PERTH & KINROSS COUNCIL 
FINANCE & RESOURCES COMMITTEE 
1 FEBRUARY 2023 
COMPOSITE CAPITAL BUDGET 2022/28 & HOUSING INVESTMENT
PROGRAMME 2022/27 – MONITORING REPORT No.3 
Report by the Head of Finance
(Report No. 23/31) 
PURPOSE OF REPORT 
This report provides a summary position to date for the 6-year Composite (General
Fund) Capital Budget for 2022/23 to 2027/28 and the 5-year Housing Investment
Programme 2022/23 to 2026/27 and seeks approval for adjustments to the budgets. 
STRUCTURE OF REPORT 
This report is structured over the following sections:
• Section 1: Background
• Section 2: Recommendations
• Section 3: Composite Capital Programme – Gross Capital Resources
• Section 4: Composite Capital Programme – Expenditure
• Section 5: Housing Investment Programme
• Section 6: Summary 
1. BACKGROUND / MAIN ISSUES 
1.1 The Finance & Resources Committee approved an updated six-year gross
Composite Capital Budget for 2022/23 to 2027/28 totalling £687,853,000 and
a five-year gross Housing Investment Programme for 2022/23 to 2027/28
totalling £84,018,000 at its meeting on 30 November 2022 (report 22/298
refers). 
1.2 This report advises on expenditure to 31 December 2022 and the latest
estimate of the projected outturn for each of the years to 2027/28 for the
Composite Programme and to 2026/27 for the Housing Investment
Programme. 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee: 
(i) notes the contents of this report.
(ii) approves the proposed adjustments to the six-year Composite Capital
Budget 2022/23 to 2027/28 set out in Sections 3 and 4 of this report
and summarised in Appendices I and II.
(iii) approves the proposed adjustments to the Housing Investment
Programme Budget 2022/23 to 2026/27 set out in Section 5 of this
report and summarised in Appendix III.

Page 2

(iv) notes progress with the delivery of major Capital projects as
summarised in Appendix IV. 
3. COMPOSITE CAPITAL PROGRAMME – GROSS CAPITAL RESOURCES 
3.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the six years 2022/23 to 2027/28 amount to £696,021,000.
Movements from the revised Composite Capital Budget approved on 30
November 2022 are summarised in the table below, and the constituent
elements for each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
30 Nov 2022
Current
Estimate
Movement
£’000 £’000 £’000
2022/23 171,528 143,465 (28,063)
2023/24 184,848 190,281 5,433
2024/25 148,122 159,900 11,778
2025/26 82,339 92,330 9,991
2026/27 56,761 65,766 9,005
2027/28 44,255 44,279 24
Total 687,853 696,021 8,168 
3.2 The overall movement in the total Gross Resources for the 6 years 2022/23 to
2027/28 shown at Section 3.1 above can be summarised as follows: 
£’000
Increase in Capital Grants (Section 3.4) 100
Increase in Third Party, Revenue and Developer Contributions
(Section 3.5) 
371
Increase in Borrowing Requirement (Section 3.7) 7,697
Increase in Gross Capital Resources (Section 3.1) 8,168 
3.3 There is only small movements in the estimated Property receipts, including
an increase of £113,000 in estimated receipts on the Commercial property
Programme. With no updated proposals for expenditure within the
Commercial Investment Programme at this stage, this increase in receipts is
therefore carried-forward to future years and has no overall impact on the
current level of resources. 
3.4 The Provisional Local Government Finance Circular issued on 20 December
2022, includes an increase of £100,000 in the Council’s General Capital Grant
in 2022/23 relating to the allocation for flood studies. The Council has already
included this expenditure as part of its Revenue Budget so while the level of
gross Capital resources increases by £100,000, there is no requirement for
corresponding Capital expenditure and the grant can be applied to reducing
the level of borrowing for the current programme.  
3.5 There is an increase in Third Party Contributions of £371,000 for Structural
Maintenance (Section 4.3.3), relating to Roads Bonds for the purpose of
bringing roads up to an adoptable standard.

Page 3

3.6 The projected Borrowing Requirement in 2022/23, which is effectively the
balancing item for resources, is £100,607,000. This is £28,095,000 lower than
the Borrowing Requirement approved on 30 November 2022, and mainly
reflects the revised phasing for the new Perth High School included within this
report following the approval of the project by Council on 21 December 2022
(report 22/312 refers). 
3.7 The total Borrowing Requirement in the subsequent years 2023/24 to 2027/28
has increased by £35,792,000 to £440,423,000, resulting in an increase of
£7,697,000 across the whole 6-year programme. The movement in borrowing
is summarised as follows: 
2022/23 2023/24 2024/25 Later 
Years
Total 
£’000 £’000 £’000 £’000 £’000
Increase in General Capital Grant
(Section 3.4) (100) 0 0 0 (100)
Increase/(Decrease) in
expenditure for the Perth High
School Replacement (Section
4.2.2)
(24,776) 14,617 6,559 15,100 11,500
(Decrease)/Increase in
Communities Prudential Borrowing
(Section 4.3.8)
(1,348) (2,977) 223 399 (3,703)
Movements arising from re-
phasing of other expenditure and
receipts (Appendix II)
(1,871) (6,368) 4,919 3,320 0
(Decrease)/Increase in
Borrowing Requirement (28,095) 5,272 11,701 18,819 7,697 
3.8 The chart below shows the Capital Resources required to fund the 2022/23
Composite Capital Programme following the proposed budget adjustments
detailed in this report. 
70.1%
25.5%
0.5%
1.1%
2.1%
0.7%
4.4%
Projected Capital Resources 2022/23
(January 2023)
Borrowing (£100.607M)
Grants (£36.543M)
Tay City Deal (£0.734M)
Developer Contributions (£1.549M)
Third Party & Revenue Contributions (£3.067M)
Receipts (£0.965M)
£Million

Page 4

4. COMPOSITE CAPITAL PROGRAMME – EXPENDITURE 
4.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
4.1.1 Total expenditure (net of grants and contributions) to 31 December 2022 on
the Composite Capital Programme amounts to £55,332,000, which is detailed
in Appendix II and summarised as follows: 
Net Expenditure
to 31 Dec 2022
£’000
Education & Children’s Services  13,485
Communities 37,211
Health and Social Care    278
Corporate & Democratic Services 4,358
Total 55,332 
4.1.2 A comprehensive monitoring exercise has been carried out, which is detailed
in Appendix II. The most significant features are discussed below. 
4.2 Education and Children’s Services 
4.2.1 The Executive Director (Education & Children’s Services) has reviewed the
programme for their Service with the following movements to report at this
time. 
4.2.2 A full business case for the Perth High School Replacement project was
considered by the Council on 21 December 2022 (Report 22/312 refers). The
Council approved that the budget for the Perth High School Replacement be
increased by £11.5M to £80.2M in order that the project could reach financial
close. Following this increase in the budget, work has been undertaken to
rephase the budget accordingly. The proposed revised budgets for each year
are detailed in Appendix II. 
4.2.3 Within the Investment in the Learning Estate there have been increased
upgrades to school furniture and blinds completed in the current financial
year. It is proposed to accelerate £180,000 from next year to the current
financial year to cover these costs. It is also proposed to transfer £600,000
from the Early Learning & Childcare (ELC) budget in the current financial year
to the Investment in the Learning Estate budget to allow works scheduled to
be undertaken in the school holidays in 2024/25. 
4.2.4 Within Technology Upgrades, due to the level of works forecast to be
undertaken before the year end, it is proposed to move £100,000 from the
current year to next financial year. 
4.2.5 The refurbishment work at Perth Academy is progressing well and it is
proposed that £350,000 of the budget is accelerated from next year to the
current year to cover the works which are now due for completion this year.
The upgrade program within Perth Grammar School is currently focused on
audio visual and Wi-Fi upgrades which requires works taking place within

Page 5

classrooms. Due to the limited access to classrooms during term time, works
that can be undertaken by the end of the financial year are less than
anticipated and it is, therefore, proposed that £200,000 of the budget is moved
from the current financial year to next year to allow the works to take place in
the school holidays. 
4.2.6 All the above proposed adjustments have been reflected in Appendix II. 
4.3 Communities 
4.3.1 The Executive Director (Communities) has reviewed the programme for their
Service and proposes various budget adjustments, the most significant of
which are described below. 
4.3.2 Within Asset Management – Roads & Lighting, additional expenditure of
£371,000 will be incurred to bring a road to an adoptable standard. While this
increases the gross Capital expenditure of the Council as reflected in section
3 above, there is no net impact on the Capital budget as the works are funded
by a matching third party contribution. 
4.3.3 Within Asset Management – Bridges, works within the Bridge Refurbishment
Programme face slight delays due to current staff capacity, with recruitment
for an engineering post ongoing. The budgets for each year have been
reviewed and it is proposed that they are rephased with reductions of
£151,000 in the current year; £194,000 next year and £575,000 in 2024/25; to
be offset with increases of £250,000 in 2025/26; £555,000 in 2026/27 and
£115,000 in 2027/28. 
Comrie Flood Protection Scheme 
4.3.4 It had previously been reported to this Committee (Report 22/298 refers) that
the consultants working on the detailed design of the Comrie Flood Protection
Scheme were approximately three months behind schedule. The Executive
Director (Communities) has provided the following position statement and
update on progress with the scheme:   
• The advance works for the Comrie Flood Protection Scheme were
substantially completed by the end of 2022, except for outstanding erosion
protection work at Field of Refuge and some minor public utility works. The
delivery of these works has helped to mitigate the risks to the main
construction works that will follow. 
• Work on the erosion protection works at the Field of Refuge were paused
in October 2022 due to the environmental (fisheries) restrictions around
working within the Water of Ruchill. The Contractor (Balfour Beatty) has
left site but will return to complete this work once these restrictions are
lifted in May.  We are also planning to commence further site clearance
works prior to this, in preparation for the main works. 
• The conclusion of the detailed design for the main works continues to take
longer than anticipated. A further meeting has been held with our

Page 6

consulting engineers, Sweco. They have just provided an updated
programme which indicates that they now plan to complete the detailed
design at the end of March 2023. 
• It is therefore likely that the main construction works will commence in
Summer 2023, following on from the outstanding erosion protection work. 
Accordingly, work to be completed in the current year and next year has been
reduced and it is proposed that the budget for the current year and next year
are reduced by £622,000 and £3,833,000 respectively, with an increase of
£4,455,000 in 2024/25.   
4.3.5 Additionally, within the Flood Protection Schemes, due to the recent flood
events across the region, resources have been diverted to deal with the
impacts of the severe weather events. This has resulted in a delay to the flood
protection schemes at Milnathort and South Kinross with both schemes
moving by one year. It is proposed that the majority of the budget for the
Milnathort Scheme is moved from 2023/24 to 2024/25; and that the majority of
the budget for the South Kinross Scheme is moved from 2024/25 to 2025/26.  
4.3.6 Following confirmation that the new Perth Museum will house objects that are
currently held within Perth Museum and Art Gallery (PMAG), it has been
determined that PMAG would be renamed Perth Art Gallery and that works
would be undertaken to convert areas to be more suitable for the increased
display of artwork. Works to facilitate this transition have begun and it is,
therefore, proposed that £100,000 is accelerated from next year into the
current year to meet the costs of altering the exhibition spaces. 
4.3.7 Within Community Greenspace, Play Areas – Improvement Implementation
Strategy, due to the current staff resource capacity there is a minor delay to
the implementation of schemes that have been prepared in various locations.
Work on the ground is not expected to commence in the current year and so it
is proposed that £248,000 of the budget is slipped from the current year to
next year in line with the anticipated works. 
4.3.8 Within Prudential Borrowing, a comprehensive review has been undertaken of
the Vehicle Replacement Programme and Disposals and the vehicles that will
be replaced through the remainder of this year and next year. This has
resulted in a reduction in the overall programme of £3,703,000 with vehicles
lasting longer than expected mainly due to a reduction in mileage, as well as
delays in the supply of new vehicles due to the shortage of chips.
Consequently, it is proposed that an adjustment is made to the Purchase and
Disposal receipts as set out in Appendix II. 
4.3.9 On 19 January 2023, the Council was informed by the Department for
Levelling Up, Housing & Communities that the application for £10 million of
round two levelling up grant funding for the Eco-Innovation Park has been
unsuccessful. The Council is currently awaiting feedback on its application. 
4.3.10 All the above proposed adjustments, together with other small movements,
have been reflected in Appendices I & II.

Page 7

4.4 Corporate & Democratic Services 
4.4.1 The Chief Operating Officer has reviewed the programme for their Service
and proposes the following adjustments described below. 
Property Services 
4.4.2 Within DDA Adaptation & Alteration Works, lift works require rescheduling due
to difficulties in sourcing components and materials with these unlikely to be
received this financial year. It is, therefore, proposed that £200,000 is moved
from the current year to next year. 
4.4.3 Within Property Compliance Works it is proposed that £221,000 is accelerated
from next year to the current year in part to cover new gas pipework required
at Blairgowrie High School. 
4.4.4 Previously within Capital Improvement Projects, £600,000 was accelerated
from 2027/28 to the current year to fund energy efficiency measures. Although
works have progressed, it is anticipated that £400,000 of this accelerated
funding will not be utilised in the current year and it is, therefore, proposed
that this budget be moved into next year. Also, within Capital Improvement
projects, following the carrying out of scheduled works at Blairgowrie High
School and The Community School of Auchterarder, structural improvements
have been identified which are due to take place this year. It is proposed that
£400,000 for these works is brought forward from next year to the current
year. 
4.4.5 Upgrades to Pitlochry High School have been paused for a couple of months
to allow electrical compliance works to be carried out. This has resulted in a
reduction in the level of upgrade works which can be completed this year and
it is proposed that £90,000 is moved from the current year to next year to
finalise this project. 
4.4.6 Energy Efficiency Works which are being fully funded by the Salix reserve are
no longer taking place in the current year, and it is therefore proposed that
both the budget and the reserve contribution of £99,000 are moved from the
current year to next year. 
Information Systems & Technology 
4.4.7 Within the ICT Infrastructure & Replacement and Upgrade programme there
has been a change to planned contracting periods in order to bring security
enhancements in line with the Microsoft licensing renewal later in 2023. As
such, it is proposed that £447,000 is rephased from the current year to next
year in line with expected spend. Also, within this budget, a review has been
undertaken of the anticipated expenditure and licensing requirements in future
years, and this has resulted in updated budget profiles. Therefore, it is
proposed to decrease the revised budget in 2023/24 by £1,854,000, giving a
net movement of £1,407,000. with this being rephased across the following 5
years of the current programme.

Page 8

4.4.8 Within the Supporting Digital programme, it is proposed to move £137,000
from the current year into next year in line with the current projection of works
that will be concluded before the end of the year. 
4.4.9 All the above proposed adjustments, together with other small movements
have been reflected in Appendices I & II. 
Major Capital Projects 
4.4.10 Appendix IV to the report shows progress on the delivery of major Capital
projects within the approved Capital programme. The appendix summarises
budgeted expenditure and the current projected outturn on these projects;
their anticipated completion date; current status and any significant changes
since the last monitoring report. This appendix will be kept updated and it is
proposed to report on an exceptions basis where there are significant
changes in the status of major Capital projects, for example in terms of
forecast cost, scope or anticipated completion date. 
4.4.11 In this regard, the Executive Director (Communities) has provided a position
statement and update on progress with the delivery of the Comrie Flood
Protection Scheme which is set out in section 4.3 of the report. 
5. HOUSING INVESTMENT PROGRAMME 
5.1 The current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2022/23 to 2026/27 amounts to
£84,018,000. Movements from the previous estimates approved by this
Committee on 30 November 2022 are summarised in the table below and
detailed in Appendix III. 
Approved 
30 Nov 2022
Current
Estimate
Movement
£’000 £’000 £’000
2022/23 18,965 18,990 25
2023/24          16,457          16,457 0
2024/25 13,858 13,858 0
2025/26 18,694 18,669 (25)
2026/27 16,044  16,044  0
Total 84,018 84,018 0 
5.2 Total Expenditure to 31 December 2022 (Housing Investment Programme) 
Net expenditure for 2022/23 to 31 December 2022 amounts to £8,174,000
and receipts amount to £9,000. This therefore means that the borrowing
requirement for the year to date is £8,165,000. 
5.3 It is proposed to transfer £25,000 to support the conversion of the former
driving test centre at 111 Rannoch Road Perth from the SHQS Future
Developments Budget in 2025/26. This is to cover additional costs associated
with installing air source heat pumps, upgrading the electrical fuse box, as
well as additional garden landscaping.

Page 9

5.4 Miscellaneous Receipts have increased by £5,000 to £9,000. Consequently,
the Borrowing Requirement has reduced by £5,000, giving a revised overall
total for the 5-year programme of £67,338,000. 
6. SUMMARY 
6.1 The projected net expenditure outturn in 2022/23 for the Composite Capital
Budget is £117,566,000 and represents 85% of the 2022/23 budget as
approved on 20 April 2022 (£138,276,000). The revised budget is based on
the latest projection of expenditure and all budget adjustments outlined within
this report. 
6.2 Net expenditure to 31 December 2022 on the Composite Capital Budget is
£55,332,000 and represents 47% of the proposed revised budget for 2022/23
of £117,566,000. However, actual expenditure to 31 December 2022 shown
above does not include accrued expenditure or provision for works certified as
completed by that date. All such expenditure is accounted for when preparing
the final outturn as at 31 March 2023. 
6.3 The projected net expenditure outturn in 2022/23 for the Housing Investment
Programme is £18,990,000 and represents 106% of the 2022/23 budget
approved on 20 April 2022 (£17,963,000). 
6.4 Net expenditure to 31 December 2022 on the Housing Investment Programme
is £8,174,000, subject to the same caveat outlined above for the Composite
Programme, which represents 43% of the proposed revised budget for
2022/23 of £18,990,000. 
6.5 A summary of the major capital projects included with the Council’s
Composite Capital Budget and Housing Investment Programme and their
current status is included at Appendix IV. 
6.6 As previously outlined in the last monitoring report to this Committee, and in
the Revenue & Capital Update at the Council meeting on 21 December 2022,
the delivery of all the approved projects and programmes within the current 6-
year Capital Budget is no longer expected to be affordable under the current
funding strategy due to the impact of contract inflation alone. This position will
likely be compounded by the impact of anticipated higher borrowing costs
over the next few years. This will be subject to ongoing discussion with
elected member Budget Review Groups as part of their consideration of the
Capital Budget on 1 March 2023. 
Author(s)
Name  Designation Contact Details
John Jennings Senior Accountant CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date
Karen Donaldson 
Stewart MacKenzie
Chief Operating Officer 
Head of Finance
24 January 2023 
24 January 2023

Page 10

No embedded text on this page.

Page 11

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND
COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2022 – 2027 lays out seven outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
(i) Tackling Poverty 
(ii) Tackling climate change and supporting sustainable places 
(iii) Growing a sustainable and inclusive local economy 
(iv) Enabling our children and young people to achieve their full potential 
(v) Protecting and caring for our most vulnerable people   
(vi) Supporting and promoting physical and mental wellbeing
(vii) Placing communities at the heart of how we work 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report.

Page 12

Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report. 
Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Chief Executive and the Executive Directors have been consulted in the
preparation of this report.

Page 13

2. BACKGROUND PAPERS 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
• Appendix I – Composite Capital Programme - Estimated Capital
Resources 2022/23 to 2027/28
• Appendix II – Composite Capital Programme - Summary of Capital
Resources and Expenditure 2022/23 to 2027/28        
• Appendix III – HRA Capital Investment Programme – Summary of
Capital Resources and Expenditure 2022/23 to 2026/27 
• Appendix IV – Significant Capital Projects Progress Update