Page 1

Our vision is a Perth and Kinross where everyone can live life well,
free from poverty and inequality
___________________________________________________________________
Committee or Board: Housing and Social Wellbeing
Date of Meeting: 25 March 2026
Report Title: Mid-Market Rent Proposal
Report Number: 26/75
Report Author: James Ross, Team Leader, Housing Strategy,
Economy, Development and Planning
Organisational Lead: Joint report by Elaine Ritchie – Strategic Lead –
Housing and Communities / Serge Merone – Strategic
Lead – Economy, Development and Planning
___________________________________________________________________
1. Purpose
1.1 The purpose of this report is to seek approval of Mid-Market Rent as an
additional affordable housing model for the Council. In addition, to the extent it
is within the Committee’s remit to do so, the report seeks approval of a
recommendation to establish a Limited Liability Partnership (LLP) to enable
the Council to directly deliver Mid-Market Rent, beginning with an initial
tranche of 13 new homes at Westfields, Rattray.
1.2 Sections
1. Purpose
2. Recommendations
3. Background/Context
4. Main Issues
5. Proposals
6. Conclusion
7. Impact Value Assessment
8. Appendices
2. Recommendations
It is recommended that Housing and Social Wellbeing Committee:
2.1 Agrees that Mid-Market Rent (MMR) is adopted as an affordable housing
model for the Council, delivered through a Limited Liability Partnership (LLP).

Page 2

2.2 Notes the proposal of the Strategic Lead – Economy, Development and
Planning, in consultation with the Strategic Lead – Legal and Governance, to
prepare a further report to the Council setting out the detail of the proposal for
approval at a future meeting.
2.3 Authorises the Strategic Lead – Economy, Development and Planning in
consultation with the Strategic Lead – Finance and Business Support to
submit to full Council a proposal to borrow £1.38m from the general fund and
then lend this to the LLP to acquire 13 new build affordable homes at
Westfields, Rattray, subject to satisfactory due diligence and acceptable
security arrangements.
2.4 Requires the Strategic Lead – Economy, Development and Planning to report
on the progress to Housing and Social Wellbeing Committee at a future
meeting.
3. Background/Context
3.1 Mid-market rent (MMR) is a type of affordable housing aimed at households
on low to moderate incomes who may struggle to access suitable rented
accommodation. MMR homes are let under a Private Residential Tenancy
(not a social tenancy), but rent levels are set at or below Local Housing
Allowance (LHA) rates to ensure they remain more affordable than typical
private rents. In practice, MMR acts as a tenure that bridges the gap between
social rent and private rent. Applicants must meet specific eligibility criteria to
be offered an MMR tenancy – criteria that can be decided by the landlord to
meet local housing need.
3.2 MMR is recognised nationally as an important element of affordable housing
delivery. Housing to 2040, Scotland’s long term housing strategy, includes a
commitment to deliver 110,000 new affordable homes by 2032. Of these, 70%
are to be for social rent, with the remaining 30% delivered through low-cost
home ownership and MMR. This report’s proposal contributes to the 30%
non-social rent share via MMR.
3.3 The Perth and Kinross Local Housing Strategy (LHS) 2022-2027 sets out the
strategic housing priorities for the area. The LHS includes a target to deliver
210 new supply affordable homes per year, with 70% for social rent and the
remaining 30% delivered through alternative tenures such as MMR and low-
cost home ownership, reflecting national policy direction.
3.4 Within Perth and Kinross, three Registered Social Landlords (RSLs) currently
provide MMR properties, with a fourth expected to deliver homes over the
next five years.
 Kingdom Housing Association manages 124 MMR properties across
Abernethy, Perth, Scone, Blairgowrie, and Crieff.
 Hillcrest Housing Association manages 87 MMR properties across
Perth and Blairgowrie.
 LAR Housing Trust manages 16 MMR properties in Blairgowrie.

Page 3

3.5 In addition, the current Strategic Housing Investment Plan (SHIP), includes
Places for People (PfP) to deliver new MMR properties in Scone, which will
add to the existing total of 227 properties.
4. Main Issues
4.1 In Perth and Kinross, demand for MMR continues to grow, particularly in
areas with high housing pressure, above-average rents, and limited access to
low-cost home ownership options. Current supply through partner RSLs is not
keeping pace with need. 
4.2 The Council must therefore adopt a more active and flexible delivery
approach if MMR outputs are to meet the expectations outlined in the LHS
and Strategic Housing Investment Plan (SHIP).
4.3 The Council cannot directly deliver MMR because a Private Residential
Tenancy cannot be issued by a Local Authority and so currently, the delivery
of MMR through the Strategic Housing Investment Plan relies entirely on
RSLs that operate MMR, via their subsidiaries.
4.4 Benefits of the Council delivering MMR are that it:
 Provides an affordable option for those that are unlikely to be allocated a
social tenancy. Many of whom approach our housing options service for
help. Thereby reducing pressures on services and providing a viable
alternative in areas with high private rents.
 Delivers greater flexibility and choice for those looking for their first, or
last, home. Households can be offered a home with 1 bedroom more
than social housing allocations would allow.
 Offers greater security of tenure than compared to the private rented
sector. As an established landlord with a strong track record in property
management and high-quality repairs, the Council offers tenants greater
stability and reassurance than individual private landlords.
5. Proposals
5.1 The Outline Business Case sets out three potential options available to the
Council to deliver MMR, a summarised version of this is provided as appendix
1. Following detailed appraisal, Option 3 has been identified as the preferred
option. The three options considered are:
- Option 1: Do Minimum / Existing Framework
- Option 2: Leasing Arrangement with an RSL
- Option 3: Establish a Limited Liability Partnership (LLP)
5.2 The development of the Outline Business Case has been informed by
contributions from Housing Strategy, Housing, Legal Services, Finance, and
procurement. In addition, external legal support has been procured from
Burness Paul to provide specialist advice.

Page 4

Officers have also engaged with Edinburgh, Fife and Stirling Councils to learn
from their experience of delivering MMR, as well as partner RSLs referenced
in the report. Support has also been provided by the Scottish Futures Trust,
who have supplied guidance and template documentation.
5.3 A suitable site has been identified for the first phase of MMR delivery.
Construction is due to commence in 2026/27 at Westfields, Rattray, a location
already approved within the Strategic Housing Investment Plan (SHIP).
5.4 Subject to Committee’s approval, it is anticipated that establishing the LLP will
take approximately six months and external business adviser, Burness Paul,
will support the full set-up process, ensuring all legal and governance
requirements are met including subsidy control, conflict management,
insurance, Health and Safety compliance and lettings/management
arrangements. It would be important to ensure that allocations/eligibility avoid
indirect discrimination and are line with Council’s priorities. A budget has also
been set aside to procure external financial advice, ensuring compliance with
all relevant financial regulations and the implementation of financial controls.
5.5 A financial appraisal has been completed for the initial tranche of 13 new
homes, which will form the LLP’s first stock. The current appraisal confirms
that £1.38m will be required, alongside Scottish Government grant funding
(£1,213,864), commuted sums (£220,000), and Council Tax second / empty
homes income (£260,000), to support the acquisition. Further sensitivity
analysis will be carried out. This capital contribution would be paid on
completion of the new homes and repaid by the LLP to the Council over a 30-
year period. Once the initial investment has been repaid, any surplus
generated will be reinvested in delivering additional MMR properties through
the LLP.
5.6 Initial discussions have taken place with Scottish Futures Trust regarding the
potential role of its investment subsidiary Scottish Futures Trust Investments
Limited as the LLP’s second member. Further consideration of alternative
second-member options will continue subject to Committee’s approval, with a
final partner to be confirmed prior to the LLP being formally established. The
selection of the second partner will be guided by criteria set by the Council
such as public purpose alignment, governance capacity or no dividend
leakage conflicting with affordability.
6. Conclusion
6.1 There is a clear and growing need for Mid-Market Rent (MMR) homes in Perth
and Kinross, particularly for households who are unable to access social
housing yet are priced out of the private rented sector. Current delivery
arrangements are not sufficient to meet this demand, particularly in
high-pressure areas.
6.2 The Outline Business Case demonstrates that establishing a Limited Liability
Partnership (LLP) provides the most effective, flexible and sustainable
mechanism for the Council to directly deliver MMR, while remaining compliant

Page 5

with legal and regulatory requirements. This approach enables the Council to
take a more active role in addressing local housing need and delivering on the
ambitions set out in the Local Housing Strategy and Strategic Housing
Investment Plan.
6.3 The proposed first phase of delivery at Westfields, Rattray will provide 13 new
MMR homes, supported by a robust financial appraisal. The required £1.38
million Council borrowing, to be on-lent to the LLP, will be fully repaid over a
30-year period, including principal and interest, ensuring the Council’s
investment is protected. Any future surplus generated by the LLP will be
reinvested to support further MMR delivery.
6.4 Approving the recommendations within this report will allow the Council to
establish a scalable and financially sustainable model for MMR delivery,
increase access to affordable housing, relieve pressure on housing services,
and provide greater housing choice and security for residents across Perth
and Kinross.
7. Impact and Value Assessment
Impact and Value Assessment
8. Appendices
8.1 Appendix 1: Business Case
8.2 Appendix 2: Mid-Market Rent FAQ’s