Appendix 3
Table 1: Site Facilities and Options regarding potential Transient Site at North
Muirton 
Site Facilities  Requirement  Option 1 Option 2 Option 3
Hard standings   A suitable hard-wearing
material which extends over
the whole area to be occupied
by a touring caravan or other
vehicle.
10 hard
standings to be
provided
6 hard standings
to be provided
4 hard standings
to be provided
Amenity Building  Small building providing access
to welfare facilities, kitchen
worktop, electrical sockets and
a communal room for site
management and resident use.   
Site Management
facility 
Office to provide facilities to
manage the site and for
residents to access – communal
space. 
No facility  No facility 
Toilet Facilities Toilets within the amenity
building 
4 toilets and 1
accessible toilet 
3 toilets and 1
accessible toilet
2 toilets and 1
accessible toilet
Showering Facilities Shower facilities within amenity
building 
3 showers (male
and female) and
1 accessible
shower room 
2 showers (male
and female) and
1 accessible
shower room
2 showers (male
and female) and
1 accessible
shower room
Water Supply One cold water supply to be
provided for the whole site.
This could be provided through
a water standpipe or water
bowser. 
Electrical Point One electrical charging point at
each pitch
10 points 6 points 4 points
Refuse and Recycling
Facilities
Refuse and recycling disposal
facilities to cater for the size of
the site   
Recreational area  Small grass area for children to
play.   
Animal Area Small, fenced area for animals
to be kept safely and securely.   
Estimated Road Provision  £450K £450K £450K
Total Cost £2.4M £1.8M £1.7M

Page 2

Site Design
Design  Consideration 
Site Layout When designing the layout of a site careful consideration must be given to the:
• health and safety of residents and in particular children in terms of entry and exit
points, including the use of effective signage 
• need for separate vehicular and pedestrian access 
• installation of traffic calming measures such as speed humps
• measures to ensure that appropriate drainage is accommodated 
• location of pitches in a circular or horseshoe design rather than the traditional
linear layout of pitches
Site Boundaries A range of different boundaries should be considered such as:
• bunding and planting, fences, low walls, hedges and natural features. 
• The aim should be to achieve a boundary that is sympathetic to and in keeping with
the surrounding area. Boundaries can also be used to provide shelter for more
exposed sites.
Size of Pitch  Pitch sizes should be in the region of 15x8.5m to accommodate a touring caravan and 
the towing vehicle.
Layout of Pitches  Each pitch should:
• be clearly demarcated to make it clear what each individual household may occupy
• aim to achieve a boundary that is clear, sympathetic to, and in keeping with,
surrounding areas.
Orientation of
Pitches 
In designing the layout of a site enough space must be provided to:
• permit the easy manoeuvrability of the residents own living accommodation both to
the site and subsequently on to a pitch
• ensure access roads and the site provide sufficient space for the manoeuvrability of
caravans and their towing vehicles
Access for
Emergency Vehicles
In designing a site, all routes for vehicles on the site must allow easy access for emergency
vehicles and safe places for turning. Emergency services should be consulted on the site
layout
Site Security  Site layout can play an important role in avoiding a sense of enclosure and isolation amongst
Gypsy/ Travellers. Security within the site should:
• be designed to ‘design out’ crime and social exclusion and ‘design in’ community
safety and social inclusion through openness of design, allowing ease in passing
through whether walking or driving
• Have a gated entrance in some sites to ensure the safety of children and provide an
element of security  
• enable residents to easily oversee all areas of the site 
Police Scotland should be consulted on site layout.
Hard Standing Each pitch must include:
• standings that are permeable and constructed in accordance with the industry code
of practice 
• a base that can bear the load placed on it by the home or vehicle and its contents,
and the anticipated level of vehicle movement.

Page 3

Table 2: Option Appraisal regarding site provision and potential phasing 
Option Appraisal
All Options  - Exceed or meets site standards
- Meets good practice and particular elements selected based on
benchmarking with various sites in Scotland and the UK as a whole
- Meets needs of Gypsy/Travellers who may have particular support
needs
- Positive feedback from Gypsy/Travellers and key partners 
Options Benefits Concerns
Option 1 - Provides more hard standings than is
currently required, based on current
need
- Providing more hard standings could
be considered as future proofing the
site, and cost effective in the long term
- Additional hard standings
could increase demand
- Costly option due to the
increased size
Option 2 - Provides the amount of hard
standings that is currently required,
based on current need
- Due to site layout and build, there is
an option to create even more hard
standings in the future, if need and
demand increases
- Although management
accommodation is not included this
can still be provided using current
service delivery method and the use
of SMART technology 
- Not as expensive as option 1
- Does not include the on-
site management
accommodation
- May require additional
funding if the site was to
be increased to meet
demand
Option 3 - Meets current need and demand
- Can be future proofed, made larger if
required – similar to option 2
- Although management
accommodation is not included this
can still be provided based using
current service delivery method and
the use of SMART technology 
- Not as expensive as options 1 and 2 
- Does not include the
number of hard
standings to meet current
need
- Does not include the on-
site management
accommodation 
- May require additional
funding if the site was to
be increased to meet
demand