PERTH AND KINROSS COUNCIL 
PROPERTY SUB-COMMITTEE 
1 MAY 2023 
LEARNING ESTATE PROGRAMME – PROGRESS UPDATE 
Report by Executive Director (Education and Children’s Services)
(Report No. 23/123) 
1. PURPOSE 
1.1 This report updates the Property Sub-Committee on the progress for
delivering the current major projects within the Education and Children’s
Services (ECS) Learning Estate Programme.  It details key milestones which
have been achieved since the last update to Property Sub-Committee on 
13 June 2022 (Report No. 22/121 refers). 
2. RECOMMENDATION 
2.1 It is recommended that the Committee: 
• Notes the significant milestones that have been achieved, rescheduled or
updated since the previous Property Sub-Committee meeting on 13 June
2022: 
➢ New Primary School at Bertha Park
• A New Project Request (NPR) for the project was submitted to Hub
East Central Scotland (HubCo) in February 2023;
• The procurement process to select the Design Team is underway.
• A bid for Learning Estate Investment Programme – Phase 3 (LEIP
3) funding for the project has been submitted to the Scottish
Government (6.3); 
➢ Blairgowrie Recreation Centre – Replacement
• The planning application was approved at the Planning and
Placemaking Committee on 10 August 2022;
• Following Council approval of additional funding on 1 March 2023,
construction work is expected to commence on site in May 2023
(6.4); 
➢ Phase 3 of refurbishment works at Perth Academy is progressing well
with 15 classrooms now refurbished and roofing works completed (6.5); 
➢ Phase 1 of classroom refurbishment work at Perth Grammar School
was completed in August 2022 and a programme to replace audio
visual equipment in teaching spaces was completed in April 2023 (6.6);

Page 2

➢ Following Council approval on 21 December 2022, the replacement of
Perth High School commenced on site in February 2023 (6.7); and 
➢ The extended nursery at Rattray Primary School became operational in
Summer 2022 (6.8). 
• Notes that the project teams continue to manage the impact of
Brexit/COVID-19/construction supply capacity, and the war in Ukraine, on
projects. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background
• Section 5: Progress
• Section 6: Updates on Current Programme 
• Appendices 
4. BACKGROUND 
4.1 The Learning Estate Strategy (November 2021) (Report No. 21/202 refers) sets
out the Council’s aspirations for our schools, and in particular, the high value
we place on learning, through our vision for well designed, maintained and
managed schools. 
4.2 The strategy is delivered through the Learning Estate Management Plan
(LEMP), approved by Lifelong Learning Committee in November 2021, which
is primarily funded through the Council Capital Programme. 
4.3 The ECS Capital Programme details the priorities for the Learning Estate until
2027/28 and is reviewed on an annual basis. 
5. PROGRESS 
5.1 This report updates Committee on the progress for delivering the current
projects within the ECS Learning Estate Programme.  The focus of the
programme is on: 
• Primary School Upgrades; 
• New Primary School Projects;
• Secondary School Upgrades;
• Replacement Secondary School; and
• Recreation Centre Replacement. 
5.2 Brexit/COVID-19/construction supply capacity, and the war in Ukraine, are
having an impact on all projects and there is currently an increase in tender
and material prices being experienced across the construction industry.

Page 3

5.3 Project teams have regular dialogue regarding options and solutions to
manage the impact of the changing situation.   
6. UPDATES ON CURRENT PROGRAMME 
6.1 Detailed updates on all current projects are provided in Appendix 1. 
6.2 The following is an update on significant project milestones since previously
reported to the Property Sub-Committee. 
6.3 New Primary School at Bertha Park 
6.3.1 As part of the School Estate Transformation Programme, the Learning and
Families Committee on 2 November 2022 approved the site adjacent to
Bertha Park High School for a new primary school (Report No. 22/265 refers). 
The extra capacity in the primary school estate is required to accommodate
expected pupil numbers generated from planned housebuilding within the
strategic sites at the north and north west of Perth. 
6.3.2 The NPR was submitted to HubCo in February 2023 and the selection
process for the Design Team is underway. 
6.3.3 A bid for LEIP 3 funding for the project has been submitted to the Scottish
Government.  If successful, the funding of 50% towards the project will be
provided over a 25-year period based on the Council meeting specified
targets. 
6.4 Blairgowrie Recreation Centre - Replacement 
6.4.1 The Council has approved a replacement recreation centre at Blairgowrie
High School (Report No. 16/277 refers). 
6.4.2 The Planning Application was approved at Planning and Placemaking
Committee on 10 August 2022 (Report No. 22/178 refers). 
6.4.3 On 1 March 2023, Council considered the Full Business Case for the project
(Report No. 23/73 refers) and agreed to proceed with an increased capital
budget for the project.  This enabled Financial Close to be reached and
construction work is expected to commence on site in May 2023. 
6.5 Perth Academy 
6.5.1 Funding has been secured to undertake a partial refurbishment of Perth
Academy to improve the condition and suitability of the facilities.  Due to the
live school environment, ongoing works are being phased into manageable
packages as part of a rolling programme. 
6.5.2 As part of the third phase of works, a further 15 classrooms have been
refurbished and roofing upgrades have been completed.

Page 4

6.6 Perth Grammar School 
6.6.1 Funding is allocated to undertake infrastructure upgrades to Perth Grammar
School.  Due to the live school environment, ongoing works are being phased
into manageable packages as part of a rolling programme. 
6.6.2 In August 2022, the first phase of ten classroom refurbishments was
completed.  In addition, a programme to replace audio visual equipment in
teaching spaces was completed in April 2023. 
6.7 Perth High School 
6.7.1 On 20 June 2018, Council approved funding from the Composite Capital
Budget (Report No. 18/212 refers) for the replacement of Perth High School. 
6.7.2 On 21 December 2022, Council considered the Full Business Case (Report
No. 22/312 refers) and approved that the project proceed with an increased
capital budget for the project.  This enabled Financial Close to be concluded
and construction works on the new school building commenced in     February
2023. 
6.8 Rattray Primary School 
6.8.1 As a part of the ELC Expansion Plan (Report No. 17/314 refers), a nursery
extension was approved for Rattray Primary School. 
6.8.2 The extended nursery became operational in Summer 2022. 
Author
Name Designation Contact Details
Greg Boland Head of Business and
Resources
ECSCommittee@pkc.gov.uk 
01738 475000 
Approved
Name Designation Date
Sheena Devlin Executive Director (Education
and Children’s Services)
20 April 2023

Page 5

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION  
Strategic Implications Yes/None
Community Plan/Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce No
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  No 
1. Strategic Implications  
Corporate Plan 
1.1 This section sets out how the proposals relate to the delivery of the Perth and
Kinross Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.   
Corporate Plan 
1.2 This section sets out how the proposals relate to the achievement of the
Council’s Corporate Plan Objectives: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.

Page 6

1.3 The report also links to the Education & Children’s Services Vision, Values
and Priorities in respect of the following key Priority area: 
• Learning and Achievement 
2. Resource Implications 
Financial 
2.1 The meeting of the Council on 1 March 2023 approved the Composite
Capital budget 2023/24 to 2027/28 (Report No. 23/73 refers). 
2.1.1 Any additional revenue implications identified through either the existing
Capital Programme, or future Capital Programmes will require to be
submitted as part of an expenditure pressure with a corresponding saving
through the ECS Revenue Budget process. 
2.1.2 There are no direct financial implications arising from this report other than
those reported within the body of the main report and related business
cases. 
Workforce 
2.2 There are no direct workforce implications arising from this report. 
Asset Management (land, property, IT) 
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.   
3.1.1 The proposals have been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals.

Page 7

3.2.1 The proposals have been considered under the Act; however, no action is
required as the Act does not apply to the matters presented in this report. 
This is because the Committee are requested to note the contents of the
report only and the Committee are not being requested to approve, adopt
or agree to an action or to set the framework for future decisions. 
Sustainability 
3.3 Under the provisions of the Local Government in Scotland Act 2003, the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.  Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• In the way best calculated to delivery of the Act’s emissions reduction
targets.
• In the way best calculated to deliver any statutory adaption programmes.
• In a way that it considers most sustainable. 
3.3.1 The information contained within this report has been considered under
the Act.  However, no action is required as the Act does not apply to the
matters presented in this report. 
Legal and Governance 
3.4 The Head of Legal and Governance Services has been consulted in the
preparation of this report. 
3.5 N/A 
Risk 
3.6 Individual risk profiles are in place for individual projects listed. 
4. Consultation 
Internal 
4.1 The Head of Finance, Head of Legal and Governance Services and Head of
Property Services have been consulted in the preparation of this report.   
External 
4.2 Participation and involvement of the community are critical to the ongoing and
future success of school estate investment and an emphasis is placed on
ensuring consultation, over and above that which might be required in terms
of planning requirements and statutory consultation requirements. 
4.2.1 A User Reference Group (URG), or equivalent, is set up for all major and
large projects.  The purpose of the URG is to assist with providing relevant

Page 8

local input to allow the Design Team to develop the outline concept design
into an operational design.  The formation of a URG is an invaluable source of
information, and any project is reliant on this level of local detail. 
5. Communication 
5.1 A stakeholder communication plan is developed for all major and large
projects.  The plan aims to support effective communication and
engagement with all project stakeholders. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (and not containing confidential or exempt information)
were relied on to a material extent in preparing the above report. 
3. APPENDICES  
3.1 Appendix 1 – Detailed Updates on Current Projects (June 2022 – May 2023)