Appendix 1
Arup Methodology
The following methodology was agreed between Arup, Tactran, and PKC to develop a
Kinross-Shire Active Travel Masterplan. This approach prioritises stakeholder
engagement, alignment with the regional work, and integration into the Regional
Delivery Plan, 
1. Inception
An initial meeting between PKC Officers and Arup to agree on project arrangements
and reporting.
2. Site visit/early engagement 
Arup to set up and facilitate a site visit and meet with key stakeholders to agree on
desired routes and local priorities.
3. Desktop study 
Arup to review information using Tactran’s regional baseline. This will include a review
of initiatives and any previous engagement work within the area.
4a. Summary note 
Preparation of a short summary note to feed into the wider Regional Active Travel
Delivery Plan.
4b. Development of Masterplan 
Mapping of potential interventions and prioritisation using Tactran and Arup’s Multi-
Criteria Approach (MCA). This process will also consider quick wins. 
5. Follow up engagement 
A follow-up engagement session with the key stakeholders to review the work to date.
6. Masterplan updates 
Final updates are to be made following engagement, and a draft Masterplan is to be
submitted to the agreed forum.