Page 1

PERTH AND KINROSS COUNCIL
Housing and Social Wellbeing Committee
7 September 2022
BOBBIN MILL GYPSY/TRAVELLER SITE TRANSFER 
Report by Executive Director (Communities)
(Report No 22/204) 
1. PURPOSE 
1.1 This report provides an update on the agreed further consultation and
engagement with residents of Bobbin Mill Gypsy/Traveller site and outlines the
long-term benefits for residents from transferring the site from the Council’s
General Fund to the Housing Revenue Account. It also seeks approval for this
transfer. 
2. RECOMMENDATION
2.1  It i It is recommended that Housing and Social Wellbeing Committee:
• approves the transfer of Bobbin Mill Gypsy/Traveller site from the
General Fund to the Housing Revenue Account (HRA) 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background 
• Section 5: Proposal
• Section 6: Financial Implications
• Section 7: Consultation and Engagement 
• Section 8: Conclusion 
4. BACKGROUND 
4.1 In March 2022, Housing and Communities Committee approved the transfer of
Double Dykes, Gypsy/Traveller site, to the HRA (Report No. 22/63 refers) and
noted the ongoing consultation with residents of Bobbin Mill Gypsy/Traveller
site. The background information within this report remains relevant for the
purpose of this report. 
4.2 Bobbin Mill is located a short distance away from Pitlochry town centre in a
private woodland area. Bobbin Mill has been in existence since 1947 and was
set up as a Gypsy/Traveller housing project by the Scottish Office Department
of Health and the Church of Scotland. The land was leased to the then County
Council for a term of 99 years by Cluniemore Estates (now Pitlochry Estates).
At that time, the provision consisted of a former Army Training Cadet hut,

Page 2

which was converted to provide 4 one-bedroom apartments with a cold-water
supply, a fire and sink and toilet facilities. 
4.3 In September 2010, the site was upgraded to provide 6 three-bedroom chalet
accommodation. This was undertaken in conjunction with Pitlochry Estates
and funding was accessed from the Scottish Government. 
4.4 Residents on the site have an occupancy agreement with Perth & Kinross
Council and pay a weekly rental of £73.08 at Bobbin Mill (over 52 weeks) to
the Council. The residents are also required to pay Council Tax.
4.5 Bobbin Mill is held on the General Fund, and the Housing Service is
responsible for the management of the site. This includes allocation of the
chalets, tenancy management, rent collection and managing rent arrears, and
repairs and maintenance of the chalets on site.
4.6 Each year when it comes to budget setting, the General Fund faces many
competing priorities from across all areas of the Council and can be subject to
reductions in funding. Unlike the General Fund, the HRA is not subject to the
same level of reductions and in the main is self-financing, as it is funded
through the rents that tenants pay. 
4.7 As the account for the site is separate from the wider HRA account, residents
do not benefit from the wider pooling of rents and the ability to deliver longer
term planned improvements, such as planned maintenance and capital
improvements.
4.8 The rent levels and rent structure at Bobbin Mill is not fully aligned with HRA
tenants.
4.9 During 2007 to 2011, £174,000 of investment (net of Scottish Government
Grant) was spent on improving Bobbin Mill to ensure it continued to meet the
minimum site standards. This investment was funded through prudential
borrowing on the General Fund and there is still approximately £77,000 of
outstanding debt on the site.
5. PROPOSALS
5.1 Through the provisions of the Housing (Scotland) Act 2010 and the
introduction of the Scottish Social Housing Charter, it has been made clear
that the provision and management of a Gypsy/Traveller site is a housing
function. There are several challenges with the existing arrangements as
detailed above. It is, therefore, proposed that the site at Bobbin Mill is
transferred from the General Fund to the HRA. 
5.2  As the HRA can provide a secure platform for building a long-term financial
strategy, transferring the site to the HRA would enable any future works and
capital spend to be made through the HRA Capital or Planned Maintenance
programmes. It would also provide the ability to provide match funding, should
further opportunities regarding additional funding to improve Gypsy/Traveller
sites become available.

Page 3

5.3 There will be no change to the structure or type of services provided to
residents. There will be an enhancement to the services provided, in terms of
a planned maintenance programme for the chalets and the site, and an
opportunity for residents to access the same level of support and assistance
that is on offer to HRA tenants. In addition, a review of the rent structure would
be undertaken to ensure alignment with other HRA tenants.
6. FINANCIAL IMPLICATIONS
6.1 As noted in section 4.9, there is currently outstanding debt of £77,000 on the
site. It is proposed to transfer this debt from the General Fund to the HRA as
part of the overall transfer. 
6.2 The loan charges associated with this debt will be met by the income paid by
the current residents of the site. There would be no negative financial
implications on current HRA tenants as a result of this transfer.
6.3  Once the site is transferred, all future costs associated with the delivery of
services, repairs and capital expenditure will be contained within HRA
budgets.
7. CONSULTATION AND ENGAGEMENT
7.1 As a social housing landlord, we are required to consult with tenants and
residents when making changes which may impact on their tenancy or the
way in which they access our services and seek their opinions. To ensure we
fully consulted with the residents of Bobbin Mill, the following actions were
taken:
• individual letters were sent to all residents providing information on the
transfer and contact details should they have any specific queries or
concerns 
• 3 separate offers to meet with residents were provided, including visits
to the site and telephone discussions 
• the development of a question-and-answer guide around the transfer
and the impact on the existing arrangements was developed and hand
delivered to all residents 
• Independent advice and support were offered from the Minority Ethnic
Carers of People Project (MECOPP) and legal advice from the Ethnic
Minority Law Centre
• a dedicated officer identified for residents to approach if they required
further information or advice.
7.2 In January 2022, as a result of COVID-19 restrictions, an initial virtual meeting
was set up to discuss the transfer with all residents, at which only one former
resident attended.
7.3 Two further face to face meetings were arranged at a time and date to suit
residents, particularly those with individual caring and work commitments.
Both these meetings were cancelled at the request of the residents with them
indicating they would consider the documentation provided and respond
directly.

Page 4

7.4 As no responses were received, a final letter was sent to all residents advising
them of the intention to seek Committee approval and a deadline given for
their feedback to be included in the report. A request for a meeting was
received and officers met some of the residents to discuss the transfer.
Reassurance was provided on the issues they raised, particularly in terms of
their right to travel. 
7.5 Wider tenant consultation and engagement, in accordance with our tenant
agreed Framework, has taken place. There were no issues or concerns in
relation to the proposal.
8. CONCLUSION   
8.1 This report outlines the benefits for residents at Bobbin Mill around the
transfer of their site to the HRA. These benefits will not only enhance the
services residents will receive, but also provide a more secure financial
platform to allow us to deliver the Scottish Government’s vision in relation to
Improving the Lives of Gypsy/Travellers. 
8.2 Having a long-term financial planning approach to continuing to improve the
site, in partnership with residents, will also allow us to have meaningful
engagement, which is a consistent approach across all the Council’s housing
stock.
Author
Name  Designation Contact Details
Elaine Ritchie  Senior Service
Manager 
(01738) 475000
ComCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
Barbara Renton  Executive Director
(Communities)
26 August 2022 
APPENDICES
• There are no Appendices to this report.

Page 5

ANNEX
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION  
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment None
Strategic Environmental Assessment None
Sustainability (community, economic, environmental) None
Legal and Governance  Yes
Risk None
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  None 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This report supports the delivery of the Strategic Objectives within Perth and
Kinross Community Plan/ (Local Outcomes Improvement Plan) 2017-2027
and Corporate Plan 2018-2022. Single Outcome Agreement in terms of the
following priorities: 
2. Resource Implications 
Financial 
2.1 Costs associated with the delivery of services, repairs and capital spends are 
contained within existing HRA budgets. 
Workforce 
2.2 There are no workforce implications arising from this report. 
Asset Management (land, property, IT) 
2.3 There are no asset management implications arising from this report.

Page 6

3. Assessments 
Equality Impact Assessment 
3.1 This report has been considered under the Corporate Equalities Impact 
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. No further action is required as it does not qualify as a PPS as
defined by the Act and is therefore exempt. 
Sustainability   
3.3 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• in the way best calculated to delivery of the Act’s emissions reduction
targets;
• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable. 
3.4 The information contained within this report has been considered under the
Act. However, no action is required as the act does not apply to the matters
presented in this report. 
Legal and Governance 
3.5      Head of Legal and Governance was consulted on this report. 
Risk 
3.6 Not applicable. 
4. Consultation 
Internal 
4.1 Heads of Service and senior managers from Communities have been
consulted on the content of this report.

Page 7

External 
4.2 All current residents at Bobbin Mills have been consulted on this proposal.
The Tenant Committee Report Panel was consulted on this report. They
commented that they were encouraged that after some challenges, the
transfer is to take place. 
5. Communication 
5.1 None. 
2. BACKGROUND PAPERS 
2.1  Double Dykes, Gypsy/Traveller site, to the HRA (Report No. 22/63 refers).