Democracy Spraffa

Agenda Document Pack - Property Sub-Committee - 01/05/2023

Perth and Kinross Council · 1 May 2023
Back to Property Sub-Committee — 1 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Securing the future… • Improving services 
• Enhancing quality of life • Making the best use of public
resources 
Council Building
2 High Street
Perth
PH1 5PH 
24/04/2023 
A hybrid meeting of the Property Sub-Committee will be held in the Council
Chamber on Monday, 01 May 2023 at 13:00. 
If you have any queries please contact Committee Services on (01738) 475000 or
email Committee@pkc.gov.uk. 
THOMAS GLEN
Chief Executive      
Those attending the meeting are requested to ensure that all notifications are
silent on their device and other devices are in silent mode. 
Please note that the meeting will be broadcast online and recorded.  The
recording will be publicly available on the Council’s website following the
meeting. 
Members:
Councillor Grant Laing  (Convener)
Councillor Eric Drysdale  (Vice-Convener)
Councillor Peter Barrett
Councillor Andy Chan
Councillor Dave Cuthbert
Councillor Angus Forbes
Councillor Tom McEwan 
Page 1 of 24

Page 2

Page 2 of 24

Page 3

Property Sub-Committee 
Monday, 01 May 2023 
AGENDA 
MEMBERS ARE REMINDED OF THEIR OBLIGATION TO DECLARE ANY
FINANCIAL OR NON-FINANCIAL INTEREST WHICH THEY MAY HAVE IN ANY
ITEM ON THIS AGENDA IN ACCORDANCE WITH THE COUNCILLORS’ CODE OF
CONDUCT. 
1 WELCOME AND APOLOGIES/SUBSTITUTES   
2 DECLARATIONS OF INTEREST   
3 MINUTE OF MEETING OF THE PROPERTY SUB-COMMITTEE
OF 11 JANUARY 2023 FOR APPROVAL
(copy herewith) 
5 - 6 
4 LEARNING ESTATE PROGRAMME - PROGRESS UPDATE
Report by Executive Director (Education and Children's Services)
(copy herewith 23/123) 
7 - 24 
IT IS RECOMMENDED THAT THE PUBLIC AND PRESS SHOULD BE EXCLUDED
DURING CONSIDERATION OF THE FOLLOWING ITEM(S) IN ORDER TO AVOID
THE DISCLOSURE OF INFORMATION WHICH IS EXEMPT IN TERMS OF
SCHEDULE 7A TO THE LOCAL GOVERNMENT (SCOTLAND) ACT 1973 
P1  STRATHCONA, SPOUTWELLS ROAD, SCONE, PERTH
• Exempt Reason 6 - Information relating to the financial or
business affairs of any particular person (other than the
authority).
• Exempt Reason 9 - Any terms proposed or to be proposed by
or to the authority in the course of negotiations for a contract for
the acquisition or disposal of property or the supply of goods or
services.
• Exempt Reason 13 - Information which, if disclosed to the
public, would reveal that the authority proposes – (a) to give
under any enactment a notice under or by virtue of which
requirements are imposed on a person; or (b) to make an
order or direction under any enactment. 
P2  DISPOSAL - SHOPS: 1-5 LEONARD STREET, PERTH
• Exempt Reason 6 - Information relating to the financial or
business affairs of any particular person (other than the
authority).
• Exempt Reason 9 - Any terms proposed or to be proposed by
or to the authority in the course of negotiations for a contract for 
Page 3 of 24

Page 4

the acquisition or disposal of property or the supply of goods or
services. 
P3  OFFERS RECEIVED TO LEASE A SITE AT RIE-ACHAN ROAD
CAR PARK, PITLOCHRY FOR A CLASS 3 BUSINESS USE
• Exempt Reason 6 - Information relating to the financial or
business affairs of any particular person (other than the
authority).
• Exempt Reason 9 - Any terms proposed or to be proposed by
or to the authority in the course of negotiations for a contract for
the acquisition or disposal of property or the supply of goods or
services. 
Page 4 of 24

Page 5

PROPERTY SUB-COMMITTEE 
Minute of hybrid meeting of the Property Sub-Committee of the Finance and
Resources Committee held in the Council Chamber, 2 High Street, Perth on
Wednesday 11 January 2023 at 10.00am. 
Present: Councillors G Laing, E Drysdale, P Barrett, A Chan, D Cuthbert, A Forbes
and T McEwan. 
In Attendance: S Crawford, K Farmer, J Janes and C Rowan (all Communities),
A Brown, J Guild, P Mair and M Pasternak (all Corporate and Democratic Services). 
Councillor G Laing, Convener, Presiding. 
1. WELCOME AND APOLOGIES 
Councillor G Laing welcomed all present to the meeting. 
2. DECLARATIONS OF INTEREST 
No Declarations of Interest were made in terms of the Councillors’ Code of
Conduct. 
3. MINUTE OF MEETING OF PROPERTY SUB-COMMITTEE OF
14 NOVEMBER 2022 
The minute of meeting of the Property Sub-Committee of 14 November 2022
was submitted and approved as a correct record. 
IT WAS AGREED THAT THE PUBLIC AND PRESS SHOULD BE EXCLUDED
DURING CONSIDERATION OF THE FOLLOWING ITEMS IN ORDER TO AVOID
THE DISCLOSURE OF INFORMATION WHICH IS EXEMPT IN TERMS OF
SCHEDULE 7A TO THE LOCAL GOVERNMENT (SCOTLAND) ACT 1973. 
P1. PROPOSED DISPOSAL OF 0.367 HECTARES (0.906 ACRES) OF
INDUSTRIAL LAND AT KINROSS WEST TO A J SPENCE LIMITED OR
THEIR NOMINEES 
There was submitted a report by the Executive Director (Communities) (23/1)
requesting the Property Sub-Committee approve disposal of 0.367 hectares (0.906
acres) of industrial land (Site 1) at Kinross West, which is part of the Council’s
Commercial Property Investment Programme (CPIP). 
Motion (Councillors G Laing and E Drysdale) 
To approve the disposal of 0.367 hectares (0.906 acres) of industrial land
(Site 1) at Kinross West as set out in report 23/1. 
3
Page 5 of 24

Page 6

Proposed Amendment (Councillor D Cuthbert) 
To sell the site under the terms of Offer 4 as set out in Appendix 3 to Report
23/1. 
In line with Standing Order 18.3, as no seconder to the amendment was
forthcoming, the amendment subsequently fell. 
Resolved:
(i) Disposal of 0.367 hectares (0.906 acres) of industrial land (Site 1) at Kinross
West to A J Spence Ltd or their nominees on the terms set out in Report 23/1
or otherwise on terms to be agreed by the Head of Planning and Development
and the Head of Legal and Governance Services, be approved. 
(ii) It be agreed that all other offers are not acceptable due to the non-compliant
nature of the offers in relation to the conditions of the closing date.
Page 6 of 24

Page 7

PERTH AND KINROSS COUNCIL 
PROPERTY SUB-COMMITTEE 
1 MAY 2023 
LEARNING ESTATE PROGRAMME – PROGRESS UPDATE 
Report by Executive Director (Education and Children’s Services)
(Report No. 23/123) 
1. PURPOSE 
1.1 This report updates the Property Sub-Committee on the progress for
delivering the current major projects within the Education and Children’s
Services (ECS) Learning Estate Programme.  It details key milestones which
have been achieved since the last update to Property Sub-Committee on 
13 June 2022 (Report No. 22/121 refers). 
2. RECOMMENDATION 
2.1 It is recommended that the Committee: 
• Notes the significant milestones that have been achieved, rescheduled or
updated since the previous Property Sub-Committee meeting on 13 June
2022: 
➢ New Primary School at Bertha Park
• A New Project Request (NPR) for the project was submitted to Hub
East Central Scotland (HubCo) in February 2023;
• The procurement process to select the Design Team is underway.
• A bid for Learning Estate Investment Programme – Phase 3 (LEIP
3) funding for the project has been submitted to the Scottish
Government (6.3); 
➢ Blairgowrie Recreation Centre – Replacement
• The planning application was approved at the Planning and
Placemaking Committee on 10 August 2022;
• Following Council approval of additional funding on 1 March 2023,
construction work is expected to commence on site in May 2023
(6.4); 
➢ Phase 3 of refurbishment works at Perth Academy is progressing well
with 15 classrooms now refurbished and roofing works completed (6.5); 
➢ Phase 1 of classroom refurbishment work at Perth Grammar School
was completed in August 2022 and a programme to replace audio
visual equipment in teaching spaces was completed in April 2023 (6.6); 
4
Page 7 of 24

Page 8

➢ Following Council approval on 21 December 2022, the replacement of
Perth High School commenced on site in February 2023 (6.7); and 
➢ The extended nursery at Rattray Primary School became operational in
Summer 2022 (6.8). 
• Notes that the project teams continue to manage the impact of
Brexit/COVID-19/construction supply capacity, and the war in Ukraine, on
projects. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background
• Section 5: Progress
• Section 6: Updates on Current Programme 
• Appendices 
4. BACKGROUND 
4.1 The Learning Estate Strategy (November 2021) (Report No. 21/202 refers) sets
out the Council’s aspirations for our schools, and in particular, the high value
we place on learning, through our vision for well designed, maintained and
managed schools. 
4.2 The strategy is delivered through the Learning Estate Management Plan
(LEMP), approved by Lifelong Learning Committee in November 2021, which
is primarily funded through the Council Capital Programme. 
4.3 The ECS Capital Programme details the priorities for the Learning Estate until
2027/28 and is reviewed on an annual basis. 
5. PROGRESS 
5.1 This report updates Committee on the progress for delivering the current
projects within the ECS Learning Estate Programme.  The focus of the
programme is on: 
• Primary School Upgrades; 
• New Primary School Projects;
• Secondary School Upgrades;
• Replacement Secondary School; and
• Recreation Centre Replacement. 
5.2 Brexit/COVID-19/construction supply capacity, and the war in Ukraine, are
having an impact on all projects and there is currently an increase in tender
and material prices being experienced across the construction industry. 
Page 8 of 24

Page 9

5.3 Project teams have regular dialogue regarding options and solutions to
manage the impact of the changing situation.   
6. UPDATES ON CURRENT PROGRAMME 
6.1 Detailed updates on all current projects are provided in Appendix 1. 
6.2 The following is an update on significant project milestones since previously
reported to the Property Sub-Committee. 
6.3 New Primary School at Bertha Park 
6.3.1 As part of the School Estate Transformation Programme, the Learning and
Families Committee on 2 November 2022 approved the site adjacent to
Bertha Park High School for a new primary school (Report No. 22/265 refers). 
The extra capacity in the primary school estate is required to accommodate
expected pupil numbers generated from planned housebuilding within the
strategic sites at the north and north west of Perth. 
6.3.2 The NPR was submitted to HubCo in February 2023 and the selection
process for the Design Team is underway. 
6.3.3 A bid for LEIP 3 funding for the project has been submitted to the Scottish
Government.  If successful, the funding of 50% towards the project will be
provided over a 25-year period based on the Council meeting specified
targets. 
6.4 Blairgowrie Recreation Centre - Replacement 
6.4.1 The Council has approved a replacement recreation centre at Blairgowrie
High School (Report No. 16/277 refers). 
6.4.2 The Planning Application was approved at Planning and Placemaking
Committee on 10 August 2022 (Report No. 22/178 refers). 
6.4.3 On 1 March 2023, Council considered the Full Business Case for the project
(Report No. 23/73 refers) and agreed to proceed with an increased capital
budget for the project.  This enabled Financial Close to be reached and
construction work is expected to commence on site in May 2023. 
6.5 Perth Academy 
6.5.1 Funding has been secured to undertake a partial refurbishment of Perth
Academy to improve the condition and suitability of the facilities.  Due to the
live school environment, ongoing works are being phased into manageable
packages as part of a rolling programme. 
6.5.2 As part of the third phase of works, a further 15 classrooms have been
refurbished and roofing upgrades have been completed. 
Page 9 of 24

Page 10

6.6 Perth Grammar School 
6.6.1 Funding is allocated to undertake infrastructure upgrades to Perth Grammar
School.  Due to the live school environment, ongoing works are being phased
into manageable packages as part of a rolling programme. 
6.6.2 In August 2022, the first phase of ten classroom refurbishments was
completed.  In addition, a programme to replace audio visual equipment in
teaching spaces was completed in April 2023. 
6.7 Perth High School 
6.7.1 On 20 June 2018, Council approved funding from the Composite Capital
Budget (Report No. 18/212 refers) for the replacement of Perth High School. 
6.7.2 On 21 December 2022, Council considered the Full Business Case (Report
No. 22/312 refers) and approved that the project proceed with an increased
capital budget for the project.  This enabled Financial Close to be concluded
and construction works on the new school building commenced in     February
2023. 
6.8 Rattray Primary School 
6.8.1 As a part of the ELC Expansion Plan (Report No. 17/314 refers), a nursery
extension was approved for Rattray Primary School. 
6.8.2 The extended nursery became operational in Summer 2022. 
Author
Name Designation Contact Details
Greg Boland Head of Business and
Resources
ECSCommittee@pkc.gov.uk 
01738 475000 
Approved
Name Designation Date
Sheena Devlin Executive Director (Education
and Children’s Services)
20 April 2023 
Page 10 of 24

Page 11

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION  
Strategic Implications Yes/None
Community Plan/Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce No
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  No 
1. Strategic Implications  
Corporate Plan 
1.1 This section sets out how the proposals relate to the delivery of the Perth and
Kinross Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.   
Corporate Plan 
1.2 This section sets out how the proposals relate to the achievement of the
Council’s Corporate Plan Objectives: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.  
Page 11 of 24

Page 12

1.3 The report also links to the Education & Children’s Services Vision, Values
and Priorities in respect of the following key Priority area: 
• Learning and Achievement 
2. Resource Implications 
Financial 
2.1 The meeting of the Council on 1 March 2023 approved the Composite
Capital budget 2023/24 to 2027/28 (Report No. 23/73 refers). 
2.1.1 Any additional revenue implications identified through either the existing
Capital Programme, or future Capital Programmes will require to be
submitted as part of an expenditure pressure with a corresponding saving
through the ECS Revenue Budget process. 
2.1.2 There are no direct financial implications arising from this report other than
those reported within the body of the main report and related business
cases. 
Workforce 
2.2 There are no direct workforce implications arising from this report. 
Asset Management (land, property, IT) 
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.   
3.1.1 The proposals have been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
Page 12 of 24

Page 13

3.2.1 The proposals have been considered under the Act; however, no action is
required as the Act does not apply to the matters presented in this report. 
This is because the Committee are requested to note the contents of the
report only and the Committee are not being requested to approve, adopt
or agree to an action or to set the framework for future decisions. 
Sustainability 
3.3 Under the provisions of the Local Government in Scotland Act 2003, the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.  Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• In the way best calculated to delivery of the Act’s emissions reduction
targets.
• In the way best calculated to deliver any statutory adaption programmes.
• In a way that it considers most sustainable. 
3.3.1 The information contained within this report has been considered under
the Act.  However, no action is required as the Act does not apply to the
matters presented in this report. 
Legal and Governance 
3.4 The Head of Legal and Governance Services has been consulted in the
preparation of this report. 
3.5 N/A 
Risk 
3.6 Individual risk profiles are in place for individual projects listed. 
4. Consultation 
Internal 
4.1 The Head of Finance, Head of Legal and Governance Services and Head of
Property Services have been consulted in the preparation of this report.   
External 
4.2 Participation and involvement of the community are critical to the ongoing and
future success of school estate investment and an emphasis is placed on
ensuring consultation, over and above that which might be required in terms
of planning requirements and statutory consultation requirements. 
4.2.1 A User Reference Group (URG), or equivalent, is set up for all major and
large projects.  The purpose of the URG is to assist with providing relevant
Page 13 of 24

Page 14

local input to allow the Design Team to develop the outline concept design
into an operational design.  The formation of a URG is an invaluable source of
information, and any project is reliant on this level of local detail. 
5. Communication 
5.1 A stakeholder communication plan is developed for all major and large
projects.  The plan aims to support effective communication and
engagement with all project stakeholders. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (and not containing confidential or exempt information)
were relied on to a material extent in preparing the above report. 
3. APPENDICES  
3.1 Appendix 1 – Detailed Updates on Current Projects (June 2022 – May 2023)
Page 14 of 24

Page 15

APPENDIX 1 
Detailed Updates on Current Projects
June 2022 – May 2023 
Milestones 
Milestones are key tasks within a project plan which mark completion of a significant or
critical phase of work or a decision point. 
When projects are in the “pre-delivery phase” (before a contract has been awarded),
milestones dates are aspirational, and a general status update is provided. 
In terms of projects that are in the “delivery phase” the key milestones have the following
dates: 
• The Programme Date (Baseline) is the date that the milestone is planned for
completion based on the master programme agreed with the appointed Main
Contractor.  It is the baseline date for projects in the delivery phase; 
• The Current Projected Date is only relevant where there has been a deviation from
the baseline and a change in achieving the milestone has occurred; and 
• Actual Date is the date the milestone is completed. 
4
Page 15 of 24

Page 16

NEW PRIMARY SCHOOL AT BERTHA PARK
Overview
Council (Report No. 16/277 refers) approved funding for a new build primary school for North/West
Perth required to accommodate expected pupil numbers generated from planned housebuilding.  As
part of the School Estate Transformation Programme, on 2 November 2022, the Learning and Families
Committee (Report No. 22/265 refers) approved the outcome of the statutory consultation on catchment
changes and the establishment of a new primary school at Bertha Park with effect from August 2026. 
The proposed site is adjacent to Bertha Park High School.
Sources of Funding The approved funding from the Composite Capital Programme for this project is £24m.
Project Pre-delivery Progress
The Statutory Consultation for the new catchment area for the school concluded in November 2022. 
A New Project Request (NPR) was submitted to Hub East Central Scotland (HubCo) in February 2023 and the procurement process for the
Design Team is underway.  
In October 2022 a bid was submitted to the Scottish Government Learning Estate Investment Programme – Phase 3 for funding of 50%
towards the project.  If the bid is successful, the funding will be provided over a 25-year period based on the Council meeting specified
targets.
The planned date for operation of the new school is August 2026.  HubCo Stage 1 design work will commence imminently. 
Page 16 of 24

Page 17

BLAIRGOWRIE RECREATION CENTRE - REPLACEMENT
Overview
Council approved a replacement Recreation Centre at Blairgowrie High School (Report No. 16/277
refers).  This project will involve the replacement of the recreation centre on the playing fields of the
existing site.
Sources of Funding The approved funding from the Composite Capital Programme for this project is £36m.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current Projected
Date Actual Date Progress Update
Submit New Project Request
(NPR) November 2018  June 2019
The Planning Application was approved at
Planning and Placemaking Committee on
10 August 2022. 
On 1 March 2023 Council considered the
Full Business Case for the project (Report
No. 23/73 refers) and approved that the
budget be increased by £9.3M to £36M. 
This enabled Financial Close to be
concluded and construction work on the
new recreation centre is expected to
commence in May 2023.
HubCo Stage 1 Formal
Commencement September 2019  September 2019
Stage 1 Agreed November 2020  April 2021
Planning Application Submitted January 2021  December 2021
Planning Application Agreed March 2022  August 2022
HubCo Stage 2 Agreed September 2021  March 2023
Financial Close October 2021  April 2023
Site Start November 2021 May 2023 
Centre Operational  March 2023 December 2024 
Completion of External Works June 2024 July 2025 
Page 17 of 24

Page 18

METHVEN PRIMARY SCHOOL – REPLACEMENT DINING/ GYM FACILITIES
Overview
As part of the School Estate Transformation Programme, on 21 March 2018, Lifelong Learning
Committee (Report No. 18/84 refers) approved the project to replace both the life-expired dining/gym
facilities to improve the condition of Methven Primary School.
Sources of Funding The project will be funded from the Composite Capital Programme.
Project Pre-delivery Progress
A feasibility exercise was carried out for the whole site and a preferred option has been selected which involves the construction of a standalone
building to house the dining and gym facilities.  Substantial enabling works have been completed on site including the demolition of the life-expired
gym hall and improvements to the site access and external landscape.
Design work for the new building is progressing and the programme to completion is currently being developed which will identify key project
milestones.  
Page 18 of 24

Page 19

PERTH ACADEMY - REFURBISHMENT
Overview
Funding has been secured to undertake a partial refurbishment of the existing school facilities to improve
the condition and suitability.  Due to the live school environment, ongoing works are being phased into
manageable packages as part of a rolling programme.
Sources of Funding This project is funded by the Composite Capital Programme.  The budget allocation was £16.9m, of
which £8.315m remains.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Phase 1 Refurbishment Works
complete on site
June 2021  July 2021 This phase involved various upgrades including a
new CCTV installation, corridor lighting, external
structural repairs, CDT ventilation and major
infrastructure upgrades to the PE building.
Phase 2 Refurbishment Works
complete on site
August 2021  August 2021 This phase involved improvements to student
social space and classroom refurbishments.
Phase 3 Refurbishment Works
commenced on site 
June 2022 Ten classrooms were refurbished during the
2022 summer holidays. 
Phase 3 Refurbishment Works
complete on site
August 2023   Further classrooms are being refurbished during
term time.  External consultants have been
appointed and are undertaking AV/Wi-Fi upgrade
surveys and design work.  Ground floor pupil
toilets will be refurbished in Summer 2023.  In
addition, extensive roof upgrades have been
completed and a furniture replacement
programme is underway.
Phase 4 Science Block Fabric
Upgrades
August 2024   Replacement of the curtain walling at the science
block will improve the energy efficiency and
performance of the external façade.
Page 19 of 24

Page 20

PERTH GRAMMAR SCHOOL - REFURBISHMENT
Overview
Funding is available to undertake infrastructure upgrades to the existing school building.  Additionally,
approval was given for works to improve the entrance, reception and administration facilities which were
carried out.  Due to the live school environment, ongoing works are being phased into manageable
packages as part of a rolling programme.
Sources of Funding This project is funded by the Composite Capital Programme.  The original budget was £7.05m, of which
£4.967m remains.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Phases 1-4 Toilet
Refurbishment Works complete
on site  
October 2021 All planned toilet refurbishment phases were
completed between April – October 2021.
Phase 1 Classroom
Refurbishment Work complete
on site
August 2022  August 2022 This phase involved improvements to student
social space and classroom refurbishments.
Audio Visual Replacement
Programme
April 2023  April 2023 Smart panels and display screens have been
replaced in teaching spaces.  Wi-Fi upgrades
will be undertaken in a future phase.
Future Phases TBC   The next phases of refurbishment are currently
being planned.
Page 20 of 24

Page 21

PERTH HIGH SCHOOL REPLACEMENT
Overview Council approved the replacement of Perth High School (Report No. 18/212 refers).  This project will
involve the replacement of the existing school building on the playing field of the existing site.
Sources of Funding
The approved funding from the Composite Capital Programme for this project is £80.2M.  A bid made to
the Scottish Government Learning Estate Investment Programme – Phase 2 for funding of 50% towards
the project was successful.  The funding will be provided over a 25-year period based on the Council
meeting specified targets.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Submit NPR  June 2019  June 2019
On 21 December 2022 Council considered the
full business case for the project (Report No. 
22/312 refers) and approved that the budget
be increased by £11.5M to £80.2M.  This
enabled Financial Close to be concluded and
construction works on the new school building
commenced in February 2023. 
HubCo Stage 1 Formal
Commencement July 2019  July 2019
Stage 1 Agreed May 2020  February 2021
Planning Application Submitted April 2021  September 2021
Planning Application Agreed August 2021  March 2022
HubCo Stage 2 Agreed January 2022  February 2023
Financial Close February 2022  March 2023
Site Start March 2022  February 2023
Construction Works Complete June 2024 July 2025 
School Operational  August 2024 August 2025 
Completion of External Works July 2025 August 2026 
Page 21 of 24

Page 22

RATTRAY PRIMARY SCHOOL – NURSERY EXTENSION & REFURBISHMENT
Overview
Lifelong Learning Committee approved Education and Children’s Services Early Learning and Childcare
(ELC) Expansion Plan (Report No. 17/314 refers).  As part of the plan, it was proposed that the capacity
of the nursery at Rattray Primary School will be increased by 26. 
Sources of Funding The Scottish Government confirmed Perth and Kinross Council’s allocation of capital funding for the
expansion of ELC.  The budget for Rattray Primary School was £4,325,000.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Review of Feasibility Study March 2018  March 2018
The extended nursery became operational in
Summer 2022.
Planning Application Submitted November 2018  January 2019
Planning Application Agreed December 2018  May 2019
Contract Cost Agreed April 2020  January 2021
Site Start June 2020  June 2021
Construction Works Complete August 2021  October 2022
Nursery Provision Operational August 2020  July 2022
Page 22 of 24

Page 23

RIVERSIDE PRIMARY SCHOOL – NEW BUILD SCHOOL
Overview
As part of the School Estate Transformation Programme Council, Lifelong Learning Committee (Report
No. 18/15 refers) approved the construction of a new primary school on the playing field of the existing
North Muirton Primary School site to accommodate pupils from both North Muirton and Balhousie
Primary Schools.
Sources of Funding
The approved funding from the Composite Capital Programme for this project is £19.9m.  A bid made to
the Scottish Government Learning Estate Investment Programme – Phase 2 for funding of 50% towards
the project was successful.  The funding will be provided over a 25-year period based on the Council
meeting specified targets.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Submit NPR June 2019  July 2019
Phase 1 is nearing completion with Riverside
Primary School due to be operational in June
2023.  Phase 2, including the demolition of the
former North Muirton Primary School building,
will commence thereafter.
HubCo Stage 1 Formal
Commencement November 2019  November 2019
Stage 1 Agreed May 2020  November 2020
Planning Application Submitted January 2021  January 2021
Planning Application Agreed May 2021  May 2021
Stage 2 Agreed July 2021  October 2021
Financial Close August 2021  October 2021
Site Start September 2021  November 2021
School Operational  April 2023 June 2023 
Completion of External Works July 2023  
Page 23 of 24

Page 24

Page 24 of 24