Detailed Updates on Current Projects (May - November 2023) 
Milestones 
Milestones are key tasks within a project plan which mark completion of a
significant or critical phase of work or a decision point. 
When projects are in the “pre-delivery phase” (before a contract has been awarded),
milestone dates are aspirational, and a general status update is provided. 
In terms of projects that are in the “delivery phase”, the key milestones have the
following dates: 
• The Programme Date (Baseline) is the date that the milestone is planned for
completion based on the master programme agreed with the appointed main
contractor.  It is the baseline date for projects in the delivery phase; 
• The Current Projected Date is only relevant where there has been a deviation
from the baseline and a change in achieving the milestone has occurred; and 
• Actual Date is the date the milestone is completed.

Page 2

2 
NEW PRIMARY SCHOOL AT BERTHA PARK
Overview
Council (Report No. 16/277 refers) approved funding for a new build primary school for North/West
Perth required to accommodate expected pupil numbers generated from planned housebuilding.  As
part of the Learning Estate Transformation Programme, (Report No. 22/265 refers), Learning and
Families Committee approved the outcome of the statutory consultation on catchment changes and the
establishment of a new primary school at Bertha Park with effect from August 2026.  The site, which is
adjacent to Bertha Park High School, was transferred to Perth and Kinross Council ownership in 2016
as part of the Section 75 (S75) Agreement with the developer, Bertha Park Limited.
Sources of Funding
The approved funding from the Composite Capital Programme for this project is £24m.  As agreed
within the S75 Agreement, developer contributions estimated in the region of £12M indexed will be
recouped against the Council’s costs for constructing the primary school.
A bid has been submitted to the Scottish Government Learning Estate Investment Programme – Phase
3 (LEIP 3) for funding of 50% towards the project and announcement is awaited.  The funding would be
provided over a 25-year period based on the Council meeting specified targets.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Submit NPR February 2023  February 2023
Stage 1 of the HubCo process is underway
including the development of a concept
design.  Procurement of the design and build
team has been completed with the selection
of Robertson Construction (Tier 1
Contractor), Architype (Architect), Goodsons
Associates (Civil and Structural Engineer)
and Baker Hicks (Mechanical and Electrical
Engineer).
HubCo Stage 1 Formal
Commencement May 2023  May 2023
Stage 1 Agreed February 2024  
Stage 2 Agreed November 2024  
Financial Close December 2024  
Site Start December 2024  
School Operational  August 2026

Page 3

3 
BLAIRGOWRIE RECREATION CENTRE - REPLACEMENT
Overview
Council approved a replacement Recreation Centre at Blairgowrie High School (Report No. 16/277
refers).  This project will involve the replacement of the recreation centre on the playing fields of the
existing site.
Sources of Funding The approved funding from the Composite Capital Programme for this project is £36m.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current Projected
Date Actual Date Progress Update
Submit New Project Request
(NPR) November 2018  June 2019 
Construction work on the new Blairgowrie
Recreation Centre commenced in May 2023
and continues to progress well on site and
to programme.
HubCo Stage 1 Formal
Commencement September 2019  September 2019
Stage 1 Agreed November 2020  April 2021
Planning Application Submitted January 2021  December 2021
Planning Application Agreed March 2022  August 2022
HubCo Stage 2 Agreed September 2021  March 2023
Financial Close October 2021  April 2023
Site Start November 2021  May 2023
Centre Operational  March 2023 December 2024 
Completion of External Works June 2024 May 2025

Page 4

4 
METHVEN PRIMARY SCHOOL – REPLACEMENT DINING/ GYM FACILITIES
Overview
As part of the Learning Estate Transformation Programme, on 21 March 2018, Lifelong Learning
Committee (Report No. 18/84 refers) approved the project to replace both the life-expired dining/gym
facilities to improve the condition of Methven Primary School.
Sources of Funding The project will be funded from the Composite Capital Programme.
Project Delivery Progress
Key Milestone Programme
Date (Baseline) 
Current
Projected Date Actual Date Progress Update
Detailed Design and
Procurement commenced   August 2023 Outline designs for the standalone
dining/assembly/gym hall have been
agreed.  Early modelling has been carried
out to ensure the replacement facilities will
meet required energy performance targets.
Site Start February 2025  
Hall Operational May 2026

Page 5

5 
PERTH ACADEMY - REFURBISHMENT
Overview
Funding has been secured to undertake a partial refurbishment of the existing school facilities to improve the
condition and suitability.  Due to the live school environment, ongoing works are being phased into
manageable packages as part of a rolling programme.  Previously reported phases have been completed
including infrastructure upgrades, improvements to pupil social space and initial classroom refurbishments.
Sources of Funding This project is funded by the Composite Capital Programme.  The budget allocation was £16.9m, of which
£8.111m remains.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Phase 3 Refurbishment Works
complete on site
August 2023  September 2023 All standard classrooms have been refurbished
including furniture replacement and upgrades to
AV equipment.  In addition, extensive roof
upgrades and refurbishment of the ground floor
pupil toilets have been completed.
Phase 4 Science Block Fabric
Upgrades commenced on site
July 2023  July 2023 This phase to improve the energy efficiency
and performance of the external façade has
now commenced on site.
Future phases of internal refurbishment to
practical classrooms will be planned in due
course.  
Other ongoing work packages include
development of designs to upgrade the Wi-Fi
system and structural repairs to the PE
building.
Phase 4 Science Block Fabric
Upgrades complete on site
November 2024

Page 6

6 
PERTH GRAMMAR SCHOOL – REFURBISHMENT
Overview
Funding is available to undertake infrastructure upgrades to the existing school building.  Additionally,
approval was given for works to improve the entrance, reception and administration facilities which were
carried out.  Due to the live school environment, ongoing works are being phased into manageable
packages as part of a rolling programme.  Previously reported phases included the AV replacement
programme and the refurbishment of toilets, classrooms and social spaces.
Sources of Funding This project is funded by the Composite Capital Programme.  The original budget was £7.05m, of which
£4.967m remains.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Assembly Hall Roof
Replacement complete
October 2023  October 2023 This phase involved replacement of structural
roofing and associated works to the assembly
hall roof.
While on site, inspections were carried out in
other areas of the building which have
identified necessary residual roof works (in
the region of £500k).  It is anticipated that
these works will take around 6 months to
complete and with no disruption to school
operations.
Wi-Fi Upgrades commence on
site
December 2023  
Works to improve the digital connectivity of
the learning environment are due to
commence in December 2023. Wi-Fi Upgrades complete on site November 2024

Page 7

7 
PERTH HIGH SCHOOL REPLACEMENT
Overview Council approved the replacement of Perth High School (Report No. 18/212 refers).  This project will
involve the replacement of the existing school building on the playing field of the existing site.
Sources of Funding
The approved funding from the Composite Capital Programme for this project is £80.2M.  A bid made to
the Scottish Government Learning Estate Investment Programme – Phase 2 for funding of 50% towards
the project was successful.  The funding will be provided over a 25-year period based on the Council
meeting specified targets.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Submit NPR  June 2019  June 2019
Construction works continue to progress on
site. 
HubCo Stage 1 Formal
Commencement July 2019  July 2019
Stage 1 Agreed May 2020  February 2021
Planning Application Submitted April 2021  September 2021
Planning Application Agreed August 2021  March 2022
HubCo Stage 2 Agreed January 2022  February 2023
Financial Close February 2022  March 2023
Site Start March 2022  February 2023
Construction Works Complete June 2024 July 2025 
School Operational  August 2024 August 2025 
Completion of External Works July 2025 August 2026

Page 8

8 
RIVERSIDE PRIMARY SCHOOL – NEW BUILD SCHOOL
Overview
As part of the Learning Estate Transformation Programme Council, Lifelong Learning Committee
(Report No. 18/15 refers) approved the construction of a new primary school on the playing field of the
former North Muirton Primary School site to accommodate pupils from both the former North Muirton
and Balhousie Primary Schools.
Sources of Funding
The approved funding from the Composite Capital Programme for this project is £19.9m.  A bid made to
the Scottish Government Learning Estate Investment Programme – Phase 2 for funding of 50% towards
the project was successful.  The funding will be provided over a 25-year period based on the Council
meeting specified targets.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Submit NPR June 2019  July 2019
Riverside Primary School became
operational in June 2023.  Phase 2, including
the demolition of the former North Muirton
Primary School building is progressing well.
HubCo Stage 1 Formal
Commencement November 2019  November 2019
Stage 1 Agreed May 2020  November 2020
Planning Application Submitted January 2021  January 2021
Planning Application Agreed May 2021  May 2021
Stage 2 Agreed July 2021  October 2021
Financial Close August 2021  October 2021
Site Start September 2021  November 2021
School Operational  April 2023  June 2023
Completion of External Works July 2023 November 2023