Agenda Document Pack - Property Sub-Committee - 13/06/2022

Perth and Kinross Council · 13 June 2022
Back to Property Sub-Committee — 13 June 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Securing the future… • Improving services 
• Enhancing quality of life • Making the best use of public
resources 
Council Building
2 High Street
Perth
PH1 5PH 
06/06/2022 
A meeting of the Property Sub-Committee will be held virtually on Monday, 13
June 2022 at 10:00. 
If you have any queries please contact Committee Services on (01738) 475000 or
email Committee@pkc.gov.uk. 
THOMAS GLEN
Chief Executive 
Those attending the meeting are requested to ensure that all notifications are
silent on their device and other devices are in silent mode. 
Please note that the meeting will be broadcast online and recorded.  The
recording will be publicly available on the Council’s website following the
meeting. 
Members:
Councillor Grant Laing  (Convener)
Councillor Eric Drysdale  (Vice-Convener)
Councillor Peter Barrett
Councillor Andy Chan
Councillor Dave Cuthbert
Councillor Angus Forbes
Councillor Tom McEwan
Page 1 of 22

Page 2

Page 2 of 22

Page 3

Property Sub-Committee 
Monday, 13 June 2022 
AGENDA 
MEMBERS ARE REMINDED OF THEIR OBLIGATION TO DECLARE ANY
FINANCIAL OR NON-FINANCIAL INTEREST WHICH THEY MAY HAVE IN ANY
ITEM ON THIS AGENDA IN ACCORDANCE WITH THE COUNCILLORS’ CODE
OF CONDUCT. 
1 WELCOME AND APOLOGIES   
2 DECLARATIONS OF INTEREST   
3 MINUTE OF MEETING OF PROPERTY SUB-COMMITTEE OF 16
MARCH 2022
(copy herewith) 
5 - 6 
4 LEARNING ESTATE PROGRAMME - PROGRESS REPORT
Report by Executive Director (Education and Children's Services)
(copy herewith 22/121) 
7 - 22 
Page 3 of 22

Page 4

Page 4 of 22

Page 5

PROPERTY SUB-COMMITTEE 
Minute of meeting of the Special Property Sub-Committee of the Strategic Policy and
Resources Committee held virtually on Wednesday 16 March 2022 at 1.00pm. 
Present:  Councillors M Lyle, R McCall, A Bailey, S Donaldson (substituting for
G Laing) and W Wilson. 
In Attendance: K Farmer, R Jobson and C Rowan (all Communities);  A Thomson,
C Irons, A Brown and M Pasternak (all Corporate and Democratic Services). 
Apologies: Councillors G Laing, T McEwan and C Shiers. 
Councillor M Lyle, Presiding 
1. APOLOGIES/SUBSTITUTES 
Apologies and a substitution were noted as above. 
2. DECLARATIONS OF INTEREST 
There were no Declarations of Interest made in terms of the Councillors’ Code
of Conduct. 
IT WAS AGREED THAT THE PUBLIC AND PRESS SHOULD BE
EXCLUDED DURING CONSIDERATION OF THE FOLLOWING ITEM IN ORDER
TO AVOID THE DISCLOSURE OF INFORMATION WHICH IS EXEMPT IN TERMS
OF SCHEDULE 7A TO THE LOCAL GOVERNMENT (SCOTLAND) ACT 1973 
P1. PROPOSED DISPOSAL OF 1.21 HECTARES OF INDUSTRIAL LAND
(SITE 5), KINROSS WEST, KINROSS 
There was submitted a report by the Head of Planning and Development
(22/59) seeking approval to dispose of Site 5, Kinross West, Kinross which is part of
the Council’s Commercial Property Investment Programme. 
Resolved: 
The disposal of 1.21 hectares of industrial land (site 5), Kinross West, Kinross
on the terms as detailed in Report 22/59 and otherwise on terms to be agreed by the
Head of Planning and Development and the Head of Legal and Governance, be
approved.    
3
Page 5 of 22

Page 6

Page 6 of 22

Page 7

PERTH AND KINROSS COUNCIL 
PROPERTY SUB-COMMITTEE 
13 JUNE 2022 
LEARNING ESTATE PROGRAMME – PROGRESS UPDATE
Report by Executive Director (Education and Children’s Services)
(Report No 22/121)
1. PURPOSE 
1.1 This report updates the Property Sub-Committee on the progress for
delivering the current major projects within the Education and Children’s
Services (ECS) Learning Estate Programme.  It details key milestones which
have been achieved since the last update to Property Sub-Committee on 
10 January 2022 (Report No. 22/2 refers). 
2.       RECOMMENDATION
2.1 It is recommended that the Committee: 
• Notes the significant milestones achieved since the previous
Property Sub-Committee meeting held on 
10 January 2022: 
➢ As part of the Early Learning and Childcare (ELC)
expansion and infrastructure plan, the nursery extension
at Rattray Primary School has been completed (6.3); 
➢ The planning application for the new build Perth High
School has been approved (6.4); and 
➢ Construction works for the North Muirton/Balhousie
Primary School project continue to progress well. 
Lifelong Learning Committee approved the proposal to
name the new combined primary school Riverside
Primary School (6.5). 
• Notes that project teams continue to manage the impact of
Brexit/COVID-19/Construction supply capacity, and the war in
Ukraine, on projects. 
3.  STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
4
Page 7 of 22

Page 8

• Section 4: Background
• Section 5: Progress
• Section 6: Updates on Current Programme 
• Appendices 
4.  BACKGROUND 
4.1 The Learning Estate Strategy (November 2021) (Report No. 21/202 refers) sets
out the Council’s aspirations for our schools, and in particular, the high value
we place on learning, through our vision for well designed, maintained and
managed schools. 
4.2 The strategy is delivered through the Learning Estate Management Plan
(LEMP), approved by Lifelong Learning Committee in November 2021, which
is primarily funded through the Council Capital Programme. 
4.3 The ECS Capital Programme details the priorities for the Learning Estate
until 2028 and is reviewed on an annual basis. 
5.  PROGRESS 
5.1 This report updates Committee on the progress for delivering the current
projects within the ECS Learning Estate Programme.  The focus of the
programme is on: 
• ELC Expansion;
• Primary School Upgrades/Replacements; 
• Secondary School Upgrades/Replacement; and
• Recreation Centre Development. 
5.2 In March 2020, construction activity stopped across all projects as a result of
the COVID-19 pandemic.  Design work continued, where possible, on
projects still in the pre-construction phase.  The long-term impact of the
pandemic to project timescales is yet to be fully understood, but there is an
expectation that new methods for working will result in extended construction
programmes and associated possible increases in costs exacerbated by
supply chain uncertainty.  The impact of Brexit/COVID-19/construction
supply capacity, and the war in Ukraine, is yet to be determined but there is
currently an increase in tender and material prices being experienced on
projects across the country. 
5.3 Project Teams have regular dialogue regarding options and solutions to
manage the impact of the changing situation.  Work is constantly undertaken
to develop various business continuity approaches in response to the
ongoing pandemic. 
6. UPDATES ON CURRENT PROGRAMME 
6.1 Detailed updates on all current projects are provided in Appendix A. 
6.2 The following is an update on significant project milestones since previously
Page 8 of 22

Page 9

reported to the Property Sub-Committee on 10 January 2022. 
6.3 Early Learning and Childcare Expansion 
6.3.1 As part of the ELC Plan (Report No. 17/314 refers), various infrastructure
projects were identified to expand ELC capacity in response to the Scottish
Government commitment to increase ELC delivery to 1140 hours per
annum. 
6.3.2 Construction works to the nursery extension at Rattray Primary School are
complete and the nursery will be operational by the end of June 2022. 
6.4 Perth High School 
6.4.1 On 20 June 2018, Council approved funding from the Composite Capital
Budget (Report No. 18/212 refers) for the replacement of Perth High School. 
6.4.2 The planning application was approved at Planning and Development
Management Committee on 16 March 2022. 
6.5 Riverside Primary School 
6.5.1 As part of the School Estate Transformation Programme, Lifelong Learning
Committee (Report No. 18/15 refers) approved the construction of a new
primary school on the playing field of the existing North Muirton Primary
School site.  The new building will accommodate pupils from both North
Muirton Primary School and Balhousie Primary School (Report No. 18/349
refers). 
6.5.2 Construction works continue to progress well on site with the structural frame
now erected.  The planned operational date remains on target for April 2023. 
6.5.3 On 31 January 2022, Lifelong Learning Committee approved the proposal to
name the new primary school as Riverside Primary School (Report No.
22/23 refers).  This was further to a consultation process involving pupils,
parents, staff, the community, local elected members and the Conveners of
Lifelong Learning Committee. 
Author
Name Designation Contact Details
Greg Boland Head of Business
and Resources
ECSCommittee@pkc.gov.uk 
01738 47500 
Approved
Name Designation Date
Sheena Devlin  Executive Director
(Education and Children’s
Services)
01/06/22
Page 9 of 22

Page 10

Page 10 of 22

Page 11

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION  
Strategic Implications Yes/None
Community Plan/Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce No
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  No 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This section sets out how the proposals relate to the delivery of the Perth and
Kinross Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.   
Corporate Plan 
1.2 This section sets out how the proposals relate to the achievement of the
Council’s Corporate Plan Objectives: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.  
Page 11 of 22

Page 12

1.3 The report also links to the Education & Children’s Services Vision, Values
and Priorities in respect of the following key Priority area: 
• Learning and Achievement 
2. Resource Implications 
Financial 
2.1 The meeting of the Council on 23 February 2022 approved the move to a 
6-year funded Capital Delivery Programme covering the period 2022/23 to
2027-28 (Report No. 22/36 refers). 
2.1.1 Any additional revenue implications identified through either the existing
Capital Programme, or future Capital Programmes will require to be
submitted as part of an expenditure pressure with a corresponding saving
through the ECS revenue budget process. 
2.1.2 There are no direct financial implications arising from this report other than
those reported within the body of the main report and related business
cases. 
Workforce 
2.2 There are no direct workforce implications arising from this report. 
Asset Management (land, property, IT) 
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.   
3.1.1 The proposals have been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
Page 12 of 22

Page 13

3.2.1 However, no action is required as the Act does not apply to the matters
presented in this report. This is because these matters relate to the School
Estate Strategy which is being considered under the Act as part of The
Council’s Asset Management Plan. 
Sustainability 
3.3 Under the provisions of the Local Government in Scotland Act 2003, the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.  Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• In the way best calculated to delivery of the Act’s emissions reduction
targets.
• In the way best calculated to deliver any statutory adaption programmes.
• In a way that it considers most sustainable. 
3.3.1 The information contained within this report has been considered under
the Act.  However, no action is required as the Act does not apply to the
matters presented in this report. 
Legal and Governance 
3.4 The Head of Legal and Governance Services has been consulted in the
preparation of this report. 
3.5 N/A 
Risk 
3.6 Individual risk profiles are in place for individual projects listed. 
4. Consultation 
Internal 
4.1 The Head of Finance, Head of Legal and Governance Services and Head of
Property Services have been consulted in the preparation of this report.   
External 
4.2 Participation and involvement of the community are critical to the ongoing and
future success of school estate investment and an emphasis is placed on
ensuring consultation, over and above that which might be required in terms
of planning requirements and statutory consultation requirements. 
4.2.1 A User Reference Group (URG), or equivalent, is set up for all major and
large projects.  The purpose of the URG is to assist with providing relevant
local input to allow the Design Team to develop the outline concept design
into an operational design.  The formation of a URG is an invaluable source of
information, and any project is reliant on this level of local detail.
Page 13 of 22

Page 14

5. Communication 
5.1 A stakeholder communication plan is developed for all major and large
projects.  The plan aims to support effective communication and
engagement with all project stakeholders. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (and not containing confidential or exempt information)
were relied on to a material extent in preparing the above report. 
3. APPENDICES  
3.1 Appendix A – Detailed Updates on Current Projects January – June 2022  
Page 14 of 22

Page 15

APPENDIX A 
Detailed Updates on Current Projects
January 2022 – June 2022 
Milestones 
Milestones are key tasks within a project plan which mark completion of a significant or
critical phase of work or a decision point. 
In terms of the following projects the milestones have the following dates: 
• The planned date is the original date planned for the project and does not change in
the life of the project.  These are generally aspirational dates based on a typical
project; 
• The actual date is the date the milestone is completed; and 
• The forecast date is the date which is currently projected for completion. 
4
Page 15 of 22

Page 16

BLAIRGOWRIE RECREATION CENTRE - REPLACEMENT 
Overview
Council (Report No. 16/277 refers) approved a replacement Recreation Centre at
Blairgowrie High School.
Sources of Funding
The approved funding from the ECS Composite Capital Programme for this project is
£26.7m. 
Progress Update
Detailed design and tendering of work packages are progressing. 
The first User Reference Group was held virtually by email during May 2020 with four
subsequent meetings held in September 2020, November 2020, May 2021 and June
2022.
Key Milestones
Milestone Planned Date Actual Date Forecast Date
End of Consultation Period and
Development of Brief November 2018 November 2018 
Submit NPR November 2018 June 2019 
HubCo Stage 1 Formal
Commencement September 2019 September 2019 
Stage 1 Agreed November 2020 April 2021 
Planning Application Submitted January 2021 December 2021 
Planning Application Agreed March 2022  TBC
Stage 2 Agreed September 2021  TBC
Financial Close October 2021  TBC
Site Start November 2021  TBC
Centre Operational March 2023  TBC
Completion of External Works June 2024  TBC 
Current Issues
A delay in the planning process, due to statutory consultee negotiations and approval, has
resulted in a programme delay.  In addition, due to current market volatility, achieving
Financial Close is proving very challenging, therefore, Stage 2 of the process has been
extended.  This will result in a revised operational date for the centre. 
The impact of Brexit/COVID-19/construction supply capacity, and the war in Ukraine, is
affecting costs and tender returns.  
Page 16 of 22

Page 17

PERTH ACADEMY – REFURBISHMENT 
Overview
Funding has been secured to undertake a partial refurbishment of the existing school
facilities to improve the condition and suitability.  Due to the live school environment,
ongoing works are being phased into manageable packages as part of a rolling
programme.
Sources of Funding
This project is funded by the ECS Composite Capital Programme.  The budget allocated
was £16.9m, of which £10.049m remains.
Progress Update
Phase 1 was completed in 2021 involving various upgrades including a new CCTV
installation, corridor lighting, external structural repairs, CDT ventilation and major
infrastructure upgrades to the PE building.  Phase 2, also completed in 2021, involved
improvements to student social space and classroom refurbishments.  
Phase 3 Refurbishment Works package will be on site from July 2022 including classroom
refurbishments, additional social spaces and roof replacement works.  Ten classrooms will
be complete during the 2022 summer holidays and then further classroom refurbishment
will continue during term time.  As part of this phase, external consultants have been
appointed and are undertaking AV/Wi-Fi upgrade surveys and design work.  A furniture
replacement programme is also underway. 
Key Milestones
Milestone Planned Date Actual Date Forecast Date
Phase 1 Refurbishment Works
complete on site June 2021 July 2021 
Phase 2 Refurbishment Works
complete on site August 2021 August 2021 
Phase 3 Refurbishment Works
complete on site June 2023   
Current Issues
The impact of Brexit/COVID-19/construction supply capacity, and the war in Ukraine, may
affect costs and tender returns as the ongoing phases progress.
Page 17 of 22

Page 18

PERTH GRAMMAR SCHOOL – REFURBISHMENT 
Overview
Funding is available to undertake infrastructure upgrades to the existing school building. 
Additionally, approval was given for works to improve the entrance, reception and
administration facilities which were carried out.  Due to the live school environment,
ongoing works are being phased into manageable packages as part of a rolling
programme.
Sources of Funding
This project is funded by the ECS Composite Capital Programme.  The original budget
was £7.05m, of which £5.581m remains.
Progress Update
All toilet refurbishment phases were completed by October 2021. 
Phase 1 of classroom refurbishments will proceed during the summer holidays 2022 and
involves upgrades of ten teaching spaces. 
Key Milestones 
Milestone Planned Date Actual Date Forecast Date
Phase 1 Toilet Refurbishment
Works complete on site April 2021 April 2021 
Phase 2 Toilet Refurbishment
Works complete on site July 2021 July 2021 
Phase 3 Toilet Refurbishment
Works complete on site August 2021 August 2021 
Phase 4 Toilet Refurbishment
Works complete on site September 2021 October 2021 
Phase 1 Class Refurbishment
Works complete on site August 2022   
Current Issues
The impact of Brexit/COVID-19/construction supply capacity, and the war in Ukraine, may
affect costs and tender returns as the ongoing phases progress.  
Page 18 of 22

Page 19

PERTH HIGH SCHOOL – REPLACEMENT 
Overview
Council approved the replacement of Perth High School (Report No. 18/212 refers).  This
project will involve the replacement of the existing school building on the playing field of
the existing site. 
Sources of Funding
The approved funding from the ECS Composite Capital Programme for this project is
£68.7m.  A bid made to the Scottish Government Learning Estate Investment Programme
– Phase 2 for funding of 50% towards the project was successful.  The funding will be
provided over a 25-year period based on the Council meeting specified targets. 
Progress Update
The planning application was approved in March 2022.
Key Milestones 
Milestone Planned Date Actual Date Forecast Date
Submit Final NPR June 2019 June 2019 
HubCo Stage 1
Formal Commencement July 2019 July 2019 
Stage 1 Agreed May 2020 Feb 2021 
Planning Application
Submitted April 2021 Sept 2021 
Planning Application Agreed August 2021 March 2022 
Stage 2 Agreed January 2022  TBC
Financial Close February 2022  TBC
Site Start March 2022  TBC
Construction Works Complete June 2024  TBC
School Operational August 2024  TBC
Completion of External Works August 2025  TBC 
Current Issues
Due to current market volatility, achieving Financial Close is proving very challenging,
therefore, Stage 2 of the process has been extended.  This will result in a revised
operational date for the new school.
The impact of Brexit/COVID-19, and the war in Ukraine, may cause delays as the project
progresses. 
Page 19 of 22

Page 20

RATTRAY PRIMARY SCHOOL - NURSERY EXTENSION & REFURBISHMENT 
Overview
Lifelong Learning Committee approved Education and Children’s Services Early Learning
and Childcare (ELC) Expansion Plan (Report No. 17/314 refers).  As part of the plan, it
was proposed that the capacity of the nursery at Rattray Primary School will be increased
by 26. 
Sources of Funding
The Scottish Government confirmed Perth and Kinross Council’s allocation of capital
funding for the expansion of ELC.  The indicative budget for Rattray Primary School is
£4,325,000.
Progress Update
Construction of the nursery extension was re-phased due to COVID-19 restrictions
preventing works starting on the programmed date.  Works included a new nursery
extension, classroom refurbishments, new electric and heating infrastructure and new 
Wi-Fi with updated audio/visual technology in teaching spaces.  
All classrooms have now been refurbished.  The staff room and general-purpose space
will be refurbished following completion of the new nursery. 
Key Milestones
Milestone Planned Date Actual Date Forecast Date
Review of Feasibility Study March 2018 March 2018 
Planning Application Submitted November 2018 January 2019 
Planning Application Agreed December 2018 May 2019 
Contract Cost Agreed April 2020  January 2021 
Site Start June 2020 June 2021 
Construction Works Complete August 2021  August 2022
Nursery Provision Operational August 2020  June 2022 
Current Issues
No issues. 
Page 20 of 22

Page 21

RIVERSIDE PRIMARY SCHOOL – NEW BUILD SCHOOL
Overview
As part of the School Estate Transformation Programme Council, Lifelong Learning
Committee (Report No. 18/15 refers) approved the construction of a new primary school
on the playing field of the existing North Muirton Primary School site.  This new building
will accommodate pupils from both North Muirton and Balhousie Primary Schools.
Sources of Funding
The approved funding from the ECS Composite Capital Programme for this project is
£19.9m. 
Progress Update
Full planning approval was granted in May 2021, financial close was approved in October
2021 and the construction works began on-site November 2021.  Works continue to
progress well on site with the structural frame now erected.
On 31 January 2022, Lifelong Learning Committee (LLC) approved the proposal to name
the new primary school Riverside Primary School (Report No. 22/23 refers).
Key Milestones
Milestone Planned Date Actual Date Forecast Date
Submit NPR July 2019 July 2019 
HubCo Stage 1 Formal
Commencement Nov 2019 Nov 2019 
Stage 1 Agreed May 2020 Nov 2020 
Planning Application Submitted Jan 2021 Jan 2021 
Planning Application Agreed May 2021 May 2021 
Stage 2 Agreed July 2021 Oct 2021 
Financial Close Aug 2021 Oct 2021 
Site Start Sep 2021 Nov 2021 
School Operational April 2023  April 2023
Completion of External Works July 2023   
Current Issues
The impact of COVID-19, Brexit and the war in Ukraine on the supply chain may cause
delays as the project progresses. 
Page 21 of 22

Page 22

Page 22 of 22