Appendix 1 - Detailed Updates on Current Projects (June 2022 - May 2023)

Perth and Kinross Council · 1 May 2023
Back to Property Sub-Committee — 1 May 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

APPENDIX 1 
Detailed Updates on Current Projects
June 2022 – May 2023 
Milestones 
Milestones are key tasks within a project plan which mark completion of a significant or
critical phase of work or a decision point. 
When projects are in the “pre-delivery phase” (before a contract has been awarded),
milestones dates are aspirational, and a general status update is provided. 
In terms of projects that are in the “delivery phase” the key milestones have the following
dates: 
• The Programme Date (Baseline) is the date that the milestone is planned for
completion based on the master programme agreed with the appointed Main
Contractor.  It is the baseline date for projects in the delivery phase; 
• The Current Projected Date is only relevant where there has been a deviation from
the baseline and a change in achieving the milestone has occurred; and 
• Actual Date is the date the milestone is completed.

Page 2

NEW PRIMARY SCHOOL AT BERTHA PARK
Overview
Council (Report No. 16/277 refers) approved funding for a new build primary school for North/West
Perth required to accommodate expected pupil numbers generated from planned housebuilding.  As
part of the School Estate Transformation Programme, on 2 November 2022, the Learning and Families
Committee (Report No. 22/265 refers) approved the outcome of the statutory consultation on catchment
changes and the establishment of a new primary school at Bertha Park with effect from August 2026. 
The proposed site is adjacent to Bertha Park High School.
Sources of Funding The approved funding from the Composite Capital Programme for this project is £24m.
Project Pre-delivery Progress
The Statutory Consultation for the new catchment area for the school concluded in November 2022. 
A New Project Request (NPR) was submitted to Hub East Central Scotland (HubCo) in February 2023 and the procurement process for the
Design Team is underway.  
In October 2022 a bid was submitted to the Scottish Government Learning Estate Investment Programme – Phase 3 for funding of 50%
towards the project.  If the bid is successful, the funding will be provided over a 25-year period based on the Council meeting specified
targets.
The planned date for operation of the new school is August 2026.  HubCo Stage 1 design work will commence imminently.

Page 3

BLAIRGOWRIE RECREATION CENTRE - REPLACEMENT
Overview
Council approved a replacement Recreation Centre at Blairgowrie High School (Report No. 16/277
refers).  This project will involve the replacement of the recreation centre on the playing fields of the
existing site.
Sources of Funding The approved funding from the Composite Capital Programme for this project is £36m.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current Projected
Date Actual Date Progress Update
Submit New Project Request
(NPR) November 2018  June 2019
The Planning Application was approved at
Planning and Placemaking Committee on
10 August 2022. 
On 1 March 2023 Council considered the
Full Business Case for the project (Report
No. 23/73 refers) and approved that the
budget be increased by £9.3M to £36M. 
This enabled Financial Close to be
concluded and construction work on the
new recreation centre is expected to
commence in May 2023.
HubCo Stage 1 Formal
Commencement September 2019  September 2019
Stage 1 Agreed November 2020  April 2021
Planning Application Submitted January 2021  December 2021
Planning Application Agreed March 2022  August 2022
HubCo Stage 2 Agreed September 2021  March 2023
Financial Close October 2021  April 2023
Site Start November 2021 May 2023 
Centre Operational  March 2023 December 2024 
Completion of External Works June 2024 July 2025

Page 4

METHVEN PRIMARY SCHOOL – REPLACEMENT DINING/ GYM FACILITIES
Overview
As part of the School Estate Transformation Programme, on 21 March 2018, Lifelong Learning
Committee (Report No. 18/84 refers) approved the project to replace both the life-expired dining/gym
facilities to improve the condition of Methven Primary School.
Sources of Funding The project will be funded from the Composite Capital Programme.
Project Pre-delivery Progress
A feasibility exercise was carried out for the whole site and a preferred option has been selected which involves the construction of a standalone
building to house the dining and gym facilities.  Substantial enabling works have been completed on site including the demolition of the life-expired
gym hall and improvements to the site access and external landscape.
Design work for the new building is progressing and the programme to completion is currently being developed which will identify key project
milestones.

Page 5

PERTH ACADEMY - REFURBISHMENT
Overview
Funding has been secured to undertake a partial refurbishment of the existing school facilities to improve
the condition and suitability.  Due to the live school environment, ongoing works are being phased into
manageable packages as part of a rolling programme.
Sources of Funding This project is funded by the Composite Capital Programme.  The budget allocation was £16.9m, of
which £8.315m remains.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Phase 1 Refurbishment Works
complete on site
June 2021  July 2021 This phase involved various upgrades including a
new CCTV installation, corridor lighting, external
structural repairs, CDT ventilation and major
infrastructure upgrades to the PE building.
Phase 2 Refurbishment Works
complete on site
August 2021  August 2021 This phase involved improvements to student
social space and classroom refurbishments.
Phase 3 Refurbishment Works
commenced on site 
June 2022 Ten classrooms were refurbished during the
2022 summer holidays. 
Phase 3 Refurbishment Works
complete on site
August 2023   Further classrooms are being refurbished during
term time.  External consultants have been
appointed and are undertaking AV/Wi-Fi upgrade
surveys and design work.  Ground floor pupil
toilets will be refurbished in Summer 2023.  In
addition, extensive roof upgrades have been
completed and a furniture replacement
programme is underway.
Phase 4 Science Block Fabric
Upgrades
August 2024   Replacement of the curtain walling at the science
block will improve the energy efficiency and
performance of the external façade.

Page 6

PERTH GRAMMAR SCHOOL - REFURBISHMENT
Overview
Funding is available to undertake infrastructure upgrades to the existing school building.  Additionally,
approval was given for works to improve the entrance, reception and administration facilities which were
carried out.  Due to the live school environment, ongoing works are being phased into manageable
packages as part of a rolling programme.
Sources of Funding This project is funded by the Composite Capital Programme.  The original budget was £7.05m, of which
£4.967m remains.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Phases 1-4 Toilet
Refurbishment Works complete
on site  
October 2021 All planned toilet refurbishment phases were
completed between April – October 2021.
Phase 1 Classroom
Refurbishment Work complete
on site
August 2022  August 2022 This phase involved improvements to student
social space and classroom refurbishments.
Audio Visual Replacement
Programme
April 2023  April 2023 Smart panels and display screens have been
replaced in teaching spaces.  Wi-Fi upgrades
will be undertaken in a future phase.
Future Phases TBC   The next phases of refurbishment are currently
being planned.

Page 7

PERTH HIGH SCHOOL REPLACEMENT
Overview Council approved the replacement of Perth High School (Report No. 18/212 refers).  This project will
involve the replacement of the existing school building on the playing field of the existing site.
Sources of Funding
The approved funding from the Composite Capital Programme for this project is £80.2M.  A bid made to
the Scottish Government Learning Estate Investment Programme – Phase 2 for funding of 50% towards
the project was successful.  The funding will be provided over a 25-year period based on the Council
meeting specified targets.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Submit NPR  June 2019  June 2019
On 21 December 2022 Council considered the
full business case for the project (Report No. 
22/312 refers) and approved that the budget
be increased by £11.5M to £80.2M.  This
enabled Financial Close to be concluded and
construction works on the new school building
commenced in February 2023. 
HubCo Stage 1 Formal
Commencement July 2019  July 2019
Stage 1 Agreed May 2020  February 2021
Planning Application Submitted April 2021  September 2021
Planning Application Agreed August 2021  March 2022
HubCo Stage 2 Agreed January 2022  February 2023
Financial Close February 2022  March 2023
Site Start March 2022  February 2023
Construction Works Complete June 2024 July 2025 
School Operational  August 2024 August 2025 
Completion of External Works July 2025 August 2026

Page 8

RATTRAY PRIMARY SCHOOL – NURSERY EXTENSION & REFURBISHMENT
Overview
Lifelong Learning Committee approved Education and Children’s Services Early Learning and Childcare
(ELC) Expansion Plan (Report No. 17/314 refers).  As part of the plan, it was proposed that the capacity
of the nursery at Rattray Primary School will be increased by 26. 
Sources of Funding The Scottish Government confirmed Perth and Kinross Council’s allocation of capital funding for the
expansion of ELC.  The budget for Rattray Primary School was £4,325,000.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Review of Feasibility Study March 2018  March 2018
The extended nursery became operational in
Summer 2022.
Planning Application Submitted November 2018  January 2019
Planning Application Agreed December 2018  May 2019
Contract Cost Agreed April 2020  January 2021
Site Start June 2020  June 2021
Construction Works Complete August 2021  October 2022
Nursery Provision Operational August 2020  July 2022

Page 9

RIVERSIDE PRIMARY SCHOOL – NEW BUILD SCHOOL
Overview
As part of the School Estate Transformation Programme Council, Lifelong Learning Committee (Report
No. 18/15 refers) approved the construction of a new primary school on the playing field of the existing
North Muirton Primary School site to accommodate pupils from both North Muirton and Balhousie
Primary Schools.
Sources of Funding
The approved funding from the Composite Capital Programme for this project is £19.9m.  A bid made to
the Scottish Government Learning Estate Investment Programme – Phase 2 for funding of 50% towards
the project was successful.  The funding will be provided over a 25-year period based on the Council
meeting specified targets.
Project Delivery Progress
Key Milestone Programme
Date (Baseline)
Current
Projected Date Actual Date Progress Update
Submit NPR June 2019  July 2019
Phase 1 is nearing completion with Riverside
Primary School due to be operational in June
2023.  Phase 2, including the demolition of the
former North Muirton Primary School building,
will commence thereafter.
HubCo Stage 1 Formal
Commencement November 2019  November 2019
Stage 1 Agreed May 2020  November 2020
Planning Application Submitted January 2021  January 2021
Planning Application Agreed May 2021  May 2021
Stage 2 Agreed July 2021  October 2021
Financial Close August 2021  October 2021
Site Start September 2021  November 2021
School Operational  April 2023 June 2023 
Completion of External Works July 2023