PERTH & KINROSS COUNCIL 
Finance & Resources Committee 
13 September 2023 
COMPOSITE CAPITAL BUDGET 2023/28 & HOUSING INVESTMENT
PROGRAMME 2023/28 – MONITORING REPORT NUMBER No.1 
Report by Head of Finance
(Report No. 23/243) 
1. PURPOSE 
1.1 This report provides a summary position to date for the 5-year Composite
Capital Budget and the 5-year Housing Investment Programme for 2023/24 to
2027/28 and seeks approval for adjustments to the programmes. 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee: 
(i) notes the contents of this report.
(ii) approves the proposed adjustments to the five-year Composite Capital
Budget 2023/24 to 2027/28 set out in Sections 5 and 6 of this report
and summarised in Appendices I and II.
(iii) approves the proposed adjustments to the Housing Investment
Programme Budget 2023/24 to 2027/28 set out in Section 7 of this
report and summarised in Appendix III. 
3. STRUCTURE 
3.1 This report is structured over the following sections. The format of the report
has been updated in light of elected member feedback from workshop
sessions held in July : 
• Section 4: Background / Main Issues
• Section 5: Composite Capital Programme – Gross Capital Resources
• Section 6: Composite Capital Programme – Expenditure
• Section 7: Housing Investment Programme
• Section 8: Summary 
4. BACKGROUND / MAIN ISSUES 
4.1 The Finance & Resources Committee approved an updated six-year gross
Composite Capital Budget for 2022/23 to 2027/28 totalling £727,448,000 and
a five-year gross Housing Investment Programme for 2022/23 to 2027/28
totalling £87,018,000 at its meeting on 26 April 2023 (report 23/121 refers).

Page 2

4.2 This report advises on the impact of the final outturn expenditure in 2022/23
on the programmes; expenditure to 31 July 2023, and the latest estimate of
the projected outturn for each of the years to 2027/28 for the Composite
Programme and for the Housing Investment Programme.
5. COMPOSITE CAPITAL PROGRAMME – GROSS CAPITAL RESOURCES 
5.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the five years 2023/24 to 2027/28 amount to £623,150,000.
Movements from the revised Composite Capital Budget approved on 26 April
2023 for these five years are summarised in the table below, and the
constituent elements for each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
26 April 2023
Current
Estimate
Movement 
£’000 £’000 £’000
2023/24 198,729 202,214 3,485
2024/25 193,284 196,980 3,696
2025/26 109,577 110,535 958
2026/27 65,408 65,942 534
2027/28 46,605 47,479 874
Total 613,603 623,150 9,547  
5.2 The monitoring position has been updated for amounts carried forward from
2022/23 as reflected within the unaudited accounts. The overall movement in
the total Gross Resources for the 5 years 2023/24 to 2027/28 shown at
Section 5.1 above can be summarised as follows: 
£’000
Resources Brought-forward from 2022/23: 
Property Receipts, including carried forward to future years 98
Capital Grants 332
Tay City, Developer, Other Third Party and Revenue
Contributions
1,339
Borrowing 6,045
Total Resources Brought-forward from 2022/23 7,814  
Increase in Resources from current monitoring: 
Increase in Commercial Property and other Receipts 381
Increase in Capital Grants (Section 5.3) 151
Increase in Third Party, Revenue and Developer
Contributions (Section 5.4) 
1,201
Total Increase in Gross Capital Resources (Section 5.1) 9,547

Page 3

5.3 There is a net increase of £151,000 in capital grants for various programmes
listed below. These have been reflected in the proposed expenditure budgets
for these programmes, and are included in Appendix II, as follows: 
• £353,000 Nature Restoration included in the General Capital Grant
(Section 6.3.5)
• £30,000 Cycling Walking & Safer Streets (Section 6.3.2)
• Less a reduction of £208,000 from the Recycling Improvement Fund
(Section 6.3.8), and £24,000 for Gypsy Traveller Site Improvements
(Section 6.3.11), reflecting reduced expenditure on the schemes. 
5.4 Third Party Contributions have increased by £1,148,000. These relate to
£150,000 from TACTRAN for the Cycling Walking & Safer Streets programme
(Section 6.3.2), £109,000 from the Forestry Commission for Timber Routes
(Section 6.3.3) and £889,000 from Scottish Water on the Commercial
Property Investment Programme (Section 6.3.10). Revenue Contributions
have increased by a net total of £53,000, with an increased contribution of
£125,000 on the Mosaic Implementation Programme (Section 6.4.3), less a
reduction in the funding of £72,000 required from the Salix Reserve (Section
6.4.2). 
5.5 The projected borrowing requirement in 2023/24, which is effectively the
balancing item for resources, is £152,394,000. This is £974,000 higher than
the borrowing requirement approved on 26 April 2023. This comprises
£6,045,000 of borrowing originally budgeted in 2022/23 which has been
brought forward to 2023/24, less a reduction of £5,071,000 arising from the
current monitoring exercise. 
5.6 The total new borrowing requirement in the subsequent years 2024/25 to
2027/28 has increased by £5,071,000 to £345,480,000, resulting in no overall
change in the total level of borrowing across the whole 5-year programme.
The movement in borrowing (excluding the amount brought-forward) is
summarised as follows: 
2023/24 2024/25 2025/26 Later
Years
Total 
£’000 £’000 £’000 £’000 £’000
Movements arising from re-
phasing of expenditure and
receipts (Appendix II)
(5,071) 2,830 958 1,283 0
Increase/(Decrease) in
Borrowing Requirement
(5,071) 2,830 958 1,283 0 
5.7 The chart below shows the Capital Resources required to fund the 2023/24
Composite Capital Programme following the proposed budget adjustments
detailed in this report.

Page 4

6. COMPOSITE CAPITAL PROGRAMME – EXPENDITURE 
6.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
6.1.1. Total expenditure (net of grants and contributions) to 31 July 2023 on the
Composite Capital Programme amounts to £40,660,000, which is detailed in
Appendix II and summarised as follows: 
Net Expenditure
to 31 July 2023 
£’000
Education & Children’s Services  13,079
Communities 26,242
Health and Social Care    64
Corporate & Democratic Services 1,275
Total 40,660 
6.1.2. A comprehensive monitoring exercise has been carried out, which is detailed
in Appendix II, which also includes the various brought forward adjustments
from 2022/23 as outlined in Section 5 above. The most significant features
are discussed below.
6.1.3. In common with all Scottish local authorities and public and private sector
bodies, the Council has experienced significant inflationary pressures on the
delivery of its Capital investment programme over the past few years. 
6.1.4. The early estimate for the BCIS All-in Tender Price Index, which shows the
general movement on construction pricing, forecasts a 1.1% increase
between Q1 2023 and Q2 2023 which represents an increase of 4.9% in the
year from Q2 2022. By comparison the increase in the year to Q2 2022 from
75.4%
20.3%
0.6%
1.4%
0.9%
1.5%
4.4%
Projected Capital Resources 2023/24
(August 2023)
Borrowing (£152.394M)
Grants (£40.975M)
Tay City Deal (£1.257M)
Developer Contributions (£2.847M)
Third Party & Revenue Contributions (£1.732M)
Receipts (£3.009M)
£Million

Page 5

Q2 2021 was 10.3%. While construction costs continue to rise, this forecast
indicates that the rate of increase is beginning to reduce. 
6.2 Education and Children’s Services 
6.2.1 The Executive Director (Education & Children’s Services) has reviewed the
programme for their Service and proposes the following budget adjustments.
6.2.2 It was previously agreed that the upgrade works at Kirkmichael Primary
School would be funded by a ring-fenced receipt from the sale of the former
Straloch Primary School. The actual amount received for Straloch Primary
exceeded the original estimate resulting in a further £28,000 for additional
upgrades at Kirkmichael Primary School. 
6.2.3 The remaining budget adjustments reflect timing differences on various
projects, with the main proposed movements detailed in the table below: 
Project 2023/24
£’000
2024/25
£’000
Later Years
£’000
Description
Technology
Upgrades
(250) 0 250 Works programme rephased and
extended to the summer
holidays in 2025
Harris Academy (150) 150 0 The refurbishment of existing
classrooms within the project to
be undertaken in summer
holidays 2024 
6.2.4 There are several other small adjustments to various Education & Children’s
Services projects relating to amounts carried forward from 2022/23 which are
included in Appendix II. These mostly relate to projects that have been
completed. All of the above proposed adjustments have been reflected in
Appendices I & II. 
6.3 Communities 
6.3.1 The Executive Director (Communities) has reviewed the programme for their
Service and proposes various budget adjustments, the most significant of
which are described below.
6.3.2 Within Traffic & Road Safety, TACTRAN have provided a £150,000 Third
Party Contribution towards the Cycling, Walking and Safer Routes (CWSR)
programme. This is supplemented by an increase in the Scottish Government
Grant of £30,000 which is proposed to be allocated to the Schools Road
Safety Measures budget (£28,000) and the CWSR budget (£2,000) in the
current year. 
6.3.3 With Asset Management – Roads & Lighting, the Forestry Commission have
allocated an additional £109,000 to the Council towards Timber Routes, which
is included within the Structural Maintenance programme. This has been

Page 6

added to the 2023/24 budget which, when combined with an acceleration of
budget from future years, increases the budget in the current year by
£394,000. 
6.3.4 Springfield have advised the Council that they will not construct the Perth
Transport Futures Phase 3 Bertha Park Link Road themselves, and instead
have exercised their legal right to provide an agreed sum through developer
contributions over time as house sales are completed. Therefore, it has now
become necessary for the Council to undertake the detailed design work for
the road. It is proposed that up to £500,000 of the contingency included within
the Phase 2 CTLR project is utilised for this design work, and that options for
funding the construction, including the use of developer contributions, is
considered by Council when it sets the next Capital Budget in February next
year. 
6.3.5 The Scottish Government has also allocated £353,000 to the Council for the
Nature Restoration programme in 2023/24. This has therefore been added to
the current year budget within the Other Planning programme, with the grant
added to the Council’s General Capital Grant. The budget is also augmented
by a small rounding adjustment of £1,000. 
6.3.6 Within the City Centre Developments – Cultural Attractions programme, the
construction phase of Perth Museum is now complete and the project remains
within the total approved budget, with only final fit-out works ongoing, prior to
its opening in the spring of next year. 
6.3.7 The Letham Hub project is scheduled to conclude prior to Christmas 2023.
Members are advised that the contractor has submitted a number of claims
for an extension of time and a corresponding substantial financial claim. This
is currently being evaluated and will be subject to ongoing discussion with the
contractor. There is no request for additional funding at this time. 
6.3.8 Within Waste Strategy, a reduction in expenditure of £208,000 has also meant
the level of grant funding from the Recycling Improvement Fund has been
reduced by a corresponding amount in the current year. 
6.3.9 During the cyclical condition survey programme the roof structure of the
Friarton Waste Transfer Station has been found to have incurred severe
corrosion. Engineering advice is that the building and surrounding area may
be at risk in the event of winter storms and/or heavy snow and remedial action
has therefore been instigated at an estimated cost of £250,000 in 2023/24
which will be met from the Property Compliance Works Programme.
Operational plans will be put in place by Communities to redirect waste to
alternative locations from October. An update on the investment requirements
on the Council’s operational estate will be included as part of the Corporate
Asset Management Plan to Council in December.

Page 7

6.3.10 Within the Commercial Property Investment Programme, the costs to deliver
the Broxden Drainage Mitigation Works have been revised with an additional
£401,000 required in the current year and £866,000 next year for the full
required works to be undertaken. Scottish Water are providing a contribution
to the cost of the project, with an additional £231,000 this year and £658,000
next year. It is proposed that the remaining costs are met from the
Commercial Receipts which have been brought forward. After allowing for
other adjustments to the programme, this results in a net increase in
expenditure of £353,000. 
6.3.11 The various programmes of works for the Gypsy Traveller Sites are being
reviewed, and specific proposals will be considered at a future meeting of this
Committee. However, reduced expenditure of £24,000 on one of the grant
funded schemes which originated in 2021/22 has resulted in a reduction in
grant for the project, which has been reflected in Appendix I and II. 
6.3.12 There have been several other small adjustments to various Communities
projects relating to amounts carried forward from 2022/23 which are included
in Appendix II. These mostly relate to projects that have been completed or
rounding adjustments. All the above proposed adjustments have been
reflected in Appendices I & II. 
6.4 Corporate & Democratic Services 
6.4.1 The Chief Operating Officer has reviewed the programme for their Service and
proposes the budget adjustments described below. 
Property Services 
6.4.2 It is proposed to reduce the Energy Efficiency Works funded from the Salix
Reserve by £72,000, due to the complexities of installing the heating control
systems in some buildings. 
Information Systems & Technology 
6.4.3 The planned go-live date for the new Mosaic system has been moved from
March 2024 to 1 April 2024. Therefore, this results in the full licence costs now
being chargeable to new financial year when the system goes live, with only
staff costs for the ongoing development and implementation being incurred in
the current year. In addition, it also means that a further year of the current
Revenue Contributions is available to meet some of the costs of the project in
2026/27. The budget has therefore been rephased for these proposed budget
adjustments and been included in Appendix II.
6.4.4 The remaining budget adjustments reflect timing differences on various
projects, with the main proposed movements detailed in the table below:

Page 8

Project 2023/24
£’000
2024/25
£’000
Later Years
£’000
Description
Property -
Decarbonisation 
(1,300) 1,300 0 Following a review of the work to
be undertaken in the new
project, the budget has been
rephased to reflect staff capacity
and procurement timescales.
ICT Infrastructure
Replacement &
Upgrade Programme
(354) (721) 1,075 The Programme has been
rephased to align with
infrastructure replacement
projects & licensing
requirements. 
IST – Data & Analytics  (442) 164 278 Rephasing of the Data
Management Programme
IST – Supporting
Digital
(564) 141 423 Works to be planned around the
re-procurement of various digital
platforms.
School audio-Visual
(AV) Replacement
Programme
(798) 173 625 The programme has been
rephased to align with
replacement plans and other
property related project work. 
6.4.5 Al the above proposed adjustments, together with other small movements,
have been reflected in Appendix II. 
6.5 Health & Social Care 
6.5.1 The Developing Supported Tenancies project is a contribution towards works
within the Housing Revenue Account. It has been confirmed that the budget of
£229,000 will not be required in the current year and it is therefore proposed
that the budget is moved to next year whilst options continue to be evaluated. 
6.5.2 The above proposed adjustment has been reflected in Appendix II. 
7. HOUSING INVESTMENT PROGRAMME 
Final Outturn 2022-23 
7.1 The final position for 2022/23 on the Housing Investment Programme (subject
to audit) was as follows: 
2022/23
Budget 
Actual to 31
March 2023
Variance to
Budget 
£’000 £’000 £000
Total Net Expenditure 18,180 13,856 (4,324)
Total Receipts & CFCR (2,652) (2,741) (89)
Borrowing Requirement 15,528 11,115 (4,413)

Page 9

7.2 In order to determine the carry-forward adjustments to 2023/24 required for
each project, the difference between the 2022/23 actuals and previous
projections are adjusted against the 2023/24 budgets. These adjustments are
neutral over the 2 years and has resulted in a movement of £4,413,000 of
borrowing from 2022/23 to 2023/24 and is shown in Appendix III.   
Current Programme: 2023/24 to 2027/28 
7.3 The current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2023/24 to 2027/28 amounts to
£92,205,000. Movements from the previous estimates approved by the
Finance & Resources Committee on 26 April 2023 are summarised in the
table below and detailed in Appendix III. 
Approved 
26 April 2023
Current
Estimate
Movement 
£’000 £’000 £’000
2023/24 20,422 27,597 7,175
2024/25 13,853          13,744 (109)
2025/26 15,519 17,253 1,734
2026/27 19,044 19,044 0
2027/28 19,044 14,567  (4,477)
Total 87,882 92,205 4,323 
7.4 The increase in resources of £4,323,000 represents £4,413,000 brought
forward from 2022/23, less the increase in CFCR of £90,000 applied in
2022/23 which has not been carried forward. 
7.5 Total Expenditure to 31 July 2023 (Housing Investment Programme) 
Net expenditure for 2023/24 to 31 July 2023 amounts to £5,015,000. As there
have been no receipts, this therefore means that the borrowing requirement
for the year to date is also £5,015,000. 
7.6 After making adjustments relating to small carry-forward amounts from last
year, which are included in Appendix III, the Executive Director (Communities)
has reviewed the Housing Investment Programme and proposes further
budget adjustments outlined below.
7.7 It is proposed to draw-down a total of £4,477,000 from the SHQS Future
Developments budget in 2027/28 and to allocate this across various
programmes as follows: 
• Heating Upgrades - £700,000 allocated to each of the years 2023/24,
2024/25 and 2025/26, due to additional properties requiring heating
upgrades, and to maintain an ongoing programme of works.
• Fire Precaution Measures - £427,000 allocated to 2023/24, to cover
additional properties which were not included in the original programme
of works.

Page 10

• Environmental Improvements - £500,000 allocated to 2023/24 to cover
additional works required due to Health & Safety requirements.
• Bathroom Modernisation Programme - £1,450,000 allocated to
2023/24, as a result of the continuing referrals from Occupational
Therapists. 
7.8 Due to the complexity of the redevelopment of the property in Balmoral Road,
Blairgowrie, the estimated costs have increased. Consequently, it is proposed
not to proceed with the project, and to transfer the budget of £264,000 to the
redevelopment of 149-151 Dunkeld Road, Perth. It is also proposed to
increase the budgets for Sheltered Housing (£20,000) and General Works
(£77,000) by transferring £97,000 from the ICT Expenditure budget in
2023/24. 
7.9 The remaining budget adjustments reflect timing differences on various
projects, with the main proposed movements detailed in the table below: 
Project 2023/24
£’000
2024/25
£’000
Later Years
£’000
Description
External Fabric (net of
Third party
Contributions)
894 (528) (366) Following conclusion of the
Tenement Management System,
additional properties have been
added to the current contract,
primarily roof and harling works
at Logie Crescent, Perth.
Kitchen Modernisation
Programme 
(1,400) 0 1,400 Increased lifespan of previous
kitchen upgrades has reduced
demand in the current
modernisation cycle. Budget
rephased to maintain a future
replacement programme
Energy Efficiency 279 (279) 0 Works have been completed
faster than anticipated,
consequently additional works
have been planned and the
budget rephased accordingly. 
7.10 Capital Financed by Current Revenue (CFCR) increased by £90,000 in
2022/23 which has reduced the borrowing requirement on the programme.
There are no further movements which impacts the borrowing requirement
over the remainder of the 5-year programme. 
8. BUDGET OVERVIEW 
8.1 The projected net expenditure outturn in 2023/24 for the Composite Capital
Budget is £180,346,000 and represents 101% of the 2023/24 budget as
approved on 26 April 2023 (£178,033,000). The revised budget is based on
the latest projection of expenditure and all budget adjustments outlined within
this report.

Page 11

8.2 Net expenditure to 31 July 2023 on the Composite Capital Budget is
£40,660,000 and represents 23% of the proposed revised budget for 2023/24 of
£180,346,000. This level of expenditure is higher than normal at this early stage
of the financial year, and reflects several larger projects being on-site with
construction works now being undertaken. 
8.3 The projected net expenditure outturn in 2023/24 for the Housing Investment
Programme is £27,597,000 and represents 135% of the 2023/24 budget
approved on 26 April 2023 (£20,422,000). The increase reflects the level of
expenditure brought forward from last year as well as the allocation of some of
the SHQS Future Developments budget from later years to specific projects in
the current year. 
8.4 Net expenditure to 31 July 2021 on the Housing Investment Programme is
£5,015,000 which represents 18% of the proposed revised budget for 2023/24 of
£27,597,000. 
8.5 Overall, the estimated Council Borrowing Requirement in 2023/24 has increased
as a result of borrowing previously budgeted last year being carried-forward to
the current year. There is no movement in the level of borrowing arising from the
current monitoring exercise. While the projections have been based on a
comprehensive monitoring exercise, they continue to remain subject to
uncertainty as a result of ongoing inflationary pressures, particularly in the
construction industry, in the current economic environment. 
Author(s)
Name  Designation Contact Details
John Jennings Senior Accountant  CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date
Karen Donaldson 
Stewart MacKenzie
Chief Operating Officer 
Head of Finance 
1 September 2023 
1 September 2023

Page 12

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2022 – 2027 lays out seven outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at a
corporate and service level and shape resources allocation.  They are as follows: 
• Tackling Poverty 
• Tackling climate change and supporting sustainable places 
• Growing a sustainable and inclusive local economy 
• Enabling our children and young people to achieve their full potential 
• Protecting and caring for our most vulnerable people   
• Supporting and promoting physical and mental wellbeing
• Placing communities at the heart of how we work 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than those
reported within the body of the main report.

Page 13

Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report. 
Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report other
than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate discrimination,
advance equality of opportunity, and foster good relations between equality
groups.  Carrying out Equality Impact Assessments for plans and policies allows
the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been assessed
as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its proposals. 
3.4 The information contained within this report has been considered under the Act. 
However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the Council
has to discharge its duties in a way which contributes to the achievement of
sustainable development. In terms of the Climate Change Act, the Council has a
general duty to demonstrate its commitment to sustainability and the community,
environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the Act. 
However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Chief Executive and the Executive Directors have been consulted in the
preparation of this report.

Page 14

2. BACKGROUND PAPERS 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above report. 
3. APPENDICES 
• Appendix I – Composite Capital Programme - Estimated Capital
Resources 2023/24 to 2027/28
• Appendix II – Composite Capital Programme - Summary of Capital
Resources and Expenditure 2023/24 to 2027/28        
• Appendix III – HRA Capital Investment Programme – Summary of Capital
Resources and Expenditure 2023/24 to 2027/28 
• Appendix IV – Significant Capital Projects Progress Update