SIGNIFICANT CAPITAL PROJECTS
PROGRESS UPDATE
APPENDIX IV
Project Title Total Gross
Budget
(£'000)
Third Party
Funding
(£'000)
Total Net
Budget
(£'000)
Projected
Outturn
(£'000)
Completion Date Contract
Awarded
On Site Status Change Since
Last Report
Additional Commentary
Blairgowrie Recreation
Centre - Replacement
36,000 0 36,000 36,000 Phase 1 completion
date December 2024,
phase 2 Easter 2025.
Yes Yes On track No Works are progressing well on-site.
New Primary School at
Bertha Park Site
24,000 0 24,000 24,000 Summer 2028 No No Rephased pending
review
Yes. Rephasing of the project to take account of the
projections for the number of catchment pupils.
Riverside Primary New
School
19,899 0 19,899 19,899 June 2023 Yes Yes Complete Yes. Complete
Perth High School - New
School Investment
80,200 0 80,200 80,200 Summer 2026 - school
building curently
scheduled to open
summer 2025
Yes Yes On track No Works are progressing on-site.
Harris
Academy/Invergowrie
Extension
5,200 0 5,200 5,200 Late 2023 Yes Yes On track No Main extension complete, reconfiguration works still to
be undertaken.
Cross Tay Link Road
(CTLR)
150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On programme No Works progressing well and remain on target for
completion in Spring 2025. on programme. Bridge deck
works due to commence and preparation works
underway for this.  One this is underway a detailed
analysis of contingency and compensation events will be
undertaken. 
Comrie Flood Protection
Scheme
28,435 0 28,435 28,435 Spring 2025 No No Advance works
complete; Main works
at tender assessment.
Yes Main works tender received in June 2023 but cost higher
than anticipated; tender assessment is currently on-
going (including independent tender estimate, tender
clarifications, tender negotiations and value
engineering). This work has also been delayed by recent
flood events. The next steps will include liaising with the
Scottish Government to seek an increase in capital grant
(equal to 80% of the project cost at tender stage) and
the Council's capital plan (for the remaining 20%). This
has delayed the commencement of the main
construction works; once started the works will have a
duration of 18 months.
Perth Eco Innovation Park* 32,817 11,275 21,542 21,542
Not currently
programmed No No
Preliminary design
works completed Yes
Following the application for Levelling Up Fund Grant
funding of £10m being unsuccessful, the Council
approved a net increased of £10m on 1 March 2023
however the balance of £20m remains unfunded and
therefore the project cannot progress.  Private sector
contributions will be required  in years beyond the
current programme to 2027/28 linked to house
completions along with receipts from employment land
plot sales.
Perth Museum 27,232 10,300 16,932 16,932 Spring 2024 Yes Yes On track No
Construction phase complete and building handover to
CPK completed 8 August. Exhibition fit out underway.
Additional support for cafe fit-out & set up costs
requested from cultural reserves, of up to £230,000
PH2O 90,000 0 90,000 90,000
Not currently
programmed No No
Outline Business Case
reported to Council  23
February 2023, and
project on hold
pending review. Yes
Council approved to put the project on hold due to
affordability and pending the outcome of a wider review
in to leisure and cultural assets and how best to target
the required investment in arts and leisure for the benefit
of the wider community.
* Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 5-year programme.