Appendix IV – Significant Capital Projects Progress Update

Perth and Kinross Council · 26 April 2023
Back to Finance and Resources Committee — 26 April 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Appendix IV
Project Title Total Gross
Budget
(£'000)
Third Party
Funding
(£'000)
Total Net
Budget
(£'000)
Projected
Outturn
(£'000)
Completion Date Contract
Awarded
On Site Status Change Since
Last Report
Additional Commentary
Blairgowrie Recreation
Centre - Replacement
36,000 0 36,000 36,000 Easter 2025 - new
centre currently
scheduled to open late
2024
Yes Yes On track Yes - on-site
and letter of
intent signed
Additional £9.3m of funding approved by the Council on
1 March 2023. Letter of intent signed with Hubco/BAM to
secure some pricing elements. Anticpated financial close
and start on site for mid-May 2023, with estimated
completion for Easter 2025.
North/West Perth New
Primary School*
24,000 0 24,000 24,000 Summer 2026 No No On track No New Project Request submitted to HubCo in February
2023. Consultant/ Contractor selection in progress.
Riverside Primary New
School
19,899 0 19,899 19,899 Early summer 2023 Yes Yes New completion
date agreed
Yes - revised
completion date
Completion date changed due to commissioning
requirements
Perth High School - New
School Investment
80,200 0 80,200 80,200 Summer 2026 - school
building curently
scheduled to open
summer 2025
Yes Yes On track Yes - on-site
and FC
concluded
FC concluded and construction works commenced.
Harris
Academy/Invergowrie
Extension
5,200 0 5,200 5,200 Late 2023 Yes Yes On track No Construction contract signed - project to be delivered by
Dundee City Council
Cross Tay Link Road
(CTLR) 150,500 40,000 110,500 110,500 Spring 2025 Yes Yes On track No
Some movement in expenditure in 2022/23 relating to
programming of works, as well as risk contingency and
compensation events not materialising in year.
Expenditure reprofiled.
Comrie Flood Protection
Scheme
28,435 0 28,435 28,435 End of 2024 No No Advance works
substantially
complete
No Detailed design on-going; anticipated completion is at
end of March 2023. Preliminary advance works are
ongoing and substantially complete with main
construction works anticipated to start in summer 2023,
with a duration of 18 months.
Perth Eco Innovation Park* 32,817 11,275 21,542 21,542
Not currently
programmed No No
Preliminary
design works
completed
Yes -
confirmation of
additional
resources
approved by
Council
Following the application for Levelling Up Fund Grant
funding of £10 million being unsuccessful, the Council
approved a net increased of £10m on 1 March 2023.
Further contributions and receipts are anticipated in
years beyond the current programme to 2027/28.
Perth Museum 27,232 10,300 16,932 16,932 Spring 2024 Yes Yes On track No
Collections Centre 0 0 0 0 n/a No No
Project
removed from
the programme
by the Council
on 1 March
2023 Yes
PH2O 90,000 0 90,000 90,000
Not currently
programmed No No
Outline
Business Case
reported to
Council  23
February 2023,
and project on
hold pending
review. Yes
Council approved to put the project on hold due to
affordability and pending the outcome of a wider review
in to leisure and cultural assets and how best to target
the required investment in arts and leisure for the benefit
of the wider community.
* Third Party Funding excludes Developer Contributions and receipts to be received in future years beyond the current 5-year programme.