Page 1

Perth and Kinross Council 
Learning and Families Committee 
29 January 2025 
Future of The City of Perth Early Childhood Centre 
Report by Strategic Lead – Education and Learning
(Report No. 25/18) 
1. Purpose
1.1 To gain approval to initiate a formal statutory consultation process to form
the basis of moving towards formal closure of the original site of City of
Perth Early Childhood Centre (CoPECC).
2. Recommendation 
2.1 It is recommended that the Committee: 
• Considers the current Early Learning and Childcare (ELC) context and
provision available to families within the North Perth ELC Community; 
• Reviews the information contained in the report, and within the Options
Appraisal (Appendix 1), as to the reasons behind the seeking of approval
for consultation to formally close the original site of CoPECC; 
• Agrees to the preferred option within the Options Appraisal to initiate the
statutory consultation process to form the basis of moving towards formal
closure of CoPECC and the continuation, on a permanent basis, of the
service currently being provided within Goodlyburn Primary School; and 
• Requests the Strategic Lead – Education and Learning brings back a
future report to this Committee to decide upon the future of CoPECC once
the statutory consultation has been completed. 
3. Structure of Report 
3.1 This report is structured over the following sections: 
• Section 4:  Background
• Section 5:  Proposals
• Appendices 
4. Background 
4.1 The original standalone CoPECC in the ELC community of North Perth at
McCallum Court was opened in 2002.  It was registered with the Care
Inspectorate to provide care to a maximum of 100 children, aged between two
years old and those not yet attending primary school.

Page 2

As well as ELC, the service provided family support and learning opportunities
and was included within Perth and Kinross Council’s (PKC) planning for
delivering the 1140 hours expansion of ELC to all eligible children.  It became
one of five Early Childhood Centres in Perth and Kinross offering year-round
flexible childcare options to families. 
4.2 The building was affected by floods in 2002 and 2010 for which insurance
claims were made.  In August 2020, due to extensive rainfall during
thunderstorms, many areas across Perth and Kinross, including Perth city,
were flooded, damaging over 225 buildings.  CoPECC was one of these
buildings and the centre was closed to families as a result and another
insurance claim was made.  Due to the extent of the flood damage to the
building, the centre was temporarily decanted to the Perth Grammar School
Community Wing where families were able to continue to access their
children’s ELC places. 
4.3 The site of the original CoPECC at McCallum Court flooded severely several
times at substantial cost to insurers and PKC.  Following the last flood in
August 2020, the site was subsequently deemed as uninsurable, and as such,
PKC is not able to develop this site with any permanent structure.  In October
2021, due to significant vandalism at the building, it was agreed that the
building would be demolished. 
4.4 By April 2022, an interim arrangement was made by combining the current
nursery at Goodlyburn Primary School with CoPECC to become Goodlyburn
and CoPECC which is located within Goodlyburn Primary School and
managed by the Centre Leader.  This service continues to deliver ELC to 74
children at any one time, including two year olds, providing continuity of
service for families in the community of North Perth and enabling all eligible
children to access high quality ELC. 
4.5 From the flooding in August 2020, all eligible children in the ELC Community
of North Perth have been able to access their full 1140 hour ELC entitlement. 
Since the expansion took place in 2020, within North Perth, two further PKC
Early Childhood Centres, five PKC nursery settings, four funded provider
nursery settings and five childminders within the community have been
established. 
4.6 The CoPECC merger with Goodlyburn Primary School nursery has also
supported the delivery of continued high-quality ELC provision within the
North Perth community.  In February 2024, the setting underwent inspection
by the Care Inspectorate and achieved gradings of ‘Very Good’ under the
Quality Indicators 1.1, 1.3, 3.1 and 4.3, and a ‘Good’ grading under Quality
Indicator 2.2.  The full Care Inspectorate inspection report for the Goodlyburn
and City of Perth Early Childhood Centre is available on their website. 
4.7 CoPECC is successfully delivering ELC from its current site at Goodlyburn
Primary School, and all families residing in the North Perth ELC Community
can access their funded ELC place within the current capacity. 
4.8  An Options Appraisal (Appendix 1) has determined that a standalone centre
on the previous site at McCallum Court is no longer required.

Page 3

5. Proposal 
5.1 It is proposed to initiate the necessary statutory consultation process to
formalise the continuation of ELC delivery at the Goodlyburn Primary School
location and close the CoPECC site at McCallum Court. 
5.1.1 The continuation of the service within Goodlyburn Primary School and other
ELC settings in the North Perth ELC Community provide all families access to
funded ELC places and associated support and services.   
5.2 The Corporate Asset Management Framework (Report No. 24/18 refers) sets
out the Council’s approach to asset management and investment, and
introduced the concept of the Asset Challenge as a key element of its
methodology.  This requires any decision on the use, maintenance and
investment in any asset to be evidence based and in alignment with the
Council’s corporate priorities and service delivery requirements, while
recognising community need, climate change considerations and the
overarching question of affordability. 
5.3 Councils, as Education Authorities, have a statutory duty in terms of the
Education (Scotland) Act 1980 to make adequate and efficient provision of
school education across their entire area for the current school population and
future patterns of demand.  Councils also have a statutory responsibility in
terms of the Local Government in Scotland Act 2003 to achieve best value.   
5.4 It is important, in light of the significant investment and cost associated with
the school estate, that it is managed in an efficient and effective manner, and
that the priorities which are addressed meet the wider strategic objectives of
the Council and the needs of our communities. 
5.5 The Schools (Consultation) (Scotland) Act 2010 compels local authorities to
apply robust consultation procedures to all proposals for school closures
(including nurseries).  PKC is committed to providing stakeholders with
reassurance that the consultation and decision-making process and
procedures are fairly, fully and rigorously carried out. 
5.6 It is proposed that a statutory consultation exercise takes place on a proposal
to close the original site of CoPECC by May 2025, with agreement to
formalise permanent delivery of the ELC from the site at Goodlyburn Primary
School from January 2026. 
Author
Name Designation Contact Details
Bernadette Martin-Scott  Service Manager,
Early Years and
Child Care 
FBSCommittee@pkc.gov.uk  
01738 475000
Annie Carr Quality Improvement
Officer, Early Years
and Childcare

Page 4

Approved
Name Designation Date
David Macluskey  Strategic Lead – Education
and Learning
20 January 2025

Page 5

Annex 
1. Implications, Assessments, Consultation and Communication  
Strategic Implications Yes/None
Community Plan/Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  None
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment None
Strategic Environmental Assessment None
Sustainability (community, economic, environmental) None
Legal and Governance  None
Risk None
Consultation 
Internal  None
External  None
Communication 
Communications Plan  Yes 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This section sets out how the proposals relate to the delivery of the Perth and
Kinross Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to Objective No. (i and ii).   
Corporate Plan 
1.2 This section sets out how the proposals relate to the achievement of the
Council’s Corporate Plan Objectives: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to Objective No. (i and ii).

Page 6

1.3 The report also links to the Education & Children’s Services Vision, Values
and Priorities in respect of the following key Priority area: 
• Best Start 
2. Resource Implications 
Financial 
2.1 There are no financial implications applicable at this stage. 
Workforce 
2.2 There are no workforce implications applicable at this stage. 
Asset Management (land, property, IT) 
2.3 There are no asset management implications in this report.  The site is not
appropriate for a construction development by PKC. 
3. Assessments 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
*The Equality Impact Assessment (EqIA) undertaken in relation to this report
can be viewed by clicking here.   
3.1.1 The proposals have been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as relevant and actions taken to reduce or remove the
following negative impacts: 
• Reduction in the offer of funded ELC places in North Perth.
• Loss of ELC in immediate area surrounding McCallum Court. 
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.2.1 The proposals have been considered under the Act; however, no further
action is required as it does not qualify as a PPS as defined by the Act and is
therefore exempt.

Page 7

Sustainability 
3.3 Under the provisions of the Local Government in Scotland Act 2003, the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.  Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• In the way best calculated to delivery of the Act’s emissions reduction
targets.
• In the way best calculated to deliver any statutory adaption programmes.
• In a way that it considers most sustainable. 
3.3.1 This is not relevant for the purposes of this report. 
Legal and Governance 
3.4 Legal and Governance Services have been consulted on proposals within this
report. 
3.5 Not applicable. 
Risk 
3.6 No significant risks have been identified. 
4. Consultation 
Internal 
4.1 The report has been written in consultation with PKC colleagues in the Early
Years team, Education and Learning Senior Management Team, Human
Resources, Finance and Business Support, and Property. 
External 
4.2 External Consultation has not taken place at this stage. 
5. Communication 
5.1 If approved, a formal consultation process will take place. 
2. Background Papers 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (and not containing confidential or exempt information)
were relied on to a material extent in preparing the above report. 
3. Appendices 
3.1 Appendix 1 – Options Appraisal: Future of the City of Perth Early Childhood
Centre (CoPECC)