Scottish Ministers, special advisers and the Permanent Secretary are
covered by the terms of the Lobbying (Scotland) Act 2016.  See
www.lobbying.scot
St Andrew’s House, Regent Road, Edinburgh  EH1 3DG
www.gov.scot


Ministear airson Ionmhas Poblach, Dealbhachadh
agus Beartas Còimhearsnachd
Minister for Public Finance, Planning and Community
Wealth
Tom Arthur MSP
T: 0300 244 4000
E: scottish.ministers@gov.scot

Pippa Milne
Chief Executive
Argyll and Bute Council
22 December 2022
Dear Pippa Milne
I am pleased to enclose feedback on your authority’s eleventh Planning Performance
Framework (PPF) Report, for the period April 2021 to March 2022. 
The reporting period which these reports cover has continued to present challenges for
people working within planning, in the development sector and across Scotland’s
communities. 
Ensuring the system is appropriately resourced is key to improving the performance of
planning,  which is why in April I implemented the biggest change to planning fees in 8 years,
with fees for most types of development increasing by between 25% and 50%. At the time I
said I would expect to see this additional  money invested in delivering improvements in
Planning Services. It is too early to know whether that has occurred, however, I have heard
positive feedback from some authorities who have managed to recruit or retain staff as a
result of the additional income. I also committed to working with Heads of Planning and
COSLA to identify how we could move planning fees closer to covering the full cost of their
determination. That work is ongoing and I expect to receive some
conclusions/recommendations early in the new year.
I am also encouraged to see the fees for applications made under the Electricity Act also
increasing on 13th December and the voluntary contribution of 50% of the fee, for certain
types of application, being passed to planning authorities being maintained. 
However, I recognise that resourcing is about more than just money and having a pipeline of
knowledgeable and skilled planners is essential to delivering on our ambitions set out in
NPF4. This is why I supported the RTPI and Heads of Planning Scotland’s Future Planners
Project which looked at proposals to help increase the numbers of people entering the
planning profession. We recognise the importance of delivering on this vision and the
resourcing and skills challenges for planning authorities, which we are taking steps to
address.
Appendix A

Page 2

Scottish Ministers, special advisers and the Permanent Secretary are
covered by the terms of the Lobbying (Scotland) Act 2016.  See
www.lobbying.scot 
St Andrew’s House, Regent Road, Edinburgh  EH1 3DG
www.gov.scot

 
Work is also progressing on 
• the introduction of mandatory training for elected members in the planning system; 
• the implementation of statutory annual reports by planning authorities; and 
• the appointment of a Planning Improvement Coordinator for Scotland. 
Turning to the 2021-22 PPF reporting year, although, as expected, there have been some
minor changes overall in the markings awarded, the figures indicate that performance has
remained relatively stable. This is a testament to the hard work and flexibility of authorities
during challenging times and I believe that overall, good progress continues to be made by
Scotland’s planning authorities. 
If you would like to discuss any of the markings awarded below, please email
chief.planner@gov.scot and a member of the team will be happy to discuss these with you. 
TOM ARTHUR 
CC: Fergus Murray, Head of Economic Development and Strategic Transportation

Page 3

Scottish Ministers, special advisers and the Permanent Secretary are
covered by the terms of the Lobbying (Scotland) Act 2016.  See
www.lobbying.scot 
St Andrew’s House, Regent Road, Edinburgh  EH1 3DG
www.gov.scot

 
PERFORMANCE MARKERS REPORT 2021-22 
Name of planning authority: Argyll & Bute Council 
The High Level Group on Performance agreed a set of performance markers. We have assessed your report against
those markers to give an indication of priority areas for improvement action. The high level group will monitor and
evaluate how the key markers have been reported and the value which they have added. 
The Red, Amber, Green ratings are based on the evidence provided within the PPF reports. Where no information or
insufficient evidence has been provided, a ‘red’ marking has been allocated. 
No. Performance Marker RAG
rating
Comments
1 Decision-making: continuous
reduction of average timescales for
all development categories [Q1 -
Q4] 
Red Major Applications
Your timescales of 40.8 weeks are slower than the previous
year but faster than the Scottish average of 44.6 weeks. 
RAG = Amber 
Local (Non-Householder) Applications
Your timescales of 13.6 weeks are slower than the previous
year and slower than the Scottish average of 13.5 weeks. 
RAG = Red 
Householder Applications
Your timescales of 10.3 weeks are slower than the previous
year and the Scottish average of 8.7 weeks.
RAG = Red 
Overall RAG = Red
2 Processing agreements:
• offer to all prospective
applicants for major
development planning
applications; and
• availability publicised on
website
Green You encourage processing agreements to applicants for all
major and locally significant developments through pre-
application discussions, user forums and online.
RAG = Green 
Processing agreement information is available through your
website.
RAG = Green 
Overall RAG = Green
3 Early collaboration with applicants
and consultees
• availability and promotion
of pre-application
discussions for all
prospective applications;
and
• clear and proportionate
requests for supporting
information
Green You provide a pre-application advice service which is
promoted through the website, user forums and by staff
engaging with prospective applicants. 
RAG = Green 
You have a proportionate and clear process for requesting
supporting information including engaging with consultees
and other council services to identify issues/constraints prior
to the application being submitted. During the 2021/22
reporting period you updated and published guidance on the
submission and processing of applications under S64 of the
planning act.
RAG = Green 
Overall RAG = Green

Page 4

Scottish Ministers, special advisers and the Permanent Secretary are
covered by the terms of the Lobbying (Scotland) Act 2016.  See
www.lobbying.scot 
St Andrew’s House, Regent Road, Edinburgh  EH1 3DG
www.gov.scot

 
4 Legal agreements: conclude (or
reconsider) applications after
resolving to grant permission
reducing number of live
applications more than 6 months
after resolution to grant (from last
reporting period)
Amber Your average timescales of 33.6 weeks for applications with
legal agreements is slower than last year and slightly slower
than the Scottish average of 33.2 weeks. 
You state that applications which are subject to a legal
agreement are regularly reviewed to ensure progress and
completion within 6 months.
5 Enforcement charter updated / re-
published within last 2 years
Green Your enforcement charter was reviewed and updated in
March 2022. 
6 Continuous improvement:
• progress ambitious and
relevant service
improvement commitments
identified through PPF
report
Amber Out of 12 service improvement commitments, 1 was
delivered, 6 are progressing, 4 are on hold and 1 has been
discontinued. You have identified a good range of further
commitments for the coming year. 
7 Local development plan less than
5 years since adoption
Red Your development plan was more than 5 years old at the time
of reporting (adopted in 2015).
8 Development plan scheme 
– next LDP:
• project planned and
expected to be delivered to
planned timescale
Amber The LDP2 was expected to be completed in 2022 according
to the 20/21 reporting period. The LDP2 is currently at
Examination Stage and scheduled for adoption in 2023. 
9 &
10 LDP Engagement:
• stakeholders including
Elected Members, industry,
agencies, the public and
Scottish Government are
engaged appropriately
through all key stages of
development plan
preparation.
N/A 
11 Policy Advice 
• Production of relevant and
up to date policy advice
Green Relevant supplementary guidance is reviewed and updated
regularly including publishing guidance on S64 submissions
and Local Place Plans during 2021/2022 reporting period. 
12 Corporate working across
services to improve outputs and
services for customer benefit (for
example: protocols; joined-up
services; single contact
arrangements; joint pre-application
advice)
Green A number of your case studies demonstrate you approach to
corporate working such as the Shopfront Improvement
Scheme, Dunbeg Masterplan and CCDC Masterplan for
Scalasaig. 
13 Sharing good practice, skills and
knowledge between authorities 
Green Your PPF report, including the case studies, set out a
number of examples of benchmarking and knowledge
sharing. Planning officers attend a number of forums, such as
HopS, the LA Aquaculture Forum,  and Clyde Marine
Planning Partnership. Officers have engaged with other rural
authorities to review and update procedures for handling prior
notification/approval submissions. 
14 Stalled sites / legacy cases:
conclusion or withdrawal of old
planning applications and reducing
number of live applications more
than one year old
Amber You have cleared 27 cases during the reporting year which is
an increase from last year however, 65 cases remain which
is an increase from 57. This is an increase on the number
which remained at the end of last year.

Page 5

Scottish Ministers, special advisers and the Permanent Secretary are
covered by the terms of the Lobbying (Scotland) Act 2016.  See
www.lobbying.scot 
St Andrew’s House, Regent Road, Edinburgh  EH1 3DG
www.gov.scot

 
15 Developer contributions: 
clear and proportionate
expectations
• set out in development plan
(and/or emerging plan);
and
• in pre-application
discussions
Green Your LDP, supported by supplementary guidance, sets out
expectations for developer contributions and sets out how
contributions are proportionate to the scale, nature and
impact of the proposed development.
RAG = Green 
Expectations for developer contributions are established in
pre-application discussions or where no pre-application
engagement is sought then established during the
assessment process. 
RAG = Green 
Overall RAG = Green

Page 6

Scottish Ministers, special advisers and the Permanent Secretary are
covered by the terms of the Lobbying (Scotland) Act 2016.  See
www.lobbying.scot 
St Andrew’s House, Regent Road, Edinburgh  EH1 3DG
www.gov.scot

 
ARGYLL AND BUTE COUNCIL 
Performance against Key Markers 
Marker 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22
1 Decision making timescales         
2 Processing agreements         
3 Early collaboration          
4 Legal agreements         
5 Enforcement charter         
6 Continuous improvement          
7 Local development plan         
8 Development plan scheme         
9
&
10
LDP Early Engagement
N/A N/A N/A   N/A N/A N/A N/A
11 Regular and proportionate
advice to support
applications 
12 Corporate working across
services         
13 Sharing good practice, skills
and knowledge         
14 Stalled sites/legacy cases         
15 Developer contributions           
Overall Markings (total numbers for red, amber and green)    
2013-14  0 5 8
2014-15 0 2 11
2015-16 0 3 10
2016-17 1 3 11
2017-18 1 3 11
2018-19 0 3 10
2019-20 0 3 10
2020-21 3 2 8
2021-22 1 4 7 
Decision Making Timescales (weeks) 
13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22
2021-22
Scottish
Average
Major
Development 59.1 14.1 23.3 22.1 37.9 28.3 33.9 40.4 40.8 44.6
Local 
(Non-
Householder)
Development
13.1 10.8 10.3 12.4 12.6 10.8
10.2 12.5 13.6
13.5
Householder
Development 7.2 6.9 7.0 7.5 7.9 7.1 7.2 9.1 10.3 8.7