on behalf of his constituents.  He
confirmed he would leave the meeting and take no part in the consideration of this
application dealt with at item 4 of this Minute. 
3. MINUTES 
a) The Minute of the Planning, Protective Services and Licensing Committee held on 17
August 2022 at 10.30 am was approved as a correct record. 
b) The Minute of the Planning, Protective Services and Licensing Committee held on 17
August 2022 at 2.00 pm was approved as a correct record. 
c) The Minute of the Planning, Protective Services and Licensing Committee held on 17
August 2022 at 2.30 pm was approved as a correct record. 
d) The Minute of the Planning, Protective Services and Licensing Committee held on 17
August 2022 at 3.00 pm was approved as a correct record.

Page 2

e) The Minute of the Planning, Protective Services and Licensing Committee held on 17
August 2022 at 3.30 pm was approved as a correct record. 
Having previously declared an interest in the following item, Councillor Mark Irvine left the
meeting at this point. 
4. MR PAUL RODGER: DEMOLITION OF DETACHED DWELLINGHOUSE,
ERECTION OF 3 DETACHED DWELLINGHOUSES AND FORMATION OF
VEHICULAR ACCESS: PEAT KNOWE, BACK ROAD, CLYNDER,
HELENSBURGH (REF: 21/01943/PP) 
At the PPSL Committee meeting on 17 August 2022, Members agreed to continue
consideration of this application to the September PPSL Committee to allow the Applicant
the extended opportunity to prepare and submit a Civil Engineering Report on the ground
engineering works required to ensure stability of the slopping ground to prevent any
slippage or flooding onto neighbouring properties. 
The Planning Officer spoke to the terms of supplementary report 3 which advised of the
detail of the investigative work carried out by the Applicant’s consultant, Ardmore Point Ltd
which provides Geomatics, Geotechnical, Drone UAV and Construction Management
Services.  This work included a desktop assessment of relevant information and
documentation already available supplemented by a walkover survey in July 2022.  A
further assessment based on in-situ testing and intrusive ground investigation including
boreholes was also carried out. 
The conclusions as set out the covering letter from the Applicant’s consultant, based on
the desk-top and site investigation survey information contend that the existing site is
stable in its current state, and “subject to a suitably designed retaining wall to the front”,
the ground would be stable for the intended road development. 
On this basis it is recommended that the application be approved, subject to the
conditions and advisory notes as set out in full in the main report of handling with the
exception of an additional planning condition as detailed in supplementary report number
3. 
Decision 
The Committee agreed to grant planning permission subject to the following conditions
and reasons and the advisory notes detailed in the report of handling: 
1. The development shall be implemented in accordance with the details specified on the
application form dated 10th October 2021, supporting information and, the approved
drawings listed in the table below unless the prior written approval of the planning
authority is obtained for an amendment to the approved details under Section 64 of the
Town and Country Planning (Scotland) Act 1997. 
Plan Title. Plan Ref. No. Version Date Received
Location Plan PL-659-00 A 20.10.2021
Existing Site Plan PL-659-01 - 13.09.2021
Proposed Site
Plan, Elevations
and Sections
PL-659-02 C 24.05.2022

Page 3

Proposed
Floorplans and
Site Elevation
PL-659-03 B 20.10.2021
Site Section E-E
& Photographs
PL-659-04 - 24.05.2022 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details. 
2. Notwithstanding the provisions of Condition 1, no development shall commence until
the following information is submitted to and approved in writing by the planning
authority in consultation with the Area Roads Engineer; - 
 A scaled drawing showing a long section demonstrating that the following gradients
can be achieved. The gradient of the new shared driveway shall be no steeper than
1 in 20 (5%) over the first 5 metres and thereafter no greater than 1 in 8 (12.5%). 
Thereafter the proposed access shall be formed in accordance with the following
criteria: - 
 Visibility splays in both directions of 2.40 metres to point X by 42 metres to point Y
from the centre line of the proposed access.
 The first 5.0 metres of the shared access driveway shall be surfaced with a
bituminous material or other alternative hard material approved in writing by the
planning authority.
 The driveway shall be formed in accordance with the approved minimum gradients.
 Surface water must not be able to flow from the site onto the public carriageway. 
Prior to work starting on site the access hereby approved shall be formed to at least
base course standard and the visibility splays shall be cleared of all obstructions such
that nothing shall disrupt visibility from a point 1.05 metres above the access at point X
to a point 0.6 metres above the public road carriageway at point Y. The final wearing
surface on the access shall be completed prior to the first occupation of any of the
houses and the visibility splays shall be maintained clear of all obstructions thereafter. 
Reason: In the interests of road safety and to ensure that the proposed development is
implemented in accordance with the provisions of the Local Development Plan policy
LDP 11 and SG LDP TRAN 4. 
3. Notwithstanding the provisions of Condition 1, no development shall commence until
full details of the layout and surfacing of a parking and turning area to accommodate 3
no. vehicles per dwellinghouse within the application site have been submitted to and
approved in writing by the Planning Authority in consultation with the Council’s Roads
Engineers. The duly approved scheme shall be implemented in full prior to the
development first being occupied and shall thereafter be maintained clear of
obstruction for the parking and manoeuvring of vehicles. 
Reason: In the interest of road safety. 
4. No development shall commence until a scheme of boundary treatment, surface
treatment and landscaping has been submitted to and approved in writing by the

Page 4

Planning Authority. The scheme shall comprise a planting plan and schedule which
shall include details of: 
(i) Existing and proposed ground levels in relation to an identified fixed datum;
(ii) Existing landscaping features and vegetation to be retained;
(iii) Location design and materials of proposed walls, fences and gates;
(iv) A biodiversity statement demonstrating how the planting strategy contributes
towards biodiversity and creation of wildlife habitat;
(v) Proposed soft and hard landscaping works including the location, species and size
of every tree/shrub to be planted;
(vi) A programme for the timing, method of implementation, completion and subsequent
on-going maintenance. 
All of the hard and soft landscaping works shall be carried out in accordance with the
approved scheme unless otherwise approved in writing by the Planning Authority. 
Any trees/shrubs which within a period of five years from the completion of the
approved landscaping scheme fail to become established, die, become seriously
diseased, or are removed or damaged shall be replaced in the following planting
season with equivalent numbers, sizes and species as those originally required to be
planted unless otherwise approved in writing by the Planning Authority. 
Reason: To assist with the integration of the proposal with its surroundings in the
interest of amenity and to encourage biodiversity and provide compensatory species
habitat in order to mitigate against loss of habitat potential as a result of site clearance. 
5. Notwithstanding the provisions of Condition 1, no development shall commence until
full details of the intended means of surface water drainage to serve the development
have been submitted to and approved in writing by the Planning Authority. The design
shall incorporate a surface water drainage system which is consistent with the
principles of Sustainable urban Drainage Systems (SuDS) compliant with the guidance
set out in CIRIA’s SuDS Manual C753. 
The duly approved scheme shall be implemented in full concurrently with the
development that it is intended to serve and shall be operational prior to the occupation
of the development and maintained as such thereafter. 
Reason: To ensure the provision of an adequate surface water drainage system and to
prevent flooding of nearby properties and/or the public adopted roads in accordance
with the provisions of policy LDP 10 and SG LDP SERV 2. 
6. Notwithstanding the provisions of Condition 1, construction activity shall be restricted
to between the hours of 08:00 – 18:00 Mon-Fri and to 08.00 - 12.00 on Saturdays. No
construction activity shall take place outside of those periods or at any time on
Sundays and Bank Holidays when such activity shall not be permitted at all. 
Reason: In order to protect the amenity of the area. 
7. Notwithstanding the provisions of the Town and Country Planning (General Permitted
Development) (Scotland) Order 1992 (as amended), (or any Order revoking and re-
enacting that Order(s) with or without modifications), nothing in Article 2(4) of or the
Schedule to that Order, shall operate so as to permit, within the area subject of this
permission, any development referred to in Part 1 and Classes 1A, 1B, 1D, 2A, 2B, 3A,

Page 5

3C, 3D and 3E and Part 2 and Classes 8 and 9 of the aforementioned Schedule, as
summarised below:  
PART 1: DEVELOPMENT WITHIN THE CURTILAGE OF A DWELLINGHOUSE 
Class 1A: Any enlargement of a dwellinghouse by way of a single storey ground floor
extension, including any alteration to the roof required for the purpose of the
enlargement. 
Class 1B: Any enlargement of a dwellinghouse by way of a ground floor extension
consisting of more than one storey, including any alteration to the roof required for the
purpose of the enlargement. 
Class 1D: Any enlargement of a dwellinghouse by way of an addition or alteration to its
roof. 
Class 2A: The erection, construction or alteration of any access ramp outside an
external door of a dwellinghouse. 
Class 3A: The provision within the curtilage of a dwellinghouse of a building for any
purpose incidental to the enjoyment of that dwellinghouse or the alteration,
maintenance or improvement of such a building. 
Class 3C: The provision within the curtilage of a dwellinghouse of a hard surface for
any purpose incidental to the enjoyment of that dwellinghouse or the replacement in
whole or in part of such a surface. 
Class 3D: The erection, construction, maintenance, improvement or alteration of any
deck or other raised platform within the curtilage of a dwellinghouse for any purpose
incidental to the enjoyment of that dwellinghouse. 
Class 3E: The erection, construction, maintenance, improvement or alteration of any
gate, fence, wall or other means of enclosure any part of which would be within or
would bound the curtilage of a dwellinghouse. 
Reason: To protect the sensitive area and the setting of the proposed dwellinghouse,
in the interest of visual amenity and public health, from unsympathetic siting and
design of developments normally carried out without planning permission; these
normally being permitted under Article 2(4) of the Town and Country Planning (General
Permitted Development) (Scotland) Order 1992 (as amended). 
8. Notwithstanding the effect of Condition 1, no development shall commence until written
details of the type and colour of materials to be used in the construction of walls, roofs,
window and door frames have been submitted to and approved in writing by the
Planning Authority. The development shall thereafter be completed using the approved
materials or such alternatives as may be agreed in writing with the Planning Authority. 
Reason: In order to integrate the development into its surroundings. 
9. The existing core footpath C283 which follows the public roads including Pier Road
and Back Road directly adjoining the application site the site shall be retained free
from obstruction across its full width, including by construction vehicles, plant or
materials associated with the proposed development, unless alternative provision has

Page 6

been implemented with the prior written approval of the Planning Authority in
consultation with the Council’s Access Officer. 
Reason: In order to maintain pedestrian access. 
10. Notwithstanding the provisions of Condition 1, no development shall commence until
full technical construction details of the proposed retaining wall, including the means of
vehicle restraint, directly adjacent to the east of the proposed shared roadway have
been submitted to and approved in writing by the Planning Authority. The retaining wall
and vehicle restraint barrier shall be implemented in full in accordance with the
approved details prior to commencement of any other development on the site in
relation to the construction of any roads/driveways or the construction of the houses
including ground excavation, and shall be retained and maintained to the satisfaction
of the planning authority unless otherwise agreed in writing by the planning authority. 
Reason: To ensure that the proposed development does not result in any ground
instability by reason of excavation and land-raising engineering operations carried out
as part of this development, and to protect adjacent land and property from potential
damage by reason of unstable ground conditions. 
(Reference: Report by Head of Development and Economic Growth dated 8 June 2022,
Supplementary Report number 1 dated 4 August 2022, Supplementary Report number 2
dated 16 August 2022 and Supplementary Report number 3 dated 9 September 2022,
submitted) 
Councillor Luna Martin joined the meeting during consideration of the foregoing item. 
Councillor Mark Irvine returned to the meeting at this point. 
5. ARDFIN ESTATE LTD: ERECTION OF BUILDINGS TO FACILITATE
RESIDENTIAL STAFF ACCOMMODATION WITH ASSOCIATED ACCESS AND
PARKING ARRANGEMENTS: LAND NORTH EAST OF COASTGUARD
STATION, CRAIGHOUSE, ISLE OF JURA (REF: 21/02141/PP) 
The Development Management Officer spoke to the terms of the report and to
supplementary report number 1 which advised of late representations consisting of a
petition and representations from local Members.  The application seeks detailed planning
permission for the erection of staff accommodation that would be occupied by employees
of Ardfin Estate.  The proposal would provide accommodation that is suitable for longer
term occupation by employees currently living in temporary accommodation on the island.   
At the time of writing the main report of handling the proposal had been subject to an
expression of concern from Jura Community Council and objections from 24 individuals. 
In light of significant local objection to the development Officers considered that a pre-
determination hearing would, in this instance, add value to the decision making process. 
The Committee were asked to consider whether or not they would wish to hold a hearing
for this application.

Page 7

Decision 
The Committee agreed to hold a discretionary pre-determination hearing on the island of
Jura. 
(Reference: Report by Head of Development and Economic Growth dated 14 September
2022 and supplementary report number 1 dated 27 September 2022, submitted) 
6. MR KEITH TURNER: USE OF ENTIRE GROUND FLOOR PREMISES AS FOOD
AND DRINK ESTABLISHMENT (CLASS 3) AND USE OF NORTH EASTERN
PART AS AN ANCILLARY SPACE FOR EVENTS (CLASS 10): FIVE WEST,
ROYAL BUILDINGS, TIGHNABRUAICH (REF: 21/02608/PP) 
The Planning Officer spoke to the terms of the report and to supplementary report number
1 which advised of late representations.  He also advised of a further late objection
submitted by Mrs Karen Raeburn on 27 September 2022 regarding residential privacy and
amenity, along with an email received this morning enclosing an objection from Mr and
Mrs Raeburn’s solicitors expanding on the issues previously raised by Mr and Mrs
Raeburn.   
The application site is within the row of commercial properties situated at the centre of the
village of Tighnabruaich.  It is located on the ground floor of a two-storey building with attic
accommodation that incorporates three residential flats.  Planning permission
20/00227/PP was approved on 17 April 2020 in relation to the ‘use of ground floor
premises as food and drink establishment (class 3) and multi-functional space (class 10)”
and, in early September 2020, the Planning Department was advised that the entire
ground floor premises had opened as a Class 3 food and drink establishment.  The
current application has been submitted in order to regularise this use.  The application has
attracted objections from 3 sources and expressions of support from 57 sources. 
The proposal is considered to be consistent with the relevant provisions of the
Development Plan and it was recommended that planning permission be granted subject
to the conditions, reasons and informative notes set out in the report. 
Decision 
The Committee agreed to grant planning permission subject to the following conditions,
reasons and informative notes 
1. The development shall be implemented in accordance with the details specified on
the application form dated 7th December 2021; supporting information; and the
approved drawings listed in the table below unless the prior written approval of the
planning authority is obtained for an amendment to the approved details under
Section 64 of the Town and Country Planning (Scotland) Act 1997. 
Plan Title.  Plan Ref. No. Version Date
Received
Location Plan  Drawing No. 574_01  C 21/04/2021
Block Plan  Drawing No. 574_02 C 21/04/2021
As Proposed Plan  Drawing No. 574_03 E 21/04/2021

Page 8

Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details. 
2. Unless otherwise agreed in writing with the Planning Authority, the opening hours of
the premises for customers or patrons shall be between 0800 hours and 2100 hours
on any given day.  
Reason: In order to protect the privacy and amenity of the area. 
NOTES TO APPLICANT 
 It is strongly recommended that the applicant engage with all relevant parties with the
objective of connecting the premises currently known as Five West into the Scottish
Water foul drainage system. Such parties would include the other owners of the
property known as Royal Buildings; Scottish Water; and the Scottish Environment
Protection Agency (SEPA). 
 The Environmental Health Service has stated that, should the applicant intend to
make any structural alterations or to change the layout of the food preparation area,
they should make contact with the Environmental Health Officer (Pamela Fraser on
01369 708686 or at pamela.fraser@argyll-bute.gov.uk) prior to starting works. 
(Reference: Report by Head of Development and Economic Growth dated 20 September
2022 and supplementary report number 1 dated 27 September 2022, submitted) 
Councillors Willie Hume and Peter Wallace left the meeting during consideration of the
foregoing item. 
7. ARGYLL COMMUNITY HOUSING ASSOCIATION: DEMOLITION OF FIVE
TENEMENT BLOCKS COMPRISING 46 FLATS: BLOCK A 19-9E JOHN
STREET, BLOCK C (1-5 DALINTOBER AND 24-26 HIGH STREET), JOHN
STREET, PRINCE'S STREET AND HIGH STREET, CAMPBELTOWN (REF:
21/02738/LIB) 
The Development Manager spoke to the terms of the report.  The application seeks listed
building consent for the substantial demolition of a category B listed building as a means
to facilitate the redevelopment of the site by a Registered Social Landlord to provide
affordable housing. 
National policy and guidance is provided respectively in Scottish Planning Policy and
Historic Environment Scotland’s Managing Change Demolition publication.  The latter
setting out a presumption against the demolition of listed buildings except where it can be
satisfactorily demonstrated that either i) the building no longer merits being listed; and/or
ii) that the building is incapable of meaningful repair; and/or iii) that the demolition is
essential to delivering significant benefits to economic growth or the wider community. 
Policy LDP ENV 3 and SG LDP ENV 16(b) of the Argyll and Bute Local Development Plan
2015 set out similar protection for the historic built environment. 
The Applicant has sought to demonstrate in their submission that the building is incapable
of meaningful repair or reuse in any manner that would both retain the special
characteristics of the building and provide a viable modern housing development that
meets the requirements of the Applicant and the Campbeltown community.  Historic

Page 9

Environment Scotland (HES) have formally objected to the application and raise concern
that, in their opinion, the Applicant has not exhausted consideration of all viable options for
re-use/partial retention of the building, and that in the absence of the property being
marketed, it cannot be satisfactorily established that demolition is acceptable as a means
of last resort. 
It is the consideration of Officers, notwithstanding the concerns raised by Historic
Environment Scotland in their objection, that the Applicant has satisfactorily demonstrated
that the category B listed building is incapable of meaningful repair or reuse for modern
purposes without loss of the key attributes of its distinctive massing and external
architectural form that provides its special interest.  Furthermore, it is recognised that the
demolition of the building would facilitate the redevelopment of the site for affordable
housing that would be tailored to meet the housing demand of the local community and
would contribute toward local and national targets for delivery of new affordable housing. 
It was recommended the Council determine to grant listed building consent subject to the
conditions and reasons detailed in the report, and accordingly, notify the decision to
Scottish Minsters in light of objections from a statutory consultee. 
Decision 
The Committee determined to grant listed building consent subject to the following
conditions and reasons and noted that this decision would be notified to Scottish Ministers
in light of the objections from Historic Environment Scotland: 
1. LIB - Approved Details & Standard Notes – Non EIA Development 
The development shall be implemented in accordance with the details specified on the
application form dated 24.12.2022, supporting information and, the approved drawings
listed in the table below. 
Plan Title. Plan Ref. No. Version Date Received
Location Plan 20351-ECD-XX-
XX-DR-A-07001
PO2 14.09.2022
Site Plan 200351-ECD-
XX-XX-DR-A-
05100
PO2 14.03.2022
Plans and
Elevations as
Existing
200351-ECD-
XX-XX-DR-A-
05101
PO2 14.09.2022 
Reason: For the purpose of clarity, to ensure that the development is implemented in
accordance with the approved details. 
Note to Applicant: 
This consent will last only for three years from the date of this decision notice, unless
the development has been started within that period [See section 16 of the Planning
(Listed Building and Conservation Areas) (Scotland) Act 1997 (as amended).]

Page 10

2. No Demolition Until A Contract Has Been Let For Redevelopment 
No demolition works shall commence until satisfactory evidence has been submitted to
the Planning Authority to show that a contract has been let for the redevelopment of
the whole site in accordance with proposals for which detailed planning
permission/approval of matters specified in conditions has been obtained. 
Reason: In order to protect the amenity of the locale and the built environment by
preventing the premature demolition of the property concerned, and in order to
underpin the justification for development of the building as being essential to
delivering significant benefits to the wider community. 
Note to Applicant: 
 Under the terms of the Planning (Listed Buildings and Conservation Areas)
(Scotland) Act 1997, section 7(2)(b)(c), applicants receiving consent for works of
demolition to a listed building/unlisted building in a conservation area must: notify
RCAHMS of their intention to carry out the work; thereafter allow RCAHMS
reasonable access to record the building for at least 3 months following the
granting of consent and the giving of notice to the Commission, during which time
demolition may not be undertaken unless RCAHMS has indicated in writing that its
record has been completed or that they do not wish to record it.  The RCAHMS
contact details are as follows: 
The Royal Commission on Ancient Historical Monuments (RCAHMS), 
Threatened Buildings Survey, 
John Sinclair House, 
16 Bernard Terrace, 
Edinburgh, EH8 9NX.  
Tel. 0131 651 6773 
3. Demolition Method Statement 
No demolition works shall commence until a Demolition Method Statement has been
submitted to and approved in writing by the Planning Authority. The Demolition Method
Statement shall address the developer’s intentions in respect of: 
 Demolition Methodology - Type and sequence of demolition and site establishment;
 Disposal of Waste Materials – details of the intended means of disposing of all
materials arising from the demolition including any special arrangements required
for the potential removal and disposal of hazardous materials; 
 Notification of demolition to adjacent property owners and local residents;
 Dust & Noise Reduction Strategy - steps to be taken to minimise the risk and
nuisance to adjoining land, building or road users;
 Proximity to Buildings, Other Structures, Roads and Accesses – measures to
protect structural integrity, to ensure exposed gables remain weather tight and
protection of means of access;
 Traffic Management – to protect safety of pedestrians and vehicular traffic. 
The development shall be implemented in accordance with the approved Demolition
Method Statement, unless otherwise approved in writing by the Planning Authority.

Page 11

Reason: In the interest of public safety and in order to protect the amenity of the locale
and the built environment. 
Note to Applicant: 
In devising the Demolition Method Statement consultation should take place with the
Council’s Building Standards Officers, Environmental Health Officers and the Roads
Authority to ensure compliance with other statutory requirements. 
4. Reclamation of Materials 
No demolition works shall commence until a schedule of items to be reclaimed from
the site during or prior to demolition has been drawn up in consultation with, and
approved in writing by the Planning Authority. These materials and items shall be
satisfactorily set aside, stored and/or used in a manner which shall first be agreed with
by the Planning Authority, prior to any demolition taking place. 
Reason: In order to protect and save materials and items which can reasonably be
retrieved, in the interests of the historical and architectural qualities of the building to
be demolished. 
Note to Applicant: 
Consultation with the Council’s Design & Conservation Officer should be undertaken in
identifying items to be reclaimed. 
(Reference: Report by Head of Development and Economic Growth dated 13 September
2022, submitted) 
8. THE SCOTTISH GOVERNMENT ON BEHALF OF ENERGIEKONTOR UK LTD:
ELECTRICITY ACT SECTION 36 CONSULTATION RELEVANT TO ROWAN
WIND FARM: LAND APPROXIMATELY 4.5KM NORTH WEST OF TARBERT,
ARGYLL & BUTE (REF: 22/00385/S36) 
The Senior Planning Officer spoke to the terms of the report and to supplementary report
number 1 which advised of errors in the main report and concerns raised by the Applicant. 
Reference was also made to supplementary report number 2 which advised of a
representation from Councillor Ross Moreland.  The Committee were also advised of 2
further representations received this morning, one in support from Mr Jonathan Shieldrick,
which she believed had been circulated to the Committee, and an objection relating to
amplitude modulation syndrome and shadow flicker. The Senior Planning Officer
confirmed that Planning were satisfied with the proposal in terms of shadow flicker and
that the Council’s Environmental Health Officer had advised that amplitude modulation
was a matter for the Energy Consents Unit to consider and that this could be controlled
with a condition. 
In Scotland, any application to construct or operate an onshore power generating station,
in this case, a renewable energy development with an installed capacity of over 50
megawatts, requires the consent of Scottish Ministers under Section 36 of the Electricity
act 1989.  Any ministerial authorisation given would include a ‘deemed planning
permission’ and in these circumstances there is then no requirement for a planning
application to be made to the Council as Planning Authority.  The Council’s role in this
process is one of a consultee along with various other consultation bodies.  It is open to

Page 12

the Council to either support or object to the proposal, and to recommend conditions it
would wish to see imposed in the event that authorisation is given by the Scottish
Government.  In the event of an objection being raised by the Council, the Scottish
Ministers are obliged to convene a Public Local Inquiry if they are minded to approve the
proposal. 
The proposed development site lies within the Knapdale Upland Forest Moor Mosaic
Landscape Character Type which covers much of the Knapdale area between West Loch
Tarbert and the southern edge of the Knapdale National Scenic Area.  In term of the Local
Development Plan, the main wind farm area is located primarily within a combination of
Countryside Zone and Very Sensitive Area, with small areas adjacent to the B8024
located within Rural Opportunity Area. 
This report reviews the policy considerations which are applicable to this proposal and the
planning merits of the development, the views of bodies consulted by the Scottish
Government along with other consultations undertaken by the Council, and third party
opinion expressed to the Scottish Government.   
It was recommended that the Council raise an objection to this Section 36 consultation on
Landscape & Visual Grounds for the reasons detailed in the report of handling. 
Decision 
The Committee agreed, on behalf of the Council, as Planning Authority, to object to this
proposal for the following reasons and that the Scottish Government be notified
accordingly: 
1. Landscape & Visual Impact (including cumulative) 
Argyll & Bute Council will assess development proposals with the aim of protecting
conserving and where possible enhancing the built, human and natural environment. 
A development proposal will not be supported when it does not protect, conserve or
where possible enhance the established character and local distinctiveness of the
landscape in terms of its location, scale, form and design.  Argyll & Bute Council will
resist renewable energy developments where these are not consistent with the
principles of sustainable development and it has not been adequately demonstrated
that there would be no unacceptable significant adverse landscape and visual impacts,
whether individual or cumulative. 
The proposed development site lies within the Knapdale Upland Forest Moor Mosaic
Landscape Character Type (LCT) which covers much of the Knapdale area between
West Loch Tarbert and the southern edge of the Knapdale National Scenic Area. This
landscape has a simpler landform in the south-west but is complex and craggy in the
north-east. The operational Allt Dearg and Srondoire wind farms occupy a prominent
location in the LCT. The consented Airigh wind farm, while comprising larger turbines,
is associated with the more subdued terrain occurring in the south-west of this LCT. 
This proposal, which comprises very large turbines of up to 200m, would be sited in a
basin which reduces its prominence and intrusion seen from Loch Fyne and from the
settled eastern coastal fringes of this loch. The containment provided by landform is
diminished in views from the south around West Loch Tarbert however where turbines
would be visible in closer proximity and where their scale would be more appreciated

Page 13

due to greater visual exposure and because they would be seen in close conjunction
with the smaller scale settled loch fringes. 
Visibility from the northern shores of West Loch Tarbert will be minimal and while this
proposal would be visible from parts of Gigha, the Ardpatrick Point area and from the
west Kintyre coast, it would not have a significant effect due to the greater distances
involved and also because of the presence of the consented Airigh wind farm which is
more prominent in some of these views. The greatest degree of visibility (and intrusion)
would occur from the waters of West Loch Tarbert, from its south-eastern coastal
fringes and from parts of the northern Kintyre uplands. 
Significant adverse effects would occur on the following landscape/seascape character
areas: 
 The Knapdale Upland Forest Moor Mosaic LCT extending approximately 2km from
the proposed wind farm site 
 The Rocky Mosaic LCT where it covers the south-eastern shores of West Loch
Tarbert 
 The West Loch Tarbert Local Coastal Character Area. 
The significant adverse visual effects associated with the proposal would principally
affect views in the West Loch Tarbert area as follows: 
 The A83 where it is aligned on the south-eastern coastal fringe of West Loch
Tarbert. This road is an important tourist route forming part of National Cycle
Network 78 and the Kintyre 66. 
 The Kennacraig to Islay ferry route within inner West Loch Tarbert 
 Footpaths in the Dun Skeig area and from a section of the Kintyre Way. 
In the above views, this proposal would be seen simultaneously or sequentially with
the operational Freasdail and consented Airigh wind farms. 
This proposal would be one of the first wind farm proposal to introduce lighting to the
dark skies of Kintyre. While the intensity of lights will reduce when seen from lower
elevation coastal fringes, it is considered that they would still be clearly visible from
these more settled and frequented areas and that they may extend the duration of
significant adverse effects on views from the West Loch Tarbert area. The potential
cumulative effects of visible aviation lighting on character and views are a concern
given the number of recent applications for turbines >150m in Argyll & Bute requiring
such lighting although it should be noted that the recent Earraghail wind farm
application is committed to the adoption of an Aircraft Detection Lighting Strategy
(ADLS) which would substantially reduce the duration of night-time lighting. 
Cumulative landscape and visual effects with the application-stage Sheirdrim wind
farm are a key concern. If the Sheirdrim proposal is consented on appeal it is
considered that the addition of the Rowan proposal would result in a major adverse
combined cumulative effect on the West Loch Tarbert area significantly affecting its
character and views from the A83, settlement, footpaths and the Islay ferry. 
It is therefore concluded that this proposal is unacceptable in landscape and visual
grounds principally because of its prominent location in relation to West Loch Tarbert

Page 14

and its sensitive coastal fringes, including impacts on views from key transport routes
which are important for visitors. 
Having due regard to the above it is concluded that the proposal will have
significant adverse landscape and visual impacts (including cumulative) and is
therefore inconsistent with the provisions of: SG LDP ENV 14 –Landscape; SG 2
Renewable Energy; LDP STRAT 1 – Sustainable Development; LDP DM1 –
Development within the Development Management Zone; LDP 3 – Supporting
the Protection, Conservation and Enhancement of our Environment; Policy LDP
6 – Supporting the Sustainable Growth of Renewables; LDP 9 – Development
Setting, Layout and Design;  of the Argyll & Bute Local Development Plan; SPP
(2014); the Onshore wind policy statement, (2017); and guidance contained in
the Argyll & Bute Landscape Wind Energy Capacity Study 2017. 
2. Aviation 
Argyll & Bute Council will assess development proposals with the aim of preventing
unnecessary dangers aircraft.  Policy requires that development is refused where it
would constrain the present and future operations of existing airports and airfields. 
National Air Traffic Services Safeguarding (NATS) have advised that an unacceptable
technical impact is anticipated and they object.  Glasgow Prestwick Airport advise that
the development raises aviation safety concerns which have an operational impact on
the airport as an air navigation services provider.  Until all technical and operational
aviation safety matters are addressed to the satisfaction of Glasgow Prestwick Airport,
and a mitigation agreement is put in place for the life of the wind farm, the airport also
objects to the proposal. 
Local Development Plan Policy is clear that developments that have an adverse
impact on the Safeguarding of Airports should be refused.   
Having due regard to the above it is concluded that due to the fact that National
Air Traffic Services Safeguarding (NATS) and Glasgow Prestwick Airport have
advised the Energy Consents Unit that they object to the proposal, it will have an
adverse impact on aviation and is therefore inconsistent with the provisions of
SG 2 Renewable Energy, Policy LDP 6 – Supporting the Sustainable Growth of
Renewables and SG LDP TRAN 7 –Safeguarding of Airports of the Argyll & Bute
Local Development Plan, SPP (2014) and the Onshore Wind Policy Statement in
this respect. 
Argyll & Bute Council therefore object to the proposal due to the adverse impact
it would have on Aviation.  The Energy Consents Unit should please note that in
the event that National Air Traffic Services (NATS) and Glasgow Prestwick
Airport withdraw their objections, then Argyll & Bute Council would no longer
object on these grounds.  Should these objections not be removed and the
proposal progresses to an Inquiry, Argyll & Bute Council would defer to National
Air Traffic Services and Glasgow Prestwick Airport as the Technical Experts on
this matter. 
(Reference: Report by Head of Development and Economic Growth dated 13 September
2022, supplementary report number 1 dated 23 September 2022 and supplementary
report number 2 dated 27 September 2022, submitted)

Page 15

The Chair ruled, and the Committee agreed, to take a short break at 1.25 pm.  The
Committee reconvened at 1.40 pm. 
9. SCOTTISH HYDRO ELECTRIC TRANSMISSION PLC: CONSTRUCTION OF
APPROXIMATELY 13.3 KM OF 275KV OVER HEAD LINE (OHL) FROM
BETWEEN A PROPOSED SUBSTATION AT CREAG DHUBH TO THE EXISTING
SCOTTISH POWER ENERGY NETWORKS (SPEN) 275 KV OHL THAT RUNS
FROM DALMALLY TO INVERARNAN: LAND SOUTH OF DAMALLY AND EAST
OF CLADICH (REF: 22/01298/S37) 
The Senior Planning Officer spoke to the terms of the report and referred to late objections
submitted to this proposal including emails Councillor Julie McKenzie had received
containing objections from Mr Jon Strickland and Ms Sue Rawcliffe which had been
circulated to the Committee by Officers.  As of this morning 40 individual objections had
been placed on the Energy Consents Unit site with no matters raised that had not already
been addressed in the report. 
In Scotland, any proposal to install and keep installed an overhead electric line, requires
the consent of Scottish Ministers under Section 37 of the Electricity Act 1989.  Section
57(2) of the Town and Country Planning (Scotland) Act 1997 also allows the Scottish
Ministers, on granting consent under Section 37, to direct that planning permission for that
development shall be deemed to be granted, subject to such conditions (if any) as may be
specified in the direction. 
With reference to the assessment and summary of determining issues and material
considerations of this proposal, detailed at Section P of the report of handling, it is
considered that the proposal is in accordance with the overall Local Development Plan
policies and objectives and it was recommended that no objection be raised to this
Section 37 proposal. 
Decision 
The Committee agreed, on behalf of the Council, as Planning Authority, to object to this
proposal for the following reasons and that the Scottish Government be notified
accordingly and noted that this would instigate the requirement for a Public Local Inquiry: 
The proposal will have adverse landscape and visual impacts (including cumulative) within
an Area of Panoramic Quality, and in particular from the Duncan Ban Monument, and is
therefore inconsistent with the provisions of: LDP DM1 – Development within the
Development Management Zone; LDP 3 – Supporting the Protection, Conservation and
Enhancement of our Environment; LDP 6 – Supporting the Sustainable Growth of
Renewables; LDP 9 – Development Setting, Layout and Design; SG LDP ENV 13 –
Development Impact on Areas of Panoramic Quality; and SG LDP ENV 16(a) –
Development Impact on Listed Buildings; of the Argyll and Bute Local Development Plan. 
(Reference: Report by Head of Development and Economic Growth dated 13 September
2022, submitted) 
Councillor Peter Wallace returned to the meeting during consideration of the foregoing
item.

Page 16

10. SCOTTISH POWER ENERGY NETWORKS (SPEN) ON BEHALF OF SCOTTISH
POWER TRANSMISSION (SPT): TEMPORARY TRANSMISSION LINE
DIVERSION, ERECTION OF TWO TEMPORARY TOWERS AND ONE
PERMANENT TOWER (LINK TOWER FROM PROPOSED SSEN 13.3KM
POWER LINE TO EXISTING SCOTTISH POWER HIGH VOLTAGE NETWORK):
LAND APPROX 2KM EAST OF DALMALLY (REF: 22/01329/S37) 
The Senior Planning Officer spoke to the terms of this report.   
In Scotland, any proposal to install and keep installed an overhead electric line, requires
the consent of Scottish Ministers under Section 37 of the Electricity Act 1989.  Section
57(2) of the Town and Country Planning (Scotland) Act 1997 also allows the Scottish
Ministers, on granting consent under Section 37, to direct that planning permission for that
development shall be deemed to be granted, subject to such conditions (if any) as may be
specified in the direction. 
Officers consider that overall the landscape, ecological, historic environment and other
potential effects have been appropriately mitigated in defining the proposed development. 
In conclusion, it was recommended that no objection be raised to this Section 37 proposal. 
Decision 
The Committee agreed not to raise an objection to this Section 37 proposal. 
(Reference: Report by Head of Development and Economic Growth dated 14 September
2022, submitted) 
11. SCOTTISH HYDRO ELECTRIC TRANSMISSION PLC: PROPOSAL OF
APPLICATION NOTICE FOR FORMATION OF ACCESS
TRACKS/ARRANGEMENTS RELATING TO REFURBISHMENT WORKS ON
EXISTING 132KV OVERHEAD LINES: LAND BETWEEN SLOY SWITCHING
STATION AND GLENMALLAN (REF: 22/01023/PAN) 
The Senior Planning Officer spoke to the terms of the report.  The proposed development
will involve the formation of access tracks associated with the refurbishment of an existing
132kv overhead line.  The length of the access tracks and their site area triggers the need
for a major planning application.  This overall site is also partly within the administrative
boundary of Loch Lomond and The Trossachs National Park Authority (NPA) and
therefore a separate planning application will be submitted to the NPA for those proposed
access tracks which are within their administrative boundary. 
The report sets out the information submissions to date as part of the Proposal of
Application Notice (PAN) and summarises the policy considerations, against which any
future planning application is likely to be judged against any potential material
considerations. 
It was recommended that Members have regard to the content of the report and
submissions and provide such feedback as they consider appropriate in respect of the
PAN to allow any matters to be considered by the Applicant in finalising any future
planning application.

Page 17

Decision 
The Committee noted the content of the report and submissions with no feedback being
provided. 
(Reference: Report by Head of Development and Economic Growth dated 13 September
2022, submitted) 
12. MH PLANNING ASSOCIATES: PROPOSAL OF APPLICATION NOTICE FOR
PROPOSED TIMBER LOADING FACILITY: LAND NORTH OF
BUNNAHABHAIN, ISLE OF ISLAY (REF: 22/01516/PAN) 
The Senior Planning Officer spoke to the terms of this report.  The proposed development
will comprise construction of a pier which would extend 223m seaward from the high tide
mark and be principally comprised of a 203m long causeway crossing foreshore and
seabed built from infill rock and rock armour.  The causeway would lead out to a 20m x
38m in plan hammerhead berthing point constructed of precast concrete units.  There will
also be a timber stacking and associated earthworks. 
The report sets out the information submissions to date as part of the Proposal of
Application Notice (PAN) and summarises the policy considerations, against which any
future planning application is likely to be judged against any potential material
considerations. 
It was recommended that Members have regard to the content of the report and
submissions and provide such feedback as they consider appropriate in respect of the
PAN to allow any matters to be considered by the Applicant in finalising any future
planning application. 
Decision 
The Committee noted the content of the report and submissions with no further feedback
being provided. 
(Reference: Report by Head of Development and Economic Growth dated 14 September
2022, submitted) 
13. ARGYLL AND BUTE DESIGN AWARDS 2022/23 
Argyll and Bute Council has successfully held three rounds of Design awards over the
past ten years, the most recent being held in 2015.  In January 2020, the PPSL
Committee agreed the launch of a further round of the competition as previously identified
in the Service Plan.  The entry period was opened in early 2020 however the competition
was subsequently postponed due to Covid 19 restrictions. 
A report inviting Members to agree the proposal to facilitate the relaunch of built
environmental Design Awards in 2022 which would run to summer 2023, was considered. 
Decision 
The Committee:

Page 18

1. noted and agreed the content of this report which set out the process required to
prepare for the postponed 2020 built environment design competition to be relaunched
in 2022; 
2. agreed the inclusion of the Chair and Vice Chair as part of the judging panel; and 
3. agreed the proposed new Members’ Award as described. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 10 August 2022, submitted) 
* 14. ARGYLL AND BUTE COUNCIL'S SHORT TERM LET LICENSING SCHEME 
A report seeking approval of the arrangements for the Council’s Short-term Let Licensing
Scheme was before the Committee for consideration. 
The licensing scheme was brought in by the Scottish Government under the Civic
Government (Scotland) Act 1982 (Licensing of Short-term Lets) Order 2022, with the aim
to ensure short-term lets are safe, address issues faced by neighbours, to facilitate local
authorities knowing and understanding what is happening in their area, and handling of
complaints effectively.  It also aims to balance the economic and tourism benefits from
short-term lets with the needs and concerns of local communities to ensure the people
providing short-term lets are suitable. 
Local authorities must introduce a new mandatory licensing system for short-term lets for
the 1 October 2022 to receive applications from existing and new “hosts” and thereafter
determine them. 
Decision 
The Committee agreed to recommend to Council that they: 
1. note the considerable work undertaken to develop the new licensing regime in a
challenging timescale, and without any additional funding or resourcing from the
Scottish Government; 
2. welcome the high level of responses to the public consultation, and recognise that
many of the issues raised had been incorporated into the final licensing regime; 
3. approve the Short-term Let Licensing regime, Licensing Policy, additional conditions
and fee and charges as set out in section 5.4 and 5.6 of the report; 
4. note the intention to focus on “New hosts” initially until resources in place; and 
5. amend the Council’s Scheme of Delegation to delegate responsibility for the Civic
Government (Scotland) Act 1982 (Licensing of Short-term Lets) Order 2022 to the
Executive Director with responsibility for Regulatory Services to enable the Council’s
Environmental Health Service to authorise officers to deliver the Short-term Let
Licensing regime. 
(Reference: Report by Executive Director with responsibility for Development and Economic
Growth dated 20 September 2022, submitted)

Page 19

15. LOCAL PLACE PLANS 
A report advising Members of one of the measures which has been introduced as part of
the Government’s work on planning reforms introduced by the Planning (Scotland) Act
2019, with the publication of Local Place Plan Regulations 2021 and Planning Circular
1/2022 Local Place Plans, was before the Committee for information. 
Decision 
The Committee noted the contents of the report. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 2 September 2022, submitted) 
16. PLANNING PERFORMANCE FRAMEWORK 2021/22 
A report introducing the 2021/22 Planning Performance Framework (PPF) Annual report
as required by the Scottish Government Planning Reform Agenda was before the
Committee for information. 
Decision 
The Committee noted the contents of the report. 
(Reference: Report by Executive Director with responsibility for Development and
Economic Growth dated 14 September 2022 and Planning Performance Framework
2021/22, submitted) 
17. PRIVATE HIRE CARS AND TAXIS LICENSED  IN ARGYLL & BUTE 
A report providing an update on the number of private hire cars and taxis across the
licensing authority’s area was before the Committee for information. 
Decision 
The Committee noted the contents of the report. 
(Reference: Report by Executive Director with responsibility for Legal and Regulatory
Support dated 31 August 2022, submitted)