Democracy Spraffa

PPA-130-2084 decision notice - dated 7 November 2022

Argyll and Bute Council · 18 January 2023
Back to Planning, Protective Services and Licensing Committee — 18 January 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Planning and Environmental Appeals Division
Hadrian House, Callendar Business Park, Falkirk, FK1 1XR
E: dpea@gov.scot                                     T: 0300 244 6668
Appeal Decision Notice – EIA Development

Decision
I allow the appeal and grant planning permission subject to the 30 conditions listed at the
end of the decision notice.  Attention is drawn to the five advisory notes at the end of the
notice.
Environmental impact assessment
The proposed development is described as above, and at Chapter 5 of the EIA report.  It is
EIA development.  The determination of this appeal is, therefore, subject to the Town and
Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2017
(“the 2017 EIA regulations”).
I am required to examine the environmental information, reach a reasoned conclusion on
the significant environmental effects of the proposed development and integrate that
conclusion into this decision notice.  In that respect I have taken the following into account:
• the EIA report submitted on 5 December 2019;
• additional supplementary confidential information on ornithology submitted in
March 2020 and May 2020;
• additional supplementary information on peat management submitted in March 2020
and May 2020;
• additional supplementary information of viewpoint 19 - Inveraray Castle Garden
Bridge submitted in September 2020;
• additional supplementary information on landscape and visual matters (part 1 and
part 2) submitted in December 2020;
• consultation responses from NatureScot, Scottish Environment Protection Agency,
Scottish Water, Scottish Forestry, Transport Scotland, Historic Environment
Scotland, Ministry of Defence, Loch Lomond and the Trossachs National Park
Decision by Gordon S Reid, a Reporter appointed by the Scottish Ministers
 Planning appeal reference: PPA-130-2084
 Site address: Creag Dhubh, North East of Strachur Village, Argyll and Bute, PA32 8YH
 Appeal by Creag Dhubh Renewables LLP against the decision by Argyll and Bute Council
 Application for planning permission 19/02544/PP dated 5 December 2019 refused by
notice dated 3 March 2022
 The development proposed: construction of wind farm comprising of nine wind turbines
(maximum blade tip height 145 metres), formation of 5.6 km new access track, erection of
substation building, welfare building, temporary construction compound and two borrow
pits
 Application drawings: listed in schedule 3 below
 Date of site visit by Reporter: 6, 7 and 8 September 2022
Date of appeal decision: 7 November 2022
Appendix A

Page 2

PPA-130-2084 2 
Authority, The Royal Society for the Protection of Birds, Marine Scotland Science, 
National Air Traffic Services, Civil Aviation Authority, Glasgow Prestwick Airport, 
CSS Spectrum Management Services, Ofcom, The Joint Radio Company, Scottish 
Rights of Way Society, Argyll District Salmon Fishery Board, and Strachur 
Community Council; and,
• representations from members of the public, Mountaineering Scotland, The Argyll 
Raptor Study Group and Lochgoil Community Trust. 
I am required by the 2017 EIA regulations to include information in this decision notice in
regard to opportunities for the public to participate in the decision-making procedure.  I set
that information out in Schedule 4 below.  My conclusions on the significant environmental
effects of the proposal are set out at paragraphs 9 to 125 below. 
Reasoning 
1. I am required to determine this appeal in accordance with the development plan,
unless material considerations indicate otherwise.  Having regard to the provisions of the
development plan the main issues in this appeal are: 
 the acceptability of landscape impacts;
 the acceptability of visual impacts;
 the acceptability of cumulative landscape and visual impacts;
 the impact on tourism and recreation; and,
 the acceptability of other relevant impacts. 
The development plan 
2. The development plan consists of the Argyll and Bute Local Development Plan 2015
and adopted supplementary guidance. 
3. Given that the appeal proposal is for the development of a wind farm, policy LDP 6
(supporting the sustainable growth of renewables) and its associated supplementary
guidance SG 2 (renewable energy) are of particular relevance.  Policy LDP 6 advises that
renewable energy developments will be supported where they are consistent with the
principles of sustainable development and it can be adequately demonstrated that there
would be no unacceptable significant adverse effects, whether individual or cumulative, on
local communities, natural and historic environments, and, landscape character and visual
amenity.  The policy sets out a comprehensive list of nineteen criteria against which
applications for wind turbine developments are to be assessed.  I note that these reflect the
criteria set out in paragraph 169 of Scottish Planning Policy. 
4. SG2 provides further detail on the factors which the council will take into
consideration when determining applications for renewable energy related development.  It
includes a ‘spatial framework’ for wind farms and wind turbine developments
over 50 metres high in line with paragraph 161 and Table 1 (spatial frameworks) of Scottish
Planning Policy and identifies areas where wind farms will not be acceptable (group 1);
areas of significant protection (group 2); and, areas which may have potential for wind farm
development (group 3). 
5. The appeal site is located primarily within a group 3 area.  I note that the limited area
located within the group 2 designation is not required for any of the physical works to
accommodate the wind turbines.  Furthermore, the Scottish Environment Protection Agency

Page 3

PPA-130-2084 3
confirms that there would be no significant effects from the development within the group 2
area. 
6. Local development plan policy LDP DM 1 (development within the development
management zones) is of relevance and establishes the acceptable scale of development
within each ‘Development Management Zone’.  The Cowal and Bute Area proposals map
indicates that the appeal site is situated within the ‘very sensitive countryside’ development
management zone.  The policy generally seeks to restrict development within these areas
with the exception of renewable energy related developments, which are encouraged on
appropriate sites. 
7. Policy LDP 3 (supporting the protection, conservation and enhancement of our
environment) is of relevance and applies to all development management zones (identified
by policy LDP DM 1).  This policy requires all planning applications to be assessed with the
aim of protecting conserving and where possible enhancing the built, human and natural
environment.  The associated supplementary guidance sets out additional detail for the
specific matters covered by policy LDP 3.  The supplementary guidance of relevance is
LDP ENV 1 (development impact on habitats, species and our biodiversity); LDP ENV 11
(protection of soil and peat resources); LDP ENV 13 (development impact on areas of
panoramic quality); LDP ENV 14 (landscape); LDP ENV 15 (development impact on historic
gardens and designed landscapes); LDP ENV 16 (a) (development impact on listed
buildings); LDP ENV 19 (development impact on scheduled monuments); and, LDP ENV 20
(development impact on sites of archaeological importance). 
8. I have also taken account of the other development plan policies referred to in
submissions.  These include, policy LDP STRAT 1 (sustainable development) which sets
out the specific sustainable development principles (a to k) that all new development
proposals should be considered against; policy LDP 9 (development setting, layout and
design) which aims to achieve high quality new development that respects the local
environment and provides a sense of place; and, supplementary guidance LDP TRAN 1
(access to the outdoors) which seeks to ensure that proposed development does not
adversely affect core and other important routes including the Cowal Way long distance
route. 
Landscape impacts 
9. As part of the EIA report a landscape and visual assessment was undertaken to
identify whether any significant effects would occur to any landscapes or key views as a
consequence of the appeal proposal.  A study area comprising a 40 km radius from the
appeal site was selected.  The extent of the study area was not contended by parties.   In
terms of valued landscapes, I note that apart from the location of one turbine within the
North Argyll Area of Panoramic Quality (APQ) the remainder of the appeal site is not
located within any statutory or non-statutory landscape designation. 
10. In terms of the potential for indirect effects there are several landscape designations
within the study area.  The EIA report identifies those landscape designations where there
is the potential for significant effects from the appeal proposal.  Those designations most
likely to be affected are Loch Lomond and the Trossachs National Park, the East and West
Loch Fyne (Coast) Areas of Panoramic Quality and Inveraray Castle Garden and Designed
Landscape.  Based on the EIA report findings I am satisfied that there are no national
scenic areas, special landscape areas or wild land areas affected in this case.  I consider
the effects on each of the identified landscape designations in turn.

Page 4

PPA-130-2084 4
North Argyll Area of Panoramic Quality 
11. The EIA report predicts that there would be limited theoretical visibility (ZTV) of the
appeal proposal across the majority of the North Argyll APQ, which I note extends over a
large geography to the north of the appeal site.  Accordingly, the report concludes that
given the potential effects would be limited in number and localised in extent, there would
be no significant adverse impact on the North Argyll APQ.  I note that the council did not
include the potential impact on this area within its reasons for refusal.  Based on the
evidence within the EIA report, I am satisfied that the appeal proposal would only be visible
from within limited areas in the southernmost part of this APQ.  Given the scale of this
designation, combined with the limited extent of the theoretical visibility, I am satisfied that
the appeal proposal would not have a significant adverse impact on the landscape
character of the North Argyll APQ and would not, therefore, undermine its integrity or
special qualities.  
East Loch Fyne (Coast) APQ 
12. The EIA report predicts that there would only be limited theoretical visibility of the
appeal proposal across the East Loch Fyne (Coast) APQ given the intervening topography
and vegetation.  As such, it is concluded that the appeal proposal would not adversely
affect the special qualities of this APQ.  The council contends that the appeal proposal
would affect the special qualities including the views of the dramatic head of Loch Fyne. 
However, I note in the reasons for refusal that the council’s primary concern regarding the
head of Loch Fyne appears to relate more to views from the west side of the Loch, which is
within the West Loch Fyne (Coast) APQ. 
13. This APQ is located along the eastern side of Loch Fyne.  I observed during my visit
that given the topography and existing vegetation, there would be limited potential for views
of the appeal proposal.  Where these views would occur they would mainly be of the blade
tips, hubs and upper towers of only two of the wind turbines, with no full view of all nine
turbines from any location.  In addition, given the intervening topography and location to the
north east, I do not consider that the appeal proposal would significantly interrupt views of
the head of Loch Fyne.  Accordingly, I am satisfied that the scale of any potential adverse
effect on the landscape character would not be significant and as such would not
undermine the integrity or special qualities of the East Loch Fyne (Coast) APQ. 
West Loch Fyne (Coast) APQ 
14. For this APQ the EIA report predicts that there would be theoretical visibility of the
appeal proposal from various locations.  However, it is contended that given the perceived
scale of the proposed turbines, when combined with their location behind the containing
slopes of Creag Dhubh, they would not adversely affect the overall integrity or special
qualities of this APQ.  The council considers that the appeal proposal would affect the
special quality relating to the dramatic head of Loch Fyne and in particular from more
distant intermittent views from the north-western side of Loch Fyne (VPs 10, 11 and 16) and
from the open waters on Loch Fyne.  In addition, the council, contend that it would
adversely affect the presently open and uncluttered hills along Loch Fyne as viewed from
elevated locations, such as Dun na Cuaiche. 
15. I am satisfied on the basis of the submitted viewpoints and observations during my
visit that only blade tips and some of the hubs of the wind turbines would be visible from
locations within this APQ, due to their location behind Creag Dhubh ridge.  Given the size of
the visible elements of the turbines, in comparison to the vertical and horizontal scale of the

Page 5

PPA-130-2084 5
topography on the east side of Loch Fyne, I do not consider that they would present a
particularly dominant visual feature.  In addition, given that the appeal proposal would be
located to the southeast of this APQ, I consider that it would not be likely to interrupt the
views of the Head of Loch Fyne or the more prominent Arrochar Alps to the northeast. 
Furthermore, the appeal site is also separated from this APQ by Loch Fyne which is a
particularly strong defining landscape feature. 
16. In terms of more elevated areas such as Dun na Cuaiche, I note the council
acknowledges that the views most affected are the least dramatic, being to the southeast
rather than towards the settlement of Inveraray or the Head of Loch Fyne and the Arrochar
Alps beyond.  Although some of the hubs in addition to the blades of the turbines would be
visible from this location, I am satisfied for the reasons already stated in relation to scale
and setting above and from observations during my visit, that the appeal proposal would not
form a particularly dominant feature when viewed from this location. 
17. Accordingly, I am satisfied that the appeal proposal would not have a significant
effect on the character of the landscape of the West Loch Fyne (Coast) APQ and would not
undermine its integrity or special qualities. 
Inveraray Castle Garden and Designed Landscape 
18. The Inveraray Castle Garden and Designed Landscape is located on the western
shore of Loch Fyne, to the north of Inveraray, and some 6 km from the appeal site.  The EIA
report acknowledges that the appeal proposal would be partially visible from within the
designated area with views of the blade tips from lower levels and views of blade tips and
some hubs from the higher vantage points.  The EIA report concludes that any adverse
effects on the designation overall would not be significant due to the limited extent of
visibility, the expansiveness of the ridgeline and the effects of woodland screening. 
19. I note that Historic Environment Scotland (HES) confirms that whilst there would be
some adverse effect from the proposed development on the setting of this designated asset
it would not be to a level which would raise issues of national interest and, therefore, raises
no objection to the appeal proposal.  In addition, I note that the West of Scotland
Archaeology Service on behalf of the council raises no objection to the proposal regarding
any indirect effects on the designation. 
20. The main effect on this designation would be on some of the views from within the
area whilst looking outwards over Loch Fyne towards the southeast.  I acknowledge that the
views would be more significant from one or two more elevated areas, but overall views are
limited by the topography and existing vegetation.  However, even the more prominent
views would still be limited to blade tips and some hubs.  Overall, I am satisfied that there
would be no significant effect on the landscape that would undermine the integrity or special
qualities of this designation. 
General landscape character types 
21. In terms of landscape character types, the EIA report predicts that there would be
some level of effect to localised areas of six of the 33 assessed landscape character types
within the study area.  Of these, it concludes that only Landscape Character Type 34 (1):
Steep Ridges and Mountains, within which the appeal site is located, would experience any
significant effects.  I note that whilst the council generally agrees with this conclusion, it
contends that significant landscape impacts would also be experienced within Landscape
Character Type 53 (1): Rocky Coastland at Strachur due to the introduction of new

Page 6

PPA-130-2084 6
large-scale infrastructure.  Having considered the assessment set out in the EIA report and
taking into account my observations during my visit, I am satisfied that these two landscape
character types are the ones most likely to experience significant landscape affects. 
22. I note that the spatial framework for wind turbines, contained within supplementary
guidance 2, identifies the appeal site as being within a group 3 area, where there is
potential for wind turbine development.  In addition, my attention has been drawn to the
Argyll and Bute Landscape Wind Energy Capacity Study 2017 (LWECS).  This study gives
this LCT a 'high' overall sensitivity rating indicating that the key landscape characteristics
are vulnerable to change.  The study concludes that there is no scope for larger typologies
(turbines >50 metres) within this landscape without significant effects occurring on a
number of key sensitivity criteria.  However, it highlights that this sensitivity is reduced
within the interior of this landscape type where the dramatic juxtaposition of water and
mountains is less evident. 
23. Notwithstanding the above, I am of the view that the guidance in both documents is
of a strategic nature.  Accordingly, it does not replace the need for a detailed assessment to
be carried out of site-specific proposals, as is the case in respect of the appeal proposal. 
Therefore, I consider the potential effects of the appeal proposal on LCT 34 (1) and
LCT 53 (1) in turn. 
Steep Ridges and Mountains LCT 34 (1) 
24. The appeal proposal would be located within Succoth Glen, which lies within the
central area of this expansive Steep Ridges and Mountains LCT.  I observed at my visit that
Succoth Glen is effectively an enclosed glen.  To the west lies the Creag Dhubh ridgeline
which extends for some 7 km from Strachur in the south to a high point at Cruach nan
Capull in the north.  To the north, east and south-east, Succoth Glen is enclosed by a series
of taller and more prominent hills extending in an arc from Cruach nam Mult in the north,
through Beinn Lochain around to Beinn Lagan in the south.  The western side of the Glen,
where the appeal proposal would be located, contains large areas of commercial forestry. 
The proposed turbines and associated infrastructure would be sited below the Creag Dhubh
ridgeline in a linear form over a distance of some 3 km. 
25. The EIA report states that given the topography of the area approximately half of the
Steep Ridges and Mountains unit to the north and much of the area to the west, would have
no theoretical visibility of the appeal proposal, and consequently no significant effects.  The
report concludes that the most significant effects would be primarily to the east and
southeast areas due to the substantial magnitude of change within these areas, which are
of medium to high sensitivity.  The appellant contends that the appeal proposal can be
absorbed within the landscape at this location without undermining the integrity of the Steep
Ridges and Mountains LCT.  However, the council contends that the proposed turbines
would dominate the narrow extent and intimate scale of Succoth Glen and detract from the
sharp ridges and open tops, which are key characteristics of this LCT. 
26. Based on my visit and taking account of the findings of the landscape assessment
and visualisations, I find that the areas affected by the appeal proposal would be those to
the east and south east as stated in the EIA report.  Although Succoth Glen is enclosed by
the surrounding topography, I found that it is a relatively wide glen with high hills to either
side.  Accordingly, I do not consider it to be of a small scale and am not persuaded that it is
characterised as being ‘intimate’ as suggested by the council.

Page 7

PPA-130-2084 7
27. Although there would be the loss of some small areas of commercial forestry to
accommodate the appeal proposal, the main effect on the landscape would be the
introduction of the nine wind turbines.  I note that the appeal proposal has been designed to
site the turbines below the Creag Dhubh ridgeline and take a linear form following the
prevailing topography and the upper edge of the commercial forestry.  Notwithstanding this,
the introduction of the proposed turbines would result in a significant change to the
landscape at this location.  I acknowledge that the siting of the appeal proposal is within the
interior area of this LCT and would avoid the impact of significant effects on the more
sensitive features of the sharp ridges and open tops identified within this LCT. 
28. Accordingly, given the scale and siting of the appeal proposal; the scale and
enclosed nature of Succoth Glen; the limited visibility within the overall designation; and, the
presence of human influences in terms of the commercial forestry, I consider that it would
not become a dominating feature within the landscape.  Overall, I am satisfied that there is
capacity to accommodate the appeal proposal at this location without undermining the
overall integrity or special qualities of LCT 34 (1). 
Rocky Coastland Landscape Character Type 53 (1) 
29. The council contend that there would be a significant adverse effect on the Rocky
Coastland Landscape Character Type 53 (1) in the Strachur area from the introduction of
the wind turbines.  It is argued by the council that whilst the appeal proposal is not located
within this LCT it is in close proximity to it and as such would dominate the scale of the
settlement and detract from the setting of this small area of the Rocky Coastland LCT.  The
EIA report predicts that there would be no significant effects to this LCT unit with only a
slight magnitude of change to an area of medium sensitivity producing a minor-moderate
significance of effect. 
30. The Rocky Coastland LCT is located to the southwest of the appeal site and is
described in the council’s LWECS as a small-scale, settled landscape highly sensitive to
large wind turbines.  The submitted Zone of Theoretical Visibility (ZTV) drawings predict
that two turbines would be partly visible (blades, hubs and upper parts of the towers) from
within some areas around Strachur.  From my visit I confirmed that the predicted views of
parts of two turbines would occur but only from a limited number of locations due to the
topography of the area and surrounding vegetation.  Therefore, whilst there would be
effects to some areas within this LCT, I am satisfied that the appeal proposal would not
introduce a feature into the landscape that would dominate the scale or setting of Strachur. 
Accordingly, I find that the appeal proposal would not undermine the overall integrity of the
Rocky Coastland LCT. 
31. The EIA report highlights that four other LCT areas would potentially be affected by
the appeal proposal.  Some of these are located within the western parts of the national
park at more elevated locations.  However, given the limited extent of any adverse effect on
these areas predicted within the EIA report, I am satisfied that they would not be significant
in this instance. 
32. Overall, I am satisfied that the appeal proposal could be accommodated without it
becoming an overly dominant feature within landscape character type 34 (1) or adversely
affecting the character of surrounding landscape character types, including LCT 53(1) or the
integrity and special qualities of designated landscape areas.

Page 8

PPA-130-2084 8
Visual impact 
33. With the inclusion of additional viewpoints (VPs 19 to 23) as supplementary
information, I note that parties agree the selected viewpoints provide an appropriate basis
upon which to assess the visual impact of the appeal proposal.  From my observations
during my visit, I am satisfied that the selected viewpoints are sufficient in this instance. 
34. The EIA report predicts that significant visual effects would occur at four of the
eighteen selected viewpoints, including Strachurmore (VP1), Beinn Bheula (VP5), Dun na
Cuaiche (VP7) and Ben Donich (VP8).  The visual effects on surrounding settlements in the
study area, including Strachur, Minard and Inveraray, and the main transport routes (A83,
A819 and A815) were predicted to be of limited magnitude and, therefore, not significant. 
Finally, the visual effects to the Cowal Way were predicted to be limited with only a few very
short sections expected to experience significant effects on visual amenity. 
35. The council contends that significant visual effects would occur at the head and
middle sections of Upper Loch Fyne and within the Loch Lomond and the Trossachs
National Park (national park).  In particular, it considers that the appeal proposal would
have significant effects on the experience of residents, travellers, tourists, walkers and
watercraft users in these areas.  I address the potential visual effects for each of the areas
of concern under the headings used by the council in its reasons for refusal. 
A83 tourist route 
36. During my visit I drove the A83 route in both directions between Minard in the south
and Garron Bridge in the north.  During my journey, I stopped at the various viewpoints
(VPs 4, 10, 12, 15, 16, 21, 22 and 23) along this route.  I observed that woodland and the
topography of the area screened the appeal site for much of the journey with only
intermittent views for relatively short durations along limited sections of the route.  Travelling
in both a northeast and southwest direction the views, where they occur, are primarily
perpendicular to the road on the east side of the A83. 
37. The views of the turbines where they occur would be distant (across Loch Fyne) and
limited to primarily the tips of the turbine blades, some hubs and associated movement
along part of the skyline above Creag Dhubh ridge.  Given the limited scale and extent of
the visible elements of the turbines over the much more expansive geography of the
ridgeline, I am of the view that the magnitude of change from this route would be slight and
the effect would not be significant.  Even at viewpoint 10 where the turbines would be most
visible these views would be distant and only for a brief duration.  In addition, I observed
that there is no formal viewpoint at this location (VP10) and that Loch Fyne does not form
part of the view due to the topography of the area.  Overall, I found that the appeal proposal
would not directly influence or detract from the more sensitive views of either the head of
Loch Fyne or the setting of any settlements, including Inveraray, when travelling on this
route. 
38. Accordingly, I am satisfied that the appeal proposal would not adversely affect the
experience of those various road users, including tourists, travelling along the A83.  In
addition, I found that when travelling along the A819 into Inveraray the views of the appeal
proposal would be limited due to topography and vegetation and, therefore, would not result
in any significant adverse effects for travellers.

Page 9

PPA-130-2084 9
Settlements on the north-western shores of Loch Fyne 
39. Representative viewpoints are provided at Inveraray (VP4), Furnace (VP12) and
Minard (VP16).  I agree with the conclusions of the appellant and the council that the likely
visual effects at Furnace would not be significant due to screening by the topography and
vegetation in the area. 
40. The EIA report predicts that the effect on views from Inveraray would not be
significant.  However, the council contends that views from Shore Walk (VP4), which it
highlights is popular with visitors, would experience a significant visual effect given its high
sensitivity and that the appeal proposal would have a medium magnitude of change. 
41. I note that it is only the blade tips of the nine turbines that would be visible above
Creag Dhubh ridgeline from Shore Walk and the other viewpoints within and around
Inveraray (including from Inveraray Castle GDL).  At a distance of some 5.4 km from
Inveraray (VP4) I consider that the visible elements of the appeal proposal would appear as
relatively small features when viewed in relation to the scale and expansiveness of the
Creag Dhubh ridgeline and Loch Fyne.  In addition, the west facing slopes of Creag Dhubh
are already characterised by large areas of commercial forestry with settlements along the
shore edge.  As such, I do not consider that the appeal proposal would form a dominant or
defining feature from any of the viewpoints within Inveraray or the Inveraray Castle GDL
when looking to the southeast. 
42. In terms of the views from Inveraray to the northeast towards the head of Loch Fyne
and the Arrochar Alps beyond, I observed at my visit that given the location of the appeal
site it would not interrupt these views to any significant extent.  Similarly, it would not
interrupt the views of Loch Fyne to the south.  Overall, I am satisfied that the appeal
proposal would not form a dominant feature in the landscape when viewed from Inveraray. 
Therefore, I find that it would not adversely impact the key scenic qualities in this area or
reduce the ability of visitors and residents to appreciate them. 
43. Whilst the council accepts that residential properties in Minard (VP16) are unlikely to
be affected by the appeal proposal due to their easterly facing orientation, it contends that
views to the Arrochar Alps within the national park would be interrupted for walkers and
watercraft users in this area. 
44. The settlement of Minard is located some 16 km to the southwest of the appeal site
and I observed at my visit that the majority of properties face eastwards with no direct views
towards the appeal site.  In addition, the topography and vegetation in the area further
reduces the potential of any views.  I acknowledge that blades and hubs of the turbines
would be visible by walkers and watercraft users in the area.  However, given the scale of
the visible elements of the turbines taken in the context of the intervening distance and
when combined with the expansive nature of the views and landscape, I find that they
would not result in visually prominent features. 
45. Overall, I consider that the visual effects would not be to such an extent as to
significantly interrupt or detract from the view towards the Arrochar Alps.  Accordingly, I am
satisfied that the appeal proposal would not have a significant adverse visual effect on the
experience of walkers or watercraft users within or around Minard.

Page 10

PPA-130-2084 10
Strachur area 
46. The EIA report predicts that effects of the appeal proposal at Strachur would not be
significant, due to the limited extent of visibility, the large scale of the containing landform
and the reduced naturalness of the surrounding landscape.  The council contends that the
two southern turbines would be intrusive in views from the A815, the Cowal Way and
Strachur Bay, adversely affecting the experience of walkers, residents, drivers and
watercraft users.  In addition, the council states that the turbines would appear visually
‘precarious’ in some close views due to their location on very steep slopes. 
47. I confirmed at my visit that the appeal proposal would only be visible from a limited
number of vantage points to the south of the settlement of Strachur, which accords with the
findings of the appellant’s ZTV findings.  I acknowledge that the upper towers, blades and
hubs of two of the nine wind turbines would be visible to varying degrees.  In terms of
residential amenity, I observed that given the orientation of the properties, topography and
surrounding vegetation there would be very few locations where any element of the two
turbines would be directly visible.  Therefore, I am satisfied that the visible elements of the
two turbines would not form dominant visual features that would adversely impact the
amenity of residents within the settlement of Strachur. 
48. Whilst driving along the A815, the A866 and other minor roads around Strachur, I
observed that views of the two turbines would be limited in both extent and duration given
the prevailing topography and vegetation.  The most prominent views for road users would
be from the A815 at Balliemeanoch (VP2) where parts of the towers and the blades/hubs of
the two turbines would be visible.  I found that as the appeal proposal is located to the north
east of the A815 the views would be at an oblique angle to the direction of travel.  I found
that the views from the A866 where they occurred (only travelling towards Strachur) were
less prominent and more distant than those from the A815.  Therefore, given the scale of
the turbines in the context of the wider landscape, which is already defined by commercial
forestry, I am satisfied that they would not form dominant visual features when viewed by
travellers on the A815, A866 or any of the other minor roads in the area. 
49. The most prominent views of the two turbines for walkers would be on the Cowal
Way at Glen Sluain (VP3), to a lesser extent at Strachurmore (VP1) and only when heading
in a north easterly direction.  I found that the views of the turbines would be limited to
relatively short sections of the walk due to screening by large areas of woodland and the
prevailing topography.  Although the turbines would be partly visible at these locations, they
would be viewed in the context of the much larger ridgeline of Creag Dhubh and the more
expansive landscape to the northeast.  I note that these views are already very much
characterised by large areas of commercial forestry.  When taken in the context of the wider
views to the northeast, I am satisfied that the turbines would not form an overly dominant
visual feature on this landscape and as such would not undermine the overall quality of
experience for walkers using the Cowal Way. 
50. In relation to watercraft users, I am satisfied that having considered the submitted
ZTV any views from on the loch at Strachur Bay would be more limited than those from the
land based viewpoints due to the topography and vegetation and would not, therefore, be
significant. 
51. Finally, the council raises a concern that the turbines would appear to be
‘precariously’ sited.  No detailed explanation is provided as to what the council means by
this term in a visual context.  I assume the council is concerned that the position of the
turbines would give the impression that they lack stability in some manner.  However, I have

Page 11

PPA-130-2084 11
no substantive evidence before me to justify this conclusion.  Based on the submitted
evidence, visualisations and my observations of the topography surrounding the appeal
site, I am not persuaded by the council’s contention that the turbines would appear to be
‘precarious’. 
52. Overall, I am satisfied that the visual effects of the appeal proposal would not
significantly impact on the visual amenity of residents or detract from the experience of
travellers, walkers or watercraft users in the Strachur area. 
Dun na Cuaiche 
53. The EIA report predicts that the effect of the appeal proposal on the views
experienced by walkers and tourists from Dun na Cuaiche (VP7) towards Creag Dhubh
would be visually significant, due to the proposed development’s wide extent and the
movement of the wind turbines. 
54. During my visit, I observed that once on the path to Dun na Cuaiche there were
would be no views of the appeal proposal along the steep walk, due to the topography and
woodland, until reaching the summit at some 225 metres above Loch Fyne.  A watchtower
is located on the summit and has two window openings one facing southwest towards the
settlement of Inveraray and the other facing southeast towards Creag Dhubh ridge.  I
observed that there was no public access to the watchtower at the time of my visit, with a
locked gate in place across the entrance. 
55. I note that there is no dispute between parties that the blades of all nine turbines and
some six hubs would be visible from the summit of Dun na Cuaiche.  However, I observed
that the appeal proposal would be seen in the least dramatic part of the view from Dun na
Cuaiche, that is, away from the settlement of Inveraray and the Castle to the southwest
and, away from the mountains within the Loch Lomond & the Trossachs National Park to
the northeast.  I note that the council does not dispute this conclusion. 
56. Whilst the views of the appeal proposal may be visually significant, I am satisfied that
given the scale of the visible elements in comparison with the extensive geography of the
Creag Dhubh ridgeline (which is partly characterised by commercial forestry) and Loch
Fyne, the appeal proposal would not introduce a dominant or over bearing visual feature
into the landscape.  I note that HES did not object to the appeal proposal in relation to the
impact on the Inveraray Castle GDL which Dun na Cuaiche forms part. 
57. Overall, I am satisfied that as the appeal proposal is situated in the least dramatic
part of the view from Dun na Cuaiche, the appreciation of the key scenic attractions of
Inveraray and the Castle; Loch Fyne; and, the Arrochar Alps by walkers and tourists, would
not be significantly undermined. 
Loch Lomond and the Trossachs National Park (national park) 
58. The National Park Authority, NatureScot and the council consider that the appeal
proposal would have significant visual effects when seen from some popular elevated
routes and viewpoints within the national park.  It is contended that the visual effects would
adversely affect the experience of walkers and tourists within these areas.  Concern is also
raised in relation to the visual impact on the section of the Cowal Way long distance walking
route within the national park.  Mountaineering Scotland also objected to the appeal
proposal on similar grounds.

Page 12

PPA-130-2084 12
59. The EIA ZTV predicts that all nine turbines would be visible from within the national
park but only to a very limited extent and only from a small number of locations (3.1% of
one or more blade tips and 1.2% of hubs).  Based on the evidence submitted, I am satisfied
that the viewpoints at Beinn Bheula (VP5) and Ben Donich (VP8), given their proximity to
the appeal site, represent the locations where the proposed turbines would be viewed to
their fullest extent and that the visual effects would be most significant.  There would also
be views from Ben Arthur (VP13) which the EIA predicts would be less significant given the
increased distance from the appeal site and intervening topography.  Whilst I acknowledge
that the turbines would be less prominent from this viewpoint, I still consider that the visual
effects would be significant. 
60. I acknowledge that there would be some limited views of the blade tips and hubs of a
number of the turbines from other locations within the national park.  However, based on
the findings of the EIA ZTV, I am satisfied that these would be very limited in extent and
number and, therefore, would not result in significant visual effects at these locations. 
61. I note that the nine turbines would be located at a lower level than the viewpoint
locations (VP5, 8 and 13) and, therefore, looked down upon within Succoth Glen.  The
appellant highlights that the turbines have been arranged in a linear form and are positioned
to follow the topography and undulating character of the ridgeline and also align with the
edge of the area of commercial forestry.  I find that this provides for a simple visual form
respecting the landscape character of the area. 
62. Given that the position of the wind turbines within Succoth Glen would at a lower
level than the viewpoints, I acknowledge, as illustrated in the visualisations, that they would
not appear as being on or above the horizon.  In addition, the linear form of the layout of the
turbines would also follow the undulating topography of Creag Dhubh ridge.  Therefore, I
find that the wind turbines would not form a dominant feature within the landscape that
would significantly interrupt the existing panoramic or distant views of Argyll and Bute to the
west.  In addition, the turbines would be viewed within a landscape already containing
existing and consented wind farms, albeit at greater distances than the appeal site.  As
noted above the landscape to the west is already characterised by large areas of
commercial forestry plantations.  Therefore, there are already external human influences
that affect these views. 
63. Accordingly, I consider that whilst the turbines would be visually prominent they
would not present as dominant features within the wider expansive landscape when viewed
from these locations (VP5, 8 and 13) or associated elevated routes.  In addition, I consider
that the more natural and scenic views from these particular locations are those to the east
and north looking out across the scenery within the national park including towards the
Arrochar Alps.  These panoramic views would not be significantly interrupted by the appeal
proposal.  Therefore, while there would be some visual impact at these viewpoints and on
some elevated routes I am satisfied that the overall adverse visual impact on the
experience of walkers and tourists would not be significant. 
64. I have already considered the potential of the visual impact on the experience for
walkers on the Cowal Way when approaching the national park from Strachur.  During my
visit I noted that the turbines would also be visible from short sections of the Cowal Way
from within the national park when heading in a south westerly direction.  Whilst these
views, where they occur, would be visually significant I am satisfied that they would limited
in extent and duration when walking the overall route due to the prevailing topography and
existing tree cover.  Overall, I am satisfied that the appeal proposal would not undermine

Page 13

PPA-130-2084 13
the integrity of the Cowal Way long distance route or have a significant adverse visual
impact on the overall experience of walkers. 
65. Taking account of the above considerations, I find that significant visual effects would
occur from a limited number of locations around Loch Fyne and from elevated locations
within the national park.  However, given the siting and scale of the appeal proposal, I am
satisfied that it would not form a particularly dominant feature when viewed within the wider
expansive landscape and, therefore, would not have a significant adverse visual impact on
the experience of residents, travellers, walkers, tourists and watercraft users. 
Cumulative landscape and visual effect 
66. The EIA report assesses whether significant cumulative landscape and visual effects
would occur from the appeal proposal in conjunction with operational, consented and
proposed commercial scale wind farm developments within a 40 km study area.  The
identified wind farms lie to the northeast, west and southwest of the appeal site.  Based on
the submitted evidence, I am satisfied that given the distance and topography there are no
wind farms to the east that would result in any significant cumulative effects.  Parties did not
dispute the approach or selected study area of the EIA report. 
67. The EIA report predicts that, based on the cumulative ZTV maps, the appeal
proposal would maintain the existing pattern of separation between wind farms, including
the closest operational wind farms at Clachan Flats, An Suidhe, A’Cruach and Cruach Mhor
and as a result cumulative effects would be limited across the study area.  The council
contends that the appeal proposal in combination with the operational Clachan Flats wind
farm would interrupt and distract the dramatic views from elevated locations (Dun na
Cuaiche) looking northeast towards the head of Loch Fyne and the mountains within the
national park. 
68. I note from the cumulative ZTV that, when the appeal proposal is considered along
with Clachan Flats wind farm there is only combined cumulative visibility from a limited
number of locations around the shoreline of Loch Fyne.  In addition, the cumulative visibility
at Dun na Cuaiche is also predicted to be very limited.  Given the limited visibility of the
appeal proposal from around Loch Fyne (which I have established above) and the distance
of separation between it and Clachan Flats wind farm (8 km to the northeast), I am satisfied
that it would not result in wind farms becoming a prevailing or principle characteristic within
the landscape of the area or when viewed from sensitive viewpoints (including Dun na
Cuaiche) around Loch Fyne.  Therefore, I find that the appeal proposal would not have a
significant cumulative landscape or visual effect with Clachan Flats wind farm when viewed
from sensitive locations towards the head of Loch Fyne and the mountains within the
national park. 
69. The cumulative ZTV predicts that the wind farm influence experienced from within
the national park as a whole is limited to elevated peaks and routes.   I note from the
submitted evidence that a number of existing, consented and proposed wind farms would
be visible to varying degrees from the selected viewpoints (VP5, 8 and 13).  These wind
farms are generally well separated across a large geography and located at significant
distances from the viewpoints.  As such, I find that they do not form a dominant feature in
the landscape and, therefore, do not interrupt the appreciation of panoramic views to the
west.  Therefore, I am satisfied that the overall visual influence from existing, consented
and proposed wind farms is relatively limited.

Page 14

PPA-130-2084 14
70. Although the appeal proposal would bring wind farm development closer to
viewpoints within the national park, I find that it has been positioned to attempt to maintain
the horizontal spacing of wind farm development across the wider panoramic view.  Whilst a
slight cumulative magnitude of change would occur, I do not consider that it would result in
wind farms becoming the principal or prevailing characteristic in the landscape or dominate
the views to the west from within this part of the national park.  Therefore, I am satisfied that
the appeal proposal would not have a significant cumulative visual impact or result in a wind
turbine defined landscape. 
71. Overall, I find in terms of the landscape, visual and cumulative impacts that the
appeal proposal would accord with policy LDP 6 and SG 2. 
Tourism and recreation impacts 
72. Chapter 16 of the EIA report recognises that the tourism profile of the locality is
potentially sensitive given its importance to the local economy.  Reference is made in the
report to a number of recent studies including the ‘Biggar Report’ which consider the impact
of wind farms on tourism within Scotland.  These reports conclude that generally tourists
are not deterred from visiting areas due to the presence of wind farms.  In addition, the
appellant highlights that these studies have suggested that increased investment (including
tourism infrastructure) in the local and regional economy can occur as a result of a wind
farm development.  Overall the appellant concludes that the appeal proposal would not
deter tourists/visitors from coming to the area and as such would have no significant
adverse impact on the local economy. 
73. The council refused the appeal proposal on the grounds that ‘given the presence of
adverse landscape and visual impacts on the Loch Lomond and the Trossachs National
Park (national park) the development may influence public attitudes to a point where
tourists might become dissuaded from visiting’.  Representations also raise similar concerns
for the local area, including around Strachur.  However, support for the potential socio-
economic benefits has been received from local residents and the Lochgoil Community
Trust. 
74. Whilst the appeal site is not located within the national park, I have established
above that some significant landscape and visual effects would occur from a limited number
of hills and elevated routes within western areas of the national park.  However, I have
concluded that the appeal proposal is capable of being accommodated within the landscape
without it becoming a dominant or prevailing feature.  Therefore, I am satisfied that it would
not have a significant adverse impact on the experience of tourists or visitors within the
national park.  No substantive evidence has been submitted by parties to quantify the level
of any potential adverse impact that the appeal proposal would have on tourism or
recreation and as such on the local economy.  Therefore, I am not persuaded that there
would be a significant adverse impact on tourism or recreation within the national park. 
75. Whilst concerns have been raised in representations regarding the potential for an
adverse impact on tourism and recreation within the Argyll and Bute area (particularly at
Strachur), no substantive evidence has been provided to allow me to quantify the scale of
any potential impact.  Representations have also been made on the grounds that some
economic benefit to the local economy may accrue as a result of the appeal proposal.  As I
have concluded above that any adverse visual and landscape impacts within Argyll and
Bute (including at Strachur) would not adversely affect the experience of tourists or visitors
within this area, I am not convinced that there would be any significant detrimental impact
on tourism and recreation within Argyll and Bute.

Page 15

PPA-130-2084 15 
76. Overall, on the basis of the evidence before me, including the findings of the EIA
report, I am satisfied that the appeal proposal would have no significant adverse impact on
either tourism or recreation within Argyll and Bute or the national park. 
Other impacts 
77. The EIA report assesses a wide range of other impacts: forestry; noise; shadow
flicker; ecology; ornithology; communications infrastructure; hydrology; cultural heritage; 
traffic and transport; and, socio-economic.  The council has not founded its refusal on any
of these impacts and I note in this regard that there are no outstanding concerns on the part
of key agencies and consultees, subject to the imposition of appropriate conditions.  The
EIA report and additional information submitted by the appellant acknowledged the
following residual significant environmental effects, in addition to those relating to landscape
and visual impacts and tourism/recreation impacts which are considered above. 
Forestry 
78. The appeal proposal would result in the loss of some 20 hectares of Sitka Spruce
woodland within a privately owned and managed commercial forestry plantation extending
to some 1,373 hectares.  Given the nature of the woodland affected, the EIA report does
not consider forestry as a sensitive receptor.  However, consideration is given in chapter 6
of the EIA report to the plans for felling and restocking and ongoing forest management
practices. 
79. Whilst Scottish Forestry agree with the appellant’s conclusion in the EIA report, it
highlights that in order to comply with the criteria of the Scottish Government's Control of
Woodland Removal Policy, off-site compensatory planting totalling 20.1 hectares would be
required.  Scottish Forestry has provided a condition to ensure that appropriate
compensatory planting is delivered and to which the appellant raises no objection.  I find
that the wording of the suggested condition is appropriate and have attached it to this
decision.  Overall I am satisfied that sufficient consideration has been given to the potential
effects on forestry. 
80. Scottish Forestry highlights that an amendment to the Long Term Forestry Plan for
the wider area would be required as a result of the appeal proposal.  I am satisfied that this
matter can be appropriately addressed under the provisions of the Forestry and Land
Management (Scotland) Act 2018. 
Noise 
81. The potential impact from both construction and operational noise was assessed with
the findings set out in chapter 8 of the EIA report.  Some objections were raised in
representations to the potential of disturbance from noise on residential properties. 
82. Operational noise was assessed using ETSU-R-97 (methodology and noise limits). 
From this assessment it is concluded that once operational, the appeal proposal would not
exceed the relevant noise limits at each of the nearby residential properties.  The
assessment of predicted construction noise was undertaken in accordance with
BS5228:2009.  Overall, it is concluded that when mitigation is implemented and good
practice site management measures followed, noise levels would be below the appropriate
limits at properties closest to construction activities.

Page 16

PPA-130-2084 16
83. The council raises no objection in terms of the potential of disturbance from noise
subject to the imposition of appropriate conditions in relation to the required mitigation for
both the construction and operational phases of the appeal proposal.  I find that subject to
the requested conditions there would be no significant adverse impact from noise on nearby
residential properties.  I have included conditions relating to noise as part of this decision. 
Shadow flicker 
84. An assessment, following accepted best practice and guidance, of the potential for
effects from shadow flicker on nearby properties was carried out, with the findings set out in
chapter 9 of the EIA report.  It was established that there were no properties within a radius
of 11 rotor diameters (1012 metres) and 130 degrees either side of north of the proposed
turbines.  On this basis I am satisfied that there is no likelihood of shadow flicker adversely
affecting the amenity of nearby residential properties. 
Ecology 
85. Chapter 10 of the EIA report considers the potential for impacts during the
construction, operational and decommissioning phases on the ecology present within the
area.  The appeal site is not located within or in close proximity to any statutory or 
non-statutory designated environmental sites.  In addition, no protected species or flora
were identified from the habitat survey of the site.  Therefore, it is concluded that the main
impacts would be from direct habitat loss through the removal of vegetation to facilitate the
appeal proposal. 
86. The appellant’s assessment concludes that the layout of the development, including
the routing of tracks and roads, has been designed to minimise any loss of habitat in any
sensitive areas within the appeal site.  Consequently, it is contended that there would be no
residual adverse significant effects on any ecological features.  No concerns were raised by
any consultee or the council to the findings of the EIA report on this matter.  Overall, I am
satisfied that a thorough assessment has been carried out in relation to the potential for any
significant adverse effects on the ecology of the area.  To ensure the site is developed in
accordance with the EIA report recommendations, I have included a condition requiring an
Ecological Clerk of Works to monitor the phases of the development. 
Ornithology 
87. The potential for any significant impact on ornithology is considered in chapter 11 of
the EIA report.  It is established that the proposed development is not located within or in
close proximity to any statutory or non-statutory sites designated for ornithological interest. 
Flight activity surveys were undertaken to monitor activity levels of particular species, and to
assess the potential for bird collisions with turbines and other interactions.  Species noted
included Golden Eagles, Hen Harriers and Merlins.  The predicted collision mortality for the
hen harriers and merlin was considered not to be significant.  This conclusion was not
contended by either NatureScot or the Royal Society for the Protection of Birds (RSPB). 
88. In terms of Golden Eagles, it was established that there are no active eyries
within 2 km of any proposed turbine.  A Predicting Aquila Territories (PAT) model was
undertaken by the appellant, which concludes that only one of two known Golden Eagle
territories is predicted to overlap with the wind farm location.  In addition, a model of the
impact of potential wind farm collision mortality on the Golden Eagle population was
undertaken.  From this it is predicted that there would be a minor adverse effect on the

Page 17

PPA-130-2084 17
Golden Eagle population from potential loss of habitat through displacement and a minor
adverse effect of collision risk. 
89. NatureScot and RSPB initially raised concerns that the assessment did not properly
demonstrate that the effects on the Golden Eagle population would not be significant. 
Further confidential supplementary information was submitted by the appellant providing
additional satellite tagging data.  On the basis of the additional information NatureScot
advised that it is unlikely that any adverse effect would create a natural heritage zone
population level risk and removed its objection on this matter.  RSPB also withdrew its
objection.  However, both parties sought the imposition of a condition requiring a habitat
management plan to improve the condition of the area and supported the proposed
mitigation measure of post construction monitoring.  I have included conditions covering
these requirements. 
90. The Argyll Raptor Study Group also objected on similar grounds to NatureScot and
RSPB.  I note that this group were not provided with the additional supplementary
information due its confidential status.  The group has, therefore, retained its concern due to
the lack of further information.  Whilst, I note the continued objection by the Argyll Raptor
Group, NatureScot and RSPB having had the benefit of reviewing the additional
supplementary confidential information, conclude that there would be no significant adverse
effects in this instance.  Overall, I am satisfied that on the basis of the evidence in the
additional supplementary information and the comments from NatureScot and RSPB, there
would be no significant adverse effects on ornithology. 
Communications infrastructure 
91. It is highlighted within chapter 12 of the EIA report that following consultation with the
relevant communication operators it was established that given its location, no
telecommunication links would be affected by the appeal proposal.  In addition, it is
highlighted that in the event television reception at local households is impacted upon, any
issues would be dealt with by the developer and appropriate mitigation measures carried
out. 
92. The Ministry of Defence in its consultation response advised that it had no objection
subject to conditions relating to accredited aviation safety lighting, timing of the construction
phase, height of construction equipment and the exact location (latitude and longitude) of
each of the proposed turbines.  No further concerns were raised by any of the other
relevant consultees or the council.  Therefore, I am satisfied that subject to the conditions
requested by the Ministry of Defence being imposed, no significant adverse effects are
likely in this instance. 
Hydrology, hydrogeology, and soils 
93. The magnitude and significance of potential effects on hydrology, hydrogeology, and
soils were assessed with the findings set out in chapter 13 of the EIA report.  It was
established that without additional mitigation, over and above best practice techniques,
there would be the potential for effects of a low to moderate significance to occur in regard
to peat hydrology, peat resource and potential ground water dependent terrestrial
ecosystems.  To reduce these effects a number of additional mitigation measures and
management plans are recommended in the EIA report.  These include more detailed site
investigations, a peat management plan, drainage design, construction method statement
and construction environmental management plan.  On this basis it is concluded that the
residual effects can be reduced to minor.

Page 18

PPA-130-2084 18 
94. Further supplementary information was submitted in relation to the proposed peat
management plan at the request of SEPA.  On the basis of the further information SEPA
confirmed it had no objection in terms of the potential impact on hydrology, hydrogeology,
and soils.  In addition, NatureScot raised no concerns given the area of peatland affected
would not be considered to be of national interest for its peatland habitat.  The council,
subject to the proposed mitigation measures, raised no concerns.  Overall, I am satisfied
that a satisfactory assessment has been carried out and that subject to conditions ensuring
the identified mitigation measures are undertaken, there would only be the potential for
minor effects. 
Cultural heritage 
95. Chapter 14 of the EIA report advises that an assessment was undertaken of all
known cultural heritage features within a 10 km radius of the appeal site.  It established that
apart from some limited areas of archaeological interest there were no cultural heritage
features of national or local importance within the site.  It was concluded that no direct
impacts would occur on any heritage assets within the appeal site. 
96. Within the 10 km study area the most significant heritage assets were considered to
be Inveraray Castle Inventory Garden and Designed Landscape and the category A-listed
Aray Bridge.  Given the potential for indirect effects on the setting of these features HES
requested additional viewpoints from these locations.  On the basis of the visualisations
provided as supplementary information, HES confirmed that whilst there would be some
adverse effect from the appeal proposal on the setting of these designated assets, it would
not be to a level which would raise issues of national interest.  The West of Scotland
Archaeology Service agreed with the findings in the cultural heritage section of the EIA
report and raised no concerns in terms of direct or indirect archaeological issues. 
97. Accordingly, I consider that a satisfactory assessment has been carried out.  Whilst
there may be some adverse indirect visual and landscape effects from the appeal proposal
on the setting of designated heritage assets, I am satisfied that the scale of any impact
would not be significant in this instance. 
Access, transport and traffic 
98. The potential for impact on transport routes, traffic and access during the
construction, operation and decommissioning stages has been considered within
chapter 15 of the EIA report.  The assessment of the potential impacts concludes that
subject to appropriate mitigation measures, including the routing and timing of deliveries to
the appeal site, no significant adverse impacts on the surrounding road network would
occur. 
99. Transport Scotland advises that it has no objection to the appeal proposal subject to
conditions ensuring that the transportation of abnormal loads would have no detrimental
effect on the trunk road network.  In addition, the council raises no objection subject to
conditions requiring improvements to the existing access; a video record of the road
corridor (A815 to site including junction); traffic management measures being put in place
(including for abnormal loads); the timing of deliveries; and, the avoidance of peak travel
times for the transportation of abnormal loads.  ScotWays whilst not objecting to the appeal
proposal requests that a condition be attached to ensure that right of way SA32 remains
open at all times.

Page 19

PPA-130-2084 19
100. Overall, I find that subject to the conditions requested by parties being imposed,
there would be no significant adverse impact on the surrounding road network or formal
walking routes. 
Socio-economics benefits 
101. It is highlighted in chapter 16 of the EIA report that direct economic benefits would
include 91-man year equivalent jobs created during the construction stage within the Argyll
and Bute area and 36-man year equivalent jobs in Scotland.  During the operational stage,
eight-man year equivalent jobs would be created within the Argyll and Bute area and 
seven-man year equivalent jobs in Scotland.  In addition, the EIA report concludes that
whilst a slight magnitude of impact is predicted there would be no significant adverse effect
on tourism and recreation in the area.  I have concluded above that there would be no
significant adverse impacts from the appeal proposal on either tourism or recreation in the
area, including within the national park.  Therefore, I am satisfied that overall the appeal
proposal would introduce socio-economic benefits to the local area and wider economy. 
The appellant also highlights that an annual benefit would be paid to the local community,
whereby, it can choose what the money should be spent on within the local area. 
Representations 
102. Of the five community council’s consulted concerns were only received from Strachur
Community Council.  In its representation it set out both matters of concern but also matters
in support of the appeal proposal.  There were also 14 individual letters of objection
received and 2 letters in support of the appeal proposal.  The concerns raised were in
relation to the scale of development; landscape and visual impacts; proximity to the national
park; impact on tourism; impact on the Cowal Way walking route; adverse impacts in
relation to noise, shadow flicker, ornithology; and, traffic and house prices.  Support for the
proposal in terms of its sustainability and financial community benefit were raised in
representations. 
103. Taking into account my assessment as set out above and after careful consideration
of the matters raised in both the consultation responses and the letters of representation, I
am satisfied that there are no outstanding issues which lead to any apparent
inconsistencies with the policies of the local development plan. 
Compliance with the development plan 
104. I acknowledge that the appeal proposal would have significant landscape and visual
effects within some localised areas of Argyll and Bute and the national park.  However,
given the scale and siting of the appeal proposal, I am satisfied that it would not result in a
dominant or prevailing visual feature.  Therefore, I find that the appeal proposal is capable
of being accommodated at this location without having a significant adverse landscape,
visual or cumulative impact or resulting in a wind turbine defined landscape.  In addition, I
consider that for the reasons set out above the appeal proposal would not have a significant
adverse impact on tourism or recreation in the area. 
105. Accordingly, I am satisfied that the appeal proposal would accord with the relevant
policies and supplementary guidance of the local development plan in terms of landscape
and visual impact, cumulative landscape and visual impact, and, impacts on tourism and
recreation.  In addition, I have also established that there are no other potential impacts that
would adversely affect the quality of the surrounding built and natural environment.

Page 20

PPA-130-2084 20
106. Therefore, I find that the appeal proposal would accord with policy LDP DM 1, policy
LDP 6 and SG 2, policy LDP 3 and associated SG, policy STRAT 1, policy LDP 9, and, SG
LDP Tran 1.  I have not been made aware of any other relevant impacts that would lead me
to conclude that the appeal proposal would not accord with other detailed policies of the
local development plan. 
107. Overall, I am satisfied that the appeal proposal accords with the provisions of the
local development plan. 
Other material considerations 
Loch Lomond and the Trossachs National Park (national park) 
108. Paragraph 212 of SPP advises that development that affects a national park should
only be permitted where ‘the objectives of designation and the overall integrity of the area
would not be compromised’. 
109. The appeal site is located outwith the national park.  Whilst there are no provisions
for buffer zones around national parks within SPP, I acknowledge that the proximity and
scale of a development may have an influence on the overall level of impact on some of the
identified special landscape qualities.  I note that parties agree that the appeal proposal
given its location would not adversely affect any of the National Scenic Areas within the
national park. 
110. The council, the National Park Authority and NatureScot have objected to the appeal
proposal on the grounds that it would adversely affect four special landscape qualities
(SLQ).  These are the Arrochar’s mountainous and distinctive peaks; a remote area of high
hills and deep glens; tranquillity; and, the easily accessible landscape splendour.  I note that
Mountaineering Scotland also raised concerns regarding the impact on the national park. 
111. Therefore, it is necessary for me to establish the extent of any significant adverse
effects on the four special landscape qualities and whether the objectives of the designation
would be undermined or the overall integrity of the national park compromised.  I have
considered the other special landscape qualities, as set out in commissioned report No 376
(The Special Landscape Qualities of the Loch Lomond and the Trossachs National
Park - 2010) and am satisfied that the appeal proposal does not raise any significant
concerns in relation to these qualities. 
112. I have established above that the appeal proposal would have significant landscape
and visual effects which would affect areas within the western edge of the national park. 
However, I have concluded that given its scale and location the appeal proposal could be
accommodated within the prevailing landscape without it becoming a dominant visual
feature or resulting in a wind farm defined landscape.  Taking account of my findings on
these matters, I do not consider that the appeal proposal would, therefore, adversely affect
the Arrochar’s mountainous and distinctive peaks or the remote area of high hills and deep
glens SLQs. 
113. In relation to the effects on tranquillity, I acknowledge that the appeal proposal would
introduce a measure of slow movement from the blades of the nine turbines which could
potentially affect the experience of walkers/tourists in some elevated locations.  I have
already established that no adverse effects from noise would be experienced by the closest
residential properties.  Given the greater intervening distance from where the appeal

Page 21

PPA-130-2084 21
proposal would be visible from within the national park (VP 5, 8 and 13), I am satisfied that
there is unlikely to be any audible intrusion of significance. 
114. Whilst, there may be some degree of adverse impact from the movement of the
blades on the sense of peace in the landscape, I do not consider that it would be overly
significant given the distance from the viewpoints and the limited extent it would occupy
within the wider panoramic view.  I note that the presence of wind farms is already a
discernible characteristic in views to the west, in addition to the presence of large areas of
commercial forestry.  I consider that this does not represent the type of natural landscape
that would necessarily contribute to a sense of tranquillity.  In addition, the views across the
national park to the north and east from these viewpoints are likely to provide a much
greater sense of tranquillity given the lack of human presence in these landscapes. 
Therefore, I am satisfied that any likely impact on the special quality of tranquillity would be
limited in both significance and extent.  Accordingly, I find that the appeal proposal would
not undermine this special landscape quality. 
115. Concerns are raised by parties regarding the potential impact on the special
landscape quality regarding ‘easily accessible landscape splendour’.  Given its location the
appeal site would not be visible from the majority of the national park area or from any of
the main vehicular routes into or through it.  Accordingly, users of main roads and other
routes to access the various attractions within the national park would not be affected. 
116. Whilst I acknowledge that the appeal proposal would be visible from some parts of
the Cowal Way, I have concluded above that the impact on this route would not be so
significant as to undermine its overall integrity or the experience enjoyed by walkers.  In
addition, I have already concluded that there would be no significant impact on tourism or
recreation within the national park.  Accordingly, on the basis of the submitted evidence, I
am not persuaded that any significant impact would occur on this particular special
landscape quality. 
117. Overall, I am satisfied that the nine turbines can be accommodated within the appeal
site without significantly undermining any of the four SLQs.  Therefore, I consider that the
appeal proposal would not undermine the ‘objectives of designation’ or compromise the
‘overall integrity’ of the national park.  
Other guidance 
118. NPF3 and SPP both seek to support the development of renewable energy
developments, including wind farms, subject to the potential impacts on the built and natural
environment being acceptable.  Paragraph 169 of SPP sets out a range factors that require
to be taken into account when considering wind farms and I note that these are similar to
those included within policy LDP 6 of the adopted plan.  Having concluded that the appeal
proposal accords with policy LDP 6, I am satisfied that it would also be acceptable in terms
of the factors set out in paragraph 169.  In addition, the spatial framework for onshore wind
that is set out in SPP (table 1 on page 39) is consistent with the approach set out in the
council’s supplementary guidance 2. 
119. I note that the adopted local development plan 2015 is out of date and as such
paragraph 33 of SPP advises that the presumption in favour of development that
contributes to sustainable development will be a significant material consideration.  In
considering this, decision makers are required to take into account any adverse impacts
which would significantly and demonstrably outweigh the benefits when assessed against

Page 22

PPA-130-2084 22
the wider policies in the SPP.  Paragraph 29 of SPP sets out the principles for establishing
whether a development would contribute to sustainable development. 
120. Given the nature of the appeal proposal I am satisfied that it would contribute to net
economic development and support climate change mitigation.  On the basis of the detailed
information set out in the EIA report and further submitted evidence, I consider that the
appeal proposal would be consistent with the other principles, in so far as they are relevant,
as set out within paragraph 29 of SPP.  I am also satisfied based on my findings as set out
above, that there would be no adverse impacts which would significantly or demonstrably
outweigh the benefits.  Overall, I find that the appeal proposal would contribute to
sustainable development and meet the wider objectives of SPP including the delivery of
Outcome 1 (a successful, sustainable place) and Outcome 2 (a low carbon place). 
121. Other government policy documents have been referred to by parties including draft
NPF4; the Scottish Energy Strategy 2017; Scottish Energy Strategy Position
Statement 2021; the Onshore Wind Policy Statement 2017; and, the Onshore Wind Policy
Statement Refresh 2021.  These documents seek to encourage and support the
development of onshore wind turbines, including larger scale turbines, in sustainable
locations similar to the guidance in NPF3 and SPP.  Therefore, I am satisfied that there are
no additional matters raised in this guidance that requires to be considered in this instance. 
122. Reference is also made to SNH Siting and Designing Wind Farms in the Landscape
Guidance August 2017 and the council’s non-statutory guidance - Landscape Wind Energy
Capacity Study 2017.  I am satisfied on the basis of the evidence submitted in the EIA
report and through my considerations as set out above, that the appeal proposal would
generally accord with the guidance in these documents. 
Proposed plan 
123. The proposed Argyll and Bute Local Development Plan 2 (November 2019) sets out
the council’s settled position in terms of the strategy and policies for future development
and is currently at examination.  The proposed plan generally restates the policies from the
adopted local development plan in relation to wind farm proposals.  The council has not
referred to the policies of the proposed plan in its reasons for refusal or brought any
particular proposed changes of policy to my attention.  Therefore, I am satisfied that there
are no proposed changes to the strategy or relevant policies that would alter my
conclusions in relation to the appeal proposal. 
Overall conclusion 
124. I have given careful consideration to the environmental information submitted and
have identified no additional significant effects.  Accordingly, subject to mitigation controlled
by means of the conditions attached to this notice, I find that there would be no
unacceptable residual impacts in relation to those matters.  Therefore, I am satisfied that
my reasoned conclusions on the significant effects of the proposed development are up to
date. 
125. I therefore conclude, for the reasons set out above, that the proposed development
accords overall with the relevant provisions of the development plan and that there are no
material considerations which would justify refusing to grant planning permission.

Page 23

PPA-130-2084 23
Planning conditions 
126. The council has submitted a schedule of 30 conditions which it considers should be
attached to planning permission, if granted.  The appellant has provided comments on the
submitted conditions which I have taken into consideration. 
127. I have amended condition 2 to reflect the amendment to section 58 of the Town and
Country Planning (Scotland) Act 1997 which now requires a condition to be attached to
permission limiting its duration.  To provide for consistency, I have amended the titles of the
list of approved drawings at condition 3 (c) to accord with the descriptions as set out in the
EIA report. 
128. I have included the appointment of an Ecological Clerk of Works under condition (8). 
Given the scale of the development and its location I do not consider it is reasonable to also
require the appointment of a Planning Monitoring Officer as requested by the council in this
instance.  Therefore, I have not included this as a condition to this permission. 
129. Finally, I have reworded condition 17 to reflect the requirements sought by Scottish
Forestry in relation to the appellant’s Forest Plan and added a condition (18) to ensure that
appropriate compensatory woodland planting is provided. 
130. The attached conditions also provide for monitoring measures where appropriate.  In
condition 8 I require the appointment of an Ecological Clerk of Works, who would have
responsibility for monitoring ecological mitigation measures relating to the proposed
development.  I have also included monitoring measures in condition 11 (trunk and local
road management); condition 15 (post construction monitoring); condition 16 (habitat
management plan); and, condition 19 (peat landslide management).  There is no evidence
to suggest that any other monitoring measures are required. 
131. I have considered all the other matters raised, but there are none which would lead
me to alter my conclusions. 
Gordon S Reid
Reporter 
Schedule 1:  Conditions 
Duration of the permission 
1. The permission is for a period of 25 years from the date of final commissioning.  Written
confirmation of the date of first commissioning shall be provided to the planning authority no
later than one calendar month after that date. 
Reason: to define the duration of the permission. 
Commencement of development 
2. The development to which this permission relates shall be begun not later than the
expiration of three years beginning with the date of grant of this permission.

Page 24

PPA-130-2084 24
Reason: section 58 of the Town and Country Planning (Scotland) Act 1997 requires a
condition to be attached to permission limiting its duration.  Three years is the default period
set by law and there is no material reason indicating that a different period should be set. 
Implementation in accordance with approved plans and requirements of this
permission. 
3. Except as otherwise required by the terms of this permission, or as agreed in writing by
the planning authority, the development shall be undertaken in accordance with: 
a) the application form dated 4th December 2019; 
b) the EIA Report dated October 2019 (as supplemented or amended by any further or
additional environmental information); and, 
c) the approved drawings EIA Report: 
5.1.    Site location
5.2.    Site layout
5.3.    Access design
5.4.    Candidate turbine elevations
5.5.    Indicative turbine foundations
5.6.    Indicative access track designs
5.7.    Indicative watercourse crossing design
5.8.    Cable trench sections
5.9.    Indicative crane hardstanding
5.10.  Indicative substation layout
5.11.  Indicative substation elevations
Site Plan with Turbine IDs 
Reason: to ensure that the development is carried out in accordance with the approved
details. 
Design and operation of turbines 
4. There shall be no commencement of development unless full details of the proposed
wind turbines (including, but not limited to, the power rating and sound power levels, the
size, type, external finish and colour which should be non-reflective pale grey semi-matt),
any anemometry masts and all associated apparatus have been submitted to and approved
in writing by the planning authority.  The turbines shall be consistent with the candidate
turbine or range assessed in the environmental statement, and the maximum tip height
shall not exceed 145 metres above ground level.  The development shall be constructed
and operated in accordance with the approved details and maintained in the approved
colour, free from external rust, staining or discolouration, until such time as the wind farm is
decommissioned.   
All wind turbine blades shall rotate in the same direction. 
None of the wind turbines, anemometers, power performance masts, switching stations or
transformer buildings/enclosures, ancillary buildings or above ground fixed plant shall
display any name, logo, sign or other advertisement (other than health and safety signage)
unless otherwise approved in advance in writing by the planning authority.

Page 25

PPA-130-2084 25
Reason: to ensure that the environmental impacts of the turbines forming part of the
development conform to the impacts of the candidate turbine assessed in the environmental
statement and in the interests of the visual amenity of the area. 
Design of sub-station and ancillary development 
5. There shall be no commencement of development unless final details of the external
appearance, dimensions, and surface materials of the substation building, associated
compounds, any construction compound boundary fencing, external lighting and parking
areas have been submitted to and approved in writing by the planning authority.  The
substation building, associated compounds, fencing, external lighting and parking areas
shall be constructed in accordance with the approved details. 
Reason: to ensure that the environmental impacts of the sub-station and ancillary
development forming part of the development conform to the impacts assessed in the
environmental statement and in the interests of the visual amenity of the area. 
Micro-siting 
6. All wind turbines, buildings, masts, areas of hardstanding and tracks shall be constructed
in the location shown on plan reference site layout with turbine ID’s (6th February 2020)
wind turbines, buildings, masts, areas of hardstanding and tracks may be adjusted by
micro-siting within the site.  However, unless otherwise approved in advance in writing by
the planning authority, micro-siting is subject to the following restrictions: 
a) no wind turbine foundation shall be positioned higher, when measured in metres above
ordinance datum (Newlyn), than the position shown on plan reference site layout with
turbine ID’s (6th February 2020); 
b) no wind turbine, building, mast or hardstanding shall be moved more than 50 metres
from the position shown on the original approved plans; 
c) no access track shall be moved more than 50 metres from the position shown on the
original approved plans; 
d) no micro-siting shall take place within areas of peat of greater depth than the original
location; 
e) no micro-siting shall take place within areas hosting ground water dependent terrestrial
ecosystems; and, 
f) all micro-siting permissible under this condition must be approved in advance in writing by
the Ecological Clerk of Works (ECoW). 
No later than one month after the date of first commissioning, an updated site plan must be
submitted to the planning authority showing the final position of all wind turbines, masts,
areas of hardstanding, tracks and associated infrastructure forming part of the
development.  The plan should also specify areas where micro-siting has taken place and,
for each instance, be accompanied by copies of the ECoW or planning authority’s approval,
as applicable. 
Reason: to control environmental impacts while taking account of local ground conditions.

Page 26

PPA-130-2084 26
Borrow pits – scheme of works 
7. There shall be no commencement of development unless a site specific scheme for the
working and restoration of each borrow pit forming part of the development has been
submitted to and approved in writing by the planning authority.  The scheme shall include: 
a) a detailed working method statement based on site survey information and ground
investigations; 
b) details of the handling of any overburden (including peat, soil and rock); 
c) drainage, including measures to prevent surrounding areas of peatland, water dependant
sensitive habitats and ground water dependant terrestrial ecosystems (GWDTE) from
drying out; 
d) a programme of implementation of the works described in the scheme; and, 
e) full details of the reinstatement, restoration and aftercare of the borrow pit(s) at the end of
the construction period, to include topographic surveys of pre-construction profiles, and
details of topographical surveys to be undertaken of the restored borrow pit profiles. 
The approved scheme shall thereafter be implemented in full. 
Reason: to ensure that excavation of materials from the borrow pit(s) is carried out in a
manner that minimises the impact on road safety, amenity and the environment, and that
the mitigation measures contained in the Environmental Statement accompanying the
application, or as otherwise agreed, are fully implemented.  To secure the restoration of
borrow pit(s) at the end of the construction period. 
Ecological Clerk of Works 
8. There shall be no commencement of development unless the planning authority has
approved in writing the terms of appointment by the developer of an independent Ecological
Clerk of Works (ECoW).  The terms of appointment shall: 
a) impose a duty to monitor compliance with the ecological and hydrological commitments
provided in the environmental statement and other information lodged in support of the
application, the Construction and Environmental Management Plan, the Habitat
Management Plan approved in accordance with condition 16, and other plans approved in
terms of condition 9 (“the ECoW works”); 
b) require the ECoW to report to the developer’s nominated construction project manager
any incidences of non-compliance with the ECoW works at the earliest practical opportunity; 
c) require the ECoW to submit a monthly report to the planning authority summarising
works undertaken on site; and, 
d) require the ECoW to report to the planning authority any incidences of non-compliance of
works at the earliest practical opportunity. 
The ECoW shall be appointed on the approved terms throughout the period from
commencement of development, throughout any period of construction activity and during
any period of post construction restoration works approved in terms of condition 9.

Page 27

PPA-130-2084 27 
No later than 18 months prior to decommissioning of the development or the expiration of
this consent (whichever is the earlier), the developer shall submit details of the terms of
appointment of an independent ECoW throughout the decommissioning, restoration and
aftercare phases of the development to the planning authority for approval.  The ECoW
shall be appointed on the approved terms throughout the decommissioning, restoration and
aftercare phases of the development. 
Reason: to secure effective monitoring of and compliance with the environmental mitigation
and management measures associated with the development during the construction,
decommissioning, restoration and aftercare phases. 
Construction and environmental management plan 
9. There shall be no commencement of development unless a Construction and
Environmental Management Plan (“CEMP”) outlining site specific details of all on-site
construction works, post-construction reinstatement, drainage and mitigation, together with
details of their timetabling, has been submitted to and approved in writing by the planning
authority.  The CEMP shall include (but shall not be limited to) the following: 
a) a site waste management plan (dealing with all aspects of waste produced during the
construction period other than peat), including details of contingency planning in the event
of accidental release of materials which could cause harm to the environment; 
b) details of the formation of the construction compound, welfare facilities, any areas of
hardstanding, turning areas, internal access tracks, car parking, material stockpiles, oil
storage, lighting columns, and any construction compound boundary fencing; 
c) a dust management plan; 
d) site specific details for management and operation of any concrete batching plant
(including disposal of pH rich waste water and substances); 
e) details of measures to be taken to prevent loose or deleterious material being deposited
on the local road network including wheel cleaning and lorry sheeting facilities, and
measures to clean the site entrances and the adjacent local road network; 
f) a pollution prevention and control method statement, including arrangements for the
storage and management of oil and fuel on the site; 
g) soil storage and management; 
h) a peat management plan, to include details of vegetated turf stripping and storage, peat
excavation (including volumes), handling, storage and re-use; 
i) a drainage management strategy, demonstrating how all surface and waste water arising
during and after development will be managed and prevented from polluting any
watercourses or sources; surface water drainage to be designed in accordance with CIRIA
C753 and be in operation prior to the start of construction; 
j) a surface water and groundwater management and treatment plan, including details of the
separation of clean and dirty water drains, and location of settlement lagoons for silt laden
water;

Page 28

PPA-130-2084 28 
k) sewage disposal and treatment; 
l) temporary site illumination; 
m) the construction of the access into the site and the creation and maintenance of
associated visibility splays; 
n) the method of construction of the crane pads; 
o) the method of construction of the turbine foundations; 
p) the method of working cable trenches; 
q) the method of construction and erection of the wind turbines and meteorological masts; 
r) details of watercourse crossings which shall be designed to pass the 1 in 200 year plus
climate change (56% allowance) flood event; 
s) post-construction restoration/reinstatement of the working areas not required during the
operation of the development, including construction access tracks, borrow pits,
construction compound, storage areas, laydown areas, access tracks, passing places and
other construction areas.  Wherever possible, reinstatement is to be achieved by the careful
use of turfs removed prior to construction works. Details should include all seed mixes to be
used for the reinstatement of vegetation; 
t) a wetland ecosystems survey and mitigation plan; and, 
u) a felling and tree management plan. 
The development shall be implemented thereafter in accordance with the approved CEMP
unless otherwise approved in advance in writing by the planning authority. 
Reason: to ensure that all construction operations are carried out in a manner that
minimises their impact on road safety, amenity and the environment, and that the mitigation
measures contained in the Environmental Statement accompanying the application, or as
otherwise agreed, are fully implemented. 
Construction hours 
10. Construction work which is audible from any noise-sensitive receptor shall only take
place on the site between the hours of 07:00 to 19:00 on Monday to Friday inclusive and
07:00 and 18:00 on Saturdays, with no such work taking place on a Sunday or Public
Holiday.  Outwith these specified hours, development on the site must be limited to turbine
erection, maintenance, emergency works, dust suppression, and the testing of plant and
equipment, unless otherwise approved in advance in writing by the planning authority. 
HGV movements to and from the site (excluding abnormal loads) during construction of the
wind farm shall be limited to 07.00 to 19.00 Monday to Friday, and 07.00 to 16.00 on
Saturdays, with no HGV movements to or from site taking place on a Sunday or Public
Holiday, unless previously approved in writing by the planning authority.

Page 29

PPA-130-2084 29
Reason: in the interests of amenity to restrict noise impact and the protection of the local
environment. 
Trunk and local road network 
11. There shall be no commencement of development, including deliveries to the site,
unless and until a Traffic Management Plan (“TMP”) has been submitted to, and approved
in writing by the planning authority.  The TMP shall include (but is not limited to): 
a) the proposed routing for all traffic (including abnormal loads) associated with the
development on the local and trunk road networks; 
b) measures to ensure that the specified routes are adhered to, including monitoring
procedures; 
c) the accommodation measures required including the removal of street furniture,
junction/bend widening and traffic management undertaken by a recognised traffic
management consultant and all signs poles and other street furniture to be removed and
replaced after each movement where feasible to maintain road safety for other road users; 
d) details of materials, plant, equipment and labour required during the construction period; 
e) details of any temporary diversions of access routes and associated signage; 
f) detailed junction design to include construction specification, swept path analysis,
kerbing, drainage and visibility splays; 
g) details of any verge strengthening and carriageway widening, which shall be reinstated
once delivery is completed and remain the responsibility of the developer; and, 
h) details of delivery programme, which shall ensure no other large loads movements are
scheduled to occur within the same timeframe, and that transportation of abnormal loads
will not coincide with peak travel times including the start and finish of nearby Strachur
Primary School. 
The approved traffic management plan shall thereafter be implemented in full, unless and
until otherwise agreed in advance in writing with the planning authority. 
Reason: in the interests of road safety and to ensure that the transportation of abnormal
loads will not have any detrimental effect on the trunk or local road network. 
Video record, access construction & visibility splays 
12. Prior to commencement of the development a video record of the road corridor from the
A815 to the site, including the junction at the A815 and the detailed design of the proposed
access junction with the A815 shall be submitted for the further written approval of the
planning authority.  The proposed access junction design with the public road shall: 
a) be surfaced with a bound material for a distance of 10 metres from the edge of the public
road; 
b) have positive surface water drainage installed to deal with both runoff from the site and
the roadside ditch; and,

Page 30

PPA-130-2084 30 
c) the carriageway shall be a minimum width of 5.5 metres across the bell-mouth. 
Prior to work starting on site the approved access junction design shall be formed in
accordance with the agreed details and maintained to the satisfaction of the planning
authority. 
Reason: in the interests of road safety and to ensure that the existing access onto the site is
improved to accommodate the components required to construct the wind turbines. 
Right of way SA32 
13. Right of way SA32 shall remain open and free from obstruction to the satisfaction of the
planning authority during and after any proposed construction works. 
Reason: in the interests of maintaining and safeguarding access rights. 
Pre-construction survey 
14. No development or other work shall be carried out on the site until a pre-
commencement survey for the presence of salmon and the quality of their baseline habitat
has been carried out by an appropriately qualified person and has been submitted for the
written approval of the planning authority. 
In circumstances where species of interest are identified as being present, or at risk from
construction works, the survey shall further provide suggested avoidance and or mitigation
measures, including timing constraints, to address such presence or risk, as well as an
appropriate programme of post construction survey work. 
The development shall be implemented in accordance with the measures identified in the
duly approved scheme. 
Reason: in order to establish that the circumstances of the site have not changed
significantly between approval and implementation of the development for the purpose of
protecting natural heritage assets in the interest of nature conservation. 
Post-construction monitoring 
15. No development shall commence unless and until an appropriate programme of post
construction monitoring as proposed in EIAR Chapter 11 Ornithology, Section 11.12.2
Mitigation During Operation Phase is submitted to and approved in writing by the planning
authority. 
Reason: to ensure the predicted impacts on important bird populations and success of
proposed mitigation, as outlined in the EIA Report can be monitored. 
Habitat Management Plan 
16. There shall be no commencement of development unless and until a Habitat
Management Plan (“HMP”) has been submitted to, and approved in writing by the planning
authority.

Page 31

PPA-130-2084 31
The HMP shall set out proposed habitat management of the wind farm site during the
period of construction, operation, decommissioning, restoration and aftercare of the site,
and shall seek to improve the condition of the G/LG3 range habitat on site. 
The approved HMP will include provision for regular monitoring and review to be
undertaken to consider whether amendments are needed to better meet the HMP
objectives.  In particular, the approved HMP will be updated to reflect ground condition
surveys undertaken following construction and prior to the date of final commissioning and
submitted to the planning authority for written approval.  Unless otherwise agreed in
advance in writing with the planning authority, the approved HMP shall be implemented in
full throughout the life time of the development, including decommissioning. 
Reason: in the interests of good land management and the protection of habitats. 
Wind Farm Forest Design Plan 
17. No development shall commence until a finalised Long Term Forest Plan for the
Forestry Study Area (as shown on Figure 6.1 in Volume 3 of the EIA Report) has been
submitted to and approved in writing by the planning authority.  The approved Long Term
Forest Plan shall thereafter be implemented in full, unless otherwise agreed in advance and
in writing by the planning authority. 
Reason: to ensure forestry works approved by the consent are carried out in accordance
with UK Forestry Standard. 
Compensatory forestry planting 
18. No forestry works, associated with the construction and operation of the development,
shall commence until a Compensatory Planting Plan (“CPP”) has been submitted to and
approved by the planning authority (in consultation with Scottish Forestry as required).  The
CPP shall provide for the planting of woodland commensurate with the level of woodland
lost (anticipated to be 20.1 ha). 
The CPP shall comply with the requirements set out in the UK Forestry Standard and the
guidelines to which it refers, or such other replacement standard agreed by the planning
authority.  The CPP shall include: 
a) details of the location of the area to be planted; 
b) the nature, design and specification of the proposed woodland to be planted; 
c) the phasing and associated timescales for implementing the replanting scheme; 
d) proposals for the maintenance of the replanting scheme, including annual checks,
replacement planting, fencing, ground preparation and drainage; and, 
e) proposals for reporting to the planning authority on compliance with timescales for
obtaining the necessary consents and implementation of the replanting scheme. 
The approved replanting scheme shall be implemented in full, unless otherwise agreed in
writing by the planning authority.

Page 32

PPA-130-2084 32
Reason: to secure compensatory planting to mitigate against effects of deforestation arising
from the development. 
Peat landslide management 
19. There shall be no commencement of the development until a detailed peat landslide risk
assessment, addressing construction phase of the development and post-construction
monitoring, has been approved in writing by the planning authority. 
The peat landslide risk assessment shall comply with best practice contained in “Peat
Landslide Hazard and Risk Assessments: Best Practice Guide for Proposed Electricity
Generation Developments” published by the Scottish Government in January 2007, or such
replacement standard as may be in place at the time of submission of the peat landslide
risk assessment for approval.  The peat landslide risk assessment shall include a scaled
plan and details of any mitigation measures to be put in place. 
The approved peat landslide risk assessment shall thereafter be undertaken in full prior to
commencement of development. 
Prior to commencement of development, the developer shall appoint and pay for an
independent and suitably qualified geotechnical engineer acceptable to the planning
authority, the terms of whose appointment (including specification of duties and duration of
appointment) shall be approved by the planning authority. 
The developer shall undertake continuous monitoring of ground conditions during the
construction and deforestation phases of the development.  Continuous analysis and call
out services shall be provided by the geotechnical engineer throughout the construction
phase of the development.  If a risk of peat failure is identified, the developer shall install
such geotechnical instrumentation to monitor ground conditions as is recommended by the
geotechnical engineer and shall monitor ground conditions.  Any remediation work
considered necessary by the geotechnical engineer shall be implemented by the developer
to the satisfaction of the geotechnical engineer.  Monitoring results shall be fed into risk
analysis reports to be submitted to the planning authority on a quarterly basis during the
construction and deforestation phases of the development. 
Reason: to minimise the risk of peat failure arising from the development. 
Noise 
20. The level of noise emissions from the combined effects of the wind turbines at Creag
Dhubh wind farm (including the application of any tonal penalty) when calculated in
accordance with a procedure agreed with the planning authority, shall not exceed the
values set out in Tables 1 to 2 as appropriate.  Noise limits for dwellings which lawfully exist
or have planning permission for construction at the date of this permission but are not listed
in the tables below shall be those of the physically closest location listed in the tables
unless otherwise agreed by the planning authority.

Page 33

PPA-130-2084 33 
Table 3 – Coordinates of properties listed in tables 1 and 2 
Location Eastings Northings
Islay Cottage 210635 700910
Succothmore Farm 212459 701796
Succothmore (Fearnoch) 212488 701778
Succothmore Cottage 212370 701641
Ardchyline Farm 211203 706000
Laglingarten 214448 707961 
Reason: to minimise the adverse impact of noise generated by the operations on the local
community. 
21. Prior to the installation of any turbines the developer shall submit a report for approval
by the planning authority which demonstrates compliance with the noise limits in
condition 20 above.  The report shall include details of any proposed noise reduction
measures and be prepared with reference to the Institute of Acoustics Good Practice Guide
to the Application of ETSU-R-97 and associated supplementary guidance notes. 
Reason: to minimise the adverse impact of noise generated by the operations on the local
community. 
22. Within 21 days from the receipt of a written request from the planning authority or
following a complaint to the planning authority from the occupant of a dwelling the wind
turbine operator shall, at the wind turbine operator’s expense, employ an independent
consultant approved by the planning authority to assess the level of noise emissions from
the wind turbines at the complainant’s property following procedures to be agreed with the
planning authority. 
Reason: to minimise the adverse impact of noise generated by the operations on the local
community.

Page 34

PPA-130-2084 34
23. The wind turbine operator shall provide to the planning authority the independent
consultant’s assessment and conclusions regarding the said request or noise complaint,
including all calculations, audio recordings and the raw data upon which those assessments
and conclusions are based.  Such information shall be provided within 2 months of the date
of the written request of the planning authority unless otherwise extended in writing by the
planning authority.  The wind turbine operator shall take such remedial action required to
the satisfaction of the planning authority. 
Reason: to minimise the adverse impact of noise generated by the operations on the local
community. 
24. Wind speed, wind direction and power generation data shall be continuously logged and
provided to the planning authority in a format to be agreed at its request and within 28 days
of such a request.  Such data shall be retained by the operator for a period of not less than
12 months. 
Reason: to minimise the adverse impact of noise generated by the operations on the local
community. 
25. No development shall commence until there has been submitted to the planning
authority details of a nominated representative for the development to act as a point of
contact for local residents (in connection with conditions 20 – 24) together with the
arrangements for notifying and approving any subsequent change in the nominated
representative.  The nominated representative shall have responsibility for liaison with the
planning authority in connection with any noise complaints made during the construction,
operation and decommissioning of the wind turbines. 
Reason: to minimise the adverse impact of noise generated by the operations on the local
community. 
Aviation safety 
26. There shall be no commencement of development until the developer has provided the
planning authority and Defence Infrastructure Organisation (Ministry of Defence) with the
following information: 
a) the date of expected commencement and completion of construction works; 
b) the maximum extension height of any construction equipment; and, 
c) the position of the wind turbines in latitude and longitude. 
Reason: in the interests of aviation safeguarding. 
Aviation lighting 
27. Prior to the erection of the first wind turbine, the developer shall submit a scheme for
aviation lighting for the wind farm to the planning authority for written approval.  The
scheme shall include details of infra-red aviation lighting to be applied.  No lighting other
than that described in the scheme may be applied at the site, other than as required for
health and safety, unless otherwise agreed in advance and in writing by the planning
authority.

Page 35

PPA-130-2084 35
No turbines shall be erected on site until the scheme has been approved in writing.  The
development shall thereafter be operated fully in accordance with the approved scheme. 
Reason: in the interests of aviation safety. 
Site decommissioning, restoration and aftercare 
28. The development will be decommissioned and will cease to generate electricity by no
later than the date falling twenty-five years from the date of final commissioning. The total
period for restoration of the site in accordance with this condition shall not exceed three
years from the date of final decommissioning without prior written approval of the planning
authority. 
There shall be no commencement of development unless a decommissioning, restoration
and aftercare strategy has been submitted to and approved in writing by the planning
authority.  The strategy shall outline measures for the decommissioning of the development,
restoration and aftercare of the site and will include, without limitation, proposals for the
removal of the development, the treatment of ground surfaces, the management and timing
of the works, and environmental management provisions. 
No later than 3 years prior to decommissioning of the development or the expiration of this
consent (whichever is the earlier) a detailed decommissioning, restoration and aftercare
plan, based upon the principles of the approved decommissioning, restoration and aftercare
strategy, shall be submitted to the planning authority for written approval.  The detailed
decommissioning, restoration and aftercare plan will provide updated and detailed
proposals for the removal of the development, the treatment of ground surfaces, the
management and timing of the works and environment management provisions which shall
include (but is not limited to): 
a) a site waste management plan (dealing with all aspects of waste produced during the
decommissioning, restoration and aftercare phases); 
b) details of the formation of the construction compound, welfare facilities, any areas of
hardstanding, turning areas, internal access tracks, car parking, material stockpiles, oil
storage, lighting columns, and any construction compound boundary fencing; 
c) a dust management plan; 
d) details of measures to be taken to prevent loose or deleterious material being deposited
on the local road network including wheel cleaning and lorry sheeting facilities, and
measures to clean the site entrances and the adjacent local road network; 
e) a pollution prevention and control method statement, including arrangements for the
storage and management of oil and fuel on the site; 
f) details of measures for soil storage and management; 
g) a surface water and groundwater management and treatment plan, including details of
the separation of clean and dirty water drains, and location of settlement lagoons for silt
laden water; 
h) details of measures for sewage disposal and treatment;

Page 36

PPA-130-2084 36
i) temporary site illumination; 
j) the construction of any temporary access into the site and the creation and maintenance
of associated visibility splays; 
k) a traffic management plan (“TMP”) which provides for the arrangements in respect of
traffic associated with the decommissioning of the development which mirrors the relevant
provisions approved in the TMP for the construction of the development; 
l) details of watercourse crossings; and, 
m) a species protection plan based on surveys for protected species (including birds)
carried out no longer than 18 months prior to submission of the plan. 
The development shall be decommissioned, the site restored and aftercare thereafter
undertaken in accordance with the approved plan, unless otherwise agreed in writing in
advance with the planning authority. 
Reason: to ensure the decommissioning and removal of the development in an appropriate
and environmentally acceptable manner and the restoration and aftercare of the site, in the
interests of safety, amenity and environmental protection. 
Financial guarantee 
29. There shall be no commencement of development unless the developer has delivered a
bond or other form of financial guarantee in terms acceptable to the planning authority
which secures the cost of performance of all decommissioning, restoration and aftercare
obligations contained in condition 28 to the planning authority.  The financial guarantee
shall thereafter be maintained in favour of the planning authority until the date of completion
of all restoration and aftercare obligations. 
The value of the financial guarantee shall be determined by a suitably qualified independent
professional as being sufficient to meet the costs of all decommissioning, restoration and
aftercare obligations contained in condition 28. The value of the financial guarantee shall be
reviewed by a suitably qualified independent professional no less than every five years and
increased or decreased to take account of any variation in costs of compliance with
restoration and aftercare obligations and best practice prevailing at the time of each review. 
Reason: to ensure that there are sufficient funds to secure performance of the
decommissioning, restoration and aftercare conditions attached to this deemed planning
permission in the event of default by the developer. 
Redundant wind turbines 
30. If any of the wind turbines hereby permitted cease to export electricity to the grid for a
continuous period of 12 months following the first export date, not due to it being under
repair or replacement, then on the written request of the planning authority, within 1 month
a partial decommissioning scheme or a scheme for repair shall be submitted to the planning
authority for its written approval.  If the scheme is for decommissioning, then it shall include
a method statement and timetable for the dismantling and removal of the relevant turbine
and associated above ground works and foundations to a depth of at least 1 metre below
ground together with a Traffic Management Plan to address likely traffic impact issues
during the decommissioning period and restoration measures for the land from which the

Page 37

PPA-130-2084 37
relevant turbine and any ancillary equipment and structures have been removed.  The
scheme shall thereafter be implemented as approved. 
Reason: to ensure that appropriate provision is made for turbine decommissioning or
repairs. 
Schedule 2:  Advisory notes 
1. Notice of the start of development:  The person carrying out the development must
give advance notice in writing to the planning authority of the date when it is intended to
start.  Failure to do so is a breach of planning control.  It could result in the planning
authority taking enforcement action (See sections 27A and 123(1) of the Town and Country
Planning (Scotland) Act 1997 (as amended)). 
2. Notice of the completion of the development:  As soon as possible after it is
finished, the person who completed the development must write to the planning authority to
confirm the position (See section 27B of the Town and Country Planning (Scotland) Act
1997 (as amended)). 
3. Display of notice:  A notice must be displayed on or near the site while work is being
carried out.  The planning authority can provide more information about the form of that
notice and where to display it (See section 27C of the Town and Country Planning
(Scotland) Act 1997 Act (as amended) and Schedule 7 to the Town and Country Planning
(Development Management Procedure) (Scotland) Regulations 2013 
4. Right to challenge this decision: This decision is final, subject to the right of any
person aggrieved by this decision to question its validity by making an application to the
Court of Session.  An application to the Court of Session must be made within 6 weeks of
the date of the decision.  Your local Citizens’ Advice Bureau or your solicitor will be able to
advise you about the applicable procedures. 
5. Notification of this decision by the planning authority:  The planning authority is
required (a) to inform the public and bodies consulted in respect of the EIA report of this
decision by publishing a notice on the application website or newspaper circulating the in
locality of the proposed development or by other reasonable means and (b) to make a copy
of the decision available for public inspection in an office of the planning authority where its
planning register may be inspected and on the application website. 
Schedule 3: Application drawings: 
EIA Report
5.1.    Site location
5.2.    Site layout
5.3.    Access design
5.4.    Candidate turbine elevations
5.5.    Indicative turbine foundations
5.6.    Indicative access track designs
5.7.    Indicative watercourse crossing design
5.8.    Cable trench sections
5.9.    Indicative crane hardstanding
5.10.  Indicative substation layout
5.11.  Indicative substation elevations
Site Plan with Turbine IDs

Page 38

PPA-130-2084 38
Schedule 4:  Opportunities for public participation in decision-making 
There is the following evidence before me of opportunities the public had to take part in
decision-making procedures on the application before I was appointed to this appeal: 
• the appellant has provided a report on pre-application consultation.  Two public 
meetings were held with Strachur Community Council on the 11 October 2017 and 13 
June 2018.  During this period informal discussions were also held with members of 
Lochgoil Community Trust.  Two public exhibitions were held at Strachur Memorial Hall 
on the 9 November 2017 and 10 April 2019.  At these events the public had an 
opportunity to comment to the appellant on the proposed development; 
• an advertisement of the application in the Dunoon Observer; Argyllshire Advertiser; 
Campbeltown Courier and The Edinburgh Gazette on the 7 February, 24 April, 11 
September 2020 and the 12 February 2021 has been provided.  The advertisements 
advised the public of the opportunity to make representations upon the proposal for the 
development and the accompanying EIA report; 
• the planning authority received 16 public representations in respect of the application. 
The main points raised in those representations are summarised in this decision notice 
at paragraph 102; and, 
• additional information was submitted to the planning authority and the public had an 
opportunity to comment on that information. 
Those who made representations upon the application have been treated as interested
parties in the appeal.  They have had the opportunity to make representations on matters
that they raised, by written response to the appeal.