APPENDIX A
PERTH AND KINROSS COUNCIL
EDUCATION AND CHILDREN’S SERVICES
CONSULTATION REPORT
REPORT ON THE OUTCOME OF THE CONSULTATION RELATING TO
THE PROPOSAL TO:
 Establish a new primary school on a preferred site at Bertha
Park, Perth; 
 Establish a catchment area for the new primary school; 
 Amend the catchment areas of Ruthvenfield Primary School,
Pitcairn Primary School, Luncarty Primary School and Tulloch
Primary School; 
 Establish the transfer arrangements for directly affected
primary pupils to attend secondary school; and
 Establish interim admission arrangements for Ruthvenfield
Primary School until the new primary school opens in August
2026.
21 September 2022
This Consultation Report has been issued by Perth and Kinross Council in accordance with
the Schools (Consultation) (Scotland) Act 2010.

Page 2

2
Contents                                                                                                            
Page   
4
1. INTRODUCTION 
5
2. BACKGROUND 
3. CONSIDERATIONS 5
4. REASON FOR FORMULATING THE PROPOSAL  6
5. SCHOOL INFORMATION  6
6. THE CONSULTATION PROCESS  7
7. THE PUBLIC MEETINGS  9
8. RESPONSES TO THE CONSULTATION EXERCISE 9
9. EDUCATION AUTHORITY RESPONSE TO WRITTEN AND ORAL   10    
REPRESENTATIONS 
10. EDUCATION SCOTLAND REPORT  15 
11.   ALLEGED OMISSIONS OR INACCURACIES  18
12.   COMPLIANCE WITH SECTION 9(1) OF THE SCHOOLS  18 
(CONSULTATION) (SCOTLAND) ACT 2010 
13.   LEGAL ISSUES  19
14.   PERSONNEL IMPLICATIONS  20
15.   CONCLUSION  20
16.    RECOMMENDATIONS  22

Page 3

3
Appendices                                                                                                         
Page
Appendix 1 Minute of Public Meeting of 31 May 2022  23
Appendix 2 Minute of Public Meeting of 13 June 2022 27
Appendix 3  Summary of Consultation Responses  30
Appendix 4 Online and Written Responses  35
Appendix 5 Pupil Consultations  37
Appendix 6  Education Scotland Report  39

Page 4

4
PERTH AND KINROSS COUNCIL
EDUCATION AND CHILDREN’S SERVICES
This report has been prepared following consultation on the Council’s proposal to:
 establish a new primary school on a preferred site at Bertha Park, Perth with effect
from August 2026; 
 establish a catchment area for the new primary school; 
 amend the catchment areas of Ruthvenfield Primary School, Pitcairn Primary
School, Luncarty Primary School and Tulloch Primary School;
 establish the transfer arrangements for directly affected primary pupils to attend
secondary school; and
 establish interim admission arrangements for Ruthvenfield Primary School until the
new primary school opens in August 2026.
Having had regard (in particular) to:
(a) Relevant written representations received by the Council (from any person) during
the consultation period;
(b) Oral representations made to it (by any person) at the public meetings held on 
31 May 2022 and 13 June 2022; and
(c) Education Scotland’s report on the proposal.
1. INTRODUCTION
This is a consultation report prepared in compliance with the Schools (Consultation)
(Scotland) Act 2010 on the above proposal.
1.1 The purpose of this report is to:
 Provide a record of the total number of written responses made during the Statutory
Consultation period; 
 Provide a summary of the written responses; 
 Provide a summary of oral representations made at the public meetings held on    
31 May 2022 and 13 June 2022;  
 Provide a statement of the Council’s response to those written and oral
representations; 
 Provide the full text of Education Scotland’s report and a statement of the Council’s
response to this report; 
 State how the Council reviewed the above proposal following the representations
received during the Statutory Consultation period and the report from Education
Scotland; and 
 Provide details of any omission from, or inaccuracy in, the Proposal Paper and
state how the Council acted upon it.

Page 5

5
2. BACKGROUND
2.1 On 22 June 2016, the Council allocated funding for a new primary school within the
Composite Capital Programme (Report No. 16/277 refers). This new primary school is
to be built to accommodate pupil numbers from housebuilding within the strategic sites
at the north and north west of Perth as it was anticipated that the catchment schools
for these strategic sites would not be able to accommodate the projected pupil
numbers. 
There is a chronology of decisions leading to this report including reports and options
appraisals presented to Lifelong Learning Committee in relation to Ruthvenfield
Primary School, the School Estate Transformation Programme and the new primary
school at Bertha Park.  These reports can be read if anyone wishes fuller background
information about the background to the decision that a new primary school is required
and where that new primary school should ideally be located. These are as follows;
 August 2016 - ‘Securing the Future of the School Estate’ (Report No. 16/347
refers) 
 November 2016 - “Securing the Future of the School Estate – Next Steps”
(Report 16/485 refers)
 March 2019 – School Estate Transformation Programme (Report No.19/94
refers)
 September 2019 - “School Estate Transformation Programme Strategic Sites
North West/North Perth” (Report No. 19/240 refers) 
 22 January 2020 Lifelong Learning Committee (Report No. 20/18 refers). 
 25 August 2021 Lifelong Learning Committee (Report No. 21/136 refers).
2.2 In the report considered by Lifelong Learning Committee on 25 August 2021, it was
agreed that the Executive Director (Education and Children’s Services) commenced a
statutory consultation in respect of the new catchment areas and associated changes
as required by the Schools Consultation (Scotland) Act 2010.
2.3 The duties in undertaking a statutory consultation on a relevant school proposal are
outlined in the Schools (Consultation) (Scotland) Act 2010 and the accompanying
Statutory Guidance.
2.4 Lifelong Learning Committee reports and the Proposal Paper referred to above are
available on the Council’s website www.pkc.gov.uk.
3. CONSIDERATIONS
3.1 The main considerations relating to the proposal are fully explained in the 
Proposal Paper, and the main points are highlighted as follows:
3.2 The Council’s Corporate Plan identifies the vision of “a confident and ambitious Perth &
Kinross with a strong identity and clear outcomes that everyone works together to
achieve.  Our area will be vibrant and successful; a safe secure and healthy
environment: and a place where people and communities are nurtured and supported’.

Page 6

6
3.3 This strategic approach embraces the vision for our area, our communities and
our people as outlined in the Corporate Plan.  Our key service priorities support
the delivery of our commitments in the Community Planning Partnership’s Single
Outcome Agreement and Corporate Plan, helping Education and Children’s Services
to focus on the local outcomes that will achieve meaningful improvements for the area,
our local communities and our citizens. 
3.4 Councils have a statutory duty in terms of the Education (Scotland) Act 1980 to make
adequate and efficient provision of school education across their entire area for the
current school population and future pattern of demand.  
3.5 Councils also have a statutory responsibility in terms of the Local Government in
Scotland Act 2003 to achieve best value.  To achieve best value and optimum
efficiency, the organisation of the school estate is therefore kept under regular review,
including the need for school provision and other factors, such as altering catchment
areas.
3.6 The Schools (Consultation) (Scotland) Act 2010 provides a strong,
accountable statutory consultation process that local authorities must apply to their
handling of all proposals of major changes to schools.  These consultation processes
are expected to be robust, open, transparent and fair, and seen to be so. They are also
expected to be consistent across Scotland.
3.7 The Education (Scotland) Act 2016 amends the Standards in Scotland’s Schools Act
2000 by adding in new duties to address inequality of outcome.  These duties apply in
different ways to both Scottish Ministers and Education Authorities. Where the
Education Authority is making or implementing strategic decisions about school
education, it is required to have due regard to the need to carry out its functions in a
way which is designed to reduce inequalities of outcome.  This is particularly directed
in the Act towards pupils who experience those inequalities through socio-economic
disadvantage, but there is also a power to extend the range of pupils who are covered
by this duty. 
4. REASON FOR FORMULATING THE PROPOSAL
4.1 There is a 30 year masterplan for housebuilding at the strategic sites of Almond Valley,
Bertha Park and Perth West.  In the next 10 years, based on the current Housing Land
Audit (HLA), it is anticipated that 2512 houses will be built. This is estimated to
generate approximately 678 primary school pupils who will need to be accommodated
in schools near to where they live.  Existing catchment schools will not be able to
accommodate projected pupil numbers from housebuilding without the provision of a
new primary school and changes being made to their catchment areas.
5. SCHOOL INFORMATION
5.1 Ruthvenfield Primary School is a non-denominational school situated in Ruthvenfield
on the outskirts of Perth. The school roll as at Census 2021 is 60 pupils.

Page 7

7
The catchment area currently covers a widespread rural area and is bordered by the
Perth By-pass from Broxden to Crieff Road, Huntingtower Castle, Inveralmond
Industrial Estate, Almondbank and round to Lochty and over to Blackruthven and
Newhouse Farm on the outskirts of Perth City. The current catchment area for
Ruthvenfield Primary School sits within the major housebuilding development of
Almond Valley. 
In addition, a part of the Perth West development (the Auld Mart) currently forms part
of Ruthvenfield Primary School catchment area.  A new housing development site
named H319 in the Local Development Plan also forms part of Ruthvenfield Primary
School catchment area and is in close proximity to Ruthvenfield Primary School. The
catchment area borders the existing Perth City boundary adjacent to Tulloch Primary
School’s catchment area. 
5.2  Pitcairn Primary School is a non-denominational school situated in Almondbank on the
outskirts of Perth. The school roll as at Census 2021 is 92 pupils. The catchment area
covers a rural area and includes the settlements of Lochty, Almondbank and
Pitcairngreen. The catchment area is bordered by the primary school catchment areas
of Luncarty, Logiealmond and Methven. The current catchment area includes part of
the strategic development site of Bertha Park. 
5.3  Luncarty Primary School is a non-denominational school situated approximately six
miles North West of Perth, turning off the A9 at the Luncarty signpost. The school roll
as at Census 2021 is 122 pupils.  The school is situated in Marshall Road, which is a
cul-de-sac. The school’s delineated boundary extends to the River Tay in the East,
from Ordie Cottage in a North Westerly line to Woodend Farm and South East to
Bertha Park which falls within the strategic site for Bertha Park. 
5.4  Tulloch Primary School is a non-denominational Perth City primary school situated in
Gillespie Place, Perth. The school roll as at Census 2021 is 378 pupils. The catchment
area covers the Hillyland area of Perth contained by the Crieff Road and Dunkeld Road
and stretches to Inveralmond and to the boundary with Ruthvenfield.
5.5 As part of an options appraisal developed, information was collated regarding the
options considered and rejected, along with feedback received during the pre-
consultation exercise.  
5.6  The Council has engaged with stakeholders and considered other options prior to
formulating its proposal.  
6. THE CONSULTATION PROCESS
6.1 A link to the Proposal Paper was issued by letter to those individuals and bodies listed
under Distribution within the document.  The Proposal Paper was also published on the
Council’s website: www.pkc.gov.uk
6.2 The Proposal Paper informed consultees that the consultation period would run from
Monday 16 May 2022 until Wednesday 29 June 2022 – a period of at least 30 school
days.

Page 8

8
6.3 The proposal on which consultation took place was to:
 establish a new primary school on a preferred site at Bertha Park, Perth with
effect from August 2026; 
 establish a catchment area for the new primary school;
 amend the catchment areas of Ruthvenfield Primary School, Pitcairn Primary
School, Luncarty Primary School and Tulloch Primary School; 
 establish the transfer arrangements for directly affected primary pupils to attend
secondary school; and 
 establish interim admission arrangements for Ruthvenfield Primary School until
the new primary school opens in August 2026.
6.4 The requirements for consulting on a relevant proposal relating to schools are set out
in the Schools (Consultation) (Scotland) Act 2010. 
 A Proposal Paper was published on Monday 16 May 2022.  All statutory
consultees were written to providing a link to the proposal paper and details of
where and how to obtain a paper copy.  A copy of this document was available
free of charge to the consultees listed within the document. 
 The Proposal Paper was published on the Perth and Kinross Council website
and was available in paper copy upon request.  .      
 Two public meetings were held to discuss the proposal on Tuesday 31 May
2022 and Monday 13 June 2022. 
 The Consultation period ended on Wednesday 29 June 2022.     
 Education Scotland’s involvement consisted of the options appraisal and
proposal paper documents being sent to them, and visits to the sites of
Luncarty, Pitcairn, Ruthvenfield and Tulloch Primary Schools, including
discussion with relevant consultees.  They also received a copy of all online and
representations and the minutes of the public meetings.  They then prepared a
report on the educational aspects of the proposal.  This is attached as   
Appendix 6. 
6.5 The following schools are affected by the proposal:
 Luncarty Primary School 
 Pitcairn Primary School 
 Ruthvenfield Primary School 
 Tulloch Primary School
6.6 In accordance with statutory requirements and good practice, the following persons
were consulted:
 The parents of the pupils and children at the affected schools
 The parents of children expected to attend the affected schools within 2 years of  
the date of publication of this proposal document
 The Parent Council of the affected schools
 Directly affected pupils at the affected schools
 The teaching and ancillary staff at the affected schools
 The trade union and professional association representatives of the above staff
 The Community Council
 Relevant users of the affected schools

Page 9

9
 Elected Members of Perth and Kinross Council
 The Constituency MSPs and List MSPs covering the Constituency
 The Constituency MP
 The Executive Director, Communities, Perth and Kinross Council
 Tayside Contracts
  LiveActive Leisure
 Education Scotland
6.7 The number of letters issued with details of the Proposal Paper was 848.  
6.8 During the consultation period, representations were sought from interested parties,
either in oral or written form or electronically.  An online response form and generic
email account was set up by the Council to receive representations and enquiries on
the proposal.
6.9 This Consultation Report is the Council’s response to the issues raised during the
consultation period on the Proposal Paper. 
6.10 This Consultation Report is to be published on the Council’s website for a period of no
less than three weeks prior to final consideration by Learning & Families Committee on 
2 November 2022. 
7. THE PUBLIC MEETINGS
7.1 A public meeting was held in Bertha Park High School on Tuesday 31 May 2022. 
Nine members of the public attended.  A full note of the meeting is attached as
Appendix 1 which details the questions and issues raised at the meeting. 
7.2 A second public meeting was held in Bertha Park High School on Monday 13 June
2022. Two members of the public attended.  A full note of the meeting is attached as
Appendix 2 which details the questions and issues raised at the meeting. 
8. RESPONSES TO THE CONSULTATION EXERCISE
8.1 In all, 10 online response forms were received.  Nine responses agreed with the
Council’s proposal and one response disagreed with the Council’s proposal.  However
four online responses were invalid as they failed to provide a required name, address
or email address to validate the response. The six valid online responses agreed with
the Council’s proposal.  One written representation was received which disagreed with
the Council’s proposal.  
The details of the respondents are contained within the Summary of Consultation
Responses, attached as Appendix 3.  
8.2 In summary, the oral and written responses and questions can be grouped broadly as
follows:
 The proposal developed is a sensible approach in adapting the catchment
areas.

Page 10

10
 Families with children already attending Ruthvenfield Primary School wish to
ensure that younger siblings will be able to attend the same school as their
sibling.
 The proposed catchment area for Ruthvenfield Primary School includes the
community of which it is the heart of, rather than splitting it down the middle. 
 The interim admission arrangements take a pragmatic approach of considering
children with siblings which is appreciated. 
 The addition of a new school at Bertha Park and the associated catchment
review shows a good understanding of the various communities being created
with the new house building as well as clear connections with the existing
communities for their secondary education at Bertha Park High School. 
 The proposals for a new primary school will support the continued development
of the Bertha Park community and support more active travel to and from school
for pupils. Improved cycle routes should be included to aid safer journeys for
children to attend school.
 The management of both Bertha Park High School and the new primary school
should be managed by one management team. 
 The houses currently in the new catchment for Ruthvenfield Primary School
(less those that are planned to be developed) should be considered to be
brought into catchment earlier than 2026.
 If the catchment area serving Huntingtowerfield was to be changed to the new
school at Bertha Park, pupils could not walk to school as they do now. This does
not help active travel and encourages use of cars which would add to
congestion and pollution.  Huntingtowerfield should remain in the catchment
area for Ruthvenfield Primary School.
8.3 In summary, 848 letters were issued inviting comments and participation in the
consultation.  Ten online submissions and one written response was received in
respect of the consultation and full details of these is attached as Appendix 4.  Eleven
members of the public attended the two public meetings to give oral representations.
8.4 Specific consultation meetings took place with directly affected pupils at Ruthvenfield,
Pitcairn, Luncarty and Tulloch Primary Schools and full details of these is attached as
Appendix 5.
9. EDUCATION AUTHORITY RESPONSE TO WRITTEN AND ORAL
REPRESENTATIONS 
9.1 Clarification was sought regarding the new Ruthvenfield catchment area not
extending to the Auld Mart and Perth West and whether this is because there is
the potential for a new school to be built in Perth West. 
Housebuilding is expected to expand in the Almond Valley area so there may be a
requirement for another primary school to be built at some point in the future within the
30 year plan.

Page 11

11
As things stand, if the Council does not take steps now to reduce the catchment area
of Ruthvenfield Primary School and with housebuilding continuing, there is a finite
number of spaces within the school.  Therefore,  catchment children may not get into
the school in the future and will have to be zoned to another school with space.  This
could mean parents may be left in a situation of not knowing where their child will go to
school and those with siblings may not be able to enrol at the same school.  The
Council wants to avoid uncertainty for all parents and avoid the situation of siblings
living in catchment not being able to attend the same school and this is reflected in the
proposed catchment area to serve Ruthvenfield Primary School. 
9.2 Clarification was sought regarding how many pupils the new school can
accommodate.
The new primary school would have capacity for 434 pupils with 14 primary
classrooms.  The new school would not open initially with this number of pupils or
classes.  The Council will be modelling pupil numbers expected from August
2026.  The Council closely monitors the Housing Land Audit for pupils from new
housebuilding.  Depending on how many pupils stay at their existing primary school
and the number who choose to move to the new school when it opens, there could
possibly be 1 or 2 classes on day one, or if all pupils move, there could possibly be 5
or 6 classes initially.  The school will grow over time and the Council will be working to
correlate pupil numbers in the year leading up to the new school opening. A number of
children living in the strategic sites go to different schools currently, and the Council will
be asking all parents in the new school catchment area of their enrolment intentions to
allow class numbers and staffing to be planned for the new school opening. 
Registrations for the new school will begin in January 2026 for the school opening in
August 2026.  
9.3 Clarification was sought regarding what provision would be in place if there are
any problems with recruitment for the new school and whether the children
would remain in their existing school if staff could not be recruited.
The school registration process will commence in January 2026, this will give an
indication of expected pupil numbers.  The Council will also consider feedback from
parents who will have been contacted to share their enrolment intentions and, during
this period, the Council will also meet with Headteachers to assess their predicted pupil
numbers.  The Council has a Staffing Standard that will be applied and before the
Council allocates school places the projected pupil numbers will determine what the
required staffing will be as part of the annual staffing exercise.  This is normal practice
for planning the staffing requirements and managing vacancies for all schools for the
new school session each year, and staff will be in place as required for the opening of
the new school. 
9.4 Clarification was sought regarding whether the school will open in August 2026
and when will building work start.
The Council has a process to follow and it is anticipated that building work would start
in November 2024 and be completed in June 2026.  The planning and design of the
school will run concurrently with the statutory consultation. The Council will engage
further with parents through the User Reference Group which will be established
regarding design works, and it is expected that it will take 2 years to complete the
design phase over the period October 2022 to October 2024.

Page 12

12
9.5 It was queried if the nursery would be open in 2026.
The Council plans to open the nursery and the intensive support provision as part of
the school, and all will open together in 2026.
9.6 Clarification was sought regarding projected pupil numbers for Ruthvenfield PS
and Pitcairn PS and whether these would be breached.
The Council closely monitors pupil numbers during the school session.  Ruthvenfield
Primary School currently operates with 3 classes but has an additional classroom that
could be used to accommodate a further class to accommodate additional catchment
pupils.  The approved capacity for Ruthvenfield Primary School is 91 pupils but this
could be temporarily increased to 100 pupils, if necessary, to accommodate catchment
pupils.  The Council would only revert to this on an exceptional basis where catchment
pupils could not be accommodated otherwise.  Pitcairn Primary School does not have
any unused classrooms and would potentially require temporary accommodation on
site if capacity were to be breached before 2026.  The pupils currently attending
Pitcairn Primary School from Bertha Park would be in the proposed catchment for the
new primary school and will have the option to move to the new primary school when it
opens, or to remain at Pitcairn Primary School until the finish their primary
education.  The Council will undertake a detailed feasibility study of potential temporary
accommodation which may be required, which may be at Pitcairn Primary School. 
The Council has a duty to manage enrolments into Pitcairn Primary School and
Ruthvenfield Primary School as it does for all schools, to ensure that there is space for
catchment children, wherever possible, and to accommodate any increase in rolls
without breaching physical capacity limits.
9.7 Clarification was sought regarding whether priority would always be given to
existing and new catchment children to attend Ruthvenfield Primary School.
This would be the case until the new primary school is open and the new catchment
areas are implemented.  The Council’s proposed interim admission arrangements for
Ruthvenfield Primary School prioritise pupils living in the existing catchment area and
then pupils living in the proposed new catchment area, and this will continue to be the
case until August 2026.
9.8 A query was raised that If not enough children opted to go to the new primary
school at Bertha Park, would temporary accommodation remain at Pitcairn
Primary School.
No pupils would be forced to move school after they had commenced attending a
particular school and the Council would honour these enrolments until the pupils left
the school.  If this resulted in a temporary increase in capacity and temporary
accommodation, then this would remain in place until pupils had moved through the
school and left or where the roll decreased, no longer requiring temporary
accommodation. 
9.9 Clarification was sought regarding whether there was a risk of a child not getting
into Pitcairn Primary School between now until August 2026.
The Council will continue to manage enrolments until the new school is built and has a
legal duty to ensure that there are enough school places for all children in Perth and
Kinross.  If it becomes necessary, temporary arrangements may need to be put into
place for catchment children but this would not be a long term arrangement and only
be in place for as long as it needed to be.

Page 13

13
The Council’s Admission Policy will continue to be applied and the proposed new
arrangements would be operational from January 2026 for August 2026 enrolments. 
9.10 Clarification was sought whether an older sibling can move from Pitcairn
Primary School to the new primary school at Bertha Park.
This would absolutely be able to happen, and the Council recognises that moving
forward, parents will start to consider this.  The Council also recognises that everyone’s
circumstances are different and that this may depend on the individual pupil’s class
stage and friendship groups at the time of the new school opening, and it will be for
parents to decide what they wish for their child.  When the new primary school opens,
pupils living in the catchment area for the new primary school may have been in
another school for a number of years and choose to leave the school they started at to
attend to the new primary school when it opens. 
9.11 It was queried that if 150 homes are to be built in Ruthvenfield’s catchment area,
whether there will be space at Ruthvenfield Primary School to accommodate all
potential children.
The Council uses the formula of 0.27 primary pupils per home to project future pupil
numbers from housebuilding, but this can vary depending on the type and size of
houses that are being built.  The Council also monitors the build out rates agreed
within the Housing Land Audit which sets out how many houses are to be built each
year, as it will not be the case that all the houses will be built at the same
time.  Ruthvenfield Primary School is currently operating with 3 classes but can
increase to 4 classes if required for catchment pupils to be accommodated.  This could
allow a maximum of 100 pupils in Ruthvenfield Primary School.  Obviously, pupils will
move through the school and leave, and it is important that the Council continues to
manage the enrolments coming into Ruthvenfield Primary School to try to ensure that
there will be space to accommodate all potential pupils living in the catchment area in
the future.    
9.12 Clarification was sought regarding whether any areas of the current Tulloch
Primary School catchment area will become catchment for the new Primary
School.
Double Dykes at Inveralmond is currently within the catchment area for Tulloch Primary
School and is proposed to become part of the new Primary School catchment area. 
9.13 Clarification was sought regarding whether the new Primary School would be the
same size at Tulloch Primary School.
The new Primary School would have capacity for 434 pupils with 14 primary
classrooms which is the same as Tulloch Primary School.  Consideration has been
given to the layout of the new Primary School and how to minimise noise within the  
open classroom layout.  Similar consideration was given to the building of the new
Riverside Primary School and will be applied to the building of the new Primary School
in Bertha Park. 
9.14 Clarification was sought regarding whether all the house building will go ahead.
Education and Children’s Services must plan ahead based on the housebuilding that
has been proposed and planned. The house building and build out rates will depend on
the sales market position.

Page 14

14
9.15 Clarification was sought regarding whether there is a risk that families living in
Ruthvenfield Primary School catchment will want to go to the new Primary
School when it opens for after school clubs and nursery, and will then move on
to Bertha Park High School.
Perth and Kinross Council undertook a pre-consultation exercise where parents’ views
were gathered, and it was found that there was not a large number of Ruthvenfield
Primary School catchment families who indicated that they wished their children to
attend the new primary school.  The feedback generally was that families who had
children at Ruthvenfield Primary School wanted them to continue to attend
Ruthvenfield Primary School.  Perth and Kinross Council is aware that new schools
can attract families from outwith the school’s catchment area, but the number of
outwith catchment pupils who would be able to attend will depend on how many
classes and teachers there are in the school when the school opens.  This will
determine how many available places there would be for pupils from outwith the
catchment area.  
Parents have a legal right to apply to the school of their choice and the Council will
continue to manage the pupil numbers during this time based on the Council’s
Admission Policy which is the case for all schools.  Pupils living in the catchment area
for Ruthvenfield Primary School and the new primary school are both within the
catchment area for Bertha Park High School for secondary education.
9.16 A view was expressed that the houses currently in the new catchment area for
Ruthvenfield Primary School should be considered to be brought into catchment
early as it was not considered that it would lead to a significant volume of
children that would cause an influx into the school and unlikely that they would
all be eligible for the school at the same time.
The Council is proposing changes to the catchment areas of four primary schools and
the timescale for all these changes is consistent with the opening of the new primary
school.  The Council has developed Interim Admission Arrangements for Ruthvenfield
Primary School to give additional priority during the period until the new school opens
to addresses which are proposed to become part of Ruthvenfield Primary School’s
catchment area in the future.  It is considered that these interim arrangements are
sufficient to ensure the management of admissions for the pupils from these areas
during this period which are consistent with the Council’s Admissions Policy for all
schools.  
It is acknowledged that a few parents may consider that this would guarantee
placements in Ruthvenfield Primary School prior to the catchment area changing.
However, the Council cannot guarantee placements for any pupils to attend any
particular school. The Council’s Admission Policy sets out that whilst the Council tries
to provide enough places for all children in the catchment area to attend the catchment
school, living within a catchment area does not guarantee a child a place at that
school. The Council has set out what it considers is reasonable Interim Admission
arrangements for Ruthvenfield Primary School for addresses which are proposed to
become part of Ruthvenfield Primary School’s catchment area in the future and for
siblings should the catchment area be amended which are in line with the Council’s
Admission Policy.

Page 15

15
9.17 A view was expressed that it was hoped that both Bertha Park High School and
the new primary school can be managed by one management team and not
duplicated, offering a better value for money proposition with less duplicated
roles.
Staffing arrangements for the new primary school will be consistent with Perth &
Kinross Council Staffing Standard for primary schools and other local agreements.
Consultation will be undertaken with staff, Trade Unions and professional associations
where appropriate on an implementation plan for staffing the new primary school. 
9.18 Clarification was sought regarding why the dates for the public consultation
meetings included in letter sent to parents of Ruthvenfield Primary School had
passed.
Letters were sent by Royal Mail directly to all parents/carers of pupils attending
Ruthvenfield Primary School, on 12 May 2022, prior to the consultation period starting
on 16 May 2022.  These were sent to the addresses held on the child's school record.   
These letters advised of the meeting dates of 31 May 2022 and 13 June 2022 and
provided more than two weeks' notice for the first meeting and four weeks' notice of the
2nd meeting.  The public meeting dates were also published on the Council Website
on 16 May 2022.  
9.19 A view was expressed that pupils living in Huntingtowerfield who attend
Ruthvenfield Primary School should not have their catchment area changed to
the new primary school at Bertha Park as pupils couldn’t walk to school as they
do now so.   This would encourage a greater use of cars and would add to
congestion and pollution.  Pupils from Huntingtowerfield should attend
Ruthvenfield Primary School and then Bertha Park for secondary school when
children are old enough to walk.
No pupils currently in attendance at Ruthvenfield Primary School would be required to
move schools to transfer to the new primary school when it opens.  Pupils living in
Huntingtowerfield who currently walk to Ruthvenfield Primary School will be able to
continue to do so until they transfer to secondary school.  If the proposal is agreed,
future pupils from Huntingtowerfield who live more than 2 miles from the new primary
school, or where there is no safe walking route for pupils accompanied by a
responsible adult, would be provided with free home to school transport and would not
require to be transported by parents’ cars.  
10. EDUCATION SCOTLAND REPORT
10.1 In accordance with the Schools (Consultation) (Scotland) Act 2010, a report was
produced by Education Scotland on the educational aspects of the proposal.
10.2 The purpose of the report is to provide an independent and impartial consideration of
Perth and Kinross Council’s proposal to. establish a new primary school on the site of
Bertha Park, Perth and associated matters relating to catchment areas, admission
arrangements and transfer to secondary school arrangements.
10.3 Education Scotland visited Ruthvenfield, Pitcairn, Luncarty and Tulloch Primary
Schools the week commencing 22 August 2022 to speak to relevant consultees.  
10.4 The Education Scotland report is reproduced in full (Appendix 6).

Page 16

16
10.5 The report supports the proposal and is summarised below:
 The council has set out clearly a number of educational benefits in its proposal
paper.  A new school has the potential to provide a high-quality learning
environment.  Stakeholders who spoke with HM Inspectors welcome the Council’s
commitment to designing a school which will allow spaces to be used flexibly.  They
are enthusiastic about the creation of different learning environments which could
be used to encourage children to learn in different ways, such as through play-
based, interdisciplinary and outdoor learning.  Children are positive about the
potential for the new school to offer a greater range of clubs and activities within
their community.  The new school is planned to include a nursery and Intensive
Support Provision for children with complex additional needs and staff recognise
the significant benefits these services will provide to children and families across
the area.  HM Inspectors agree that the proposed school has the potential to inspire
and motivate children in their learning. 
 Perth and Kinross Council recognise the potential adverse impact of a change of
school to a child’s wellbeing.  Parents and children appreciate the Council, as part
of the proposal, allowing children to remain at their existing school should they
wish.  Staff and children recognise that selecting a school could be difficult and that
they and their families may need help to do this.  A few senior leaders also identify
that children changing schools in P7 may need enhanced primary to secondary
transition support.
 The Council intends to establish a User Reference Group to contribute local
information to support the design and development of the new school.  This
intended group would include staff from local schools, parents and members of the
community. Should the proposal go ahead, the Council should consider how best to
recruit for this group whilst the new catchment area is not yet established. 
They should also reflect on how children will be able to contribute their ideas for the
development of the plans for the new school.
 Most of the parents who met with HM Inspectors want further information about the
impact on their child’s current school if a new school is built.  Parents from Pitcairn
Primary School and Ruthvenfield Primary School also seek clarity on the transition
arrangements until the new school opens.  They want to know if these schools will
experience a short term increase to their school roll as additional families move into
the area and if so, how the council plan to support this.  A few parents of
Ruthvenfield Primary School remain anxious about whether younger siblings will be
offered a place at the school.  The Council should continue to listen to these
families and seek to address their concerns.  Parents from Ruthvenfield Primary
School are also worried that the proposals will lead to the school’s catchment area
being reduced.  They are legitimately concerned that a reduction in the school roll
may lead to the school being considered for closure again in the future. They seek
further reassurance from the Council about how it intends to support the school to
progress and thrive moving forward. 
 Perth and Kinross Council has taken important steps to address the genuine
concerns of parents about the school roll at Ruthvenfield Primary School. They
have suggested an amendment to the school’s admission arrangements until the
new school opens.

Page 17

17
This recognises the significant number of placing requests received by the school
and the prioritisation of children moving into the new housing sites.
 HM Inspectors agree that the Council’s proposal to build a new school at the Bertha
Park site has clear educational benefits. A new school would provide a high-quality
learning environment.   The purpose-build design has the potential to offer flexible
learning and social spaces.  Stakeholders recognise the value of the new school to
the local community, as well as the benefits of an additional nursery and Intensive
Support Provision.
 Perth and Kinross Council should seek to support families through the transition to
newly defined catchment areas.  Parents value the option for their child to stay at
their existing school should they wish. Stakeholders recognise this may not be an
easy decision and children and families may need support through this process.
 A few parents reported to HM Inspectors that they did not find the consultation and
supporting documents accessible or easy to understand.
10.6 Perth and Kinross Council’s Response to Education Scotland’s Report
The Council welcomes the report from Education Scotland and accepts its findings.
In response to the findings contained within the Education Scotland report, Perth and
Kinross response is as follows:
10.6.1 The Council should consider how best to recruit for the User Reference Group
whilst the new catchment area is not yet established.  They should also reflect
on how children will be able to contribute their ideas for the development of the
plans for the new school.
The User Reference Group will be established with representation from the existing
schools and communities serving the pupils and their families who live in the proposed
new catchment area.  
In respect of opportunities for children to contribute their ideas for the development of
the plans for the new school, as part of preparing a strategic design brief for the new
school, the Council has undertaken a pupil voice consultation.  In order to learn
lessons about Perth and Kinross Council’s recent school designs, views from pupils at
several new build primary schools were gathered. Focus groups of primary pupils at
each of these schools were asked questions about their building, what they feel works
well and what they feel could be improved in their learning environments so that these
can be understood and considered as a part of developing a strategic direction for the
design of the new primary school at Bertha Park. A pupil voice focus group will be
formed with pupils from the directly affected schools which will form the catchment area
for the new primary school to inform the ongoing design process and to capture the
thoughts and ideas that pupils have for the new primary school. 
10.6.2 Perth and Kinross Council should seek to support families through the transition
to newly defined catchment areas.
If the proposals are approved, the Council will attend the affected schools following the
Committee decision, offering initial meetings with parents to discuss the transition to
the newly defined catchment areas and provide opportunities for individual parents to
discuss any concerns or queries they may have.

Page 18

18
As the opening of the new primary school approaches, the Council will be engaging
with each individual family within the new catchment area to discuss and understand
their views and potential plans for their children to either attend the new primary school
or remain in their existing schools.   
10.6.3 Most of the parents who met with HM Inspectors would value further information
around the transition period and impact of the new school on existing
provisions.  Parents from Ruthvenfield Primary School also remain legitimately
concerned about the long term future of their school.  Moving forward, it is
important that the Council continues to listen to these concerns.
The Council is committed to continuing to engage with, and listen to, the concerns of
parents at Ruthvenfield Primary School.  Following consideration of the proposal by
Committee, officers will facilitate meetings with parents and staff to discuss the
outcome and provide further information around the transition period and future
admissions to the school and how these will be managed.  This work will continue
during the period leading up to the new primary school opening and beyond. 
10.6.4The Council should continue to consult and communicate effectively with all
stakeholders to engage them fully in the future planning and design stages of
the proposal.
The Council will continue to use a broad range of mechanisms for consulting and
communicating with all stakeholders in the future planning and design stages.  The
Council has well established arrangements in place for projects such as these and will
continue to build on the positive engagement opportunities which have been
successful in similar school projects undertaken by the Council.
10.6.5 A few parents reported to HM Inspectors that they did not find the consultation
and supporting documents accessible or easy to understand.  The Council
should seek to address this to ensure all stakeholders can fully engage in the
process.
The Council is disappointed to note that a few parents advised that they did not find the
consultation and supporting documents accessible.  The Council published all
documentation on its website as it is legally required to do.  All parents were sent a
letter by post which advised step by step how to access the documents online.  In
addition, the letter advised that anyone who experienced any difficulty could telephone
or email the Council in order that a paper copy could be sent to them by post, or a copy
emailed directly to them.  The Council was not contacted by any parents advising they
could not access the documents.  It is noted that a few parents also advised that they
did not find the documents easy to understand. This is regrettable and it is
acknowledged that much of the required content of these documents is determined by
the Schools (Consultation) (Scotland) Act 2010.  The format of the documentation has
been in use since 2010 for all statutory consultations relating to relevant school
proposals and the Council will to seek to review and amend future documentation to
simplify this, where possible.  
11. ALLEGED OMISSIONS OR INACCURACIES
11.1 Section (10) (3) of the 2010 Act also places a requirement on the Council to provide
details of any inaccuracy or omission within the Proposal Paper which has either been
identified by the Council or raised by consultees.

Page 19

19
This section of the 2010 Act also requires the Council to provide a statement on the
action taken in respect of the inaccuracy or omission, or, if no action was taken, to
state that fact and why.  
11.2 In the course of the consultation exercise, there were no areas identified by
respondents as being inaccurate or omitted from the Proposal Paper during the
consultation period. 
12. COMPLIANCE WITH SECTION 9(1) OF THE SCHOOLS (CONSULTATION)
(SCOTLAND) ACT 2010
12.1 Section 9(1) of the Schools (Consultation) (Scotland) Act 2010 states that: 
After the Education Authority has received Education Scotland’s report, the Authority is
to review the relevant proposal having regard (in particular) to:
(i) written representations received by the Authority (from any
person) during the consultation period;
(ii) oral representations made to it (by any person) at the public
meetings; and
(iii) Education Scotland’s report.
12.2 Following receipt of the Education Scotland report, six online representations, one
written representations and oral representations made at the two public meetings held
during the consultation period, officers reviewed the proposals.
12.3 The feedback from the consultation was considered by officers where all the questions
and comments raised were considered in detail.  This ensured that the Council met the
requirements to review the proposal under section 9(1) and 13(5) of the 2010 Act.
12.4 Officers of the Education Authority have listened carefully to the points made at the
public meeting and have considered equally carefully the Education Scotland report
and the online representations.  The proposal was reviewed to consider whether any of
the representations led the Council to reconsider other options as being reasonable
alternatives to the proposal.  
12.5 None of the representations led officers to conclude that there were any other
reasonable alternatives to the proposal, nor that the proposal should be reconsidered.
12.6 The educational benefits were reviewed in respect of the Education Scotland report
and representations made. 
12.7 There were no factors included in the Education Scotland report or representations
made requiring any aspect of the educational benefits to be reconsidered.
12.8 Having reviewed the Education Scotland report and feedback from consultees, officers
concluded that the basis of the original proposal continues to be the most appropriate
response to establishing a new primary school, establishing a catchment area for the
new primary school and the associated arrangements for interim admissions and
transfer to secondary school for affected pupils.

Page 20

20
12.9 It is considered that the proposal sets out a clearly defined catchment area to serve the
new primary school, makes appropriate adjustments to the existing school catchment
areas serving Ruthvenfield, Pitcairn, Luncarty and Tulloch Primary Schools.  The
proposal also provides appropriate interim admission arrangements for Ruthvenfield
Primary School until the new primary school opens, and provides clarity on the transfer
arrangements for directly affected pupils to attend secondary school. 
13.   LEGAL ISSUES
13.1 The Council has complied in full with the requirements of the Schools (Consultation)
(Scotland) Act 2010 throughout this statutory consultation.
13.2 The Council is mindful of its duties in respect of equality and the Equality Impact
Assessment did not identify that any parent, child or young person would be treated
less favourably as a result of this proposal.  The new primary school will comply with
the Council’s Accessibility Strategy and, therefore, would positively promote equal
opportunities for any child who has a disability.  
In terms of Socio Economic Impact, the assessment identified that having a new
school located in the community of Bertha Park means that it is more accessible for
those who may be economically disadvantaged.
13.3 Under the terms of the Schools (Scotland) (Consultation) Act 2010, it is a legal
requirement that the Council should not reach any formal decision without waiting until
a period of three weeks starting on the day on which this Consultation Report is
published in electronic and printed form has expired.
13.4 As it is the intention that this Consultation Report should be published, both
electronically and in written form, if required, on 26 September 2022, this meets the
statutory requirement to publish this report for more than three weeks before
consideration of the proposal by Learning & Families Committee on 2 November 2022.
14. PERSONNEL IMPLICATIONS
14.1 Staffing arrangements for the new primary school will be consistent with Perth &
Kinross Council Staffing Standard for primary schools and other local agreements.
Consultation will be undertaken with staff, Trade Unions and professional associations
where appropriate on an implementation plan for staffing the new primary school. 
15.  CONCLUSION
15.1 The Council now has 4 broad options to consider, namely: 
(a)  adopt the proposal; 
(b)  withdraw the proposal;   
(c)  amend the proposal in some way which allows the proposal to proceed; or
(d)  amend the proposal significantly and undertake a further consultation exercise
on a new proposal.

Page 21

21
15.2 Education Scotland has identified that the proposal to build a new school at the Bertha
Park site has clear educational benefits. A new school has the potential to provide a
high-quality learning environment. The purpose-build design has the potential to offer
flexible learning and social spaces. Stakeholders recognise the value of the new
school to the local community, as well as the benefits of an additional nursery and
Intensive Support Provision.
15.3 If the Council adopts the proposal, it is understood that the educational benefits set out
in the Proposal Paper would likely materialise.  
15.4 The key points that have been highlighted during the consultation period are as
follows:
 The report from Education Scotland acknowledges that the proposal has clear
educational benefits for pupils.  This includes the potential to provide a high-quality
learning environment with purpose-build design which has the potential to offer
flexible learning and social spaces. The value of the new school to the local
community is recognised, as well as the benefits of an additional nursery and
Intensive Support Provision.
 The potential adverse impact of a change of school to a child’s wellbeing has been
recognised by the Council, and parents and children appreciate the Council
allowing children to remain at their existing schools should they wish.
 It has been acknowledged that the Council has been consulting and communicating
effectively with stakeholders and should continue to engage them fully in the future
planning and design stage, as well as continuing to support families through the
process of transition to the new school and/or new catchment areas.
 Feedback from stakeholders generally has been that the approach developed in
determining the proposed catchment areas and interim admission arrangements for
Ruthvenfield Primary School has been sensible and appropriate.  
 Stakeholders have considered the interim admission arrangements for Ruthvenfield
Primary School as a pragmatic approach to considering children with siblings at the
school and those who will reside within the proposed new catchment in determining
the priorities for admission to the school.  The addition of a new school at Bertha
Park and the associated catchment review is considered sensible and shows a
good understanding of the various communities being created with the new house
building as well as showing clear connections with the existing communities for their
further secondary education at Bertha Park High School.  
 The Council’s proposals have generally been supported by those who participated
in the consultation, and the majority of those consulted have raised no issues or
opposition to the proposal.

Page 22

22
16. RECOMMENDATIONS
16.1 On the basis of the feedback received and taking account of the educational and social
benefits of the proposal, it is recommended that the Council approves:
 the establishment of a new primary school on a preferred site at Bertha Park, Perth
with effect from August 2026; 
 the established catchment area for the new primary school as proposed; 
 the amendment of the catchment areas of Ruthvenfield Primary School, Pitcairn
Primary School, Luncarty Primary School and Tulloch Primary School as proposed; 
 the transfer arrangements for directly affected primary pupils to attend secondary
school as proposed; and
 the interim admission arrangements for Ruthvenfield Primary School until the new
primary school opens in August 2026 as proposed.
Sheena Devlin 
Executive Director (Education and Children’s Services)
21 September 2022

Page 23

23
Appendix 1
Education & Children’s Services
Improving Lives Together
Ambition I Compassion I Integrity
Statutory Consultation Public Meeting
Minute of meeting held on Tuesday 31 May 2022
at 7:00p.m. in Bertha Park High School
Present:
Councillor John Rebbeck       Convener, Learning & Families Committee
Sheena Devlin       Executive Director (Education & Children’s Services)
Karen Robertson       Service Manager – Business Services
Evelyn Gilruth       Team Leader – Resource Management 
Present:
Gill Innes – Minutes        Perth and Kinross Council
9 members of the public
Welcome and Introductions
Karen Robertson opened the meeting and welcomed the members of public in attendance to
the Statutory Consultation Public Meeting.  Karen Robertson introduced herself and the panel
to the members of the public and thanked them for attending.
Format of meeting
Karen Robertson then explained the format the meeting would follow.
The Proposal
Karen Robertson explained the consultation proposal to the attendees. The Council proposes
to: 
 Establish a new primary school on a preferred site at Bertha Park, Perth; 
 Establish a catchment area for the new primary school; 
 Amend the catchment areas of Ruthvenfield Primary School, Pitcairn Primary School,
Luncarty Primary School and Tulloch Primary School; 
 Establish the transfer arrangements for directly affected primary pupils to attend
secondary school; and 
 Establish interim admission arrangements for Ruthvenfield Primary School until the
new primary school opens in August 2026.

Page 24

24
Presentation
Karen Robertson gave a presentation explaining the proposal in further detail and explained
the background to the proposal and the reasons a new primary school is required. This proposal
relates to the provision of a new, additional primary school in Perth and Kinross.  The
presentation outlined the current arrangements and the proposed catchment area for the new
school.  It was explained that the proposed timeline for the new primary school opening was
August 2026.  The presentation outlined the proposed interim admission arrangements and
anticipated educational benefits.  
Karen Robertson then went on to explain the statutory consultation process including the legal
framework, consideration by Learning & Families Committee, the statutory consultation period
and the different ways in which representations from interested parties could be made as the
first part of the consultation process. Karen Robertson then went on to explain the next stages
of the process which includes the involvement of Education Scotland, the preparation and
publication of the consultation report and the final decision made by the Learning & Families
Committee, currently anticipated to be November 2022. 
Karen Robertson then opened up the meeting to any questions, comments or observations
from the floor. 
Q.  The new Ruthvenfield catchment area does not extend to the Auld Mart and Perth
West, is this because there is the potential for a new school to be built in Perth West? 
A.  Karen Robertson advised that housebuilding is expected to expand in the Almond Valley
area so there may be a requirement for another primary school to be built at some point in the
future within the 30 year plan.  As things stand, if the Council does not take steps now to reduce
the catchment area of Ruthvenfield Primary School and with housebuilding continuing, there is
a finite number of spaces within the school.  Therefore,  catchment children may not get into
the school in the future and will have to be zoned to another school with space.  This could
mean parents may be left in a situation of not knowing where their child will go to school and
those with siblings may not be able to enrol at the same school.  The Council wants to avoid
uncertainty for all parents and avoid the situation of siblings living in catchment not being able
to attend the same school.
Q.  How many pupils can the new school accommodate?
A.  Karen Robertson advised that the new primary school would have capacity for 434 pupils
with 14 primary classrooms.  The new school would not open initially with this number of pupils
or classes.  The Council will be modelling pupil numbers expected on day one.  The Council
closely monitors the Housing Land Audit for pupils from new housebuilding, and depending on
how many pupils stay at their existing primary school and the number who choose to move to
the new school when it opens, there could possibly be 1 or 2 classes on day one, or if all pupils
move, there could  possibly be 5 or 6 classes.  
The school will grow over time and the Council will be working on correlating pupil numbers in
the year leading up to the new school opening. A number of children living in the strategic sites
go to different schools currently, and the Council will be asking all parents in the new school
catchment area of their enrolment intentions to allow class numbers and staffing to be planned
for the new school opening.  Registration for the new school will begin in January 2026 for the
school opening in August 2026.  
Q. What provision would be in place if there are any problems with recruitment for the
new school?  Will the children remain in their existing schools?
A.  Karen Robertson advised that the school registration process will commence in January
2026, this will give an indication of expected pupil numbers.

Page 25

25
The Council will also consider feedback from parents who will have been contacted to share
their enrolment intentions and during this period we will also meet with Headteachers to assess
their predicted pupil numbers.  The Council has a Staffing Standard that will be applied and
before the Council allocates school places the projected pupil numbers will determine what the
required staffing will be as part of the annual staffing exercise.  This is normal practice for
planning the staffing requirements for all schools for the new school session each year and staff
will be in place as required for the opening of the new school.
Q.  If this new school is to open in August 2026, when will building work start?
A.  Karen Robertson and Evelyn Gilruth jointly advised that the Council’s Project Support Team
have a process to follow, and it is anticipated that building work would start in November 2024
and complete in June 2026.  The planning and design of the school will run concurrently with
the statutory consultation. The Council will engage further with parents through the User
Reference Group which will be established regarding design works, and it is expected that it
will take 2 years to complete the design phase over the period October 2022 to October 2024.
Q.  Will the nursery open in 2026?
A.  Karen Robertson advised that the Council plans to open the nursery and the intensive
support provision as part of the school, and all will open together.
Q.  When will projected pupil numbers for Ruthvenfield PS and Pitcairn PS be breached?
A.  Karen Robertson advised that the Council closely monitors pupil numbers during the school
session.  Ruthvenfield Primary School currently operates with 3 classes but has an additional
classroom that could be used to accommodate a further class to accommodate additional
catchment pupils.  The approved capacity for Ruthvenfield Primary School is 91 pupils but this
could be temporarily increased to 100 pupils, if necessary, to accommodate catchment
pupils.  The Council would only revert to this on an exceptional basis where catchment pupils
could not be accommodated otherwise.  Pitcairn Primary School does not have any unused
classrooms and would potentially require temporary accommodation on site if capacity were to
be breached before 2026.  The pupils currently attending Pitcairn Primary School from Bertha
Park would be in the proposed catchment for the new primary school.  The Council is still to
undertake a detailed feasibility study of potential temporary accommodation which may be
required, and which may be at Pitcairn Primary School.
The Council has a duty to manage enrolments into Pitcairn Primary School and Ruthvenfield
Primary School as it does for all schools, to ensure that there is space for catchment children,
wherever possible, and to accommodate any increase in rolls without breaching physical
capacity limits.
Q. Would priority always be given to existing and new catchment children?
A. Karen Robertson responded to confirm that this would be the case as the Council’s proposed
interim admission arrangements are to prioritise pupils living in the existing catchment area and
then pupils living in the proposed new catchment area.
Q.  If not enough children opted to go to the new primary school at Bertha Park, would
temporary accommodation remain at Pitcairn Primary School?
A.  Karen Robertson advised that no pupils would be forced to move school after they had
commenced attending a particular school and the Council would honour these enrolments until
the pupils left the school.  
If this resulted in a temporary increase in capacity and temporary accommodation, then this
would remain in place until pupils had moved through the school and left or where the roll
decreased, no longer requiring temporary accommodation.

Page 26

26
Q.  Is there a risk for a child not getting into Pitcairn Primary School from now until
August 2026?
A.  Karen Robertson advised that the Council would continue to manage enrolments until the
new school is built and has a legal duty to ensure that there are enough school places for all
children in Perth and Kinross.  If it becomes necessary, temporary arrangements may need to
be put into place for catchment children but this would not be a long term arrangement and only
be in place for as long as it needed to be.  The Council’s Admission Policy will continue to be
applied and the proposed new arrangements would be operational from January 2026 for
August 2026 enrolments.
Q.  Can an older sibling move from Pitcairn Primary School to the new primary school at
Bertha Park?
A.  Karen Robertson responded that this would absolutely be able to happen and advised that
the Council recognises that moving forward parents will start to consider this.  The Council also
recognises that everyone’s circumstances are different and that this may depend on the
individual pupil’s class stage and friendship groups at the time of the new school opening, and
it will be for parents to decide what they wish for their child.  When the new primary school
opens, pupils may have been in a school for a number of years and choose to leave the school
they started at to go to the new primary school.
Councillor Rebbeck, Convener, Learning & Families Committee shared with the parents
attending that it was nice to see them and noted that he was keen to get their views as there
would be a lot of nuances over the next 4 years.  Councillor Rebbeck advised the parents of
the importance to feedback into this consultation, confirming that the final decision is made by
Elected Members who would pay attention to what is said during the consultation.
Sheena Devlin, Executive Director (Education & Children’s Services) added that it was not
possible to predetermine the outcome of the consultation until we have gone through each
stage, and that the process is understandably long with a multi-million pound investment.  
Sheena Devlin noted that this was an exciting and good news story and that the Council have
put together a proposal to get the best fit for as many pupils as possible.  
Sheena Devlin encouraged parents to look at the PKC web page relating to the consultation
and to share their views, advising that all information received will be provided to Elected
Members for their consideration to allow them to make a full and informed decision.
Karen Robertson thanked everyone for attending and closed the meeting.

Page 27

27
Appendix 2
Education & Children’s Services
Improving Lives Together
Ambition I Compassion I Integrity
Statutory Consultation Public Meeting
Minute of meeting held on Monday 13 June 2022
at 7:00p.m. in Bertha Park High School
Present:
Councillor John Rebbeck Convener, Learning & Families Committee
Sharon Johnston Head of Education and Learning
Karen Robertson Service Manager – Business Services
Present:
Jodie Watt – Minutes Perth and Kinross Council
2 members of the public
Welcome and Introductions
Karen Robertson opened the meeting and welcomed the members of public in attendance to
the Statutory Consultation Public Meeting.  Karen Robertson introduced herself and the panel
to the members of the public and thanked them for attending.
Format of meeting
Karen Robertson then explained the format the meeting would follow.
The proposal
Karen Robertson explained the consultation proposal to the attendees. The Council proposes
to:
 Establish a new primary school on a preferred site at Bertha Park, Perth; 
 Establish a catchment area for the new primary school; 
 Amend the catchment areas of Ruthvenfield Primary School, Pitcairn Primary School,
Luncarty Primary School and Tulloch Primary School; 
 Establish the transfer arrangements for directly affected primary pupils to attend
secondary school; and 
 Establish interim admission arrangements for Ruthvenfield Primary School until the
new primary school opens in August 2026. 
Presentation
Karen Robertson gave a presentation explaining the proposal in further detail and explained
the background to the proposal and the reasons a new primary school is required. This
proposal relates to the provision of a new, additional primary school in Perth and Kinross.

Page 28

28
The presentation outlined the current arrangements and the proposed catchment area for the
new school.  It was explained that the proposed timeline for the new primary school opening
was August 2026.  The presentation outlined the proposed interim admission arrangements
and anticipated educational benefits.  
Karen Robertson then went on to explain the statutory consultation process including the
legal framework, consideration by Learning & Families Committee, the statutory consultation
period and the different ways in which representations from interested parties could be made
as the first part of the consultation process.  Karen Robertson then explained the next stages
of the process which includes the involvement of Education Scotland, the preparation and
publication of the consultation report and the final decision made by the Learning & Families
Committee, currently anticipated to be November 2022. 
Karen Robertson then opened up the meeting to any questions, comments or observations
from the floor.
Q. If 150 homes are to be built in Ruthvenfield’s catchment area, will there be space at
Ruthvenfield Primary School to accommodate all potential children?
A. Karen Robertson advised that the formula of 0.27 primary pupils per home is used to
project future pupil numbers from housebuilding, but this can vary depending on the type and
size of houses that are being built.  The Council also monitors the build out rates agreed
within the Housing Land Audit which sets out how many houses are to be built each year, as
it will not be the case that all the houses will be built at the same time.  Ruthvenfield Primary
School is currently operating with 3 classes but can increase to 4 classes if required for
catchment pupils to be accommodated.  This could allow a maximum of 100 pupils in
Ruthvenfield Primary School.   Obviously, pupils will move through the school and leave, and
it is important that the Council continues to manage the enrolments coming into Ruthvenfield
Primary School to try to ensure that there will be space to accommodate all potential pupils
living in the catchment area in the future.    
Q. We are slightly unclear of the current catchment area of Ruthvenfield Primary
School.
A. Karen Robertson explained the catchment area of Ruthvenfield Primary School using a
map from the PowerPoint presentation.
Q. Will any areas of the current Tulloch Primary School catchment area become
catchment for the new Primary School?
A. Karen Robertson advised that Double Dykes is currently within Tulloch Primary School’s
catchment area and is proposed to become part of the new Primary School catchment
area.  Karen Robertson explained this using a map from the PowerPoint presentation.
Q. Will the new Primary School be the same size at Tulloch Primary School?
A. Karen Robertson advised that the new Primary School would have capacity for 434 pupils
with 14 primary classrooms.  The new school would not open initially with this number of
pupils or classes.  The Council will be modelling pupil numbers expected on day one. The
Council closely monitors the Housing Land Audit for pupils from new housebuilding, and
depending on how many pupils stay at their existing primary school and the number who
choose to move to the new school when it opens, there could possibly be 1 or 2 classes on
day one, or if all pupils move, there could possibly be 5 or 6 classes.
The school will grow over time and the Council will be working on correlating pupil numbers in
the year leading up to the new school opening.

Page 29

29
Sharon Johnston shared that consideration has been given to the layout of the new Primary
School and how to minimise noise within the   open classroom layout.  Similar consideration
was given to the building of the new Riverside Primary School and will be applied to the
building of the new Primary School in Bertha Park.
Q. Will all the house building go ahead?
A. Councillor Rebbeck, Convener, Learning & Families Committee advised that as an
Education Service we must plan ahead based on the housebuilding that has been proposed
and planned. The house building will depend on the sales market position.
Q. Is there a risk that families living in Ruthvenfield Primary School catchment will
want to go to the new Primary School when it opens for after school clubs and nursery,
and will then move on to Bertha Park High School?
A. Karen Robertson advised that Perth and Kinross Council undertook a pre consultation
exercise where parents’ views were gathered, and it was found that there was not a large
number of Ruthvenfield Primary School catchment families who indicated that they wished
their children to attend the new Primary School.  The feedback generally was that families
who had children at Ruthvenfield Primary School wanted them to continue to attend
Ruthvenfield Primary School.  Perth and Kinross Council is aware that new schools can
attract families from outwith the school’s catchment area, but the number of outwith
catchment pupils who would be able to attend will depend on how many classes and teachers
there are in the school when the school opens.  This will determine how many available
places there would be for pupils from outwith the catchment area.  Parents have a legal right
to apply to the school of their choice and the Council will continue to manage the pupil
numbers during this time based on the Council’s Admission Policy which is the case for all
schools. 
There being no further questions or comments, Karen Robertson thanked everyone for
attending and closed the meeting.

Page 30

30
Appendix 3
Perth & Kinross Council
Education and Children’s Services
New Primary School at Bertha Park
Summary of Consultation Responses

Page 31

31
The statutory consultation on the proposal to establish a new primary school and catchment
area at Bertha Park commenced on Monday 16 May 2022 and closed on Wednesday 29
June 2022.
Details of the proposal document were issued to the list of consultees contained within the
Proposal Paper. 848 letters were issued with a link to the proposal paper and details of
where and how to obtain a paper copy.  The Proposal Paper was also published on the
Council website.  
A specific email address was set up for representations and enquiries.  This was in addition to
the usual methods of submitting representations.  An online response form was set up on the
consultation webpage. 
Online Response Forms
10 online response forms were received.  9 responses agreed with the Council’s proposal and
1 disagreed with the Council’s proposal.  However 4 responses were invalid as they failed to
provide a required name, address or email address to validate the response.
RESPONDENT GROUP NUMBER OF
RESPONSES
AGREE DISAGREE
Parents 4 4 -
Pupils 1 1 -
Staff - - -
Elected Members - - -
Parent Councils - - -
Community Members - - -
Grandparents - - -
Trade Unions - - -
Other 1 1 -
Not disclosed (Invalid) 4 3 1
Total 10 9 1
Validated Total 6 6 -
Public Meetings
As part of the statutory consultation process, 2 public meetings were held on 31 May 2022
and 13 June 2022 at Bertha Park High School.  The same presentation was given at each
meeting.  
Tuesday 31 May 2022 – Bertha Park High School
Attended by 9 members of the public.  
The questions and comments were around:

Page 32

32
 Ruthvenfield Primary School’s proposed catchment area not including Auld Mart and
Perth West and whether there was the potential for a new school to be built in Perth
West in the future.
 The size of the new primary school.
 What provision would be made if there were problems recruiting staff for the new
primary school.
 When building work will start for the new school opening in August 2026.
 If the nursery will also open in August 2026.
 When will Ruthvenfield Primary School and Pitcairn Primary School breach capacity.
 Whether priority will be given to existing and new catchment area pupils to attend
Ruthvenfield Primary School.
 Whether temporary accommodation would remain at Pitcairn Primary School if pupils
did not opt to move to the new primary school.
 Whether there was a risk that pupils will not be able to attend Pitcairn Primary School
before the new primary school opens.
 Whether older siblings could move from Pitcairn Primary School to the new primary
school when it opens.
Monday 13 June 2022 – Bertha Park High School
Attended by 2 members of the public.
The questions and comments were around:
 The planned housebuilding in Ruthvenfield Primary School’s catchment area and
whether the school would have capacity for all potential pupils.
 The current catchment area of Ruthvenfield Primary School.
 Which areas of Tulloch Primary School’s current catchment area would become
catchment for the new primary school.
 Whether the new primary school will be the same size as Tulloch Primary School.
 Whether all planned housebuilding will go ahead.
 Whether families living in Ruthvenfield Primary School’s catchment area may choose
to attend the new primary school to access nursery and out of school provision.
Written Representations
During the consultation period between 16 May 2022 and 29 June 2022, representations
were invited from statutory consultees and interested parties.  1 written response was
received in total:
RESPONDENT GROUP NUMBER OF
RESPONSES
AGREE DISAGREE
Grandparents 1 1
The written representation stated they did not agree with the proposals.  
The comments were around:
 Why would the catchment area serving Huntingtowerfield be changed to the new
school at Bertha Park.

Page 33

33
 Pupils could not walk to school as they do now so if green active travel is to be
considered then this does not help.  More use of cars would add to congestion and
pollution. 
 Huntingtowerfield should remain in the catchment area for Ruthvenfield Primary School
and then Bertha Park for secondary school when children are old enough to walk.
 Ruthvenfield Primary is a lovely rural school offering a good education to local children
and is part of our community.  Bertha Park would not give this.
Comments Received on Response Forms
The comments were around:
 The proposals developed is a sensible approach in adapting the catchment areas. 
 Families with children already attending Ruthvenfield Primary School wish to ensure
that younger siblings will be able to attend the same school as their sibling. 
 It is important for families living in the village of Ruthvenfield who are currently within
the catchment area for Tulloch Primary School, for their children to attend the same
school in the community in which they live. 
 The catchment review takes the sensible approach of building a catchment for
Ruthvenfield Primary School that includes the community of which it is the heart rather
than splitting it down the middle. 
 The interim admission arrangements take the pragmatic approach of considering
children with siblings at the school and who will reside within the new catchment in the
priorities for placement are appreciated. 
 The addition of a new school at Bertha Park and the associated catchment review is
very sensible and shows a good understanding of the various communities being
created with the new house building as well as showing clear connections with the
existing communities for their further secondary education at Bertha Park High School. 
 The proposals for a new primary school which will support the continued development
of the Bertha Park community are welcomed and the catchment area changes seem to
be reasonable and support more active travel to and from school for pupils. 
 It is hoped that both Bertha Park High School and the new primary school can be
managed by one management team and not duplicated, therefore, offering a better
value for money proposition with less duplicated roles. 
 The houses currently in the new catchment for Ruthvenfield Primary School (less those
that are planned to be developed) should be considered to be brought into catchment
early.  Ruthvenmill View and The Orchard would not have a significant volume of
children that would cause an influx into the school.  
It would also be unlikely that they would all be eligible for the school at the same time if
they were brought into catchment early. 
 Improved cycle routes should be included around the school to aid safer journeys for
children to both schools. 
Pupil Consultation
Consultation with pupils in stages P1 - P3 was undertaken in the 4 directly affected primary
schools.  Pupils in P4 - P7 are not affected by the new primary school as these pupils will be
at secondary school in August 2026 when the new primary school opens.  The consultation
took place on 21 and 22 June 2022.

Page 34

34
Ruthvenfield Primary School
19 pupils from P1 to P3 were involved in the session.  Comments were around where the
individual children lived, whether they would have to move school and whether Ruthvenfield
Primary School would be closed. 
14 agreed with the proposal and 5 were against the proposal.
Pitcairn Primary School 
41 pupils from P1 to P3 were involved in the sessions.  Questions were around moving
school, not wanting too many children in Pitcairn Primary School, and why the Council is
moving catchment boundaries. 
37 agreed with the proposal and 4 were against the proposal.
Luncarty Primary School 
This was undertaken as a focus group session as the proposed changes have a lesser impact
for Luncarty Primary School, with representatives from P1, P2 and P3.  There were 15 pupils
in this session.  They discussed catchment areas, the new house building, and what any
impact would be on them and their school.  
12 agreed with the proposal and 3 were against the proposal. 
Tulloch Primary School
This was undertaken as a focus group session as the proposed changes have a lesser impact
for Tulloch Primary School, with representatives from P1, P2 and P3.  There were 13 pupils in
this session. They discussed catchment areas, the new house building, and what any impact
would be on them and their school. 
11 agreed with the proposal and 2 were against the proposal.

Page 35

35
Appendix 4
Online and Written Responses
I hope that both Bertha Park High School and the new primary school can be managed by ONE
management team and not duplicated therefore offering a better value for money proposition with
less duplicated roles.
I welcome the proposals for a new primary school which will support the continued development of
the Bertha Park community and the catchment area changes seem to be reasonable and support
more active travel to and from school for pupils.
We live in the village of Ruthvenfield a 2 min (300m) walk from the school and yet as a result of the
existing catchment are currently expected to send our children to Tulloch a 26 min (2km) walk away. 
Our two eldest children have been fortunate enough to have successful applications to attend the
school, our youngest will be due to register in 2025.   It is really important for us for our children to
attend the same school in the community in which we live.  This new catchment review takes the
sensible approach of building a catchment for Ruthvenfield school that includes the community of
which it is the heart rather than splitting it down the middle.  We also appreciate the interim
admission arrangements which take the pragmatic approach of considering children with siblings at
the school and who will reside within the new catchment in the priorities for placement.  The addition
of a new school at Bertha Park and the associated catchment review is very sensible and shows a
good understanding of the various communities being created with the new house building as well as
showing clear connections with the existing communities for their further secondary education at
Berth Park High school.  We are in firm agreement that the proposed approaches are the right ones
for our children and to build strong foundations for the communities which they support.  Thank You.
I believe that what has been developed is a sensible approach in adapting the catchment areas. My
primary concern was around the catchment areas for Ruthvenfield Primary. Specifically the estate
directly across from the school at Ruthvenmill View as I am purchasing a property in this area with a
view that my youngest will be able to attend the school , the same school as his sister.
Improved cycle routes around the school to aid safer journeys for children to both schools
I believe for the houses currently in the new catchment (less those that are in plan to be developed)
should be considered to be brought into catchment early.  I dont believe that the area of Ruthvenmill
View and the Orchard would have significant volume of Children that would cause an influx into the
school.  It would also be unlikely that they would all be eligible for the school at the same time if they
were brought into catchment.  In addition it was advised that the school currently works to a 2m per
child rule and this could be flexed to 1.7 even in the unlikely event that this was going to cause and
issue.
Firstly I would like to ask why are dates for public consultation included in letter sent to parents of
Ruthvenfield primary school  are past? Not very helpful!  I live in Huntingtowerfield as does my
granddaughter and she attends Ruthvenfield school along with many of her friends who also live in
Huntingtowerfield. Why would catchment area be changed to proposed new school at Bertha Park?
She couldn’t walk to school as she does now so if green active travel is to be considered then this does
not help. More use of cars would add to congestion and pollution.  I have no problem with new
catchment areas being made but Huntingtowerfield should be included in Ruthvenfields and then
Bertha Park for secondary school when children are old enough to walk!

Page 36

36
Ruthvenfield primary is a lovely rural school  offering a good education to local children and is part of
our community. Bertha Park would not give this.  Please consider these arguments when making any
decisions.

Page 37

37
Appendix 5
New School at Bertha Park
Catchment Review
Pupil Consultations – 21 and 22 June 2022
Anne Lemon, Quality Improvement Officer and Lorna Hamilton, Project Manager visited the four schools
impacted by the formation of a catchment area for the new primary school, and the revision of the existing
catchment areas.
Ruthvenfield Primary School
19 pupils from P1 to P3 were involved in the consultation exercise.   The session focussed on the meaning of
catchment areas, and checking the pupils’ understanding of what this meant in terms of their school and other
schools involved. 
Discussion took place around what a change to the catchment area, as outlined in the proposal, would mean
for these pupils, and any future pupils.
The pupils had opportunity to look at maps, and to ask questions and make comments.
Comments were around where the individual children lived, and whether they would have to move.
There was a question asking whether Ruthvenfield would be closed down.
Discussion took place around different sizes of schools, different sizes of catchment areas, and the new houses
that were being built. 
The pupils enjoyed the maps and showed good understanding of where the areas were and where the schools
were.
Understanding of all the points was checked and then the pupils were asked to say what they thought of the
proposal. 
Voting was secret, to allow the pupils to make their own decisions.
Five were against the proposal 
14 were for the proposal
Pitcairn Primary School
Due to the numbers involved, the sessions were split between classes, to encompass all P1, P2 and P3 pupils.
41 children were involved in the sessions.
The format was similar to that at Ruthvenfield. 
The pupils understood what a catchment area was, and how it affected them at the school. 
Questions were around moving school,  not wanting too many children in Pitcairn, and why we were moving
boundaries.

Page 38

38
The pupils enjoyed the maps and showed good understanding of where the areas were and where the schools
were. 
Understanding of all the points was checked and then the pupils were asked to say what they thought of the
proposal. 
Four were against the proposal
37 were for the proposal
Luncarty Primary School
As the changes for Luncarty Primary would have a lesser impact than those of Ruthvenfield and Pitcairn, this
was conducted as a focus group session, with representatives from P1, P2 and P3. 
There were 15 pupils in this session, and the format followed that used at the other schools.   They discussed
catchment areas, the new house building, and what any impact would be on them and their school.
Maps were left with the school, for any future questions.
The pupils showed a good understanding of the proposal, and had a secret vote on whether they thought the
proposal was a good idea or not.
Three were against the proposal 
12 were for the proposal
Tulloch Primary School
This followed the same format as Luncarty. 
There were 13 pupils in the focus group, and the questions and comments were similar to the other schools.
Two were against the proposal 
11 were for the proposal

Page 39

39
Appendix 6

Page 40

Schools (Consultation) (Scotland) Act 2010 
Report by HM Inspectors of Education addressing educational
aspects of the proposal by Perth and Kinross Council to: 
 establish a new primary school on the site of Bertha Park, Perth;
 establish a catchment area for the new school and amend the
catchment areas of Luncarty Primary School, Pitcairn Primary
School, Ruthvenfield Primary School and Tulloch Primary School;
 establish the transfer arrangements for affected primary pupils to
attend secondary school; and
 establish interim admission arrangements for Ruthvenfield
Primary School until the new primary opens in August 2026. 
August 2022

Page 41

1   | Schools (Consultation) (Scotland) Act 2010 
Perth and Kinross Council © Crown Copyright
1. Introduction 
1.1 This report from Education Scotland has been prepared by His Majesty’s Inspectors of
Education (HM Inspectors) in accordance with the terms of the Schools (Consultation) (Scotland)
Act 2010 (“the 2010 Act”). The purpose of the report is to provide an independent and impartial
consideration of Perth and Kinross Council’s proposal to establish a new primary school on the
site of Bertha Park, Perth. Section 2 of the report sets out brief details of the consultation process.
Section 3 of the report sets out HM Inspectors’ consideration of the educational aspects of the
proposal, including significant views expressed by consultees. Section 4 summarises
HM Inspectors’ overall view of the proposal. Upon receipt of this report, the 2010 Act requires the
council to consider it and then prepare its final consultation report. The council’s final consultation
report should include this report and must contain an explanation of how, in finalising the proposal,
it has reviewed the initial proposal, including a summary of points raised during the consultation
process and the council’s response to them. The council has to publish its final consultation report
three weeks before it takes its final decision. 
1.2 HM Inspectors considered:
 the likely effects of the proposal for children of the proposed school’s catchment area; any
other users; children likely to become pupils when the school opens; and other children and
young people in the council area;
 any other likely effects of the proposal;
 how the council intends to minimise or avoid any adverse effects that may arise from the
proposal; and
 the educational benefits the council believes will result from implementation of the proposal,
and the council’s reasons for coming to these beliefs. 
1.3 In preparing this report, HM Inspectors undertook the following activities:
 consideration of the records of the public meetings held on 31 May 2022 and 13 June 2022
in connection with the council’s proposals;
 consideration of all relevant documentation provided by the council in relation to the
proposal, specifically the educational benefits statement and related consultation
documents, written and oral submissions from parents and others; and
 visits to the site of Luncarty Primary School, Pitcairn Primary School, Ruthvenfield Primary
School and Tulloch Primary School, including discussion with relevant consultees. 
2. Consultation process 
2.1 Perth and Kinross Council undertook the consultation on its proposals with reference to the
Schools (Consultation) (Scotland) Act 2010. 
2.2 The statutory consultation ran from 16 May 2022 to 29 June 2022. Copies of the
consultation proposal were made available to statutory consultees. The council distributed
848 letters to consultees, including parents of the impacted schools, with a link to the proposal
paper and details of how to obtain a paper copy. The proposal paper was also published on the
council website. 
2.3 Public meetings were held at Bertha Park High School on 31 May 2022 and 13 June 2022.
Eleven stakeholders took part in these public meetings. They sought further information about the
changes to the catchment areas, the size of the new primary school, and the transition

Page 42

2   | Schools (Consultation) (Scotland) Act 2010 
Perth and Kinross Council © Crown Copyright
arrangements until the new school would be built. In order to seek further the views of
stakeholders, the council arranged consultation sessions with children from Luncarty Primary
School, Pitcairn Primary School, Ruthvenfield Primary School and Tulloch Primary School. Most
children who participated in the consultation sessions agreed with the proposals. The council
received ten responses to an online questionnaire relating to the public consultation, in addition to
one email response from a stakeholder. Eighty two percent of these online responses were in
favour of the proposal and 18% were against. 
3. Educational aspects of proposal 
3.1 Perth and Kinross Council are seeking to address a substantial increase in housebuilding in
the Perth West region of the council area. The council estimate housebuilding will result in an
additional 678 primary aged children who will need to be accommodated in schools near to where
they live. The existing catchment schools will not be able to accommodate these projected pupil
numbers. Perth and Kinross Council propose to create a new primary school at the Bertha Park
site and adapt existing catchment areas. This will ensure all children can be educated in their local
community. 
3.2 The council has set out clearly a number of important educational benefits in its proposal
paper. A new school has the potential to provide a high-quality learning environment. Stakeholders
who spoke with HM Inspectors welcome the council’s commitment to designing a school which will
allow spaces to be used flexibly. They are enthusiastic about the creation of different learning
environments which could be used to encourage children to learn in different ways, such as
through play-based, interdisciplinary and outdoor learning. Children are positive about the
potential for the new school to offer a greater range of clubs and activities within their community.
The new school is planned to include a nursery and Intensive Support Provision for children with
complex additional needs. Staff recognise the significant benefits these services will provide to
children and families across the area. 
3.3 Perth and Kinross Council recognise the potential adverse impact of a change of school to
a child’s wellbeing. Parents and children appreciate the council, as part of the proposal, allowing
children to remain at their existing school should they wish. Staff and children recognise that
selecting a school could be difficult and that they and their families may need help to do this. A few
senior leaders also identify that children changing schools in P7 may need enhanced primary to
secondary transition support. 
3.4 The council intend to establish a User Reference Group to contribute local information to
support the design and development of the new school. This intended group would include staff
from local schools, parents and members of the community. Should the proposal go ahead, the
council should consider how best to recruit for this group whilst the new catchment area is not yet
established. They should also reflect on how children will be able to contribute their ideas for the
development of the plans for the new school. 
3.5 Most of the parents who met with HM Inspectors want further information about the impact
on their child’s current school if a new school is built. Parents from Pitcairn Primary School and
Ruthvenfield Primary School also seek clarity on the transition arrangements until the new school
opens. They want to know if these schools will experience a short term increase to their school roll
as additional families move into the area and if so, how the council plan to support this. Perth and
Kinross Council have taken important steps to address the genuine concerns of parents about the
school roll at Ruthvenfield Primary School. They have suggested an amendment to the school’s
admission arrangements until the new school opens. This recognises the significant number of
placing requests received by the school and the prioritisation of children moving into the new
housing sites. A few parents of Ruthvenfield Primary School remain anxious about whether

Page 43

3   | Schools (Consultation) (Scotland) Act 2010 
Perth and Kinross Council © Crown Copyright
younger siblings will be offered a place at the school. The council should continue to listen to
these families and seek to address their concerns. Parents from Ruthvenfield Primary School are
also worried that the proposals will lead to the school’s catchment area being reduced. They are
legitimately concerned that a reduction in the school roll may lead to the school being considered
for closure again in the future. They seek further reassurance from the council about how it intends
to support the school to progress and thrive moving forward. 
3.6 A few parents reported to HM Inspectors that they did not find the consultation and
supporting documents accessible or easy to understand. The council should seek to address this
to ensure all stakeholders can fully engage in the process. 
4. Summary 
HM Inspectors agree that the council’s proposal to build a new school at the Bertha Park site has
clear educational benefits. A new school has the potential to provide a high-quality learning
environment. The purpose-build design has the potential to offer flexible learning and social
spaces. Stakeholders recognise the value of the new school to the local community, as well as the
benefits of an additional nursery and Intensive Support Provision. Should the proposal be
successful, Perth and Kinross Council should seek to support families through the transition to
newly-defined catchment areas. Parents value the option for their child to stay at their existing
school should they wish. Stakeholders recognise this may not be an easy decision and children
and families may need support through this process. The council should consider how to develop
an appropriate User Reference Group and ensure the views of children are considered by this
group. Most of the parents who met with HM Inspectors would value further information around the
transition period and impact of the new school on existing provisions. Parents from Ruthvenfield
Primary School also remain legitimately concerned about the long term future of their school.
Moving forward, it is important that the council continues to listen to these concerns. The council
should continue to consult and communicate effectively with all stakeholders to engage them fully
in the future planning and design stages of the proposal. 