PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
Estimated Capital Resources 2022/23 to 2027/28
APPENDIX I
Capital Capital Capital Capital Capital Capital Capital
Resources Resources Resources Resources Resources Resources Resources
2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Revised Revised Revised Revised Revised Revised Revised
Budget Budget Budget Budget Budget Budget Budget
Capital Grants
Cycling, Walking & Safer Routes (CWSR) 973 982 200 200 200 200 2,755
Town Centre Fund 26 0 0 0 0 0 26
Regeneration Fund 524 0 0 0 0 0 524
Recycling Improvement Fund 358 2,363 0 0 0 0 2,721
Cross Tay Link Road - Transport Scotland 20,000 15,000 0 0 0 0 35,000
General Capital Grant 14,739 22,147 13,847 12,639 12,150 12,150 87,672
Total Capital Grants 36,620 40,492 14,047 12,839 12,350 12,350 128,698
General Capital Receipts
General Fund - Capital Receipts 8 972 250 250 250 250 1,980
General Fund - Ring Fenced Receipts 122 372 377 377 927 1,072 3,247
Total General Capital Receipts 130 1,344 627 627 1,177 1,322 5,227
Commercial Property Receipts
Capital Receipts brought-forward 2,556 2,157 1,006 2,685 2,993 2,993 2,556
Commercial Property Capital Receipts 1 243 1,679 308 0 0 2,231
Capital Receipts carried-forward (2,157) (1,006) (2,685) (2,993) (2,993) (2,993) (2,993)
Total Commercial Property Receipts Applied 400 1,394 0 0 0 0 1,794
Contributions
Tay Cities Deal 634 1,171 999 550 505 1,956 5,815
Third Party Contributions 2,434 709 0 0 2,000 3,000 8,143
Developer Contributions 1,549 2,100 2,300 2,367 2,600 2,600 13,516
Revenue Budget Contributions 814 99 124 125 0 0 1,162
Total Contributions 5,431 4,079 3,423 3,042 5,105 7,556 28,636
Capital Borrowing Requirement 71,264 151,420 175,187 93,069 46,776 25,377 563,093
TOTAL CAPITAL RESOURCES/
GROSS BUDGET EXPENDITURE 113,845 198,729 193,284 109,577 65,408 46,605 727,448

Page 2

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
Estimated Capital Resources 2022/23 to 2027/28
APPENDIX I
Movements in Resources from Approved Budget - 1 March 2023
Revised Revised Revised Revised Revised Revised Revised
Budget Budget Budget Budget Budget Budget Budget
2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Increase/(Decrease) in:
Capital Receipts - General Fund (38) 38 0 0 0 0 0
Capital Receipts - Commercial Property (342) (710) 1,054 0 0 0 2
Capital Receipts - Ring Fenced (172) 172 0 0 0 0 0
Capital Grants:
Cycling, Walking & Safer Routes (CWSR) 0 310 0 0 0 0 310
Road Safety Improvement Fund 0 0 0 0 0 0 0
Free School Meals Expansion 0 0 0 0 0 0 0
Regeneration Fund 0 0 0 0 0 0 0
Recycling Improvement Fund 77 282 0 0 0 0 359
Town Centre Fund 0 0 0 0 0 0 0
Cross Tay Link Road - Transport Scotland 0 0 0 0 0 0 0
General Capital Grant 0 (13) 0 0 0 0 (13)
Tay Cities Deal (100) 100 0 0 0 0 0
Third Party Contributions (36) 141 0 0 0 0 105
Revenue Contributions 77 0 124 125 0 0 326
Developer Contributions 0 0 0 0 0 0 0
Resources b/f 0 (117) (1,076) (22) (22) (22) (1,259)
Resources c/f to future years 117 1,076 22 22 22 22 1,281
Borrowing Requirement (12,262) 4,570 10,499 (2,013) (2,408) 386 (1,228)
Total Increase/(Decrease) in Resources (12,679) 5,849 10,623 (1,888) (2,408) 386 (117)
Approved Resources 1 March 2023 126,524 192,880 182,661 111,465 67,816 46,219 727,565
Revised Resources 113,845 198,729 193,284 109,577 65,408 46,605 727,448