Perth and Kinross Council
Strategic Housing 
Investment Plan
2024/25 – 2028/29
‘Everyone in Perth and Kinross has access to the right home, in
the right place and at the right cost”
October 2023

Page 2

1. Introduction
1.1 Good quality homes in well-designed places make a significant
contribution to Perth and Kinross Council’s (PKCs) wider aims of creating
safe and sustainable communities where people aspire to live. 
1.2    The Strategic Housing Investment Plan (SHIP) 2024/25 – 2028/29
outlines investment priorities for affordable housing which will support
delivery of the outcomes that are set out through our Local Housing
Strategy (LHS) with the following 4 new strategic priorities: 
Priority 1 – Providing more affordable homes to support liveable and 
sustainable communities; 
Priority 2 – Providing a range of housing options that people can easily 
access, afford and keep; 
Priority 3 – Delivering housing for people with varying needs; 
Priority 4 – Delivering quality homes with affordable warmth, zero 
emission and SMART technology. 
1.3 Good quality affordable homes can have a positive impact on quality of
life. With demand for housing in Perth and Kinross continuing, and the
housing needs of our communities becoming increasingly complex, our
commitment to providing a range of affordable housing options remains a
key strategic priority. We remain committed to building more homes and
overseeing a long-term programme of new affordable housing
development to meet local needs and to support the Scottish
Government’s Housing to 2040 strategy. 
1.4 The SHIP 2024/25 – 2028/29 proposes to deliver 1490 affordable homes
over the next 5-year period. This confirms our commitment to continue
with the scale, pace of delivery, and exceed with our new LHS 2022 - 2027
target of 210 affordable homes per year.
1.5 The SHIP has been developed in partnership with Community members,
Registered Social Landlords (RSLs), the Health and Social Care
Partnership, the Planning Service, and the Housing Service.
1.6 The SHIP is designed to be a working tool which:
 improves longer-term strategic planning
 provides a practical plan detailing how investment in affordable
housing will be directed
 provides an opportunity for the Council to set out key investment
priorities for affordable housing and demonstrates how these will
be delivered and the resources which will help deliver these
priorities
 forms the basis for more detailed programme planning
 provides a focus for partnership working
 informs, and is informed by, the preparation of Registered Social
Landlord (RSL) development funding plans

Page 3

 informs the allocation of resources from a national to a local
authority level.
1.7  Confirmation of our Resource Planning Assumption (RPA) was
announced during July 2021 by the Scottish Government which covered
the period 2021/22 – 2025/26. For the Financial Years 2026/27 – 2027/28,
the 2025/26 RPA has been used in line with Scottish Government
Guidance until further announcements are made. 
Table 1
Financial
Year 
2023/24  2024/25  2025/26  2026/27*  2027/28*  TOTAL 
RPA
(£Millions) 
£16.587  £16.645  £16.921  £16.921  £16.921  £83.995 
*More Homes Division Guidance Note 2020/02 only covers a 3-year
period. 
1.8 The Council will continue to increase the scale and pace of delivery of
affordable housing over the next five years through an estimated RPA of
circa £83.995m as highlighted in Table 1. 
1.9  All projects identified as priorities for funding and delivery over the 5-year
period are identified in Appendix 1. All projects are recorded through the
Scottish Government’s Housing and Regeneration Programme (HARP)
system.
1.10  Projects included within the SHIP as affordable housing will be delivered
through new build, buybacks, regeneration, renovation, and re-modelling.
The Scottish Government will use this information to draft a Strategic Local
Programme (SLP) Agreement. Once agreed, the SLP will form the basis
of the Council’s and our partner RSL Programme Agreements. It should
be noted that this SHIP is subject to developments coming forward
timeously, including obtaining the necessary approvals and consents
where appropriate. 
1.11 There are significant challenges with the development of affordable
housing projects. These challenges relate to:
 market volatility being experienced in the construction sector 
 increasing energy prices
 high material prices labour and material shortages
 construction boom
 economic uncertainty
 inflation
 risk allocation 
1.12 Some of the above factors have resulted in substantial tender prices 
increases and contractor claims, along with contractors unwilling to

Page 4

tender or hold prices for any length of time. These issues are resulting in
a significant increase on tender costs where over the past 12 months are
on average 16% to 20% and this trend of tender price increases will extend
into 2024. The Scottish Government More Homes Division are fully aware
of the current issues and to help mitigate the increased costs they have
advised that additional grant monies can be considered on a project by
project basis for abnormal costs to address site specific constraints. 
1.13 This is particularly significant in relation to contributions from the private
development industry to affordable housing through the Local
Development Plan’s Affordable Housing Policy (Policy 20) where 25% of
new housing developments must include affordable housing. A high
proportion of current and future affordable housing provision is, or will be,
as a consequence of this policy. As such, the pace of this provision will be
dictated by the development industries build-out rate, intrinsically linked to
the performance of the economy and local housing markets. 
1.14 Due to unprecedented conditions within the construction market, there is
extreme volatility both with the pricing and availability of materials &
labour. 
1.17 It should be noted that some sites which are included in the SHIP are
identified for forward planning purposes only and their inclusion does not
represent a contract or award of funding for projects.
2. The Strategic Context
2.1 The planning and delivery of affordable housing is focused on meeting
local needs by supporting the ‘right homes in the right place’. The Council,
as both the statutory housing and planning authority, is responsible for
assessing housing requirements and for ensuring appropriate land in the
right places to enable the delivery of housing. 
2.2  The LHS sets out our strategic vision for housing, considering both
national policy objectives and local priorities, based on housing need and
demand evidence. As well as our strategic response to national outcomes
and national housing priorities, the LHS sets out the approach to meeting
other statutory housing responsibilities, including fuel poverty, house
condition and homelessness. It also provides people with a vital
opportunity to have their say and influence the future delivery of housing
and housing related services in their communities. The SHIP seeks to
deliver affordable housing within Perth & Kinross in the form of new build
projects, refurbishment, and renovation projects, off the shelf acquisitions
and buybacks in following tenure types to meet local needs:
 Social Rent
 Mid Market Rent
 Shared Equity
 Self Build Plots

Page 5

2.3 The new LHS 2022 – 2027, approved at the Housing and Social Wellbeing
Committee on 15th March 2023, sets out how PKC and its partner RSLs will
continue to deliver our vision that ‘Everyone in Perth and Kinross has access
to the right home, in the right place and at the right cost.” 
2.4 The LHS has been informed by the themes and aims set out in Housing
to 2040 for Perth and Kinross to have a well-functioning housing system –
where people can find and afford a home in the place they want to live,
including in rural communities. This is supported by the principles of
supplying high quality homes that are affordable to live in, within
sustainable communities where people want to live, supported by a good
mix of housing options. It means that places are well designed and
connected, supporting people’s wellbeing, and that homes are connected
to services, facilities, and transport links. 
2.5 The new LHS incorporates the following to meet the aims set out in
Housing to 2040: 
1. providing more homes at the heart of great places
2. providing a range of housing options that people can easily     
access, afford and keep
3. delivering housing for people with varying needs
4. delivering quality homes with affordable warmth, zero emission
and SMART technology.
2.6  This will be achieved through a set of outcomes which reflect local priorities,
national policy objectives and provide a clear strategic direction for the SHIP
2024/25 – 2028/29. 
2.7 Housing to 2040 is Scotland’s first ever long-term national housing
strategy providing a vision for what housing should look like and how it will
be provided. The strategy has four key themes: 
 More homes at the heart of great places
 Affordability and choice
 Affordable warmth and zero emissions
 Improving the quality of all homes 
2.8 PKC through the Housing to 2040 commitment will increase housing
supply by assisting to deliver the Scottish Government’s ambition to
deliver 110,000 affordable homes over the next ten years up to 2031/32
where at least 70% of these homes will be for social rent. 
2.9 The Housing to 2040 strategy sets out a specific vision for ensuring: 
 A well-functioning housing system 
 High Quality, Sustainable Homes 
 Sustainable Communities 
 Homes that Meet People’s Needs

Page 6

2.10 We have reviewed our strategic priorities considering the ongoing impact
of COVID and new/emerging challenges, particularly the cost-of-living
crisis and its impact on our communities and the growing climate
emergency.
2.11 Through the new Perth and Kinross Corporate Plan 2022 – 2027, we have
set a vision where everyone can live life well, free from poverty and
inequality. The Corporate Plan will guide PKC to help make decisions
about where to prioritise activity and resources in the future. This is as the
Council transforms as an organization, to deliver on our commitments, to
listen to communities and work in partnership to tackle poverty, reduce
inequalities, improve wellbeing, and support sustainable communities.
2.12 The Perth and Kinross Offer sets out how we, together with local
communities, will deliver on our ambition to recognise that everyone in
Perth and Kinross has something to offer. Our ambition is to make sure
that we acknowledge this across the area, drawing on the strengths and
assets of individuals and communities, working together so everyone in
Perth and Kinross can live life well.
2.13 The Community Planning Partnership has revised its ambition for our area
to be the best place in Scotland for everyone to live life well, free from
poverty and inequality. We will do this through:
 Reducing Poverty 
 Physical and Mental Wellbeing 
 Digital Participation 
 Learning and Development 
 Employability 
2.14 The Scottish Government’s fourth National Planning Framework (NPF4)
which was adopted by Scottish Ministers on 13th February 2023, sets out
a vision for what Scotland, as a place, could and should look like in 2050.
This will include national planning policies and provide a plan for future
development in Scotland. Driven by the overarching goal of addressing
climate change, this long-term strategy is expected to focus on achieving
four key outcomes which the Council will incorporate into its future delivery
of affordable housing through the SHIP 2024/25 – 2028/29: 
 Net Zero Emissions
 A Wellbeing Economy
 Resilient Communities
 Better Greener Places 
2.15 In addition to the ‘Housing to 2040 Strategy’, the SHIP takes cognisance
of the Scottish Government’s Housing and Planning Delivery Framework
(HPDF) which promotes more efficient collaboration between Housing and
Planning Services in relation to the Local Housing Strategy, Housing Need
and Demand Assessment and Scottish Planning Policy. Perth and Kinross
Council's Strategic Housing Investment Plan, the Local Housing Strategy,

Page 7

and the Local Development Plan all aim to support the implementation of
the Housing and Planning Delivery Framework which aims to: 
1. increase the supply of housing 
2. make the housing system more responsive to demand
3. improve long term housing affordability 
4. reduce volatility in the housing market
2.16  A range of key strategic and planning documents including  the Local
Development Plan (LDP), the Housing Land Audit and the Perth and
Kinross Health and Social Care Partnership Strategic Investment Plan and
the Rapid Rehousing Transition Plan have also informed the SHIP.
2.17 The Council’s Child Poverty Action Report plays a pivotal role in
investment priorities for affordable housing to put poverty at the heart of
housing to reduce the cost of living and invest in areas where child poverty
is highest within Perth and Kinross. We do this by:
 increasing the supply of affordable homes within Perth and Kinross by
achieving as a minimum the Building Technical Silver Standard
(Aspects 1 & 2) to address fuel poverty
 continuing to build on the success of the ‘Home First’ initiative to
reduce the potential impact of homelessness on families 
2.18 The SHIP also recognises the fundamental role housing has in tackling
poverty. This SHIP aims to support the delivery of a range of property
types and sizes that meet the needs of households of all sizes through the
creation of high-quality energy efficient homes in sustainable communities
that support health, wellbeing, and educational attainment.
2.19 As such, our investment priorities are reflected by significant regeneration
investment in areas where levels of poverty are highest. 
Rural Areas
2.21 The Council has allocated resources to identify opportunities for new 
affordable housing in all rural areas across Perth and Kinross, including
Highland Perthshire.
2.22 The Rural Housing Fund (RHF) is available specifically for Affordable 
Housing projects in rural areas. In the current period to 2026, £25 million 
is available to fund rural projects, which is open to community-led
projects, landowners and private/charitable sector organisations. This 
fund is not open to Councils. However, to progress this opportunity the 
Council is working closely with the rural specialist agency Community 
Housing Trust (CHT) who have a proven track record of working with 
rural communities to deliver community-driven affordable housing 
projects, to date, three Community Development Trusts have been set up
in Perth & Kinross. To support this, the Council have also increased
resources in  this area and are focused on maximising RHF investment in
rural communities in the current period to 2026.

Page 8

City and Town Centre Living
2.23 The LHS Action Plan seeks to maximise the potential to generate more
homes through brownfield regeneration to encourage mixed use
developments and increase the number of homes created as a result of
this. A register of potential brownfield sites that would be suitable as
housing subject to change of use will be established with a PKC target of
delivery of 50% affordable homes through brownfield regeneration and
change of use for vacant properties by 2027.
3. Housing Need and Demand
3.1 The Perth and Kinross Housing need and Demand Assessment (HNDA)
was conducted across the Tayside area which includes Angus, Dundee,
Perth and Kinross and Northern Fife during 2021.
3.2 For development planning purposes, the Perth and Kinross housing
market is considered in terms of five Housing Market Areas (HMAs)
(Appendix 2 provides a list of the HMAs) and the need for additional
housing is reported at this level. The report on our most recent HNDA
completed in November 2022. The information from this will be used to
inform Housing Supply Targets in our recently adopted LHS.
3.3  The LHS sets an annual Housing Supply Target which determines the type
of market and affordable housing required to meet housing need and
demand throughout the LHS period. This includes the level of affordable
housing required to meet housing needs and a target for the delivery of
affordable homes for households with particular needs.
3.4 In order to increase housing supply and contribute towards the Housing
Supply Target, the Council, and its partners, will aim to deliver our new LHS
target of 210 affordable homes per year, an increased from previous LHS
target of 150, and is an annual average During the period 2016/17 –
2022/23 PKC delivered 1919 affordable homes, delivering on average 274
affordable homes per year. During the 2022/23 Financial Year, the Council
and its partners delivered 167 new build affordable homes and 36 buy backs
in total 203 new homes.
3.5  Our Vacant Property Development and Private Sector Housing Teams
provide advice and assistance to owners of long-term empty properties.
Having empty homes as an integral part of affordable housing provision
ensures a coordinated approach within Perth and Kinross. Through Vacant
Property Feasibility Grants, funding of professional fees for owners enables
them to undertake feasibility studies to enable repairing or re-purposing of
their empty properties. Initiative grants also enable owners to upgrade or
repair their properties in return for the properties being let through the Rent
Bond Guarantee Scheme for a period of 5 years, not exceeding current
Local Housing Allowance rent levels. The Council’s aim is to bring back 130
privately owned empty properties back into use as housing each year.
3.6  The housing needs and accommodation activity of Gypsy/Traveller
communities continues to be closely monitored by the Council. Although

Page 9

there are no plans in the current SHIP for affordable homes for
Gypsy/Travellers, work is progressing to establish the unmet needs of
transient Gypsy/Travellers. Consultation is also continuing with the local
Gypsy/Traveller community through the findings of the Local House
Condition Survey and following the transfer of two sites to the Housing
Revenue Account (HRA). The information obtained will be used to plan
future investment and maintenance of existing sites. Recognising that
needs may change, the Council will continue to monitor the position and
be ready to embrace this through new LHS guidance as well as the action
plan.
3.7  Engagement work with site residents at existing Gyspy/Traveller
communities have resulted identifying solutions to change the
management of the council owned sites to the Housing Revenue Account.
This will enable planned maintenance programmes to ensure Scottish
Housing Regulator standards are maintained in the future. The Council
secured £3.9m of Scottish Government funding, along with its own
funding, for one of the sites to replace the chalets with energy efficient
accommodation and installation of energy-efficient lighting, heating and
hot water systems using renewable technologies. Site fencing and paths
were improved and a new play park, community garden and playing field
were created. Digital inclusion has been improved through the supply of
free internet devices to residents. Further funding will be applied for to
enable improvements at both sites along with the long-term management.
These improvements will contribute to improving fuel poverty on the sites
as well as health and wellbeing outcomes. The Council will support
applications to develop land into permanent or transit sites for
Gypsy/Travellers. The land does not need to be identified in the Local
Development Plan and no evidence of need is required. Consultation is
currently ongoing regarding Gypsy / Traveler site standards.
4. Wheelchair & Particular Needs Housing
4.1  We are committed to increasing the supply of wheelchair accessible
homes in accordance with requirements set out in the Scottish
Government Guidance Note MHDGN 2019/02.
4.2  Work is currently underway with our RSL partners to deliver wheelchair
accessible homes across urban and rural Perth and Kinross. Through our
Strategic Local Plans, the aim is to ensure that where possible, 10% of all
homes built are suitable for people with particular needs, such as
wheelchair users, where this can be met within affordable housing
development sites.
4.3  Improvements in information on the requirement for wheelchair accessible
homes alongside demographic information has developed a clearer
picture of the future requirement for wheelchair accessible housing. This
is incorporated into the 2022-27 LHS to support developers to include
specialist housing provision in private sector developments.
5. Rapid Rehousing Transition Plan (RRTP) Priorities

Page 10

5.1  Addressing the key Homelessness and Rough Sleeping Action Group
(HARSAG) recommendation, the Council aligns strategic housing
priorities consistent with the RRTP and ensures that the new supply of
affordable housing is fully integrated within the Council’s ‘Home First’
model.
5.2 The Council’s ‘Home First’ model was introduced in 2017 and its aim is to
assist homeless households move straight into settled accommodation
and avoiding the use of temporary accommodation. Minimising the
duration, impact, stigma, and cost of homelessness is the key objective 
as well as ensuring the best outcome for homeless households.
5.3  Increasing the supply of affordable housing will assist in meeting the RRTP
strategic aims of prevention of homelessness. In addition, it will also support
the commitment to ensuring that those in housing need to find the fastest
route to safe and secure accommodation to help them resettle in their new
homes quickly and successfully with support.
5.4  With a strong focus on the prevention of homelessness, the Council
identifies and supports those at highest risk of homelessness. This is whilst
also assisting those who find themselves homeless to be rehoused as
quickly as possible, promoting choice, and ensuring positive outcomes to
reduce the stress and trauma that homelessness brings to individuals and
families.
6. Partnership Working, Consultation and Collaboration
6.1 The SHIP has been developed and implemented through close
partnership working with the Scottish Government, RSLs, Perth and
Kinross Health and Social Care Partnership, Tenants, Housing Service,
Planning Service and community members. A number of mechanisms are
in place to ensure that a range of partners participate in the ongoing
delivery of the SHIP. There is a strong history of partnership working in
Perth and Kinross with RSLs and internal and external partners to deliver
the ambitious housing programme. There are five RSLs with active projects
within the SHIP. They also have a keen interest in continuing the
partnership working to develop affordable housing within Perth and Kinross
where we continue to maintain the increased levels of routine
communication with regular meeting in the form of the Strategic Housing
Providers Forum with senior representatives of the five main housing
associations currently operating new build programmes in Perth &
Kinross.
6.2 The Council will continue to explore options for joint working around
innovative delivery mechanisms that support the provision of affordable
housing throughout Perth and Kinross. Both the Council and RSL Partners
will continue to look for efficiencies in construction methods and will work
with the construction industry and design teams to determine the suitability
of non-traditional construction methods for projects included with the
SHIP.

Page 11

6.3 Monthly updates with the RSL partners continue to take place. The RSL
partners continue to engage with the PKC Affordable Housing Enablers
about potential future development opportunities. The monthly meetings
bring an opportunity for partners to discuss the wider programme and
strategic issues including updates from the Scottish Government, Scottish
Water, the SHIP, and site prioritisation. Every two months, updates are
provided to the Scottish Government to discuss the programme and key
requirements throughout the programme year (focus is specific project
issues relating to planning, public utilities and slippage impacting
current/future year funding).
6.4 This structure provides the Council with a proactive approach to
monitoring project progress which complements discussions on strategic
issues affecting the delivery of affordable housing in Perth and Kinross.
6.5 In developing the SHIP 2024/25 – 2028/29, all RSLs provided project
proposals. All proposals were assessed alongside Council projects by the
Strategic Affordable Housing Board see Appendix 3. The Strategic
Affordable Housing Board were provided with projects that were assessed
against the SHIP prioritisation Framework (See Appendix 4) and approved
which projects to include within the SHIP.
6.7 The Perth and Kinross multi-agency Independent Living Panel provides
key information to the SHIP. They meet monthly and are made up of
Housing and Health and Social Care Partnership representatives,
including RSL and Care Providers. The Panel provides an integrated
approach to meeting housing, health and social care needs of people who
have been assessed with the eligibility criteria as requiring support to
enable them to live as independently as possible in their own home or
within specialist provision.
6.8 The Panel reviews and analyses and authorises the allocation of
appropriate housing provision for individuals as requiring specialist
housing, care, and support to live independently in Perth and Kinross.
6.9 The Independent Living Panel:
 makes recommendations for the allocation of accommodation for the
provision for independent living need
 ensures that an overview of demand and supply for independent living
needs in Perth & Kinross is maintained and regularly reviewed
 provides a link between NHS, PKC, HSCP and third sector partners to
ensure a joined-up approach and co-design of housing solutions for
those with specialist housing, care, and support needs
 links with the New Build Programme to ensure gaps in service
provision are met effectively and to inform the future planning and
development of services
 seeks reviews on placements in specialist accommodation to ensure
the provision is being used appropriately for those in most need

Page 12

 conducts quality assurance checks on cases referred to the Panel to
ensure consistency across and within the allocation process and the
provision of specialist accommodation
 ensures the efficient and effective use of resources
6.10  The Council has frequent meetings with developers to discuss
development sites and how housing developments can contribute to LHS
priorities through inclusion of their proposed developments in the SHIP.
The Council have procured housing through the Scottish Procurement
Framework as well as through Section 75 agreements being made with
Developers in fulfilling the requirements of the Affordable Housing Policy.
6.11  In taking forward the LHS and the SHIP, workshop events are organised
to consult on the objectives of both and thoughts on how objectives can
best be met are invited from a wide audience of partners and community
representatives.
6.12  The SHIP document is widely circulated, and comments are invited ahead
of finalisation.
7.  Review Mechanism – Response & Resolution of Constraints
7.1  The Council regularly reviews affordable housing projects, both internally
and with RSL Partners, to ascertain progress through monthly meetings.
Tripartite meetings with officers from the Council, RSLs and the Scottish
Government will take place every 2 months.
7.2  Frequent, formal review process assists with the identification of constraints
and potential slippage in the programme at an early stage. Early contact
and liaison with internal stakeholders, such as Planning, or external
stakeholders, such as Scottish Water, has assisted the Council in
resolving constraints and achieving effective programme management
outcomes. 
8. Affordable Housing Supply Programme (AHSP) 
8.1  The Affordable Housing Supply Programme forms part of the Scottish
Government’s More Homes Scotland approach, which aims to increase
and accelerate the supply of homes across all tenures. The Programme
supports the Council in delivering our affordable housing priorities, by
providing quality homes in mixed communities that fit local need.
8.2  The grant subsidy which is available through the Affordable Housing
Supply Programme supports the delivery of social rented housing, homes
for mid-market rent, and the provision of housing for low-cost home
ownership (most notably the new supply shared equity scheme).
8.3 Resource Planning Assumptions (RPA) support the delivery of new
affordable homes across Perth and Kinross by providing grant support at
flexible benchmark rates for each affordable home developed.

Page 13

8.4  The Council RPA for the 2023/24 Financial Year is £16.587m. Future
years 2024/25 – 2025/26 RPA funding was agreed during July 2021 as
highlighted within Table 1, (paragraph 1.8). Through Scottish Government
Guidance MHDGN 2022/02, it advises to use the 2025/26 RPA as the
basis for future years until announced. As such, it is prudent to take a
conservative approach for future years within the SHIP until further
information on RPA levels post 2026 is known, to avoid abortive work or
other cost risks.
8.5  The Affordable Housing Enablers continue to identify additional projects
and liaise with RSL partners to bring further opportunities for affordable
housing into the programme.
8.6  The SHIP projects that 1688 affordable homes could be delivered in the
period to 2028/29.
8.7  The Funding from the Scottish Government, required to deliver the
proposed affordable Housing projects as outlined within the SHIP 2024/25
– 2028/29, as per Table 1. 
8.8 Over and above the increased flexible grant benchmark rates, Scottish
Government’s baseline benchmark for the council starts at £83,584 per
unit and £91,182 per unit for housing associations (based on 3-person
equivalent as well as additional grant funding available for the following
additional quality measures additional grant funding is available from
existing benchmarks):  Resource Planning Assumptions to affordable
housing developers who meet Scottish Government criteria in relation to
specific quality and design features. This includes: 
 Delivering homes to Section 7, Silver Level, of the 2019 Building
Regulations in respect of Energy for Space Heating (this is, full Bronze
Level plus Aspect 2 of Silver Level) - £2,338 per unit (3-person
equivalent benchmark)
 Provision of balconies within flatted developments where the provision
of private or communal outdoor space cannot otherwise be
accommodated - £4,676 per unit (3-person equivalent benchmark)
 Provision of space for home working or study – £4,092 per unit (3-
person equivalent benchmark)
 Ensuring that all new social rented housing is digitally-enabled – £351
per unit (3-person equivalent benchmark)
 Installation of ducting infrastructure for electric vehicle charge point 
connectors - £585 per unit (3-person equivalent benchmark)
 Installation of electric vehicle charge points - £585 per unit (3-person
equivalent benchmark)
 Installation of automatic fire suppression systems - £3,507 per unit
(3-person equivalent benchmark)
 Installation of heating systems which produce zero direct emissions
at the point of use - £4,676 per unit (3-person equivalent benchmark).

Page 14

8.9 The increased flexible benchmark rates of grant and additional grant being
made available to affordable housing developers who incorporate
enhanced design elements is being met from current known RPA. This
may have an impact on the number of new affordable homes being
delivered as the level of grant for each property increases.
8.10  The Council, alongside its RSL partners, has sought to be as realistic as
possible in detailing the programme. Projects that have been assessed as
having completions by March 2024 have been programmed within the first
year of this SHIP. Years 2 and 3 of the SHIP see the conclusion of large
projects with a fewer number of projects detailed in later years. It should
be noted that the SHIP is reviewed every year.
8.11 The Council, in consultation with the Scottish Government, will continue
to manage the AHSP in conjunction with its Housing Capital Plan, Housing
Revenue Account investment, Council Tax 2nd Homes Funds, Commuted
Sums to support and maximise delivery of affordable housing in priority
areas during the SHIP period.
9. Funding Resources, Housing Revenue Account, Developer
Contributions and Council Tax (Second Homes)
Funding Resources to support delivery of SHIP priorities are summarised: 
 Housing Revenue Account (HRA) 
9.1 Prudential borrowing via the HRA is the key funding component used in
addition to Scottish Government Housing Subsidy to support the delivery
of new affordable homes for PKC affordable housing. The financial
viability of all potential Council new build projects is assessed in terms of
the Housing Revenue Account 30-year business plan, to ensure that the
capital costs generate a reasonable return on investment over the long
term. The new build programme is monitored as part of the HRA capital
monitoring process between Finance, Housing, and Property.
 Developer Contributions
9.2 Applications that meet the criteria can be made to PKC to support the
delivery of affordable homes from Developer Contributions (DCs).
Information on applications received during 2022/23 and 2023/24 to date
in respect of supporting the delivery of affordable homes are detailed
below:
Table 2:
PROVIDER PROJECT AFFORDABLE
HOMES
HMA DCs Used
(£0.00M)
Kingdom HA Bertha Park
Phase 2B
28 Strathmore &
Glens
0.056
Hillcrest Homes Old
Causeway
9 Kinross 0.096

Page 15

Hillcrest Homes Abernethy
MMR
7 Perth 0.077   
9.3      As of 29 September 2023, there was £1.26M available within Developer
Contributions to assist in bringing forward affordable housing
developments throughout Perth and Kinross. Policy requires these funds
to be invested in the same HMA they were collected. 
 Council Tax Reserve Income from the Reduction of
Discount for Empty and Second Homes
9.4 The Council has funding available through income raised each financial
year from Council Tax (Empty Homes and 2nd Homes). This funding
assists in supporting the delivery of all affordable homes delivered by the
Council (new build and Empty Homes) and new builds for RSLs.
9.5 These funds are used to support the Vacant Property Development and
Private Sector Teams bring empty homes back into use for housing. The
following empty properties have been brought back into use as housing
through assistance of these funds:
Financial Year Empty Homes Brought Back into
2015/16 149
2016/17 138
2017/18 146
2018/19 145
2019/20 139
2020/21 93
2021/22 130
2022/23 66
TOTAL 1006 
9.6  As of 1 April 2023, the balance of funds remaining from Council Tax for
the delivery of affordable housing was £4,353,000. Since 2015/16
through the delivery of New Build affordable housing and Empty homes,
the Council has used funding of over £11m from the Council Tax to assist
with the delivery of affordable homes.
10. Affordable Housing Policy
10.1 The Developer Contributions and Affordable Housing Supplementary
Guidance (2020) which is linked to Policy 20: Affordable Housing in the
Perth and Kinross Local Development Plan 2 (2019) and sets out the
contribution that developers must make towards the delivery of affordable
housing as a condition of securing planning approval for a new build
development. The Supplementary Guidance requires new housing
developments within Perth and Kinross to provide a 25% Affordable
Housing Contribution and is currently being updated.in 2023.

Page 16

10.2  Affordable Housing can include a variety of forms, such as social rent,
Low-Cost Home Ownership options such as Shared Equity, Mid-market /
intermediate rent, and self-build plots. Sites delivered though the
Supplementary Guidance make a significant contribution to the SHIP.
10.3  Commuted Sums make a  contribution towards the delivery of affordable
housing in Perth and Kinross. The Council continues to utilise
contributions resulting from the Supplementary Guidance to support the
delivery of affordable homes within its own programme and with RSL
partners where appropriate.
11. SHIP Prioritisation Framework
11.1  All affordable housing proposals that are to be included within the SHIP
are prioritised by the SHIP Prioritisation Framework (PF) (APPENDIX 4).
This framework prioritises investment whilst assessing the proposals
against the Council’s strategic aims and priorities, along with
deliverability, and the community benefits it will provide
11.2  In assessing projects for inclusion in the SHIP, the Council considers the
following:
 Whether the development assists with the delivery of LHS                   
outcomes
 The extent to which the development addresses housing needs
 Site attributes
 Whether planning approval is in place
 Funding requirements
 Strategic priority
 Deliverability
11.3  The PF is not intended to provide the only assessment of priority;
however, the Council will continue to balance its investment decisions
through a mixture of Council, RSL and developer delivery and by
considering a range of affordable housing tenures to meet housing need
across all the HMAs.
11.4  In recognising the need for housing to address particular support needs,
including wheelchair accessible homes, projects which provide this type
of housing will attract extra points under the scoring criteria.
12. Energy Efficiency
12.1  The Council seeks to maximise the opportunities for energy efficiency and
reduction of fuel poverty through achieving the ‘Greener’ energy
efficiency standard in new builds where practical. To meet this standard,
homes must meet Section 7 (Aspect 1 & 2) of the 2011 Building
Regulations in relation to Carbon Dioxide emissions and energy for space
heating.

Page 17

12.2  The standard may not be attainable in all projects, particularly where an
existing building is to be redeveloped or where homes form part of a larger
development for market provision or through the PKC Buyback scheme.
12.3  The Council supports RSL partners to develop to Silver Standards as a
minimum and to provide enhanced levels as set out within the Scottish
governments Housing to 2040 vision.
12.4  The Council has developed a new net zero Design Guide. It is anticipated
by 2023/24 that all PKC new build affordable homes will meet the ‘Gold
Standard’ as a minimum and meet some of the key objectives within the
Council’s climate change strategy and action plan.
13. Equalities
13.1  The Council are fully committed to equalities and diversity. The General
Equality Duty has three main aspects:
 Eliminate Discrimination
 Advance equality of opportunity
 Foster good relations between communities. 
13.2  The Council will respond to the different needs and service requirements
of people regardless of sex, race, colour, disability, age, nationality,
marital status, ethnic origin, religion or belief, sexual orientation, or
gender re-assignment. The planning and delivery of good quality housing
and appropriate information, advice and support services embrace the
principle of equal opportunities and equality in outcomes. 
13.3  The SHIP plays a vital role in promoting this agenda. People with
specialist needs should have the opportunity to live independently in their
own homes and community. To address specialist needs, at least 10% of
new affordable homes will be delivered to meet particular support needs
(this also includes wheelchair accessible).
14. Strategic Environmental Assessment
14.1  The Strategic Environmental Assessment (Scotland) Act 2005 requires
that all qualifying plans, programmes, and strategies, including policies
are screened to assess the potential environmental impact of the plan. A
Strategic Environmental Assessment (SEA) ensures that environmental
issues are considered by decision makers alongside social and economic
issues.
14.2  The SHIP, as part of the LHS, was considered under the Environmental
Assessment (Scotland) Act 2005 and pre-screening identified that the
SHIP would have no, or minimal, environmental effects. It is therefore
exempt, and the SEA Gateway has been notified.

Page 18

15.  Monitoring
15.1  The SHIP is closely monitored, and funding is claimed promptly to promote
and maximise the funding invested within Perth and Kinross. Annual
reviews of progress in increasing the supply of housing are reported to the
Council’s Housing and Social Wellbeing Committee, as part of the review
of progress in implementing the LHS. 
15.2 A range of project management activities are used to ensure resources
are managed effectively with projects progressing as planned. These 
include: 
 ongoing liaison between services within the Council and between the
Council and Registered Social Landlord partners on specific projects
 multi-agency project group meetings 
 quarterly tripartite meetings involving the Council, individual
developing Registered Social Landlord partners and the Scottish
Government
 regular internal Board meetings to review progress. Throughout the
duration of this SHIP progress will continue to be monitored to support
project delivery

Page 19

APPENDIX 1 - Strategic Housing Investment Plan (2024/25 – 2028/29)
Affordable Housing Site Starts (2024/25 –
2028/29)     
PROVIDER 24/25 25/26 26/27 27/28 28/29 Total AH
PKC 152 174 135 105 72 638
KHA 90 16 54 58 0 218
HH 128 102 0 0 0 230
CHA 34 46 16 0 0 96
PfP 236 31 0 0 0 267
Ark 18 0 41 0 0 59
TBD 55 0 0 0 125 180
Total Site Starts 713 369 246 163 197 1688 
Affordable Housing Completions (2024/25 –
2028/29)     
PROVIDER 24/25 25/26 26/27 27/28 28/29 Total AH
PKC 82 150 121 135 75 563
KHA 149 53 28 40 14 284
HH 101 87 40 36 0 264
CHA 17 41 42 8 0 108
PfP 124 105 44 0 0 273
Ark 18 0 10 20 21 69
TBD 25 35 0 0 40 100
Total Completions 516 471 285 239 150 1661 
ARK – Ark Housing Association, Caledonia Housing Association, HH – Hillcrest Homes, KHA – Kingdom Housing Association, PKCHS – Perth & Kinross
Council Housing Service, PfP –  Places for People, TBD – To be Determined

Page 20

Pre 2024/25 Site starts with Completions
in 2024/25+       
Project Address HMA Provider Total New
Homes Site Start Pre 24/25 Completions
24/25
Completions
25/26
Completions
26/27
Hayfield Brae, Lynedoch
Road, Methven  Perth PKC 12 12 12 0 0
Bertha Park Phase 3,
Perth Perth KHA 41 41 41 0 0
Lathro Farm, Kinross Kinross KHA 35 35 35 0 0
Broich Road Phase 4,
Crieff Strathearn KHA 12 12 12 0 0
Milnathort, Kinross  Kinross KHA 16 16 16 0 0
Abbeyfield, Crieff  Strathearn HH 9 9 9 0 0
Wester Tomaknock, Crieff Strathearn HH 25 25 25 0 0
Bertha Park Phase 4A,
Perth Perth  PfP 16 16 16 0 0      
166 166 166 0 0

Page 21

2024/25 Site Starts with Completions 24/25+       
Project Address HMA Provider
Total
New
Homes
Site Start
24/25 Completions 24/25 Completions 25/26 Completions
26/27
Buybacks Various PKC 30 30 30 0 0
Grewar Farm, Coupar
Angus Strathmore PKC 42 42 0 42 0
Former Balhousie
School, Perth Perth  PKC 40 40 20 20 0
Former Beechgrove
Residential Home,
Perth 
Perth  PKC 40 40 20 20 0
East of St Cedd’s
Road, Ballinluig Highland CHA 16 16 8 8 0
H31 Stanley  Perth  CHA  18 18 9 9 0
Moyness, Blairgowrie Strathmore & Glens KHA 36 36 18 18 0
Forfar Road, Meigle Strathearn KHA  36 36 18 18 0
Broich Road Phase 3,
Crieff Strathearn KHA 18 18 9 9 0

Page 22

Hatton Road, Rattray Strathmore & Glens HH 42 42 21 21 0
Duntaylor Avenue,
Aberfeldy Highland HH 45 45 25 20 0
Oudenarde Site Perth HH 41 41 21 20 0
Westpark Phase 1,
Blairgowrie Strathmore & Glens PfP 73 73 30 30 13
Scone North Perth PfP 60 60 30 30 0
Bertha Park Phase 4B,
Perth  Perth PfP 18 18 18 0 0
Almond Valley Phase
1, Perth Perth  PfP 85 85 30 30 25
Hawarden Terrace,
Perth  Perth  Ark  18  18  18  0  0 
Broich Road, Crieff Strathearn TBD 55 55 25 35 0      
695 695 332 330 38

Page 23

2025/26 Site Starts with Completions
2025/26+       
Project Address HMA Provider
Total
New
Homes
Site Start 25/26 Completions 25/26 Completions 26/27 Completions 27/28
Buybacks Various PKC 30 30 30 0 0
Atholl Road/Elm Court,
Pitlochry Highland PKC 18 18 8 10 0
Former Hillside Hospital,
Perth  Perth  PKC/HH 70 70 20 25 25
Thimblerow, Perth  Perth  PKC/HH 60 60 10 25 25
Borlick Phase 1,
Aberfeldy Highland PKC 35 35 10 15 10
Haugh Road, Blairgowrie Strathmore &
Glens CHA 30 30 15 15 0
Former Co-op &
Adjacent Site, Perth  Perth  CHA 16 16 8 8 0
H30 Stanley Perth  KHA 16 16 8 8 0
Strathmore Terrace,
Alyth
Strathmore &
Glens HH/PKC 51 51 10 20 21
Moncur Road, Inchture Perth HH 12 12 6 6 0
Westpark Phase 2A,
Blairgowrie
Strathmore &
Glens PfP 31 31 15 16 0      
369 369 140 148 81

Page 24

2026/27 Site Starts with Completions
2026/27+       
Project Address HMA Provider
Total
New
Homes
Site Start 26/27 Completions 26/27 Completions 27/28 Completions 28/29
Buybacks Various PKC 30 30 30 0 0
St Catherines Square,
Perth Perth PKC 30 30 10 20 0
Borlick Phase 2,
Aberfeldy Highland PKC 35 35 10 10 15
Rossie Place (Ph 1 & 2),
Auchterarder Strathearn PKC 40 40 10 10 20
Former Co-op &
Adjacent Site, Perth  Perth  CHA 16 16 8 8 0
Bertha Park Phase 4C,
Perth Perth KHA 54 54 20 20 14
Westpark Phase 2B Strathmore
& Glens Ark 41 41 10 20 21      
246 246 98 88 70

Page 25

2027/28 Site Starts with
Completions 2027/28+                
Project
Address HMA Provider Total New Homes Site Start 27/28 Completions 27/28 Completions 28/29 Completions 29/30
Buybacks Various PKC 30 30 30 0 0
Rossie Place
(Ph 3 & 4),
Auchterarder
Perth  PKC 40 40 10 10 20
Perth West Perth PKC 35 35 10 10 15
Bertha Park,
Perth (Ph5) Perth KHA 58 58 20 20 18      
163 163 70 40 53

Page 26

2028/29 Site Starts with
Completions 2028/29+                
Project
Address  HMA Developer  Total
Units  Site Start 28/29  Completions 28/29  Completions 29/30  Completions 30/31 
Buybacks  Various  PKC  30 30 30 0  0 
Stanley H30
(Ph2)  Perth  PKC  22 22 0  22 0 
Perth West Perth TBD 65 65 20 20 25
Bertha Park,
Perth (Ph6) Perth TBD 60 60 20 20 20
Rossie Place
(Ph 5),
Auchterarder
Perth PKC  20 20 10 10 0      
197 197 80 72 45

Page 27

Appendix 2 – HMAs
Perth and Kinross Settlements by HMA 
HMA 
Greater Perth Abernethy. Abernyte. Almond bank. Balbeggie. Bankfoot. Bridge of Earn.
Dunning. Errol. Forgandenny. Glencarse. Glenfarg. Guildtown. Inchture,
Invergowrie, Longforgan. Luncarty. Methven, Murthly, Perth. Scone.
Stanley. St Madoes. Wolfhill
Highland  Aberfeldy. Ballinluig, Blair Atholl. Dunkeld. Fearnan. Kenmore.
Kinloch Rannoch. Pitlochry
Kinross  Blairingone. Crook of Devon, Glendevon. Keltybridge.
Kinnesswood, Kinross, Milnathort, Powmill, Scotlandwell
Strathearn  Aberuthven, Auchterarder, Blackford. Braco, Comrie, Crieff.
Gilmerton. Gleneagles, Greenloaning. Muthill, St Fillans
Strathmore and
Glens (formerly
Eastern Perthshire) 
Alyth. Ardler. Blairgowrie. Bridge of Cally. Burrelton. Caputh. Coupar
Angus. Kettins, Kirkmichael, Meigle. Meikleour, New Alyth.
Spittalfield. Woodside

Page 28

Appendix 3
Strategic Affordable Housing Board Members (Note: a separate Board, with the following members plus the Council’s Capital Programme officer
is responsible for detailed governance of PKC-only sites. Governance arrangements are under review pending the implementation of the Council’s
Senior Leadership Review.) 
Name Position within PKC
Elaine Ritchie Senior Service Manager (Housing)  
Ben Wilson Service Manager – Planning and Housing Strategy
Nicola Lennon Service Manager - Housing
Kevin Divin Team Leader – Housing Strategy
Steven Coyle Finance and Governance Team Leader

Page 29

Appendix 4 – SHIP Prioritisation 
Methodology Prioritisation Framework Scoring
Introduction
The Prioritisation Framework provides a tool to prioritise investment which balances the Council’s strategic objectives, deliverability,
and community benefits. It is used to assess projects for inclusion in the SHIP, which will assist in deciding whether we bring projects
forward to SHIP inclusion.
The framework does not provide the only assessment of priority and Perth and Kinross Council will continue to balance its investment
decisions through a mixture of Council, Registered Social Landlord and Developer delivery by considering a range of affordable
housing tenures to meet housing needs across its Housing Market Area.
As projects develop there may be a need to adjust to the scoring output as, for example, planning permission is granted, or wider
community benefits are realised. This may cause the priority of a project to be revised during the life of the SHIP.
Scoring Criteria
1. Contribution to general unmet Housing Need: 
What level of demand can we evidence for a project? How much need is there in the area for affordable housing? What are  
the waiting lists like? What are we predicting for future trends? The scoring structure for demand:
 High - between 7 and 10
 Medium - between 4 and 6
 Low - between 0 and 3
2. Inclusion, Equality and Meeting Particular Needs 
If a project is planned to make additional provision for particular needs (such as wheelchair accessible housing) and/or             
meets a particular needs demand in an area it should score more highly.
 High - between 7 and 10
 Medium - between 4 and 6
 Low - between 0 and 3

Page 30

3. Wider Community benefit and Regeneration: 
If a project delivers wider community amenities or benefits that make a significant contribution to the regeneration of an area    
it should score more highly. Points should also be awarded if the project secures the future of a historic or listed building or 
reuses a brownfield site.
 High - between 7 and 10
 Medium - between 4 and 6
 Low - between 0 and 3
4. Meets agreed strategic priority (Contribution to SOA and LHS Objectives) 
Project is assessed in terms of the overall contribution it would make to achieve the strategic objectives of the Single Outcome  
Agreement and the Local Housing Strategy. The project is assessed depending upon how many objectives the project was 
assessed as contributing towards. The scoring structure:
 High - between 7 and 10
 Medium - between 4 and 6
 Low - between 0 and 3
5. Project Deliverability             
This assesses whether a project is likely to be deliverable within the SHIP timescale. Factors that are considered are whether     
the site is in the ownership of Perth and Kinross or the RSL, and the progress anticipated to be achievable. The scoring               
structure:
 High - between 7 and 10
 Medium - between 4 and 6
 Low - between 0 and 3 
 
Weighting of scores
Whilst all these measures are important considerations when deciding whether a project goes on to the SHIP, it is felt that the
importance of criteria one should give it extra weighting relative to the other criteria.
Thus, the scoring will be out of a possible sixty, with each of the five criteria scored out of ten but with the score for criteria one
doubled to reflect its importance.

Page 31

The RAG rating for projects:
Low priority Medium priority High priority
1 – 20 20 - 40 40 + 
Reds should be presented to the project board with a recommendation not to add to the SHIP, Ambers would be considered for
inclusion after reviewing any other pertinent factors, Greens would be strong recommendation for inclusion and progression as a
priority.