PERTH AND KINROSS COUNCIL 
PROPERTY SUB-COMMITTEE 
13 JUNE 2022 
LEARNING ESTATE PROGRAMME – PROGRESS UPDATE
Report by Executive Director (Education and Children’s Services)
(Report No 22/121)
1. PURPOSE 
1.1 This report updates the Property Sub-Committee on the progress for
delivering the current major projects within the Education and Children’s
Services (ECS) Learning Estate Programme.  It details key milestones which
have been achieved since the last update to Property Sub-Committee on 
10 January 2022 (Report No. 22/2 refers). 
2.       RECOMMENDATION
2.1 It is recommended that the Committee: 
• Notes the significant milestones achieved since the previous
Property Sub-Committee meeting held on 
10 January 2022: 
➢ As part of the Early Learning and Childcare (ELC)
expansion and infrastructure plan, the nursery extension
at Rattray Primary School has been completed (6.3); 
➢ The planning application for the new build Perth High
School has been approved (6.4); and 
➢ Construction works for the North Muirton/Balhousie
Primary School project continue to progress well. 
Lifelong Learning Committee approved the proposal to
name the new combined primary school Riverside
Primary School (6.5). 
• Notes that project teams continue to manage the impact of
Brexit/COVID-19/Construction supply capacity, and the war in
Ukraine, on projects. 
3.  STRUCTURE OF REPORT 
3.1 This report is structured over the following sections:

Page 2

• Section 4: Background
• Section 5: Progress
• Section 6: Updates on Current Programme 
• Appendices 
4.  BACKGROUND 
4.1 The Learning Estate Strategy (November 2021) (Report No. 21/202 refers) sets
out the Council’s aspirations for our schools, and in particular, the high value
we place on learning, through our vision for well designed, maintained and
managed schools. 
4.2 The strategy is delivered through the Learning Estate Management Plan
(LEMP), approved by Lifelong Learning Committee in November 2021, which
is primarily funded through the Council Capital Programme. 
4.3 The ECS Capital Programme details the priorities for the Learning Estate
until 2028 and is reviewed on an annual basis. 
5.  PROGRESS 
5.1 This report updates Committee on the progress for delivering the current
projects within the ECS Learning Estate Programme.  The focus of the
programme is on: 
• ELC Expansion;
• Primary School Upgrades/Replacements; 
• Secondary School Upgrades/Replacement; and
• Recreation Centre Development. 
5.2 In March 2020, construction activity stopped across all projects as a result of
the COVID-19 pandemic.  Design work continued, where possible, on
projects still in the pre-construction phase.  The long-term impact of the
pandemic to project timescales is yet to be fully understood, but there is an
expectation that new methods for working will result in extended construction
programmes and associated possible increases in costs exacerbated by
supply chain uncertainty.  The impact of Brexit/COVID-19/construction
supply capacity, and the war in Ukraine, is yet to be determined but there is
currently an increase in tender and material prices being experienced on
projects across the country. 
5.3 Project Teams have regular dialogue regarding options and solutions to
manage the impact of the changing situation.  Work is constantly undertaken
to develop various business continuity approaches in response to the
ongoing pandemic. 
6. UPDATES ON CURRENT PROGRAMME 
6.1 Detailed updates on all current projects are provided in Appendix A. 
6.2 The following is an update on significant project milestones since previously

Page 3

reported to the Property Sub-Committee on 10 January 2022. 
6.3 Early Learning and Childcare Expansion 
6.3.1 As part of the ELC Plan (Report No. 17/314 refers), various infrastructure
projects were identified to expand ELC capacity in response to the Scottish
Government commitment to increase ELC delivery to 1140 hours per
annum. 
6.3.2 Construction works to the nursery extension at Rattray Primary School are
complete and the nursery will be operational by the end of June 2022. 
6.4 Perth High School 
6.4.1 On 20 June 2018, Council approved funding from the Composite Capital
Budget (Report No. 18/212 refers) for the replacement of Perth High School. 
6.4.2 The planning application was approved at Planning and Development
Management Committee on 16 March 2022. 
6.5 Riverside Primary School 
6.5.1 As part of the School Estate Transformation Programme, Lifelong Learning
Committee (Report No. 18/15 refers) approved the construction of a new
primary school on the playing field of the existing North Muirton Primary
School site.  The new building will accommodate pupils from both North
Muirton Primary School and Balhousie Primary School (Report No. 18/349
refers). 
6.5.2 Construction works continue to progress well on site with the structural frame
now erected.  The planned operational date remains on target for April 2023. 
6.5.3 On 31 January 2022, Lifelong Learning Committee approved the proposal to
name the new primary school as Riverside Primary School (Report No.
22/23 refers).  This was further to a consultation process involving pupils,
parents, staff, the community, local elected members and the Conveners of
Lifelong Learning Committee. 
Author
Name Designation Contact Details
Greg Boland Head of Business
and Resources
ECSCommittee@pkc.gov.uk 
01738 47500 
Approved
Name Designation Date
Sheena Devlin  Executive Director
(Education and Children’s
Services)
01/06/22

Page 4

No embedded text on this page.

Page 5

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION  
Strategic Implications Yes/None
Community Plan/Single Outcome Agreement  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce No
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  Yes
Risk Yes
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  No 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 This section sets out how the proposals relate to the delivery of the Perth and
Kinross Community Plan/Single Outcome Agreement in terms of the following
priorities: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.   
Corporate Plan 
1.2 This section sets out how the proposals relate to the achievement of the
Council’s Corporate Plan Objectives: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
This report relates to all of these objectives.

Page 6

1.3 The report also links to the Education & Children’s Services Vision, Values
and Priorities in respect of the following key Priority area: 
• Learning and Achievement 
2. Resource Implications 
Financial 
2.1 The meeting of the Council on 23 February 2022 approved the move to a 
6-year funded Capital Delivery Programme covering the period 2022/23 to
2027-28 (Report No. 22/36 refers). 
2.1.1 Any additional revenue implications identified through either the existing
Capital Programme, or future Capital Programmes will require to be
submitted as part of an expenditure pressure with a corresponding saving
through the ECS revenue budget process. 
2.1.2 There are no direct financial implications arising from this report other than
those reported within the body of the main report and related business
cases. 
Workforce 
2.2 There are no direct workforce implications arising from this report. 
Asset Management (land, property, IT) 
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.   
3.1.1 The proposals have been considered under the Corporate Equalities Impact
Assessment process (EqIA) with the following outcome: 
(i) Assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.2 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals.

Page 7

3.2.1 However, no action is required as the Act does not apply to the matters
presented in this report. This is because these matters relate to the School
Estate Strategy which is being considered under the Act as part of The
Council’s Asset Management Plan. 
Sustainability 
3.3 Under the provisions of the Local Government in Scotland Act 2003, the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.  Under the Climate Change
(Scotland) Act 2009 the Council also has a duty relating to climate change
and, in exercising its functions must act: 
• In the way best calculated to delivery of the Act’s emissions reduction
targets.
• In the way best calculated to deliver any statutory adaption programmes.
• In a way that it considers most sustainable. 
3.3.1 The information contained within this report has been considered under
the Act.  However, no action is required as the Act does not apply to the
matters presented in this report. 
Legal and Governance 
3.4 The Head of Legal and Governance Services has been consulted in the
preparation of this report. 
3.5 N/A 
Risk 
3.6 Individual risk profiles are in place for individual projects listed. 
4. Consultation 
Internal 
4.1 The Head of Finance, Head of Legal and Governance Services and Head of
Property Services have been consulted in the preparation of this report.   
External 
4.2 Participation and involvement of the community are critical to the ongoing and
future success of school estate investment and an emphasis is placed on
ensuring consultation, over and above that which might be required in terms
of planning requirements and statutory consultation requirements. 
4.2.1 A User Reference Group (URG), or equivalent, is set up for all major and
large projects.  The purpose of the URG is to assist with providing relevant
local input to allow the Design Team to develop the outline concept design
into an operational design.  The formation of a URG is an invaluable source of
information, and any project is reliant on this level of local detail.

Page 8

5. Communication 
5.1 A stakeholder communication plan is developed for all major and large
projects.  The plan aims to support effective communication and
engagement with all project stakeholders. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (and not containing confidential or exempt information)
were relied on to a material extent in preparing the above report. 
3. APPENDICES  
3.1 Appendix A – Detailed Updates on Current Projects January – June 2022