Appendix 2: Digital Perth and Kinross - Digital Strategy 2023-27 
Delivery Plan to 31 December 2024 
Our Digital Strategy signposts Perth & Kinross Council’s digital ambitions for the next 5 years. 
The Plan focusses on realistic headline actions we can take now to develop and maintain the sound digital foundations and common building
blocks on which our new digital services and capabilities will be built. 
Beyond our core infrastructure:
• the Council continues to operate a de-centralised model, with strategic responsibility for digital ways of working, change initiatives, direction
and planning managed within individual Services’ BMIPs: this includes investment in, and delivery of, business systems and applications 
• planning approval and monitoring routines are already in place for active strategic workstreams such as Data and Analytics; Mobile Working
and Online Services; Mosaic implementation and delivery of the Customer Services Strategy
• new digital initiatives that launch during the life of the Strategy will be agreed via the Digital Board, a key responsibility for which will be
endorsing proposals for the governance, planning and scrutiny of related activities. 
Indicative start times for planned activities are summarised as follows: 
• Now indicates work has started or is planned to start within the next 6 months 
• Next indicates work is planned to begin within the next 12 months 
• Later indicates work is planned to begin before end December 2024. 
This plan highlights the headline actions to enable delivery of this Strategy. Following approval of the Digital Strategy, further engagement and
consultation with Services will take place, and together with ongoing alignment with the evolving Transformation and Change Programme, this
will ensure the digital delivery plan remains relevant, aligned to Council priorities and current. The Plan will be approved, assured and overseen
by the Digital Board.

Page 2

2 
STRATEGIC
AREA ACTIVITY
INDICATIVE START
TIME
Now Next Later
Placing
communities
and the
citizen at the
heart of how
we work
One Front Door
Consolidation / standardisation of contact centres, tools and technologies; use of webchat functionality;
streamlining of processes
X  
Simple, standardised access to all services
Implementing a standard, secure approach for citizens to confirm their personal identity    X
Council Concessions: streamlining the application process
Optimising the application process / flagging entitlement to other concessions / benefits / assistance)  X 
E-billing for Council Tax and Non-Domestic Rates
Avoiding costs (postage) / improving service efficiency by promoting Council Tax e-billing to citizens and
businesses 
X 
Everyone
Connected
Digital Ambassador Network
Creation of community of digital good practice to support citizens interacting with the Council online, reduce
risk of digital exclusion and grow uptake in the Council’s online services
Continue to progress the Digital Exclusion Action Plan and work with partners on this through the Digital
Participation Working Group
X  
Tackling the
climate
challenge
Informed Climate Action Plan decision-making
Combining data & analytics capabilities with data gathered via new technologies such as IoT, sensors and
drones to inform Climate Action Plan priorities and workstreams (e.g. monitoring / reducing property and
energy costs) 
X
P&K Digital
welcome
Consolidation / rebrand of Council websites
Modernisation / consolidation of the Council’s external facing websites: reducing costs, securing content and
keeping it accessible / up to date 
X

Page 3

3 
STRATEGIC
AREA ACTIVITY
INDICATIVE START
TIME
Now Next Later
Perth Museum digital infrastructure 
Deliver a fit for the future digital infrastructure for Perth Museum that enables an engaging, interactive visitor
experience
X  
Smart P&K /
Internet of
Things 
Corporate IoT Roadmap 
Investigate options for implementing an enterprise IoT platform: to encompass multi-disciplinary deployment
of sensors / drones and tie in directly with corporate platforms such as Building Management; Data
warehouse and Mobile Working platform 
X 
Connected
Places
Open Data
Continuing to make more data available via the P&K Open data platform, to stimulate local digital business
growth and development 
X 
Protecting /
caring for
vulnerable
people
Enterprise social care platform for adults and children services: Mosaic Implementation
Technical implementation of enterprise social care: integration with Integra, Mobile Working platform and
Community Health systems; and implementation of a secure Citizen self-service portal 
Programme ongoing
til 2025
Digital
Classroom:
helping our
children and
young people
to achieve
their full
potential
Enabling digital classrooms 
Evaluating emerging options for managing school based users and devices to optimise digital for learning
and teaching 
X 
One to One devices
Rethinking device provision in schools: supporting roll out of Scot Gov Device for Every Learner initiative:
device standards; accessibility; security / all remote device management; repurposing existing classroom
devices
Dependent on release
of Scot Gov funding
Full Fibre Connectivity: schools
Concluding LFFN programme; planning full fibre provision in all education establishments to meet growing
demand for broadband from increasing use of digital and the number of devices in use 
X

Page 4

4 
STRATEGIC
AREA ACTIVITY
INDICATIVE START
TIME
Now Next Later
Wi-Fi in schools
Improving Wi-Fi density as well as coverage in schools to support new ways of delivering learning and
teaching / readiness for Scot Gov Device for Every Learner initiative
X  
Infrastructure design for new school builds
Planning / delivery of core infrastructure for school rebuilds / refurbishments (Riverside PS; Perth High
School; Bertha Park PS; Rattray PS; Perth Academy and Perth Grammar School)  
As per ECS delivery
timelines
Smarter
Working
“One Council” review / rationalisation of business systems
Reviewing business systems including mapping the existing application landscape; governance; technical
and business fit; future development strategies; supplier engagement; contract management and
opportunities for sharing and rationalisation (in alignment with the Transformation and Change programme) 
Review to include opportunities for strengthening the role of the Digital Board as governance group /
strategic owner of PKC business systems 
X 
Growing our Digital Leadership
Taking a collaborative approach to growing digital leadership and awareness across the organisation:
embedding a “One Council” culture for digital planning, investment and change / redesigning services around
life events, to respond to the end to end customer journey. Reinforcing the Digital Board’s governance role /
IT’s role as the Council’s trusted digital partner
Digital Board
reviewed Now; Digital
Leadership
programme ongoing
2023-27
Delivering the IT Asset Management Plan
Ensuring our digital foundations remain optimised, secure, maintained and fit for the future; delivering the IT
Capital Programme to renew key assets, support Council priorities and put in place the building blocks
needed for future digital change and improvement
Ongoing 2023 -27 
Enabling hybrid working
Ensuring fit for purpose infrastructure, including provision of video conferencing equipment to a limited
number of meeting spaces within 2 High Street, Pullar House, Carpenter House and Secondary Schools /
Campuses to support hybrid working and meet the needs of evolving workstyles 
X

Page 5

5 
STRATEGIC
AREA ACTIVITY
INDICATIVE START
TIME
Now Next Later
Mobile Working and Online Services Programmes
Approved as part of 2015 Building Ambition Programme.
Platform approaches in place to provide standard enterprise tools, approaches and development expertise /
support. 
Programme Plan / methodology for prioritising development requests approved and monitored by the Digital
Board
Ongoing 2023 -27 
Microsoft Environment
Develop sustainable support model for the Council’s evolving MS Cloud environment (Azure) 
Investigate emerging MS analytics capabilities to inform corporate future licensing profile / target digital skills
support
Build capacity / standard approaches for optimising value from investment in Microsoft resources. To include
actively seeking opportunities for using evolving MS tools to streamline, simplify and automate processes
and working with Services to identity more efficient ways of working / collaborating with service users and
colleagues 
X  
PKC / MS Teams telephony integration
Moving from fixed provision to flexible anywhere calling / telephony communications. Integrating internal and
external telephone calls into MS Teams to make softphone services available for up to 3000 PKC users. 
Removes requirement for physical handsets / supports hybrid working
X  
Full Fibre Connectivity: corporate buildings
Concluding LFFN programme / planning full fibre connectivity beyond LFFN to meet growing demand for
gigabit internet speeds from increasing use of digital
X  
Wi-Fi: corporate buildings
Redesign of corporate workplaces / delivery of robust Wi-Fi for flexibility / to support hybrid working  X

Page 6

6 
STRATEGIC
AREA ACTIVITY
INDICATIVE START
TIME
Now Next Later
New mobile device management solution / processes
Implementing improved remote administration and maintenance for devices, to align with fit for the future
network model and smarter ways of working
X  
Migration of Business Systems to the Cloud
Vendors increasingly nudging system owners towards cloud-based solutions: 
• embed a standard organisational approach for identifying opportunities / benefits of migrating
business systems to the cloud. To include informed consideration of PKC business requirements;
availability of alternative / existing solutions; fit with PKC digital architecture; information security and
data protection; total cost of ownership; continuing ownership / availability of data; and vendor’s
roadmap and licensing model 
• develop a P&KC Cloud Framework / Playbook to positively influence safe, consistent use of cloud
solutions 
Ongoing
Data and
Analytics
Strategic Data and Analytics (D&A) Programme
The Council’s strategic vision for D&A, approved by EOT in 2020, is to ensure trusted data enables the
Council to make information driven decisions and to innovate to deliver better services and value. Associated
D&A work programme provides the roadmap for delivering:
• New data and analytics tools, including visualisation and reporting capabilities (MS PowerBI and
ESRI ArcGIS Enterprise) and cloud hosted data warehousing built in MS Azure
• Improved data quality and consistency resulting in better intelligence and more efficient service
delivery
• An effective data and analytics organisation and operating model ensuring resources, skills, expertise
and services are appropriately aligned with the needs of the Council
• Proactive data sharing and re-use, breaking down information silos and maximising the value and
intelligence gained 
Ongoing 2023-27

Page 7

7 
STRATEGIC
AREA ACTIVITY
INDICATIVE START
TIME
Now Next Later
Securing and
Accessing
our
Information
Assets 
Fit for the future IT network model 
Significantly enhanced security, flexibility and resilience through delivery of a fit for the future IT network
model. 
Includes developing options and cost / benefit analysis for moving to a zero trust architecture model to
provide secure, verified, personalised access to Council resources.
Initial foundations in
place by end 2023
Optimising benefit from the Council’s Cyber Security Operations Centre (CSOC) 
Extending the infrastructure monitored and embedding / enhancing CSOC processes, to provide expanded
24/7 security monitoring and increased protection 
X  
Enhanced MS365 Security features
Implement enhanced security / compliance features available within the MS365 licensing environment  X