Democracy Spraffa

Agenda Document Pack - Housing and Social Wellbeing Committee - 25/03/2026

Perth and Kinross Council · 25 March 2026
Back to Housing and Social Wellbeing Committee — 25 March 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Ambition | Compassion | Integrity
Our vision is for
a Perth and Kinross where everyone can live life
well, free from poverty and inequality
Council Building
2 High Street
Perth
PH1 5PH
18/03/2026
A hybrid meeting of the Housing and Social Wellbeing Committee will be held in
the Council Chamber on Wednesday, 25 March 2026 at 09:30.
If you have any queries please contact Democratic Services on (01738) 475000 or
email Committee@pkc.gov.uk.
THOMAS GLEN
Chief Executive
Those attending the meeting are requested to ensure that all notifications are silent
on their device and other devices are in silent mode.
Please note that the meeting will be broadcast online and recorded.  The recording
will be publicly available on the Council’s website following the meeting.
Members:
Councillor Tom McEwan  (Convener)
Councillor Sheila McCole  (Vice-Convener)
Bailie Mike Williamson  (Vice-Convener)
Bailie Chris Ahern
Councillor Peter Barrett
Councillor Bob Brawn
Bailie Rhona Brock
Councillor Angus Forbes
Councillor Ian James
Councillor Iain MacPherson
Councillor Carol Mair
Bailie Claire McLaren
Councillor Frank Smith
Councillor Colin Stewart
Councillor Jack Welch
Page 1 of 48

Page 2

Page 2 of 48

Page 3

Housing and Social Wellbeing Committee
Wednesday, 25 March 2026
Agenda
Members are reminded of their obligation to declare any financial or non-
financial interest which they may have in any item on this agenda in
accordance with the councillors’ code of conduct.
1 WELCOME AND APOLOGIES
2 DECLARATIONS OF INTEREST
3 MINUTE OF MEETING OF HOUSING AND SOCIAL WELLBEING
COMMITTEE OF 21 JANUARY 2026 FOR APPROVAL
(copy herewith)
5 - 8
4 OUTSTANDING BUSINESS STATEMENT
(copy herewith 26/73)
9 - 12
5 ENHANCED COMMUNITY POLICING MODEL
Presentation by Police Scotland
6 UK TOWN OF CULTURE 2028
Report by Strategic Lead - Economy, Development and Planning
(copy herewith 26/74)
13 - 24
7 MID-MARKET RENT PROPOSAL
Joint Report by Strategic Lead - Housing and Communities and
Strategic Lead - Economy, Development and Planning (copy
herewith 26/75)
25 - 48
Page 3 of 48

Page 4

Page 4 of 48

Page 5

DRAFT
HOUSING AND SOCIAL WELLBEING COMMITTEE
Minute of hybrid meeting of the Housing and Social Wellbeing Committee held in the
Council Chambers, 2 High Street, Perth, on 21 January 2026 at 1:00pm.
Present: Bailies R Brock, C McLaren and M Williamson, Councillors P Barrett,
B Brawn, J Duff (substituting for Bailie C Ahern), A Forbes, K Harvey (substituting for
Councillor J Welch), I James, I MacPherson, C Mair, S McCole, T McEwan, F Smith
and C Stewart.
In Attendance: C Mailer, Depute Chief Executive; E Ritchie, Strategic Lead –
Housing and Communities; A Singh Strategic Lead – Children, Families and Justice;
E Lindsay, N Rogerson, R Ross (all Children, Families and Justice); S Coyle
(Finance and Business Support); N Lennon, J McColl (both Housing and
Communities); S Hendry, J Guild, A Brown and M Pasternak (all Legal and
Governance).
Also in Attendance: G Binnie, Independent Chair of the Child Protection Committee;
L Palmer (Tenant’s Committee Report Panel).
Apologies: Bailies C Ahern and Councillor J Welch.
Councillor T McEwan, Convener, Presiding.
Councillor McEwan led on Items 1 – 4 and 8, with Bailie M Williamson leading on
Items 5 and 6 and Councillor McCole leading on Item 7.
1. Welcome and Apologies
Councillor T McEwan welcomed everyone to the meeting. Apologies were
noted as above.
2. Declarations of Interest
There were no Declaration of Interests in terms of the Councillors’ Code of
Conduct.
3. Minute of Previous Meeting
The minute of the meeting of the Housing and Social Wellbeing Committee of
26 November 2025 was submitted and approved as a correct record.
4. Outstanding Business Statement
The Outstanding Business Statement was noted, and it was agreed to remove
the completed actions.
3
Page 5 of 48

Page 6

DRAFT
5. Justice Update Report 2024/25
There was submitted a report by Strategic Lead – Children, Families and
Justice (26/18) providing the Housing and Social Wellbeing Committee with an
update on the work of council services and partners to meet local and national
outcomes for Community Justice for the period 1 April 2024 to 31 March 2025.
In introducing the report, E Lindsay, Community Justice Improvement Team
Leader, provided a slide-based presentation and answered Members’ questions
thereon.
Resolved:
(i) The approach being undertaken by PKC teams in respect of the Partnership,
be noted.
(ii) The contents of the report, be endorsed.
(iii) It be requested the Strategic Lead for Children, Families and Justice bring
forward an annual report detailing the PKC contribution to the Partnership.
6. Community Payback Order Annual Report 2024-25
There was submitted a report by Strategic Lead – Children, Families and
Justice (26/19) introducing the Perth and Kinross CPO Annual Report for 2024-25 in
compliance with that requirement and was submitted to CJS on 28 October 2025
and tabled at the Perth and Kinross Community Justice and Safety Partnership on
12 December 2025 for noting.
In introducing the report, N Rogerson, Community Safety Service Manager,
provided a slide-based presentation and answered Members’ questions thereon.
Resolved:
(i) Assurance be taken about the work being undertaken by the Community
Justice Social Work (CJSW) team and the Unpaid Work (UPW) teams in
respect of CPOs in Perth and Kinross.
(ii) The contents of the report, be endorsed.
(iii) It be requested, the Strategic Lead for Children, Families and Justice bring
forward an annual report regarding the activity and performance of CPOs.
7. Tayside MAPPA Annual Report 2024/25
There was submitted a report by Strategic Lead – Children, Families and
Justice (26/20) sharing the Tayside Multi-Agency Public Protection Arrangements
(MAPPA) Annual Report for 2024 - 2025 (Appendix 1). The report was approved by
the Tayside Strategic Oversight Group (SOG) on 21 October 2025 and subsequently
published by the Scottish Government on 27 November 2025. Furthermore, the
report was tabled at the Perth and Kinross Community Justice Safety Partnership on
12 December 2025 for noting.
Resolved:
(i) Assurance be taken about the work being undertaken in respect of the
MAPPA in Tayside, and specifically, in Perth and Kinross.
Page 6 of 48

Page 7

DRAFT
(ii) The contents of this report, be endorsed.
(iii) It be requested that the Strategic Lead for Children, Families and Justice bring
back future annual reports to this committee.
(There followed a recess and the meeting reconvened at 3.17pm)
8. Housing Revenue Account (HRA) Strategic Financial Plan incorporating
the 5 Year Capital Investment Programme and Rent Strategy to 2030/31,
Reserves Strategy and other Housing Charges for 2026/27
There was submitted a report by Strategic Lead – Housing and Communities
and Chief Finance Officer (26/21) (1) seeking approval of the proposed Housing
Revenue Account (HRA) budget for five years from 2026/27 to 2030/31, (2) outlining
recommended increases to rents for houses and other HRA property service
charges, and an appropriate level of reserves, it is also (3) seeking approval of the
proposed budget for the next five years of the Capital Investment Programme,
totalling £81.1 million from 2026/27 to 2030/31.
Resolved:
(i) It be noted that the HRA 30-year Business Plan has been updated to reflect
and confirm the affordability of the proposals;
(ii) The Housing Revenue Account Budget for 2026/27 and provisional budgets
for financial years 2027/28 to 2030/31 as set out in Appendix 1, be approved;
(iii) The proposed Housing Revenue Account Capital Investment Programme for
2026/27 to 2030/31 as set out in Appendix 3, be approved.
(iv) The Rent Strategy for 2026/27 and a provisional Rent Strategy for the
following 4 years to 2030/31 as stated in Section 8, be approved;
(v) The rent increase of 6.5% in line with option 1, for the year commencing 6
April 2026 for all Council houses, be approved. This will mean an average
weekly rent increase of £5.49 per week, resulting in an average weekly rent of
£90.01 per week based on 52 weeks.
(vi) The rent increase of 6.5% for the year commencing 6 April 2026, be approved
for:
• all lock-ups
• all garage sites
• dispersed tenancies owned by the HRA
• Greyfriars Hostel.
(vii) The Housing Revenue Account Reserves Strategy proposed in Section 9, be
approved.
(viii) The final movement in the Housing Revenue Account in 2025/26 is
transferred to an earmarked Reserve (HRA) as proposed in Section 9.10, be
approved.
(ix) The proposal to set Housing service charges from 6 April 2026 as stated in
Section 12, be approved.
(x) The revised level of all housing related charges as detailed in Appendix 5, be
endorsed and approved where necessary
(xi) The progress made to date in delivering and maintaining the Scottish Housing
Quality Standard (SHQS) for improving and managing the housing stock as
set out in Section 6 and the related Business Cases, be endorsed.
Page 7 of 48

Page 8

Page 8 of 48

Page 9

HOUSING AND SOCIAL WELLBEING
OUTSTANDING BUSINESS STATEMENT (OBS)
(Report No. 26/73)
Please note that this statement sets out outstanding decisions of Council / this committee / sub-committee along with an update and estimated
completion date.  Actions which are overdue are shaded for ease of reference.  Where an update reflects that an action is complete then
agreement will be sought to its removal from the OBS.
No Date / Minute
Reference /
Report Number
Subject Title Outstanding
Action
Update Lead Officer
/Service
Action
Due/completed
Action
Expected
50. 8 October 2025 Item 6 – SFRS
Thematic Update
– Wildfire Strategy
Consideration to
be given to
implementation
of guidance in
relation to use of
concrete pipes in
high-risk wildfire
areas.
Further consideration and
discussion with
stakeholders to take
place to allow informed
consideration of
appropriate guidance. 
This will come through
the review of the Local
Development Plan.
N Sworowski /
Economy,
Development
and Planning
COMPLETE 25 March
2026
53. 8 October 2025 Item 7 – Strategic
Housing
Investment Plan
Results of
keyworker need
survey to be
shared and
incorporated into
housing
objectives.
Survey to be shared once
follow up scrutiny of
results is complete.
Consideration will be
given to including the
survey results into the
new and Housing Need
and Demand
Assessment (HNDA) that
is currently underway and
renewed every 5 years.
N Sworowski /
Economy,
Development
and Planning
ONGOING Late 2026
4
Page 9 of 48

Page 10

No Date / Minute
Reference /
Report Number
Subject Title Outstanding
Action
Update Lead Officer
/Service
Action
Due/completed
Action
Expected
Update March 26 –
Survey response rate
was low and advice has
been sought from HSCP
about whether it’s in line
with what was expected
or if an extension of the
survey would be
possible.
The responses that have
been received will be fed
into the Housing Needs
and Demand
Assessment that is
currently underway that
supports the Local
Development Plan and
the Local Housing
Strategy. The results of
this assessment will be
fed into both documents
and results can be
shared once finalised.
56. 21 January 2026 Item 6 –
Community
Payback Order
Annual Report
2024 – 25
Actual figures in
in relation to
Chart 5:
Reasons for
CPO
Terminations to
be provided
along side
percentages.
Circulated to Elected
Members via email
16/03/2026.
A Singh, N
Rogerson /
Children,
Families and
Justice
COMPLETE 25 March
2026
Page 10 of 48

Page 11

No Date / Minute
Reference /
Report Number
Subject Title Outstanding
Action
Update Lead Officer
/Service
Action
Due/completed
Action
Expected
57. 21 January 2026 Item 6 –
Community
Payback Order
Annual Report
2024 – 25
Further
information to be
provided in
relation to
lessons learned,
outcomes and
improvements
from Mental
Health
Treatment Case
Study on
“Andrew”.
Circulated to Elected
Members via email
16/03/2026.
A Singh, N
Rogerson /
Children,
Families and
Justice
COMPLETE 25 March
2026
58. 21 January 2026 Item 6 –
Community
Payback Order
Annual Report
2024 – 25
Further information
to be provided on
Caledonia Project
funding,
particularly in
relation to figures
and availability for
P&K.
Circulated to Elected
Members via email
16/03/2026.
A Singh, N
Rogerson /
Children,
Families and
Justice
COMPLETE 25 March
2026
59. 21 January 2026 Item 8 – Housing
Revenue Account
Strategic Financial
Plan
HRA affordability
tracker graph to be
provided.
Circulated to Elected
Members via email
26/01/2026.
S Coyle /
Finance and
Business
Support
COMPLETE 25 March
2026
Page 11 of 48

Page 12

Page 12 of 48

Page 13

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality
___________________________________________________________________
Committee: Housing & Social Wellbeing Committee
Date of Meeting: 25 March 2026
Report Title: UK Town of Culture 2028
Report Number: 26/74
Report Author: Julie Barnsley, Economic Development Officer
Organisational Lead: Serge Merone, Strategic Lead – Economy,
Development & Planning
___________________________________________________________________
1. Purpose
1.1 The purpose of this Report is to provide an update on the UK Town of Culture
2028 competition which is being run by the UK Department of Culture, Media
& Sport (DCMS). The Report seeks Committee’s approval to support the
expressions of interest to the competition from Crieff (via Creative Crieff) and
Pitlochry (via Pitlochry Community Action Trust).
1.2 Sections
1. Purpose
2. Recommendation(s)
3. Background
4. Links with Culture Strategy and wider cultural ambitions
5. Expressions of Interest
6. Shortlisting
7. Timescale
8. Conclusion
9. Impact Value Assessment
10. Appendices
2. Recommendations
It is recommended that the Housing & Social Wellbeing Committee:
2.1 Note that Officers have been informed by Creative Crieff and the Pitlochry
Community Action Trust of their intention to submit Expressions of Interest to
the UK Town of Culture 2028 competition for Crieff and Pitlochry respectively,
6
Page 13 of 48

Page 14

and that Officers are working collaboratively with both organisations to support
the development of their submissions.
2.2 Agree that Perth and Kinross Council will support the submission of both
Expressions of interest and provide Officers’ assistance as required.
2.3 Ask Strategic Lead – Economy, Development and Planning to report back to a
future meeting of the Committee or the Council.
3. Background
3.1 The UK Town of Culture 2028 is a new competition which was announced by
the Department of Culture, Media and Sport (DCMS) on 14 January 2026.  It
is a UK-wide programme, developed in collaboration with the devolved
governments in Northern Ireland, Scotland and Wales. The UK Town of
Culture is intended to complement and build on the success of the UK City of
Culture.  
3.2 The competition states that its aims are to celebrate the significant
contributions of towns to the UK’s national story, with a focus on building
social cohesiveness where communities feel proud of their place and
empowered to celebrate it. Furthermore, the UK Town of Culture provides an
opportunity for towns and communities to use culture and creativity to tell their
story.
3.3 The competition is intended to drive local economic growth and opportunity,
bring local investment, create a lasting sense of pride, and open doors to the
arts for everyone.
3.4 The competition is open to small, medium and large towns, with the winner
delivering a vibrant cultural programme in 2028 which showcases the town’s
story and visions.  Bids can also be made by groups of places where these
places share a common story and common geography.
3.5 Three finalists - one small, one medium, one large town - will be chosen. The
winning town will be awarded £3 million to deliver a cultural programme in
2028 with a duration of around six months. Additionally, the two finalists from
their category will receive £250,000 each to deliver elements of their bid.
Category Population size
Small Town Under 20,000
Medium Town 20,000-75,000
Large Town Over 75,000
The DCMS is using the Office of National Statistics definitions for towns based on population
size.
3.6 The judging panel, led by the television producer Sir Phil Redmond, will
decide which category bids fall within.  The names of the full judging panel will
be announced in due course.
Page 14 of 48

Page 15

4. Links with Culture Strategy and wider cultural ambitions
4.1 Supporting local towns to bid for UK Town of Culture 2028 aligns directly with
the Perth and Kinross Culture Strategy 2023–2028 approved by this
Committee, which prioritises widening access to culture, strengthening
placemaking, and supporting creative communities across all localities. The
UK Town of Culture’s focus on local storytelling, inclusive participation, and
partnership-led cultural delivery reflects the Culture Strategy’s strategic
pledges and offers an opportunity to enhance cultural engagement and
visibility across the region.
4.2 This activity complements Perth’s status as the UK’s first and only UNESCO
City of Craft and Folk Art, reinforcing commitments to nurturing local makers,
expanding creative networks, and embedding craft and creativity within
sustainable community development.
4.3 Collectively, these UK Town of Culture bids will strengthen the cultural identity
of Perth and Kinross and support our ambition to grow a vibrant, inclusive and
internationally recognised cultural offer.
5. Expressions of Interest (deadline: 31 March 2026)
5.1 The invitation to submit Expressions of Interest was opened by the DCMS on
14 January 2026 (Appendix 1). This part of the process will close on 31 March
2026. 
5.2 Bids must be made by a partnership representing the relevant town - this
partnership must include the local authority. The partnership can be newly
formed or well-established.
5.3 To help manage partnerships at a local level, Perth and Kinross Council
launched an Interest Form for towns to indicate their intentions to apply. The
deadline for making intentions known was 13 February 2026.
5.4 Creative Crieff and Pitlochry Community Action Trust both responded to
the Perth and Kinross Council Interest Form and are both developing their UK
Town of Culture Expressions of Interest. Officers are supporting both
organisations with their submissions.
5.5 At the time of writing this report, the bidding towns are developing the content
of their submissions.  We will be able to share further information once these
have been finalised, with the deadline for submissions to the DCMS being 31
March 2026.
5.6 A single organisation within the partnership must be nominated as ‘Lead’ and
as such must be a formal, constituted and accountable organisation. This can
be the local authority, or it can be another organisation within the partnership.
5.7 The partnership should demonstrate a commitment to work collaboratively
and could include a range of community and cross-sector partners.
Page 15 of 48

Page 16

5.8 The partnership should demonstrate commitment to actively including local
communities in decision-making and supporting them to directly shape what
happens in their area. It is highlighted that a commitment to community
collaboration should be demonstrated at all stages of the competition.
5.9 Bids will be judged on three main criteria:
 Story – the unique story of the town.
 Culture for everyone – how the town will design a cultural programme for
all.
 Making it happen - how the town will then deliver a successful
programme.
6. Shortlisting
6.1 Shortlisted towns will be announced in Spring 2026.
6.2 DCMS has advised that in the event of a high number of applications, an
initial sift will take place on the first criterion only i.e. ‘Story – the unique story
of the town’.
6.3 Shortlisted towns will each receive £60,000 to support them with developing
and strengthening their full application.
6.4 The panel will visit the shortlisted towns, who will be invited to present to the
panel and engage in detailed discussions about their plans. 
6.5 The panel will assess the full applications and presentations against the
competition criteria, including any outcomes of public engagement and
communications.
6.6 The panel will submit their recommendations for the finalists and overall
winner of UK Town of Culture 2028 to the Secretary of State for DCMS, who
will make the final decision. DCMS aims to announce the UK Town of Culture
2028 winners in early 2027
7. Timescale
Milestones Dates
Expressions of Interest (EOI) Opened: 14 January 2026
Deadline: 31 March 2026
Shortlisted places announced Spring 2026
Full application period Spring 2026 – Autumn 2026
Finalists and winners announced Early 2027
Delivery period 2028
Page 16 of 48

Page 17

8. Conclusion
8.1 Applying for the UK Town of Culture 2028 title gives our towns a powerful
opportunity to articulate their vision and work collaboratively with partners and
communities to shape and celebrate their story.
8.2 Through the development of a cultural programme, these partnerships will be
strengthened as they co-create activities that address local challenges and
make culture accessible to everyone.
8.3 This process encourages communities to express pride in their town, using
creativity to showcase what makes their place unique. By putting forward a
strong, inclusive programme of cultural events, towns can demonstrate
meaningful collaboration and place themselves firmly on the map as centres
of culture.
9. Impact and Value Assessment
9.1 This report has been classified as being an operational report and as such
does not require a full Impact and Value Assessment.
10. Appendices
10.1 Appendix 1 - Expression of Interest Form
Page 17 of 48

Page 18

Page 18 of 48

Page 19

Appendix 1
UK Town of Culture 2028 Competition
Expression of Interest (EOI)
Thank you for your interest in the UK Town of Culture 2028.
Please ensure you have read the “UK Town of Culture 2028 Expression of Interest:
Guidance for bidders” document before applying. All EOIs must be submitted using this
standard template.
The form comprises four sections which each require a statement response. You are
provided with a series of prompts to use as a guide. You do not need to answer each prompt
individually but your responses should address all prompts. The prompts draw from the
competition criteria and bidding places should refer back to the criteria when completing the
form to show the potential of their programme to make a contribution to the aims of the UK
Town of Culture programme.
The form has set formatting (e.g., font size and line spacing) which should be adhered to.
Please note that the EOI form is strictly word limited and we do not expect at this stage
detailed economic data, research or in depth fundraising or delivery plans. Responses
should also only include text.
The application deadline is 31 March 2026. Applications received after this date will not be
considered. If a large number of applications are received, an initial sift will be
conducted on the section, 'Section 2: Your Story', only.
Contact: uktownofculture2028-competition@dcms.gov.uk
6
Page 19 of 48

Page 20

SECTION 1: BID INFORMATION
In this section, we ask for information relating to your bidding team and place. The
information will not be scored but will be used to confirm your eligibility.
1.1 Contact Information
Please provide contact information for the single point of contact for your bidding team.
Name, Position, Team / Organisation, Telephone Number, Email Address.
1.2 The Bidder
Please provide information for the bidder. With reference to the definitions of the
Accountable Body and Delivery Body in “UK Town of Culture 2028 Expression of Interest:
Guidance for bidders”. You should include information on who the lead bidder is and who
the key partners are.
1.3 The Geographical Area
Please specify the geographical area that you are bidding for, with reference to the
relevant geographical boundary designations. You may want to note the town categories
set out in the “UK Town of Culture 2028 Expression of Interest: Guidance for bidders”. We
will use your geographical area’s population size to categorise your bid.
Page 20 of 48

Page 21

SECTION 2: YOUR STORY
In this section, we want to understand the unique story and culture of your town. [Maximum
400 words for each section]
2.1 Vision
Please use the following prompts to guide your response:
● What is the story of your town (e.g., places and landscapes, people, communities,
culture and heritage) and what is special about it (e.g., including, how it has
contributed to a local identity - and, if relevant, how it has contributed to the
national story)?
● How will your programme celebrate the story of your town, and what themes will be
explored in your programme?
● How will your programme help to build knowledge of your town (e.g., improving,
celebrating, raising the profile)?
2.2 Local Needs
Please use the following prompts to guide your response:
● What local challenges and issues does your town face that your bid can help to
address? What priorities, needs, groups and demographics will your programme
target and why?
● How does your bid align with any other local and / or regional plans to tackle local
needs?
2.3 Empowerment
Please use the following prompts to guide your response:
● How have you developed the ideas within this bid? To what extent have you
already consulted your local community and community groups (i.e., residents,
businesses, institutions, creative providers, and cultural organisations) on your
interest in UK Town of Culture?
● How will your local community and community groups be involved in developing
and delivering the full application, programme and its legacy? How will you hold
yourself accountable to community groups and members when making decisions
about the programme?
Page 21 of 48

Page 22

SECTION 3: CULTURE FOR EVERYONE
In this section, we want to understand how you will design a cultural programme for all which
will provide visible, accessible culture that boosts the profile of your town. [Maximum 400
words for each section]
3.1 Quality and Innovation
Please use the following prompts to guide your response:
● What is your cultural and heritage infrastructure, and how will you use it and build
upon them in your programme? If your infrastructure is more limited, how could you
leverage UK Town of Culture to develop your infrastructure on a permanent or
temporary basis?
● What type of activities will your programme deliver, and how will they work
together? Please refer to proposed lead artists / creatives, if they are known. You
may refer to creating and / or promoting existing events that could become a
returning event using the leverage generated by UK Town of Culture investment
3.2 Opportunity
Please use the following prompts to guide your response:
● How will you ensure the initiatives and opportunities (e.g., learning and skills-
building, career awareness, bringing different communities together) you are
planning are genuinely aligned with your community's needs and interests,
especially for younger members of the community?
● What social and community impacts will these help you to achieve in your area,
and why are these important to your town?
3.3 Accessible
Please use the following prompts to guide your response:
● How will you embed accessibility across the design and content of your
programme?
● How would you aim to reach the widest possible audience?
3.4 Communication
Please use the following prompts to guide your response:
● How will you build a communication plan that utilises a breadth of media formats
and reaches different types of audiences?
Page 22 of 48

Page 23

SECTION 4: MAKING IT HAPPEN
In this section, we want to understand how you will deliver a successful programme.
[Maximum 400 words for each section]
4.1 Partnerships
Please use the following prompts to guide your response:
● How will you secure and work with additional external partners (e.g., artists and
creatives, cultural and heritage organisations, funders, institutions, businesses,
voluntary sector and civic society partners, and residents) to deliver the
programme?
● How will you ensure your partners are representative of your town population?
4.2 Programme Management
Please use the following prompts to guide your response:
● How will the programme be managed throughout the year, including leadership
structure and delivery model?
● How will you provide clear roles and responsibilities, and ensure the team has the
skills and capacity to deliver?
● What are the key risks associated with your proposed programme (i.e., risk,
mitigating action, RAG rating)?
4.3 Financial Management
Please use the following prompts to guide your response:
● If shortlisted, how would you use a £60,000 grant to strengthen your full
application?
● How much do you expect it will cost to deliver your programme?
● How much additional funding will you need to raise to deliver the programme, and
where will you get that additional funding (e.g., existing / reallocated budgets,
income from charitable trusts and foundations, income from public funding bodies,
business investment / sponsorship, crowdfunding, cultural partnership cash
contributions / joint funding applications, in-kind support)?
4.4 Monitoring, Evaluation and Legacy
Please use the following prompts to guide your response:
● What outcomes of your programme can be monitored and evaluated? Please refer
to outcomes referenced throughout your bid, including those referenced in "Local
Needs" and "Opportunity".
● How are you currently monitoring the impact of any culture and heritage
programme(s) and how could these methods be adapted and used to evaluate UK
Town of Culture?
● What baseline information is available to help assess the impact of your
programme?
Page 23 of 48

Page 24

Page 24 of 48

Page 25

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality
___________________________________________________________________
Committee or Board: Housing and Social Wellbeing
Date of Meeting: 25 March 2026
Report Title: Mid-Market Rent Proposal
Report Number: 26/75
Report Author: James Ross, Team Leader, Housing Strategy,
Economy, Development and Planning
Organisational Lead: Joint report by Elaine Ritchie – Strategic Lead –
Housing and Communities / Serge Merone – Strategic
Lead – Economy, Development and Planning
___________________________________________________________________
1. Purpose
1.1 The purpose of this report is to seek approval of Mid-Market Rent as an
additional affordable housing model for the Council. In addition, to the extent it
is within the Committee’s remit to do so, the report seeks approval of a
recommendation to establish a Limited Liability Partnership (LLP) to enable
the Council to directly deliver Mid-Market Rent, beginning with an initial
tranche of 13 new homes at Westfields, Rattray.
1.2 Sections
1. Purpose
2. Recommendations
3. Background/Context
4. Main Issues
5. Proposals
6. Conclusion
7. Impact Value Assessment
8. Appendices
2. Recommendations
It is recommended that Housing and Social Wellbeing Committee:
2.1 Agrees that Mid-Market Rent (MMR) is adopted as an affordable housing
model for the Council, delivered through a Limited Liability Partnership (LLP).
7
Page 25 of 48

Page 26

2.2 Notes the proposal of the Strategic Lead – Economy, Development and
Planning, in consultation with the Strategic Lead – Legal and Governance, to
prepare a further report to the Council setting out the detail of the proposal for
approval at a future meeting.
2.3 Authorises the Strategic Lead – Economy, Development and Planning in
consultation with the Strategic Lead – Finance and Business Support to
submit to full Council a proposal to borrow £1.38m from the general fund and
then lend this to the LLP to acquire 13 new build affordable homes at
Westfields, Rattray, subject to satisfactory due diligence and acceptable
security arrangements.
2.4 Requires the Strategic Lead – Economy, Development and Planning to report
on the progress to Housing and Social Wellbeing Committee at a future
meeting.
3. Background/Context
3.1 Mid-market rent (MMR) is a type of affordable housing aimed at households
on low to moderate incomes who may struggle to access suitable rented
accommodation. MMR homes are let under a Private Residential Tenancy
(not a social tenancy), but rent levels are set at or below Local Housing
Allowance (LHA) rates to ensure they remain more affordable than typical
private rents. In practice, MMR acts as a tenure that bridges the gap between
social rent and private rent. Applicants must meet specific eligibility criteria to
be offered an MMR tenancy – criteria that can be decided by the landlord to
meet local housing need.
3.2 MMR is recognised nationally as an important element of affordable housing
delivery. Housing to 2040, Scotland’s long term housing strategy, includes a
commitment to deliver 110,000 new affordable homes by 2032. Of these, 70%
are to be for social rent, with the remaining 30% delivered through low-cost
home ownership and MMR. This report’s proposal contributes to the 30%
non-social rent share via MMR.
3.3 The Perth and Kinross Local Housing Strategy (LHS) 2022-2027 sets out the
strategic housing priorities for the area. The LHS includes a target to deliver
210 new supply affordable homes per year, with 70% for social rent and the
remaining 30% delivered through alternative tenures such as MMR and low-
cost home ownership, reflecting national policy direction.
3.4 Within Perth and Kinross, three Registered Social Landlords (RSLs) currently
provide MMR properties, with a fourth expected to deliver homes over the
next five years.
 Kingdom Housing Association manages 124 MMR properties across
Abernethy, Perth, Scone, Blairgowrie, and Crieff.
 Hillcrest Housing Association manages 87 MMR properties across
Perth and Blairgowrie.
 LAR Housing Trust manages 16 MMR properties in Blairgowrie.
Page 26 of 48

Page 27

3.5 In addition, the current Strategic Housing Investment Plan (SHIP), includes
Places for People (PfP) to deliver new MMR properties in Scone, which will
add to the existing total of 227 properties.
4. Main Issues
4.1 In Perth and Kinross, demand for MMR continues to grow, particularly in
areas with high housing pressure, above-average rents, and limited access to
low-cost home ownership options. Current supply through partner RSLs is not
keeping pace with need. 
4.2 The Council must therefore adopt a more active and flexible delivery
approach if MMR outputs are to meet the expectations outlined in the LHS
and Strategic Housing Investment Plan (SHIP).
4.3 The Council cannot directly deliver MMR because a Private Residential
Tenancy cannot be issued by a Local Authority and so currently, the delivery
of MMR through the Strategic Housing Investment Plan relies entirely on
RSLs that operate MMR, via their subsidiaries.
4.4 Benefits of the Council delivering MMR are that it:
 Provides an affordable option for those that are unlikely to be allocated a
social tenancy. Many of whom approach our housing options service for
help. Thereby reducing pressures on services and providing a viable
alternative in areas with high private rents.
 Delivers greater flexibility and choice for those looking for their first, or
last, home. Households can be offered a home with 1 bedroom more
than social housing allocations would allow.
 Offers greater security of tenure than compared to the private rented
sector. As an established landlord with a strong track record in property
management and high-quality repairs, the Council offers tenants greater
stability and reassurance than individual private landlords.
5. Proposals
5.1 The Outline Business Case sets out three potential options available to the
Council to deliver MMR, a summarised version of this is provided as appendix
1. Following detailed appraisal, Option 3 has been identified as the preferred
option. The three options considered are:
- Option 1: Do Minimum / Existing Framework
- Option 2: Leasing Arrangement with an RSL
- Option 3: Establish a Limited Liability Partnership (LLP)
5.2 The development of the Outline Business Case has been informed by
contributions from Housing Strategy, Housing, Legal Services, Finance, and
procurement. In addition, external legal support has been procured from
Burness Paul to provide specialist advice.
Page 27 of 48

Page 28

Officers have also engaged with Edinburgh, Fife and Stirling Councils to learn
from their experience of delivering MMR, as well as partner RSLs referenced
in the report. Support has also been provided by the Scottish Futures Trust,
who have supplied guidance and template documentation.
5.3 A suitable site has been identified for the first phase of MMR delivery.
Construction is due to commence in 2026/27 at Westfields, Rattray, a location
already approved within the Strategic Housing Investment Plan (SHIP).
5.4 Subject to Committee’s approval, it is anticipated that establishing the LLP will
take approximately six months and external business adviser, Burness Paul,
will support the full set-up process, ensuring all legal and governance
requirements are met including subsidy control, conflict management,
insurance, Health and Safety compliance and lettings/management
arrangements. It would be important to ensure that allocations/eligibility avoid
indirect discrimination and are line with Council’s priorities. A budget has also
been set aside to procure external financial advice, ensuring compliance with
all relevant financial regulations and the implementation of financial controls.
5.5 A financial appraisal has been completed for the initial tranche of 13 new
homes, which will form the LLP’s first stock. The current appraisal confirms
that £1.38m will be required, alongside Scottish Government grant funding
(£1,213,864), commuted sums (£220,000), and Council Tax second / empty
homes income (£260,000), to support the acquisition. Further sensitivity
analysis will be carried out. This capital contribution would be paid on
completion of the new homes and repaid by the LLP to the Council over a 30-
year period. Once the initial investment has been repaid, any surplus
generated will be reinvested in delivering additional MMR properties through
the LLP.
5.6 Initial discussions have taken place with Scottish Futures Trust regarding the
potential role of its investment subsidiary Scottish Futures Trust Investments
Limited as the LLP’s second member. Further consideration of alternative
second-member options will continue subject to Committee’s approval, with a
final partner to be confirmed prior to the LLP being formally established. The
selection of the second partner will be guided by criteria set by the Council
such as public purpose alignment, governance capacity or no dividend
leakage conflicting with affordability.
6. Conclusion
6.1 There is a clear and growing need for Mid-Market Rent (MMR) homes in Perth
and Kinross, particularly for households who are unable to access social
housing yet are priced out of the private rented sector. Current delivery
arrangements are not sufficient to meet this demand, particularly in
high-pressure areas.
6.2 The Outline Business Case demonstrates that establishing a Limited Liability
Partnership (LLP) provides the most effective, flexible and sustainable
mechanism for the Council to directly deliver MMR, while remaining compliant
Page 28 of 48

Page 29

with legal and regulatory requirements. This approach enables the Council to
take a more active role in addressing local housing need and delivering on the
ambitions set out in the Local Housing Strategy and Strategic Housing
Investment Plan.
6.3 The proposed first phase of delivery at Westfields, Rattray will provide 13 new
MMR homes, supported by a robust financial appraisal. The required £1.38
million Council borrowing, to be on-lent to the LLP, will be fully repaid over a
30-year period, including principal and interest, ensuring the Council’s
investment is protected. Any future surplus generated by the LLP will be
reinvested to support further MMR delivery.
6.4 Approving the recommendations within this report will allow the Council to
establish a scalable and financially sustainable model for MMR delivery,
increase access to affordable housing, relieve pressure on housing services,
and provide greater housing choice and security for residents across Perth
and Kinross.
7. Impact and Value Assessment
Impact and Value Assessment
8. Appendices
8.1 Appendix 1: Business Case
8.2 Appendix 2: Mid-Market Rent FAQ’s
Page 29 of 48

Page 30

Page 30 of 48

Page 31

1 | O u t l i n e B u s i n e s s C a s e
Appendix 1
Summarised Business Case
FOR PROPOSED CAPITAL FUNDED PROJECT
Title: Mid-Market Rent Proposal - PKC
Executive
Sponsor:
Elaine Ritchie / Serge Merone Version:
Author: James Ross Date: 27/02/2026
7
Page 31 of 48

Page 32

2 | O u t l i n e B u s i n e s s C a s e
Executive Summary
1. Strategic Case
1.1. Project Objectives
Mid-market rent (MMR) is a type of affordable housing aimed at households on low to
moderate incomes, designed to help them access affordable rented accommodation.
Homes for MMR are let under a Private Residential Tenancy (not a social tenancy)
however rent levels should be at or below Local Housing Allowance (LHA) rates, to
ensure that they are more affordable than private rents. Broadly it can be seen as a
tenure that bridges the gap between social rent and private rent. There are criteria that
must be met to be offered an MMR tenancy.
National context
MMR is seen as an important component of the delivery of new affordable housing
nationally. Housing to 2040, Scotland’s long term national housing strategy, sets out a
target to deliver 110,000 new affordable homes by 2032, with 70% of these for social
rent, and the remaining 30% to be made up of low-cost home ownership and MMR
properties.
With the slowdown of low-cost home ownership schemes available, only 5 new shared
equity units planned within the currently agreed Strategic Housing Investment Plan
(SHIP) and the suspension, now lifted, of the Scottish Government’s Open Market
Shared Equity (OMSE) scheme, to new applicants, there has been a greater reliance
on MMR to deliver an alternative affordable tenure to social rent. The current climate
makes it increasingly challenging to deliver new low‑cost home ownership schemes.
Rising construction costs are undermining the viability of such models, as the market
value of a property must exceed the cost of building it. At the same time, high interest
rates are making mortgages less affordable for people on modest incomes. As market
values rise, properties become less suitable for inclusion in low‑cost home ownership
schemes, further limiting their feasibility
The provision of MMR can assist young people looking to enter home ownership by
providing a secure, affordable home, which enables them to save for. deposit on their
first home and so creates a stepping stone into home ownership.
MMR homes are often found in large urban areas to help those households on low to
moderate incomes that have difficulty buying their own home or renting privately but
who also would be unlikely to be allocated a social rented property. MMR properties
can also be provided in more rural areas where residents often experience similar
problems in securing housing within their community, as normally there is fewer
options.
Page 32 of 48

Page 33

3 | O u t l i n e B u s i n e s s C a s e
This tenure is broadly seen as providing a route for young people to secure housing,
often for the first time, alleviating the challenges they face navigating the housing
market with a lower income. However, the tenant profile of MMR is varied and often is
dictated by the type of housing on offer and its location, and so it should be seen as a
tenure open to all ages.
Through the affordable housing supply programme’s main grant fund, Registered
Social Landlord’s (RSLs) will deliver MMR properties via a subsidiary, and many have
substantial MMR properties as part of their stock.  Whilst Local Authorities can also
deliver MMR using Scottish Government grant, there is a need for a third party as they
are excluded from directly offering Private Residential Tenancies. There are different
approaches to how Local Authorities can deliver new supply MMR, and these are set
out in this paper.
Perth and Kinross
The Perth and Kinross Local Housing Strategy (LHS) 2022-2027 sets out the strategic
aims for housing within Perth and Kinross. This report aims to contribute to the
following actions and milestones within that strategy:
Action 1.1
Deliver PKC’s affordable housing programme of 1,050 homes over the next five years.
Milestone
 Achieve an average of 210 affordable housing completions each year
 30% other affordable tenure (315 out of total 1050 over five years – Low-Cost
Home Ownership (LCHO), MMR and Self Build).
Action 1.4
Seek opportunities to deliver a wider range of affordable housing options e.g.,
intermediate housing, LCHO and affordable self-build etc.
Milestone
 Carry out feasibility studies.
 Identify and develop partnerships to deliver wider range of affordable housing
options.
In Perth and Kinross there are three RSLs that currently operate MMR properties, with
a fourth RSL due to deliver new properties within the next 5 years. Kingdom Housing
Association has 124 MMR properties across Abernethy, Perth, Scone, Blairgowrie,
and Crieff. Hillcrest Housing Association has 87 properties across Perth and
Blairgowrie. LAR Housing Trust has 16 properties in Blairgowrie. Within the current
Strategic Housing Investment Plan, Places for People (PfP) are also programmed to
deliver MMR properties in Scone, thus adding further to the 227 existing properties.
The MMR properties by Kingdom, Hillcrest and PfP are delivered via the Strategic
Housing Investment Plan using Scottish Government grant to part fund the cost. LAR
however use a different model whereby Scottish Government loan funding has been
used rather than grant, with additionally sourced private investment to fund the cost. It
Page 33 of 48

Page 34

4 | O u t l i n e B u s i n e s s C a s e
is not known whether this loan funding will continue to be available for LAR to deliver
more homes in Perth and Kinross in that manner, though this is funding outwith the
Strategic Housing Investment Plan.
The Gannochy Trust, although not an RSL, are a charitable organisation within Perth
and Kinross with almost 300 properties that they let out below LHA rates and so also
make a valuable contribution to affordable rented accommodation in the area.
However, Kingdom, Hillcrest, and PfP are continuing to pursue further MMR
opportunities through the programme in Perth and Kinross and are being supported to
do so by PKC as part of our role as strategic housing authority. Housing Strategy will
remain in dialogue with LAR to consider any opportunities that fit in with their model.
Work is also ongoing within PKC to enable organisations to harness Rural and Islands
Housing Fund monies to assist the delivery of this tenure in rural areas also.
The broad objective of this paper is to ensure that the delivery of MMR keeps pace
with the targets set out in the Local Housing Strategy 2022-2027.
1.2. Existing Arrangements
The current framework allows for PKC to direct where MMR is delivered on sites,
where there is an identified need, though this would always be subject to a financial
appraisal by the RSL, who would deliver the product. PKC has also in the past used
commuted sums to support MMR projects where viability has been an issue, this
ensures that the projects do not falter and can be delivered in areas of strategic
importance.
PKC’s Housing Strategy Team are tasked with coordinating the Strategic Housing
Investment Plan, and it is via this document where the majority of MMR is delivered in
Perth and Kinross. Beyond this, support is provided to qualifying applicants to access
the Rural Housing Fund, where one of the potential end tenures is MMR. This is
valuable work to enable local communities to have real input into the delivery of
affordable housing local to them, but its outputs can be small, and time consuming,
and so its capacity to supplement delivery of MMR is limited.
The recently approved Strategic Housing Investment Plan sought to fund the delivery
of 1426 new supply properties with 124 of these being MMR. It was hoped that a
further 16 could be developed for low-cost home ownership, however this is proving
difficult to make viable. Unfortunately, the delivery of MMR and low-cost home
ownership homes are not keeping up with the expected targets, as these projections
indicate less than 10% being delivered against a target of 30%. Low-cost ownership
schemes are unlikely to deliver in the short term due to challenging conditions thereby
placing greater weight on the delivery of MMR. The previous 5-year delivery of MMR
also indicates that the Strategic Housing Investment Plan outputs will not increase
significantly the MMR delivery without some action.
1.3. Business Needs
Need and Demand
Page 34 of 48

Page 35

5 | O u t l i n e B u s i n e s s C a s e
Rents for MMR are capped at the LHA rate for first let, though are often slightly below
and so the need for this product tends to be in areas where private rents are higher.
LHA is the maximum rate of housing benefit a qualifying applicant can expect to
receive to cover the cost of their rent in a private tenancy, in any given market area.
For the properties proposed in this paper, the LHA rates are around 50% higher than
the rent levels set if they were PKC social housing and so should be seen as very
much a different type of tenure from social rent, albeit a recognised form of affordable
housing.
Often MMR is not deemed to be needed in areas where the LHA rates are too similar
to the market levels. Across the Perth and Kinross area, the private rents are higher
than LHA rates for all property sizes, though there is variance across the different size
of properties, as shown in Table 1 below:
Property
Size
Market
Rents
MMR
100% Difference 100%
Difference
95%
Difference
85%
Difference
1 Bedroom £452 £424 -£28 -7% -12% -25%
2 Bedroom £613 £558 -£55 -10% -16% -29%
3 Bedroom £836 £748 -£88 -12% -18% -32%
4 Bedroom £1,348 £1,247 -£102 -8% -14% -27%
Average £812 £744 -£68 -9% -15% -28%
Table 1: LHA/Market rates by property size for Perth and Kinross. 2022/23 data
The allocation of MMR, because it is different to social housing, allows for households
to apply for a property that has one bedroom more than the households needs.
Therefore, 2 or 3 beds would be a typical property size for new supply MMR and are
the house sizes where there is greatest variance between market rents and LHA
rates, indicating an alignment with need and prospective supply.
However, as table 1 also highlights, by ensuring that the rent levels are lower than the
maximum LHA rates, which would typically be the aim, the rent savings for all property
types can become substantial and would therefore allow a greater number of people
to access them.
Naturally, there are specific areas within Perth and Kinross where market rents are
higher and so places greater pressure on those seeking housing in the private sector.
Table 2 sets out where the highest average rents are and the size of property with the
highest rents.
Size 1 bed -
shared
1 bed 2 beds 3 beds 4+ bed Average
Eastern £490 £422 £604 £774 £1,406 £801
Greater Perth £437 £447 £609 £819 £1,282 £789
Highland £431 £518 £660 £923 £1,302 £850
Kinross £261 £508 £650 £873 £1,310 £835
Strathearn £456 £472 £625 £891 £1,483 £868
Comrie £446 £458 £565 £773 £1,496 £823
Page 35 of 48

Page 36

6 | O u t l i n e B u s i n e s s C a s e
Crieff £446 £458 £565 £773 £1,496 £823
North Eastern - £425 £650 £598 £1,600 £818
City Centre £431 £443 £600 £805 £1,209 £764
Perth & Kinross £441 £452 £613 £836 £1,348 £812
Table 2: Average market rents by location and property size. 2022/23 data
Whilst evidence here shows that Highland, Strathearn, and Kinross would be areas to
target delivery of MMR, it should be noted that it can be popular as a product even
when the savings households can make on rents is minimal. This is because
prospective tenants will consider aspects such as the quality of the property, the
likelihood that repairs will be attended to promptly, and the security the landlord can
offer.
MMR landlords are typically recognised organisations with a well-functioning repairs
system in place and as they are not private individuals, the risk of the property being
needed back by the landlord is diminished. Whilst the introduction of Private
Residential Tenancies meant that tenants had greater security of tenure than they did
under Short Assured Tenancies, there are still a number of grounds that a landlord
can evict a tenant under. These include, but are not limited to, the landlord wanting to
sell the property, undertake major repair, to live in the property themselves or let out to
a family member. This means that in practice, a prospective tenant will consider that
renting from a landlord with only one or two properties, comes with less security.
The locations where MMR has been delivered successfully in Perth and Kinross,
demonstrates that it is not only the areas where need is greatest that have proved
popular. All projects listed in table 3 have proved be in high demand and are
successful MMR schemes.
Site RSL Unit
Number
Year
Moyness (Hazelwood),
Blairgowrie
Kingdom HA 7 24/25
Duchlage Road, Crieff Kingdom HA 8 23/24
Broich Road, Crieff Kingdom HA 4 23/24
Earlsgate, Scone (over 55’s only) Kingdom HA 51 21/22
Glenalmond Road, Rattray Kingdom HA 6 21/22
Table 3: MMR delivery in 2020/21 - 2024/25 (5 years)
As noted earlier, MMR is not only targeted at those struggling to access good quality
private rented accommodation but also those that cannot afford to access the home
ownership market. For people living in communities where house prices are high, it is
especially difficult to enter this market with a modest income. The table below shows
the average house prices across a number of areas, and reflects the challenges faced
within Perth and Kinross in trying to access home ownership.
Page 36 of 48

Page 37

7 | O u t l i n e B u s i n e s s C a s e
Table 4:
Average house prices. 2022/23 data
Whilst the average house price can demonstrate, broadly, the challenges faced within
specific areas, it will include house prices of properties that many with modest
incomes will not be pursuing. To assess the impact of house prices on the those with
modest incomes, the lower end of the market needs to be considered.
2022/23 All
Sales
Average
Price
1st
Quartile Median
3rd
Quartile 4th Quartile
Eastern £228,176 £139,500 £219,975 £284,963 £844,626
Greater Perth £242,468 £133,390 £215,255 £315,548 £950,000
Highland £327,130 £187,000 £288,527 £432,500 £1,000,000
Kinross £305,881 £184,875 £283,000 £387,750 £800,000
Strathearn £313,241 £179,475 £270,000 £397,500 £995,000
Comrie £359,268 £202,488 £276,391 £389,250 £995,000
Crieff £286,330 £160,000 £249,450 £355,000 £865,000
North Eastern £354,616 £255,000 £280,000 £410,000 £844,626
Perth City Centre £205,533 £117,250 £187,886 £276,500 £780,000
Perth and
Kinross £274,907 £155,385 £239,500 £344,998 £1,000,000
Table 5: House price quartiles. 2022/23 data
Table 6 demonstrates how much a household would need to be earning, to purchase
a property at the lowest quartile in each area, assuming a mortgage multiplier of 3.2,
which is an affordable level. Many of the incomes listed below would be above the
maximum income an applicant for an MMR property could have and so shows how
out of reach home ownership is for many. It should also be noted. hat the more
pressured an area, the greater the constraint there will be on supply also and so even
if a household could afford a property at the lower end of the market, they are further
inhibited by a constrained supply.
Required for market
entry
LQ income
to buy
Ave income to
buy
Eastern £37,055 £60,609
Greater Perth £35,432 £64,406
Highland £49,672 £86,894
2022/23 All Sales Average Price
Scottish
Average
+ / -
Eastern £228,176.13 11,839.13
Greater Perth £242,467.80 26,130.80
Highland £327,129.88 110,792.88
Kinross £305,880.21 89,543.21
Strathearn £313,240.84 96,903.84
Comrie £359,267.96 142,930.96
Crieff £286,330.02 69,993.02
North-Eastern £354,615.54 138,278.54
Perth City Centre £205,532.71 -£10,804.29
Perth and Kinross £274,906.82
£216,337
58,569.82
Page 37 of 48

Page 38

8 | O u t l i n e B u s i n e s s C a s e
Kinross £49,107 £81,249
Strathearn £47,673 £83,205
Comrie £53,786 £95,431
Crieff £42,500 £76,056
North Eastern £67,734 £94,195
Perth City Centre £31,145 £54,595
P&K £41,274 £73,022
Table 6. Income needed to buy property. 2022/23
Furthermore, it should be noted that this reflects data from 2023/23, and it is known
that property prices and private rents have been on the rise, and so the current
situation is even more challenging for those on modest incomes than data here
shows.
Whilst traditionally MMR is seen as a tenure for young people entering the housing
market for the first time, it should not be seen as solely a tenure for the young. The
Earlsgate, Scone development has demonstrated that MMR is attractive to older
people also, if the property types are suitable and in the right area. Here, 51 properties
were delivered, managed by Kingdom Housing Association, and for over 55’s only,
with great success and high levels of demand.
Providing suitable, affordable housing for older people ensures that they are not left in
increasingly unsuitable accommodation as their physical capacity declines. This means
for those households their needs are better met and reduces the risk of reaching crisis
point and a sudden need for additional services. Beyond that, often these households
are downsizing and so it creates a chain by freeing up more housing for younger people
both in the social and private sectors.
The Scottish Governments ‘Mid-Market Rent Analysis: The Characteristics of MMR
providers and MMR tenants - December 2020 to February 2025’ shows that whilst most
tenants are below 34, there are tenants throughout the age groups living in MMR
properties.
2. Economic Case
A full Outline Business Case has been undertaken, including options appraisal, and can be
made available on request. This summarised business case, provides a headline summary
of the options available.
2.1 Options Available
Summary of Options
Option 1 – Do minimum / Business as usual
The starting point for any options appraisal is to consider whether any substantial actions
outwith current ways of working is required to achieve the results that are being looked for.
The current approach to deliver MMR in Perth and Kinross, as set out in 1.2, is to support
our partner RSLs to deliver MMR projects.
Page 38 of 48

Page 39

9 | O u t l i n e B u s i n e s s C a s e
To increase supply of MMR in Perth and Kinross within the existing framework, a re-
orientation of the prioritisation framework that is used to assess potential sites, so that
those sites delivering MMR are prioritised, could be done. This could achieve an increase
in supply with minimal intervention, though naturally still relies on partner RSL’s to deliver
them.
Furthermore, if needs can be identified, such as key workers, or over 55’s, a negotiation
can be had with our partner Housing Associations delivering these new properties to
ensure that suitable allocations can be made. If PKC contributes to a scheme by providing
additional finance via commuted sums, conditionality can be included to ensure that
appropriate groups are targeted. An example of this, was the Earlsgate, Scone,
development, which is an MMR project for over 55’s.
Option 2 – Leasing arrangement with RSL
A leasing arrangement is a type of agreement between the Local Authority and an RSL
that operates or is keen to operate in that Local Authority area. These types of
arrangements are used in neighbouring authority, Fife, where the Local Authority own 167
MMR properties that are managed by Kingdom and Ore Housing Association. PKC
currently has a leasing arrangement with Kingdom Housing Association, though this
relates to a social housing, rather than MMR, development in Perth.
This would work by PKC delivering new supply homes via its new build programme and
then leasing out the properties to a partner RSL’s subsidiary, who will then manage and
deliver those properties as MMR.
The leasing contract will set out:
 The length of the lease, how it rolls on thereafter, as well as any notification
periods.
 Delineation of repairs responsibilities. These can be divided up between planned
and reactive repairs, or a different negotiated position can be derived, right up to
full repairs responsibility being passed on as part of the lease.
 The leasing price paid by the RSL, including how yearly increases are to be
calculated.
 How allocations are to be administered and whether specific groups are to be
targeted.
The leasing price would be derived from a financial appraisal conducted by PKC, that
considers the cost of the following: 
 Construction, and other associated project costs, less any grant.
 Planned maintenance costs, if applicable.
 Ongoing costs, e.g. staff time, insurance, white goods
Once a leasing price is derived (which will vary by site, location and maybe the number of
units on offer), the prospective RSL, will then need to make their own assessment on
whether it’s a viable scheme or not, and thereafter this will inform rent levels charged to
prospective tenants. Naturally, the lower the leasing price, the more likely a below LHA
rent can be applied by the RSL.
Page 39 of 48

Page 40

10 | O u t l i n e B u s i n e s s C a s e
The properties will then be managed by the RSL until the agreement is terminated by
either party. As PKC are leasing the buildings to an RSL, it will be the RSL’s subsidiary
that is deemed to be the landlord of the tenants and not PKC and so Private Residential
Tenancies can be issued.
This approach can either be used indefinitely, or as part of a transition to option 3.
Option 3 – Establish a Limited Liability Partnership (LLP)
Establishing a PKC Limited Liability Partnership (LLP) would be the most active approach
to take forward the delivery of MMR. This is an approach taken by Local Authorities such
as Stirling and Edinburgh. Stirling Council’s LLP, Steadfast Homes, has 128 properties
and is actively seeking more opportunities. Whereas Edinburgh Council’s LLP, Edinburgh
Living, has over 500 properties as part of its portfolio and similarly is continuing to look for
opportunities.
This would typically be funded via Scottish Government grant and a loan from PKC, who
would obtain the loan from the Public Works Loan Board (‘PWLB’), which is then ‘on-lent’
to the LLP. This on lending should come from PKC’s general fund, rather than the HRA
and would need to be approved by the Scottish Government. The loan would then be paid
back by the LLP as part of its ongoing business operation.
An LLP structure requires a minimum of two members to form, and so it would be a joint
venture between PKC and a second party.
External legal advice has been sought, and provided, which confirms
1. That the LLP set up is the most appropriate legal form
2. The legislative powers that PKC can use to establish an LLP to deliver MMR
3. The type of 2nd member that the LLP can have as a prospective 2nd member.
The key legal documents required to aid the governance of this LLP would be the
following.
 A Members Agreement
This is the main document between the Local Authority and the second member
that sets out and regulates what the LLP can do.
 A Facility Agreement:
This is the document that sets out the terms of funding from the Local Authority to
the LLP.
 A Deed of Entrustment
This is the document that ties the mid-market rent LLP to deliver a service of public
economic interest (SPEI) for subsidy control purposes.
 A Management and Maintenance Agreement:
This is the document that sets out the agreement between the LLP and PKC to
deliver management and maintenance services. PKC can do this in house or
contract this out to an external party.
PKC’s control and accountability would be enshrined within the governance structure to
ensure strategic objectives are met and gives PKC complete control.
Page 40 of 48

Page 41

11 | O u t l i n e B u s i n e s s C a s e
There are two different approaches as to how the management of such properties would
be undertaken, as different models are used by the Local Authorities, highlighted here.
Option A – External Management Organisation
The first approach is to contract an external organisation to manage the properties on
behalf of the LLP and pay a fee for this arrangement.  A procurement exercise would be
needed to establish who would be best place to contract this out to.
Option B – In House Management by PKC
The second would be to pay a fee to PKC itself to manage the properties. As PKC Lets, a
team based within the Housing Options Service, operates in this area currently for private
landlords, the council is in a unique position to have existing structures in place to manage
such a proposal or make minimal adaptations to current working to enable this.
Due to the reasons outlined above the proposal here is to implement option B, and utilise
PKC Lets as the preferred party to manage the stock.
3. Commercial Case
1.1. Procurement Strategy
The 13 new build properties relate to a developer led housing scheme within the PKC
new build programme. The PKC New Build Delivery Working Group, chaired by
Property Services, has procurement representation ensuring that all procurement
requirements are adhered to.
External legal advice from Burness Paul has been sought to consider the procurement
implications of the LLP, specifically the prospective 2nd member. This advice will be
adhered to, and only suitable 2nd members are being considered.
1.2. Service Requirements
The LLP will be formed of a ‘Board of Members’ and ‘Board of Management’ structure.
The Board of Members would typically be made up of PKC senior management and
elected members, with one representative from the 2nd member. Voting rights would
be weighted in favour of PKC so it had complete control of the LLP.
The day-to-day management of the LLP is delegated to a Board of Management,
appointed by the Member organisations. This would typically comprise of six
individuals, with five from PKC and one from the second member. The Board of
Management would be made up of senior officers from PKC who oversee its
operations day to day, and so this could be representatives from Housing, Housing
(Strategy), Finance, Legal, and any other appropriate dept.
Page 41 of 48

Page 42

12 | O u t l i n e B u s i n e s s C a s e
The maintenance of the stock would be contracted out to PKC Lets, however whilst
this is a service requirement, it is one that would be paid for by the LLP in terms of a
management fee.
1.3. Charging Mechanism
The development costs will be paid for as part of the PKC new build programme.
These works will be funded by Scottish Government grant, Council Tax 2nd / Empty
Homes, commuted sums and a capital contribution. The capital contribution will be
paid by way of a loan from the general fund. A payment schedule from the LLP to
PKC general fund will be required as part of the ongoing business operations, to cover
the cost of loan and interest.
The payment from the LLP to PKC Lets will be made via the management agreement,
a draft version of which is held on file that can be shared internally on request.
A budget for external financial advice has been included within the startup costs to
ensure that the appropriate financial arrangements are in place.
1.4. Risk Transfer
The exit strategy, should the LLP default on repayment of the loan, will consist of
various options
 The HRA can purchase the properties and convert all the tenancies to social
housing, with the loan being repaid to PKC.
 A partner RSL can be offered to purchase the properties to continue as MMR,
with loan being repaid to PKC.
 The properties can be sold on open market, with grant returned to Scottish
Govt, and loan repaid to PKC.
4. Financial Case
1.1. Capital and Revenue Requirements
A separate appraisal has been conducted to establish the viability of the development.
This sets out the capital costs in greater detail; however, the headline costs are set
out below
Capital
Scottish Government Grant (Resource Planning Assumption – annual affordable
housing grant allocation) - £1,213,864
Council Tax 2nd / Empty Homes - £260,000
Commuted sums - £220,000
Prudential borrowing - £1,380,000
Page 42 of 48

Page 43

13 | O u t l i n e B u s i n e s s C a s e
Total - £3,073,864
An allowance has been provisioned in for external legal and financial advice, bringing
the total capital contribution from the general fund to be on lent and paid back over 30
years at £1,380,000
Revenue
The main revenue implication is derived from the management and maintenance of
the stock. This will be undertaken by PKC Lets, though will be done for a management
fee of £450 per property, per year, paid by the LLP to PKC Lets. This fee will increase
3% every year.
Other revenue implications relate to the staffing required to be part of the ‘Board of
Management’ and ‘Board of Members.’ It is expected that this role can be subsumed
within current business operations and relates more to the governance of the LLP.
This will need to be kept under review as more stock is added to the LLP, and future
review may consider whether payment from the LLP to PKC needs to be made for
these services also.
5. Management Case (for preferred option)
1.1. Programme and Project Management Methodology
The new build properties will be managed and delivered in accordance with the
current process for PKC new builds. They will be sold to the LLP on completion as
they cannot be held on the HRA account.
The management of the LLP is set out within the suite of legal documents that sit
alongside this outline business case. These agreements are in draft form, with
finalised versions to be created in tandem with external legal advisers.
1.2. Programme and Project Management Plans
The delivery of the properties themselves will be part of the PKC New Build
programme and will adhere to project management processes agreed. The function of
the LLP is set out in the draft legal agreements held on file.
The proposal itself seeks to deliver on our Local Housing Strategy (LHS) vision that
“Everyone in Perth and Kinross has access to the right home, in the right place, at the
right cost."
It further seeks to deliver on the specific LHS objectives, such as
 Seek opportunities to deliver a wider range of affordable housing options e.g.,
intermediate housing, LCHO and affordable self-build etc.
Page 43 of 48

Page 44

14 | O u t l i n e B u s i n e s s C a s e
 Achieve an average of 210 affordable housing completions each year
 30% being of other affordable tenure such as LCHO, MMR, Self Build
The proposed development sits within the Strategic Housing Investment Plan. This
sets out investment priorities in new supply affordable housing over a 5-year period.
1.3. Use of Specialist Advisers
External legal advice has been procured for initial advice and to assist with the suite of
legal documents needed to establish the LLP. They will support PKC Legal Services
in overseeing the establishment of the LLP.
A budget for external financial advice has also been included as part of the startup
costs, should that be required, to ensure that the necessary financial arrangements
are in place to adhere to regulatory requirements.
Page 44 of 48

Page 45

Appendix 2
Mid-Market Rent (MMR)
FAQ’s
Q. Do we really need MMR, when social housing is better and cheaper for people?
A. Yes, MMR is needed wherever rents are much higher than Local Housing Allowance
(LHA) rates, and this is clearly the case in some housing market areas in Perth and Kinross.
Beyond that, MMR has been delivered in areas where rents are not substantially higher than
LHA rates and these have still proved very popular. This shows that there is an identified
need in some parts, but demand everywhere. MMR is not a substitute for social housing, it
targets households who are unlikely to be allocated a social housing tenancy, but whom
have a housing need and often approach our service for housing options assistance.
Q. Will MMR properties reduce the number of social houses being built?
A. No, the current Local Housing Strategy states 210 new affordable homes per year are
needed. 70% of those are to be social rent with 30% of those to be either mid-market rent or
low-cost home ownership, and this target will not change. Delivering MMR helps to achieve
the 30% target and compliments the delivery of social housing, rather than replacing it.
Q. Why do PKC need to do MMR, can we not just insist that the Housing Associations do
more?
A. As Strategic Authority, we can prioritise the delivery of MMR, though this still relies on
partners doing it at the scale that we would want and in areas we would want. There are
however competing priorities in terms of type of affordable housing being delivered such as
adapted, supported etc. Having the capacity to do MMR ourselves gives us opportunities we
do not have right now. Developing large scale developments requires a mix of tenures to
create sustainable communities and so having the ability to deliver MMR will complement
our PKC programme. We can also grasp smaller, off the shelf opportunities not suited for
social housing.
Q. Fife Council have a leasing arrangement with other Housing Associations, why can we
not do the same?
A. We can, though this is not the typical approach Local Authorities take to deliver MMR
directly and does not offer us the control over management of the properties. This was a
temporary measure to enable the formation of an LLP and so proposal is to deliver MMR
directly using the mainstream approach to doing so. A leasing arrangement would not allow
for PKC Lets to manage the properties and accrue income, and so would be an opportunity
missed. A leasing arrangement and ‘business as usual’ were considered as options within
the business case. These were assessed by representatives from Legal, Finance, and
Housing Strategy and scored lower than the LLP option. This was due to the LLP providing
greater control over the delivery of MMR and the allocation of the properties thereafter.
Q. Why does it need to be an LLP?
A. We have procured external legal advice on this matter and the advice is clear that the LLP
is the appropriate type of legal entity to create to deliver MMR. PKC cannot issue Private
Residential Tenancies for ourselves and so we need a 2nd member to provide the necessary
separation from PKC to enable these tenancies to be issued. The LLP model is the one used
by other local authorities.
Q. An LLP seems complicated, how do we ensure all legal requirements are met and
adhered to?
7
Page 45 of 48

Page 46

A. External legal adviser, Burness Paul, have been procured for initial advice and for after
LLP is approved, to provide the necessary oversight ensuring that the LLP will meet all legal
requirements. They are there to support the PKC legal service, who will oversee the actual
legal arrangements. This has been budgeted for as part of start-up costs. There is also
scope for procuring external financial advice to adhere to financial regulations, should
finance team decide that is necessary.
Q. Who will the 2nd Member organisation be?
PKC have several options though first preference would be Scottish Futures Trust, though
they have their own approval process for agreeing to be a 2nd member. They have, so far,
not committed to us, though have been open to considering the proposal. This would enable
the LLP to be established and allow us the opportunity to demonstrate how the LLP works to
prospective 2nd members. Scottish Futures Trust would only agree to this in short term and
so work will need to commence early on to identify the 2nd member that this would be
thereafter. The external legal advice also specified what type of 2nd member organisation we
can partner with, this will ensure that whomever we choose, the LLP will be a legally
competent member.
Q. Who is responsible for managing the LLP?
A. PKC staff will operate the LLP as it will have no staff. PKC Lets will undertake the day-to-
day management of the stock. A fee for these lettings' agency services will be paid. Beyond
this, there will be a Lead Officer coordinating a working group of Officers from Legal,
Finance, Housing, and Property to oversee the operation of the LLP itself. This group will
report directly into the Board. Each Officer will have a different role, with varying levels of
input, within the ongoing management of the LLP, summarised below.
 Team Leader, Housing Strategy (Lead Officer) – Coordinating role ensuring that all
operational requirements are being met. Establishing working group meetings,
providing board / committee reports, and ensuring a link between the varying
departments.
 Solicitor, Legal and Democratic Services – Oversee the external legal advisors
providing advice on startup. Thereafter providing ad hoc legal advice and assistance,
within the parameters of what is appropriate, to the working group as part of ongoing
operations.
 Team Leader, Finance – Oversee the establishment of the financial ledgers for the
operation of the LLP and ensure payments can be made for services performed by
PKC. Thereafter, providing budget monitoring statements from the LLP accounts to
the working group ensuring that performance can be reviewed against targets by
Lead Officer.
 Service Manager, Repairs and Improvements – Reactive repairs. Properties will be
placed on PKC repairs schedule, as per council houses, and repairs done in same
way. The cost of repairs will be paid for by the LLP. The role involves feeding in any
issues with the repairs scheduling.
 Capital Projects and New Build, Service Manager – Large cyclical repairs. Properties
will be placed on cyclical maintenance programmes as per PKC housing. This will
not be needed for the first 10 years, though costs will be paid for by the LLP.
Q. Will the LLP have a board, and if so, who sits on it?
Page 46 of 48

Page 47

Yes, it will have two boards. However, the make-up of the boards will be agreed through the
members agreement and so may vary depending on who the 2nd member is.
A proposed board structure model would look like the below.
1. Board of Members. This is the main board that makes specific decisions about the
LLP and sets its direction. It is made up of representatives from PKC and the 2nd
member organisation. The PKC voting always outweighs that of the 2nd Member so
that control is retained by PKC. Elected Members can sit on the Board of Members.
There is an obligation on members to make decisions based on the best interests of
the LLP
Suggested participants include
 Strategic Lead, Housing and Communities,
 Strategic Lead, Economy, Development, and Planning
 2nd Member Representative.
 Elected Members
2. Board of Management, or Senior Management Team (SMT) sits beneath the Board
of Members and will oversee the day-to-day management of the LLP. This will be
made up of senior management within PKC and representative from 2nd member
organisation. The Lead Officer reports into this board.
Suggested participants include:
 Strategic Lead, or Service Manager Housing and Communities
 Strategic Lead, or Service Manager Finance and Business Support
 Strategic Lead, or Service Manager Legal and Governance
 Strategic Lead, or Service Manager Economy, Development and Planning
 Strategic Lead, or Service Manager Property Services
 2nd Member Representative
There will be an obligation on all board members to review board reports, and act in the best
interests of the LLP.
Q. Who will do the LLP’s accounts?
The ongoing financial management of the LLP will be done by the working group with budget
monitoring by the Finance team feeding into the board reports. The proposal is that financial
accounts will be reported to SMT for approval before being submitted by Strategic Lead,
Finance. The initial tranche of properties is 13 and so financial arrangements should be
straightforward to manage, however as the assets accrue, the ongoing financial oversight
may need to be outsourced, paid for by the LLP.
Q. Who will manage the actual properties?
A. PKC Lets will manage the properties. They currently offer lettings agency services and so
will take up this role on behalf of the LLP, for a fee. The maintenance of the properties will be
undertaken by PKC, again with the cost paid for by the LLP. The properties will be added to
planned maintenance cycles with a fee being paid for this. They will also be added to routine
maintenance cycles, again for a fee. Any repairs to items such as white goods, blinds etc will
be coordinated directly by PKC Lets. The LLP will have a budget for reactive repairs each
year, which increases each year with inflation, and this will be used part of budget
Page 47 of 48

Page 48

monitoring. Income will be held back to pay for future cyclical maintenance and
replacements also.
Q. Why does the LLP need a general fund loan to part fund the upfront capital cost, rather
than the HRA?
A. The HRA is prohibited from lending to the LLP. Whilst Scottish Government approval is
needed to do so from general fund, this is the typical approach for Local Authorities to
directly deliver MMR and so getting approval should be straightforward.
Q. Does it have to be general funded, is there no other funds that can be used?
A. Council Tax 2nd / Empty Homes has been used by Shetland, but the funding required
would lead to a large reduction in monies available and this fund is needed to support wider
delivery of affordable housing programme. Private finance can be used however this
requires an interested private sector partner and substantial negotiation and so this avenue
will be pursued once the LLP is established.
Q. How can PKC justify using general fund monies for affordable housing, when budgets are
so tight?
A. Whilst the general fund will be ‘on lending’ £1.38m, there will be no detriment because
this will be paid back with the interest charges covered and so it is being lent on a no
detriment principle. The LLP will pay PKC Lets, a general funded service, a management fee
for managing the properties and so there are also opportunities for generating income for the
general fund. If there is a default on re-payment, the properties can be purchased by HRA
and converted to social housing with loan repaid in full.
Q. How long will it take to pay the loan back?
A. The loan, with interest, will be paid back over a 30-year period. If the LLP accrues profit
quicker than anticipated, then there will be option to increase payments, however the plan
would be to pay back over 30-year period, and it has been appraised on such a basis.
Q. What appraisals have been done to assess the financial viability of this proposal?
A. A development viability assessment has been undertaken and established that the
proposal stacks up financially, and furthermore, there are identified exit strategies should
something go wrong.
Page 48 of 48