APPENDIX A 
Detailed Updates on Current Projects
January 2022 – June 2022 
Milestones 
Milestones are key tasks within a project plan which mark completion of a significant or
critical phase of work or a decision point. 
In terms of the following projects the milestones have the following dates: 
• The planned date is the original date planned for the project and does not change in
the life of the project.  These are generally aspirational dates based on a typical
project; 
• The actual date is the date the milestone is completed; and 
• The forecast date is the date which is currently projected for completion.

Page 2

BLAIRGOWRIE RECREATION CENTRE - REPLACEMENT 
Overview
Council (Report No. 16/277 refers) approved a replacement Recreation Centre at
Blairgowrie High School.
Sources of Funding
The approved funding from the ECS Composite Capital Programme for this project is
£26.7m. 
Progress Update
Detailed design and tendering of work packages are progressing. 
The first User Reference Group was held virtually by email during May 2020 with four
subsequent meetings held in September 2020, November 2020, May 2021 and June
2022.
Key Milestones
Milestone Planned Date Actual Date Forecast Date
End of Consultation Period and
Development of Brief November 2018 November 2018 
Submit NPR November 2018 June 2019 
HubCo Stage 1 Formal
Commencement September 2019 September 2019 
Stage 1 Agreed November 2020 April 2021 
Planning Application Submitted January 2021 December 2021 
Planning Application Agreed March 2022  TBC
Stage 2 Agreed September 2021  TBC
Financial Close October 2021  TBC
Site Start November 2021  TBC
Centre Operational March 2023  TBC
Completion of External Works June 2024  TBC 
Current Issues
A delay in the planning process, due to statutory consultee negotiations and approval, has
resulted in a programme delay.  In addition, due to current market volatility, achieving
Financial Close is proving very challenging, therefore, Stage 2 of the process has been
extended.  This will result in a revised operational date for the centre. 
The impact of Brexit/COVID-19/construction supply capacity, and the war in Ukraine, is
affecting costs and tender returns.

Page 3

PERTH ACADEMY – REFURBISHMENT 
Overview
Funding has been secured to undertake a partial refurbishment of the existing school
facilities to improve the condition and suitability.  Due to the live school environment,
ongoing works are being phased into manageable packages as part of a rolling
programme.
Sources of Funding
This project is funded by the ECS Composite Capital Programme.  The budget allocated
was £16.9m, of which £10.049m remains.
Progress Update
Phase 1 was completed in 2021 involving various upgrades including a new CCTV
installation, corridor lighting, external structural repairs, CDT ventilation and major
infrastructure upgrades to the PE building.  Phase 2, also completed in 2021, involved
improvements to student social space and classroom refurbishments.  
Phase 3 Refurbishment Works package will be on site from July 2022 including classroom
refurbishments, additional social spaces and roof replacement works.  Ten classrooms will
be complete during the 2022 summer holidays and then further classroom refurbishment
will continue during term time.  As part of this phase, external consultants have been
appointed and are undertaking AV/Wi-Fi upgrade surveys and design work.  A furniture
replacement programme is also underway. 
Key Milestones
Milestone Planned Date Actual Date Forecast Date
Phase 1 Refurbishment Works
complete on site June 2021 July 2021 
Phase 2 Refurbishment Works
complete on site August 2021 August 2021 
Phase 3 Refurbishment Works
complete on site June 2023   
Current Issues
The impact of Brexit/COVID-19/construction supply capacity, and the war in Ukraine, may
affect costs and tender returns as the ongoing phases progress.

Page 4

PERTH GRAMMAR SCHOOL – REFURBISHMENT 
Overview
Funding is available to undertake infrastructure upgrades to the existing school building. 
Additionally, approval was given for works to improve the entrance, reception and
administration facilities which were carried out.  Due to the live school environment,
ongoing works are being phased into manageable packages as part of a rolling
programme.
Sources of Funding
This project is funded by the ECS Composite Capital Programme.  The original budget
was £7.05m, of which £5.581m remains.
Progress Update
All toilet refurbishment phases were completed by October 2021. 
Phase 1 of classroom refurbishments will proceed during the summer holidays 2022 and
involves upgrades of ten teaching spaces. 
Key Milestones 
Milestone Planned Date Actual Date Forecast Date
Phase 1 Toilet Refurbishment
Works complete on site April 2021 April 2021 
Phase 2 Toilet Refurbishment
Works complete on site July 2021 July 2021 
Phase 3 Toilet Refurbishment
Works complete on site August 2021 August 2021 
Phase 4 Toilet Refurbishment
Works complete on site September 2021 October 2021 
Phase 1 Class Refurbishment
Works complete on site August 2022   
Current Issues
The impact of Brexit/COVID-19/construction supply capacity, and the war in Ukraine, may
affect costs and tender returns as the ongoing phases progress.

Page 5

PERTH HIGH SCHOOL – REPLACEMENT 
Overview
Council approved the replacement of Perth High School (Report No. 18/212 refers).  This
project will involve the replacement of the existing school building on the playing field of
the existing site. 
Sources of Funding
The approved funding from the ECS Composite Capital Programme for this project is
£68.7m.  A bid made to the Scottish Government Learning Estate Investment Programme
– Phase 2 for funding of 50% towards the project was successful.  The funding will be
provided over a 25-year period based on the Council meeting specified targets. 
Progress Update
The planning application was approved in March 2022.
Key Milestones 
Milestone Planned Date Actual Date Forecast Date
Submit Final NPR June 2019 June 2019 
HubCo Stage 1
Formal Commencement July 2019 July 2019 
Stage 1 Agreed May 2020 Feb 2021 
Planning Application
Submitted April 2021 Sept 2021 
Planning Application Agreed August 2021 March 2022 
Stage 2 Agreed January 2022  TBC
Financial Close February 2022  TBC
Site Start March 2022  TBC
Construction Works Complete June 2024  TBC
School Operational August 2024  TBC
Completion of External Works August 2025  TBC 
Current Issues
Due to current market volatility, achieving Financial Close is proving very challenging,
therefore, Stage 2 of the process has been extended.  This will result in a revised
operational date for the new school.
The impact of Brexit/COVID-19, and the war in Ukraine, may cause delays as the project
progresses.

Page 6

RATTRAY PRIMARY SCHOOL - NURSERY EXTENSION & REFURBISHMENT 
Overview
Lifelong Learning Committee approved Education and Children’s Services Early Learning
and Childcare (ELC) Expansion Plan (Report No. 17/314 refers).  As part of the plan, it
was proposed that the capacity of the nursery at Rattray Primary School will be increased
by 26. 
Sources of Funding
The Scottish Government confirmed Perth and Kinross Council’s allocation of capital
funding for the expansion of ELC.  The indicative budget for Rattray Primary School is
£4,325,000.
Progress Update
Construction of the nursery extension was re-phased due to COVID-19 restrictions
preventing works starting on the programmed date.  Works included a new nursery
extension, classroom refurbishments, new electric and heating infrastructure and new 
Wi-Fi with updated audio/visual technology in teaching spaces.  
All classrooms have now been refurbished.  The staff room and general-purpose space
will be refurbished following completion of the new nursery. 
Key Milestones
Milestone Planned Date Actual Date Forecast Date
Review of Feasibility Study March 2018 March 2018 
Planning Application Submitted November 2018 January 2019 
Planning Application Agreed December 2018 May 2019 
Contract Cost Agreed April 2020  January 2021 
Site Start June 2020 June 2021 
Construction Works Complete August 2021  August 2022
Nursery Provision Operational August 2020  June 2022 
Current Issues
No issues.

Page 7

RIVERSIDE PRIMARY SCHOOL – NEW BUILD SCHOOL
Overview
As part of the School Estate Transformation Programme Council, Lifelong Learning
Committee (Report No. 18/15 refers) approved the construction of a new primary school
on the playing field of the existing North Muirton Primary School site.  This new building
will accommodate pupils from both North Muirton and Balhousie Primary Schools.
Sources of Funding
The approved funding from the ECS Composite Capital Programme for this project is
£19.9m. 
Progress Update
Full planning approval was granted in May 2021, financial close was approved in October
2021 and the construction works began on-site November 2021.  Works continue to
progress well on site with the structural frame now erected.
On 31 January 2022, Lifelong Learning Committee (LLC) approved the proposal to name
the new primary school Riverside Primary School (Report No. 22/23 refers).
Key Milestones
Milestone Planned Date Actual Date Forecast Date
Submit NPR July 2019 July 2019 
HubCo Stage 1 Formal
Commencement Nov 2019 Nov 2019 
Stage 1 Agreed May 2020 Nov 2020 
Planning Application Submitted Jan 2021 Jan 2021 
Planning Application Agreed May 2021 May 2021 
Stage 2 Agreed July 2021 Oct 2021 
Financial Close Aug 2021 Oct 2021 
Site Start Sep 2021 Nov 2021 
School Operational April 2023  April 2023
Completion of External Works July 2023   
Current Issues
The impact of COVID-19, Brexit and the war in Ukraine on the supply chain may cause
delays as the project progresses.