Page 1

PERTH AND KINROSS COUNCIL 
Housing & Social Wellbeing Committee 
19 June 2024 
ANNUAL UPDATE ON PERTH AND KINROSS LOCAL HOUSING
STRATEGY 2022-2027 
Report by Strategic Lead – Housing and Communities
(Report No. 24/191) 
1. PURPOSE 
1.1 To note progress in implementing the Local Housing Strategy for Perth and
Kinross previously approved at Housing and Social Wellbeing Committee on
15 March 2023 and to approve priorities for the current year. 
2. RECOMMENDATIONS 
2.1 It is recommended that Housing and Social Wellbeing Committee: 
• Notes the progress made during 2022-2023 and 2023-2024 towards
achieving the outcomes set out within the LHS Action Plan (Appendix
1). 
• Approves the priorities for 2024-2025 set out in Section 7 below. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
Section 4 – Background
Section 5 – Context 
Section 6 – Perth and Kinross Local Housing Strategy 2022-2027 Annual
Progress Update Year 1 and Year 2
Section 7 – Implementation and Review
Section 8 – Conclusion 
Appendix 
4. BACKGROUND 
4.1 The Housing (Scotland) Act 2001 places a statutory requirement on local
authorities to prepare a Local Housing Strategy (LHS) supported by an
assessment of housing need and demand. The LHS provides the direction for
tackling housing issues and informs future investment in housing and related
services.

Page 2

4.2 The LHS outlines what the Council and its partners would like to deliver for all
areas within Perth and Kinross during the five-year period 2022-2027. The
LHS 2022-2027 was prepared in accordance with the Scottish Government’s
Local Housing Strategy Guidance 2019 which sets out statutory requirements,
essential links and outcomes that should be considered within the LHS
framework. 
4.3 Annual updates are to be provided on how the LHS is implementing its
priorities and plans for the delivery of housing and housing related services
within the five year period of the strategy. 
4.4 The Local Housing Strategy 2022-2027 was approved at Housing and Social
Wellbeing Committee on 15 March 2023 (Report No.23/82). Due to delays in
approving the LHS 2022-2027 and subsequent impacts on reporting on
progress, it was agreed that the first update of the LHS would be delayed until
2024 and would include an update on the first two years of the strategy. This
is the first annual progress update to Housing and Social Wellbeing
Committee in implementing the strategy and presents progress of the first two
years covering the period 2022 to 2024. 
5. CONTEXT 
5.1 The LHS 2022-2027 is firmly aligned to the priorities and vision of the
Corporate Plan 2022/23 – 2027/28 (December 2022) for a Perth and Kinross
where everyone can live life well, free from poverty and inequality. The LHS
2022-2027 reflects the views of our communities, elected members,
stakeholders, and partner organisations. These views have helped influence
the development of the LHS priorities and outcomes which are most important
for Perth and Kinross, in enabling Perth and Kinross Council and partners to
deliver high quality housing and housing services to meet the needs of local
people in all housing tenures. 
6. PERTH AND KINROSS LOCAL HOUSING STRATEGY 2022-2027 ANNUAL
PROGRESS UPDATE 2022-2024 YEAR 1 AND YEAR 2 
6.1 The annual progress report for Year 1 (2022-23) and Year 2 (2023-24) is
attached in Appendix 1. The Local Housing Strategy has the following four
priorities for action. Key areas of progress in delivering the outcomes include
the following: 
Priority 1: Providing more affordable homes to support liveable and
sustainable communities: 
6.2 Our aim is to evidence local housing need and set a strategic vision over the
next five years for housing across public and private sectors, by providing the
right size, type, and tenure of housing in sustainable, well-connected places.

Page 3

6.3 During 2022-23 to 2023-24, we delivered new affordable homes for social
rent, low-cost home ownership, and mid-market rent across the Perth and
Kinross area. We increased the Council’s own housing stock through the
purchase of buybacks and bringing empty homes back into use for affordable
housing. We supported a number of projects to identify the potential for more
housing in rural areas through housing needs assessments, feasibility studies
and establishing our first Self-Build Register. Our Sustainable Inclusive
Homes Net Zero Carbon Design Guide was also published to support delivery
of new build affordable homes through construction innovation and house
design. We also undertook consultation for Short Term Let (STL) control
areas, with research and feedback helping to shape the associated non-
statutory Planning Guidance. 
6.4 The impact of these activities has been to help meet housing need in the area
and provide affordable housing across tenures. The additional social housing
has enabled turnover within the overall stock. Additional buybacks and empty
homes ensure we have more homes of the right type and size in areas people
want to live in. This has reduced waiting lists and met a range of housing
needs in the area including overcrowding, under occupying, alleviating
homelessness, and meeting mobility needs. 
Priority 2: Providing a range of housing options that people can easily
access, afford and keep 
6.5 Our aim is to set out the role that housing can play in improving housing
choice across all housing tenures and the LHS contribution to tackling child
poverty and further development of the Council’s Rapid Rehousing Transition
Plan (RRTP), building on the Home First model. 
6.6 During 2022-23 to 2023-24, we increased our support to households to
sustain their tenancy through our Tenancy Sustainment Fund, Financial
Inclusion Project and Think Yes budget. We made it easier for people to
access a range of housing options through the launch of a new self-serve
online Housing Options service. We continued to support people from Ukraine
to settle into accommodation and further developed our approach to Rapid
Rehousing via the Home First model through minimising the number of
children in temporary accommodation and increasing our spend on essential
goods for moving home and assistance through our Property Ready and
Prevention Funds. We commissioned an Intensive Housing Support service to
provide enhanced personalised transitional housing support to homeless
households with the service already at capacity. We consulted on our
Common Allocations Policy which includes proposing a new downsizing policy
with improved incentives to enable better targeting of properties that are
under-occupied. We are also set to become a local authority member of the
City of Sanctuary with a commitment to resettle 20 people per year.

Page 4

6.7 The impact of these activities has been to support people to have increased
awareness and access to suitable housing options to mitigate the impact of
housing induced poverty and poor housing affordability.  We have reduced the
stigma associated with homelessness and minimised the impact and duration
of households experiencing homelessness in Perth and Kinross. 
Priority 3: Delivering housing for people with varying needs 
6.8 Our aim is to deliver accessible homes, wheelchair homes and particular
forms of provision such as supported accommodation for key client groups to
enable people to live independently and well, for as long as possible, through
investment in property adaptations, technology, care and support services. 
6.9 During 2022-23 to 2023-24, we supported investment in adaptations to
Council and Housing Association properties and supported private tenants
and homeowners through our Care and Repair Scheme. We have undertaken
a review of our Occupational Therapy (OT) provision for social housing to
support this delivery further. We delivered further wheelchair accessible and
adapted properties through our new build programme, and supported
wheelchair users to move into fully adapted housing with our Housing OT
service. Through our multi-agency Independent Living Panel, we continued to
match individuals with housing and support needs to supported and bespoke
accommodation. We delivered a number of refurbishment and new build core
and cluster projects, including for wheelchair users, with built-in technology
linked to 24/7 onsite staff support. We have continued to work collaboratively
to promote the benefits of technology within a housing setting and launched
an online interactive smart house. We secured funding of almost £4 million to
transform our Gypsy Traveller site with new energy-efficient accommodation
and upgrades to create a sustainable environment for residents and support
climate change ambitions. A review of our buyback policy has also been
carried out to include increasing the number of buybacks the Council will aim
to purchase and to consider where buybacks may be suitable to support those
with adaptation needs. 
6.10 The impact of these activities has been to enable people to live independently
and well for as long as possible through investment in property adaptations,
technology, care, and support services. Through increased partnership
working, and an increase in preventative housing and support services, more
people have been enabled to remain in their own home, leave hospital or out
of area placements and to live in their chosen community independently with
support, close to family and support networks. 
Priority 4: Delivering quality homes with affordable warmth, zero
emission and SMART technology 
6.11 Our aim is to provide the strategic framework for improving the quality and
energy efficiency of homes across all tenures, driving improvement in housing
induced poverty and proactively tackling fuel poverty through investment in
housing condition and energy improvements; and setting a road map for
reducing domestic carbon emissions.

Page 5

6.12 During 2022-23 to 2023-24, we have developed and consulted on our Local
Heat and Energy Efficiency Strategy (LHEES) setting out energy efficiency
improvements across all tenures and established a LHEES Coordination
Team. We have increased the energy efficiency advice offered to households
through working with Save Cash and Reduce Fuel (SCARF) and our Home
Energy Advice Team (HEAT) service, resulting in savings for residents,
reductions in carbon emissions and removing some residents from fuel
poverty. We have invested in existing stock and new build housing with
installation of energy efficiency improvements. We have invested £150k in
communal repairs for homeowners through our Missing Shares service. We
have progressed pilot projects to incorporate net zero planning and retrofit
opportunities and continue to address Council stock which requires additional
work to meet the Scottish Housing Quality Standard (SHQS). In partnership
with Registered Social Landlords, 65 new build properties have benefited from
fibre installation. 
6.13 The impact of these measures ensures that people can live in and benefit
from homes which meet energy efficiency, climate change and housing quality
ambitions. Investment in housing condition and energy improvements,
including mechanisms and support to enable landlords and owners to invest in
repairs and maintenance has improved the quality of housing for residents. 
7. ONGOING IMPLEMENTATION AND CHALLENGES 
7.1 While good progress is being made towards delivering LHS outcomes,
various challenges remain. 
7.2 In particular, the Scottish Government More Homes Division confirmed on 28th
March 2024 that the Resource Planning Assumption (RPA) for Perth and
Kinross Council for 2024-25 is £12.216m, which is a reduction of
approximately £4.429m, down from £16.645m. In line with the Strategic
Housing Investment Plan for 2024-25, this will be carefully coordinated
throughout the year. It is currently projected that there are no projects at direct
risk from the funding reduction and anticipated that the reduced RPA for
2024-25 can be managed within the SHIP where updates will be reported to
the PKC Strategic Housing Board. 
7.3 During 2024-25 we intend to continue to work with partners to deliver
progress on LHS actions, including the following priorities: 
Priorities for 2024-25 
Priority 1: 
• Accelerate delivery of our affordable housing programme of 1,050
homes over the five year LHS period, through our Strategic Housing
Investment Plan and actions to build the affordable housing land supply.
• Increasing our buyback target to 40 for the coming year 
• Develop an Empty Homes Action Plan which targets investment in areas
where housing pressure is evidenced.

Page 6

• Further embed our newly published Net Zero Carbon Design Guide in all
new build developments to implement design and enhanced energy
efficiency standards.
• Continue to support delivery of local Housing Need Assessments and
Community-led projects in rural areas.
• Make a further report on potential for Short Term Let Control Area(s) to
the relevant committee. 
Priority 2: 
• Continue to develop and improve tailored debt advice and welfare
assistance to households across Perth and Kinross.
• Explore potential projects to deliver key worker housing in Northern
Perthshire.
• Continue to work with partners to offer housing and support options to
refugees in response to national dispersal and resettlement
programmes.
• Increase engagement with private landlords in Perth and Kinross to
improve awareness of proposed Private Rented Sector reforms and
investment regarding energy efficiency measures. 
Priority 3: 
• Update our Housing Contribution Statement
• Progress with publication of our first Mobility Strategy 
• Develop dementia-friendly design for social rented new build
developments through our Design Guide.
• Ensure planning policy, placemaking and housing investment contribute
to health and wellbeing, particularly through development in rural areas
in partnership with RSLs and HSCP.
• Implement any revised Scottish Government Housing for Varying Needs
standards through our Design Guide once published, including a
minimum of 10% of all affordable homes built to wheelchair and
adaptable standards.
• Further engagement with our Gypsy Traveller community through face to
face satisfaction survey work. 
Priority 4: 
• Support implementation of LHEES Delivery Plan to improve energy
efficiency across all tenures.
• Build an understanding of the current and future skills and training
requirements of the construction sector to deliver quality homes.
• Further facilitate delivery of high-speed broadband into social housing 
7.4 Committee is asked to approve these priorities identified within the LHS Action
Plan 2022-2027 for the coming year 2024-2025.

Page 7

8. MONITORING AND REVIEW 
8.1 Actions are being implemented through the LHS Delivery Group and by
operational teams. The LHS Delivery Group continues to build on the strong
partnerships already in place, recognising that achieving LHS priorities will
require a collective effort from delivery partners, stakeholders, communities,
and residents of Perth and Kinross. 
8.2 The LHS Communications Plan has set out how the Delivery Group are
conducting regular consultation and engagement with stakeholders. It also
ensures there is awareness of the key housing priorities for Perth and Kinross
until 2027. 
9. CONCLUSION 
9.1 The report outlines the significant outcomes achieved in the first two years of
delivering actions within the Local Housing Strategy 2022-2027, alongside the
key priority actions for 2024-2025. 
Author
Name  Designation Contact Details
Hannah Maclean  Planning and Policy
Officer, Planning and
Housing Strategy
ComCommitteeReports@pkc.gov.uk 
Approved 
Name Designation Date
Elaine Ritchie Strategic Lead – Housing
and Communities 
12 June 2024 
APPENDICES 
• Appendix 1 – Local Housing Strategy (LHS) 2022-2027 Annual Progress
Report

Page 8

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION  
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce No
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment No
Strategic Environmental Assessment No
Sustainability (community, economic, environmental) No
Legal and Governance  No
Risk No
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  Yes 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 The proposal aims to set out how the LHS will deliver more affordable homes
in sustainable places; improve housing choice and reduce inequality; support
independent living; ensure homes are easy and affordable to heat; and
ensure housing contributes to tackling the climate emergency and therefore
directly contribute to the delivery of the Perth and Kinross Community Plan /
Single Outcome Agreement in terms of: 
(i) Giving every child the best start in life
(ii) Developing educated, responsible and informed citizens
(iii) Promoting a prosperous, inclusive and sustainable economy
(iv) Supporting people to lead independent, healthy and active lives
(v) Creating a safe and sustainable place for future generations 
Corporate Plan 
1.2 The LHS 2022-2027 reflects the Council’s Corporate Plan objectives listed
above and therefore the proposal in this report would directly contribute to the
achievement of the priorities: 
(i) Giving every child the best start in life; 
(ii) Developing educated, responsible and informed citizens;

Page 9

(iii) Promoting a prosperous, inclusive and sustainable economy; 
(iv) Supporting people to lead independent, healthy and active lives; and 
(v) Creating a safe and sustainable place for future generations. 
2. Resource Implications 
Financial 
2.1  Funding implications arising directly from this report emanate from the
proposed local authority new build housing programme. In addition to the
Scottish Government Grant, the Council Tax Second Homes Fund, and
developer’s contributions for affordable housing will be used to support the
delivery of the programme including prudential borrowing. Funding from RSL
and Private Finance, as well as from Perth and Kinross HSCP and NHS will
also apply in relation to particular priority actions. Further Resource and
Funding Sources are detailed in Section 9 of the LHS 2022-2027. 
Workforce 
2.2 There are no direct workforce implications regarding this report. 
Asset Management (land, property, IT) 
2.3 Resource implications of this report relate to the local authority affordable
housing programme and the use of land currently in Council ownership
(Housing Revenue Account / General Fund). 
3. Assessments 
All impact assessments carried out in the development of the Local Housing
Strategy 2022-2027 and previously approved at Housing and Social Wellbeing
Committee (Report No.23/82) cover the duration of the LHS until 2027. 
The Impact Assessment Toolkit (IAT) Final Report produced on completing
the integrated appraisal was completed and can be viewed by clicking here. 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups. Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
The Equality Impact Assessment undertaken can be viewed by clicking here. 
The proposals were considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome:

Page 10

(i) Assessed as relevant and the following positive outcomes expected
through implementation: 
The broad ranging remit of the Local Housing Strategy and the range of
actions outlined in the priorities should have a broad spectrum of positive
impacts across Perth and Kinross residents.   
• By providing more homes in sustainable place where connectivity to jobs
and local services is easy 
• By improving housing choice and reducing inequality  
• By supporting people to live independently and well at home  
• By ensuring everyone finds it easy and affordable to heat their home  
• By ensuring housing makes a strong contribution to tackling the climate
emergency in Perth & Kinross.   
These actions will also improve the socio-economic position of residents.  
There are a number of Actions that are aimed at meeting the needs of people
with protected characteristics, including: 
• Priority 3 will have positive impacts on people with disabilities 
• Priority 3 contains several actions that may be relevant to the needs of
people aged over 65
• Action 4.3 within Priority 4 is aimed at younger people 
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
The proposals were considered under the Act and pre-screening identified
that the PPS would have no or minimal environmental effects, it is therefore
exempt, and the SEA Gateway was notified. The reason for concluding that
the PPS will have no, or minimal environmental effects is that the LHS is a
broad policy document which sits within the framework of the TAYplan SDP
(2016-2036) and the Perth and Kinross Local Development Plan (2019). The
SDP defines the spatial strategy while the LDP allocates specific sites to meet
identified demand. Strategic Environmental Assessments have been carried
out in respect of both these plans. 
Health Inequalities Impact Assessment 
A non-statutory Health Inequalities Impact Assessment pilot was also
undertaken with Public Health Scotland, NHS Tayside and Dundee City
Council and Angus Council in developing the new LHS. As housing is a key
driver of health outcomes, this assessment was an opportunity to review the
potential health impacts of the new LHS.

Page 11

It was determined that the broad ranging remit of the LHS and the range of
actions outlined in the priorities should have a broad spectrum of positive
impacts across Perth and Kinross residents. 
Recommendations made by the Health Inequalities Assessment for
integration into the LHS are available to view here. 
Sustainability   
3.3 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• in the way best calculated to delivery of the Act’s emissions reduction
targets.
• in the way best calculated to deliver any statutory adaptation
programmes; and
• in a way that it considers most sustainable. 
The Local Housing Strategy 2022-2027 Action Plan was considered against
the 17 Sustainable Development Goals (SDGs) where the actions made a
positive contribution to the measures: 
1. No Poverty: 15 of the actions in the LHS plan were assessed as being     
positive. 
3. Good Health and Wellbeing: 6 supporting actions 
4.  Quality Education: 1 positive action 
7. Affordable and Clean Energy: 5 supporting actions 
8. Decent Work and Economic Growth: 3 supporting actions 
9. Industry Innovation and Infrastructure: 2 positive actions 
10. Reduced Inequalities: a significant positive impact progressed by the
actions in all Priority areas 1 to 4.  
11. Sustainable Cities and Communities: 8 supporting actions 
13. Climate Action: 4 positive actions   
Legal and Governance 
3.4 The Strategic Lead, Legal and Governance has been consulted and there are
no direct legal implications in this report. 
Risk 
3.5 Risks associated with the delivery of LHS actions are covered within the 
Housing Service Risk Profile.

Page 12

4. Consultation 
Internal 
4.1 LHS Delivery Group officers were involved in preparing this update. 
External 
4.2 Consultation as part of LHS priority actions were carried out and included in
Section 6 of the report. 
4.3 The Tenant Committee Report Panel were consulted on this report. 
5. Communication 
5.1 An LHS 2022-2027 Communications Plan is in place. 
2. BACKGROUND PAPERS 
2.1  All documents that have been relied on in preparing the report are already
referenced within the main body of the report in Section 4 and 5 and Appendix
1.