Appendix 4 - Significant Capital Projects Progress Update
Perth and Kinross Council · 13 September 2023
Back to Finance and Resources Committee — 13 September 2023 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
SIGNIFICANT CAPITAL PROJECTS PROGRESS UPDATE APPENDIX IV Project Title Total Gross Budget (£'000) Third Party Funding (£'000) Total Net Budget (£'000) Projected Outturn (£'000) Completion Date Contract Awarded On Site Status Change Since Last Report Additional Commentary Blairgowrie Recreation Centre - Replacement 36,000 0 36,000 36,000 Easter 2025 - new centre currently scheduled to open late 2024 Yes Yes On track Yes - on-site. Works are progressing well on-site. North/West Perth New Primary School* 24,000 0 24,000 24,000 Summer 2026 No No On track Yes. New Project Request submitted to HubCo in February 2023. Design team selected and early design process has began. Riverside Primary New School 19,899 0 19,899 19,899 Early summer 2023 Yes Yes Phase 2 On Track Yes - School operational. Phase 1 is now complete and school is occupied, phase 2 is on-site being demolition works and new external spaces. Perth High School - New School Investment 80,200 0 80,200 80,200 Summer 2026 - school building curently scheduled to open summer 2025 Yes Yes On track Yes - on-site. FC concluded and construction works have now commenced. Harris Academy/Invergowrie Extension 5,200 0 5,200 5,200 Late 2023 Yes Yes On track Yes. Main extension complete, reconfiguration works still to be undertaken. Cross Tay Link Road (CTLR) 150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On programme No Works progressing well and on programme. No significant movements in projected spend. Once piling works complete at River Tay structure, the constrution of the bridge deck works will commence - Autumn 2023. Monthly risk meetings taking place with T&T and once bridge deck works ongoing detailed analysis of contingency and compensation events will be undertaken. Comrie Flood Protection Scheme 28,435 0 28,435 28,435 Spring 2025 No No Advance works complete; Main works at tender assessment. Yes Detailed design completed April 2023 and tender for main works issued. Preliminary advance works completed in July 2023. Main works tender received in June 2023 but cost higher than anticipated; tender assessment is currently on-going (including independent tender estimate, tender clarification and value engineering). This has delayed the commencement of the main construction works; once started the works will have a duration of 18 months. Perth Eco Innovation Park* 32,817 11,275 21,542 21,542 Not currently programmed No No Preliminary design works completed Yes Following the application for Levelling Up Fund Grant funding of £10m being unsuccessful, the Council approved a net increased of £10m on 1 March 2023 however the balance of £20m remains unfunded. Further contributions and receipts are anticipated in years beyond the current programme to 2027/28. Perth Museum 27,232 10,300 16,932 16,932 Spring 2024 Yes Yes On track No Construction phase complete and building handover to CPK completed 8 August. Exhibition fit out underway. PH2O 90,000 0 90,000 90,000 Not currently programmed No No Outline Business Case reported to Council 23 February 2023, and project on hold pending review. Yes Council approved to put the project on hold due to affordability and pending the outcome of a wider review in to leisure and cultural assets and how best to target the required investment in arts and leisure for the benefit of the wider community. * Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 5-year programme.