PERTH & KINROSS COUNCIL 
Finance & Resources Committee 
31 January 2024 
COMPOSITE CAPITAL BUDGET 2023/28 & HOUSING INVESTMENT
PROGRAMME 2023/28 – MONITORING REPORT No.3 
Report by Head of Finance
(Report No. 24/41) 
1. PURPOSE 
1.1 This report provides a summary position to date for the 5-year Composite
Capital Budget and the 5-year Housing Investment Programme for 2023/24 to
2027/28 and seeks approval for adjustments to the programmes. 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee: 
(i) notes the contents of the report.
(ii) approves the proposed adjustments to the five-year Composite Capital
Budget 2023/24 to 2027/28 set out in Sections 5 and 6 of the report
and summarised in Appendices I and II.
(iii) approves the proposed adjustments to the Housing Investment
Programme Budget 2023/24 to 2027/28 set out in Section 7 of the
report and summarised in Appendix III. 
3. STRUCTURE 
3.1 The report is structured over the following sections: 
• Section 4: Background / Main Issues
• Section 5: Composite Capital Programme – Gross Capital Resources
• Section 6: Composite Capital Programme – Expenditure
• Section 7: Housing Investment Programme
• Section 8: Summary 
4. BACKGROUND / MAIN ISSUES 
4.1 The Finance & Resources Committee approved an updated five-year gross
Composite Capital Budget for 2023/24 to 2027/28 totalling £623,484,000 and
a five-year gross Housing Investment Programme for 2023/24 to 2027/28
totalling £92,205,000 at its meeting on 22 November 2023 (report 23/316
refers). 
4.2 This report advises on expenditure to 30 November 2023, and the latest
estimate of the projected outturn for each of the years to 2027/28 for the
Composite Programme and for the Housing Investment Programme.

Page 2

5. COMPOSITE CAPITAL PROGRAMME – GROSS CAPITAL RESOURCES 
5.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the five years 2023/24 to 2027/28 amount to £623,916,000. 
5.2 Movements from the revised Composite Capital Budget approved on 22
November 2023 for the five years are summarised in the table below, and the
constituent elements for each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
22 November 2023
Current
Estimate
Movement 
£’000 £’000 £’000
2023/24 196,328 191,182 (5,146)
2024/25 201,340 199,095 (2,245)
2025/26 111,750 97,252 (14,498)
2026/27 65,582 72,809 7,227
2027/28 48,484 63,578 15,094
Total 623,484 623,916 432  
5.3 The overall movement in total Gross Resources for the 5 years 2023/24 to
2027/28 shown at Section 5.2 above can be summarised as follows: 
£’000
Increase in Ring-Fenced Receipts (Section 5.4) 9
Increase in Capital Grants (Section 5.5) 305
Increase in Third Party Contributions (Section 5.6)  57
Increase in Borrowing Requirement (Section 5.7 and 5.8) 61
Increase in Gross Capital Resources (Section 5.2) 432 
5.4 There has been some rephasing of General Fund and Commercial Property
receipts across the 5-year programme but no change to the overall totals
under each category. However, there is an increase in Ring-Fenced receipts
of £9,000 in the current year (disposal of recycling containers). 
5.5 The Scottish Government have announced the allocation of the Inspiring
School Age Childcare Spaces programme grant, with the Council being
allocated a Capital Grant of £105,000 in 2023/24 (Section 6.2.2 refers). In
addition, the Scottish Government has also allocated a further £200,000 in
2023/24 under the Cycling Walking & Safer Streets programme (Section 6.3.2
refers). 
5.6 Third Party Contributions have increased by £57,000 in 2023/24, relating to
Structural Maintenance (£28,000, Section 6.3.3 refers), Community
Greenspace (£4,000) and Property Compliance works at Perth Concert Hall
(£25,000).

Page 3

5.7 The projected borrowing requirement in 2023/24, which is effectively the
balancing item for resources, is £142,121,000. This is £4,628,000 lower than
the borrowing requirement approved by the Committee on 22 November
2023. 
5.8 The total new borrowing requirement in the subsequent years 2024/25 to
2027/28 has increased by £4,689,000 to £355,916,000, resulting in an overall
increase of £61,000 in the total level of borrowing across the whole 5-year
programme. The movement in borrowing is summarised as follows: 
2023/24 2024/25 2025/26 Later
Years
Total 
£’000 £’000 £’000 £’000 £’000
Increase in Prudential Borrowing –
Recycling Containers
Replacement Programme (net of
receipts) (Section 6.3.7)
46 15 0 0 61
Movements arising from re-
phasing of expenditure and
receipts (Appendix II)
(4,674) (2,159) (14,498) 21,331 0
Increase/(Decrease) in
Borrowing Requirement
(4,628) (2,144) (14,498) 21,331 61 
5.9 The chart below shows the Capital Resources required to fund the 2023/24
Composite Capital Programme following the proposed budget adjustments
detailed in this report. 
74.3%
21.7%
0.1%
1.5%
1.0%
1.4%
4.0%
Projected Capital Resources 2023/24
(December 2023)
Borrowing (£142.121M)
Grants (£41.479M)
Tay City Deal (£0.267M)
Developer Contributions (£2.847M)
Third Party & Revenue Contributions (£1.822M)
Receipts (£2.646M)
£Million

Page 4

6. COMPOSITE CAPITAL PROGRAMME – EXPENDITURE 
6.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
6.1.1 Total expenditure (net of grants and contributions) to 30 November 2023 on
the Composite Capital Programme is detailed in Appendix II and summarised
as follows: 
Projected
Outturn
(£’000)
Net Expenditure
to 30 November
2023 (£’000)
% of
Projected
Outturn    
Education & Children’s Services  56,744 29,132 51%
Communities 102,371 55,050 54%
Health and Social Care 1,303    403 31%
Corporate & Democratic Services 9,382 3,828 41%
Total Net Capital Expenditure 169,800 88,413 52% 
6.1.2 A comprehensive monitoring exercise has been carried out, which is detailed
in Appendix II. The most significant features are discussed below. 
6.1.3 In common with all Scottish local authorities and public and private sector
bodies, the Council has experienced significant inflationary pressures on the
delivery of its Capital investment programme over the past few years. 
6.1.4 The Building Cost Information Service (BICS) publish well established cost
indices for the construction industry. The BCIS All-in Tender Price Index,
which shows the general movement on construction pricing, currently
forecasts a 4.0% increase in construction costs in the current year compared
to 9.4% last year, indicating a continuing slow down in construction inflation.
However, the current conflict in the Middle East may significantly impact both
haulage costs for raw materials and fuel costs and the situation will be kept
under review. 
6.2 Education and Children’s Services 
6.2.1 The Executive Director (Education & Children’s Services) has reviewed the
programme for their Service and proposes the following budget adjustments. 
6.2.2 The Scottish Government have provided a grant of £105,000 towards
Inspiring School Age Childcare Spaces with the expenditure budget for
Investment in the Learning Estate increased to reflect the funding. The grant
will be used to support projects which expand and improve school-age
childcare at Letham Primary School, Fairview School and also to support the
Westbank Outdoor Project. 
6.2.3 The remaining movements all reflect the realigning of existing budgets and
programmes of works, the most significant of which are summarised below:

Page 5

Project 2023/24
£’000
2024/25
£’000
Later
Years
£’000
Description
Blairgowrie
Recreation Centre
(950) 950 0 Rephasing of budget to align with
latest estimated cashflow from the
contractor. There is no change to
the planned completion date. 
New Primary School
at Bertha Park site
(500) (7,500) 8,000 Programme revised in line with
current/anticipated housebuilding
in the catchment area. Zoning of
some pupils may be required in
the intervening years. 
Perth Grammar
School
(620) 620 0 Planned works rephased by one
year to reflect diversion of
resources towards replacement of
Reinforced Autoclaved Aerated
Concrete (RAAC) roof during
2023. 
6.2.4 On 2 November 2022, the Learning and Families Committee approved the
catchment for a new primary school at Bertha Park site, with a target
completion date of August 2026. (Report No. 22/265 refers).   The Council
continues to analyse house building data in the catchment area and the
forecast pupil numbers generated from the new housing. Given the recent
economic slowdown in house building and the localised pupil numbers to
date, a review of the timescales associated with the need for a new primary
school in this area is being undertaken. The outcome of this review will be
reported to the Finance & Resources Committee at a future date. In the
meantime, the project’s budget has been rephased by 2 years pending the
outcome of the review with the recognition that there may be some additional
revenue costs from re-zoning pupils, where necessary, during this period. 
6.2.5 All of the above proposed adjustments have been reflected in Appendices I &
II. 
6.3 Communities 
6.3.1 The Executive Director (Communities) has reviewed the programme for their
Service and proposes various budget adjustments, the most significant of
which are described below. 
6.3.2 Within Traffic & Road Safety, the Scottish Government has provided
additional grant funding of £200,000 under the Cycling, Walking and Safer
Routes programme. It is proposed that this is allocated to the Schools Road
Safety Measures programme (£66,000) and the Cycling Walking & Safer
Routes programme (£134,000). Itis also proposed to move £119,000 of the
budget for the 20mph Signage Programme (Schools) from the current year to
next year to focus resources on the delivery of grant funded Road Safety
Measures.

Page 6

6.3.3 An additional £28,000 of Third-Party Contributions have been received
towards the Structural Maintenance programme in 2023/24. This comprises
£14,000 from the Forestry Commission for Timber Routes and £14,000
towards road adoption. 
6.3.4 Within Asset Management – Bridges, a review has been carried out to assess
the work that can be completed in the current year and future years with the
current staff capacity. Accordingly, it is proposed that the budgets for
Dalhenzean Culvert (£279,000) and Dunkeld Golf Course Bridge (£225,000)
are transferred back to the Bridge Refurbishment Programme, as there is
currently no work scheduled on these projects within the current capital
programme. It is, therefore, proposed to rephase a total of £498,000 across
the Bridge Refurbishment Programme as set out in the table below to better
reflect the ability for works to be scheduled: 
2023/24
£’000
2024/25
£’000
2025/26
£’000
2026/27
£’000
2027/28
£’000
(142) 245 126 127 (356) 
6.3.5 Within Improvement Schemes, it is proposed to transfer £190,000 from the
current year into next year, to allow a review of any further works required
once the A977/B9097 junction alignment works have been assessed for their
effectiveness. 
6.3.6 Within Other Planning Projects, it is proposed that the 2023/24 budget for
Perth Eco-Innovation Park of £3,000,000 is moved to next year as there is no
anticipated expenditure in the current year pending ongoing discussions with
the landowners. Consequently, the Tay Cities Deal funding of £990,000 also
needs to be re-phased. 
6.3.7 Within the Prudential Borrowing Projects budget, it is proposed to increase the
borrowing for Recycling Containers, Oil Banks & Battery Banks by £70,000
over this year and next year to purchase additional skips and cardboard
compactors to facilitate the twin stream recycling project. This is offset by an
increase of £9,000 in the income received from the disposal of replaced
containers, which reduces the required increase in borrowing. 
6.3.8 All the above proposed adjustments, together with other small movements,
have been reflected in Appendices I & II. 
6.4 Corporate & Democratic Services 
6.4.1 The Chief Operating Officer has reviewed the programme for their Service.
There are only small movements proposed, and these have been reflected in
Appendix II. 
7. HOUSING INVESTMENT PROGRAMME 
7.1  The total current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2023/24 to 2027/28 remains
unchanged at £92,205,000. Movements from the previous estimates

Page 7

approved by the Committee on 22 November 2023 are summarised in the
table below and detailed in Appendix III. 
Approved 
22 November
2023
Current
Estimate
Movement 
£’000 £’000 £’000
2023/24 22,238 18,738 (3,500)
2024/25          13,503        18,831 5,328
2025/26 17,253 17,248 (5)
2026/27 17,644 16,283 (1,361)
2027/28 21,567  21,105  (462)
Total 92,205 92,205 0 
Total Expenditure to 30 November 2023 (Housing Investment Programme) 
7.2 Net expenditure for 2023/24 to 30 November 2023 amounts to £12,454,000
and receipts amount to £8,000. Therefore, the borrowing requirement for the
year to date is £12,446,000. 
7.3 The Executive Director (Communities) has reviewed the Housing Investment
Programme and proposes the budget adjustments outlined below.
7.4 It is proposed to transfer £462,000 from the New Build Future Developments
Budget in 2027/28 to the Council House Buy-Back programme in 2023/24 to
reflect the additional properties being purchased in the current year. This
exceeds the target of 30 properties to be purchased this year. 
7.5 Phase 4 of the Central Heating programme is concluding with Phase 5 now
due to commence. In order to facilitate this, it is proposed to re-allocate
amounts from the Scottish Housing Quality Standard (SHQS) Future
Developments budget to the Central Heating budget with phasing as follows: 
2023/24
£’000
2024/25
£’000
2025/26
£’000
2026/27
£’000
Central Heating 71 620 620 811
SHQS Future
Developments
0 0 0 (2,122)
7.6 Based on the number of installations now expected within the Energy
Efficiency measures programme, it is proposed that £625,000 of the budget is
accelerated from 2025/26 and £45,000 is accelerated from 2024/25 into the
current year (£670,000). 
7.7 Delays have arisen in commencing the contract for works on Multi-Storey
Flats with improvement works unlikely to start in the current year due to the
significant investigatory work required to ensure the works meet new climate
change targets and to allow for a full scope of works to be established. It is,
therefore, proposed that £1,815,000 of this budget is moved into next year. 
Similarly, the only costs anticipated to be incurred in the current year towards
the St Catherine’s Square Redevelopment are professional fees, and it is
proposed that the remainder of the budget (£2,975,000) is moved from the
current year to next year.

Page 8

7.8 The remaining minor budget adjustments are proposed: 
Project 2023/24
£’000
2024/25
£’000
Later
Years
£’000
Description
General Capital Works 50 0 0 Fund the cost of Alyth
Pumping Station and
Rorrie Terrace adoption
works from SHQS Future
Developments budget.
SHQS Future
Developments
0 0 (50)
Lynedoch Road New
Builds
37 0 0 Fund additional works
instructed throughout the
construction at Lynedoch
Road from New Build
Future Developments
budget.
New Build Future
Development 
0 (37) 0 
7.9 The above proposed adjustments do not impact the borrowing requirement
over the 5-year programme. However, there is an increase in capital receipts
of £8,000 in the current year, therefore, the total borrowing requirement has
reduced by this amount to £80,704,000. 
8. BUDGET OVERVIEW 
8.1 The projected net expenditure outturn in 2023/24 for the Composite Capital
Budget is £169,800,000 and represents 95% of the original 2023/24 budget
approved on 26 April 2023 (£178,033,000). The revised budget is based on
the latest projections of expenditure and all budget adjustments outlined within
this report. 
8.2 Net expenditure to 30 November 2023 on the Composite Capital Budget is
£88,413,000 and represents 52% of the proposed revised budget for 2023/24
of £169,800,000. This level of expenditure is higher than normal at this stage
of the financial year, and reflects several large projects currently on-site,
notably Destiny Bridge (formerly the Cross Tay Link Road project); the Perth
High School replacement project and Blairgowrie Recreation Centre. 
8.3 The projected net expenditure outturn in 2023/24 for the Housing Investment
Programme is £18,738,000 and represents 92% of the original 2023/24
budget approved on 26 April 2023 (£20,422,000). The reduction reflects the
rephasing of expenditure on the Multi-Storey Flats and St. Catherines
Redevelopment projects from the current year into 2024/25. 
8.4 Net expenditure to 30 November 2023 on the Housing Investment Programme
is £12,454,000 which represents 66% of the proposed revised budget for
2023/24 of £18,738,000. 
8.5 The Council’s total Borrowing Requirement to 30 November 2023, based on
the Composite and Housing Investment Programmes, is £85,721,000. The
estimated overall Council Borrowing Requirement for 2023/24 as a whole has
reduced by £8,136,000 to £158,796,000 as a result of the monitoring

Page 9

adjustments reflected within this report. Over the whole 5-year programme,
there is only a small increase of £61,000 in the overall level of borrowing,
relating to Communities Prudential Borrowing projects. 
8.6 While the projections have been based on a comprehensive monitoring
exercise, they continue to remain subject to uncertainty due to ongoing
inflationary pressures in the current economic environment. 
Author(s)
Name  Designation Contact Details
John Jennings Senior Accountant  CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date
Stewart MacKenzie  Head of Finance  18 January 2024
Clare Mailer Director (Strategy, People &
Resources)

Page 10

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2022 – 2027 lays out seven outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
• Tackling Poverty 
• Tackling climate change and supporting sustainable places 
• Growing a sustainable and inclusive local economy 
• Enabling our children and young people to achieve their full potential 
• Protecting and caring for our most vulnerable people   
• Supporting and promoting physical and mental wellbeing
• Placing communities at the heart of how we work 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report.

Page 11

Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report. 
Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Chief Executive and the Executive Directors have been consulted in the
preparation of this report.

Page 12

2. BACKGROUND PAPERS 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
• Appendix I – Composite Capital Programme - Estimated Capital
Resources 2023/24 to 2027/28
• Appendix II – Composite Capital Programme - Summary of Capital
Resources and Expenditure 2023/24 to 2027/28        
• Appendix III – HRA Capital Investment Programme – Summary of
Capital Resources and Expenditure 2023/24 to 2027/28 
• Appendix IV – Significant Capital Projects Progress Update