Agenda Document Pack - Finance and Resources Committee - 07/09/2022

Perth and Kinross Council · 7 September 2022
Back to Finance and Resources Committee — 7 September 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Securing the future… • Improving services 
• Enhancing quality of life • Making the best use of public
resources 
Council Building
2 High Street
Perth
PH1 5PH 
31/08/2022 
A hybrid meeting of the Finance and Resources Committee will be held in the
Council Chamber on Wednesday, 07 September 2022 at 14:00. 
If you have any queries please contact Committee Services on (01738) 475000 or
email Committee@pkc.gov.uk. 
THOMAS GLEN
Chief Executive 
Those attending the meeting are requested to ensure that all notifications are
silent on their device and other devices are in silent mode. 
Please note that the meeting will be broadcast online and recorded.  The
recording will be publicly available on the Council’s website following the
meeting. 
Members:
Councillor Stewart Donaldson  (Convener)
Councillor Grant Laing  (Vice-Convener)
Bailie Chris Ahern
Bailie Alasdair Bailey
Councillor Peter Barrett
Councillor Andy Chan
Councillor Dave Cuthbert
Councillor Eric Drysdale
Councillor John Duff
Councillor Angus Forbes
Provost Xander McDade
Councillor Tom McEwan
Councillor Andrew Parrott
Councillor John Rebbeck
Councillor Caroline Shiers
Councillor Colin Stewart
Page 1 of 132

Page 2

Page 2 of 132

Page 3

Finance and Resources Committee 
Wednesday, 07 September 2022 
AGENDA 
MEMBERS ARE REMINDED OF THEIR OBLIGATION TO DECLARE ANY
FINANCIAL OR NON-FINANCIAL INTEREST WHICH THEY MAY HAVE IN ANY
ITEM ON THIS AGENDA IN ACCORDANCE WITH THE COUNCILLORS’ CODE
OF CONDUCT. 
1 WELCOME AND APOLOGIES/SUBSTITUTES   
2 DECLARATIONS OF INTEREST   
3 MINUTE OF MEETING OF THE FINANCE AND RESOURCES
COMMITTEE OF 5 JUNE 2022 FOR APPROVAL
(copy herewith) 
5 - 8 
4 OUTSTANDING BUSINESS STATEMENT
(copy herewith) 
9 - 10 
5 REVENUE BUDGET 2022/23 - UPDATE NO. 1
Report by Chief Accountant (copy herewith 22/208) 
11 - 40 
6 COMPOSITE CAPITAL BUDGET 2022/28 & HOUSING
INVESTMENT PROGRAMME 2022/27 - MONITORING REPORT
NO. 1
Report by Head of Finance (copy herewith 22/209) 
41 - 90 
7 TREASURY ACTIVITY AND COMPLIANCE REPORT 2022/23
QUARTER 1
Report by Head of Finance (copy herewith 22/210) 
91 - 110 
8 ANNUAL TREASURY REPORT 2021/22
Report by Head of Finance (copy herewith 22/211) 
111 - 126 
9 COMMUNITY INVESTMENT FUND 2022/23
Report by Head of Culture and Community Services (copy herewith
22/212) 
127 - 132 
10  APPOINTMENT OF MEMBER OF THE EXECUTIVE SUB-
COMMITTEE
The Committee is asked to note the decision taken to appoint the
following members of the Finance and Resources Committee to the
Executive Sub-Committee: 
Page 3 of 132

Page 4

Councillor Stewart Donaldson
Councillor Grant Laing
Councillor Eric Drysdale
Councillor John Duff
Councillor Caroline Shiers
Councillor Peter Barrett
Councillor Dave Cuthbert 
Page 4 of 132

Page 5

FINANCE AND RESOURCES COMMITTEE 
Minute of hybrid meeting of the Finance and Resources Committee held in the
Council Chamber, 2 Hight Street, Perth on Wednesday 15 June 2022 at 2.00pm. 
Present: Councillors S Donaldson, Baillie Ahern, Baillie Bailey, P Barrett, A Chan,
D Cuthbert, E Drysdale, J Duff, N Freshwater (substituting for Councillor A Forbes),
G Laing, Provost McDade, T McEwan, A Parrott, J Rebbeck, C Shiers and C
Stewart. 
In Attendance: T Glen, Chief Executive; K Donaldson, Chief Operating Officer;
B Renton, Executive Director (Communities), M Butterworth, C France, C Guild,
D Littlejohn, C Mailer, P Marshall, B Murray, F Robertson, A Taylor and R Wills (all
Communities); S Devlin, Executive Director (Education and Children’s Services);
G Boland (Education and Children’s Services); and I Caldow, S Crawford, K Fraser,
L Harris, J Jennings, P Johnstone, S Mackenzie, L Simpson, N Sutherland,
S Walker, A Brown, K Molley, B Parker and A McMeekin (Corporate and Democratic
Services) and S Strathearn (Health and Social Care Partnership). 
Apology: Councillor A Forbes 
Councillor S Donaldson, Convener, Presiding. 
1. WELCOME AND APOLOGIES 
The Convener welcomed all those present to the meeting and apology was noted
above. 
2. DECLARATIONS OF INTEREST 
There were no Declarations of Interest in terms of the Councillors’ Code of
Conduct. 
3. MINUTE OF PREVIOUS MEETINGS 
The minute of meeting of the Strategic Policy and Resources Committee of
20 April 2022 was submitted and approved. 
4. APPOINTMENT OF MEMBERS TO THE EXECUTIVE SUB-COMMITTEE
OF FINANCE AND RESOUCES COMMITTEE 
It was decided to withdraw this from the agenda to allow further discussion as
part of the changes to the Scheme of Administration at full Council on 22 June. 
5. APPOINTMENT OF MEMBERS TO THE PROVOSTS SUB-COMMITTEE 
It was decided to withdraw this from the agenda to allow further discussion as
part of the changes to the Scheme of Administration at full Council on 22 June. 
3
Page 5 of 132

Page 6

6. TREASURY ACTIVITY AND COMPLIANCE REPORT 2021/22 QUARTER 4 
There was submitted a report by the Head of Finance (22/122) (1) updating
the Committee on the Treasury Activity for the quarter ending 31 March 2022 and to
report on compliance with the Council’s Treasury Management Policy Statement
(TMPS); Investment Strategy and Prudential Indicators; and (2) covering the fourth
quarter of the financial year for the period 1 January to 31 March 2022. 
Resolved: 
The contents of Report 22/8, which is submitted in accordance with the
Council’s approved Treasury Management Practices, be noted. 
7. AUTHORITY TO WRITE OFF BAD DEBTS AND OBSOLETE STOCK 
There was submitted a report by the Head of Finance (22/123) seeking
approval to write off identified debs in respect of Sales Ledger; Council Tax
(including Water & Waste Water charges); Non-Domestic Rates; Irrecoverable
Rents; Housing Benefit Overpayments and Car Park Trading Account Income; and is
sought to write off obsolete stock and write on other miscellaneous balances. 
Resolved:
(i)  It be approved that all amounts detailed in section 4 of report 22/123 and the
attached appendices are written off or on accounting purposes. 
(ii)  It be noted that whilst these amounts are written off or written on, the files are
not closed, and every effort will be made to collect outstanding debt where
recovery is cost effective. 
(iii) The removal of charges for services for people seeking asylum detailed in
section 5 of report 22/123, be approved. 
8. CORPORATE AND DEMOCRATIC SERVICES JOINT BUSINESS
MANAGEMENT AND IMPROVEMENT PLAN 2022/23 
There was submitted a report by the Chief Operating Officer (22/124) (1)
presenting the Joint Service Business Management and Improvement Plan 2022/23
and Annual Performance Report 2021/22 for Corporate and Democratic Services; (2)
detailing the progress of our work in supporting the Council’s objectives and service
delivery; and (3) highlighting the challenges and priority focus areas for the coming
year. 
Resolved:
The Corporate and Democratic Services Joint Business Management
Improvement Plan 2022/23 and Annual Performance Report 2021/22, be approved. 
COUNCILLOR P BARRETT LEFT THE MEETING AT THIS POINT. 
9. LOCH LEVEN GUIDANCE   
There was submitted a report by the Head of Planning and Development
(22/125) summarising the comments received during the consultation on non-
statutory planning guidance published for consultation in 2022; and (2) seeking
Page 6 of 132

Page 7

approval to finalise and adopt the guidance document to support the Local
Development Plan (adopted November 2019) as non-statutory Supplementary
Guidance. 
Resolved:  
The Loch Leven Guidance to support the implementation of Policy 46 of the
Local Development Plan, be approved. 
Page 7 of 132

Page 8

Page 8 of 132

Page 9

FINANCE AND RESOURCES COMMITTEE
(Report No. 22/215)
OUTSTANDING BUSINESS STATEMENT (OBS) 
Please note that this statement sets out outstanding decisions of this committee along with an update and estimated completion date.  Actions
which are overdue are shaded for ease of reference.  Where an update reflects that an action is complete then the Committee’s agreement will be
sought to its removal from the OBS. 
No  Minute
Reference
Subject Title Outstanding Action Update  Lead Officer
/Service
Action 
due
Action
Expected
1. 15 June 2022
Item 4.
Appointment of
Members to the
Executive Sub-
Committee of
Finance and
Resources
Committee
Appointment of
Members to be
deferred to a future
meeting of the
Finance and
Resources
Committee to allow
further discussion
with officers. 
It was agreed at Council
on 22 June for the
membership to increase
to 7 members. 
Names of members will
be added to the agenda
on 7 September 2022 for
noting. 
NOT COMPLETE 
7 September
2022
7 September
2022
2. 15 June 2022
Item 5. 
Appointment of
Members to the
Provosts Sub-
Committee of
Finance and
Resources
Committee
Appointment of
Members to be
deferred to a allow
further discussion
with officers.
It was agreed at Council
on 22 June for the
membership to increase
to 7 members and will
consist of the Provost,
Depute Provost and the
five Bailies. The sub-
committee will now report
to Council. 
COMPLETED 
22 June
2022
22 June
2022 
3. 15 June 2022
Item 6. 
Treasury Activity
and Compliance
Report 2021/22
Quarter 4 
Provide members
with an update on
what would be the
additional cost to
the Council per
Briefing note issued. 
COMPLETED.
Stewart MacKenzie  7 September
2022 
7 September
2022 
4
Page 9 of 132

Page 10

No  Minute
Reference
Subject Title Outstanding Action Update  Lead Officer
/Service
Action 
due
Action
Expected
annum of a 1%
increase in PWLB
borrowing rates. 
4. 15 June 2022
Item 7. 
Authority to Write
Off Bad Debts and
Obsolete Stock 
Provide members
with a briefing note
on Funding
Arrangements for
Ukrainian
Displaced People
resettling in Perth
and Kinross
Briefing note issued. 
COMPLETED 
Elaine Ritchie 7 September
2022
7 September
2022
5.  15 June 2022.
Item 7. 
Authority to Write
Off Bad Debts and
Obsolete Stock 
Provide members
with details on
collections rates on
garage sites and
lock ups and the
percentage of
income it
represents. 
Email response issued to
members. 
COMPLETED.
Elaine Ritchie   7 September
2022
7 September
2022
6. 15 June 2022
Item 8.
Corporate and
Democratic
Services Joint
Business
Management and
Improvement Plan
2022/23 and
Service Annual
Performance
Report 2021/22
A briefing session
to be arranged with
members as part of
the Development
Programme on the
different IT
systems the
Council uses. 
Briefing session to be
arranged as soon as
possible for members. 
NOT COMPLETED 
Alan Taylor/Karen
Donaldson
TBC 7 September
2022
Page 10 of 132

Page 11

PERTH & KINROSS COUNCIL 
Finance & Resources Committee 
7 September 2022 
REVENUE BUDGET 2022/23 – UPDATE NO.1 
Contact Officer: Scott Walker, Chief Accountant
(Report No. 22/208) 
1. PURPOSE 
1.1 This report provides an update on progress with the 2022/23 General Fund
Revenue Budget based upon the June 2022 ledger, updated for any
subsequent known material movements, and the projected financial position
of the Housing Revenue Account. 
1.2 The total net projected over spend on the 2022/23 General Fund Management
Budget is £2.012 million (see Appendix 1). 
2. RECOMMENDATIONS 
2.1 The Committee is requested to: 
i) note the contents of the report, 
ii) note the projected outturn for General Fund Services set out in Section
4 and Appendix 1 and 2 
iii) approve a review of Perth Harbour operations for consideration by
elected members – see paragraph 4.16 
iv) note the projected outturn for Corporate Budgets set out in Section 5 
v) note the Health & Social Care projected outturn, which is summarised
in section 5 and Appendix 3, 
vi) note the projected outturn for the Housing Revenue Account which is
summarised in Section 6 and Appendix 4. 
vii) approve the adjustments to the 2022/23 Management Revenue Budget
detailed in Appendices 1, 2, 4, 5 and 6 and Section 7, 8, 9 and 10. 
viii) note that this position will be kept under review and mitigating action
may be required to manage the projected over spend in 2022/23. 
3. BACKGROUND 
3.1 This report updates the Committee on progress with the 2022/23 Revenue
Budget.  Appendix 1 to this report summarises the current projected year end
5
Page 11 of 132

Page 12

(outturn) position for each Service based upon the June 2022 ledger, updated
for any subsequent known material movements. 
3.2 The budget total reflected in Column 1 of Appendix 1 to this report is that
approved by the Council in setting the 2022/23 Final Revenue Budget on 23
February 2022 (Report No. 22/35 refers).  In addition, adjustments approved
by Council on 25 May and 17 August 2022 and by the Strategic Policy &
Resources Committee on 20 April 2022 (Report No. 22/87 refers) are
reflected in Appendix 1 (Column 2).   
3.3 The Council’s Financial Regulations currently allow Executive Directors to vire
budgets up to £100,000 within their Service.  Any virements between Services
of more than £100,000 are either included in the body of the revenue
monitoring report or in the appendices for approval. 
3.4 This report details the latest projected outturns and proposed adjustments to
the 2022/23 General Fund and Housing Revenue Account budgets. 
3.5 On 22 June 2022, the Council approved the Financial Strategy which set out a
number of principles that will assist Medium Term Financial Planning and
development of Revenue and Capital Budgets (Report No. 22/141 refers). 
4. REVENUE MONITORING – SERVICE BUDGETS 
4.1 Details of variances against Service budgets are shown in Appendix 2 to this
report with the most significant variances summarised below.  The total net
projected over spend on Service budgets, as set out in Appendix 1 to this
report, is £1.568 million which represents 0.45% of total net Service
expenditure. 
4.2 The management of Service over and under spends are considered
throughout the financial year and may also form part of the Revenue Budget
strategy for future years. 
4.3 There remains a risk that the Council continues to experience increases in
costs over the short to medium term that are higher than budgeted inflation
levels.  This is already being seen in the cost of the materials required by
property and housing maintenance teams.  Going forward, this may have an
impact on projected outturns and future years’ budgets. 
4.4 In addition, the 2022/23 pay negotiations have not yet concluded which
presents a further risk to both the current year’s Revenue Budget and future
years. 
Education & Children’s Services
4.5 The projected outturn for Education & Children’s Services excluding Devolved
School Management (DSM) and the Pupil Equity Fund (PEF) is currently
anticipated to be in line with the budget.  However, there are several
projected over and under spends that are summarised as follows. 
Page 12 of 132

Page 13

4.6 Within non devolved Education Services there is a projected under spend of
£737,000.  This is primarily a result of staff slippage within the Nursery Sector,
an insurance rebate in the Secondary Sector and projected under spends on
home to school transport and additional support needs provision within the
Special Sector. 
4.7 In Services for Children, Young People & Families there is a projected net
over spend of £1.376 million.  The main factor contributing to this position is
increased demand / need for support for young people with complex
behavioural issues, kinship care, support for care experienced young people
and self-directed support.  Officers continue to monitor the need for
placements and consider any mitigations which could prevent residential care. 
However, this is frequently governed via legislative controls and the need to
manage high levels of risk.  Furthermore, the staff slippage target is not being
achieved and there is a projected over spend on legal fees and the cost of
translation / interpreter services.  This position is partially offset by additional
grant funding. 
4.8 In Business & Resource Services there is a projected under spend of £71,000
due to staff slippage and reduced recharges. 
4.9 In Catering Services there is a projected net under spend of £568,000 due
primarily to reduced uptake for nursery and breakfast club meals and staff
slippage. 
4.10 There is a planned under spend of £449,000 on Devolved School
Management budgets (DSM) due to staff slippage which represents 0.4% of
the overall DSM budget.  It is anticipated that in line with the approved DSM
scheme, the eventual over and under spends will be carried forward into
2023/24.  The budgets for the Devolved School Management scheme are
allocated by financial year (April – March), whereas expenditure is incurred by
academic year (August – June). 
4.11 At this stage of the academic year, expenditure met from the Pupil Equity
Fund (PEF) is projected to be £300,000 less than the allocation from the
Scottish Government of £1.874 million.  Schools are being instructed to use
this year’s PEF by 31 March 2023.  It is anticipated that the projected under
spend on teacher and support costs will be carried forward to 2023/24 to meet
commitments.  The budgets for the Pupil Equity Fund scheme are allocated
by financial year, whereas expenditure is incurred by academic year. 
Communities 
4.12 The projected outturn for Communities is currently anticipated to be £248,000
more than budget.  The movements are summarised as follows. 
4.13 In Business & Resources there is a projected net under spend of £40,000. 
This is made up of asset management savings partially offset by additional
costs at Perth Bus Station.  Within this projection there is a projected deficit
on the Car Park Trading Account of £355,000 which will be funded by the Car
Park Trading Account earmarked Reserve.
Page 13 of 132

Page 14

4.14 In Environmental & Consumer Services there is a projected net over spend of
£115,000 due to inflationary pressures on fuel and shortfall in commercial
waste income partially offset by a rephasing of loan charges relating to the
vehicle replacement programme and income from statutory road charges. 
4.15 In Planning & Development there is a projected over spend of £98,000 due to
additional operating costs and reduced income at Perth Harbour – this is in
addition to the budgeted deficit of £178,000.   
4.16 Perth Harbour continues to underperform against Business Plan expectations
with a total of four cargo consignments this year, and one since April.  The
industrial land around the Harbour is either privately owned or held in the
Common Good and therefore the principal income generated by the Harbour
is from vessel dues and leasing out the Fair Maid tug to Montrose Port.  Total
income to date this financial year is £12,600 of which £1,800 is from vessel
dues. The Harbour Board has indicated that it anticipates additional
expenditure in the region of £80,000 later this year largely in respect of
proposed dredging at the Harbour mouth, due to the build-up of sediment
normally dispersed by vessel propellors. Accordingly the Board is looking to
the Council to fund this further pressure. 
4.17 The following table provides elected members with a high-level summary of
the final outturns for Perth Harbour over the last five years. 
Gross Expenditure Gross Income Deficit
FINAL OUTTURNS
2017/18 244,000 29,000 215,000
2018/19 394,000 39,000 355,000
2019/20 241,000 68,000 173,000
2020/21 265,000 72,000 193,000
2021/22 334,000 45,000 289,000
PROJECTED OUTTURNS
2022/23 315,000 39,000 276,000 
4.18 Given the uncertainty around future income relative to expenditure, officers
would propose  undertaking a review of Harbour operations for consideration
by members, prior to any decision being taken regarding additional funding. 
4.19 ACTION: The Committee approves a review of Perth Harbour operations for
consideration by elected members. 
4.20 In Housing there is a projected over spend of £75,000 due to additional costs
relating to Greyfriars Hostel and the Local House Condition Survey.
Page 14 of 132

Page 15

Corporate & Democratic Services 
4.21 The projected outturn for Corporate & Democratic Services is currently
anticipated to be £1.340 million more than budget.  The movements are
summarised as follows. 
4.22 In Property there is a net projected over spend of £1.658 million.  This is
primarily as a result of inflationary pressures on energy and maintenance
costs.  Work is underway to manage these over spends including energy
management measures and revisiting maintenance works. 
4.23 In Legal and Governance Services there is a projected net under spend of
£150,000.  The main reason for this is additional income from licensing and
recharges. 
4.24 Within Human Resources there is a projected under spend of £148,000 due
primarily to additional income from recharges. 
4.25 Across the remainder of the Service there is a projected under spend of
£20,000 due to staff slippage and additional income. 
Chief Executive Service
4.26 The projected outturn for the Chief Executive’s Service is currently anticipated
to be £20,000 less than budget due to staff slippage. 
5. REVENUE MONITORING – CORPORATE BUDGETS 
Health & Social care 
5.1 Across the Perth and Kinross Health & Social Care Partnership there is a
projected under spend of £1.196 million which is set out in Appendix 3.  This
projected under spend on social care is driven by slippage in planned Perth &
Kinross Integration Joint Board (PKIJB) investment in Older Peoples Services
as well as under spends in Care at Home and Care Home Placements. 
Recruitment of staff to support the planned expansion of services continues to
be a significant challenge.  Within Health, Older Peoples Services is
projecting an over spend within hospital activity levels leading to an
unplanned increase in bed numbers.  Similar recruitment challenges are being
experienced requiring significant use of premium rate staffing.  
5.2 Further information on the range of other factors impacting on this projection
is included in the PKIJB Finance Report for the quarter to 30 June 2022 which
will be published on 19 September 2022. 
5.3 In addition, there is a projected under spend of £356,000 on non-devolved
social care functions.   
Council Tax Income 
5.4 The amount of income the Council will generate from Council Tax is
dependent on two main factors, firstly the collection levels and secondly, the
number of Band D properties on the Valuation Roll.
Page 15 of 132

Page 16

5.5 Monitoring of Council Tax collection levels is carried out monthly.  The
following graph sets out collection performance to 31 July together with prior
year comparative figures for the previous five financial years (the collection
level for 2022/23 has been adjusted to reflect the consequences of the
Scottish Government funded Cost of Living Award on in year performance). 
5.6 Between 2017/18 and 2021/22, the average collection figure to 31 March was
37.24%.  The actual collection figure to 31 July 2022 was 37.35% which is an
increase of 0.11% compared to the historical average and a 0.28% increase
on the comparable position in 2021. 
5.7 Secondly, in setting the Council’s Revenue Budget, assumptions are made on
increases in the number of Band D equivalent properties.  The graph set out
below suggests that actual growth levels are in line with budget assumptions. 
2017/18 2018/19 2019/20 2020/21 2021/22 2022/23
Series1 37.79% 37.60% 37.49% 36.23% 37.07% 37.35%
35.0%
35.5%
36.0%
36.5%
37.0%
37.5%
38.0%
In Year Collection to 31 July
Page 16 of 132

Page 17

\
5.8 The latest projected outturn indicates that Council Tax income is in line with
budgeted assumptions in 2022/23.  There are several national issues that
may impact on Council Tax income going forward.  The potential impact of
these issues will be kept under review with updates to elected members being
provided to future meetings of this Committee. 
Council Tax Reduction Scheme 
5.9 Council Tax Reduction is a statutory function and encouraging take up is a
key responsibility for the Council, particularly when households are facing
significant pressures on the cost of living. 
5.10 The Council is currently supporting approximately 8,300 households across
Perth and Kinross with the Council Tax Reduction Scheme with an average
award of £16 per week.  This results in a projected over spend on the Council
Tax Reduction Scheme of approximately £800,000. 
Non-Domestic Rates 
5.11 The actual collection rate to 31 July 2022 was 24.06%, compared to 21.88%
for the same period in 2021/22. 
6. REVENUE MONITORING – OTHER REVENUE BUDGETS 
Housing Revenue Account 
6.1 The Housing Revenue Account is currently projected to break even in the
current financial year.  The main reasons for this movement are summarised
below and set out in Appendix 4.
Page 17 of 132

Page 18

6.2 In Housing & Repairs there is a projected over spend of £273,000 due, in the
main, to inflationary pressures on materials, fuel and energy costs. 
6.3 In Perth City and Specialist there is a projected over spend of £104,000 due
to additional energy and staff costs. 
6.4 In Administration there is a projected under spend of £186,000 due to a
reduced bad debt provision and reduced recharges, partially offset by void
rent loss and Council Tax / utility charges. 
6.5 Across the remainder of the Housing Revenue Account there is a projected
net under spend of £35,000. 
6.6 As a result of the variances identified above Capital from Current Revenue will
be reduced by £156,000. 
6.7 In addition, it is proposed that £950,000 is drawn down from the HRA Covid-
19 earmarked Reserve to fund the activity set out in Appendix 4. 
Impact on Arm’s Length External Organisations (ALEOs) 
6.8 The Council continues to work closely with its three Arm’s Length External
Organisations (ALEOs) – Live Active Leisure (LAL), Horsecross Arts (Hx Arts)
and Culture Perth & Kinross (CPK) who make an important contribution to the
wellbeing of both citizens and visitors to Perth and Kinross. 
6.9 As sole member and core funder of all three ALEOS, the Council has
managed financial risk by maintaining normal monthly service level
agreement payments to all three organisations to mitigate the impact of
Covid-19.  In addition, officers continue to work closely with all three ALEOs to
understand the impact of Covid-19 more fully on service delivery. 
6.10 To date, no significant financial issues have been identified relating to Culture
Perth and Kinross or Horsecross Arts Ltd. 
6.11 Based on monitoring to 31 July 2022, Live Active Leisure (LAL) is projecting a
deficit in the range of between £600,000 and £1.2 million for 2022/23.  This
projection is based on four months of activity and therefore too early to
provide a firm position.  However, officers are closely monitoring the LAL
position given that in both 2020/21 and 2021/22 they delivered small
surpluses.  Key financial variables include – 
• staff costs (a number of key posts remain vacant, and this is likely to be
the case throughout the remainder of 2022/23); 
• maintenance expenditure (some works may not take place in 2022/23
due to key staff vacancies);
• the positive impact on income resulting from the continued closure of
Olympia in Dundee.
• LAL is now on the Scotland Excel procurement framework for energy
so is able to project utility costs with more certainty than in previous
years. 
Page 18 of 132

Page 19

6.12 Live Active Leisure continues to retain £600,000 in its reserves to contribute
to any year end deficit position. 
6.13 The long-term impact on Covid-19 on the Council’s ALEOs across future
financial years will be kept under review with updates provided to future
meetings of the Finance & Resources Committee. 
7. ISSUES ARISING FROM FINANCIAL YEAR 2021/22 
7.1 In completing the 2021/22 Unaudited Annual Accounts, several issues have
been identified which require adjustments to be made to the 2022/23
Management Budget. 
Devolved School Management 
7.2 In setting the 2022/23 Final Revenue Budget on 23 February 2022 (Report
No. 22/35 refers) the Council approved a Devolved School Management
(DSM) carry forward of £776,000.  However, the final under spend (which
included agreed planned carry forwards) on the DSM scheme was £1.191
million, an increase of £415,000 mainly due to a further rephasing of
expenditure in line with the academic year. 
7.3 ACTION: The Committee is requested to allocate the additional under spend
of £415,000 to Education & Children’s Services to reflect the additional
Devolved School Management scheme balances brought forward from
2021/22.  This adjustment is reflected in Appendix 1 (Column 3) to this report
and has no overall impact on the level of uncommitted Reserves. 
Revenue Grants 
7.4 Accounting arrangements under International Accounting Standards require
that, subject to certain conditions, revenue grants which were received by the
Council in 2021/22 but not utilised by 31 March 2022 should be accounted for
in Reserves at the end of the financial year.  Approval is sought to draw down
£8.815 million in 2022/23 from the earmarked Reserve for Revenue Grants. 
These revenue grants are set out in detail in Appendix 5. 
7.5 Approval is now sought to adjust the budgets of Education & Children’s
Services (£2.900 million), Communities (£4.147 million), Corporate &
Democratic Services (£1.610 million) and Health & Social Care (£158,000). 
7.6 ACTION: The Committee is asked to approve the adjustments totalling £8.815
million to the above Service budgets (set out in detail in Appendix 5), funded
from Reserves, to reflect revenue grants received in 2021/22 in respect of
expenditure which will not be incurred until 2022/23.  These additional
adjustments are reflected in Appendix 1 (Column 3) to this report and have no
overall impact on the budgeted level of uncommitted Reserves. 
Page 19 of 132

Page 20

8. 2022/23 ADDITIONAL FUNDING 
8.1 Since the 2022/23 Revenue Budget was updated on 20 April 2022 (Report
No. 22/87 refers), the Council has been advised of additional funding for the
current financial year from several sources.  To ensure that the 2022/23
Management Budget continues to reflect the operational requirements of the
Council, several adjustments are required, which are summarised below and
included in Appendix 1 and Appendix 6. 
Scottish Government – Revenue Support Grant: 
• Boost Targeted In-Person Easter Study Support 2022: £54,124
(Education & Children’s Services - ECS)
• 1+2 Languages: £30,942 (ECS)
• Targeted Holiday Provision for Primary School Children in Summer
2022: £242,363 (ECS)
• Whole Family Wellbeing 2022-23: £805,000 (ECS)
• SNCT Pay Award 2021/22 Recurring Costs for 2022/23: £863,000
(Reserves) 
8.2 The Scottish Government has advised that the increase in Revenue Support
Grant identified above of £1.995 million will be made through a
redetermination of the Council’s Revenue Support Grant.  It is therefore
necessary to adjust budgets for Education & Children’s Services, Reserves
and Revenue Support Grant. 
8.3 ACTION: The Council is asked to approve the adjustments set out at
paragraph 8.2 which is reflected in Appendix 1 (Column 4) to this report. 
Scottish Government – Ring Fenced Grants 
8.4 The Scottish Government has advised that the final amount allocated for Pupil
Equity Funding will be £209,410 more than previously advised.  In addition,
the Scottish Government has also advised that the total Criminal Justice
Social Work Grant for 2022/23 will be £467,265 more than originally
budgeted.  It is therefore necessary to adjust both the budget for Education &
Children’s Services and Ring Fenced Grant. 
8.5 ACTION: The Committee is asked to approve the adjustments set out at 8.4
above.  These adjustments are reflected in Appendix 1 (Column 4) to this
report. 
Other Funding 
8.6 Other funding amounting to £5.119 million will be paid outside the Revenue
Support Grant mechanism as Other Grant income and is, therefore, cost
neutral in terms of the budget summary.   Details of this funding is set out in
Appendix 6. 
8.7 ACTION: The Committee is asked to note the receipt of £5.119 million of
additional resources, with this funding being reflected within Education &
Page 20 of 132

Page 21

Children’s Services, Communities and Health & Social Care as additional
grant income.  The current projected outturn assumes that all these additional
resources will be fully expended in 2022/23 or will be carried forward under
the terms of the grant award. 
9. 2022/23 VIREMENTS 
Contribution to/from Capital Fund 
9.1 In line with the strategy for managing the Council’s Capital Programme over
the medium term, it is recommended that the eventual over or under spend on
Capital Financing Costs and Interest on Revenue Balances be transferred
from or to the Capital Fund.   
9.2 The latest monitoring indicates a reduction in the projected outturn for capital
financing costs (loan charges) of £947,000 based on the latest treasury
management activity and an increase of £1.077 million in income from
interest on revenue balances.  This will result in an increased Contribution to
the Capital Fund of £2.024 million in the current financial year 
9.3 ACTION: The Committee is requested to approve the virement of £947,000
from the Capital Financing Costs (Loan Charges) Budget and £1.077 million
to Interest on Revenue Balances with a corresponding increase in the
projected Contribution from the Capital Fund.  These adjustments have been
reflected in Appendix 1 (Column 5) to this report. 
Service Virements
9.4 To ensure that the 2022/23 Management Revenue Budget continues to reflect
current Service needs and operational requirements the following virements
between budgets is required. 
• Communities to Chief Executive’s Service - £1.817 million to reflect
operational changes in the support of the Council’s approved
Transformation and Change Strategy. 
9.5 ACTION: The Committee is asked to approve the adjustment to Service
Revenue Budgets listed in 9.4 above. These adjustments are reflected in
Appendix 1 (Column 5) to this report. 
10. 2022/23 MOVEMENTS IN RESERVES 
Transformation Projects 
10.1 Due to a rephasing of expenditure there is a requirement to draw down
funding to support several approved projects as follows: 
• Modernising Performance - £60,000 (Chief Executive’s Service)
• Open Data - £124,000 (Corporate & Democratic Services (CDS))
• Working Smarter - £78,000 (CDS)
Page 21 of 132

Page 22

10.2 ACTION: The Committee is asked to approve the transfer of £262,000 to
Corporate & Democratic Services from the earmarked Reserve for Workforce
Management (including Transformation).  This adjustment is reflected in
Appendix 1 (Column 6) to the report and has no impact on the level of
unearmarked Reserves. 
Earmarked Reserves 
10.3 The Reserves Strategy approved by Council on 23 February 2022 (Report
No. 22/35 refers) and Unaudited 2021/22 Accounts approved by the Audit and
Risk Committee on 28 June 2022 (Report No. 22/157 refers) include
recommendations on earmarked Reserves. 
10.4 Specifically, approval is sought to draw down the following earmarked
Reserves for the purposes originally specified – 
• Financial Insecurity - £638,000
• Ventilation Measures - £437,000
• Contribution to the Insurance Fund - £1 million 
10.5 ACTION: The Council is asked to approve the contributions from earmarked
Reserves set out in 10.4 above.  These adjustments are reflected in
Appendix 1 (Column 6) to this report and have no impact on the level of
unearmarked Reserves. 
Covid-19 Earmarked Reserve 
10.6 Children, Families & Young People Services continue to experience a
significant increase in the number of referrals for support because of Covid-
19.  Approval is sought to draw down additional funding of £188,000 from the
Covid-19 earmarked Reserve to maintain additional capacity to meet this
growing need. 
10.7 ACTION: The Committee is asked to approve the transfer of £188,000 to
Education & Children’s Services from the Covid-19 earmarked Reserve.  This
adjustment is reflected in Appendix 1 (Column 6) to this report. 
Affordable Housing
10.8 On 2 June 2021, the Strategic Policy & Resources Committee approved
funding for a 2 year period to progress a Missing Shares scheme from the
Council’s Affordable Housing earmarked Reserve (Report No 21/70 refers).
This work commenced in September 2021 and approval is now sought to
draw down the required funding for 2022/23. 
10.9 ACTION: The Committee is asked to approve the transfer of £28,000 to
Communities from the Council’s Affordable Housing earmarked Reserve to
take forward the Missing Shares scheme.  This adjustment is reflected in
Appendix 1 (Column 6) to this report. 
Page 22 of 132

Page 23

11. CONCLUSION 
11.1. Currently, a projected over spend of £1.949 million has been identified.  This
position will be kept under review and mitigating action may be required to
support the delivery of the 2022/23 Final Revenue Budget. 
11.2. The Council’s financial position remains challenging and regular updates will
be provided to the Council and the Finance & Resources Committee as the
position develops. 
APPROVED 
Name  Designation Date
Stewart Mackenzie  Head of Finance 29 August 2022
Karen Donaldson  Chief Operating Officer 29 August 2022 
Page 23 of 132

Page 24

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2018 – 2022 lays out five outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible, and informed citizens;
(iii) Promoting a prosperous, inclusive, and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
1.2 This report relates to all these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report. 
Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report.
Page 24 of 132

Page 25

Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3 Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council must discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Executive Leadership Team have been consulted in the preparation of
this report. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
Page 25 of 132

Page 26

information) were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
• Appendix 1 – 2022/23 Management Budget
• Appendix 2 – General Fund 2022/23 Projected Outturn – Service
Analysis
• Appendix 3 – Perth & Kinross Integration Joint Board
• Appendix 4 – Housing Revenue Account 2022/23 Projected Outturn
• Appendix 5 – Revenue Grants
• Appendix 6 – Other Grant Funding 
Page 26 of 132

Page 27

Appendix 1
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
2022/23 Previously Issues Movements Virements Movements 2022/23 Projected Variance Variance
Council Approved Arising in in Revised Outturn to to
Approved Adjustments From Funding Reserves Mgt Revised Revised
Budget (Net) 2021/22 Budget Mgt Mgt
Accounts Budget Budget
SERVICE £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 %
Education & Children's Services 212,418 5,153 3,315 1,809 188 222,883 222,883 0 0.00%
Communities 71,165 1,876 4,147 (1,817) 28 75,399 75,647 248 0.33%
Corporate & Democratic Services 35,228 2,334 1,610 1,277 40,449 41,789 1,340 3.31%
Chief Executives 1,174 1,817 60 3,051 3,031 (20) (0.7%)
Sub - Total: Service Budgets 319,985 9,363 9,072 1,809 0 1,553 341,782 343,350 1,568 0.46%
Corporate Budgets
Health & Social Care 74,866 6,730 158 81,754 81,398 (356) (0.4%)
Contribution to Valuation Joint Board 1,309 1,309 1,309 0 0.00%
Capital Financing Costs 13,866 (947) 12,919 12,919 0 0.00%
Interest on Revenue Balances (200) (1,077) (1,277) (1,277) 0 0.00%
Net Contribution to/(from) Capital Fund 1,530 2,024 3,554 3,554 0 0.00%
Contribution to/(from) Insurance Fund 200 1,000 1,200 1,200 0 0.00%
Trading Operations Surplus (550) (550) (550) 0 0.00%
Support Service External Income (2,153) (2,153) (2,153) 0 0.00%
Tayside Pension Fund 1,565 1,565 1,565 0 0.00%
Apprenticeship Levy 818 818 818 0 0.00%
Council Tax Reduction Scheme 6,200 6,200 7,000 800 12.90%
Discretionary Relief 150 150 150 0 0.00%
Net Expenditure (General Fund) 417,586 16,093 9,230 1,809 0 2,553 447,271 449,283 2,012 0.45%
Financed By:
Revenue Support Grant (234,656) (16,454) (1,995) (253,105) (253,105) 0 0.00%
Ring Fenced Grant (17,194) (677) (17,871) (17,871) 0 0.00%
Non Domestic Rate Income (46,141) (46,141) (46,141) 0 0.00%
Council Tax Income (98,941) 6,035 (92,906) (92,906) 0 0.00%
Capital Grant (1,600) (120) (1,720) (1,720) 0 0.00%
Total Financing (398,532) (10,539) 0 (2,672) 0 0 (411,743) (411,743) 0 0.00%
Financed from/(returned to) Reserves 19,054 5,554 9,230 (863) 0 2,553 35,528 37,540 2,012
PERTH
&
KINROSS
COUNCIL GENERAL FUND
2022/23 REVENUE
BUDGET - SUMMARY
5
Page 27 of 132

Page 28

Page 28 of 132

Page 29

APPENDIX 2
PERTH & KINROSS COUNCIL - GENERAL FUND 2022/23 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 June 2022)
Variance Variance
£'000 £'000
Education & Children's Services
Total 0
DEVOLVED SCHOOL MANAGEMENT SCHEME (DSM)
There are 66 primary schools, 7 secondary schools, 4 all through schools, 46 nurseries and early learning
centres and 1 special school within the Council's DSM scheme.  Each school has an individual budget,
primarily based on pupil numbers.  Headteachers are responsible for the annual budgets devolved to them in
April each year. The total DSM budget for 2022/23 is £113.876 million including carry forwards. 
Within the scheme there is a facility allowing for DSM balances, whether surplus or deficit, to be brought
forward from the previous financial year. In addition to the resources devolved, balances may also be available
to headteachers of schools that have a carry forward. In 2021/22, £1.191 million of DSM balances were
brought forward.
(449) Staff Costs
Additional slippage due to staff turnover
449 There is currently a projected net under spend of £449,000 based on current spending plans from schools for
the current academic year that runs to June 2023.  The maximum carry forward under the DSM scheme is
2.5%,  the current projection is 0.4%.
Pupil Equity Fund
(300) The majority of schools within Perth & Kinross Council have been allocated a share of £1.874 million of Pupil
Equity Funding from the Scottish Government as a ring fenced grant.  Schools are being instructed to use this
year’s PEF Grant by 31 March 2023 as per the revised Scottish Government guidance. At this time £300,000
is projected to be carried forward into 2023/24 for teacher and support staff costs to the end of the current
academic year.
300 Projected carry forward of Pupil Equity Funding.
NON DEVOLVED
Education Services
Nursery Sector
(184) Additional slippage due to turnover of staff.
(31) Savings from non-domestic rates as early learning centres are exempt from the charge.
Secondary Sector
(181) Projected under spend on investment in learning unitary charge due to  an insurance rebate.
Special Sector
(130) Projected under spend on home to school transport after allowing for non-recurring increase of £250,000.
(211) There is a projected under spend on the  budget for young people with additional support needs (ASN) who
are educated out with the Council's mainstream school provision.
Services for Children, Young People & Families
188 Projected costs of additional social work capacity to meet increasing need.
(188) Contribution from Covid-19 earmarked Reserve
86 Projected over spend on legal fees and translation / interpreter services
734 The budget for young people with complex behavioural issues, which includes a number of pupils placed
within residential schools, is projected to overspend due to additional demand.
286 A projected over spend on Kinship Care (£555,000) due to demand partially offset by a projected under spend
in Foster Care (£229,000).
309 There is a projected over spend in relation to supporting care experienced young people (continuing care,
supported accommodation,) due to increasing demand.
85 There is a projected over spend on self directed support (children & disability team - respite provision) due to
the level of demand and an increase to the hourly rate paid to clients.
(124) Additional grant funding for Unaccompanied Asylum Seeking Children (£86,000); Wellbank Rental Income
(£23,000) and Alcohol & Drug Partnership (£15,000)
Business and Resources Services
(44) Additional slippage due to turnover of staff.
(27) Projected underspend due to Area Office recharge no longer required.
SERVICE Summary of Service Variances
5
Page 29 of 132

Page 30

APPENDIX 2
PERTH & KINROSS COUNCIL - GENERAL FUND 2022/23 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 June 2022)
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
Catering Services
(76) Additional staff slippage.
(600) Projected under spend (£600,000) within the Early Learning & Childcare 1140 grant, for nursery meals.
(255) Projected under spend of school meals due to uptake (£255,000) partially offset below by reduced income.
363 Projected shortfall in income from breakfast clubs (£120,000) and school meals (£243,000).
Communities
Total 248
BUSINESS AND RESOURCES
Public Transport Unit / Corporate Property Asset Management
40 Perth Bus Station - increased costs
(80) Corporate Asset Management - accelerated savings
355 Car Park Trading Account - projected reduction in income and increased provision for bad debts
(355) Drawdown from Car Park Trading Account earmarked Reserve
ENVIRONMENTAL AND CONSUMER SERVICES
Roads
(150) Projected additional income from statutory road network works
Regulation
25 Projected shortfall in Corporate Health and Safety income
Operations
270 Projected shortfall in commercial waste income
(150) Projected additional income from sale of recyclates due to favourable market prices
400 Projected additional cost of fuel across Operations due to increase in price
Fleet Management
(280) Saving on loan charges due to slippage on planned vehicle replacement programme
PLANNING AND DEVELOPMENT
98 Perth Harbour - projected increase in operating costs /shortfall in income
HOUSING
35 Greyfriars - projected increased in void rent loss and provision for bad debts
10 Greyfriars - projected increase in energy costs
30 Cost of Local House Condition Survey to inform the Local Housing Strategy
Page 30 of 132

Page 31

APPENDIX 2
PERTH & KINROSS COUNCIL - GENERAL FUND 2022/23 PROJECTED OUTTURN  - SERVICE ANALYSIS
(Based on Expenditure to 30 June 2022)
Variance Variance
£'000 £'000SERVICE Summary of Service Variances
Corporate & Democratic Services
Total 1,340
Legal & Governance Services
(130) Projected additional income from licensing and recharges
(94) Rephasing of expenditure relating to Council approved projects (Kinross Area Committee & Events Support)
36 Projected over spend in relation to elected members
38 Net projected overspend across function (including non-achievement of slippage target)
Human Resources
(113) Additional projected income from salary sacrifice scheme and other recharges
(26) Additional staff slippage
(9) Net projected under spend on other budgets
Information Technology and Revenues & Benefits
(20) Miscellaneous other projected net under spends.
Property
959 Projected over spend on energy costs due to inflationary pressures.
740 Projected over spend on maintenance relating to compliance remedial works.
(41) Miscellaneous other projected net under spends.
Chief Executive's Service
Total (20) Core Costs
(20) Staff slippage
TOTAL 1,568
Page 31 of 132

Page 32

Page 32 of 132

Page 33

APPENDIX 3
Perth and Kinross Integration Joint Board (IJB)
Projected outturn based on Revenue Monitoring to 30 June 2022
£'000 £'000 £'000
DEVOLVED FUNCTIONS
Older People Services (1,748) 3,033 1,285
Adult Services 548 (488) 60
Other Community Services (130) 0 (130)
Management/Commissioned/Other 1,203 396 1,599
Undelivered Savings 923 740 1,663
Planned use of Covid-19 Reserves (1,992) (3,681) (5,673)
Projected Outturn - Social Care (Devolved) (1,196) 0 (1,196)
Projected Outturn - Social Care (Non-Devolved) (356) 0 (356)
Projected Out-turn Over / (Under) Spend
5
Page 33 of 132

Page 34

Page 34 of 132

Page 35

APPENDIX 4
PERTH & KINROSS COUNCIL - HOUSING REVENUE ACCOUNT 2022/23 PROJECTED OUTTURN
(Based on expenditure to 30 June 2022)
£'000
273 Housing Repairs
A projected over spend within stores (£216,000) as a result of the increased cost of materials, diesel (£46,000) and gas & electricity
(£37,000).  These projected over spends are partially offset by staff slippage (£26,000).
(50) Improvements
Projected under spend on staff costs.
10 Letham, North & South
Projected over spend on staff costs.
104 Perth City and Specialist
Projected net over spends on electricity and gas costs within Sheltered Housing (£75,000) and staff costs (£29,000).
12 Housing Management
Projected over spend on staff costs, including the Apprenticeship Levy.
(186) Administration
Projected under spend on bad debt provision (£350,000), lower corporate recharges compared to budget (£103,000), reduced
recharges from the General Fund (£93,000) and under spends in non-staff budgets (£9,000).  These are partially offset by projected
over spends on void rent loss based on similar trend to last year (£262,000), void rates / Council Tax / utilities (£94,000) and recharges
(£13,000). 
(7) Income
Projected additional income from Interest on Revenue Balances (£25,000). 
(156) Capital Financed from Current Revenue
As a result of the projected net over spends highlighted above, this is the reduction in the amount available to invest in the HRA capital
programme from the Revenue Budget.
950 Specific Covid-19 Related Expenditure
Projected expenditure funded by earmarked Reserves:-
- Estate Based Initiatives - £100,000
- Project management capacity to take forward Multi-Storey Works - £62,000
- Electrical Inspection Condition Reports (EICR) and capacity - £398,000                         
- Repairs Backlog from 2021/22 - £150,000
- Tenancy Sustainment Fund - additional funding to support tenants in hardship - £50,000
- Service & Compliance capacity - £95,000
- Capacity to take forward land grabbing issues - £35,000
- Safer Communities Co-ordination - £38,000
- Support for Gypsy Travellers - £22,000
(950) Contribution from HRA Earmarked Reserve for Covid-19
0
Summary of Service Variances
5
Page 35 of 132

Page 36

Page 36 of 132

Page 37

APPENDIX 5
Revenue Grants
Education & Children’s Services
Scottish Government - Education Recovery £1,152,000
Scottish Government - Pupil Equity Fund £419,000
Scottish Government - Fair Employability & Skills £379,000
Scottish Government - Free School Meals £180,000
Non RSG Carry Forward £541,000
Other Grants (x4) £229,000
Communities
Scottish Government -Regeneration Capital Grant Fund - Place Based Investment
Programme £1,119,000
Scottish Government - Rural Tourism Infrastructure Fund £586,000
Scottish Government - Fair Employability & Skills £1,017,000
The Edrington Trust - Creative Exchange Hub £159,000
UK Government - Levelling Up Fund £94,000
Scottish Government - Young Persons Guarantee £299,000
Other Grants (x16) £873,000
Corporate & Democratic Services
Scottish Government - Business Support & Low Income £1,075,000
Scottish Government - Financial Insecurity £141,000
Scottish Government - Scottish Child Bridging Payment £302,000
Other Grants (x2) £92,000
Health & Social Care
Mental Health Officers - Capacity & Training £83,000
Other Grants (x2) £75,000
TOTAL £8,815,000
5
Page 37 of 132

Page 38

Page 38 of 132

Page 39

APPENDIX 6
Other Grant Funding
Education & Children’s Services
Scottish Government – Community Mental Health & Wellbeing £418,000
Scottish Government – Justice Social Work Service - Support Pandemic Recovery Work £324,491
Scottish Government – Caledonian Men’s Programme £155,040
Scottish Government – Scottish Milk and Healthy Snack Scheme £355,000
Scottish Government – Education Maintenance Allowance 2022/23 £307,998
Scottish Government – Scottish Attainment Challenge – Care Experienced Children &
Young People £155,232
Scottish Government – Strategic Equity Funding 2022/23 £251,412
European Social Fund – Westbank Project (Year 4) £120,991
Gannochy Trust – Universal Youth Service Partnership £153,402
Bord na Gaidhlig Immersion Course £69,680
Communities
Scottish Government – No One Left Behind 22/23 £971,711
Scottish Government – Public Electric Vehicle Charging Strategy & Infrastructure £60,000
Scottish Government – Local Air Quality Management £99,868
Scottish Government – Local Air Quality Action Plan £166,830
Scottish Government – Ukraine Warm Scottish Welcome £159,939
Visit Scotland – Destination & Sector Marketing Fund Top Up £70,000
UK Government – Homes for Ukraine £1,208,200
Health & Social Care
Scottish Government – Support Gathering Supporting Information on behalf of Clients
applying for Adult Disability Payments £71,000
TOTAL £5,118,794
5
Page 39 of 132

Page 40

Page 40 of 132

Page 41

PERTH & KINROSS COUNCIL 
Finance & Resources Committee 
7 September 2022 
COMPOSITE CAPITAL BUDGET 2022/28 & HOUSING INVESTMENT
PROGRAMME 2022/27 – MONITORING REPORT No.1 
Report by Head of Finance
(Report 22/209) 
1. PURPOSE 
1.1 This report provides a summary position to date for the 6-year Composite
Capital Budget for 2022/23 to 2027/28 and the 5-year Housing Investment
Programme 2022/23 to 2026/27 and seeks approval for adjustments to the
programmes. 
2. BACKGROUND 
2.1 The Strategic Policy & Resources Committee approved an updated six-year
gross Composite Capital Budget for 2022/23 to 2027/28 totalling
£646,040,000 and a five-year gross Housing Investment Programme for
2022/23 to 2027/28 totalling £83,856,000 at its meeting on 20 April 2022
(report 22/88 refers). 
2.2 This report advises on the impact of the final outturn expenditure in 2021/22
on the programmes; expenditure to 31 July 2022, and the latest estimate of
the projected outturn for each of the years to 2027/28 for the Composite
Programme and to 2026/27 for the Housing Investment Programme. 
3. RECOMMENDATIONS 
3.1 It is recommended that the Committee: 
(i) notes the contents of this report.
(ii) approves the proposed adjustments to the six-year Composite Capital
Budget 2022/23 to 2027/28 set out in Sections 5 and 6 of this report
and summarised in Appendices I and II.
(iii) notes the implications for the Council’s approved Capital funding
strategy as set out in section 5.2.8 and 5.2.9 of the report.
(iv) approves the proposed adjustments to the Housing Investment
Programme Budget 2022/23 to 2026/27 set out in Section 6 of this
report and summarised in Appendix IV. 
4. COMPOSITE CAPITAL PROGRAMME – GROSS CAPITAL RESOURCES 
4.1 The current estimated total gross capital resources (which includes
movements in Capital Receipts, Capital Grants, Contributions and borrowing)
available over the six years 2022/23 to 2027/28 amount to £683,102,000.
Movements from the revised Composite Capital Budget approved on 20 April
6
Page 41 of 132

Page 42

2022 are summarised in the table below, and the constituent elements for
each year are shown in Appendix I. 
Total Gross Composite Capital Resources 
Approved 
20 April 2022
Current
Estimate
Movement 
£’000 £’000 £’000
2022/23 162,452 176,488 14,036
2023/24 187,177 176,322 (10,855)
2024/25 137,954 148,027 10,073
2025/26 61,769 81,489 19,720
2026/27 52,830 56,639 3,809
2027/28 43,858 44,137 279
Total 646,040 683,102 37,062 
4.2 The report on 20 April 2022 did not include estimates for amounts carried
forward from 2021/22. To determine the carry-forward adjustment required for
each project in 2022/23, the 2021/22 actual position (subject to audit) has
been compared to the projected outturn. These adjustments, are, however,
cost neutral over the 2 financial years as they simply reflect changes in the
timing of expenditure or the application of income. It is, therefore, proposed to
adjust the budget in 2022/23 by the carry forward amounts detailed within
Appendix II. 
4.3 The overall movement in the total Gross Resources for the 6 years 2022/23 to
2027/28 shown at Section 4.1 above can be summarised as follows: 
£’000
Increase in General Fund Property, Commercial Property and
Ring-Fenced Receipts (Section 4.4)
107
Increase in Capital Grants (Section 4.5) 802
Increase in Third Party, Revenue and Developer Contributions
(Section 4.6) 
1,356
Reduction in Receipts c/f to future years (Section 4.4) 213
Increase in new Borrowing Requirement (Section 4.8) 34,584
Increase in Gross Capital Resources (Section 4.1) 37,062 
4.4 Estimated receipts have increased by £107,000, however £103,000 of this
relates to timing differences between 2021/22 and 2022/23, with a £4,000
increase in Ring-Fenced receipts relating to Waste Operations in 2022/23
(Section 5.3.12). Similarly, the reduction in Receipts Carried-Forward to future
years includes a £68,000 adjustment from last year together with £145,000
relating to the proposed increased expenditure on the Commercial Investment
Programme (Section 5.3.11). 
4.5 There is an adjustment of £318,000 in capital grants carried forward from last
year. In addition, the Scottish Government has made additional grant
allocations in 2022/23 for the programmes listed below. These have been
reflected in the proposed expenditure budgets for these programmes, and are
included in Appendix II, as follows: 
• £308,000 additional allocation for Cycling Walking & Safer Streets
• £176,000 Nature Restoration Fund
Page 42 of 132

Page 43

4.6 Third Party Contributions have increased by £1,356,000, of which £221,000
relates to the adjustments to the programme and amounts carried forward
from last year, and £1,135,000 are new Contributions to the programme in
2022/23. These relate to £75,000 from TACTRAN for the Cycling Walking &
Safer Streets programme (Section 5.3.2), £945,000 from the Forestry
Commission for Timber Routes (Section 5.3.4) and £115,000 on the
Commercial Property Investment Programme (Section 5.3.11). All movements
in Developer Contributions and Revenue Contributions relate to carry forward
adjustments between 2021/22 and 2022/23. 
4.7 The projected borrowing requirement in 2022/23, which is effectively the
balancing item for resources, is £136,959,000. This is £11,315,000 higher
than the borrowing requirement approved on 20 April 2022. 
4.8 The total borrowing requirement in the subsequent years 2023/24 to 2027/28
has increased by £23,269,000 to £399,628,000, resulting in an overall
increase of £34,584,000 across the whole 6-year programme. After allowing
for the amount brought forward from 2021/22 of £1,384,000, this leaves an
increase of £33,200,000 relating to new borrowing. The movement in
borrowing is summarised as follows: 
2022/23 2023/24 2024/25 Later
Years
Total 
£’000 £’000 £’000 £’000 £’000
Increased Borrowing Requirement
brought forward from 2021/22
(Appendix II)
1,384 0 0 0 1,384
Increase in Borrowing due to
inflationary pressures (Section 5.1)
16,597 5,045 11,558 0 33,200
Movements arising from re-
phasing of other expenditure and
receipts (Appendix II)
(6,666) (15,657) (1,485) 23,808 0
Increase/(Decrease) in
Borrowing Requirement
11,315 (10,612) 10,073 23,808 34,584 
4.9 The chart below shows the Capital Resources required to fund the 2022/23
Composite Capital Programme following the proposed budget adjustments
detailed in this report. 
78.0%
18.2%
0.9%
1.9%
1.0%
3.8%
Projected Capital Resources 2022/23
(August 2022)
Borrowing (£136.959M)
Grants (£31.995M)
Developer Contributions (£1.549M)
Third Party & Revenue Contributions (£3.345M)
Receipts (£1.827M)
£Million
Page 43 of 132

Page 44

5. COMPOSITE CAPITAL PROGRAMME – EXPENDITURE 
5.1 Total Expenditure and Proposed Budget Adjustments to the Current
Programme 
5.1.1 Total expenditure (net of grants and contributions) to 31 July 2022 on the
Composite Capital Programme amounts to £20,846,000, which is detailed in
Appendix II and summarised as follows: 
Net Expenditure
to 31 July 2022 
£’000
Education & Children’s Services  4,016
Communities 15,047
Health and Social Care    43
Corporate & Democratic Services 1,740
Total 20,846 
5.1.2 A comprehensive monitoring exercise has been carried out, which is detailed
in Appendix II. The most significant features are discussed below under the
respective service headings . 
5.1.3 In setting the 6-year Capital Budget in February 2022 (report 22/36 refers),
the Council approved a Capital funding strategy based upon a £450,000
annual increase in the Council’s debt servicing or “loan charges” budget each
and every year. This funding strategy provided for the estimated cost of
delivering the Capital programme at that time, together with some further
capacity for future investment needs. There were no specific commitments
against this capacity but, as examples, it was recognised that the Council
would likely require future Capital investment to support the delivery of the
Climate Change Strategy and Economic Wellbeing Plan amongst others. 
5.14 Since the Capital Budget was set, the cost uncertainty caused by construction
inflation and supply chain difficulties has been exacerbated by the impact of
the conflict in Ukraine on global energy prices and the consequential impact
on the supply and cost of construction materials. As a consequence project
costs have escalated beyond anything reasonably anticipated back in
February. 
5.2 Communities 
5.2.1 The Executive Director (Communities) has reviewed the programme for their
Service and proposes various budget adjustments, which are described
below. The two most significant are CTLR and Perth City Hall. 
5.2.2 The estimated cost of delivering these has been revised upwards as follows: 
• Cross Tay Link Road (CTLR) - up to £32,500,000 
• Perth City Hall - £700,000 
Both projects are on site with considerable expenditure already incurred in
their delivery to date. 
Page 44 of 132

Page 45

5.2.2 With regard to the Cross Tay Link Road (CTLR) project, Appendix III to the
report provides the committee with background to the development of the
project; its role in the delivery of the approved Local Development Plan 2 and
the factors giving rise to a potential increase in forecast cost of up to £32.5
million. 
5.2.3 The contractor has provided a range of forecast cost estimates for the
construction element of the contract. Separately, the Council has engaged
Turner & Townsend to review the adequacy of the contingency provision
through an assessment of potential risks to the project using industry standard
methodology. The table below summarises the main elements of the forecast
increase in cost:   
Approved 
Budget
£ million
Revised
Estimate
£ million
Variance 
£ million
Construction 94.5 108.9 to
111.7
14.4 to 17.2
Risk Assessment
(contingency)
2.4 16.9  14.5
Land and compensation 5.6 5.6 0
Professional Fees 6.8 6.6 (0.2)
Licenses and Public Utilities 3.6 4.0 0.4
Insurance 2.0 2.2 0.2
Consultancy, Surveys &
Investigations
1.9 1.9 0
Engineering Administration 1.2 1.6 0.4    
Total 118 147.7 to
150.5
29.7 to 32.5
Transport Scotland Funding (40) (40) 0    
Revised Net Cost 78 107.7 to
110.5
29.7 to 32.5 
5.2.4 The range of potential cost estimates for the CTLR reflect the scale and
complexity of the project which is the largest civil engineering works ever
undertaken by the Council. The revised forecast for construction costs
includes £5 million of cost mitigation measures achieved though value
engineering in relation to the design. The risk assessment, in particular, has
been revised to reflect the impact of a range of scenarios as outlined in
Appendix III and the estimated costs of contingency works are, by definition,
uncertain. Given the uncertainties and challenges being experienced across a
range of Capital projects, it is , therefore, proposed that the committee make
provision for the current  “worst-case” scenario with the potential that the
eventual cost of the project may not be as high as this forecast. 
5.2.5 There are a number of significant legal, financial and reputational risks in
relation to the CTLR should the Council not progress with the project. These
are detailed in Appendix III and include significant risk around the strategic
Page 45 of 132

Page 46

housing land allocations set out within the Local Development Plan 2 which
cannot be delivered without the CTLR 
5.2.6 In terms of the financial risks, these are significant and are outlined below: 
• The Council has incurred a total of  £23.5 million to 31 July 2022 on the
delivery of the project since its inception, including expenditure in prior
financial years.
• In the current financial year, the Council has spent £6.7 million on the
delivery of the project up to the end of July with a further £3.8m million
forecast to be spent in August, bringing total expenditure in year on the
project to £10.5 million.  Should the project not be progressed, any
expenditure in year would require to be accounted for as Revenue
pressure rather than Capital expenditure as there is no resultant
Capital asset. As this expenditure has not been budgeted for, it would
add to  the  Council’s existing structural deficit.
• The Council would forfeit the £40 million of Transport Scotland funding
for the CTLR and be required to pay back the £5 million received to
date as the conditions of the grant funding will  not have been met.
• In addition, the cost of reinstating the site  would require to be met
together with any resultant costs from the early termination of contracts
or through any successful claims against the Council. 
5.2.7 The Perth City Hall project is on track to open in early 2024 and the majority of
the works are contained within the budget. However, unanticipated additional
works surrounding archaeology and repairs to the building fabric mean that
the contingency provision is now fully committed. It is anticipated that further
expenditure will be required on internal repairs and some aspects of the
exhibition fit-out. It is proposed that a further £700,000 is allocated in 2023/24
to replenish the contingency fund, with Culture Perth and Kinross committing
to fundraise a further £300,000 to support the project’s exhibition and display
requirements. 
5.2.8 In respect of these two key committed  projects, based on the latest
assessment under the approved funding Strategy which was approved in
February 2022, there is approximately £70 million of forecast uncommitted
capacity available to support the delivery of the approved Capital Budget . The
Committee is therefore requested to approve the application of £33,200,000 of
that uncommitted capacity to support the delivery of these projects as
reflected in Appendix II to the report.  
5.2.9 Subject to the approval of these adjustments, the remaining forecast capacity
available to  absorb  the anticipated  construction inflation and increasing
costs in relation to other approved projects and programmes  or indeed, for
any for new investment will be approximately £37 million. 
5.2.10 Given the challenging financial position, officers will continue to monitor and
review the capital programme in line with the Financial Strategy and
Investment Blueprint . 
Page 46 of 132

Page 47

In addition; 
5.2.11 Within Traffic & Road Safety, further funding has been allocated to Cycling
Walking and Safer Streets (CWSS) by the Scottish Government and
TACTRAN of £308,000 and £75,000 respectively. Resources have been
prioritised towards these grant funded schemes and this has impacted upon
the staff resources available for other projects within this programme with
proposed adjustments as follows: 
- Road Safety Initiatives – £298,000 from the current year with £237,000
rephased to next year and £61,000 in 2024/25;
- Pedestrian Crossings - £175,000 from the current year to 2025/26; and
-  Schools Road Safety Measures - £106,000 from the current year to
next year. 
5.2.12 Also, within Traffic & Road Safety it is proposed to rephase £177,000 for Car
Parking Investment from the current year to next year due to unexpected
delays surrounding drainage issues and to minimise disruption to parking over
the festive period.  In addition, Car Parking Investment at Pitlochry is currently
being reviewed whilst a suitable site is identified and so it is proposed that the
budget of £150,000 is moved to next year.   
5.2.13 Within Asset Management – Roads & Lighting, it is proposed to increase the
budget for Structural Maintenance by a net £1,358,000. This follows allocation
of third-party funding totalling £945,000, combined with a proposed
acceleration of £433,000 from 2023/24 to the current year. These budget
adjustments in the current year are offset by a proposed transfer of £20,000
from the Welton Road Retaining Wall underspend within Structural
Maintenance to the Bridge Refurbishment Programme.  Also, within Roads &
Lighting, due to staff resources being focused on grant funded projects, it is
proposed that £100,000 for Investment in Local Footpaths is moved to
2024/25 from the current year. 
5.2.14 Within Asset Management – Bridges, works within the Bridge Refurbishment
Programme are currently at the planning stage and as such, anticipated
spend in the current year is less than previously budgeted. It is therefore
proposed that £1,080,000 is rephased with £125,000 next year and £955,000
in 2024/25. In addition, there is expected to be an £80,000 underspend on
Glendevon Bridge and it is proposed that this is combined with the
underspend of £20,000 from section 5.3.4 above, and that the £100,000 total
is allocated to the Bridge Refurbishment Programme in 2026/27.  Due to
current engineering staff resource constraints, reduced works on Perth
Queens Bridge and Culteuchar Culvert are expected to take place in the
current year and therefore it is proposed that their budgets of £70,000 and
£278,000 respectively, be moved from the current year to next year. 
5.2.15 Within the Perth & Kinross Place-making programme it is proposed that the
budgets for Perth City Centre Golden Route, Green Network Routes, Tay
Street, Mill Street and South Street be consolidated into one budget heading
for Perth, Place, People where funding can be drawn down towards various
projects as they commence. 
Page 47 of 132

Page 48

5.2.16 Within Other Planning Projects, following a reduction of £120,000 funding
from the Department of Digital, Culture, Media & Sport, the budget for Local
Full Fibre Network has been adjusted accordingly. The Council has been
allocated £176,000 in 2022/23 from the Nature Restoration Fund by the
Scottish Government, and this has been included in the budget. 
5.2.17 The community in Auchterarder have raised £140,000 towards Auchterarder
Public Park, and the budget for the works has been increased to reflect the
additional funding towards this project.Within the Commercial Property
Investment Programme, it is proposed that the budget of £1,398,000 for the
Eco-Hub Manufacturing Facility is removed from the current programme of
works, and that industrial units be created with a budget of £1,655,000 over
this year and next year. These units are part funded by a £115,000 third party
contribution. These proposed adjustments, together with a £3,000 adjustment
carried forward from last year, result in a net increase in expenditure of
£145,000. 
5.2.18 Within the Prudential Borrowing programme the Street Lighting Renewal for
the current year has been reviewed. As a result of additional works completed
last year it is proposed that the budget for the programme in relation to
column replacements is rephased over the remaining years of the project. In
addition, following the disposal of skips and containers as part of the
replacement programme, it is proposed to increase the budget for new skips
by the £4,000 net proceeds received to date. 
5.2.19 All the above proposed adjustments have been reflected in Appendices I & II. 
5.3 Education and Children’s Services 
5.3.1 The Executive Director (Education & Children’s Services) has reviewed the
programme for their Service and proposes the following budget adjustments. 
5.3.2 Works on the new Riverside Primary School are progressing well and it is
proposed to accelerate £3,008,000 from next year into the current year to
reflect the level of work due for completion this year. 
5.3.3 The following adjustments reflect the movement in the overall programme
following the effects of Covid-19 on the timescales across the projects. 
5.3.4 There have been several small adjustments to various Education & Children’s
Services projects relating to amounts carried forward from 2021/22 which are
included in Appendix II. These mostly relate to projects that have been
completed. 
5.3.5 Within the Investment in the Learning Estate, it is proposed to move
£2,000,000 from the current year, and £5,000,000 from next year, with
£4,000,000 being allocated to 2024/25 and £1,000,000 into each of the
subsequent three years of the programme.  Further details for the use of this
funding will be provided following a review of the programme. 
5.3.6 In line with a proposed opening date of August 2026, the budget for a new
primary school at Bertha Park requires rephasing. It is proposed to transfer
Page 48 of 132

Page 49

£7,500,000 from both 2023/24 and 2024/25 into 2025/26; and to reduce the
current year by £400,000 with a corresponding increase in 2026/27. 
5.3.7 Within the budget for Technology Upgrades, planned works indicate that
£400,000 of the budget will not be utilised in the current year and it is
proposed that this budget be moved to 2023/24. 
5.3.8 The expected payment profile for the extension of Harris Academy has also
been updated, and it is proposed that £1,100,000 of the budget is moved from
2022/23 to 2023/24. In addition, works are continuing on-site upgrading
facilities at Perth Grammar and Perth Academy. Following an update to the
actual value of the current phases, it is proposed that both budgets be
rephased as follows: 
- A reduction at Perth Academy of £1,300,000 in the current year and
£3,000,000 next year with a budget of £2,150,000 being allocated to
both 2025/26 and 2026/27;  
- A reduction at Perth Grammar of £2,000,000 in the current year and
£815,000 next year, with £811,000 allocated to 2024/25, £1,500,000 to
2025/26 and the remainder of £504,000 to 2026/27. 
5.3.9 All of the above proposed adjustments have been reflected in Appendices I &
II.
5.4 Corporate & Democratic Services 
5.4.1 The Chief Operating Officer has reviewed the programme for their Service
and proposes the budget adjustments described below. 
Property Services 
5.4.2 Within Capital Improvement Projects it is proposed that £600,000 is
accelerated from 2027/28 to the current year to fund energy efficiency
measures. 
Information Systems & Technology 
5.4.3 The works within Data & Analytics for the year have been assessed and it is
proposed to rephase £135,000 from the current year to next year in line with
planned activity. 
5.4.4 Within Information Systems and Technology there are separate budgets for
Supporting Digital, Online/Mobile Working and Customer Service Blueprint. As
there are strong links and crossovers between these areas of IT work it is
proposed that the budgets for these areas are consolidated into one budget
under the overarching Supporting Digital programme. This will enable a
streamlined approach to prioritising works and for testing and deploying digital
improvements.  In addition, it is proposed that within the Supporting Digital
programme £477,000 is moved from the current year to next year to reflect
the level of anticipated spend. 
Page 49 of 132

Page 50

5.4.5 The roll out of School Audio Visual Equipment Replacement is progressing
well and it is proposed that the budget is accelerated in the current year with
an increase of £848,000 to be funded from future year budgets within the
programme. 
5.4.6 Following the appointment of the preferred supplier for the Swift Social Work
System Replacement last year, it is proposed to adjust the budget in line with
the terms of the agreed contract. In particular, the licence costs are due in
2023/24 when the system goes lives, with only staff costs for the ongoing
development and implementation being incurred in the current year. It is also
proposed to move the unallocated budget of £292,000 to 2024/25 to allow for
further development works to be undertaken post-implementation. The
proposed budget adjustments have been included in Appendix II. 
5.4.7 All the above proposed adjustments, together with other small movements,
have been reflected in Appendix II. 
5.5 Health & Social Care 
5.5.1 The Developing Supported Tenancies project is a contribution towards works
within the Housing Revenue Account. It has been confirmed that the budget of
£229,000 will not be drawn down in the current year and it is proposed that
the budget is moved to next year will options continue to be evaluated. 
5.5.2 The above proposed adjustment has been reflected in Appendix II. 
6. HOUSING INVESTMENT PROGRAMME 
Final Outturn 2021-22 
6.1 The final position for 2021/22 on the Housing Investment Programme (subject
to audit) was as follows: 
2021/22
Budget 
Actual to 31
March 2022
Variance to
Budget 
£’000 £’000 £000
Total Net Expenditure 12,018 11,856 (162)
Total Receipts & CFCR (2,259) (2,328) (69)
Borrowing Requirement 9,759 9,528 (231) 
6.2 In order to determine the carry-forward adjustments required for each project
in 2022/23, the 2021/22 actual outturns have been compared to the previous
projections. The difference between the actuals and previous projections are
then adjusted against the 2022/23 budgets, which are shown in Appendix IV.
These adjustments are neutral over the 2 years and has resulted in a
movement of £231,000 of borrowing from 2021/22 to 2022/23.   
Current Programme: 2022/23 to 2026/27 
6.3 The current estimated expenditure, net of contributions, for the Housing
Investment Programme over the 5 years 2022/23 to 2026/27 amounts to
Page 50 of 132

Page 51

£84,018,000. Movements from the previous estimates approved by the
Strategic Policy & Resources Committee on 20 April 2022 are summarised in
the table below and detailed in Appendix IV. The overall increase of £162,000
represents the amount of expenditure carried forward from last year. 
Approved 
20 April 2021
Current
Estimate
Movement 
£’000 £’000 £’000
2022/23 17,963 18,131 168
2023/24 15,983          17,022 1,039
2024/25 13,871 13,867 (4)
2025/26 19,995 18,954 (1,041)
2026/27 16,044 16,044  0
Total 83,856 84,018 162 
6.4 Total Expenditure to 31 July 2022 (Housing Investment Programme) 
Net expenditure for 2022/23 to 31 July 2022 amounts to £3,186,000 and
receipts amount to £4,000. This therefore means that the borrowing
requirement for the year to date is £3,182,000. 
6.5 After making adjustments relating to small carry-forward amounts from last
year, the Executive Director (Communities) has reviewed the Housing
Investment Programme and proposes the budget adjustments outlined below
and which are included in Appendix IV. 
6.6 It is proposed to transfer a net total of £1,746,000 from the New Build Future
Development budget in 2022/23 for the scheme at Lynedoch Road, Methven
in 2022/23 (£707,000) and 2023/24 (£1,039,000). These amounts are after
applying £480,000 from the Council Tax Reserve and £1,643,000 of Scottish
Government Grant. It is also proposed to transfer a further £90,000 from the
Glebe, Scone budget which is now effectively completed. 
6.7 The New Build scheme at Newburgh Road, Abernethy is also nearing
completion. It is proposed to adjust the expenditure budget by £1,200,000 in
2022/23 in relation to the share equity properties, of which £492,000 is being
funded from Scottish Government grant and £708,000 from sales to the
shared equity owners. 
6.8 In order to support the Council House Buy-Back programme, Scottish
Government Grant of £1,050,000 has been sought in 2022/23, based on
£35,000 per property (30 properties). It is, therefore, proposed to increase the
expenditure budget in 2022/23 by this amount. 
6.9 With various work programmes ongoing, it is also proposed to allocate funding
from the Scottish Housing Quality Standard Future Developments budget in
2025/26 to various schemes in the current year, and these are summarised as
follows:- 
• Central Heating & Rewiring - £938,000, with a reduction of £98,000 in
Third party Contributions from last year.
• Triple Glazing - £60,000.
Page 51 of 132

Page 52

• Fire Precaution Measures - £250,000.
• 111 Rannoch Road, Perth (Conversion) - £211,000. 
6.10 With no works currently planned within the Structural Programme, it is
proposed to move £418,000 from 2022/23 to 2025/26, in order to maintain a
rolling programme of works in future years. 
6.11 The estimate for Capital Financed by Current Revenue (CFCR) in 2022/23
has reduced by £156,000 to £2,458,000, which is offset by an adjustment of
£73,000 relating to Receipts. These result in an overall increase in borrowing
of £83,000 in the current year. After including the reduction in borrowing
brought forward from last year of £231,000, the overall increase in the
Borrowing Requirement for the current 5 years to 2026/27 is £320,000. 
7. BUDGET OVERVIEW 
7.1 The projected net expenditure outturn in 2022/23 for the Composite Capital
Budget is £150,335,000 and represents 109% of the 2022/23 budget as
approved on 20 April 2022 (£138,276,000). The revised budget is based on
the latest projection of expenditure and all budget adjustments outlined within
this report. 
7.2 Net expenditure to 31 July 2022 on the Composite Capital Budget is
£20,846,000 and represents 14% of the proposed revised budget for 2022/23
of £150,335,000. 
7.3 The projected net expenditure outturn in 2022/23 for the Housing Investment
Programme is £18,131,000 and represents 101% of the 2022/23 budget
approved on 20 April 2022 (£17,963,000). 
7.4 Net expenditure to 31 July 2021 on the Housing Investment Programme is
£3,186,000 which represents 18% of the proposed revised budget for 2022/23
of £18,131,000. 
7.5 While the projections have been based on a comprehensive monitoring
exercise, they continue to remain subject to uncertainty as a result of ongoing
inflationary pressures, particularly in the construction industry, in the current
economic environment. 
Author(s)
Name  Designation Contact Details
John Jennings Senior Accountant CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date
Karen Donaldson 
Stewart MacKenzie
Chief Operating Officer 
Head of Finance
24 August 2022 
24 August 2022 
Page 52 of 132

Page 53

Page 53 of 132

Page 54

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2018 – 2023 lays out five outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report. 
Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report.
Page 54 of 132

Page 55

Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
Internal 
4.1 The Chief Executive and the Executive Directors have been consulted in the
preparation of this report.   
2. BACKGROUND PAPERS 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
Page 55 of 132

Page 56

information) were relied on to any material extent in preparing the above
report. 
3. APPENDICES 
• Appendix I – Composite Capital Programme - Estimated Capital
Resources 2022/23 to 2027/28
• Appendix II – Composite Capital Programme - Summary of Capital
Resources and Expenditure 2022/23 to 2027/28 
• Appendix III – Cross Tay Link Road – Revised Cost Analysis Report
July 2022       
• Appendix IV – HRA Capital Investment Programme – Summary of
Capital Resources and Expenditure 2022/23 to 2026/27 
Page 56 of 132

Page 57

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
Estimated Capital Resources 2022/23 to 2027/28
APPENDIX I
Capital Capital Capital Capital Capital Capital Capital
Resources Resources Resources Resources Resources Resources Resources
2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Revised Revised Revised Revised Revised Revised Revised
Budget Budget Budget Budget Budget Budget Budget
Capital Grants
Cycling, Walking & Safer Streets (CWSS) 973 200 200 200 200 200 1,973
Town Centre Fund 26 0 0 0 0 0 26
Regeneration Fund 524 0 0 0 0 0 524
Cross Tay Link Road - Transport Scotland 20,000 15,000 0 0 0 0 35,000
General Capital Grant 10,472 12,837 15,934 12,279 12,265 12,265 76,052
Total Capital Grants 31,995 28,037 16,134 12,479 12,465 12,465 113,575
General Capital Receipts
General Fund - Capital Receipts 730 250 250 250 250 250 1,980
General Fund - Housing Receipts 0 0 0 0 0 0 0
General Fund - Ring Fenced Receipts 472 300 300 300 850 850 3,072
Total General Capital Receipts 1,202 550 550 550 1,100 1,100 5,052
Commercial Property Receipts
Capital Receipts brought-forward 2,556 2,777 1,976 2,093 2,401 2,401 2,556
Commercial Property Capital Receipts 846 344 117 308 0 0 1,615
Capital Receipts carried-forward (2,777) (1,976) (2,093) (2,401) (2,401) (2,401) (2,401)
Total Commercial Property Receipts Applied 625 1,145 0 0 0 0 1,770
Contributions
Tay Cities Deal 813 0 990 1,899 550 505 4,757
Third Party Contributions 2,531 0 0 2,500 1,000 1,000 7,031
Developer Contributions 1,549 2,100 2,300 2,367 2,600 2,600 13,516
Revenue Budget Contributions 814 0 0 0 0 0 814
Total Contributions 5,707 2,100 3,290 6,766 4,150 4,105 26,118
Capital Borrowing Requirement 136,959 144,490 128,053 61,694 38,924 26,467 536,587
TOTAL CAPITAL RESOURCES/
GROSS BUDGET EXPENDITURE 176,488 176,322 148,027 81,489 56,639 44,137 683,102
6
Page 57 of 132

Page 58

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
Estimated Capital Resources 2022/23 to 2027/28
APPENDIX I
Movements in Resources from Approved Budget - 20 April 2022
Revised Revised Revised Revised Revised Revised Revised
Budget Budget Budget Budget Budget Budget Budget
2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 TOTAL
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Increase/(Decrease) in:
Capital Receipts - General Fund (11) 0 0 0 0 0 (11)
Capital Receipts - Commercial Property 94 0 0 0 0 0 94
Capital Receipts - Housing Receipts 0 0 0 0 0 0 0
Capital Receipts - Ring Fenced 24 0 0 0 0 0 24
Capital Grants:
Cycling, Walking & Safer Streets (CWSS) 308 0 0 0 0 0 308
Road Safety Improvement Fund 0 0 0 0 0 0 0
Regeneration Fund 292 0 0 0 0 0 292
Town Centre Fund 26 0 0 0 0 0 26
Cross Tay Link Road - Transport Scotland 0 0 0 0 0 0 0
General Capital Grant 176 0 0 0 0 0 176
Tay Cities Deal 208 0 0 0 0 0 208
Third Party Contributions 1,117 0 0 0 0 0 1,117
Revenue Contributions 2 0 0 0 0 0 2
Developer Contributions 29 0 0 0 0 0 29
Resources b/f 68 (388) (145) (145) (145) (145) (900)
Resources c/f to future years 388 145 145 145 145 145 1,113
Borrowing Requirement 11,315 (10,612) 10,073 19,720 3,809 279 34,584
Total Increase/(Decrease) in Resources 14,036 (10,855) 10,073 19,720 3,809 279 37,062
Approved Resources 20 April 2022 162,452 187,177 137,954 61,769 52,830 43,858 646,040
Revised Resources 176,488 176,322 148,027 81,489 56,639 44,137 683,102
Page 58 of 132

Page 59

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Approved Proposed Proposed Revised Actuals Projected Approved Proposed Revised Approved Proposed Revised
Budget Carry forward Budget Budget to Outturn Budget Budget Budget Budget Budget Budget
02-Feb-22 Adjustment 31-Jul-22 02-Feb-22 Adjustment 02-Feb-22 Adjustment
Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2022/23 2022/23 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
EDUCATION AND CHILDREN'S SERVICES 58,923 (327) (4,192) 54,404 4,016 54,404 58,641 (17,823) 40,818 51,979 (2,689) 49,290
COMMUNITIES 66,974 1,404 14,754 83,132 15,047 83,132 102,621 5,749 108,370 74,631 12,694 87,325
HEALTH AND SOCIAL CARE 1,561 0 (229) 1,332 43 1,332 1,303 229 1,532 1,303 0 1,303
CORPORATE AND DEMOCRATIC SERVICES 10,818 487 162 11,467 1,740 11,467 9,112 990 10,102 8,551 68 8,619
TOTAL NET EXPENDITURE 138,276 1,564 10,495 150,335 20,846 150,335 171,677 (10,855) 160,822 136,464 10,073 146,537
(NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS)
GENERAL CAPITAL GRANT (10,296) 0 (176) (10,472) (4,181) (10,472) (12,837) 0 (12,837) (15,934) 0 (15,934)
DEVELOPER CONTRIBUTIONS (1,520) (29) 0 (1,549) 0 (1,549) (2,100) 0 (2,100) (2,300) 0 (2,300)
CAPITAL RECEIPTS (1,493) (83) 0 (1,576) (4) (1,576) (594) 0 (594) (367) 0 (367)
ANNUAL BORROWING REQUIREMENT 124,967 1,452 10,319 136,738 16,661 136,738 156,146 (10,855) 145,291 117,863 10,073 127,936
CAPITAL RECEIPTS BROUGHT FORWARD (2,488) 0 (68) (2,556) (2,556) (2,556) (3,165) 388 (2,777) (2,121) 145 (1,976)
CAPITAL RECEIPTS CARRIED FORWARD 3,165 (68) (320) 2,777 2,493 2,777 2,121 (145) 1,976 2,238 (145) 2,093
TOTAL NET BORROWING REQUIREMENT 125,644 1,384 9,931 136,959 16,598 136,959 155,102 (10,612) 144,490 117,980 10,073 128,053
6
Page 59 of 132

Page 60

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
EDUCATION AND CHILDREN'S SERVICES
COMMUNITIES
HEALTH AND SOCIAL CARE
CORPORATE AND DEMOCRATIC SERVICES
TOTAL NET EXPENDITURE
(NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS)
GENERAL CAPITAL GRANT
DEVELOPER CONTRIBUTIONS
CAPITAL RECEIPTS
ANNUAL BORROWING REQUIREMENT
CAPITAL RECEIPTS BROUGHT FORWARD
CAPITAL RECEIPTS CARRIED FORWARD
TOTAL NET BORROWING REQUIREMENT
Approved Proposed Revised Approved Proposed Revised Approved Proposed Revised
Budget Budget Budget Budget Budget Budget Budget Budget Budget
02-Feb-22 Adjustment 02-Feb-22 Adjustment 02-Feb-22 Adjustment
Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2025/26 2025/26 2025/26 2026/27 2026/27 2026/27 2027/28 2027/28 2027/28
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
8,950 19,650 28,600 5,650 4,054 9,704 5,823 1,000 6,823
39,514 195 39,709 36,350 120 36,470 27,126 9 27,135
1,303 0 1,303 1,303 0 1,303 1,319 0 1,319
7,103 (125) 6,978 6,927 (365) 6,562 7,035 (730) 6,305
56,870 19,720 76,590 50,230 3,809 54,039 41,303 279 41,582
(12,279) 0 (12,279) (12,265) 0 (12,265) (12,265) 0 (12,265)
(2,367) 0 (2,367) (2,600) 0 (2,600) (2,600) 0 (2,600)
(558) 0 (558) (250) 0 (250) (250) 0 (250)
41,666 19,720 61,386 35,115 3,809 38,924 26,188 279 26,467
(2,238) 145 (2,093) (2,546) 145 (2,401) (2,546) 145 (2,401)
2,546 (145) 2,401 2,546 (145) 2,401 2,546 (145) 2,401
41,974 19,720 61,694 35,115 3,809 38,924 26,188 279 26,467
Page 60 of 132

Page 61

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
EDUCATION AND CHILDREN'S SERVICES
COMMUNITIES
HEALTH AND SOCIAL CARE
CORPORATE AND DEMOCRATIC SERVICES
TOTAL NET EXPENDITURE
(NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS)
GENERAL CAPITAL GRANT
DEVELOPER CONTRIBUTIONS
CAPITAL RECEIPTS
ANNUAL BORROWING REQUIREMENT
CAPITAL RECEIPTS BROUGHT FORWARD
CAPITAL RECEIPTS CARRIED FORWARD
TOTAL NET BORROWING REQUIREMENT
Revised
Budget
Report 1
(£'000)
189,639
382,141
8,092
50,033
629,905
(76,052)
(13,516)
(3,595)
536,742
(2,556)
2,401
536,587
Page 61 of 132

Page 62

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Approved Actual Proposed Approved Proposed Proposed Proposed Actual Projected Approved Proposed Proposed Approved Proposed Proposed Approved Proposed
Budget Expenditure Carry Budget Brought Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Budget Budget
20-Apr-22 Forward 20-Apr-22 Forward Adjustment 14-Sep-22 31-Jul-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment
to from Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2021/22 2021/22 2022/23 2022/23 2021/22 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25 2025/26 2025/26
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
EDUCATION AND CHILDREN'S SERVICES
MIS - Procurement & Integration 0 0 0 55 0 55 57 55 49 49 0 0 0
Digital Inclusion 216 216 0 0 0 0 0 0 0 0 0 0
Blairgowrie Recreation Centre - Replacement 1,100 1,232 (132) 10,000 (132) 9,868 1 9,868 8,435 8,435 6,600 6,600 0
Schools Modernisation Programme
Investment in the Learning Estate 500 705 (205) 3,000 (205) (2,000) 795 191 795 10,084 (5,000) 5,084 6,413 4,000 10,413 5,650 1,000
Methven Primary School Refurbishment 150 189 (39) 350 (39) 311 3 311 0 0 250 250 0
Kirkmichael Primary School Upgrades 0 2 (2) 100 (2) 98 98 0 0 0 0 0
Capital Receipt (ring-fenced) 0 0 0 (100) 0 (100) (100) 0 0 0 0 0
Early Learning & Childcare 40 59 (19) 657 (19) 638 11 638 0 0 0 0 0 
- Letham Primary School Upgrade Project 432 413 19 0 19 19 19 0 0 0 0 0 
- Oakbank Primary School Upgrade Project 8 8 0 0 0 0 0 0 0 0 0 0 
- Rattray Primary School Upgrade Project 2,200 2,105 95 1,250 95 1,345 608 1,345 470 470 0 0 0
North/West Perth - New Primary School 0 0 0 500 0 (400) 100 100 8,500 (7,500) 1,000 15,000 (7,500) 7,500 0 15,000
Riverside Primary New School 4,600 4,590 10 9,000 10 3,008 12,018 2,406 12,018 5,643 (3,008) 2,635 0 0 0
Technology Upgrades 53 88 (35) 580 (35) (400) 145 15 145 300 400 700 586 586 0
Perth Academy - Refurbishment 1,006 1,075 (69) 2,387 (69) (1,300) 1,018 108 1,018 5,162 (3,000) 2,162 2,500 2,500 0 2,150
Perth Grammar School - Upgrade Programme Phase 3 578 594 (16) 2,577 (16) (2,000) 561 7 561 2,315 (815) 1,500 689 811 1,500 0 1,500
Perth High School - Internal Services & Refurbishment 0 0 0 21 0 21 21 0 0 0 0 0
Perth High School - New School Investment 1,500 1,434 66 26,346 66 26,412 609 26,412 15,683 15,683 19,941 19,941 3,300
Harris Academy/Invergowrie - Extension 0 0 0 2,200 0 (1,100) 1,100 1,100 2,000 1,100 3,100 0 0 0
TOTAL: EDUCATION AND CHILDREN'S SERVICES 12,383 12,710 (327) 58,923 (327) (4,192) 54,404 4,016 54,404 58,641 (17,823) 40,818 51,979 (2,689) 49,290 8,950 19,650
COMMUNITIES
Traffic & Road Safety
Road Safety Initiatives (20mph Zones etc..) 86 59 27 271 27 (298) 0 0 275 237 512 274 61 335 200
Road Safety Iniatives 51 51 0 0 0 0 0 0 0 0 0 0
Additional Road Safety - Pedestrian Crossings 0 0 0 175 0 (175) 0 0 175 175 175 175 0 175
Schools Road Safety Measures 20 15 5 541 5 (106) 440 24 440 0 106 106 0 0 0
20mph Signage Programme - Schools 0 0 0 200 0 (89) 111 13 111 0 89 89 0 0 0
20mph Signage Programme 38 41 (3) 79 (3) 76 76 0 0 0 0 0
Cycling Walking & Safer Streets (CWSS) 839 839 0 665 0 383 1,048 195 1,048 200 200 200 200 200
Scottish Government Grant - CWSS (776) (776) 0 (665) 0 (308) (973) (973) (200) (200) (200) (200) (200)
Third Party Contribution (TACTRAN) (63) (63) 0 0 0 (75) (75) (75) 0 0 0 0 0
Car Parking Investment 97 36 61 261 61 (177) 145 8 145 0 177 177 0 0 0
Revenue Contribution (10) (10) 0 0 0 0 0 0 0 0 0 0
Car Parking Investment - Pitlochry 0 0 0 150 0 (150) 0 0 0 150 150 0 0 0
Strathmore Cycle Network 0 0 0 84 0 (84) 0 0 0 84 84 0 0 0
Sub-Total 282 192 90 1,761 90 (1,079) 772 240 772 450 843 1,293 449 61 510 200 175
Asset Management - Roads & Lighting
Structural Maintenance 14,675 15,673 (998) 13,039 (998) 1,358 13,399 3,721 13,399 9,973 (432) 9,541 9,593 9,593 9,593
Third Party Contribution (Forestry Commission Timber Routes) (1) (1) 0 0 0 (945) (945) (172) (945) 0 0 0 0 0
Traffic Signal Renewals - Upgrading 191 166 25 174 25 199 199 0 0 0 0 0
Third Party Contributions (60) (57) (3) 0 (3) (3) (3) 0 0 0 0 0
Footways 404 375 29 495 29 524 111 524 435 435 435 435 435
Investment in Local Footpaths 0 0 0 100 0 (100) 0 0 100 100 0 100 100 0
Road Safety Barriers 54 3 51 0 51 (41) 10 1 10 0 23 23 0 0 0
Third Party Contribution (18) 0 (18) 0 (18) 18 0 0 0 0 0 0 0
Pedestrian Gritters 7 7 0 0 0 0 0 0 0 0 0 0
Sub-Total 15,252 16,166 (914) 13,808 (914) 290 13,184 3,661 13,184 10,508 (409) 10,099 10,028 100 10,128 10,028 0
Asset Management - Bridges
Bridge Refurbishment Programme 390 379 11 2,198 11 (1,080) 1,129 5 1,129 2,091 125 2,216 1,091 955 2,046 1,091
Dalhenzean Culvert 0 0 0 0 0 0 0 287 287 0 0 0
Dunkeld Golf Course 0 0 0 0 0 0 0 0 0 226 226 0
Vehicular Bridge Parapets Programme - Assess & Upgrade 0 0 0 29 0 29 29 0 0 0 0 0
Old Perth Bridge - Strengthening 0 0 0 10 0 10 10 180 180 10 10 2,369
Perth Queens Bridge - Strengthening 7 7 0 70 0 (70) 0 0 315 70 385 10 10 70
Culteuchar Culvert 10 11 (1) 400 (1) (278) 121 121 0 278 278 0 0 0
Glendevon Bridge 133 161 (28) 383 (28) (80) 275 166 275 0 0 0 0 0
Tullyfergus Bridge 12 1 11 0 11 (11) 0 0 123 11 134 0 0 0
Sub-Total 552 559 (7) 3,090 (7) (1,519) 1,564 171 1,564 2,996 484 3,480 1,337 955 2,292 3,530 0
Page 62 of 132

Page 63

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Approved Actual Proposed Approved Proposed Proposed Proposed Actual Projected Approved Proposed Proposed Approved Proposed Proposed Approved Proposed
Budget Expenditure Carry Budget Brought Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Budget Budget
20-Apr-22 Forward 20-Apr-22 Forward Adjustment 14-Sep-22 31-Jul-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment
to from Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2021/22 2021/22 2022/23 2022/23 2021/22 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25 2025/26 2025/26
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Improvement Schemes
A9/A85 Road Junction Improvements 420 61 359 0 359 359 1 359 0 0 0 0 0
Cross Tay Link Road (CTLR) 11,432 10,751 681 34,524 681 16,597 51,802 6,690 51,802 53,198 4,345 57,543 12,800 11,558 24,358 0
Scottish Government Grant (5,000) (5,000) 0 (20,000) 0 (20,000) (20,000) (15,000) (15,000) 0 0 0
A977 Upgrades 27 23 4 186 4 190 190 0 0 0 0 0
Brioch Road, Crieff - Road Realignment & Safety Measures 0 0 0 31 0 31 31 0 0 0 0 0
Third Party Contribution (Developers) (65) (65) 0 0 0 0 0 0 0 0 0 0
Sub-Total 6,814 5,770 1,044 14,741 1,044 16,597 32,382 6,691 32,382 38,198 4,345 42,543 12,800 11,558 24,358 0 0
Rural Flood Protection Schemes
Almondbank Flood Protection Scheme 70 61 9 34 9 43 11 43 0 0 0 0 0
Revenue Contribution (22) (22) 0 0 0 0 0 0 0 0 0 0
Perth Flood Protection Scheme (Pump Replacement) 216 200 16 145 16 161 161 0 0 0 0 0
Comrie Flood Protection Scheme 378 338 40 3,651 40 3,691 621 3,691 9,919 9,919 12,473 12,473 0
Milnathort Flood Protection Scheme 135 112 23 97 23 120 120 1,093 1,093 541 541 0
South Kinross Flood Protection Scheme 210 139 71 171 71 242 242 156 156 2,562 2,562 350
Scone Flood Protection Scheme 0 0 0 81 0 81 81 227 227 416 416 48
Coastal Change Adaptation 0 0 0 0 0 0 0 100 100 0 0 0
Sub-Total 987 828 159 4,179 159 0 4,338 632 4,338 11,495 0 11,495 15,992 0 15,992 398 0
Rural Iniaitives
Conservation of Built Heritage 36 (6) 42 0 42 (42) 0 0 0 0 0 0 0
Sub-Total 36 (6) 42 0 42 (42) 0 0 0 0 0 0 0 0 0 0 0
Perth & Kinross Place-making
Mill Street Environmental Improvements 0 0 0 127 0 127 127 0 0 0 0 0
Perth, Place, People 0 0 0 0 0 0 0 0 3,629 3,629 0 0 0
St Paul's Church 142 175 (33) 0 (33) 33 0 0 0 0 0 0 0
Perth City Centre Golden Route (Rail Station) 0 0 0 0 0 0 0 493 (493) 0 0 0 0
Green Network Routes 0 0 0 0 0 0 0 115 (115) 0 0 0 0
City Greening 31 0 31 0 31 31 31 0 0 0 0 0
Tay Street, Perth 0 0 0 0 0 0 0 1,472 (1,472) 0 0 0 0
Mill St, Perth (Phase 3) - Shared Space at Bus Station 0 0 0 0 0 0 0 600 (600) 0 0 0 0
South Street, Perth - Transport Hub 0 0 0 0 0 0 0 940 (940) 0 0 0 0
Perth & Kinross Lighting Action Plan 388 178 210 1,889 210 2,099 109 2,099 653 653 0 0 0
Sub-Total 561 353 208 2,016 208 33 2,257 109 2,257 4,273 9 4,282 0 0 0 0 0
Other Planning Projects
Creative Exchange (former St. John's Primary School) 84 31 53 0 53 53 53 0 0 0 0 0
Town Centre - Regeneration & Economic Improvements 2,034 2,008 26 0 26 26 26 0 0 0 0 0
Scottish Government Grant (2,034) (2,008) (26) 0 (26) (26) (26) 0 0 0 0 0
Local Full Fibre Network 3,769 3,451 318 0 318 (120) 198 2 198 0 0 0 0 0
Third Party Contribution  - DCMS (2,569) (2,524) (45) 0 (45) 45 0 0 0 0 0 0 0
Scottish Government Grant (Town Centre Fund) (200) (200) 0 0 0 0 0 0 0 0 0 0
Third Party Contribution - Tay Cities Deal (1,000) (728) (272) 0 (272) 74 (198) (195) (198) 0 0 0 0 0
Low Carbon Transport & Active Travel Hub - Broxden EV Chargers 52 34 18 1,008 18 1,026 1 1,026 0 0 0 0 0
Third Party Contribution - ERDF (21) (14) (7) (403) (7) (410) (410) 0 0 0 0 0
Third Party Contribution - Tay Cities Deal (31) (21) (10) (605) (10) (615) (615) 0 0 0 0 0
Perth Eco Innovation Park 0 0 0 6,889 0 6,889 6,889 10,661 10,661 3,536 3,536 0
Third Party Contributions - Tay Cities Deal 0 0 0 0 0 0 0 0 0 (990) (990) (1,899)
Other Third Party Contributions 0 0 0 0 0 0 0 0 0 0 0 (2,500)
Capital Receipts - Ring Fenced Land Disposals 0 0 0 0 0 0 0 0 0 0 0 0
Nature Restoration 166 136 30 0 30 176 206 1 206 0 0 0 0 0
Sub-Total 250 165 85 6,889 85 175 7,149 (191) 7,149 10,661 0 10,661 2,546 0 2,546 (4,399) 0
City Centre Developments - Cultural Attractions
Perth City Hall 9,567 10,071 (504) 7,840 (504) 7,336 2,500 7,336 4,311 700 5,011 663 663 0
Perth Museum & Art Gallery (PMAG) 12 0 12 0 12 12 12 3,304 3,304 0 0 0
Collections Centre 24 0 24 0 24 24 24 6,400 6,400 0 0 0
Third Party Contribution (Tay Cities Deal) (7,200) (7,200) 0 0 0 0 0 0 0 0 0 0
PH2O 0 0 0 500 0 500 500 3,500 3,500 26,000 26,000 25,000
Sub-Total 2,403 2,871 (468) 0 8,340 (468) 0 7,872 2,500 7,872 17,515 700 18,215 26,663 0 26,663 25,000 0
Community Planning
Letham Community Wellbeing Hub 768 476 292 3,577 292 3,869 593 3,869 0 0 0 0 0
Scottish Government Grant (Regeneration Fund) (768) (476) (292) (232) (292) (524) (524) 0 0 0 0 0
Third Party Contribution (Letham4All) 0 0 0 (519) 0 (519) (519) 0 0 0 0 0
Page 63 of 132

Page 64

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Approved Actual Proposed Approved Proposed Proposed Proposed Actual Projected Approved Proposed Proposed Approved Proposed Proposed Approved Proposed
Budget Expenditure Carry Budget Brought Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Budget Budget
20-Apr-22 Forward 20-Apr-22 Forward Adjustment 14-Sep-22 31-Jul-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment
to from Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2021/22 2021/22 2022/23 2022/23 2021/22 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25 2025/26 2025/26
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
Revenue Contribution (Place Based Development Grant) 0 0 0 (735) 0 (735) (735) 0 0 0 0 0
Sub-Total 0 0 0 0 2,091 0 0 2,091 593 2,091 0 0 0 0 0 0 0 0
Community Greenspace
Play Areas - Improvements Implementation Strategy 309 270 39 669 39 708 708 150 150 150 150 150
Third Party Contribution (131) (131) 0 (47) 0 (47) (47) 0 0 0 0 0
Revenue Contribution (Developer Contribution Reserve) (12) (10) (2) 0 (2) (2) (2) 0 0 0 0 0
3G Pitch, Blairgowrie 400 362 38 0 38 38 38 100 100 0 0 0
Settlement/Neighbourhood Parks 18 10 8 0 8 8 8 0 0 0 0 0
Countryside Sites 16 18 (2) 150 (2) 148 1 148 0 0 0 0 0
Community Greenspace Sites 20 0 20 486 20 506 506 410 410 410 410 410
Community Greenspace Bridges 50 21 29 35 29 64 64 0 0 0 0 0
Core Path Implementation 35 30 5 73 5 78 78 0 0 0 0 0
Third Party Contribution (19) (15) (4) (56) (4) (60) (60) 0 0 0 0 0
Alyth Environmental Improvements 16 6 10 0 10 10 10 0 0 0 0 0
Premier Parks 10 6 4 0 4 4 4 0 0 0 0 0
Auchterarder Public Park 15 19 (4) 127 (4) 140 263 263 0 0 0 0 0
Third Party Contribution 0 0 0 0 0 (140) (140) (140) 0 0 0 0 0
The Knock 40 16 24 0 24 24 5 24 0 0 0 0 0
Third Party Contribution (6) (6) 0 0 0 0 0 0 0 0 0 0
Kinnoull Hill 158 117 41 0 41 41 41 0 0 0 0 0
Third Party Contribution (110) (110) 0 0 0 0 0 0 0 0 0 0
Cemetery Extensions 3 0 3 60 3 63 63 406 406 150 150 100
Sub-Total 812 603 209 1,497 209 0 1,706 6 1,706 1,066 0 1,066 710 0 710 660 0
Support Services
PC Replacement & IT Upgrades
Hardware 20 27 (7) 17 (7) 10 4 10 17 17 17 17 17
Licenses 15 57 (42) 77 (42) 35 12 35 120 120 120 120 120
Corporate Programme Management System 23 23 0 0 0 0 0 0 0 0 0 0
Sub-Total 58 107 (49) 94 (49) 0 45 16 45 137 0 137 137 0 137 137 0
Commercial Property Investment Programme
North Muirton Industrial Estate - Site Servicing & Provision of Units 208 103 105 0 105 105 1 105 0 0 0 0 0
Western Edge, Kinross - Site Servicing 12 2 10 0 10 10 10 0 0 0 0 0
Additional Infrastructure Investment - Broxden 46 0 46 0 46 46 46 0 0 0 0 0
Broxden Drainage Mitigation Works 0 6 (6) 314 (6) 308 62 308 0 0 0 0 0
Third Party Contribution (Scottish Water) 0 0 0 (239) 0 (239) (239) 0 0 0 0 0
Ruthvenfield Business Centre 0 0 0 0 0 510 510 510 0 1,145 1,145 0 0 0
Third Party Contribution 0 0 0 0 0 (115) (115) (115) 0 0 0 0 0
Eco-Hub Manufacturing Facility 10 0 10 0 10 (10) 0 0 1,388 (1,388) 0 0 0 0
North Muirton Industrial Estate Expansion Land - Servicing 30 33 (3) 0 (3) 3 0 0 0 0 0 0 0
Sub-Total 306 144 162 75 162 388 625 63 625 1,388 (243) 1,145 0 0 0 0 0
Prudential Borrowing Projects
Wheeled Bin Replacement Programme - Domestic Bins 201 179 22 243 22 265 82 265 200 200 200 200 200
Wheeled Bin Replacement Programme - Commercial Bins 0 0 0 39 0 39 39 20 20 20 20 20
Recycling Containers, Oil Banks & Battery Banks Replacement Programme79 76 3 104 3 4 111 111 65 65 65 65 65
Capital Receipts - Disposals (14) (14) 0 0 0 (4) (4) (4) (4) 0 0 0 0 0
Litter Bins 15 15 0 25 0 25 25 25 25 50 50 50
Capital Receipts - Disposals 0 0 0 0 0 0 0 0 0 0 0 0
Smart Cities - Smart Waste 294 37 257 48 257 305 42 305 0 0 0 0 0
Third Party Contribution (ERDF) (116) (15) (101) (17) (101) (118) (118) 0 0 0 0 0
Vehicle Replacement Programme 2,647 2,390 257 4,345 257 4,602 218 4,602 3,000 3,000 3,000 3,000 3,000
Capital Receipts - Vehicle Disposals (262) (242) (20) (348) (20) (368) (22) (368) (300) (300) (300) (300) (300)
Crematorium - Abatement Works 15 6 9 0 9 9 9 0 0 0 0 0
Street Lighting Renewal - LED & Column Replacement 793 844 (51) 910 (51) (89) 770 198 770 924 20 944 934 20 954 925 20
LED Traffic Signal Replacement 26 24 2 144 2 146 39 146 0 0 0 0 0
Almondbank Flood Protection Scheme 4 4 0 0 0 0 0 0 0 0 0 0
Land Purchase & Development (Hotel Development) 0 0 0 1,900 0 1,900 1,900 0 0 0 0 0
Technology & Innovation Incubator Units 0 0 0 1,000 0 1,000 1,000 0 0 0 0 0
Sub Total 3,682 3,304 378 8,393 378 (89) 8,682 553 8,682 3,934 20 3,954 3,969 20 3,989 3,960 20
Housing Projects
Gypsy Travellers Site Improvement Works 252 45 207 0 207 207 3 207 0 0 0 0 0
Additional Gypsy Traveller Site Improvement Works 225 0 225 0 225 225 225 0 0 0 0 0
Gypsy Traveller Site Community Improvement Works 125 92 33 0 33 33 33 0 0 0 0 0
Sub Total 602 137 465 0 0 465 0 465 3 465 0 0 0 0 0 0 0 0
Page 64 of 132

Page 65

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Approved Actual Proposed Approved Proposed Proposed Proposed Actual Projected Approved Proposed Proposed Approved Proposed Proposed Approved Proposed
Budget Expenditure Carry Budget Brought Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Budget Budget
20-Apr-22 Forward 20-Apr-22 Forward Adjustment 14-Sep-22 31-Jul-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment
to from Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2021/22 2021/22 2022/23 2022/23 2021/22 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25 2025/26 2025/26
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
TOTAL: COMMUNITIES 32,597 31,193 1,404 0 66,974 1,404 14,754 83,132 15,047 83,132 102,621 5,749 108,370 74,631 12,694 87,325 39,514 195
Health & Social Care
Occupational Therapy Equipment 248 248 0 250 0 250 250 250 250 250 250 250
Technology Enabled Telecare 0 0 0 1,000 0 1,000 43 1,000 1,000 1,000 1,000 1,000 1,000
Moving & Handling Office Refurbishment 0 0 0 29 0 29 29 0 0 0 0 0
Software Licences 53 53 0 53 0 53 53 53 53 53 53 53
Developing Supported Tenancies 0 0 0 229 0 (229) 0 0 0 229 229 0 0 0
TOTAL: HEALTH & SOCIAL CARE 301 301 0 1,561 0 (229) 1,332 43 1,332 1,303 229 1,532 1,303 0 1,303 1,303 0
Page 65 of 132

Page 66

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Approved Actual Proposed Approved Proposed Proposed Proposed Actual Projected Approved Proposed Proposed Approved Proposed Proposed Approved Proposed
Budget Expenditure Carry Budget Brought Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Budget Budget
20-Apr-22 Forward 20-Apr-22 Forward Adjustment 14-Sep-22 31-Jul-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment
to from Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2021/22 2021/22 2022/23 2022/23 2021/22 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25 2025/26 2025/26
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
CORPORATE AND DEMOCRATIC SERVICES
Property Services
DDA Adaptation & Alteration Works Programme 208 163 45 329 45 374 9 374 200 200 200 200 200
Property Compliance Works Programme 550 573 (23) 1,428 (23) 1,405 182 1,405 650 650 650 650 650
Capital Improvement Projects Programme 3,092 2,887 205 1,182 205 600 1,987 136 1,987 1,800 1,800 1,800 1,800 1,800
Pitlochry High School - Upgrade Programme 312 342 (30) 755 (30) 725 93 725 0 0 0 0 0
Community School of Auchterarder - Structural Improvements 275 264 11 725 11 736 262 736 0 0 0 0 0
CO2 Monitors for Schools Programme 174 93 81 0 81 81 81 0 0 0 0 0
Crieff Primary School - PV Energy Efficiency Works 0 0 0 77 0 77 77 0 0 0 0 0
Revenue Contribution (Salix Reserve) 0 0 0 (77) 0 (77) (77) 0 0 0 0 0
Energy Conservation & Carbon Reduction Programme (PB) 89 71 18 150 18 168 168 150 150 150 150 150
Information Systems & Technology
ICT Infrastructure & Replacement and Upgrade Programme 4,040 4,132 (92) 2,956 (92) 2,864 580 2,864 3,711 3,711 4,087 4,087 2,744
Data & Analytics 0 0 0 635 0 (135) 500 500 655 135 790 675 675 646
Supporting Digital 0 0 0 632 0 205 837 837 652 517 1,169 674 40 714 697 40
Revenue Contribution 0 (78) 78 0 78 (78) 0 0 0 0 0 0 0
Third Party Contribution (ERDF) 0 (48) 48 0 48 (48) 0 0 0 0 0 0 0
Software Licences (Revenues & Benefits) 26 26 0 51 0 51 51 51 51 51 51 51
School Audio-Visual (AV) Equipment Replacement Programme 1,524 1,442 82 470 82 848 1,400 394 1,400 530 (4) 526 224 (224) 0 125 (125)
Online/Mobile Working 897 832 65 461 65 (526) 0 0 0 0 0 0 0
Third Party Contribution (ERDF) 0 0 0 (133) 0 133 0 0 0 0 0 0 0
Swift Social Work System Replacement 374 369 5 1,008 5 (674) 339 84 339 673 382 1,055 0 292 292 0
Customer Service Blueprint 40 46 (6) 169 (6) (163) 0 0 40 (40) 0 40 (40) 0 40 (40)
TOTAL: CORPORATE AND DEMOCRATIC SERVICES 11,601 11,114 487 0 10,818 487 162 11,467 1,740 11,467 9,112 990 10,102 8,551 68 8,619 7,103 (125)
TOTAL COMPOSITE NET EXPENDITURE 56,882 55,318 1,564 138,276 1,564 10,495 150,335 20,846 150,335 171,677 (10,855) 160,822 136,464 10,073 146,537 56,870 19,720
(NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS)
CAPITAL RECEIPTS
General Capital Grant - Scottish Government (24,841) (24,841) 0 (10,296) 0 (176) (10,472) (4,181) (10,472) (12,837) (12,837) (15,934) (15,934) (12,279)
Developer Contributions (978) (949) (29) (1,520) (29) (1,549) (1,549) (2,100) (2,100) (2,300) (2,300) (2,367)
General Fund - Capital Receipts/Disposal (430) (441) 11 (741) 11 0 (730) (4) (730) (250) 0 (250) (250) 0 (250) (250) 0
Commercial Property - Capital Receipts/Disposal (265) (171) (94) (752) (94) 0 (846) 0 (846) (344) 0 (344) (117) 0 (117) (308) 0
General Fund Housing Receipts (3) (3) 0 0 0 0 0 0 0 0 0 0
Total: Capital Receipts (26,517) (26,405) (112) (13,309) (112) (176) (13,597) (4,185) (13,597) (15,531) 0 (15,531) (18,601) 0 (18,601) (15,204) 0
Annual Composite Borrowing Requirement 30,365 28,913 1,452 124,967 1,452 10,319 136,738 16,661 136,738 156,146 (10,855) 145,291 117,863 10,073 127,936 41,666 19,720
CAPITAL RECEIPTS BROUGHT FORWARD (2,529) (2,529) 0 (2,488) 0 (68) (2,556) (2,556) (2,556) (3,165) 388 (2,777) (2,121) 145 (1,976) (2,238) 145
CAPITAL RECEIPTS CARRIED FORWARD 2,488 2,556 (68) 3,165 (68) (320) 2,777 2,493 2,777 2,121 (145) 1,976 2,238 (145) 2,093 2,546 (145)
TOTAL NET COMPOSITE BORROWING REQUIREMENT 30,324 28,940 1,384 125,644 1,384 9,931 136,959 16,598 136,959 155,102 (10,612) 144,490 117,980 10,073 128,053 41,974 19,720
Page 66 of 132

Page 67

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
EDUCATION AND CHILDREN'S SERVICES
MIS - Procurement & Integration
Digital Inclusion
Blairgowrie Recreation Centre - Replacement
Schools Modernisation Programme
Investment in the Learning Estate
Methven Primary School Refurbishment
Kirkmichael Primary School Upgrades
Capital Receipt (ring-fenced)
Early Learning & Childcare
- Letham Primary School Upgrade Project
- Oakbank Primary School Upgrade Project
- Rattray Primary School Upgrade Project
North/West Perth - New Primary School
Riverside Primary New School
Technology Upgrades
Perth Academy - Refurbishment
Perth Grammar School - Upgrade Programme Phase 3
Perth High School - Internal Services & Refurbishment
Perth High School - New School Investment
Harris Academy/Invergowrie - Extension
TOTAL: EDUCATION AND CHILDREN'S SERVICES
COMMUNITIES
Traffic & Road Safety
Road Safety Initiatives (20mph Zones etc..)
Road Safety Iniatives
Additional Road Safety - Pedestrian Crossings
Schools Road Safety Measures
20mph Signage Programme - Schools
20mph Signage Programme
Cycling Walking & Safer Streets (CWSS)
Scottish Government Grant - CWSS
Third Party Contribution (TACTRAN)
Car Parking Investment
Revenue Contribution
Car Parking Investment - Pitlochry
Strathmore Cycle Network
Sub-Total
Asset Management - Roads & Lighting
Structural Maintenance
Third Party Contribution (Forestry Commission Timber Routes)
Traffic Signal Renewals - Upgrading
Third Party Contributions
Footways
Investment in Local Footpaths
Road Safety Barriers
Third Party Contribution
Pedestrian Gritters
Sub-Total
Asset Management - Bridges
Bridge Refurbishment Programme
Dalhenzean Culvert
Dunkeld Golf Course
Vehicular Bridge Parapets Programme - Assess & Upgrade
Old Perth Bridge - Strengthening
Perth Queens Bridge - Strengthening
Culteuchar Culvert
Glendevon Bridge
Tullyfergus Bridge
Sub-Total
Proposed Approved Proposed Proposed Approved Proposed Proposed Revised
Budget Budget Budget Budget Budget Budget Budget Budget
14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22
Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2025/26 2026/27 2026/27 2026/27 2027/28 2027/28 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
0 0 0 0 0 104
0 0 0 0 0 0
0 0 0 0 0 24,903
6,650 5,650 1,000 6,650 5,823 1,000 6,823 36,415
0 0 0 0 0 561
0 0 0 0 0 98
0 0 0 0 0 (100)
0 0 0 0 0 638
0 0 0 0 0 19
0 0 0 0 0 0
0 0 0 0 0 1,815
15,000 0 400 400 0 0 24,000
0 0 0 0 0 14,653
0 0 0 0 0 1,431
2,150 0 2,150 2,150 0 0 9,980
1,500 0 504 504 0 0 5,565
0 0 0 0 0 21
3,300 0 0 0 0 65,336
0 0 0 0 0 4,200
28,600 5,650 4,054 9,704 5,823 1,000 6,823 189,639
200 200 200 200 200 1,447
0 0 0 0 0 0
175 0 0 0 0 525
0 0 0 0 0 546
0 0 0 0 0 200
0 0 0 0 0 76
200 200 200 200 200 2,048
(200) (200) (200) (200) (200) (1,973)
0 0 0 0 0 (75)
0 0 0 0 0 322
0 0 0 0 0 0
0 0 0 0 0 150
0 0 0 0 0 84
375 200 0 200 200 0 200 3,350
9,593 9,800 9,800 7,500 7,500 59,426
0 0 0 0 0 (945)
0 0 0 0 0 199
0 0 0 0 0 (3)
435 435 435 435 435 2,699
0 0 0 0 0 200
0 0 0 0 0 33
0 0 0 0 0 0
0 0 0 0 0 0
10,028 10,235 0 10,235 7,935 0 7,935 61,609
1,091 1,091 100 1,191 1,291 1,291 8,964
0 0 0 0 0 287
0 0 0 0 0 226
0 0 0 0 0 29
2,369 0 0 0 0 2,569
70 2,153 2,153 0 0 2,618
0 0 0 0 0 399
0 0 0 0 0 275
0 0 0 0 0 134
3,530 3,244 100 3,344 1,291 0 1,291 15,501
Page 67 of 132

Page 68

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Improvement Schemes
A9/A85 Road Junction Improvements
Cross Tay Link Road (CTLR)
Scottish Government Grant
A977 Upgrades
Brioch Road, Crieff - Road Realignment & Safety Measures
Third Party Contribution (Developers)
Sub-Total
Rural Flood Protection Schemes
Almondbank Flood Protection Scheme
Revenue Contribution
Perth Flood Protection Scheme (Pump Replacement)
Comrie Flood Protection Scheme
Milnathort Flood Protection Scheme
South Kinross Flood Protection Scheme
Scone Flood Protection Scheme
Coastal Change Adaptation
Sub-Total
Rural Iniaitives
Conservation of Built Heritage
Sub-Total
Perth & Kinross Place-making
Mill Street Environmental Improvements
Perth, Place, People
St Paul's Church
Perth City Centre Golden Route (Rail Station)
Green Network Routes
City Greening
Tay Street, Perth
Mill St, Perth (Phase 3) - Shared Space at Bus Station
South Street, Perth - Transport Hub
Perth & Kinross Lighting Action Plan
Sub-Total
Other Planning Projects
Creative Exchange (former St. John's Primary School)
Town Centre - Regeneration & Economic Improvements
Scottish Government Grant
Local Full Fibre Network
Third Party Contribution  - DCMS
Scottish Government Grant (Town Centre Fund)
Third Party Contribution - Tay Cities Deal
Low Carbon Transport & Active Travel Hub - Broxden EV Chargers
Third Party Contribution - ERDF
Third Party Contribution - Tay Cities Deal
Perth Eco Innovation Park
Third Party Contributions - Tay Cities Deal
Other Third Party Contributions
Capital Receipts - Ring Fenced Land Disposals
Nature Restoration
Sub-Total
City Centre Developments - Cultural Attractions
Perth City Hall
Perth Museum & Art Gallery (PMAG)
Collections Centre
Third Party Contribution (Tay Cities Deal)
PH2O
Sub-Total
Community Planning
Letham Community Wellbeing Hub
Scottish Government Grant (Regeneration Fund)
Third Party Contribution (Letham4All)
Proposed Approved Proposed Proposed Approved Proposed Proposed Revised
Budget Budget Budget Budget Budget Budget Budget Budget
14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22
Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2025/26 2026/27 2026/27 2026/27 2027/28 2027/28 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
0 0 0 0 0 359
0 0 0 0 0 133,703
0 0 0 0 0 (35,000)
0 0 0 0 0 190
0 0 0 0 0 31
0 0 0 0 0 0
0 0 0 0 0 0 0 99,283
0 0 0 0 0 43
0 0 0 0 0 0
0 0 0 0 0 161
0 0 0 0 0 26,083
0 0 0 0 0 1,754
350 0 0 0 0 3,310
48 0 0 0 0 772
0 0 0 0 0 100
398 0 0 0 0 0 0 32,223
0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 127
0 0 0 0 0 3,629
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 31
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 2,752
0 0 0 0 0 0 0 6,539
0 0 0 0 0 53
0 0 0 0 0 26
0 0 0 0 0 (26)
0 0 0 0 0 198
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 (198)
0 0 0 0 0 1,026
0 0 0 0 0 (410)
0 0 0 0 0 (615)
0 0 0 0 0 21,086
(1,899) (550) (550) (505) (505) (3,944)
(2,500) (1,000) (1,000) (1,000) (1,000) (4,500)
0 (550) (550) (550) (550) (1,100)
0 0 0 0 0 206
(4,399) (2,100) 0 (2,100) (2,055) 0 (2,055) 11,802
0 0 0 0 0 13,010
0 0 0 0 0 3,316
0 0 0 0 0 6,424
0 0 0 0 0 0
25,000 20,000 20,000 15,000 15,000 90,000
25,000 20,000 0 20,000 15,000 0 15,000 112,750
0 0 0 0 0 3,869
0 0 0 0 0 (524)
0 0 0 0 0 (519)
Page 68 of 132

Page 69

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
Revenue Contribution (Place Based Development Grant)
Sub-Total
Community Greenspace
Play Areas - Improvements Implementation Strategy
Third Party Contribution
Revenue Contribution (Developer Contribution Reserve)
3G Pitch, Blairgowrie
Settlement/Neighbourhood Parks
Countryside Sites
Community Greenspace Sites
Community Greenspace Bridges
Core Path Implementation
Third Party Contribution
Alyth Environmental Improvements
Premier Parks
Auchterarder Public Park
Third Party Contribution
The Knock
Third Party Contribution
Kinnoull Hill
Third Party Contribution
Cemetery Extensions
Sub-Total
Support Services
PC Replacement & IT Upgrades
Hardware
Licenses
Corporate Programme Management System
Sub-Total
Commercial Property Investment Programme
North Muirton Industrial Estate - Site Servicing & Provision of Units
Western Edge, Kinross - Site Servicing
Additional Infrastructure Investment - Broxden
Broxden Drainage Mitigation Works
Third Party Contribution (Scottish Water)
Ruthvenfield Business Centre
Third Party Contribution
Eco-Hub Manufacturing Facility
North Muirton Industrial Estate Expansion Land - Servicing
Sub-Total
Prudential Borrowing Projects
Wheeled Bin Replacement Programme - Domestic Bins
Wheeled Bin Replacement Programme - Commercial Bins
Recycling Containers, Oil Banks & Battery Banks Replacement Programme
Capital Receipts - Disposals
Litter Bins
Capital Receipts - Disposals
Smart Cities - Smart Waste
Third Party Contribution (ERDF)
Vehicle Replacement Programme
Capital Receipts - Vehicle Disposals
Crematorium - Abatement Works
Street Lighting Renewal - LED & Column Replacement
LED Traffic Signal Replacement
Almondbank Flood Protection Scheme
Land Purchase & Development (Hotel Development)
Technology & Innovation Incubator Units
Sub Total
Housing Projects
Gypsy Travellers Site Improvement Works
Additional Gypsy Traveller Site Improvement Works
Gypsy Traveller Site Community Improvement Works
Sub Total
Proposed Approved Proposed Proposed Approved Proposed Proposed Revised
Budget Budget Budget Budget Budget Budget Budget Budget
14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22
Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2025/26 2026/27 2026/27 2026/27 2027/28 2027/28 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
0 0 0 0 0 (735)
0 0 0 0 0 0 0 2,091
150 150 150 150 150 1,458
0 0 0 0 0 (47)
0 0 0 0 0 (2)
0 0 0 0 0 138
0 0 0 0 0 8
0 0 0 0 0 148
410 410 410 410 410 2,556
0 0 0 0 0 64
0 0 0 0 0 78
0 0 0 0 0 (60)
0 0 0 0 0 10
0 0 0 0 0 4
0 0 0 0 0 263
0 0 0 0 0 (140)
0 0 0 0 0 24
0 0 0 0 0 0
0 0 0 0 0 41
0 0 0 0 0 0
100 100 100 100 100 919
660 660 0 660 660 0 660 5,462
17 17 17 17 17 95
120 120 120 120 120 635
0 0 0 0 0 0
137 137 0 137 137 0 137 730
0 0 0 0 0 105
0 0 0 0 0 10
0 0 0 0 0 46
0 0 0 0 0 308
0 0 0 0 0 (239)
0 0 0 0 0 1,655
0 0 0 0 0 (115)
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0 0 1,770
200 200 200 200 200 1,265
20 20 20 20 20 139
65 65 65 65 65 436
0 0 0 0 0 (4)
50 50 50 50 50 250
0 0 0 0 0 0
0 0 0 0 0 305
0 0 0 0 0 (118)
3,000 3,000 3,000 3,000 3,000 19,602
(300) (300) (300) (300) (300) (1,868)
0 0 0 0 0 9
945 939 20 959 923 9 932 5,504
0 0 0 0 0 146
0 0 0 0 0 0
0 0 0 0 0 1,900
0 0 0 0 0 1,000
3,980 3,974 20 3,994 3,958 9 3,967 28,566
0 0 0 0 0 207
0 0 0 0 0 225
0 0 0 0 0 33
0 0 0 0 0 0 0 465
Page 69 of 132

Page 70

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
TOTAL: COMMUNITIES
Health & Social Care
Occupational Therapy Equipment
Technology Enabled Telecare
Moving & Handling Office Refurbishment
Software Licences
Developing Supported Tenancies
TOTAL: HEALTH & SOCIAL CARE
Proposed Approved Proposed Proposed Approved Proposed Proposed Revised
Budget Budget Budget Budget Budget Budget Budget Budget
14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22
Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2025/26 2026/27 2026/27 2026/27 2027/28 2027/28 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
39,709 36,350 120 36,470 27,126 9 27,135 382,141
250 250 250 250 250 1,500
1,000 1,000 1,000 1,000 1,000 6,000
0 0 0 0 0 29
53 53 53 69 69 334
0 0 0 0 0 229
1,303 1,303 0 1,303 1,319 0 1,319 8,092
Page 70 of 132

Page 71

PERTH AND KINROSS COUNCIL
COMPOSITE CAPITAL PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2027/28
APPENDIX II
CORPORATE AND DEMOCRATIC SERVICES
Property Services
DDA Adaptation & Alteration Works Programme
Property Compliance Works Programme
Capital Improvement Projects Programme
Pitlochry High School - Upgrade Programme
Community School of Auchterarder - Structural Improvements
CO2 Monitors for Schools Programme
Crieff Primary School - PV Energy Efficiency Works
Revenue Contribution (Salix Reserve)
Energy Conservation & Carbon Reduction Programme (PB)
Information Systems & Technology
ICT Infrastructure & Replacement and Upgrade Programme
Data & Analytics
Supporting Digital
Revenue Contribution
Third Party Contribution (ERDF)
Software Licences (Revenues & Benefits)
School Audio-Visual (AV) Equipment Replacement Programme
Online/Mobile Working
Third Party Contribution (ERDF)
Swift Social Work System Replacement
Customer Service Blueprint
TOTAL: CORPORATE AND DEMOCRATIC SERVICES
TOTAL COMPOSITE NET EXPENDITURE
(NET OF GRANTS, REVENUE AND 3RD PARTY CONTRIBUTIONS, AND RING FENCED RECEIPTS)
CAPITAL RECEIPTS
General Capital Grant - Scottish Government
Developer Contributions
General Fund - Capital Receipts/Disposal
Commercial Property - Capital Receipts/Disposal
General Fund Housing Receipts
Total: Capital Receipts
Annual Composite Borrowing Requirement
CAPITAL RECEIPTS BROUGHT FORWARD
CAPITAL RECEIPTS CARRIED FORWARD
TOTAL NET COMPOSITE BORROWING REQUIREMENT
Proposed Approved Proposed Proposed Approved Proposed Proposed Revised
Budget Budget Budget Budget Budget Budget Budget Budget
14-Sep-22 20-Apr-22 Adjustment 14-Sep-22 20-Apr-22 Adjustment 14-Sep-22
Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2025/26 2026/27 2026/27 2026/27 2027/28 2027/28 2027/28 TOTAL
(£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000) (£'000)
200 200 200 200 200 1,374
650 650 650 650 650 4,655
1,800 1,800 1,800 1,494 (600) 894 10,081
0 0 0 0 0 725
0 0 0 0 0 736
0 0 0 0 0 81
0 0 0 0 0 77
0 0 0 0 0 (77)
150 150 150 150 150 918
2,744 2,283 2,283 2,884 2,884 18,573
646 668 668 691 691 3,970
737 720 40 760 745 40 785 5,002
0 0 0 0 0 0
0 0 0 0 0 0
51 51 51 51 51 306
0 365 (365) 0 130 (130) 0 1,926
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 1,686
0 40 (40) 0 40 (40) 0 0
6,978 6,927 (365) 6,562 7,035 (730) 6,305 50,033
76,590 50,230 3,809 54,039 41,303 279 41,582 629,905
(12,279) (12,265) (12,265) (12,265) (12,265) (76,052)
(2,367) (2,600) (2,600) (2,600) (2,600) (13,516)
(250) (250) 0 (250) (250) 0 (250) (1,980)
(308) 0 0 0 0 0 0 (1,615)
0 0 0 0 0 0
(15,204) (15,115) 0 (15,115) (15,115) 0 (15,115) (93,163)
61,386 35,115 3,809 38,924 26,188 279 26,467 536,742
(2,093) (2,546) 145 (2,401) (2,546) 145 (2,401) (2,556)
2,401 2,546 (145) 2,401 2,546 (145) 2,401 2,401
61,694 35,115 3,809 38,924 26,188 279 26,467 536,587
Page 71 of 132

Page 72

Page 72 of 132

Page 73

Appendix III 
CROSS TAY LINK ROAD 
REVISED COST ANALYSIS REPORT 
1. PURPOSE
2. 
2.1 This Report has been prepared to provide an update on the costs associated
with the Cross Tay Link Road project, highlighting that the forecasted costs
exceed the current budget. This analysis indicates a worst case scenario cost
increase of £32.5 million above the overall budget of £118 million. 
3. STRUCTURE OF REPORT 
2.1 This report is structured over the following sections: 
• Section 3: Background
• Section 4: Revised Costing Analysis 
• Section 5: Risk Analysis
• Section 6: Conclusions
• Appendices:
- Appendix A: Revised Costing Analysis
- Appendix B: Principal Project Commodities (Inflation comparisons)
- Appendix C: QRA Model Summary 
3. BACKGROUND 
CROSS TAY LINK ROAD 
3.1 The Cross Tay Link Road (CTLR) has been a strategic priority of the Council
since 2008 and is a vital component of Shaping Perth’s Transport Future
Strategy which was approved by the Council in January 2012. This Strategy
forms four phases and is an integrated series of measures to support the
sustainable economic growth of the Perth and Kinross area, whilst also
addressing the major congestion and air quality issues in and around Perth. 
3.2 The four phases are:   
1. A9/A85 Junction Improvement and Link Road to Bertha Park 
2. Cross Tay Link Road (connecting the A9, A93 and A94); 
3. Bertha Park connection road (will be taken forward by the developer); and
4. Associated Perth city centre improvements.
6
Page 73 of 132

Page 74

3.3 Phase 1 was completed in 2019 and Phase 2, the CTLR, is underway. The
third phase is the link road from Bertha Park to the CTLR and the fourth phase
an ambitious programme of active travel initiatives in Perth (including the
rail/bus interchange).   
3.4 The CTLR is a key element of the Council’s statutory Development Plan
comprising the TAYplan Strategic Development Plan 2016-2036 and the Perth
and Kinross Local Development Plan 2 (2019). The adoption of the Local
Development Plan (LDP2) by the Council on 29 November 2019 was the
culmination of 4 years’ work, and was the result of an extensive consultation
process, an examination and Council resolutions. Delivery of the CTLR is
therefore central to the housing, employment and transport strategies for the
plan area and for the Perth Core Area. 
3.5 The infrastructure which is included in the CTLR project is listed below: 
• realignment of the A9 dual carriageway between Perth and Luncarty
• a grade separated junction on the A9
• a bridge spanning the Perth-Inverness railway line and River Tay
• a link road connecting the A9 to the North of Scone
• a green bridge at Highfield
• a wetland area at the Caravan Park
• new footways and cycle paths including links to existing routes, and
crossings
• a Park & Cycle facility. 
3.6 The preferred route for the CTLR was agreed by the Council in December
2016 (Report No. 16/560) and reaffirmed in respect of the eastern end in June
2019. As with any major roads infrastructure project, the route has been
subject to many years of detailed technical assessment and professional and
independent scrutiny. It follows the multi-stage process directed by both
legislation and Transport Scotland guidance and can be summarised as
follows:  
Page 74 of 132

Page 75

• Scottish Transport Appraisals Guidance (STAG) (2008);
• Strategic Environmental Assessment (2010/2011);
• Design Manual for Roads and Bridges (DMRB) Stage 1 Assessment (2011); 
• DMRB Stage 2 assessment and associated environmental assessment
(2012 – 2016); 
• Planning Application and Environmental Impact Assessment Report (Nov
2019); and
• DMRB Stage 3 assessment (April 2020). 
3.7 Planning consent (Ref: 19/01837/FLM) for the CTLR scheme was granted in
October 2020. 
3.8 All land required for the scheme has been acquired by the Council through
compulsory purchase. 
BUDGET 
3.9 The approved budget for the project, including for services, works, fees and
land, is £118 million.  The Council approved a Capital Budget of £78 million
for the Cross Tay Link Road in June 2016 (Report No. 16/277). The project
was included in the updated the Capital Budget 2020/21 - 2028/29  and
funding re-approved alongside a decision to proceed with the project (Report
20/175). 
3.10 The Scottish Government is contributing £40 million to the project as part of a
side deal negotiated as part of the Tay Cities Deal. The Grant Offer has been
finalised and the first payment of £5 million was received in early August
2022. It should also be noted that over time there will be developer
contributions towards the CTLR in excess of £17 million. 
CONTRACT 
3.11 The Procurement Strategy for the contract was approved by the Project Board
and signed off by Procurement and the Executive Sponsor in October 2019. In
accordance with that Strategy, the contract has been procured through a
staged tender process under Competitive Procedure with Negotiation in
accordance with The Public Contracts (Scotland) Regulations 2015. 
3.12 Following the decision to proceed with the project, tenders were returned on
19 April 2021 and following evaluation a Contract Award Report was prepared
and approved by the Project Board on 26 May 2021. 
3.13 In accordance with the approved Procurement Strategy (October 2019) the
contract for the Detailed Design and Construction of the CTLR is made up of
three stages: 
Page 75 of 132

Page 76

Stage
One 
Early Contractor
Involvement 
Preparation of the detailed design including
carrying out advance works that are necessary
to de-risk the main construction works  
Stage
Two
Construction  Main construction works including completion
of any outstanding detailed design.
Stage
Three
Landscaping
Management
and
Maintenance
(5 years) 
After completion of Stage Two the Contractor
automatically enters into a separate term
services contract for the management and
maintenance of the scheme landscaping. 
3.14 Following a robust procurement process through Public Contracts Scotland
the contract for Stage One was awarded to BAM Nuttall Ltd (BAM) and
commenced in August 2021. Stage Two is due to commence upon the
successful completion of Stage One. The current programme estimates
completion in Spring 2025. The total value of the contract is £94.5million. 
3.15 Due to the uncertainty surrounding COVID-19 and EU Exit at the time of
tender, the contract includes a clause to cover for the price to be adjusted for
inflation and uses the BCIS General Civil Engineering Cost Index to ensure
this is done fairly.  A clause to allow the price to be adjusted due to a change
in the law is also included. These clauses were included to ensure that the
contractors invited to tender did not inflate prices significantly to protect
themselves from risks associated with COVID-19 and EU Exit. Details of
these were contained in the Contract Award Report prior to contract award. 
3.16 The contract is a NEC 4 (Engineering and Construction Contract) Option C
Target Price where the Council only pays the actual cost of the work carried
out (known as Defined Cost under the contract) plus an agreed percentage
fee. Regular audits and assessments are carried out to ensure that the costs
paid are transparent and the percentage fee covers all the Contractor's
overheads and profit. At the end of the contract, the final cost is measured
against the Target Price which was agreed at contract award stage. The
Council and the Contractor share the difference between the End Defined
Cost and Target Price. In the event, that the costs exceed the Target Price
there is a capped limit on what the Council would need to share. 
3.17 Stage One of the contract is nearing completion with over 80% of the
deliverables successfully achieved. To avoid delay Stage Two will need to
commence immediately after the additional budget provision is confirmed. 
4. REVISED COSTING ANALYSIS 
4.1 As Stage Two of the contract approaches, a detailed costing analysis of the
full project has been undertaken with the costs and variances shown in the
table at Appendix A. The supporting narrative of this analysis has been
broken down into three sections: 
Page 76 of 132

Page 77

• Design and Build Works (BAM Contract)
• Contractors All Risk Insurance
• Quantitative Risk Assessment (Contingency)
• 
DESIGN AND BUILD WORKS (BAM CONTRACT) 
4.2 Changes in Law (National Insurance and Fuel Duty) 
4.2.1 At the time of contract award, it was known that the UK Government proposed
in April 2022 to abolish the tax exemption on red diesel. Under the contract
BAM are entitled to this cost adjustment which equates to £3.3 million. 
4.2.2 In April 2022 National Insurance contributions increased when the Health and
Social Care Levy came into effect in the UK. Similarly, under the contract BAM
are entitled to this cost adjustment of £0.3 million. 
4.3 Compensation Events (Change) 
4.3.1 Many construction contracts over the duration will be subject to changes for
various reasons. For example, changes to the design or specification and
unforeseen ground conditions. In this contract changes are called
Compensation Events (CEs). To date, only a small number of changes have
been implemented with an expected cost of around £1 million.  Over half of this
is attributed to the additional archaeological investigations required under the
project’s Written Scheme of Archaeology Investigation and overseen by Perth &
Kinross Heritage Trust. 
4.3.2 It should be noted that there will be changes throughout the duration of the
Stage Two contract and an analysis has been undertaken to provide a level of
cost contingence. The output from this analysis (Quantitative Risk Analysis), is
detailed later in this report. 
4.4 Inflation and Current Market Conditions 
4.4.1 BAM and the construction industry generally are continuing to experience an
adverse impact on prices and availability of construction materials and the
resulting steep rise in inflation. During the latter months of 2021, the principal
drivers affecting inflation were materials (cement, timber, steel and oil), but in
the first quarter of 2022 this impact has been exacerbated by significant price
rises in gas and the conflict in Ukraine. Market conditions are exceptional, and
the impact is global. 
4.4.2 The initial drivers of rising inflation, in the last half of 2021, were the increased
activity on projects as COVID-19 restrictions start easing and a shortfall in the
availability of materials because production had been reduced, to match
reduced demand, during the lockdown periods. The short-term view had been
that price rises and shortages would remain until Q4/21, but forecasts
suggested that supply would catch up with demand by Q3/22 and that
ongoing price/shortage impacts would ease. However, these forecasts have
been compromised by ever increasing gas and oil prices, the ongoing reduced
Page 77 of 132

Page 78

availability of materials and the global impact of the conflict in Ukraine.
Inflation forecasts for Q4/22 are currently +25% for some commodities such
as sheet piles, oil, fabricated steel, cement and copper which will have knock
on effects on the price of ready-mixed concrete, drainage products, steel
reinforcement, transport and plant. In addition to the global impact of supply
and demand on inflation, it is unlikely that the supply chain will be able to offer
fixed prices for goods and/or services for any meaningful length of time and it
is also evident that delivery periods have extended. 
4.4.3 During the Stage One contract, BAM has worked diligently to identify and
secure sub-contractors and suppliers through early procurement, with several
key sub-contracts in place for Stage Two providing a price fix. However, this is
not possible for all for all suppliers and materials with some unwilling to fix
price due to market volatility. 
4.4.4 In accordance with the contract there is a clause (X1) to cover for the overall
price to be adjusted for inflation and the BCIS General Civil Engineering Cost
Index is used to ensure this is done fairly. This has been calculated as a
forecast in BAM’s End Defined Cost as shown below. 
4.4.5 Under normal circumstances these indices would provide a reasonable
approach to inflation assessments. However, these are currently
disproportionately low when compared with actual market conditions. An
analysis of the principal project commodities has been undertaken to show
how these are influencing the Defined Cost. The graphs show the comparison
between the BCIS data, the general indices and actual market conditions and
are included at Appendix B. 
4.5 Value Engineering 
4.5.1  During the early stages of the Stage One contract BAM undertook a
substantial value engineering exercise to develop proposals to benefit the
project, principally in terms of costs savings and carbon reduction.  Eighteen
proposals were accepted providing a total cost saving of just over £5 million.
These are now being incorporated into the final detailed design. Unfortunately,
due to the steep rise in inflation, the cost benefit of this exercise anticipated at
tender will not be realised. 
4.6 Stage Two Earthworks 
4.6.1 Under the contract for BAM were able to submit a proposal to undertake
works identified in Stage Two during Stage One if it is beneficial to the
contract outcomes. A proposal to commence bulk earthworks in Stage One to
capture time in the 2022 earthworks season was subsequently put forward by
BAM and accepted. 
4.6.2 Bringing the earthworks forward to start in May 2022 has provided greater
programme and cost certainty. 
Page 78 of 132

Page 79

4.7 BAM’s End Defined Cost Forecast 
4.7.1 In accordance with the contract BAM are required to submit forecasts of their
End Defined Cost. This forecast takes account of the project cost, value
engineering, changes in law, CEs, sub-contractor and supplies secured,
contractor risks, inflation indices and assessment. This forecast has been
expressed as a range: 
• Minimum £108.9 million
• Expected £109.8 million
• Maximum £111.7 million 
4.7.2. Due to inflation and the current volatile market conditions as outlined in this
report, the Maximum End Forecast Defined Cost has been used in this
Revised Costing Analysis. 
CONTRACTORS ALL RISK INSURANCE 
4.8  At the time of tender BAM submitted a price of £2.217 million for this contract
insurance requirement. This was higher than the other tender submissions
and BAM were subsequently asked to obtain an alternative quotation. A
revised quotation is currently being reviewed by the Council’s insurance
broker. 
QUANTITATIVE RISK ASSESSMENT (CONTINGENCY) 
4.9 Turner & Townsend have been engaged to provide the Council with
commercial management support on the Stage One and Two contracts. This
has included working with the Council’s Project Team to undertake a complete
cost risk assessment, utilising Quantitative Risk Analysis (QRA) techniques.
This methodology incorporates assessments of the key sources of risk and
uncertainty associated with the project, with the purpose of ascertaining a
level of confidence in setting a contingency. 
4.10 The model output gives a contingency value of £16.9 million at industry
standard level (P80). This includes values for unknown events/risks (£3.6
million) and the cost of delay (£4.3 million). See table at Appendix C. 
4.11 Examples of the events and risks included in this model are unchartered
services, delays in securing consents (e.g. Network Rail and Transport
Scotland approvals), inflation, health and safety incidents, construction
defects, delays/insufficient resourcing by utility companies (e.g. Scottish
Water), adverse weather, major works interfaces and delays to design
approvals. 
4.12 The Project Risk Register is reviewed on a monthly basis, and it is the
intention to re-evaluate the QRA on a quarterly basis moving forward. 
Page 79 of 132

Page 80

5. RISK ANALYSIS 
5.1 The following analysis outlines the potential risks of not making an additional
provision of up to £32.5 million is made in the capital budget to provide cover
for the worse case scenario, resulting in the CTLR not proceeding. 
Strategic 
5.2 The strategic rationale for the project remains unchanged both in respect of
enabling the delivery of LDP2 in respect of enabling housing and employment
land; and mitigating long term road traffic congestion and poor air quality in
Perth City Centre. 
Legal 
5.3 The main risks at this stage of the project should the Council choose not to
proceed will primarily relate to a) the expenditure incurred to date and
breaching the Council’s statutory duty to secure best value; and b) the risk of
legal actions. 
5.4 An additional risk if the scheme does not go ahead is that the Council now
owns land it would not need, costing some £5.570 million (including
disturbance etc). 
5.5  The strategic housing land allocations set out in LDP2, as adopted by the
Council, cannot be delivered without the CTLR. During the examination
leading to the adoption of LDP2 assurance required to be given to the reporter
appointed by the Scottish Ministers that the Council was committed to funding
the CTLR.   The non-delivery of the proposal would impact on existing land
deals and investment decisions. Some of these will have been made in the
expectation the Council would deliver the infrastructure to which it had
committed in LDP2, with the potential for claims to be raised against the
Council. 
Finance 
5.6 Up to 31 March 2022 expenditure is £16.8million and the totally legally
committed expenditure to 30 June 2022 totals £23.5 million.   
5.7 There would be a loss of £40 million grant from the Scottish Government if
project stopped. £5 million of this has been received by the Council and would
therefore need to be returned. 
5.8 A proportion of CTLR expenditure is also being used as match funding for the
Sustrans cycle network project (the bridge will have a cycle lane). 
5.9 Inflation has been estimated in BAM’s End Defined Cost although this can
only remain a forecast until realised. 
Page 80 of 132

Page 81

5.10 There will be expenditure associated with reinstating the land which has now
been significantly impacted by the advance works and earthworks. This would
also include the replacement of woodland. The cost of this work is difficult to
estimate but the works would be extensive and likely to be several £ millions. 
Reputational 
5.11 The risks are magnified in terms of stopping the project given the expenditure
to date and the construction works already undertaken, particularly the bulk
earthworks and tree removal. 
5.12 The reputational risk of continuing with a more expensive scheme is mitigated
in the sense that the inflationary pressure is not unique to the CTLR as it is
now a widely recognised factor across the construction industry and beyond. 
5.13    The reputational risk of adopting a local development plan, for the 10 year
period to 2029, with a council commitment to delivering the CTLR as key
infrastructure for the delivery of required allocations of housing and
employment land based, but failing to deliver this infrastructure, is significant. 
6. CONCLUSIONS 
6.1 Expenditure to date on the project is £16.8million with a legally committed
total of £23.5 million. 
6.2 The current project costs as detailed in the table at Appendix A show that up
to an additional £32.5 million may be required to complete the project. The
reasons for the increased costs are outlined in this report. Primarily these are
due to the steep increase in inflation, changes in law and the inclusion of
Quantitative Risk Analysis contingency of £16.9 million. This QRA takes
cognisance of the contract type and potential costs associated with all known
risks. 
6.3 In order to proceed to Stage Two it is recommended that an additional
provision of up to £32.5 million is made in the capital budget to provide cover
for the worst case scenario. 
6.4 The contract for Stage Two is due to commence imminently and is needed to
enable the bridge pier cofferdam and major piling works to take place in and
adjacent to the River Tay. These are critical to the programme given the
seasonal constraints placed upon river works. It should also be noted that the
inflationary cost increase has no impact on BAM’s fee (and therefore profit)
which was fixed in their tender. 
6.5 In line with current governance arrangements further cost updates will be
reported regularly to the Finance and Resources Committee. 
Report by:   Jillian Ferguson, Roads Infrastructure Manager
Date:    31 August 2022
Subject: Cross Tay Link Road – Revised Costing Analysis
Responsible Officer: David Littlejohn, Head of Planning and Development
Page 81 of 132

Page 82

APPENDIX A 
Page 82 of 132

Page 83

APPENDIX B
Page 83 of 132

Page 84

Page 84 of 132

Page 85

Page 85 of 132

Page 86

APPENDIX C 
Page 86 of 132

Page 87

APPENDIX IV
Approved Actuals Proposed Approved Proposed Proposed Revised Actual Projected Approved Proposed Revised Approved Proposed Revised Approved Proposed Revised
Budget to Carry Budget Brought Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Budget Budget Budget
20-Apr-22 31-Mar-22 Forward 20-Apr-22 Forward Adjustment 31-Jul-22 20-Apr-22 Adjustment 20-Apr-22 Adjustment 20-Apr-22 Adjustment
to from Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2021/22 2021/22 2022/23 2022/23 2021/22 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25 2025/26 2025/26 2025/26
£'000 £'000 £'000 £'000 (£'000) £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Council House New Build Programme
Glebe, Scone - 65 Units 915 804 111 0 111 (90) 21 21 0 0 0 0 0 0   
Council Tax (Second Income) 0 0 0 0 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0 0 0 0 0
915 804 111 0 111 (90) 21 0 21 0 0 0 0 0 0 0 0 0
Milne Street, Perth - 8 Units 179 176 3 0 3 3 3 0 0 0 0 0 0   
Council Tax (Second Income) 0 0 0 0 0 0 0 0 0 0 0 0   
Third Party Contribution (Commuted Sums) 0 0 0 0 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0 0 0 0 0
179 176 3 0 3 0 3 0 3 0 0 0 0 0 0 0 0 0
Ardler Road, Meigle - 8 Units 4 4 0 0 0 0 0 0 0 0 0 0 0   
Council Tax (Second Income) 0 0 0 0 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0 0 0 0 0
4 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Huntingtower, Perth - 70 Units 650 648 2 0 2 2 2 0 0 0 0 0 0   
Council Tax (Second Income) 0 0 0 0 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0 0 0 0 0
650 648 2 0 2 0 2 0 2 0 0 0 0 0 0 0 0 0
Fairfield, Perth 360 383 (23) 2,676 (23) 2,653 564 2,653 0 0 0 0 0 0   
Council Tax (Second Income) 0 0 (360) 0 (360) (360) 0 0 0 0 0 0   
Scottish Government Subsidy (360) (364) 4 (656) 4 (652) (373) (652) 0 0 0 0 0 0
0 19 (19) 1,660 (19) 0 1,641 191 1,641 0 0 0 0 0 0 0 0 0
Blackthorne Place, Blairgowrie 0 (14) 14 0 14 (14) 0 0 0 0 0 0 0 0   
Council Tax (Second Income) 0 0 0 0 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0 0 0 0 0
0 (14) 14 0 14 (14) 0 0 0 0 0 0 0 0 0 0 0 0
Lynedoch Road, Methven 2 560 (558) 0 (558) 2,920 2,362 673 2,362 0 1,039 1,039 0 0 0 0   
Council Tax (Second Income) 0 0 0 0 (480) (480) (480) 0 0 0 0 0 0   
Scottish Government Subsidy 0 (569) 569 0 569 (1,643) (1,074) (672) (1,074) 0 0 0 0 0 0
2 (9) 11 0 11 797 808 1 808 0 1,039 1,039 0 0 0 0 0 0
Newburgh Road, Abernethy 1,195 2,169 (974) 188 (974) 1,200 414 226 414 0 0 0 0 0 0   
Council Tax (Second Income) (200) (200) 0 0 0 0 0 0 0 0 0 0 0 0   
Scottish Government Subsidy (401) (893) 492 0 492 (492) 0 0 0 0 0 0 0 0   
Capital Receipts 0 0 0 0 0 (708) (708) (3) (708) 0 0 0 0 0 0
594 1,076 (482) 188 (482) 0 (294) 223 (294) 0 0 0 0 0 0 0 0 0
Future Developments 0 28 (28) 5,525 (28) (1,746) 3,751 3,751 4,894 4,894 5,128 5,128 6,014 6,014   
Council Tax (Second Income) 0 0 0 0 0 0 0 0 0 0 0 0   
Scottish Government Subsidy 0 0 0 0 0 0 0 0 0 0 0 0
0 28 (28) 5,525 (28) (1,746) 3,751 0 3,751 4,894 0 4,894 5,128 0 5,128 6,014 0 6,014
Total Council House New Build 2,344 2,732 (388) 7,373 (388) (1,053) 5,932 415 5,932 4,894 1,039 5,933 5,128 0 5,128 6,014 0 6,014
Increase in Council House Stock
Council House Buy-Backs 3,435 3,989 (554) 2,802 (554) 1,050 3,298 1,365 3,298 3,000 1,050 4,050 3,000 3,000 3,000 3,000
Scottish Government Subsidy (1,120) (1,120) 0 0 0 (1,050) (1,050) (1,050) 0 (1,050) (1,050) 0 0 0 0
2,315 2,869 (554) 2,802 (554) 0 2,248 1,365 2,248 3,000 0 3,000 3,000 0 3,000 3,000 0 3,000
Lock-ups and Garage Sites 0 0 0 0 0 0 0 0 0 50 50 0 0
HRA CAPITAL INVESTMENT PROGRAMME
SUMMARY OF CAPITAL RESOURCES AND EXPENDITURE 2022/23 to 2026/27
PERTH AND KINROSS COUNCIL
6
Page 87 of 132

Page 88

APPENDIX IV
Approved Actuals Proposed Approved Proposed Proposed Revised Actual Projected Approved Proposed Revised Approved Proposed Revised Approved Proposed Revised
Budget to Carry Budget Brought Budget Budget to Outturn Budget Budget Budget Budget Budget Budget Budget Budget Budget
20-Apr-22 31-Mar-22 Forward 20-Apr-22 Forward Adjustment 31-Jul-22 20-Apr-22 Adjustment 20-Apr-22 Adjustment 20-Apr-22 Adjustment
to from Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1 Report 1
2021/22 2021/22 2022/23 2022/23 2021/22 2022/23 2022/23 2022/23 2022/23 2023/24 2023/24 2023/24 2024/25 2024/25 2024/25 2025/26 2025/26 2025/26
£'000 £'000 £'000 £'000 (£'000) £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
Standard Delivery Plan
Central Heating and Rewiring Works 1,240 1,216 24 0 24 840 864 176 864 0 0 0 0 0 0 
- less Third Party Contribution (435) (337) (98) 0 (98) 98 0 0 0 0 0 0 0 0
Rewiring, Infrastructure & Property Refurbishment 107 166 (59) 1,000 (59) 941 50 941 1,000 1,000 1,686 1,686 0 0
Triple Glazing 268 277 (9) 0 (9) 60 51 22 51 0 0 0 0 0 0
Controlled Door Entry 37 12 25 10 25 35 15 35 0 0 30 30 0 0 
- less Third Party Contribution 0 2 (2) 0 (2) (2) (2) 0 0 0 0 0 0
Kitchen Modernisation Programme 270 112 158 632 158 790 790 1,332 1,332 1,504 1,504 625 625
Bathroom Modernisation Programme 617 672 (55) 600 (55) 545 297 545 565 565 0 0 0 0
External Fabric 1,156 1,326 (170) 1,858 (170) 12 1,700 582 1,700 1,098 1,098 528 528 625 625 
- less Third Party Contribution 0 (12) 12 0 12 (12) 0 0 0 0 0 0 0 0
Energy Efficiency 535 287 248 83 248 331 8 331 0 0 875 875 625 625
Multi Storey Flats 331 41 290 2,000 290 2,290 5 2,290 0 0 0 0 0 0
Environmental Improvements 23 25 (2) 604 (2) 602 1 602 333 333 0 0 0 0
Fire Precaution Measures 1,733 1,659 74 0 74 250 324 154 324 0 0 0 0 0 0
Sound Insulation 5 6 (1) 141 (1) 140 140 162 162 100 100 42 42
Structural 0 0 0 438 0 (418) 20 20 458 458 250 250 104 418 522
SHQS Future Developments 0 0 0 0 0 0 0 0 0 0 0 8,960 (1,459) 7,501
Total Standard Delivery Plan 5,887 5,452 435 7,366 435 830 8,631 1,310 8,631 4,948 0 4,948 4,973 0 4,973 10,981 (1,041) 9,940
Other Investment in Council House Stock
Total Major Adaptations to Council House Stock 62 58 4 0 4 4 4 0 0 100 100 0 0
Balmoral Road, Rattray, Refurbishment (3 Units) 275 2 273 0 273 273 273 0 0 0 0 0 0
Anchor House, Rannoch Road, Perth - Conversion (5 Units) 123 14 109 0 109 109 109 0 0 0 0 0 0
149-151 Dunkeld Road, Perth 588 563 25 0 25 25 1 25 0 0 0 0 0 0 
- Government Grant (14) (14) 0 0 0 0 0 0 0 0 0 0 0
111 Rannoch Road, Perth (Former Driving Test Centre) 0 9 (9) 0 (9) 211 202 87 202 0 0 0 0 0 0
St.Catherine's Square Redevelopment 0 0 0 0 0 0 0 2,991 2,991 402 402 0 0
Shops & Offices 139 17 122 70 122 192 192 50 50 50 50 0 0
Greyfriars and Satellite Sites 0 0 0 34 0 34 34 0 0 50 50 0 0
Sheltered Housing 80 80 0 0 0 4 4 4 4 0 0 18 (4) 14 0 0
General Capital Works 37 20 17 0 17 14 31 4 31 0 0 0 0 0 0
Upgrade and Replacements to Lifts Programme 0 0 0 143 0 143 143 0 0 0 0 0 0
ICT Expenditure 182 54 128 50 128 178 178 50 50 50 50 0 0
Mortgage to Rent 0 0 0 125 0 125 125 50 50 50 50 0 0
Total Other Investment in Council House Stock 1,472 803 669 422 669 229 1,320 96 1,320 3,141 0 3,141 720 (4) 716 0 0 0
Total Net Expenditure 12,018 11,856 162 17,963 162 6 18,131 3,186 18,131 15,983 1,039 17,022 13,871 (4) 13,867 19,995 (1,041) 18,954
Income
CAPITAL RECEIPTS (112) (181) 69 0 69 (73) (4) (4) (4) 0 0 0 0 0 0
CFCR (2,147) (2,147) 0 (2,614) 0 156 (2,458) (2,458) (2,645) (2,645) (3,329) (3,329) (3,960) (3,960)
TOTAL BORROWING REQUIREMENT 9,759 9,528 231 15,349 231 89 15,669 3,182 15,669 13,338 1,039 14,377 10,542 (4) 10,538 16,035 (1,041) 14,994
Page 88 of 132

Page 89

APPENDIX IV
Approved Proposed Revised Revised
Budget Budget Budget Budget
20-Apr-22 Adjustment
Report 1 Report 1 Report 1
2026/27 2026/27 2026/27 TOTAL
£'000 £'000 £'000 £'000
0 0 21
0 0 0
0 0 0
0 0 0 21
0 0 3
0 0 0
0 0 0
0 0 0
0 0 0 3
0 0 0
0 0 0
0 0 0
0 0 0 0
0 0 2
0 0 0
0 0 0
0 0 0 2
0 0 2,653
0 0 (360)
0 0 (652)
0 0 0 1,641
0 0 0
0 0 0
0 0 0
0 0 0 0
0 0 3,401
0 0 (480)
0 0 (1,074)
0 0 0 1,847
0 0 414
0 0 0
0 0 0
0 0 (708)
0 0 0 (294)
3,014 3,014 22,801
0 0 0
0 0 0
3,014 0 3,014 22,801
3,014 0 3,014 26,021
3,000 3,000 16,348
0 0 (2,100)
3,000 0 3,000 14,248
0 0 50
Page 89 of 132

Page 90

APPENDIX IV
Approved Proposed Revised Revised
Budget Budget Budget Budget
20-Apr-22 Adjustment
Report 1 Report 1 Report 1
2026/27 2026/27 2026/27 TOTAL
£'000 £'000 £'000 £'000
0 0 864
0 0 0
0 0 3,627
0 0 51
0 0 65
0 0 (2)
0 0 4,251
0 0 1,110
0 0 3,951
0 0 0
0 0 1,831
0 0 2,290
0 0 935
0 0 324
0 0 444
0 0 1,250
10,030 10,030 17,531
10,030 0 10,030 38,522
0 0 104
0 0 273
0 0 109
0 0 25
0 0 0
0 0 202
0 0 3,393
0 0 292
0 0 84
0 0 18
0 0 31
0 0 143
0 0 278
0 0 225
0 0 0 5,177
16,044 0 16,044 84,018
0 0 (4)
(4,279) (4,279) (16,671)
11,765 0 11,765 67,343
Page 90 of 132

Page 91

PERTH AND KINROSS COUNCIL 
Finance & Resources Committee 
7 September 2022 
TREASURY ACTIVITY AND COMPLIANCE REPORT
2022/23 QUARTER 1 
Report by Head of Finance
(Report No. 22/210) 
1. PURPOSE 
1.1 The purpose of this report is to update the Committee on Treasury Activity for
the quarter ending 30 June 2022 and to report on compliance with the
Council’s Treasury Management Policy Statement (TMPS); Investment
Strategy and Prudential Indicators. The report also sets out proposed
amendments to the Temporary Loans policy and Empty Homes Loans Fund
policy. 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee: 
(i) notes the content of this report, 
(ii) approves the amendment to the Temporary Loans Policy, detailed at
Section 8 of this report, 
(iii) approves the amendment to the Empty Homes Loans Fund policy,
detailed at Section 9 of this report. 
3. ECONOMIC BACKGROUND 
3.1 The Bank of England’s Monetary Policy Committee (MPC) increased the UK
Bank Base Rate over the quarter from 0.75% to 1% at its meeting on 5 May
2022, and then from 1% to 1.25% at its meeting on 16 June 2022. The
increases in the Bank Base Rate were mainly in response to continuing rising
inflation, as increased energy and food costs, as well as the economic impact
of the conflict in Ukraine continued. UK Gross Domestic Product (GDP)
increased by 0.8% over the quarter to March 2022, however the rate of
growth has slowed in recent months. 
3.2 Subsequently, at its meeting on 4 August 2022, the MPC increased the Bank
Base Rate further by 0.5% to 1.75%. This was as a result of an increase in
inflation expectations, which has been rising faster than previously forecast,
and was now expected to reach 13% by the end of the year. The MPC also
projected the UK would enter recession by the end of the year and for inflation
to remain at elevated levels over most of next year. They also advised that
future changes in the Bank Base Rate would reflect the prevailing economic
outlook and inflation data and pressures. Many economic forecasts are now
7
Page 91 of 132

Page 92

projecting the Bank Base Rate to increase to around 4% by the end of next
year. 
3.3 Internationally, Europe and the US also showed a continued rise in inflation
due to similar factors affecting the UK. 
3.4 The Public Works Loan Board’s (PWLB) certainty fixed interest rates for the
quarter, which are based on yields on UK gilts, are shown in the graph in
Appendix I. PWLB borrowing rates showed significant volatility over the
quarter due to the conflict in Ukraine and inflationary pressures. In addition,
the impact of the base rate increases and increasing inflationary expectations
increased rates over the quarter in all durations. 
4.  TREASURY ACTIVITY 
4.1 A summary of the Council’s treasury position and transactions is shown in
Appendix II. The main activities are detailed below. 
4.2 During the quarter there was no new long-term PWLB borrowing undertaken,
whilst there was the repayment of one maturing PWLB fixed-rate loan of £5
million at 2.97% which had been borrowed for 10 years. 
4.3 Over the quarter the Council’s total long-term debt decreased from £611.3
million at an average interest rate of 2.57% to £606.3 million at an average
interest rate of 2.56%. There was one short-term loan borrowed in the quarter
to manage daily cashflows over the end of the quarter, for £8 million at 1.10%
for 3 weeks. 
4.4 Common Good and Charitable Fund balances held on fixed deposit within the
Loans Fund remained at £2.169 million, with the average interest rate paid
remaining at 1.05%. Funds held from associated bodies and organisations
increased from £2.983 million to £3.767 million over the quarter, in line with
their own cash flow requirements, whilst the average rate paid on these funds
decreased from 0.20 to 0.18% in accordance with the approved Temporary
Loan policy. 
4.5 Short term cashflow surpluses are invested in a mixture of fixed term
deposits, instant access accounts, notice accounts and money market funds.
All investments were made in accordance with the approved Investment
Strategy and permitted Investments. 
Fixed Term Deposits 
4.6 Cashflow surpluses which arise during the year and which are not
immediately required are generally invested in fixed term deposits for periods
of up to 12 months, or up to 3 years where forecast cashflow requirements
allow. 
4.7 There were 12 fixed rate deposits made in the quarter (totalling £62.5 million)
for an average amount of £5.2million each and at an average interest rate of
1.98% for an average term of 272 days. Fixed deposit activity in the current
quarter was therefore lower than the previous quarter to 31 March (£117
Page 92 of 132

Page 93

million). With interest rate increases anticipated, deposits were initially made
in shorter durations with a view to re-investing some funds as rates increase.
Interest rates increased over the quarter in line with the Bank Base Rate and
with expectations of further increased over the next few months.
Subsequently, with the increase in interest rates, longer duration deposits
were undertaken for up to 12 months. Deposits in the quarter will generate
almost £1 million in interest at their maturity. 
Investments for Daily Cashflow Requirements  
4.8 Cashflow surpluses which are required for more immediate needs are
invested in the Council’s instant access, notice deposit accounts and money
market funds. These investment transactions in the quarter can be
summarised as follows: 
• The daily average amount of such funds over the quarter increased
from £5.7million in the last quarter to £6.37 million in the current
quarter.
• The average interest rate achieved on these accounts over the quarter
increased from 0.27% to 0.79% reflecting the increase in base rate.
• Due to their relatively low rates, the only activity in notice accounts
related to existing balances where notice had previously been given, to
be re-invested in alternative investments. 
• Instant access facilities were used over the quarter to meet day-to-day
cashflow requirements. However, the interest rate on such facilities
remains low at 0.10%.
• Interest generated on these investments over the quarter amounted to
almost £58,000 
4.9 The total amount of investments outstanding at 30 June 2022 was £246.8
million compared to £252 million at the end of the previous quarter in March
2022. The overall average rate of interest on the investments outstanding
increased from 0.88% at the end of the previous quarter to 1.30% at the end
of the current quarter. This increase reflects the increases in base rates over
the quarter. 
4.10 Total investment income generated on the investments undertaken during the
quarter is £1,057,115 (£1,105,813 in the quarter ended 31 March 2022). This
measure reflects the total return on the investment activity undertaken in each
quarter and is only slightly lower in the current quarter compared to last
quarter despite the reduced activity, due to the increased interest rates. 
4.11 All of the above investment activities are consistent with the Council’s current  
investment strategy and cashflow requirements. 
5. COMPLIANCE  
5.1  For the quarter ending 30 June 2022, there were no breaches in compliance
with the Council’s approved Treasury Management Policy Statement,
Treasury Management Practices (TMP’s) or lending limits as detailed in TMP
4 (Approved Instruments, Methods & Techniques).
Page 93 of 132

Page 94

5.2 Appendix III shows the list of approved counterparties, based on the Council’s
current lending policy, as at July 2022.  
5.3  For the quarter ending 30 June 2022 the average closing cleared bank
balance was £35,000 in credit. This reflects the daily target balance applied by
the Council’s “sweep facility” applied by the bank, with any credit balance in
excess of £35,000 being “swept up” overnight to the Council’s instant access
account. 
6. INVESTMENT STRATEGY COMPLIANCE AND PERFORMANCE  
6.1  The Treasury Investment Strategy for 2022/23 was approved by the Council
at its meeting on 9 March 2022 (report 22/47 refers).  
6.2  In the current quarter the level of Council investments peaked at £269.204
million on 13 April 2022 and reduced to £246.774 million by the end of the
quarter. The average daily investment balance over the quarter was £256.348
million, which decreased from an average of £262.917 million in the previous
quarter and increased from £228.988 million in the same quarter of last year. 
6.3  Due to the Council taking long-term borrowing of £90 million in November and
December last year the investment balances in the current year are higher.
However, this is gradually reducing (subject to daily fluctuations) over the next
few years as the Capital programme accelerates, and in line with forecast
cashflows.  
6.4  The Investment Strategy was applied in full over the quarter, with liquidity
being maintained using instant access accounts and money market funds as
detailed in paragraph 4.8 above. There were no other risks identified in the
quarter.   
6.5  The Investment Strategy also incorporates investments held by the Common
Good Funds. All such investments during the quarter were with the Council’s
Loans Fund. The only Council funds held by external fund managers relate to
Council administered Charitable Trusts and are, therefore, not covered by this
Investment Strategy. 
6.6  The budgeted income in 2022/23 for Commercial Property investments is
£1,812,000 whilst the latest projection for the year is £1,861,000. There were
no new property investments entered into during the quarter.  
7. PRUDENTIAL INDICATORS  
7.1 Revised Prudential Indicators for 2022/23 to 2027/28 were approved by the
Council at the meeting on 9 March 2022 (report 22/47 refers) as part of the
Annual Treasury & Investment Strategy report.  
7.2 The latest estimates of the Prudential Indicators, in line with the Council’s
current approved Capital Budget and Capital Financing (borrowing)
requirements, are shown in Appendix IV. These show that the Council
adhered to all Prudential limits in the quarter, and that the Council’s plans
remain prudent, affordable and sustainable.
Page 94 of 132

Page 95

8. PROPOSED REVISED LOCAL TEMPORARY LOANS POLICY 
8.1 The Council offers the facility for several associated bodies to deposit money
with the Council which is managed as part of the overall Treasury activity.
These deposits are referred to as “temporary loans” to the Council. At
present, the Council holds funds on behalf of TACTRAN and Culture Perth &
Kinross amongst others. The current policy for local Temporary Loans was
devised around 20 years ago, when the Bank base rates averaged around 4
to 5% and is based on a formula of base rate less various percentage points
depending on the size of the balance of the temporary loan. The policy was
subsequently updated when the base rate fell to below 3% in December 2008
to accommodate lower levels of base rate in order to avoid negative interest
rates. 
8.2 The base rate has remained below these levels ever since, and even with the
current increases in the base rate, they are not projected to rise to the levels
experienced in the past. Therefore, it is considered that the current policy is
no longer fit for purpose, particularly given the low level of rates produced with
the current formula. 
8.3 It is therefore proposed to amend the formula within the Temporary Loan
policy as follows: 
Loans of £1,000,000 or more: Rate – 0.5% below Bank Base Rate 
Loans of £250,000 or more but less than £1,000,000: Rate – 0.75% below Bank
Base Rate 
Loans of £50,000 or more but less than £250,000: Rate – 1.0% below Bank
Base Rate 
Loans of less than £50,000: No new deposit can be accepted which is less than
£50,000. Any existing deposit whose balance falls below £50,000 will receive
interest at Bank Base Rate less 1.10%. For the avoidance of doubt, the rate
offered will never be less than 0% should the Bank Base Rate fall to 1.10% or
less. 
8.4 Interest on temporary loans are paid half-yearly on 31 March and
30 September each year. It is therefore further proposed that the revised
policy outlined above be introduced with effect from 1 October 2022. 
8.5 For comparison, current and proposed local Temporary Loan rates are
summarised in the table below: 
Balance Current Rate Proposed Rate   
£1,000,000+ 0.25% 1.25%
£250,000 to £1M 0.10% 1.00%
50,000 to £250,000 0.10% 0.75%
less than £50,000 0.10% 0.65% 
Page 95 of 132

Page 96

9. PROPOSED AMENDMENT TO THE EMPTY HOMES LOANS FUND
POLICY 
9.1 The policy and criteria for the Empty Homes Loan Fund was approved by the
Council in October 2015 (report 15/413 refers), and subsequently amended in
April 2017 (report 17/174 refers). The fund was established following the
receipt of an interest free loan of £350,000 from the Scottish Government,
with the purpose of being lent out as interest free loans to property owners in
order that they can bring unoccupied properties back into use. The properties
are then let as affordable homes at local housing allowance rent levels set by
the Scottish Government. Under the existing policy, the loans are secured on
the property in question; the maximum loan amount per property is £20,000
for an individual property, with larger projects considered on a case by case
basis; owners are required to bring the property up to a Council approved
lettable “repairing standard” and to then make the property available for letting
or sale at affordable levels. 
9.2 To date the scheme has proved successful, with 4 individual loans given out
totalling £330,000, and providing an additional 14 properties to let in the Perth
& Kinross area. A further application for funding has been received, as well as
further expressions of interest in the scheme from the owners of other
unoccupied properties. However, as there is only £20,000 of the original
amount remaining in the Fund, the Council would only be able to offer limited
support. 
9.3 It is therefore proposed to operate the fund on a rolling basis, with repayments
from existing loans being made available to be re-lent to subsequent
applications. The balance outstanding on the current loans is £215,000, which
would therefore mean that £135,000 would currently be available to lend
under the scheme. The total repayments on the current loans are around
£4,000 per month at present, and to date there have been no repayment
defaults. It is not proposed to make any changes to the criteria for approving
loans under the scheme, and therefore delegated authority for approving
loans would remain with the Executive Director (Communities). 
10. CONCLUSION AND RECOMMENDATIONS 
10.1 The Bank of England’s MPC increased the Bank Base Rate from 0.75% to
1.25% over the quarter due to continued inflationary pressures. PWLB
borrowing rates were volatile over the quarter due to the continued inflationary
expectations and economic growth prospects. All borrowing durations
increased in rate over the quarter. There was no new PWLB borrowing
undertaken, whilst there was one loan repaid at maturity. 
10.2  Investment activity in the quarter consisted of the use of instant access and
money market funds to meet short term liquidity requirements, and use of fixed
rate deposits as rates improved with the increases to Base rate. Investment
activity and the total level of investments reduced over the quarter. 
Page 96 of 132

Page 97

10.3  The Council adhered to its Investment Strategy and policies throughout the
quarter, with no breaches in compliance. However, it is proposed to amend
the policy for local Temporary Loans with the Council to fit with current levels
of interest rates, and to extend the operation of the Empty Homes Loans
Fund. 
10.4  The Council’s Prudential Indicators were also adhered to throughout the
quarter, and the Council’s plans remain prudent, affordable and sustainable.   
Author(s)
Name  Designation Contact Details 
John Jennings  Senior Accountant  CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date 
Stewart MacKenzie 
Karen Donaldson 
Head of Finance 
Chief Operating Officer 
24 August 2022 
24 August 2022 
Page 97 of 132

Page 98

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION  
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2018 – 2023 lays out five outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
1.2 This report relates to all these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report. 
Workforce 
2.2 There are no direct workforce implications arising from this report.
Page 98 of 132

Page 99

Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions.   
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
4.1 The Chief Executive and the Council’s Treasury advisors, Link Asset
Services, have been consulted in the preparation of this report.   
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above
report.
Page 99 of 132

Page 100

3. APPENDICES 
• Appendix I – PWLB Fixed Maturity Interest Rates from 1 April to
30 June 2022.
• Appendix II – Summary of the Treasury Position and Transactions from
1 April to 30 June 2022.
• Appendix III – Approved Investment Counterparty List.
• Appendix IV – Monitoring of Prudential Indicators – Quarter ending
30 June 2022.
Page 100 of 132

Page 101

PWLB Fixed Maturity Interest Rates
From 1st April to 30th June 2022
(Certainty Rate)
APPENDIX  I
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
01-Apr-22
08-Apr-22
15-Apr-22
22-Apr-22
29-Apr-22
06-May-22
13-May-22
20-May-22
27-May-22
03-Jun-22
10-Jun-22
17-Jun-22
24-Jun-22
1 Year
5 Years
10 Years
20 Years
30 Years
50 Years
7
Page 101 of 132

Page 102

Page 102 of 132

Page 103

SUMMARY OF THE TREASURY POSITION AND TRANSACTIONS
1 APRIL TO 30 JUNE 2022
APPENDIX II
1 LONG TERM BORROWING
(a) Long Term Borrowing 1st April to 30th June 2022
Average Average Amount
No. Rate (%) Life (years) (£)
None 0 0.00% 0.00 0
0 0.00% 0.0 0
(b) Long Term Debt Repayments 1st April to 30th June 2022
Average Amount
No. Rate (%) (£)
PWLB - Maturity Loan - Scheduled Repayments 1 2.97% 5,000,000
1 2.97% 5,000,000
(c) Long Term Debt Outstanding
Outstanding Average Outstanding Average
31-Mar-22 Rate 30-Jun-22 Rate
£ £
Public Works Loan Board 568,000,000 2.41% 563,000,000 2.41%
Money Market Loans (LOBO's) 43,200,000 4.59% 43,200,000 4.59%
Other Long Term Debt 140,000 0.00% 140,000 0.00%
TOTAL 611,340,000 2.57% 606,340,000 2.56%
2 SHORT TERM BORROWING
(a) Short Term Market Borrowing - 1st April to 30th June 2022
Average Average Average Interest
No. Amount (£) Rate (%) Term (Days) (£)
Temporary Borrowing 1 8,000,000 1.10% 21 5,063.01
1 8,000,000 1.10% 21 5,063.01
(b) Short Term Borrowing Outstanding
Outstanding Average Outstanding Average
31-Mar-22 Rate 30-Jun-22 Rate
£ £
Market Borrowing 0 0.00% 8,000,000 1.10%
Common Good and Charitable Funds 2,169,254 1.05% 2,169,272 1.05%
Local Trusts & Investors 2,983,512 0.20% 3,766,980 0.18%
TOTAL 5,152,766 0.56% 13,936,252 0.84%
7
Page 103 of 132

Page 104

SUMMARY OF THE TREASURY POSITION AND TRANSACTIONS
1 APRIL TO 30 JUNE 2022
APPENDIX II
3 INVESTMENTS
(a) Investment Transactions - 1st April to 30th June 2022
Average Average Average Total
Fixed Deposits & Investments No. Amount (£) Rate (%) Term (Days) Interest (£)
Banks 7 5,714,286 2.19% 309 778,021.92
Foreign Banks and Institutions 5 4,500,000 1.61% 207 221,203.56
None
12 5,208,333 1.98% 272 999,225.48
Average Average Total
Instant/Notice Accounts & Money Market Funds Amount (£) Rate (%) Interest (£)
Instant Access/Notice accounts 965,117 0.42% 29,573.16
Money Market Funds 10,668,391 0.82% 28,316.09
6,376,558 0.79% 57,889.25
(b) Investments Outstanding Outstanding Average Outstanding Average
31-Mar-22 Rate 30-Jun-22 Rate
£ £
UK Banks 115,035,371 0.74% 125,024,462 1.29%
Foreign Banks and Institutions 92,000,000 1.15% 86,500,000 1.53%
Money Market Funds 0 0.00% 250,000 1.11%
Other Local Authorities 45,000,000 0.71% 35,000,000 0.75%
TOTAL 252,035,371 0.88% 246,774,462 1.30%
Page 104 of 132

Page 105

APPROVED INVESTMENT COUNTERPARTY LIST APPENDIX III
Fitch Credit CDS Maximum
Country Rating Range Lending Note (2)
Category 1 - Principal UK Clearing Banks  -  40% Investment total (or £20M per Counterparty if higher)
(Minimum rating required Fitch A, F1)
Bank of Scotland (RFB) (5) UK A+, F1 In range 6 months £80million Group limit
Barclays Bank plc (NRFB) (5) UK A+, F1 No data 6 months
Barclays Bank plc (RFB) (5) UK A+, F1 In range 6 months
Goldman Sachs International Bank UK A+, F1 In range 6 months
Handelsbanken plc UK AA, F1+ No data 12 months
HSBC Bank plc (NRFB) UK AA-, F1+ In range 12 months
HSBC Bank plc (RFB) UK AA-, F1+ No data 12 months
Lloyds Bank Corporate Markets Plc (NRFB) UK A+, F1 No data 6 months £80million Group limit
Lloyds Banking Group plc (RFB) UK A+, F1 In range 6 months £80million Group limit
NatWest Markets Plc (NRFB) UK A+, F1 In range 12 months
Royal Bank of Scotland plc (RFB) (inc Nat West) (3) (4) UK A+, F1 Nationalised 12 months Sovereign Rating AA
Santander UK plc (inc Cater Allen) UK A+, F1 No data 6 months
Standard Chartered Bank UK A+, F1 In range 6 months
Sumitomo Mitsui Banking Corporation Europe Ltd UK A, F1 In range 6 months
Category 2 - Foreign Banks & Institutions -  25% Investment total (or £10M per Counterparty if higher)
(Minimum rating required Fitch A, F1)
Australia and New Zealand (ANZ) Banking Group Ltd Aus A+, F1+ In range 12 months
Commonwealth Bank of Australia Aus A+, F1+ In range 12 months
Macquarie Bank Ltd Aus A, F1 No data 6 months
National Australia Bank Ltd Aus A+, F1+ In range 12 months
Westpac Banking Corporation Aus A+, F1+ In range 12 months
BNP Paribas Fortis Bank Belgium A+, F1 No data 1 month Sovereign Rating AA-
KBC Bank Belgium A+, F1 No data 1 month Sovereign Rating AA-
Bank of Montreal Can AA-, F1+ No data 12 months
Bank of Nova Scotia Can AA-, F1+ No data 12 months
Canadian Imperial Bank of Commerce Can AA-, F1+ No data 12 months
National Bank of Canada Can A+, F1 No data 6 months
Royal Bank of Canada Can AA, F1+ No data 12 months
Toronto Dominion Bank Can AA-, F1+ No data 12 months
Danske Bank Denmark A, F1 In range 6 months
Nordea Bank Finland plc Finland AA-, F1+ No data 1 month Sovereign Rating AA+
BNP Paribas France A+, F1 In range 1 month Sovereign Rating AA
Credit Agricole Corporate and Investment Bank France A+, F1 In range 1 month Sovereign Rating AA
Credit Agricole SA France A+, F1 In range 1 month Sovereign Rating AA
Credit Industriel et Commercial France A+, F1 No data 1 month Sovereign Rating AA
DZ Bank AG Germany AA-, F1+ No data 12 months
Landesbank Hessen-Thueringen Girozentral (Helaba) Germany A+, F1+ In range 12 months
Landwirtschaftliche Rentenbank Germany AAA, F1+ No data 24 months
NRW Bank Germany AAA, F1+ No data 24 months
ABN AMRO Bank Netherlands A, F1 No data 6 months
Bank Nederlandse Germeenten Netherlands AAA, F1+ No data 24 months
Cooperatieve Rabobank Netherlands A+, F1+ In range 12 Months
ING Bank Netherlands AA-, F1+ In range 12 Months
DBS Bank Limited Singapore AA-, F1+ No data 12 months
United Overseas Bank Ltd Singapore AA-, F1+ No data 12 months
Skandinaviska Enskilda Banken AB Sweden AA-, F1+ No data 12 months
Svenska Handelsbanken AB Sweden AA, F1+ No data 12 months
Swedbank AB Sweden A+, F1 No data 12 months
UBS AG Switzerland AA-, F1+ In range 12 months
Bank of America, NA USA AA-, F1+ No data 12 months
Bank of New York Mellon USA AA, F1+ No data 24 months
Citibank, NA USA A+, F1 In range 12 months
JP Morgan Chase Bank, NA USA AA, F1+ No data 12 months
Wells Fargo Bank, NA USA AA-, F1+ In range 12 months
7
Page 105 of 132

Page 106

APPROVED INVESTMENT COUNTERPARTY LIST APPENDIX III
Category 3 - Subsidiary Banks & Building Societies - 15% of Investment total (or £10M per Counterparty if higher)
(Minimum rating required Fitch A, F1)
(parent bank shown in brackets)
Subsidiary Banks
None
Building Societies
Nationwide Building Society UK A, F1 No data 6 months
Category 4 - Other Local Authorities - 20% of Investment total (or £20M per Counterparty if higher)
As arranged
Category 5 Money Market Funds - 10% of Investment Total (or £10M per Counterparty if higher)
(Minimum rating required Fitch AAA)
Aberdeen Standard Investments UK AAA
Aviva Investors Liquidity Fund UK AAA
Federated Sterling Liquidity Fund (Class 3) UK AAA
Insight Sterling Liquidity Fund (Class 5) UK AAA
Deutsche Bank Sterling Fund UK AAA
Note:
(1) - Standard & Poor's credit ratings shown, as no Fitch credit rating available
(2) - All Soveriegn credit ratings for above Countries are AAA, unless stated otherwise.
(3) - Banks are part/majority owned by the UK government
(4) - UK Sovereign Rating is AA (Fitch and Standard & Poor's)
Last Updated: 29-Jul-22(5) -  NRFB = Non Ring Fenced Bank,  RFB = Ring Fenced Bank
Page 106 of 132

Page 107

PERTH AND KINROSS COUNCIL
PRUDENTIAL INDICATORS - QUARTER ENDING 30 JUNE 2022
APPENDIX IV
1 Financing Costs:Net Revenue Stream
The ratio of Capital Financing Costs (Loan Charges) to the Council's net revenue stream shall not exceed the following limits, which are based on historic levels, and allow some headroom
for movement in interest rates. The estimated Financing Costs below are based on the latest monitoring figures.
2022/23 2023/24 2024/25 2025/26 2026/27 2027/28
Prudential Limit - General Fund 15.00% 15.00% 15.00% 15.00% 15.00% 15.00%
Estimated Ratio of Financing Costs to Revenue 6.83% 7.39% 8.27% 8.89% 9.15% 9.03%
Prudential Limit - HRA 30.00% 30.00% 30.00% 30.00% 30.00% 30.00%
Estimated Ratio of Financing Costs to Revenue 21.44% 23.21% 23.04% 22.36% 22.24% 22.45%
2 Gross & Net Borrowing and Capital Financing Requirements
For prudence, net external borrowing must not exceed the total capital financing requirement, thus ensuring that over the medium term, borrowing is only undertaken for capital purposes.
The estimated total net borrowing and Capital Financing Requirement at the end of each of the years are as follows:
Actual as at Projected Projected Projected Projected Projected Projected
30-Jun-22 31-Mar-23 31-Mar-24 31-Mar-25 31-Mar-26 31-Mar-27 31-Mar-28
Net External Borrowing* 499,227,000 580,136,000 804,214,000 950,431,000 1,029,949,000 1,074,466,000 1,104,709,000
Gross External Borrowing* 746,001,000 730,136,000 874,214,000 1,000,431,000 1,079,949,000 1,124,466,000 1,154,709,000
Capital Financing Requirement 653,019,000 747,361,000 893,876,000 1,018,575,000 1,098,272,000 1,144,056,000 1,175,930,000
*For the purpose of this indicator, Borrowing includes the outstanding liability under PPP/PFI contracts.
3 Estimates of Gross Capital Expenditure
The total estimated Capital Expenditure contained within the Council's Budgets for each year is as follows, based on updated monitoring figures.
Composite Programme 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28
Current estimate 163,988,000 171,930,000 137,333,000 83,294,000 58,519,000 46,128,000
Original Budget Estimate (including Budget Motion) 176,562,000 173,493,000 126,749,000 61,376,000 52,519,000 43,737,000
Movement in Estimated Capital Expenditure (12,574,000) (1,563,000) 10,584,000 21,918,000 6,000,000 2,391,000
The Original Budget Estimates are those per the 2022/23 to 2027/28 Composite Capital Budget Report on 23 February 2022
The latest estimates for Capital Expenditure are based on the F&R Capital Monitoring Report No 1 on 7 September 2022.
HRA Programme 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28
Current estimate 18,131,000 17,022,000 13,867,000 18,954,000 16,044,000 16,500,000
Original Budget Estimate 17,299,000 15,983,000 13,886,000 20,085,000 16,044,000 16,500,000
Movement in Estimated Capital Expenditure 832,000 1,039,000 (19,000) (1,131,000) 0 0
The Original Budget Estimates are those per the 2020/21 Housing & Communities Budget Report on 24 January 2022.
The latest estimates for Capital Expenditure are based on the F&R Capital Monitoring Report No 1 on 7 September 2022.
7
Page 107 of 132

Page 108

PERTH AND KINROSS COUNCIL
PRUDENTIAL INDICATORS - QUARTER ENDING 30 JUNE 2022
APPENDIX IV
4 Estimate of Capital Financing Requirement
The estimate (as at JUly 2022) of the Capital Financing Requirement (ie new borrowing requirement for Capital Expenditure) for each year based on these plans is as follows:
Composite Programme 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28
Current Estimated Capital Financing Requirement 123,419,000 137,855,000 115,359,000 61,499,000 38,804,000 26,458,000
Original Budget Estimate (including Budget Motion) 140,264,000 137,906,000 106,775,000 41,581,000 34,804,000 26,067,000
Movement in Estimated Capital Financing Requirement (16,845,000) (51,000) 8,584,000 19,918,000 4,000,000 391,000
The Original Budget Estimates are those per the 2022/23 to 2027/28 Composite Capital Budget Report on 23 February 2022
The latest estimates for Capital Expenditure are based on the F&R Capital Monitoring Report No 1 on 7 September 2022.
HRA Programme 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28
Current Estimated Capital Financing Requirement 15,673,000 14,377,000 10,538,000 14,994,000 11,765,000 12,000,000
Original Budget Estimate 14,685,000 13,338,000 10,557,000 16,125,000 11,765,000 12,000,000
Movement in Estimated Capital Financing Requirement 988,000 1,039,000 (19,000) (1,131,000) 0 0
The Original Budget Estimates are those per the 2020/21 Housing & Communities Budget Report on 24 January 2022.
The latest estimates for Capital Expenditure are based on the F&R Capital Monitoring Report No 1 on 7 September 2022.
5 External Debt (Gross and Net)
As at Projected Projected Projected Projected Projected Projected
External Borrowing 30-Jun-22 31-Mar-23 31-Mar-24 31-Mar-25 31-Mar-26 31-Mar-27 31-Mar-28
Public Works Loan Board 563,000,000 560,000,000 710,000,000 842,000,000 927,000,000 977,000,000 1,012,000,000
Market Bonds (LOBOs) 43,200,000 43,200,000 43,200,000 43,200,000 43,200,000 43,200,000 43,200,000
Project Borrowing 140,000 140,000 0 0 0 0 0
Special Loans 2,169,272 2,169,272 2,169,272 2,169,272 2,169,272 2,169,272 2,169,272
Temporary Loans/Other Borrowing 11,766,980 3,300,000 3,000,000 2,700,000 2,700,000 2,700,000 2,700,000
Other Long Term Liabilities (PPP/PFI) 125,724,977 121,326,977 115,844,477 110,361,977 104,879,477 99,396,977 94,639,577
Total Gross External Debt 746,001,229 730,136,249 874,213,749 1,000,431,249 1,079,948,749 1,124,466,249 1,154,708,849
Short Term Investments (246,774,462) (150,000,000) (70,000,000) (50,000,000) (50,000,000) (50,000,000) (50,000,000)
Long Term Investments 0 0 0 0 0 0 0
Total Net External Debt 499,226,767 580,136,249 804,213,749 950,431,249 1,029,948,749 1,074,466,249 1,104,708,849
Note:
Operational Boundary 746,000,000 730,000,000 874,000,000 1,000,000,000 1,080,000,000 1,124,000,000 1,155,000,000
Authorised Limit 1,200,000,000 1,200,000,000 1,200,000,000 1,200,000,000 1,200,000,000 1,200,000,000 1,200,000,000
The Operational Boundary and Authorised Limit are based on Gross External Debt.
Page 108 of 132

Page 109

PERTH AND KINROSS COUNCIL
PRUDENTIAL INDICATORS - QUARTER ENDING 30 JUNE 2022
APPENDIX IV
6 Principal Sums Invested Longer Than 365 Days
The Upper Limit for sums invested for over 1 year up to 3 years is £45 million. There were no amounts invested within this period as at the end of the quarter.
7 MATURITY STRUCTURE
The lower and upper limit for the proportion of the Council's total-long term debt which matures in each of  the time bandings below, and is therefore subject to refinancing at the
prevailing market rates, is as follows:
Borrowing Maturity Structure Lower Limit Upper Limit Estimated
Under 12 months 0% 35% 1.21%
over 12 months and < 24 months 0% 35% 1.43%
over 2 years and < 5 years 0% 50% 6.05%
over 5 years and < 10 years 0% 75% 7.24%
over 10 years 10% 95% 84.08%
The maurity profile for the Council's current long-term portfolio as at 30 June 2022, measured from the start of the financial year, is as follows:
Less 1 Year 1 - 2 Years 2 - 5 Years 5 - 10 Years 10 - 20 Years 20 - 30 Years 30 - 40 Years 40 - 50 Years Over 50 Years Total
PWLB 3,000,000 5,000,000 23,000,000 27,500,000 5,000,000 0 40,500,000 459,000,000 0 563,000,000
LOBOs 0 0 0 0 0 13,000,000 25,200,000 5,000,000 0 43,200,000
Other 0 0 140,000 0 0 0 0 0 0 140,000
PPP/PFI Liability 5,864,000 5,482,500 21,204,900 25,611,400 69,028,177 0 0 0 0 127,190,977
Total 8,864,000 10,482,500 44,344,900 53,111,400 74,028,177 13,000,000 65,700,000 464,000,000 0 733,530,977
Percentage 1.21% 1.43% 6.05% 7.24% 10.09% 1.77% 8.96% 63.26% 0.00% 100.00%
Page 109 of 132

Page 110

Page 110 of 132

Page 111

PERTH AND KINROSS COUNCIL 
Finance & Resources Committee
7 September 2022 
ANNUAL TREASURY REPORT 2021/22 
Report Head of Finance
(Report No. 22/211) 
1. PURPOSE 
1.1 A requirement of the Council’s approved Treasury Management Practice 6
(TMP6 – Reporting Requirements & Management Information Arrangements)
is the reporting to Council of the expected treasury activity for the forthcoming
year (i.e. the Treasury and Investment Strategy) and the subsequent reporting
of the actual results and activities (i.e. this Annual Treasury Report). The
Council meeting on 31 March 2021 approved the Treasury Strategy for the 8
financial years 2021/22 to 2028/29 and the annual Investment Strategy for
2021/22 (Report No. 21/42 refers). 
1.2 This Annual Treasury Report covers: 
• The Council’s treasury position
• The forecast economic outlook and borrowing strategy for 2021/22
• The actual economic situation for 2021/22
• Actual long-term borrowing and repayments in 2021/22
• The Statutory Loans Fund position
• The Investment Strategy and outturn for 2021/22
• Compliance with treasury policies and limits during 2021/22 
2. RECOMMENDATIONS 
2.1 It is recommended that the Committee notes the content of this report, which
is submitted in accordance with the Council’s approved Treasury
Management Practices. 
3. THE TREASURY POSITION 
3.1 In order to place this report in context, the Council’s Treasury position at the
beginning and at the end of the year is shown below:  
8
Page 111 of 132

Page 112

Principal
31 Mar 2021
£M 
Average
Rate
%
Principal
31 Mar 2022
£M 
Average
Rate
%
Fixed Rate/Long Term Funding
• Public Works Loan Board (PWLB)  490.5   2.59   568.0   2.41
• Market & Local Authority Bonds 43.2  4.59  43.2  4.59
• Other Loans & Bonds* 0.1  0.00  0.1  0.00 
533.8  2.75  611.3  2.57
Variable Rate/Short Term Funding       
• Temporary Loans 51.8  0.08  3.0  0.19
• Internal Loans 2.2  0.10  2.2  1.05 
54.0  0.08  5.2  0.56        
TOTAL DEBT 587.8  2.51  616.5  2.55                
Short Term Investments 191.7  0.50  252.0  0.99
Long Term Investments 45.0  0.71  0.0  0.00        
TOTAL INVESTMENTS 236.7  0.54  252.0  0.88 
*Interest free loan from the Scottish Government       
4. THE FORECAST ECONOMIC OUTLOOK AND BORROWING STRATEGY
2021/22 
4.1 Following the pandemic it was anticipated that economic growth and inflation
would steadily increase, but with no immediate increase in the Bank base
rate. However, gilt yields were anticipated to rise gradually throughout
2021/22 and beyond, subject to any new economic restrictions. The Council’s
Treasury Strategy for 2021/22 was that with no immediate long-term
borrowing required as a result of the significant borrowing undertaken in 2019,
any such borrowing would only be undertaken if capital expenditure recovered
quicker than expected, or if opportunities arose to borrow at low rates. With
short term rates expected to rise slower than medium and long-term rates,
short term borrowing could be undertaken if required and long-term borrowing
would then be deferred. 
4.2 The amounts reflected in the Council’s approved Capital Budget showed that
the estimated capital borrowing requirement for 2021/22 at the start of the
year was £86.5M, with further significant borrowing totalling £227.7M required
in the subsequent 2 years. However, much of this borrowing had already
been undertaken in advance in the previous year. 
4.3 Therefore consideration was given to borrowing for future year requirements
earlier within the 8-year period, whilst rates were at their forecast low point.
This approach is consistent with the Prudential Code but should be
considered in conjunction with the assessment of the additional risks and
potentially low returns from the resultant short-term increase in the level of
investments. 
4.4 Whilst the use of short-term borrowing would initially be cheaper, the use of
longer-term borrowing would give rise to longer term savings and reduce the
refinancing risk in later years. However, if rates stayed low, new borrowing
Page 112 of 132

Page 113

could be delayed and short-term borrowing used to meet immediate cashflow
requirements. The approved Treasury Strategy also allowed for consideration
of other market borrowing instruments where they offered favourable rates.
However, the associated risks due to their variable rate nature and their less
flexible terms in comparison to the Public Works Loan Board would also need
to be considered. 
4.5 Whilst minimising risk by favouring fixed longer-term borrowing, it was
acknowledged that there were several factors which could impact on interest
rates over the year. Therefore, the Council applies an approach of managing
risk and monitoring interest rates on an ongoing basis with a view to reviewing
this strategy should circumstances change. 
5. ACTUAL ECONOMIC SITUATION 2021/22 
5.1 2021/22 was another volatile year for the financial markets. Economic growth
in the UK initially fell at the start of the year before increasing over the
remainder of the year as restrictions were lifted. However, the rate of growth
did decline towards the end of the year. Consumer Price Index (CPIH)
inflation steadily rose over the year from 2.4% to 7.0% by March 2022, with
forecasts that it would exceed 10% by the end of the year. This was due to a
large increase in demand for commodities, including oil and gas, and the war
in Ukraine which is affecting global commodity supplies. Unemployment fell
throughout the year. 
5.2 Whilst no increases in the Bank base rate in 2021 were anticipated, with the
rapid rise in inflation and improving economic activity, the Bank of England’s
Monetary Policy Committee (MPC) did increase the Bank base rate to 0.25%
in November 2021, with further rises to in February 2022 to 0.75% by March
2022. The MPC has subsequently increased the rate further to its current
level of 1.75%, with further increases expected over the remainder of this
year. 
5.3 PWLB rates gradually fell in the first half of the year due to uncertainty over
future economic activity, before increasing as inflation started to rise rapidly.
However the rise in PWLB rates was reversed in November and December
2021 as fears over the impact of the new coronavirus variant Omicron
surfaced. At this time, PWLB rates fell to historic low levels not seen since the
start of the pandemic in March 2020. However, with no further restrictions
being made in the UK, and with inflation increasing, rates rose rapidly over the
remainder of the financial year. The PWLB rates for various periods are
shown at Appendix I. 
5.4 The 50-year rate was 2.03% at the start of the year and fell to 1.52% by
August. This was followed by a period of increases until they peaked at 2.15%
in October, before rapidly falling to their low point of 1.26% in December.
Thereafter they rose quickly and ended the year at around 2.40% in March
2022. All other durations followed a similar pattern, with the 20 and 30 year
rates being higher than the 50-year rate for the whole year. PWLB fixed rates
underwent a year of significant volatility and were higher than forecast in the
Page 113 of 132

Page 114

original strategy for most of the year, however the falls in November and
December 2021 did give rise to some borrowing opportunities. 
5.5 Investment deposit rates were little changed in the first half of the year,
however they increased significantly in the second half of the year, and
particularly towards the financial year end. This reflected the increased Bank
base rate during the year, as well as expectations of further increases in the
Bank Rate in the future. The average rate on the Council’s investments at the
start of the year was 0.54% and increased to 0.99% at the end of the year. 
6. ACTUAL LONG-TERM BORROWING & REPAYMENTS 
6.1 Treasury activity during 2021/22 is detailed in the four quarterly Treasury
reports previously submitted to the Council (Report No 21/141), the Strategic
Policy & Resources Committee (Report No’s 21/216 and 22/26) and the
Finance & Resources Committee (Report No 22/122). 
6.2 As noted in paragraph 4.2 above, before the start of the year, the Council’s
estimated new capital borrowing for 2021/22 was £86.5M. However, as this
had already been borrowed in a previous year, no new actual borrowing was
expected to be undertaken in the year, unless, for example, interest rates
started to increase rapidly or fell to historic low levels. This may have included
borrowing of future year’s requirements. 
6.3 Following a sharp fall in rates, a total of £90M of new longer-term borrowing
was undertaken in the year from the PWLB which is summarised below: 
Date Amount      
(£)
Interest
Rate
(%)
Duration
(Years)
16 Nov 2021 25,000,000 1.51 50
3 Dec 2021 25,000,000 1.46 49.5
3 Dec 2021 25,000,000 1.46 50
15 Dec 2021 15,000,000 1.26 50 
6.4 These loans are required to fund the Capital programme. Whilst there was no
borrowing required in the year, these loans were drawn down against the
borrowing required in 2022/23. With PWLB rates reaching historic lows, these
loans give estimated savings in interest of £728,000 per annum against
forecast interest rates in future years. 
6.5 The Council’s scheduled repayments to the PWLB during the year related to 2
maturing loans which had been borrowed for 5 and 12 years totalling £12.5M
at an average interest rate of 2.43%. The average PWLB debt portfolio rate
for the Council reduced from 2.59% at the start of the year, to 2.41% for the
total of £568M of PWLB debt held by the Council on 31 March 2022. There
were no other repayments of long-term debt in the year. 
6.6 Overall, the Council’s total Fixed Rate borrowing increased by £77.5M to
£611.3M, whilst the average rate reduced from 2.75% to 2.57%. 
Page 114 of 132

Page 115

6.7 Short term variable funding at the year-end reduced from £54.0M at 31 March
2021 to £5.2M at 31 March 2022. The reduction mostly relates to a reduced
requirement for short term funding over the financial year end in March 2022. 
6.8 As a result of the above strategy and actual treasury activities in the year, the
Council’s average Consolidated Loans Fund (CLF) interest rate was broadly
unchanged from 3.1% in 2020/21 to 3.11% in 2021/22 (based on applying
statutory guidance). The impact of borrowing at lower rates in the year was
offset by the small increase in capital debt outstanding, however it will lead to
a lower CLF rate in subsequent years (the 2022/23 CLF rate is currently
projected to be 2.49%). 
6.9 A comparison of the Council’s CLF rate over recent years with the average for
other Scottish Local authorities is shown graphically at Appendix II. Whilst
figures for the 2021/22 Scottish average will not be published until the
autumn, this graph shows that over time, this Council’s average borrowing
costs have reduced to a level significantly below the Scottish average. This
equates to savings in Loan Charges of around £2.2M per annum on the
Council’s portfolio compared to the Scottish average. Further, the impact of
the advance borrowing and debt rescheduling undertaken in the last 2 years
can be seen in the forecast of the Council’s Loans Fund rate over the next few
years. 
7. STATUTORY LOANS FUND 
7.1 The Loans Fund is an internal fund operated by the Council to manage: 
• The write down (repayments or “amortisation”) of capital expenditure
(capital advances) over the life of the various assets being funded by
borrowing as part of the Council’s Loan Charges, and
• To manage the external borrowing raised to finance the capital
expenditure. 
7.2 Whilst both these elements of the Loans Fund operate independently of each
other, because they are based on the same capital plans of the Council, they
will broadly be consistent with each other over the long term. However,
significant differences may arise in the short-term due to, for example,
delaying external borrowing, or borrowing in advance in light of prevailing
interest rates, or where the Council has significant levels of Reserves. 
7.3 The approved Loans Fund policies allow the amortisation of capital
expenditure (advances) for periods of up to 50 years in line with the asset
useful lives, using the annuity method. The repayment of Loans Fund
advances is also deferred until the asset being funded is completed and
operational. 
7.4 It is a requirement of the Loans Fund regulations that the outstanding amount
of Loans Fund advances at the end of each financial year is reported as part
of the annual report. The value of Loans Fund advances outstanding at 31
March 2022 is £491,270,000 (subject to completion and audit of the Council’s
Annual Accounts). This is made up as follows:
Page 115 of 132

Page 116

• Capital Advances outstanding 1 April 2021 - £462,132,000
• Add New capital Advances 2021/22 - £38,460,000
• Less Capital Advances repaid in the year - £9,322,000 
7.5 The future repayment of these advances is summarised in the table below: 
Core
Composite
Programme 
Prudential
Borrowing
Sub-Total:
General
Fund
Housing
Revenue
Account
TOTAL
(£’000)     
Within 1 Year 2,382 2,747 5,129 3,697 8,826
Between 1 and 2 Years 2,107 2,802 4,909 4,145 9,054
Between 2 and 5 Years 3,413 6,504 9,917 10,990 20,907
Between 5 and 10 Years (8,091) 5,221 (2,870) 19,341 16,471
Between 10 and 15 Years (5,402) 4,062 (1,340) 24,807 23,467
Between 15 and 20 Years 28,291 3,399 31,690 9,461 41,151
Between 20 and 25 Years 37,104 3,592 40,696 2,490 43,186
Between 25 and 30 Years 43,802 4,216 48,018 6,055 54,073
Between 30 and 35 Years 47,789 5,644 53,433 11,338 64,771
Between 35 and 40 Years 59,987 3,921 63,908 11,455 75,363
Between 40 and 45 Years 68,095 3,572 71,667 13,543 85,210
Between 45 and 50 Years 35,833 155 35,988 7,957 43,945
Over 50 Years 4,846 0 4,846 0 4,846      
TOTAL 320,156 45,835 365,991 125,279 491,270 
7.6 Comparison of the outstanding capital advances above with the long-term
external debt shown in paragraph 3.1 demonstrates that actual capital
expenditure funded by borrowing is lower than the actual borrowing
undertaken to date by around £120M. This reflects the strategy adopted in
recent years of undertaking new borrowing whilst rates were at historic low
levels, in order to fund the significant borrowing requirement approved by the
Council over the next 2-3 years. This strategy has reduced the risks and the
interest charges of borrowing in future at higher interest rates. 
7.7 The last report to the Strategic Policy & Resources Committee on 20 April
2022 (report 22/88) approved adjustments to the General Fund Composite
Capital Budget and Housing Investment Programmes. The amount of capital
expenditure to be funded by borrowing (ie new Loans Fund advances) in each
of the next 6 years as approved in April is as follows: 
Composite
Programme
Housing
Investment
Programme
TOTAL
(£’000)   
2022/23 125,644 15,349 140,993
2023/24 155,102 13,338 168,440
2024/25 117,980 10,5420 128,522
2025/26 41,974 16,035 58,009
2026/27 35,115 11,765 46,880
2027/28 26,188 0 26,188    
TOTAL 502,003 67,029 569,032 
Page 116 of 132

Page 117

7.8 All the above Loans Fund repayments and new borrowing have been included
in the Loan Charge estimates within the approved Medium Term Financial
Plan, and therefore remain affordable under the current Loan Charge Budget
strategy. This also includes estimates of new borrowing in the years beyond
2027/28. 
8. INVESTMENT STRATEGY AND OUTURN 2021/22 
8.1 Short term deposit rates remained at low levels throughout most of the year,
however they did increase from December 2021 following the increases in the
Bank base rate. The low deposit rates also reflect funding requirements for
banks which make it less attractive for banks to hold short term cash deposits.
Therefore, instant access and short-term deposit rates offered by most banks
and institutions remained low relative to the bank base rate. 
8.2 The original Strategy anticipated that investments would reduce gradually over
the year unless, for example, new borrowing was undertaken in the year or
the Council’s expenditure during the year was later than anticipated. As
described in paragraph 6.3, a total of £90M of new borrowing was undertaken
in November and December 2021. Consequentially, the level of investments
gradually reduced in the first half of the year before they increased and
peaked at £294M on 16 December 2021. They then gradually reduced again
over the remainder of the year, reflecting the Council’s day-to-day cashflow
over that period. The level of investments stood at £236.7M at the start of the
year, peaked at £294.1M in December, before ending at £252.0M on 31
March 2022. 
8.3 For shorter investment periods, notice deposit accounts and money market
funds held by the Council provided a higher return on investments than rates
available on instant access bank accounts and shorter-term fixed deposits. In
the first half of the year, notice deposit rates for 3 months with some of the
banks were particularly competitive and increased relative to other investment
rates. These facilities also helped to meet short term cashflow requirements
and keep within counterparty limits. As the investment rates increased, short
term fixed deposit rates become more attractive relative to notice accounts.
With the expectation of rates increasing further as the year progressed, the
strategy was to invest in shorter term fixed deposits (up to 3 months) in order
to benefit from the rising interest rates as they matured. Towards the end of
the year, fixed deposits up to 12 months became more attractive, with several
deposits then being undertaken for this period. 
8.4 During the year, no investment was made for more than 12 months, and all
investment activities were in line with the approved strategy for 2021/22. The
average rate on investments outstanding at 31 March 2022 was 0.88%
(0.54% at 31 March 2021). This increase in the average rate over the year
reflected the increase in the Bank base rate. In comparison, the average
temporary borrowing rate for the year was 0.14%. Total interest received on
investments in 2021/22 amounted to £1,076,000. Whilst this was lower than
the previous year (£1,663,000 in 2020/21), the previous year included
significant levels of local authority borrowing at higher than market rates
(reflecting local authority cash requirements at the height of the pandemic).
Page 117 of 132

Page 118

8.5 All financial investments by the Council’s Common Good Funds and
Charitable Trusts were made through the Council’s Loans Fund, in
accordance with the Council’s and Common Good Fund’s policy for Permitted
Investments. As a result, £2,169,000 of Common Good funds and Charitable
Trusts are placed on deposit with the Loans Fund for periods of between 6
and 12 months at an average rate of 1.05%. 
8.6 Any investments held with external fund managers are outside the scope of
the investment regulations, as they all relate to funds held by Council
administered Charities or Trusts. 
8.7 The Annual Property Investment Strategy for 2021/22 was also approved by
the Council at its meeting on the 31 March 2021 and was complied with in full,
with no breaches in compliance with permitted investment limits. The
budgeted income from the Council’s property portfolio for 2021/22 was
£1,819,000, whilst the final position (subject to audit) was £1,847,000. There
were no additional risks identified or new property investments entered into
over the year. The strategy action plan remained on programme. 
9. COMPLIANCE WITH TREASURY POLICIES AND LIMITS 
9.1 There were no breaches of compliance with the Council’s approved borrowing
and investment policies and strategy in 2021/22. All aspects of the Prudential
Code, including Prudential Indicators and limits, were also fully adhered to
throughout the year. 
10. CONCLUSION 
10.1 Global economic and political uncertainties have kept UK interest rates low for
several years, and particularly in the last couple of years during the pandemic.
However, whilst there was no immediate expectation of rates rising in
2021/22, the interest rate forecast was that rates would start rising gradually
from the end of the year. As a result of rapidly rising inflation, the Bank base
rate did increase, and at a faster rate than anticipated.  However, some
uncertainties did remain and thus market and interest rate volatility continued,
giving rise to new borrowing opportunities in the year. Consequently, £90M of
new long-term borrowing was undertaken in the year 
10.2 As the new borrowing is required to fund the 2022/23 capital programme,
there was increased short term investment activity as a result of the increased
balances arising from the borrowing. As interest rates rose over the year, the
investment Strategy moved from notice accounts to shorter term fixed
deposits. 
10.3 There were no breaches of compliance with the lending policy and all
Prudential Indicators were complied with throughout the year. As a result of
the activities undertaken during 2021/22 the Council’s plans remain
affordable, prudent and sustainable. The report also includes detailed
information on the repayment profiles and future estimates of Loans Fund
Advances. 
Page 118 of 132

Page 119

10.4 The Council’s Consolidated Loans Fund (CLF) rate for the year remained
broadly unchanged, increasing marginally from 3.10% last year to 3.11%.
However, as a result of the treasury activities during 2021/22, the CLF rate in
future years is projected to reduce significantly (currently estimated at 2.49%
for 2022/23). 
Author(s)
Name  Designation Contact Details 
John Jennings  Senior Accountant  CHXFinance@pkc.gov.uk 
Approved 
Name Designation Date
Stewart MacKenzie 
Karen Donaldson
Head of Finance 
Chief Operating Officer
12 August 2022 
12 August 2022 
Page 119 of 132

Page 120

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Single Outcome Agreement  None
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce Yes
Asset Management (land, property, IST) Yes
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  Yes
Communication 
Communications Plan  None 
1. Strategic Implications 
Corporate Plan 
1.1 The Council’s Corporate Plan 2018 – 2023 lays out five outcome focussed
strategic objectives which provide clear strategic direction, inform decisions at
a corporate and service level and shape resources allocation.  They are as
follows: 
(i) Giving every child the best start in life;
(ii) Developing educated, responsible and informed citizens;
(iii) Promoting a prosperous, inclusive and sustainable economy;
(iv) Supporting people to lead independent, healthy and active lives; and
(v) Creating a safe and sustainable place for future generations. 
1.2 This report relates to all of these objectives. 
2. Resource Implications 
Financial 
2.1 There are no direct financial implications arising from this report other than
those reported within the body of the main report. 
Workforce 
2.2 There are no direct workforce implications arising from this report other than
those reported within the body of the main report.
Page 120 of 132

Page 121

Asset Management (land, property, IT)   
2.3 There are no direct asset management implications arising from this report
other than those reported within the body of the main report. 
3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties. 
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development. In terms of the Climate Change Act,
the Council has a general duty to demonstrate its commitment to sustainability
and the community, environmental and economic impacts of its actions. 
3.6 The information contained within this report has been considered under the
Act.  However, no action is required as the Act does not apply to the matters
presented in this report.   
4. Consultation 
4.1 The Chief Executive, and the Council’s Treasury advisors, Capita Asset
Services, have been consulted in the preparation of this report.   
2. BACKGROUND PAPERS 
No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to any material extent in preparing the above
report.
Page 121 of 132

Page 122

3. APPENDICES 
• Appendix I – PWLB Fixed Maturity Interest Rates From 1 April 2021 to
1 April 2022.
• Appendix II – Average Loans Fund Rates 
Page 122 of 132

Page 123

PWLB Fixed Maturity Interest Rates
from 1st April to 30th June 2022
(Certainty Rates)
APPENDIX I
1.50
1.75
2.00
2.25
2.50
2.75
3.00
3.25
3.50
3.75
4.00
01-Apr-22
08-Apr-22
15-Apr-22
22-Apr-22
29-Apr-22
06-May-22
13-May-22
20-May-22
27-May-22
03-Jun-22
10-Jun-22
17-Jun-22
24-Jun-22
1 Year
5 Years
10 Years
20 Years
30 Years
50 Years
8
Page 123 of 132

Page 124

Page 124 of 132

Page 125

APPENDIX II
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
7.0
7.5
8.0
2000/01
2001/02
2002/03
2003/04
2004/05
2005/06
2006/07
2007/08
2008/09
2009/10
2010/11
2011/12
2012/13
2013/14
2014/15
2015/16
2016/17
2017/18
2018/19
2019/20
2020/21
2021/22
2022/23
2023/24
Rate (%)
Year
Average Loans Fund Rates
(actual and projetced)
PKC
Scottish
Average
8
Page 125 of 132

Page 126

Page 126 of 132

Page 127

PERTH AND KINROSS COUNCIL 
Finance and Resources Committee 
Wednesday 7 September 2022 
COMMUNITY INVESTMENT FUND 2022/23 
Report by Head of Culture & Community Services
(Report No. 22/212) 
1. PURPOSE 
1.1 This report asks Committee to consider and approve changes to the operation
of the Community Investment Fund and sets out the timescales and funding
levels for the 2022/23 round. 
2. RECOMMENDATIONS 
2.1  It is recommended that the Committee: 
i. agrees the proposed changes to decision making and grant
monitoring/administration of CIF as set out in Sections 5 and 6,
highlighted in bold italics.
ii. notes the timings for the 2022/23 round of CIF as set out in paragraph
6.1.
iii. notes the funding available for the 2022/23 round of CIF in paragraph
6.2. 
3. STRUCTURE OF REPORT 
3.1 This report is structured over the following sections: 
• Section 4: Background
• Section 5: CIF Governance and Decision Making 2022/23
• Section 6: CIF 2022/23: Timescale and Process
• Section 7: Conclusion 
4. BACKGROUND 
4.1 In 2018/19, the Council established a Community Investment Fund (CIF) as
part of its commitment to devolve more decisions to local communities. Since
then, £1.6m has been distributed in total to approximately 300 community-led
projects. 
4.2 In February 2022, the Council approved a further £100,000 in addition to the
previously approved £300,000 for a further round of Community Investment
Fund in 2022/23. This included an additional funding criterion relating to
supporting community groups which are facing significant financial challenges
as a result of rising energy costs. Including the small underspend from
2021/22 l, there is a grant pot of £410,665.79 for Community Investment Fund
2022/23. 
9
Page 127 of 132

Page 128

5. CIF GOVERNANCE AND DECISION MAKING 2022/23 
5.1 In November 2021, Committee approved Report 21/222 which outlined
proposed changes to how the CIF is managed. Following further work by
officers, the following changes are recommended for CIF 2022/23: 
5.2 Governance and Decision Making 
Decisions on the use of CIF funds are currently made by Ward Panels,
composed of elected members and community representatives from each
electoral ward. The only exception is in Kinross-shire, where final decisions on
the use of the funds are taken by the Kinross-shire Local Committee within its
approved remit. 
5.3 Given the anticipated level of interest in the CIF, to ensure that there is as
quick decision making as possible, each ward panel is asked to determine
which elected member is available to chair the Panel meeting. Panel meetings
will be scheduled at least 4 weeks in advance. 
5.4 It is proposed that when funded projects need to change deliverables or
timescales for good reason and the total grant award is less than £3,000,
the Ward Panel Chair is asked to approve the change, on the basis of
assessment and advice of a Communities Team officer. Only proposed
changes to grants over £3,000 would require approval from the whole
Ward Panel. 
5.5 Impact on Outcomes 
CIF was established to support community-led projects which have a positive
impact on inequalities and quality of life in our communities. CIF projects have
varied enormously in their scale and coverage. This has made assessment of
their collective strategic impact (as set out in the Local Outcomes
Improvement Plan) challenging. 
5.6 To improve this and to streamline the monitoring process, it is also proposed
to introduce a tiered monitoring system proportionate to the size of the
project: 
Tier Proposed monitoring solution
1 (project
value less
than £3,000)
Provide a summary of the overall impact of the project;
number of beneficiaries and number of volunteers involved.
2 (project
value
between
£3,000-
£9,999)
Demonstrate how the project has impacted against
identified priorities of the LOIP and a range of quantitative
evidence to support this (tailored to reflect the specifics of
the grant purpose and based on assessment of
deliverability and reasonable impact.
3 (project
value
£10,000 or
more)
Demonstrate how the project has impacted against
identified priorities of the LOIP, any wider outcomes and
evidence to support this. Qualitative evaluation alongside
quantitative measures will be required, tailored to reflect the
specifics of the grant purpose and based on assessment of
deliverability and reasonable impact.
Page 128 of 132

Page 129

5.7 Previous rounds of CIF have required successful applicants to complete a
project monitoring form at 6 months and again at 12 months. As CIF has run
to different timescales and sometimes multiple rounds in each financial year,
this has also been complex to administer. To streamline this, it is proposed
to apply the requirement for 6-month monitoring updates to projects of
£10,000 and over. For all other projects, a report 12 months after they
have received their funding will be required. 
5.8 CIF has provided funding to community-led projects for four years and the
different rounds of funding have seen a growing number of bids from the
same organisations. It is a requirement of the CIF that projects are time-
limited or can be self-sustained longer term; ongoing revenue costs cannot be
supported. Therefore, it is proposed that Ward Panels are asked to give
extra weighting, at their local discretion, to applications from groups
which have not previously received CIF funding. 
6. CIF 2022/23: TIMESCALE AND PROCESS 
6.1 If approved, these changes would be implemented for CIF 2022/23, which will
open for applications on Monday 12 September and close on Friday 4
November 2022. Ward Panels will meet to make decisions between Monday
14 November and Friday 16 December, with funding paid out to successful
applicants from January 2023. 
6.2 Report 21/83 set out new arrangements for funding levels in each ward, which
saw 50% of the committed funding being divided equally among all 12 multi-
member wards and the remaining 50% split on the basis of the population of
each ward. This ensures that there is a balance between more heavily
populated wards receiving additional funding, whilst also ensuring that the
less populated and more rural wards are not penalised. It is proposed that
this distribution model is retained for 2022/23, which will result in the
following funding being available across Perth and Kinross: 
Ward  
Base Fund  Population 
Per Capita
Top Up 
2021/22
Underspend
Total 
2022/23 
1 – Carse of Gowrie   £16,667 10,079  £13,350 £3,846 £33,863
2 – Strathmore   £16,667 15,518  £20,500 £2,857* £40,024*
3 – Blairgowrie & Glens  £16,667 11,009  £14,500 £0 £31,167
4 – Highland   £16,667 9,344  £12,400 £2,981 £32,048
5 – Strathtay   £16,667 12,583  £16,600 £0.40 £33,267.40
6 – Strathearn  £16,667 11,053  £14,600 £49 £31,316
7 – Strathallan  £16,667 11,671  £15,500 £0 £32,167
8 – Kinross-shire  £16,667 14,045  £18,500 £0 £35,167
9 – Almond & Earn  £16,667 9,345  £12,450 £0 £29,117
10 – Perth City South   
£49,997  46,643  £61,600  £932.78  £112,529.78 11 – Perth City North 
12 – Perth City Centre  
TOTAL  £200,000  151,290  £200,000  £10,666.18 £410,666.18
*£1,200 of this carryover has been agreed (in principle) for Year 2 of the CanDo
Project being delivered by the Strathmore Community Hub, subject to grant
conditions. Taking this into account funding available in Ward 2 will be £38,824.
Page 129 of 132

Page 130

7. CONCLUSION 
7.1 The Community Investment Fund (CIF) invests in community-led projects
which tackle inequalities and improve quality of life across Perth and Kinross.
Governance and decision making has evolved since the first round of CIF in
2018/19 and further changes are proposed for 2022/23. 
7.2 The 2022/23 CIF is the last round in the current form and Council will wish to
consider proposals for its further evolution in the context of 2023/24 budget
and the forthcoming new Council Corporate Plan. Alongside this, a
Transformation Review of community engagement and empowerment has
been scoped and will proceed later this year taking into account: the policy
priorities of the Council; the changing external context, in particular the impact
of cost of living and climate change on communities; and national policy aims
including the 1% Community Choices programme. 
Author(s)
Name  Designation Contact Details
Lee Haxton 
David Stokoe 
Community Planning 
Team Leader 
Service Manager – 
Communities 
comcommitteereports@pkc.gov.uk
01738 475000 
Approved 
Name Designation Date
Barbara Renton  Executive Director
(Communities)
26 August 2022 
• Appendix - None 
Page 130 of 132

Page 131

ANNEX 
1. IMPLICATIONS, ASSESSMENTS, CONSULTATION AND COMMUNICATION 
Strategic Implications Yes / None
Community Plan / Local Outcomes Improvement Plan  Yes
Corporate Plan  Yes
Resource Implications  
Financial  Yes
Workforce None
Asset Management (land, property, IST) None
Assessments  
Equality Impact Assessment Yes
Strategic Environmental Assessment Yes
Sustainability (community, economic, environmental) Yes
Legal and Governance  None
Risk None
Consultation 
Internal  Yes
External  None
Communication 
Communications Plan  None 
1. Strategic Implications  
Community Plan/Single Outcome Agreement 
1.1 Supporting and investing in community-led solutions to locally identified
issues contributes to the delivery of the Perth and Kinross Community Plan /
LOIP in terms of the following priorities: 
(i) Giving every child the best start in life
(ii) Developing educated, responsible and informed citizens
(iii) Promoting a prosperous, inclusive and sustainable economy
(iv) Supporting people to lead independent, healthy and active lives
(v) Creating a safe and sustainable place for future generations 
Corporate Plan 
1.2 Supporting and investing in community-led solutions to locally identified
issues contributes to the delivery of the Perth and Kinross Council Corporate
Plan in terms of the following priorities: 
(i) Giving every child the best start in life; 
(ii) Developing educated, responsible and informed citizens; 
(iii) Promoting a prosperous, inclusive and sustainable economy; 
(iv) Supporting people to lead independent, healthy and active lives; and 
(v) Creating a safe and sustainable place for future generations. 
2. Resource Implications 
Financial 
2.1 Community Investment Fund has a budget of £410,666 for 2022/23.
Page 131 of 132

Page 132

3. Assessments 
Equality Impact Assessment 
3.1 Under the Equality Act 2010, the Council is required to eliminate
discrimination, advance equality of opportunity, and foster good relations
between equality groups.  Carrying out Equality Impact Assessments for plans
and policies allows the Council to demonstrate that it is meeting these duties.   
3.2 The information contained within this report has been considered under the
Corporate Equalities Impact Assessment Process (EqIA) and has been
assessed as not relevant for the purposes of EqIA. 
Strategic Environmental Assessment 
3.3 The Environmental Assessment (Scotland) Act 2005 places a duty on the
Council to identify and assess the environmental consequences of its
proposals. 
3.4 The information contained within this report has been considered under the Act.
However, no action is required as the Act does not apply to the matters
presented in this report.   
Sustainability 
3.5 Under the provisions of the Local Government in Scotland Act 2003 the
Council has to discharge its duties in a way which contributes to the
achievement of sustainable development.   Under the Climate Change
(Scotland) Act 2009 the Council has a general duty to demonstrate its
commitment to sustainability and the community, environmental and
economic impacts of its actions. 
3.6 The information contained within this report has been considered under the
Act. However, no action is required as the Act does not apply to the matters
presented in this report.  
4. Consultation 
Internal 
4.1 There has been consultation with the Finance Department, Communities and
the Executive Officer Team. 
2. BACKGROUND PAPERS 
2.1 No background papers, as defined by Section 50D of the Local Government
(Scotland) Act 1973 (other than any containing confidential or exempt
information) were relied on to a material extent in preparing the above report.
Page 132 of 132